HomeMy WebLinkAbout20160130 Ver 1_Table 1_20170524Table 1. Project Components and Mitigation Credits
North Fork Little River Mitigation Site
Monitoring Year 0 - 2017
Mitigation Type
Buffer Zone
Credit Type
Total Acreage
Credit Ratio Credit Per Acre
Mitigation Credit
BPDP
Zone A: Top of Bank -50'
Riparian Buffer
8.34
N/A
1:1 43,560 ft'
363,290.4 ft'
Restoration
Zone 8: 51'-100'
Riparian Buffer
5.56
April 2017
1:1 43,560 ft'
242,193.6 ft'
December 2017
Year 2 Monitoring
2018
December 2018
Subtotal
605,484.00 ft2
December 2019
Zone A: 0-50'
Nitrogen
1.08
Year 5 Monitoring
1:1 2,273.0216./acre
2,454.861bs.
Restoration
Zone B: 51'-100'
Nitrogen
3.18
1:1 2,273.0216./acre
7,228.201bs.
Zone C: 101'-200'
Nitrogen
14.05
1:1 2,273.0216./acre
31,935.93 lbs.
Subtotal
41,619 lbs.
Zone A: 0-50'
Phosphorous
1.08
1:1 146.4 lb./acre
158.11 las.
Restoration
Zone B: 51'-100'
Phosphorous
3.18
1:1 146.4 lb./acre
465.55 lbs.
Zone C: 101'-200'
Phosphorous
14.05
1:1 146.4 lb./acre
2,056.92 lbs.
Subtotal
2,680.S8 lbs.
Total Buffer Restoration Credits
605,484.00 W
Total Nutrient Offset Credits— Nitrogen
41,619 lbs.
Total Nutrient Offset Credits - Phosphorus
2,680.58 lbs.
Table 2. Project Activity and Reporting History
North Fork Little River Mitigation Site
Monitoring Year 0 - 2017
Activity or Report
Date Collection Complete
Completion or Scheduled Delivery
Wildlands Holdings 11, LLC Neuse MBI
N/A
April 2016
BPDP
N/A
May 2016
Conservation Easement
N/A
May 2016
Bare Root Planting
N/A
January 2017
As -Built & Baseline Monitoring Document
2017
April 2017
Year 1 Monitoring
2017
December 2017
Year 2 Monitoring
2018
December 2018
Year 3 Monitoring
2019
December 2019
Year 4 Monitoring
2020
December 2020
Year 5 Monitoring
2021
December 2021
Table 3. Project Contact Table
North Fork Little River Mitigation Site
Monitoring Year 0 - 2017
Table 4. Project Information and Attributes
North Fork Little River Mitigation Site
Monitoring Year 0 - 2017
PROJECT INFORMATION
Wildlands Holdings II, LLC
Bank Sponsor
312 West Millbrook Road, Suite 225
Durham County
Raleigh, NC 27609
33.4 acres
919.851.9986
36° 10'9.48- N, 78° 55'49.44- W
Bruton Natural Systems, Inc
Planting Contractor
P.O. Box 1197
River Basin
Fremont, NC 27830
Nursery Stock Suppliers
Dykes and Son Nursery
Monitoring Performers
Wildlands Engineering, Inc.
Monitoring, POC
Jason Lorch
Project Drainiage Area (acres)
919.851.9986, ext. 107
Table 4. Project Information and Attributes
North Fork Little River Mitigation Site
Monitoring Year 0 - 2017
PROJECT INFORMATION
Project Name
North Fork Little River Nutrient Offset and Buffer Mitigation Bank Parcel
County
Durham County
Project Area (acres)
33.4 acres
Project Coordinates (latitude and longitude)
36° 10'9.48- N, 78° 55'49.44- W
PROJECT WATERSHED SUMMARY INFORMATION
Physiographic Province
Piedmont
River Basin
Neuse
USGS Hydrologic Unit 8 -digit
03020201
USGS Hydrologic Unit 14 -digit
03020201020010
DWR Sub -basin
02-00-10
Project Drainiage Area (acres)
128 acres
Project Drainage Area Percentage of Impervious Area
<5%
CGIA Land Use Classification
Cropland