HomeMy WebLinkAbout20140957 Ver 2_22_Appendix_L_Cumulative Impact Assessment REV_20170509ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
and
DOMINION TRANSMISSION, INC.
SUPPLY HEADER PROJECT
Resource Report 1
General Project Description
APPENDIX 10
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
Atlantic
Coast
Pipeline sM
,
II�� -
� �D41'1 inion
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Docket Nos.
and
CP15-
-000
CP15-
-000
CP15-
-000
DOMINION TRANSMISSION, INC.
SUPPLY HEADER PROJECT
Docket No. CP15- -000
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
Prepared by
NATURAL
RESOURCE
GROUP
September 2015
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
TABLE OF CONTENTS
1.0
INTRODUCTION..............................................................................................................1
1.1 Project Description...................................................................................................1
1.2 Background and Approach......................................................................................4
2.0
PROJECTS AND ACTIVITIES CONSIDERED...........................................................5
3.0
POTENTIAL CUMULATIVE IMPACTS BY RESOURCE........................................7
3.1 Geology and Soils....................................................................................................7
3.2 Waterbodies, Groundwater, and Wetlands..............................................................8
3.3 Vegetation, Wildlife and Habitat, and Aquatic Resources....................................10
3.4 Land Use, Recreation, Special Interest Areas, and Visual Resources
...................13
3.5 Socioeconomics.....................................................................................................17
3.6 Cultural Resources.................................................................................................20
3.7 Air Quality and Noise............................................................................................21
3.8 Reliability and Safety.............................................................................................23
4.0
CONCLUSION................................................................................................................24
5.0
REFERENCES.................................................................................................................25
LIST OF TABLES
Table 3.4-1 Other Projects Proposing to Cross the Appalachian Trail .................................... 15
LIST OF ATTACHMENTS
Attachment A Table A-1: Past, Present, and Reasonably Foreseeable Future Projects
1 O -i
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
LIST OF ACRONYMS AND ABBREVIATIONS
ACP
Atlantic Coast Pipeline
AGL
AGL Resources, Inc.
Appalachian Trail
Appalachian National Scenic Trail
AQCR
Air Quality Control Regions
ATC
Appalachian Trail Conservancy
Atlantic
Atlantic Coast Pipeline, LLC
CEQ
Council on Environmental Quality
CFR
Code of Federal Regulations
Chmura
Chmura Economics and Analytics
Commission
Federal Energy Regulatory Commission
dBA
decibels on the A -weighted scale
Dominion
Dominion Resources, Inc.
DTI
Dominion Transmission, Inc.
EFH
essential fish habitat
EPA
U.S. Environmental Protection Agency
ER
Environmental Report
FERC
Federal Energy Regulatory Commission
FWS
U.S. Fish and Wildlife Service
GHG
greenhouse gases
HDD Plan
Directional Drill Fluid Monitoring, Operations, and Contingency
Plan
HDD
horizontal directional drill
Ldn
day -night equivalent sound level
M&R
metering and regulating
MMDth/d
million dekatherms per day
MP
milepost
NAAQS
National Ambient Air Quality Standards
NEPA
National Environmental Policy Act
NRNP
National Register of Historic Places
NSA
noise -sensitive area
PHMSA
U.S. Department of Transportation's Pipeline and Hazardous
Materials Safety Administration
Piedmont
Piedmont Natural Gas Co., Inc.
Plan
Upland Erosion Control, Revegetation, and Maintenance Plan
Procedures
Wetland and Waterbody Construction and Mitigation Procedures
Projects
Atlantic Coast Pipeline and Supply Header Project
PSD
Prevention of Significant Deterioration
SHP
Supply Header Project
SPCC Plan
Spill, Prevention, Control, and Countermeasures Plan
U2GC
Uniontown to Gas City Expansion
USACE
U.S. Army Corps of Engineers
USDOT
U.S. Department of Transportation
ATLANTIC COAST PIPELINE — Docket Nos. CP15-_-000, CP15-_-000, CP15-_-000
SUPPLY HEADER PROJECT — Docket No. CP15- -000
CUMULATIVE IMPACTS ASSESSMENT FOR THE
ATLANTIC COAST PIPELINE AND SUPPLY HEADER PROJECT
1.0 INTRODUCTION
1.1 PROJECT DESCRIPTION
Atlantic Coast Pipeline
Atlantic Coast Pipeline, LLC (Atlantic) is a company formed by four major U.S. energy
companies — Dominion Resources, Inc. (Dominion; NYSE: D), Duke Energy Corporation (Duke
Energy; NYSE: DUK), Piedmont Natural Gas Co., Inc. (Piedmont; NYSE: PNY), and AGL
Resources, Inc. (AGL; NYSE: GAS). 1 The company was created to develop, own, and operate
the proposed Atlantic Coast Pipeline (ACP or Project), an approximately 564.1 -mile -long,
interstate natural gas transmission pipeline system designed to meet growing energy needs in
Virginia and North Carolina (see Figure 1.1.1-1 in Resource Report 1). The ACP will be capable
of delivering up to 1.5 million dekatherms per day (MMDth/d) of natural gas that will be used to
generate electricity, heat homes, and run local businesses. The pipeline Project will facilitate
cleaner air, increase the reliability and security of natural gas supplies, and provide a significant
economic boost in West Virginia, Virginia, and North Carolina. More information is provided at
the company's website at www.dom.com/acpipeline. Atlantic has contracted with Dominion
Transmission, Inc. (DTI), a subsidiary of Dominion, to permit, build, and operate the ACP on
behalf of Atlantic. 2
Atlantic is seeking authorization from the Federal Energy Regulatory Commission
(FERC or Commission) under Section 7(c) of the Natural Gas Act to construct, own, operate,
and maintain the following proposed facilities for the ACP system: 3
Mainline Pipeline Facilities:
AP -1: approximately 300.1 miles of underground 42 -inch outside diameter
natural gas transmission pipeline in Harrison, Lewis, Upshur, Randolph, and
Pocahontas Counties, West Virginia; Highland, Augusta, Nelson, Buckingham,
Cumberland, Prince Edward, Nottoway, Dinwiddie, Brunswick, and Greensville
Counties, Virginia; and Northampton County, North Carolina.
On August 24, 2015, Southern Company and AGL Resources announced that the boards of directors of both companies have approved a
definitive merger agreement. Pursuant to the agreement, AGL Resources will become a new wholly owned subsidiary of Southern
Company. The companies expect to complete the transaction in the second half of 2016.
As described in this report, DTI actions associated with the ACP are on behalf of Atlantic.
Atlantic is also requesting a Blanket Certificate of Public Convenience and Necessity pursuant to Part 284, Subpart G, of the Commission's
regulations authorizing open -access transportation of natural gas for others with pre -granted abandonment authority, and a Blanket
Certificate of Public Convenience and Necessity pursuant to Part 157, Subpart F, of the Commission's regulations authorizing certain
facility construction and operation, certain certificate amendments and abandonments.
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
AP -2: approximately 183.0 miles of underground 36 -inch outside diameter
natural gas transmission pipeline in Northampton, Halifax, Nash, Wilson,
Johnston, Sampson, Cumberland, and Robeson Counties, North Carolina.
Lateral Pipeline Facilities:
AP -3: approximately 79.3 miles of underground 20 -inch outside diameter natural
gas lateral pipeline in Northampton County, North Carolina; and Greensville and
Southampton Counties and the Cities of Suffolk and Chesapeake, Virginia.
AP -4: approximately 0.6 mile of underground 16 -inch outside diameter natural
gas lateral pipeline in Brunswick County, Virginia.
AP -5: approximately 1.1 miles of underground 16 -inch outside diameter natural
gas lateral pipeline in Greensville County, Virginia.
Compressor Station Facilities:
Compressor Station 1 (Marts Compressor Station): a new, natural gas-fired
compressor station approximately at milepost 4 (MP) 7.6 of the AP -1 mainline in
Lewis County, West Virginia.
Compressor Station 2 (Buckingham Compressor Station): a new, natural gas-
fired compressor station approximately at MP 191.5 of the AP -1 mainline in
Buckingham County, Virginia.
Compressor Station 3 (Northampton Compressor Station): a new natural gas-
fired compressor station approximately at MP 300.1 of the AP -1 mainline and
MP 0.0 of the AP -2 mainline and 0.0 of the AP -3 lateral in Northampton County,
North Carolina.
Other Aboveground Facilities:
Nine new metering and regulating (M&R) stations at receipt and/or delivery
points along the new pipelines (including one at Compressor Station 1 and one at
Compressor Station 2).
Thirty-one valve sites at select points along the new pipelines at intervals
specified by U.S. Department of Transportation (USDOT) regulations at Title 49
Code of Federal Regulations (CFR) Part 192.
Eight sets of pig launcher and/or receiver sites at 11 points along the new
pipelines (including launcher/receiver sites at Compressor Stations 2 and 3).
4 The mileposts used in this report are based on three-dimensional changes in topography (elevation) along the proposed pipeline routes.
Therefore, the straight-line distance between two mileposts depicted on two-dimensional maps and figures of the routes may be less than
5,280 feet. The mileposts are reference points along the routes.
10-2
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
As required by 18 CFR 380.12, Atlantic is submitting this Environmental Report (ER) in
support of its Application to the Commission for a Certificate of Public Convenience and
Necessity (Certificate) to construct and operate the proposed ACP facilities.
Supply Header Project
DTI proposes to construct and operate approximately 37.5 miles of pipeline loop and
modify existing compression facilities in Pennsylvania and West Virginia (see Figure 1.1.1-1 in
Resource Report 1). This Project, referred to as the Supply Header Project (SHP), will enable
DTI to provide firm transportation service of up to 1.5 MMDth/d to various customers, including
Atlantic. Atlantic will be a Foundation Shipper in the SHP, and will utilize the SHP capacity to
allow its shippers access to natural gas supplies from various DTI receipt points for further
delivery to points along the ACP. By providing its customers access to an affordable and stable
source of natural gas, the SHP also satisfies the same purpose and need as the ACP by increasing
the reliability and security of natural gas supplies in Virginia and North Carolina.
DTI is seeking authorization from the Commission under Section 7(c) of the Natural Gas
Act to construct, own, operate, and maintain the following proposed facilities for the SHP:
Pipeline Loops:
TL -636: approximately 3.9 miles of underground 30 -inch outside diameter
natural gas pipeline looping DTI's existing LN -25 pipeline in Westmoreland
County, Pennsylvania.
TL -635: approximately 33.6 miles of underground 30 -inch outside diameter
natural gas pipeline looping DTI's existing TL -360 pipeline in Harrison,
Doddridge, Tyler, and Wetzel Counties, West Virginia.
Compressor Station Modifications:
JB Tonkin Compressor Station: modifications at DTI's existing JB Tonkin
Compressor Station in Westmoreland County, Pennsylvania.
Crayne Compressor Station: modifications at DTI's existing Crayne Compressor
Station in Greene County, Pennsylvania.
Burch Ridge Compressor Station: crossover piping at DTI's existing Burch
Ridge Compressor Station in Marshall County, West Virginia.
Mockingbird Hill Compressor Station: modifications at or near DTI's existing
Mockingbird Hill Compressor Station in Wetzel County, West Virginia.
Other Aboveground Facilities:
One new M&R station at a new delivery point within Atlantic's proposed
Compressor Station 1 in Lewis County, West Virginia.
Six valve sites at select points along the new pipeline loops at intervals specified
by USDOT regulations at 49 CFR 192.
10-3
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
Two sets of pig launcher and receiver sites at the ends of each of the new pipeline
loops.
DTI is also requesting authorization from the FERC under Section 7(b) of the Natural
Gas Act to abandon in place two existing gathering compressor units (Hasting Compressor Units
1 and 2) at its existing Hastings Compressor Station in Wetzel County, West Virginia.
As required by 18 CFR 380.12, DTI is submitting this ER in support of its Application to
the Commission for a Certificate to construct and operate the proposed SHP facilities.
1.2 BACKGROUND AND APPROACH
Cumulative impacts represent the incremental effects of a proposed action when added to
other past, present, and reasonably foreseeable future actions. Although the individual impact of
each separate action may be minor, the additive or synergistic effects of multiple actions could
be significant.
The purpose of this analysis is to identify and describe cumulative impacts that could
potentially result from construction and operation of the ACP and SHP (collectively, the
Projects) when considered in relation to other projects. In accordance with the National
Environmental Policy Act (NEPA), the cumulative impacts of the ACP and SHP and other
projects or actions in the same areas are considered. This analysis uses an approach consistent
with the methodology set forth in relevant guidelines from the Council on Environmental Quality
(CEQ) (1997, 2005) and the U.S. Environmental Protection Agency (EPA) (1999). Under these
guidelines, the inclusion of actions within the analysis is based on identifying commonalities of
impacts from other actions to potential impacts that will result from the Projects.
With respect to past actions, CEQ guidance (2005) allows for the adoption of a broad,
aggregated approach without "delving into the historical details of individual past actions." That
approach is adopted here. The current local or regional landscape in the ACP Project area and
SHP Project area forms the environmental baseline against which the impacts of reasonably
foreseeable future actions are considered. Recently completed and past projects are considered
part of the environmental baseline. Reasonably foreseeable projects that might cause cumulative
impacts in combination with the ACP and SHP include projects that are under construction,
approved, proposed, or planned. Impacts that are neither direct, indirect, nor reasonably
foreseeable do not warrant review under the NEPA.
In order to avoid unnecessary discussion of insignificant impacts and projects and to
focus the analysis on relevant projects and potentially significant impacts, the cumulative
impacts assessment for the Projects was conducted using the following guidelines:
Another project must impact a resource category that also is potentially impacted
by the ACP or SHP in the same general area as the Projects. More geographically
distant projects were not considered because their impacts will generally be
localized and, therefore, will not contribute significantly to cumulative effects in
the same areas as the Projects. Exceptions are impacts on air quality and
watersheds in which cumulative impacts were considered on a broader, more
regional basis.
10-4
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
The distance into the past and future that other projects could cumulatively impact
the same areas as the Projects is based on whether the impacts are short term, long
term, or permanent. The majority of the impacts related to the Projects will occur
during the construction phase. Atlantic and DTI are proposing to begin
construction in the Fall of 2016, assuming all necessary permits and regulatory
approvals are obtained, and placing the proposed ACP and SHP facilities into
service by the end of 2018.
Where a potential for cumulative impacts was indicated, those impacts have been
quantified to the extent practicable. In most cases, however, the potential impacts
could only be described qualitatively (e.g., impacts from projects that are in
planning stages or are contingent on economic conditions, availability of
financing, or the issuance of permits).
The criteria listed below define the Projects' region of influence, which is used in this
cumulative impacts assessment to describe the general area for which the Projects could
contribute to cumulative impacts. The region of influence varies depending on the resource
being discussed.
Potential impacts of the Projects on geology and soils, land uses, residential areas,
visual resources, cultural resources, and traffic will be highly localized; therefore,
other projects within 0.5 mile of the ACP and SHP work areas (e.g., commercial
developments or transportation projects) were evaluated for cumulative impacts
on these resources.
Waterbody and wetland crossings, as well as potential impacts on groundwater,
vegetation, and wildlife by the ACP and SHP will be localized. Therefore, the
analysis included cumulative impacts on these resources from other projects
within the same watersheds crossed by the Projects.
Ongoing operation of the ACP and SHP compressor stations will result in
continuing impacts on air quality in various Air Quality Control Regions
(AQCRs). Therefore, other projects with the potential to result in continuing
impacts on air quality (e.g., natural gas compressor stations or industrial facilities)
within the AQCRs that will also be impacted by an ACP or SHP compressor
station were considered.
Continuing noise impacts from the ACP or SHP compressor stations will be
localized to within 0.5 mile of each compressor station. Therefore, other projects
that will result in continuing impacts on noise affecting the same noise -sensitive
areas (NSAs) as the ACP and SHP compressor stations were evaluated.
The anticipated cumulative impacts of the Projects and other actions are discussed below.
2.0 PROJECTS AND ACTIVITIES CONSIDERED
Atlantic and DTI identified past, present, or reasonably foreseeable projects from review
of topographic maps, internet research, and by contacting County and City officials regarding
10-5
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
recent or planned developments and significant commercial/industrial developments within the
Counties and Cities crossed or affected by the Projects. Table A-1 in Attachment A lists past,
present, and reasonably foreseeable future projects that may cumulatively or additively impact
resources that could be affected by construction and operation of the ACP and/or SHP. s As
noted in the following subsections, some projects were eliminated from further consideration if it
was determined that they will not meet the criteria listed above or if insufficient information is
available to allow for a meaningful analysis.
Descriptions of potential cumulative impacts by resource category are presented in
Section 3.0. In cases where quantitative information is not available for the projects considered
in this analysis (e.g., projects in the planning stages or those contingent on economic conditions,
availability of financing, or the issuance of permits), the potential impacts of those projects have
been considered qualitatively.
Other Known Federal Energy Regulatory Commission -Jurisdictional Projects
In addition to the projects listed in Table A-1, there are FERC jurisdictional natural gas
projects recently completed, currently proposed, recently approved, or under consideration in the
States/Commonwealths crossed by the ACP and SHP, but not the same Counties or Cities.
These include the Atlantic Sunrise Project in North Carolina, Pennsylvania, and Virginia;
Constitution Pipeline and Wright Interconnect Projects in Pennsylvania; East Side Expansion
Project in Pennsylvania; Marcellus to Manhattan Project in Pennsylvania; Niagara Expansion
Project in Pennsylvania; Northeast Expansion Project in Pennsylvania; Northern Access 2015 —
West Side Expansion Project in Pennsylvania; West to East Overbeck to Leidy Project in
Pennsylvania; Giles County Project in Virginia and West Virginia; Kingsport Expansion Project
in Virginia; Smithfield III Expansion Project in West Virginia; Uniontown to Gas City
Expansion (U2GC) Project in Pennsylvania; and West Side Expansion and Modernization
Project in Pennsylvania and West Virginia. None of these projects will occur within the same
region of influence as the ACP and SHP; therefore, they are not discussed further.
There are several FERC jurisdictional projects currently proposed, under consideration,
being constructed, or recently completed that are located in whole or in part in the same Counties
or Cities as some of the ACP and SHP facilities. These include the Mountain Valley Pipeline
Project in Doddridge, Harrison, Lewis, Tyler, and Wetzel Counties, West Virginia (in pre -filing);
Rover Pipeline Project in Tyler and Doddridge Counties, West Virginia (in pre -filing); Natrium
to Market Project in Greene and Westmoreland Counties, Pennsylvania (completed in 2014);
Texas Eastern Appalachia Market 2014 Project in Westmoreland County, Pennsylvania
(construction ongoing), and Virginia Southside Expansion Project in Brunswick County,
Virginia (construction ongoing). These projects are included in the cumulative impacts
assessment (see Table A-1 in Attachment A).
5 Because the majority of potential project impacts will occur during the construction phase, the past projects included in Table A-1 primarily
are recently completed projects (2014 or later). Projects completed prior to 2014 are considered part of the environmental baseline and are
removed from further consideration unless operational impacts would affect the same resources as the ACP and SHP.
10-6
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
In addition to the FERC jurisdictional projects, DTI is proposing to add additional gas
coolers at the existing Mockingbird Hill Compressor Station in Wetzel County, West Virginia as
part of its proposed Monroe to Cornwell Project; and add a new turbine at the existing Burch
Ridge Compressor Station in Marshall County, West Virginia as part of its Clarington Project.
These Projects are not associated with the ACP or SHP. Construction activities for both Projects
are expected to be confined to the existing station sites. Therefore, no cumulative impacts
associated with these minor construction Projects are anticipated.
3.0 POTENTIAL CUMULATIVE IMPACTS BY RESOURCE
3.1 GEOLOGY AND SOILS
The facilities associated with the Projects are expected to have a direct but temporary
impact on near -surface geology and soils. Clearing activities could expose the soil to erosive
elements such as precipitation and wind. Atlantic and DTI will minimize impacts on geological
and soil resources by returning contours to preconstruction conditions to the maximum extent
practicable and implementing the 2013 versions of the FERC's Upland Erosion Control,
Revegetation, and Maintenance Plan (Plan) and Wetland and Waterbody Construction and
Mitigation Procedures (Procedures) as well as appropriate State/Commonwealth requirements or
guidelines.
The effects on geology and soils will be highly localized and limited primarily to the
period of construction; therefore, cumulative impacts on geology and soils will only occur if
other projects are constructed at the same time and place as the proposed facilities. Although the
Mountain Valley Pipeline Project has planned facilities in some of the same Counties as the ACP
and SHP, and the construction schedule is very similar to that of the Projects (December 2016
through December 2018), the facilities are considered too distant to contribute to cumulative
impacts on soils or geology. If the Mountain Valley Pipeline Project moves forward as currently
planned, the impacts of that project on geology and soils will be similar to those of the ACP and
SHP (i.e., short-term and localized impacts on topography and soils during construction).
The Texas Eastern Appalachia to Market 2014, Natrium to Market, Virginia Southside
Expansion, and Rover Pipeline Projects also have facilities located in the same Counties as the
ACP or SHP. These projects are either completed or anticipated to be completed prior to
construction of the ACP and SHP. Because impacts on topography and soils are short term and
localized, and the rights-of-way and workspaces associated with construction of the Projects will
be restored and stabilized prior to construction of the ACP and SHP, the potential for cumulative
impacts is significantly reduced. No major long-term impacts are anticipated and, therefore, no
significant cumulative impacts on geology and soils are expected.
Construction of some of the other projects listed in Table A-1 in Attachment A could
coincide with the schedule proposed for the ACP and SHP. Projects that require significant
excavation or grading will also have temporary, direct impacts on near -surface geology and soils.
Like the ACP and SHP, however, the duration and effect of these projects will be minimized by
the implementation of erosion control and restoration measures. It is anticipated that project
construction and restoration activities as well as operation and maintenance activities will be
monitored throughout the process to verify compliance with erosion control and restoration
10-7
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
requirements. Consequently, potential cumulative effects on geological and soil resources are
expected to be minor.
3.2 WATERBODIES, GROUNDWATER, AND WETLANDS
Waterbodies
Cumulative effects on surface water resources affected by the ACP and SHP will be
limited to waterbodies that are affected by other projects located within the same watersheds. A
total of 1,294 waterbodies will be crossed by the ACP, including 526 perennial streams,
542 intermittent streams, 151 ephemeral streams, 48 canals/ditches, and 27 open water ponds. A
total of 145 waterbodies will be crossed by the SHP, including 119 perennial streams,
24 intermittent streams, and 2 open water pond. The ACP will cross 14 major waterbodies via
the horizontal directional drill (HDD), dam-and-pump/flume, or wet crossing methods; the SHP
will not cross major waterbodies.
The Texas Eastern Appalachia to Market 2014, Natrium to Market, Virginia Southside
Expansion, and Rover Pipeline Projects have facilities located in or near the same watersheds as
the SHP; however, these projects are either completed or anticipated to be completed prior to
construction of the ACP and SHP. Therefore, the potential for cumulative impacts is
significantly reduced. Some of the other projects listed in Table A-1 will be located within the
same watersheds crossed by the ACP and SHP, but only a small number of these will likely
involve direct in -stream impacts.
The ACP and SHP will not involve the construction of permanent diversions or dams.
Therefore, the Projects are expected to have only temporary impacts on surface water quality.
The greatest potential impacts of pipeline construction on surface waters will result from an
increase in sediment loading to surface waters during construction and an increase in internal
sediment loading due to channel/floodplain instability as a result of a change in
erosion/deposition patterns. The level of impact will depend on precipitation events, sediment
loads, stream area/velocity, channel integrity, bed material, and the proposed construction
method. These impacts will be avoided or minimized by implementation of the measures in the
Plan and Procedures as well as the construction, restoration, and mitigation plans that have been
developed for the Projects, including a Spill Prevention, Control, and Countermeasures Plan
(SPCC Plan) and Directional Drill Fluid Monitoring, Operations, and Contingency Plan (HDD
Plan).
The construction of some of the other projects listed in Table A-1 in Attachment A could
coincide with the schedule proposed for the ACP and SHP. Like the ACP and SHP, projects that
result in increased sediment loading will also have temporary, direct impacts on waterbodies.
However, the duration and effect of these projects will be minimized by the implementation of
erosion control and restoration measures. Consequently, potential cumulative effects on
waterbodies are expected to be minor.
Atlantic and DTI will hydrostatically test the new pipeline in accordance with the
USDOT's Pipeline and Hazardous Materials Safety Administration's (PHMSA) pipeline safety
regulations in 49 CFR 192 prior to placing the facilities into service. Water for hydrostatic
BY.,
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
testing will be withdrawn and discharged in accordance with State/Commonwealth regulations
and required permits. The planned locations of withdrawals and discharges are identified in
Resource Report 2.
It is unknown at this time if the projects listed in Table A-1 will use water from the same
surface sources within the same timeframe as the Projects. However, the proposed withdrawals
and discharges for the ACP and SHP will be conducted in accordance with applicable
State/Commonwealth permits and the Plan and Procedures (e.g., the test water will be discharged
to well -vegetated upland areas). Therefore, long-term impacts on surface water sources are not
expected as a result of hydrostatic testing activities, and the cumulative impacts on surface water
resources associated with the ACP and SHP and the projects listed in Table A-1 are expected to
be minor.
Groundwater
Cumulative effects on groundwater resources will be limited to areas that are affected by
other projects located near the ACP and SHP facilities. ACP and SHP construction activities
potentially could affect groundwater through increased turbidity, reduced water levels, and
contamination from accidental spills and leaks of hazardous materials associated with
construction equipment, refueling or maintenance of vehicles, and storage of fuel, oil, and other
fluids. Upon completion of construction, Atlantic and DTI will restore the ground surface as
closely as practicable to original contours and revegetate the rights-of-way to facilitate
restoration of preconstruction overland flow and recharge patterns. Potential impacts on
groundwater will be avoided or minimized by the use of both standard and specialized
construction techniques, including those specified in the Plan and Procedures as well as
implementation of the SPCC Plan.
Portions of the ACP and SHP will be built in areas containing karst terrain. These areas
have unique hydrology and highly productive aquifers which can be highly susceptible to
contamination via sinkholes and other features which provide a direct connection to
groundwater. Cumulative impacts on groundwater in karst areas are possible if construction of
the projects listed in Table A-1 occur in areas with karst. Atlantic and DTI are conducting a
survey to identify karst features along the route and will implement a Karst Monitoring and
Mitigation Plan for the Projects. The plan identifies best management practices for erosion and
sediment control, refueling, and other activities in the vicinity of karst features with a direct
connection to groundwater. The plan also includes practices for monitoring construction and
restoration activities in the vicinity of karst features. With the implementation of the Karst
Monitoring and Mitigation Plan, no cumulative impacts on karst due to construction and
operation of the Projects are anticipated.
The new pipelines and aboveground facilities for the Projects are not expected to result in
impacts on groundwater use or quality under typical operating conditions. Impacts could occur
if maintenance activities require excavation or repair in proximity to water supply wells or
springs. In such cases, the impacts and mitigation would be similar to those described above for
construction activities.
10-9
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
Wetlands
There will be a loss of some existing wetland features as a result of the construction and
operation of the proposed ACP and SHP facilities and other reasonably foreseeable projects in
West Virginia, Virginia, North Carolina, and Pennsylvania. Based on field and National
Wetlands Inventory data, a total of 1,068 wetlands will be crossed by the proposed ACP
pipelines and 24 wetlands will be crossed by the proposed SHP pipelines. Maintenance activities
along the ACP and SHP pipeline rights-of-way will permanently affect approximately
204.7 acres of wetlands due to the conversion of palustrine forested wetland and palustrine
scrub -shrub wetland to palustrine emergent wetland types. Additional wetlands will be affected
by construction of aboveground facilities and use of access roads. Some of the projects listed in
Table A-1 will be located within the same watersheds crossed by the ACP and SHP, but only a
small number of these, if any, will likely involve direct impacts to the same wetland features.
Atlantic and DTI will minimize impacts on wetlands by following the wetland
construction and restoration guidelines contained in the Plan and Procedures; by implementing
Compensatory Wetland Mitigation Plans; and by complying with the conditions of the wetland
permits that will be issued by the U.S. Army Corps of Engineers (USACE) and
State/Commonwealth agencies. Similar mitigation is expected to be required for wetland
impacts associated with the other projects listed in Table A-1. Although construction of the ACP
and SHP along with the other projects in the area could result in the conversion or reduction in
the amount of existing wetlands in the vicinity, the creation of new wetlands and restoration or
enhancement of existing wetlands as required by the USACE are expected to appropriately
mitigate for impacts on wetland resources and minimize cumulative wetland effects.
3.3 VEGETATION, WILDLIFE AND HABITAT, AND AQUATIC RESOURCES
Vegetation
The Projects cross various upland and wetland land cover classes that support diverse
vegetation communities. The proposed ACP pipeline facilities upland forest/woodland
(241.8 miles), cultivated cropland (86.8 miles), wetlands (69.9 miles), pasture (64.2 miles), tree
plantation/harvested forest (59.4 miles), developed (21.7 miles), open land (17.0 miles), and
open water (3.3 miles). The proposed SHP pipeline facilities cross upland forest/woodland
(33.0 miles), pasture (2.2 miles), developed land (1.3 miles), cultivated cropland (0.5 mile),
wetlands (0.3 mile), open water (0.2 mile), open land (less than 0.1 mile), and tree
plantations/harvested forest (less than 0.1 mile). The types of upland woodland/forest crossed by
the Projects include coniferous forests, deciduous forests, mixed forests, deciduous savanna and
glades, and floodplain and riparian forests.
Right-of-way clearing and grading and other construction activities associated with the
Projects along with some of the other projects listed in Table A-1 could result in the removal of
vegetation, alteration of wildlife habitat, displacement of wildlife, and other potential secondary
effects such as increased population stress, predation, and the establishment of invasive plant
species. These effects would be greatest where the other projects are constructed within the
same timeframe and areas as the ACP and SHP, and where the recovery time of the vegetation or
habitat takes longer to restore to its preconstruction state.
10-10
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
Most areas disturbed by the Projects will be allowed to return to pre-existing conditions
following construction. In addition, the extent and duration of impacts caused by construction of
the ACP and SHP in these areas will be reduced by implementation of the Plan and Procedures,
the SPCC Plan, and other construction, restoration, and mitigation plans. The other projects
most likely will implement similar plans and procedures to avoid or minimize impacts.
Most vegetation types affected by the Projects will be restored following construction. In
forested areas, however, recovery of woody vegetation in temporary workspace could take
decades. Additionally, forested land in the maintained pipeline rights-of-way will be converted
to herbaceous cover types. If other projects built in the same areas as the ACP and SHP remove
woody vegetation, cumulative impacts to forests could occur.
As discussed previously, the Mountain Valley Pipeline Project will include pipeline
facilities in some of the same Counties as the ACP and SHP and will be constructed on a similar
schedule. For the shared Counties, the Mountain Valley Pipeline Project will likely result in
vegetation impacts similar to the ACP and SHP. Although construction of the Texas Eastern
Appalachia to Market 2014, Natrium to Market, Virginia Southside Expansion, and Rover
Pipeline Projects are either completed or anticipated to be completed by the time the ACP and
SHP are constructed, the effects of tree clearing and associated change in habitats will persist
beyond restoration of the areas.
Wildlife and Habitat
Construction and operation of the Projects may result in short- and long-term impacts on
wildlife species and their existing habitats along the proposed pipeline routes and at aboveground
facility sites. The extent and duration of impacts will vary depending on the species present in
each affected habitat type and their individual life histories. Construction activities will likely
displace species from areas within and adjacent to the rights-of-way, but the impact is expected
to be short term and limited to the period of construction. Operation of the proposed pipelines
will cause minimal impacts on wildlife species because vegetation mowing or clearing will occur
outside of the nesting season for migratory birds and no more than once every three years.
Operation of the aboveground facilities may displace some species due to noise but there is
ample suitable habitat available in the vicinity of the aboveground facility sites to accommodate
these species.
To minimize potential impacts on wildlife species, such as nesting and migratory birds
and roosting bats, Atlantic and DTI will implement timing restrictions for vegetation clearing.
After construction is complete, Atlantic and DTI will restore the rights-of-way as near as
practicable to preconstruction conditions in accordance with the Plan and Procedures and the
other construction, restoration, and mitigation plans prepared for the Projects. Cropland will be
restored to active agricultural production, and other areas will be revegetated using methods and
seed mixes appropriate to existing land uses and cover types. With the exception of forested
lands, the Projects will not permanently alter the characteristics of the majority of the available
wildlife habitats. Consequently, most impacts on wildlife are expected to be temporary.
As discussed above, the Mountain Valley Pipeline Project will include pipeline facilities
in some of the same Counties as the ACP and SHP and will be constructed on a similar schedule.
10-11
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
For the shared Counties, the Mountain Valley Pipeline Project will likely result in wildlife
habitat impacts similar to the ACP and SHP. For the Texas Eastern Appalachia to Market 2014,
Natrium to Market, Virginia Southside Expansion, Rover Pipeline Projects, and other projects
listed in Table A-1 that are either completed or anticipated to be completed by the time the ACP
and SHP are constructed, the effects of tree clearing and associated change in habitats will persist
beyond restoration of the areas.
Fish
Construction of the ACP and SHP at the same time as other projects listed in Table A-1
could result in cumulative impacts on aquatic resources, such as groundwater, surface water, and
wetlands. It is unclear how many of the streams crossed by the Projects could also be affected
by other projects. Given that the Mountain Valley Pipeline will include pipeline facilities in
some of the same Counties as the ACP and SHP, and will be constructed on a similar schedule,
there is a potential for cumulative surface water and aquatic resource impacts. Potential impacts
on waterbodies within the collective ACP/SHP and Mountain Valley Pipeline project areas could
include temporary sedimentation and turbidity, destruction of stream cover, introduction of
pollutants, interruption of fish migration and spawning, and entrainment of fish.
Many of the potential impacts of the Projects on essential fish habitat (EFH) and
managed fish species will be similar to those described for surface waters. Atlantic is evaluating
the HDD method for the crossing of the Southern Branch Elizabeth River, which is designated as
a Habitat Area of Particular Concern for the sandbar shark, serving as a primary and secondary
nursery for this large coastal species. If implemented, the HDD method will avoid direct impacts
on the waterbody. However, impacts on EFH could result from an inadvertent return of drilling
fluid, inadvertent hazardous material spills, runoff of sediment from construction areas into the
waterbody, or water withdrawals for hydrostatic testing. Most of the other waterbodies will be
crossed using a dry crossing method, which will minimize impacts from sedimentation and
turbidity.
Based on the current schedule for the Projects, in -stream construction activities could
take place year round. Nonetheless, Atlantic and DTI will comply with time of year restrictions
and conditions unless specifically authorized by the appropriate agencies. To the extent that in -
stream activities are necessary outside of construction timing windows for fish species, Atlantic
and DTI will seek approvals from the appropriate agencies for these crossings on a case-by-case
basis. Following construction, streambeds and banks will be restored to preconstruction contours
to the extent practicable and stabilized. Disturbed areas will be seeded and mulched, as
necessary, to prevent erosion. Permanent erosion and sediment controls will be installed as
described in the Procedures. The potential impacts of the Projects on aquatic resources,
including EFH, will be minimized through implementation of the measures described in the
Procedures, SPCC Plan, HDD Plan, and other applicable mitigation measures. Operation of the
ACP and SHP is not expected to affect fisheries.
The Mountain Valley Pipeline Project is expected to implement similar plans and
procedures. The potential for cumulative impacts will be minimized due to the short duration of
the proposed in -stream activities and use of the HDD crossing method or dry crossing methods,
10-12
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
where applicable. Collectively, these measures will avoid significant cumulative impacts on
aquatic resources, including EFH and managed fish species.
If the other projects listed in Table A-1 involve direct in -stream impacts on waterbodies,
they will be required to obtain permits from the USACE and appropriate State/Commonwealth
agencies, and consult with the U.S. Fish and Wildlife Service (FWS) and other agencies as
applicable. These agencies will assess the potential for cumulative impacts from these projects
and require measures to mitigate impacts on aquatic resources associated with these other
projects. Therefore, the cumulative effects on aquatic resources, including EFH and managed
fish species, are expected to be minor.
3.4 LAND USE, RECREATION, SPECIAL INTEREST AREAS, AND VISUAL
RESOURCES
Land Use
The ACP and SHP, in combination with other foreseeable future projects listed in Table
A-1, will result in temporary and permanent changes in current land uses. Construction of the
ACP will affect a total of approximately 9,829.9 acres, and construction of the SHP will affect a
total of approximately 796.2 acres. For the ACP, upland forest/woodland is the principal land
use type crossed at 241.8 miles or approximately 42.9 percent of the combined length of the
proposed mainline and lateral pipelines. In descending order, the other land use types crossed by
the ACP pipeline facilities are: cultivated cropland (86.8 miles or 15.4 percent), wetlands
(69.9 miles or 12.4 percent), pasture (64.2 miles or 11.4 percent), tree plantation/harvested forest
(59.4 miles or 10.5 percent), developed (21.7 miles or 3.8 percent), open land (17.0 miles or
3.0 percent), and open water (3.3 miles or 0.6 percent).
The principal land use type crossed by the proposed SHP pipeline facilities is upland
forest/woodland at 33.0 miles or approximately 88.0 percent of the combined length of the
pipeline loops. In descending order, the other land uses crossed by the SHP facilities are pasture
(2.2 miles or 5.9 percent), developed land (1.3 miles or 3.5 percent), cultivated cropland (0.5
mile or less than 1.3 percent), wetlands (0.3 mile or 0.8 percent), open water (0.2 mile of 0.5
percent), open land (0.1 mile or less that 0.1 percent), and tree plantations/harvested forest (less
than 0.1 mile or less than 0.1 percent).
The majority of land use impacts associated with the Projects will be temporary because
most land uses will be allowed to revert to prior uses following construction, which will
minimize cumulative impacts. An exception will be the conversion of forested land to
herbaceous cover or developed land in the maintained easements for the pipelines and at
aboveground facility sites.
Recreation and Special Interest Areas
Recreation and special interest areas include Federal, State/Commonwealth, or County
parks and forests, conservation lands, wildlife habitat management areas, game management
areas, natural landmarks, scenic byways, designated trails, recreational rivers, campgrounds, and
cemeteries. The proposed ACP and SHP pipelines will cross or pass within 0.25 mile of a
10-13
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
number of publicly owned and managed lands, including lands managed by the U.S. Forest
Service, National Park Service, FWS, State of West Virginia, and Commonwealth of Virginia.
These lands include the Monongahela National Forest, George Washington National Forest,
Appalachian National Scenic Trail (Appalachian Trail or Trail), Blue Ridge Parkway, Great
Dismal Swamp National Wildlife Refuge, Huttonsville Wildlife Management Area, Lewis
Wetzel Wildlife Management Area, and Highland Wildlife Management Area. For these areas,
Atlantic and DTI will comply with the standards and guidelines of applicable land management
plans and will implement the Plan and Procedures and other construction restoration and
mitigation plans to avoid, minimize, or mitigate impacts. Addition discussion regarding the
Appalachian Trail is provided in a separate subsection below.
A number of other recreational or special interest areas will be affected by the ACP and
SHP. Project impacts on these recreational and special interest areas occurring outside of
forested land will be temporary and limited to the period of active construction. These impacts
will be minimized by implementing the Plan and Procedures, the SPCC Plan, and other
applicable mitigation measures. Some of the other projects listed in Table A-1 have crossed or
will cross Federal, State/Commonwealth, or local recreation and special interest areas. However,
none appear to cross at the same locations as those affected by the ACP and SHP. As a result,
although the Projects could have impacts on recreation and special interest areas, cumulative
impacts on those same areas are not anticipated.
Appalachian Trail
Atlantic is aware of several other pipeline projects under development that are proposing
to cross the Appalachian Trail at various points along its approximately 2,180 -mile -long
distance. Table 3.4-1 identifies projects where public information is available indicating that the
projects are actively under development as of the date of this filing. After reviewing available
information, Atlantic has omitted from this table projects for which development has been
suspended or on hold (e.g., Spectra Energy's Carolina Pipeline Project and Transcontinental Gas
Pipeline Company's Appalachian Connector Project). Atlantic is not involved with the
development of other pipeline projects that may cross the Appalachian Trail.
The purpose of the ACP is to provide new natural gas infrastructure at delivery points to
serve consumers in southeastern Virginia and eastern North Carolina. No other project shares
the same delivery points or meets the same demand for natural gas service at these locations. If
constructed, the Mountain Valley Pipeline, as currently proposed, will cross the Appalachian
Trail over 110 miles to the southwest of the proposed ACP crossing of the Trail. This is the
closest known potential pipeline crossing of the Appalachian Trail to the ACP. The distance
between the ACP and the Mountain Valley Pipeline will avoid potential cumulative impacts by
separating the areas of effect. Other proposed pipeline projects crossing the Appalachian Trail
are at even greater distances away from the ACP creating even less cumulative effects should
these projects ever be constructed.
10-14
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
TABLE 3.4-1
Other Projects Proposing to Cross the Appalachian Trail
Distance and Direction from
Location of the Proposed
Existing Facilities
Proposed
the ACP crossing of the
Applicant
Project
Description
Appalachian Trail Crossing
at Crossing
Crossing Method
Status
Appalachian Trail
Tennessee Gas
Northeast
30 -inch diameter
Berkshire County, MA,
Adjacent to an
Conventional
FERC pre -filing;
Approximately 480 miles to
Pipeline
Energy Direct
natural gas transmission
approximately 1 mile east of
existing electric
bore
construction
the northeast
pipeline
Pittsfield
transmission line
anticipated in
2017
UGI Penn
Unknown
16 -inch diameter
Berks/Schuylkill County line,
Greenfield
Unknown
Unknown
Approximately 230 miles to
natural gas transmission
PA, approximately 5 miles
the northeast
pipeline
northwest of Bethel
Transcontinental
Atlantic Sunrise
42 -inch diameter
Lebanon County, PA,
Greenfield
Conventional
FERC
Approximately 230 miles to
Gas Pipeline
natural gas transmission
approximately 4 miles
bore
proceeding;
the northeast
pipeline
north/northeast of Ft
construction
Indiantown Gap
anticipated in
2016
Mountain Valley
Mountain Valley
42 -inch diameter
Monroe County, WV/Giles
Greenfield
Undetermined
FERC pre -filing;
Approximately 100 miles to
Pipeline
Pipeline
natural gas transmission
County, VA line,
construction
the southwest
pipeline
approximately 4 miles north of
anticipated in
Pearisburg
2017
PermEast
PennEast
36 -inch diameter
Carbon County, PA,
Greenfield
Conventional
FERC pre -filing;
Approximately 270 miles to
Pipeline
Pipeline
natural gas transmission
approximately 0.5 mile north
bore
construction
the northeast
Company
pipeline
of Danielsville
anticipated in
2017
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
By utilizing the trenchless HDD method to install the proposed pipeline beneath the
Appalachian Trail (and adjacent Blue Ridge Parkway and portions of the George Washington
National Forest), direct impacts to the Trail will be minimized, including impacts on vegetation
immediately adjacent to the Trail. The proposed entry and exit locations for the HDD will be
located approximately 1,385 feet to the northwest and 3,375 feet to the southeast of the AT,
respectively. These distances from the Appalachian Trail will represent areas where no clearing
of trees along the right-of-way will occur on the land surface in the immediate vicinity of the
Trail, significantly minimizing the potential for visual impacts to users of the Trail. Short-term
impacts on visitors to the Appalachian Trail and Blue Ridge Parkway could result from
construction noise associated with the HDD, but these impacts will be temporary, localized, and
limited to the period of construction. Atlantic will implement mitigation measures during the
HDD to minimize noise, if necessary.
In May of 2015, the Appalachian Trail Conservancy (ATC) finalized its Policy on
Pipeline Crossings of the Appalachian Trail (ATC, 2015). This policy document states that the
ATC will participate and encourage Appalachian Trail -maintaining clubs, individual members,
agency partners, and natural resource conservation organizations to participate in public review
procedures for all pipelines proposed to cross the Appalachian Trail landscape. The ATC Policy
sets out criteria the ATC will utilize to consider new pipeline proposals. As noted on its website,
the ATC "seeks to avoid, minimize, or eliminate the visual and experiential impacts of all
utilities, including oil, gas, and petroleum products pipelines, on the Appalachian Trail and its
surrounding landscapes. Where it is not possible to eliminate impacts, the ATC's goal is to
obtain mitigation or offsets that result in no net loss of Trail values." As outlined in Resource
Report 1, Atlantic is consulting with the ATC on the Project to minimize its impacts to the
Appalachian Trail and its visitors.
For these reasons, cumulative impacts to the Appalachian Trail system due to
construction and operation of the ACP are not anticipated.
Visual Resources
The proposed ACP and SHP cross a range of visual landscapes, from mountainous areas
to mosaics of forest and farmland to suburban and urban settings. Visual resources in these areas
are a function of geology, climate, and historical processes as influenced by topographic relief,
vegetation, water, wildlife, and land use (e.g., industrial, timber, agriculture, and urban
development activities). The visual qualities of the landscape are further influenced by existing
linear installations such as highways, railroads, pipelines, and electrical transmission and
distribution lines. The physiographic provinces crossed by the ACP and SHP include the
Appalachian Plateau Province, Valley and Ridge Province, Blue Ridge Province, Piedmont
Province, and Coastal Plain Province.
Visual impacts will be greatest where the pipeline route parallels or crosses roads and the
pipeline right-of-way may be seen by passing motorists, at residences where vegetation used for
visual screening or for ornamental value is removed, in forested areas, and in mountainous areas.
The duration of visual impacts will depend on the type of vegetation that is cleared or altered.
The impact will be greater in forested land, which will take longer than other vegetation types to
10-16
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
regenerate and will be prevented from re-establishing on the permanently maintained rights-of-
way. Topographic alterations such as side -hill cuts that may be necessary to construct the
pipeline will be restored during right-of-way restoration. The visibility of such alterations will
diminish over time as the affected areas age and begin to blend with the surrounding landscape.
To minimize construction impacts on visual resources, Atlantic and DTI have aligned the
proposed pipeline routes adjacent to existing utility transmission rights-of-way or other
transportation corridors where feasible. In areas where right-of-way collocation is not feasible,
Atlantic and DTI have aligned the pipeline to avoid aesthetic features to the extent practicable,
and will restore the right-of-way in accordance with the Plan and Procedures and the other
construction, restoration, and mitigation plans prepared for the Projects.
In many cases, aboveground facilities will be constructed on the same sites (e.g., the
Kincheloe M&R Station will be built on the same site as Compressor Station 1), at existing
aboveground facility sites, or along existing pipeline facilities, which will minimize visual
impacts. Upon completion of construction, all of the aboveground facility sites will be stabilized
with gravel within a fenced enclosure for security. Lighting and signage will be designed to
minimize impacts on adjacent residences and sensitive resources. Atlantic and DTI will consult
with local jurisdictions regarding appropriate landscaping and/or other means of mitigating
visual impacts of these facilities.
For public lands and aboveground historic properties affected by the Projects, Atlantic
and DTI will mitigate for effects on visual resources in accordance with the requirements of the
visual resource management system specific to the applicable agency.
Of the projects listed in Table A-1, the proposed linear projects are likely to have the
greatest cumulative impact on visual resources. The ACP and SHP facilities will add
incrementally to this impact but the overall contribution will be relatively minor given that the
majority of the ACP and SHP pipeline facilities will be buried. For aboveground facilities, the
impacts on visual resources from each individual facility will depend on the preconstruction
condition and the visibility from the surrounding area. As discussed above, the impact of the
aboveground facilities on visual resources will be minimized by constructing them on the same
site or at or along existing sites/facilities in many cases. Disturbed areas will be revegetated after
construction, and mitigation measures will be implemented to minimize visual impacts to the
extent practicable. Projects listed in Table A-1 may also be required to evaluate potential visual
impacts and implement appropriate mitigation measures as required by land management
agencies and applicable regulations. Therefore, cumulative visual impacts will be reduced.
3.5 SOCIOECONOMICS
Economy and Employment
Atlantic and DTI estimate that approximately 50 percent of the ACP and SHP workforces
will be individuals who reside within commuting distances of the Projects or are members of a
local union hall. The Counties and Cities affected by the Projects have a combined civilian labor
force of approximately 950,347 people and an average unemployment rate of 6.7 percent
(U.S. Census Bureau, 2015). These data suggest that the local labor force could meet much of
10-17
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
the employment needs required for construction of the Projects. However, if other projects are
built at the same time, the demand for workers could exceed the local supply of appropriately
skilled labor.
If the Mountain Valley Pipeline Project moves forward as planned, the construction
schedule will be similar to the Projects, which could impact the supply of available local
workers. Should the portions of the projects, or portions of the other projects in Table A-1 that
are in the same or surrounding Counties, be constructed at the same time as the Projects, skilled
labor from the adjacent non -shared Counties could potentially be employed. Because the Texas
Eastern Appalachia to Market 2014, Natrium to Market, Virginia Southside Expansion, and
Rover Pipeline Projects are completed or anticipated to be completed prior to construction of the
ACP and SHP, no cumulative impacts are likely from these projects.
Atlantic and DTI will hire an estimated 92 permanent employees to support operation and
maintenance of the ACP and SHP facilities, and it is likely that new permanent employees will
be hired for some the other projects. The hiring of these workers will have a minor but positive
impact on unemployment in the Counties crossed or affected by the Projects. The long-term
employment opportunities associated with the other projects in Table A-1 are unknown, but they
are likely to provide some other permanent employment opportunities.
In addition to a positive impact on local employment, all of the projects will provide an
increase in tax revenue for Pennsylvania, West Virginia, Virginia, and North Carolina and a
positive impact on local economies through the payment of payroll, sales, and property taxes and
other taxes and fees. Construction and operation of the ACP will result in economic benefits
through increased payroll, tax revenue, purchase of materials, and utilization of local vendors
and businesses. Atlantic and DTI commissioned a study by Chmura Economics and Analytics
(Chmura) to assess the economic impact of construction and operation of the ACP (Chmura,
2014). Assuming that capital expenditures associated with construction of the ACP will total
$4.6 billion dollars, 6 the study found a total economic impact (direct, indirect, and induced) of
$2.7 billion supporting a total of 17,240 jobs in West Virginia, Virginia, and North Carolina.
During operation, the ACP will have an annual direct spending impact of $69.2 million in
2019 dollars and employ 82 permanent workers in the three-State/Commonwealth region (22 in
West Virginia, 39 in Virginia, and 20 in North Carolina). Additionally, operation of the ACP
will have an indirect annual impact of $15.3 million in spending supporting 99 jobs (including
operational support positions with other regional companies, such as equipment maintenance and
repair personnel), and an induced annual impact of $12.6 million in spending supporting 90 jobs.
The annual induced impact will mostly support consumer service industries (Chmura, 2014).
Cumulatively, the Projects and the other nearby projects will have both short- and long-
term beneficial impacts on State/Commonwealth, County, City, and local economies. At a
County/City or local level, these beneficial impacts are anticipated wherever one or more
projects occur in the same County or City. Table A-1 includes a column which identifies
common Counties and Cities between the ACP, SHP, and other projects. At least one past,
6 The $4.6 billion capex is at the lower end of the range of $4.5 to $5 billion to construct the ACP.
10-18
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
present or reasonably foreseeable project occurs in each of the Counties and Cities crossed or
affected by the ACP and SHP, with the exception of Nottoway County, Virginia, where there are
none.
Temporary Housing
Temporary housing will be required for construction workers who will be needed for the
portion of the workforce not drawn from the local area. Given the current vacancy rates, the
number of rental housing units in the area, and the number of hotel/motel rooms available in the
cities and towns in the vicinity of the Projects, construction workers should not encounter
difficulty in finding temporary housing. If construction of the ACP and SHP occurs concurrently
with other projects, temporary housing may be more difficult to find and/or more expensive to
secure due to increased demand among workers. Some workers could be displaced to adjacent
Counties or Cities, which could increase commute times for these workers. These effects will be
temporary, lasting only for the duration of construction. There will be no long-term cumulative
impact on housing from the proposed Projects.
Public Services
The cumulative impact of the ACP and SHP and the other projects listed in Table A-1 on
infrastructure and public services will depend on the number of projects under construction at
one time. The small incremental demands of several projects occurring at the same time could
increase the need for police, fire, and emergency services. The increased need will be
temporary, occurring only for the duration of construction, and could be mitigated by the various
project sponsors providing their own personnel to augment the local capability or by providing
additional funds or training for local personnel. These activities would avoid or minimize the
potential for cumulative impacts.
As discussed in Resource Report 5, Atlantic and DTI will work with police, fire, and
medical services in the affected Counties and Cities to coordinate activities and confirm that
adequate resources are available for effective emergency response. The construction team
leaders (representing the construction contractors, DTI construction managers, DTI Project
supervisors, and DTI Project managers) will meet with emergency responders in each
County/City along the proposed pipeline routes to develop a response plan tailored to the
capabilities or needs of each County/City. These actions will help ensure adequate resources to
minimize cumulative impacts on emergency responders.
No long-term impacts from implementation of the ACP and SHP on infrastructure and
public services are anticipated. Therefore, no long-term cumulative effects are likely to occur.
Traffic and Transportation
Construction of the ACP and SHP could have a temporary impact on road traffic in some
areas and could contribute to cumulative traffic, parking, and transit impacts if other projects are
scheduled to take place at the same time and in the same area as the Projects.
10-19
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
Construction of the Projects will result in minor, short-term impacts on transportation
networks due to construction across roads and highways, commuting of the workforce, and the
movement of vehicles and delivery of equipment and materials to work areas. In addition, the
movement of construction equipment, materials, and personnel will cause a slight, temporary
increase in traffic volumes along area roadways. Impacts are expected to be minor and short
term because construction spreads and personnel will be geographically dispersed and personnel
will commute to and from work areas in early morning and late evening during non -peak traffic
hours. Additionally, Atlantic and DTI have developed and will implement a Traffic and
Transportation Management Plan, which will identify measures to minimize impacts on
roadways and traffic during construction. Once construction is complete, Atlantic's and DTI's
construction contractors will repair road damage that occurs as a result of construction, and
roadways will be restored to their preconstruction condition.
It is anticipated that other projects that may be constructed at the same time in the ACP
Project area or SHP Project area will be expected to implement similar transportation and traffic
control mitigation measures as described above. With the implementation of these measures, no
significant cumulative traffic impacts are anticipated during construction of the Projects.
Summary
Overall, the ACP and SHP will have short-term but positive effects on the economy in
the ACP Project area and SHP Project area, such as increased employment and sales and tax
revenues. Other major projects in the area will likely have similar impacts on the economy.
Thus, cumulative positive effects on socioeconomics in the ACP Project area and SHP Project
area are likely.
3.6 CULTURAL RESOURCES
As discussed in Resource Report 4, Atlantic and DTI have/are conducting field surveys to
identify archaeological and other historic sites that may be impacted by the Projects. The sites
will be evaluated to determine their eligibility for listing in the National Register of Historic
Places (NRHP). Atlantic and DTI intend, to the extent practicable, to avoid impacts on cultural
resource sites that are listed on or eligible for listing on the NRNP. A number of route variations
and adjustments to date have been identified, evaluated, and incorporated into the proposed
routes to avoid impacts on listed, eligible, or potentially eligible properties. In the event that
listed or eligible sites cannot be avoided, Atlantic and DTI will prepare treatment plans for these
sites in consultation with FERC staff; the appropriate Federal, Tribal, and State/Commonwealth
agencies; and applicable stakeholders. Additionally, Atlantic and DTI have developed and will
implement a Plan for the Unanticipated Discovery of Cultural Resources or Human Remains
during Construction for each State/Commonwealth to address unanticipated finds of artifacts or
human remains during construction of the Projects. All these actions collectively will avoid,
minimize, or mitigate impacts on significant cultural resource sites.
The currently proposed projects listed in Table A-1 which are Federal actions will
include measures (like the Projects) for avoiding, minimizing, or mitigating impacts on listed,
eligible, or potentially eligible properties. Where direct impacts on significant cultural resources
are unavoidable, mitigation (e.g., recovery and curation of artifacts) will occur before
10-20
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
construction. Non -Federal actions will need to comply with mitigation measures required by the
historical preservation office in the affected State/Commonwealth. For these reasons, and
because impacts tend to be highly localized, cumulative impacts on cultural resource sites are not
anticipated or will not be significant.
3.7 AIR QUALITY AND NOISE
Air Quality
Construction Emissions
Construction of most of the reasonably foreseeable future projects and activities listed in
Table A-1 will involve the use of heavy equipment that will generate emissions of air pollutants,
including fugitive dust. Consequently, construction of the ACP and SHP will contribute
cumulatively to air quality impacts. The combined impact of multiple construction projects
occurring in the same air shed and timeframe as the Projects could temporarily cause cumulative
air impacts in the ACP Project area and SHP Project area.
Construction activities for the proposed ACP and SHP facilities will result in emissions
of some pollutants due to the use of non -stationary equipment powered by diesel fuel or gasoline
engines; the temporary generation of fugitive dust due to disturbance of the ground surface and
other dust -generating actions; and indirect emissions attributable to workers commuting to and
from work sites during construction. These emissions will be temporary and localized and are
not expected to cause or significantly contribute to an exceedance of the National Ambient Air
Quality Standards (NAAQS). Construction of many of the projects listed in Table A-1 either
will not occur at the same time as construction of the ACP and SHP facilities or they are located
sufficiently far away as to not result in cumulative air impacts due to construction.
Operations Emissions
The proposed ACP compressor stations are all located in Counties designated as being in
attainment with the NAAQS for all criteria pollutants (i.e., sulfur dioxide, carbon monoxide,
nitrogen dioxide, inhalable particulate matter [both particulate matter sized 10 microns and
smaller in diameter and sized 2.5 microns and smaller in diameter], lead, and ozone). Therefore,
the stations must be evaluated to determine applicability of the Clean Air Act preconstruction
permitting program for attainment areas — the Prevention of Significant Deterioration (PSD)
program. Because the estimated potential compressor station emissions are not expected to
exceed the threshold value of 250 tons per year for criteria air pollutants, construction and
operation of the proposed ACP compressor stations will not trigger PSD requirements.
Moreover, none of the compressor stations are expected to emit more than 100,000 tons per year
of greenhouse gases (GHG).
The proposed modifications to the SHP compressor stations in West Virginia will occur
in Counties designated as being in attainment with the NAAQS for all criteria
pollutants. Because the Commonwealth of Pennsylvania is part of the Ozone Transport Region,
all Counties in Pennsylvania are treated as non -attainment for ozone. However, the estimated
potential emissions associated with the proposed work at the JB Tonkin and Crayne Compressor
Stations will not exceed applicable Non -attainment New Source Review permitting
10-21
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
thresholds. Further, the modifications to the Crayne and JB Tonkin compressor stations do not
trigger PSD for non -ozone precursor pollutants either. However, the modifications to the
Mockingbird station trigger the PSD major modification thresholds for particulate matter and
GHG emissions.
Recent projects performed at the existing compressor stations do not change this analysis.
In 2014, DTI completed construction of the Natrium to Market Project in Greene and
Westmoreland Counties, Pennsylvania. This project included the construction and operation of a
new 7,700 -horsepower compressor unit, upgrades to an existing measurement and regulation
station at the Crayne Compressor Station in Greene County, and changes to the JB Tonkin
Compressor Station in Westmoreland County. Although DTI will perform additional work at the
Crayne and JB Tonkin Compressor Stations for the SHP, the potential cumulative increase in
emissions at these compressor station sites will be minor and is not anticipated to trigger PSD
permitting, even considering the previous work at these facilities.
In addition to the new and modified compressor stations, the proposed new M&R stations
for the ACP will be sources of air emissions during operations. Additionally, non -combustion
related emissions will occur from the pipeline and at the proposed M&R stations during normal
operations. The potential emissions associated with the operation of the other projects in Table
A-1 are unknown, but because the projects listed in the table are located over a large area, have
varying construction schedules, and must adhere to Federal, State/Commonwealth, and local
regulations for the protection of ambient air quality, significant cumulative impacts on air quality
are not anticipated.
Greenhouse Gas Emissions
On December 18, 2014, the Council on Environmental Quality (CEQ) issued a draft
guidance document designed to assist federal agencies in the review of greenhouse gas (GHGs)
emissions under NEPA. The document — Draft Guidance for Greenhouse Gas Emissions and
Climate Change Impacts ("Draft Guidance") — was released for public comment and
consideration and, to date, CEQ has not indicated how it will respond to the significant
comments it received. As guidance, this document is subject to revision, modification, or even
withdrawal, and is not a final product of CEQ. Nevertheless, the following is noted with respect
to the draft CEQ guidance.
The ACP and SHP will have de minimis direct emissions of GHGs resulting from
temporary construction equipment, the operation of compressor stations, and occasional minor
methane leaks from pipeline operations. Total direct GHG emissions from these ACP and SHP
sources are projected by source in Resource Report 9. Currently, there is no standard
methodology to determine how a project's relatively small incremental contribution to GHGs
would result in physical effects on the global environment. Nonetheless, while comparing the
Project's emissions to emissions across the region is not determinative of potential impacts, such
a comparison is helpful in putting the emissions into context. The annual increase in future
potential GHG emissions for the Projects is negligible in comparison to the reported GHG
emissions for the States/Commonwealths encompassing the project area (e.g., West Virginia,
Virginia, and North Carolina). While the potential GHG emissions associated with the operation
of the other projects in Table A-1 are unknown, the emissions from the Project would not
10-22
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
produce significant incremental impacts in the Project area. Moreover, by increasing the
availability of natural gas for electricity generation, it is expected that the Project will facilitate
long-term reductions of GHG emissions in the Project area.
Noise
The Projects could contribute to cumulative noise impacts. In general, the operation of
the new and modified compressor stations and proposed new M&R stations for the Projects will
result in an increase in noise levels in the vicinity of the respective stations over the life of the
facilities. In addition, the installation of the new pipelines and other related construction
activities, including HDD crossings, will result in short-term increases in noise in the vicinity of
those activities. As needed, Atlantic and DTI will incorporate noise control measures and
equipment sound specifications into facility design plans to minimize noise impacts. Noise
impacts during construction will be highly localized and attenuate quickly as the distance from
the noise source increases.
Noise studies were completed to assess possible operational noise impacts at the ACP
and SHP aboveground facilities. For the analysis, the sound contribution of each station, as well
as the total noise (i.e., estimated sound level contribution of the station plus the measured
ambient noise level) was estimated at the closest NSA. The results of the acoustical analysis for
the compressor stations and M&R stations indicate that, with the implementation of adequate
noise control measures, the estimated noise attributable to the operation of the compressor or
M&R stations will be lower than 55-dBA L& or would be consistent with the existing noise
environment. Because noise sources that could cause perceptible vibration will be adequately
mitigated, no perceptible increase in vibration at NSAs during operation of the new compressor
stations is anticipated.
Noise associated with a blowdown event during operations will be controlled to minimize
impacts on nearby NSAs. The noise level of a unit blowdown event via a blowdown silencer
will be specified to meet a sound level of 60 dBA at a distance of 50 feet to control noise levels
at the closest NSA.
Long-term cumulative noise impacts are possible in the areas surrounding the ACP and
SHP compressor stations if other noise -generating facilities are constructed in close proximity to
the ACP and SHP compressor stations. As discussed above, DTI completed construction of the
Natrium to Market Project in Greene and Westmoreland Counties, Pennsylvania, which included
the construction and operation of a new 7,700 -horsepower compressor unit, upgrades to an
existing M&R station at the Crayne Compressor Station in Greene County, and modifications to
the JB Tonkin Compressor Station in Westmoreland County. Although DTI will also perform
modifications to the Crayne and JB Tonkin Compressor Stations for the SHP, the cumulative
potential increase in noise at the compressor station sites is anticipated to be relatively minor.
Therefore, significant noise impacts associated with construction and operation of the ACP or
SHP are not anticipated.
3.8 RELIABILITY AND SAFETY
Potential impacts of the ACP and SHP on public safety will be mitigated through
implementation of PHMSA's Minimum Federal Safety Standards in 49 CFR 192, which are
10-23
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
designed to protect the public and prevent natural gas facility accidents and failures. Atlantic
and DTI will design, construct, operate, and maintain the pipeline, aboveground, and other
associated facilities in accordance with the regulations in 49 CFR 192 and other applicable laws
and regulations. In addition, Atlantic and DTI will implement the mitigation measures specified
in all safety plans and procedures (see Resource Report 11). Other projects potentially
constructed in the vicinity of the ACP and SHP will be required to adhere to the safety
requirements, procedures, and laws and regulations applicable to those projects. Therefore, no
cumulative reliability or safety impacts are anticipated.
4.0 CONCLUSION
Past, present, and reasonably foreseeable future projects in the ACP Project area and SHP
Project area were identified for inclusion in this cumulative impacts assessment (see Table A-1
in Attachment A). The majority of the potential impacts associated with the Projects will be
temporary and minor when considered in combination with other past, present, and reasonably
foreseeable activities. However, some long-term cumulative impacts will occur on wetlands and
forested lands and associated wildlife habitats. Some long-term cumulative socioeconomic
benefits to the communities in the ACP Project area and SHP Project area will be realized from
increased spending and tax revenues. Short-term cumulative benefits will also be realized
through increased jobs and wages and purchases of goods and materials.
In summary, due to the implementation of specialized construction techniques, the
relatively short construction timeframe in any one location, and carefully developed resource
protection and mitigation plans, minimal cumulative effects are anticipated when the impacts of
the ACP and SHP are added to the projects identified in Table A-1.
10-24
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
5.0 REFERENCES
Appalachian Trail Conservancy. 2015. ATC Policy on Pipeline Crossings of the Appalachian
Trail. Available online at http://www.ratc.org/wp-content/uploads/2015/08/policy-on-
pipeline-crossings-2015.pdf Accessed August 2015.
Chmura Economics & Analytics. 2014. The Economic Impact of the Atlantic Coast Pipeline in
West Virginia, Virginia, and North Carolina.
Council on Environmental Quality. 1997. Considering Cumulative Effects under the National
Environmental Policy Act. January 1997.
Council on Environmental Quality. 2005. Guidance on the Consideration of Past Actions in
Cumulative Effects Analysis. June 2005.
Federal Energy Regulatory Commission. 2014. Major Pipeline Projects on the Horizon.
January 2010 to February 2014. Available online at https://www.ferc.gov
industries/gas/indus-act/pipelines/horizon-pipe.pdf Accessed March 2015.
Penn State Extension. 2013. Pennsylvania Natural Gas Pipeline Roundup. Marcellus & Utica
Shale Project. Available online at http://extension.psu.edu/natural-resources/natural-
gas/webinars/pennsylvania-natural-ag_s-pipeline-roundup/pennsylvania-natural-gas-
pipeline-roundup-powerpoint-october-17-2013. Accessed March 2015.
U.S Global Change Research Program. Global Climate Change Impacts in the United States.
Available online at http://downloads.globalchange.gov/usimpacts/pdfs/climate-impacts-
report.pdf Accessed March 2015.
U.S. Census Bureau. 2015. 2008-2012 Employment Status. American Community Survey 5 -
Year Estimates. Available online at: http://www.census.gov/acs/www/data_
documentation/2012 release/. Accessed March 2015.
U.S. Environmental Protection Agency. 1999. Consideration of Cumulative Impacts in EPA
Review of NEPA Documents. EPA 315-R-99-002. May 1999.
10-25
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
and
DOMINION TRANSMISSION, INC.
SUPPLY HEADER PROJECT
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
ATTACHMENT A
Table A-1— Past, Present, and Reasonably Foreseeable Future Projects for
the Atlantic Coast Pipeline and Supply Header Project
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
1 L -A-1
Company
TABLE A-1
Clark District of Harrison
Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project a, b
Closest Distance
Facility/State/
Common
and Direction
Run Substation
Project Name
Proponent
Counties/Cities Description
From Project
Status
ATLANTIC COAST PH'ELINE
5.1 miles
Anticipated
Falls 138kV
West Virginia
line from West Milford
northeast
completion December
Oak Mound —
Trans -Allegheny
Harrison An 18 -mile -long 138 kV
9.7 miles
Anticipated
Waldo Run 138 kV
Interstate Line
transmission line from the
northeast
completion in
Transmission
Company (TYAILCO),
existing Oak Mound
Company
December 2015
Project
a FirstEnergy
Substation, located in the
Mountain Valley
EQT Midstream
1 L -A-1
Company
Clark District of Harrison
County and the Waldo
Run Substation
Buckhannon — Glen
Trans -Allegheny
Harrison, Lewis
New 138 kV transmission
5.1 miles
Anticipated
Falls 138kV
Interstate Line
line from West Milford
northeast
completion December
Transmission
Company (TrAILCo),
Substation to the existing
2015
Project
a FirstEnergy
Buckhannon to Glen Falls
Company
138 KV transmission line
Mountain Valley
EQT Midstream
Harrison, Lewis
FERC jurisdictional
0.7 miles
FERC pre -filing in
Pipeline Project
Partners, LP
natural gas pipeline
northwest
progress — pipeline
system spanning
construction
approximately 300 miles
anticipated to begin in
from northwestern West
December 2016,
Virginia to southern
anticipated in-service
Virginia
date of December
2018
Northwest Lewis
Lewis County
Lewis
Extension of water service
0.9 mile south
Anticipated
Water Extension
Commission
to homes located in areas
served by individual wells
Atlantic Coast
Atlantic Coast
Lewis
Utility services for
Intersects
Proposed, to coincide
Pipeline Utility
Pipeline, LLC
Compressor Station I
Compressor
with construction of
Services `
Station 1
the compressor
station
Atlantic Coast
Atlantic Coast
Lewis
Microwave tower at
Within
Proposed, to coincide
Pipeline
Pipeline, LLC
Compressor Station 1
Compressor
with construction of
Communications
Station 1
the compressor
Network °
station
Upshur County
Upshur County
Upshur
Improvements to the
4.1 miles
In progress
Development
Development
industrial park including
northeast
Authority Industrial
Authority
water, sewer, and gas
Park
service
Corridor H
West Virginia
Randolph
Expansion of highway
40.3 miles
hi progress
Expansion Project
Department of
corridor
northeast
Transportation
Hannon Water
Town of Harmon
Randolph
Improvements to the
28.7 miles
Anticipated
Extension
Town of Hannon Water
northeast
Treatment Plant and
extension of water service
along Route 32
Atlantic Coast
Atlantic Coast
Lewis
Microwave tower at the
Within Long
Proposed, to coincide
Pipeline
Pipeline, LLC
Long Run M&R Station
Run
with construction of
Communications
Compressor
the compressor
Network'
Station
station
Upper Greenbrier
U.S. Forest
Randolph,
Timber management
Unknown
Decision
North Project
Service/Monongahela
Pocahontas
project; also aquatic,
Notice/Finding of No
National Forest
watershed, and recreation
Significant Impact
improvements throughout
No. 4 issued in May
the Upper Greenbrier
2015; anticipated to
River Watershed
start 3`" or 4"' quarter
of 2015
1 L -A-1
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
1 O -A-2
National Forest
TABLE A-1 (cont'd)
movement, including
Past, Present,
and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project a'"
Closest Distance
Facility/State/
Common
and Direction
Project Name
Proponent
Counties/Cities Description
From Project Status
West Fork of
West Virginia State
Randolph, Reconstruction of
Intersects at Under review
Greenbrier Rail
Rail Authority/U.S.
Pocahontas approximately 27.2 miles
milepost (MP)
With Trail
Forest Service/
of railroad for commercial
71.4
Development
Monongahela
tourism and freight
wastewater treatment
1 O -A-2
National Forest
movement, including
approximately 21 -mile -
long parallel foot and
horse trail for public
Linwood -Snowshoe
Pocahontas Public
Pocahontas
Construction of a new
13.7 miles
Anticipated
Wastewater Project
Service District
wastewater treatment
south-southwest
system
Virginia
Route 250
Virginia Department
Highland
Widening of existing
1.1 miles west
Completed November
(Highland
of Transportation
bridge
2012
Turnpike) — Crab
Run Bridge
Replacement
Augusta County —
Virginia Department
Augusta
Improvements to
3.2 miles
In progress —
Interstate 64, Exit
of Transportation
entrance/exit ramps,
northeast
anticipated
91 Improvements
expanding lanes near
completion Summer
and Route 285
intersection, bridge
2015
(Tinkling Spring
widening
Road)
Augusta County —
Virginia Department
Augusta
Repaving of 1.5 miles of
Intersects near
Completed Summer
Interstate 81
of Transportation
Interstate 81
MP 140.9
of 2015
Southbound
Pavement
Rehabilitation
Augusta County —
Virginia Department
Augusta
Bridge replacement
0.5 mile south
Anticipated Spring
Route 250 (Hankey
of Transportation
2015
Mountain Highway)
Calfpasture River
Bridge Replacement
Augusta County —
Virginia Department
Augusta
Bridge replacement
0.5 mile south-
Anticipated late 2014
Route 250 (Hankey
of Transportation
southeast
to Spring 2016
Mountain Highway)
White Oak Draft
Bridge
Augusta County —
Virginia Department
Augusta
Bridge replacement
0.8 mile north
In progress — Spring
Route 250
of Transportation
2014
(Shenandoah
Mountain Road)
Ramseys Draft
Bridge Replacement
Augusta County —
Virginia Department
Augusta
Intersection improvement
4.8 miles east
Construction pending
Route 262
of Transportation
project
funding
(Woodrow Wilson
Parkway) and Route
613 (Spring Hill
Road)
Augusta County —
Virginia Department
Augusta
Intersection improvements
2.5 miles
Anticipated — Spring
Route 608 (Tinkling
of Transportation
northeast
2015
Springs Road)
Augusta County —
Virginia Department
Augusta
Half -mile -long road
0.5 mile
Anticipated 2017 and
Route 610
of Transportation
widening
southeast
2018
Improvements
1 O -A-2
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
10-A-3
TABLE A-1 (cont'd)
340 in Stuarts Draft
Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project a'"
Closest Distance
planned development)
Facility/State/
Dominion
Common
Replacement of original
and Direction
In progress —
Project Name
Proponent
Counties/Cities
Description
From Project
Status
Augusta County —
Virginia Department
Augusta
Improve intersection
7.8 miles west-
Anticipated Fall 2015
Route 612 and
of Transportation
alignments
northwest
Route 792
towers between Lexington
hitersection
and Dooms
improvements
Virginia Department
Nelson
Shoulder widening at
4.4 miles
Anticipated April -
Augusta County —
Virginia Department
Augusta
Bridge replacement
12.9 miles
Anticipated
Route 685 (Lehigh
of Transportation
intersection with Highway
southwest
early 2016
Road) Bridge over
6 (River Road) to the
Little Calfpasture
north at the Albemarle
River
County border.
Augusta County —
Virginia Department
Augusta
Replacement of truss
0.5 mile east
Anticipated Fall 2014
Route 801 (Hangers
of Transportation
bridge with new structure
northeast
2014
Mill Road) Jennings
Branch Bridge
Augusta County —
Virginia Department
Augusta
Replacement of two-lane
0.5 mile west
Anticipated
Route 250
of Transportation
bridge
Spring 2016
(Churchville
Unknown
Nelson
Approximately 100 -acre
Intersects
Planning stage;
Avenue) — Bridge
resort and market
between
construction schedule
Replacement Over
development straddling
MPs 162.5 and
unknown
Whiskey Creek
Spruce Creek
162.7
Stone Valley Mixed
Integra Realty
Augusta
About 247 townhouse lots
1.3 miles north
Construction started
Use Planned
Resources
and 128 single family
in 2008 and is
Development
Virginia Department
Buckingham
residential lots off U.S.
5.6 miles
ongoing (pipeline was
10-A-3
340 in Stuarts Draft
rerouted to avoid
planned development)
Dooms — Lexington
Dominion
Augusta
Replacement of original
Intersects near
In progress —
Transmission Line
500 kV lattice -style
MP 142.8
estimated completion
Rebuild Project
transmission towers with
December 2015
new, galvanized steel
towers between Lexington
and Dooms
Route 29 Shoulder
Virginia Department
Nelson
Shoulder widening at
4.4 miles
Anticipated April -
Widening, Nelson
of Transportation
various locations from
southwest
December 2015
County
intersection with Highway
6 (River Road) to the
north at the Albemarle
County border.
Route 623
Virginia Department
Nelson
Bridge replacement
1.1 miles
Completed September
(Stagebridge Road)
of Transportation
northeast
2014
Bridge
Superstructure
Replacement over
Rockfish River
Spruce Creek
Unknown
Nelson
Approximately 100 -acre
Intersects
Planning stage;
Resort and Market
resort and market
between
construction schedule
development straddling
MPs 162.5 and
unknown
Spruce Creek
162.7
Water Treatment
Water and Sewer
Buckingham
Construction of a new
Unknown
In progress
Plant Project
Committee
water treatment facility
Route 20
Virginia Department
Buckingham
Intersection improvement
5.6 miles
Anticipated August
(Constitution
of Transportation
northeast
2015
Route)
Route 20 over Slate
Virginia Department
Buckingham
Bridge replacement
8.7 miles
Anticipated
River
of Transportation
northeast
September 2015
Atlantic Coast
Atlantic Coast
Buckingham
Utility services for
Intersects
Proposed, to coincide
Pipeline Utility
Pipeline, LLC
Compressor Station 2
Compressor
with construction of
Services `
Station 2
the compressor
station
10-A-3
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
10-A-4
TABLE A-1 (cont'd)
northern Cumberland
Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project a'"
Closest Distance
Facility/State/
Route 623 (Twin
Common
and Direction
Bridge replacement
Project Name
Proponent
Counties/Cities Description
From Project
Status
Atlantic Coast
Atlantic Coast
Buckingham Microwave tower at
Within
Proposed, to coincide
Pipeline
Pipeline, LLC
Compressor Station 2
Compressor
with construction of
Communications
Station 2
ACP aboveground
Network `
Virginia Department
Prince Edward
Bridge replacement
facilities
Cobbs Creek
Henrico County
Cumberland 1,100 -acre reservoir
25.2 miles
In progress — dam
Reservoir
anticipated 2014
partially located in
northeast
construction in 2017
10-A-4
northern Cumberland
County
Route 623 (Twin
Virginia Department
Prince Edward
Bridge replacement
10.7 miles
In progress
Bridges Road) over
of Transportation
southwest
Norfolk -Southern
Railroad
Route 633 (Virso
Virginia Department
Prince Edward
Bridge replacement
15.1 miles
In progress —
Road) Bridge
of Transportation
southwest
anticipated 2014
Replacement over
through October 2014
Bush River
Atlantic Coast
Atlantic Coast
Nottoway
Microwave tower at or
Within or
Proposed, to coincide
Pipeline
Pipeline, LLC
adjacent to Valve Site 12
adjacent to
with construction of
Communications
Valve Site 12
ACP aboveground
Network `
facilities
Route 600/226
Virginia Department
Dinwiddie
Two existing intersections
22.5 miles
Anticipated
Roundabout and
of Transportation
will be replaced with
northeast
Spring 2015 to Spring
Route 1/226
roundabouts
2016
Improvements
Foreign Affairs
U.S. Department of
Dinwiddie
Training center for
5.1 miles south-
Anticipated
Security Training
State
diplomatic security
southwest
Center
personnel within Fort
Pickett
Atlantic Coast
Atlantic Coast
Dinwiddie
Microwave tower at or
Within or
Proposed, to coincide
Pipeline
Pipeline, LLC
adjacent to Valve Site 13
adjacent to
with construction of
Communications
Valve Site 13
ACP aboveground
Network `
facilities
Brunswick Power
Dominion Virginia
Brunswick
1.358 -megawatt, natural
Intersects at MP
In progress —
Station a
Power
gas-fired power station
1.1 of AP -4;
estimated completion
and 13.5 -mile -long 500
encompasses
by Summer of 2016
kV transmission line
Brunswick
M&R Station
Brunswick Power
Dominion Virginia
Brunswick
13.5 miles of 500 kV
Adjacent
In progress —
Line
Power
electric transmission line
between MPs
estimated completion
267.1 and 279.1
by Summer of 2016
Virginia Southside
Transcontinental Gas
Brunswick
FERC jurisdictional
0.3 mile west
In progress —
Expansion Project
Pipe Line Company,
natural gas pipeline and
construction
LLC
associated facilities in
anticipated to be
Virginia
complete in
September 2015
Atlantic Coast
Atlantic Coast
Brunswick
Utility services for the
Intersects
Proposed, to coincide
Pipeline Utility
Pipeline, LLC
Brunswick M&R Station
Brunswick
with construction of
Services °
M&R Station
the M&R Station
Atlantic Coast
Atlantic Coast
Brunswick
Microwave tower at the
Within the
Proposed, to coincide
Pipeline
Pipeline, LLC
Brunswick M&R Station
Brunswick
with construction of
Communications
M&R Station
ACP aboveground
Network `
facilities
Dominion Power
Dominion Virginia
Greensville
Installation of road and
Immediately
Proposed, activities
Plant road and
Power
sewer lines
adjacent (south)
will coincide with
sewer lines (non-
construction of
jurisdictional
Atlantic Coast
activities)
Pipeline
10-A-4
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
General Thomas
Highway and Rose
Valley Road road
widening
Route 35 Bridge
Replacement over
Tarrara Creek
Route 58 Concrete
Rehabilitation
Route 58
Interchange
Route 671 over
Nottoway River
Route 671
Widening
Route 58/Holland
Road Improvements
Suffolk Gate 1
Heater Installation
Market Street
SAVE Project
Chesapeake Energy
Center
Decommissioning/
Fly Ash Removal
City of Chesapeake
Future Stormwater
Outfall and Related
Facilities
Copart Auto
Auction Expansion
Dominion
Boulevard
Virginia Department
of Transportation
Virginia Department
of Transportation
Virginia Department
of Transportation
Virginia Department
of Transportation
Virginia Department
of Transportation
Virginia Department
of Transportation
Virginia Department
of Transportation
Virginia Natural Gas
Virginia Natural Gas
Dominion Virginia
Power
Southampton Road widening to
accommodate increased
truck traffic
Southampton Bridge replacement
Southampton
Southampton
Southampton
Southampton
Suffolk
Suffolk
Suffolk
Chesapeake
City of Chesapeake Chesapeake
Copart Auto Auction Chesapeake
Virginia Department Chesapeake
of Transportation
<0.25 mile
Varies but In progress through
portions 2017 or 2018
0.5 mile north
0.9 mile Anticipated July 2016
southeast
5.1 miles of concrete
87.0 miles
TABLE A-1 (cont'd)
rehabilitation
southwest
Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project a'"
Installation of bridge to
87.0 miles
Scheduled to start
improve intersection
Closest Distance
Winter 2014/2015
Facility/State/
1.4 miles
Common
bridges
and Direction
2019 to Summer 2021
Project Name
Proponent
Counties/Cities
Description
From Project
Status
Greensville Power
Dominion Virginia
Greensville
1,600 -megawatt natural
Intersects at MP
Anticipated
Station d
Power
2021
gas -fueled power station
0.6 of AP -5;
construction mid -
for heating gas
Replacement of 20,000
encompasses
2016 and completion
feet of main and service
northwest
lines
Greensville
by 2019
Decommissioning of four
0.1 mile south
Unknown
coal-fired generating units
M&R Station
Route 633
Virginia Department
Greensville
Pavement replacement
2.2 miles
Completed August
Improvements
of Transportation
Phased construction
along 1.5 miles
southwest
2012
Atlantic Coast
Atlantic Coast
Greensville
Utility services for the
Intersects
Proposed, to coincide
Pipeline Utility
Pipeline, LLC
Greensville M&R Station
Greensville
with construction of
Services `
M&R Station
the M&R Station
Atlantic Coast
Atlantic Coast
Greensville
Microwave tower at the
Within the
Proposed, to coincide
Pipeline
Pipeline, LLC
Greensville M&R Station
Greensville
with construction of
Communications
M&R Station
ACP aboveground
Network `
facilities
Columbia Gas
Columbia Pipeline
Southampton
System improvements and
Various but
Phased construction
Pipeline Expansion
Group
pipeline expansions
some within
through 2017
General Thomas
Highway and Rose
Valley Road road
widening
Route 35 Bridge
Replacement over
Tarrara Creek
Route 58 Concrete
Rehabilitation
Route 58
Interchange
Route 671 over
Nottoway River
Route 671
Widening
Route 58/Holland
Road Improvements
Suffolk Gate 1
Heater Installation
Market Street
SAVE Project
Chesapeake Energy
Center
Decommissioning/
Fly Ash Removal
City of Chesapeake
Future Stormwater
Outfall and Related
Facilities
Copart Auto
Auction Expansion
Dominion
Boulevard
Virginia Department
of Transportation
Virginia Department
of Transportation
Virginia Department
of Transportation
Virginia Department
of Transportation
Virginia Department
of Transportation
Virginia Department
of Transportation
Virginia Department
of Transportation
Virginia Natural Gas
Virginia Natural Gas
Dominion Virginia
Power
Southampton Road widening to
accommodate increased
truck traffic
Southampton Bridge replacement
Southampton
Southampton
Southampton
Southampton
Suffolk
Suffolk
Suffolk
Chesapeake
City of Chesapeake Chesapeake
Copart Auto Auction Chesapeake
Virginia Department Chesapeake
of Transportation
<0.25 mile
Varies but In progress through
portions 2017 or 2018
0.5 mile north
0.9 mile Anticipated July 2016
southeast
5.1 miles of concrete
87.0 miles
Completed October
rehabilitation
southwest
2012
Installation of bridge to
87.0 miles
Scheduled to start
improve intersection
southwest
Winter 2014/2015
Replacement of two major
1.4 miles
Anticipated Summer
bridges
northwest
2019 to Summer 2021
Widening from two to five
1.3 miles north-
Completed September
lanes between Delaware
northwest
2013
and Shady Brooke Roads
Widening two-lane road to
0.6 mile north
Anticipated Summer
five lanes, with bike lanes
2021
Installation of water bath
Unknown
Anticipated
for heating gas
Replacement of 20,000
1.4 miles
Anticipated
feet of main and service
northwest
lines
Decommissioning of four
0.1 mile south
Unknown
coal-fired generating units
and removal of fly ash
stored at the site
Stormwater outfall
<0.25 anile
Phased construction
improvements and
starting in 2015
associated activities
Southward extension of
<0.1 mile north
Planned
auto auction yard
(opposite side of
Norfolk and
Southern
Railroad)
Widening two-lane
1.3 miles
In progress —
highway to four lanes
southeast
estimated completion
April 2017
10-A-5
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
and Repair Deck
Military Highway
36 -inch -diameter
water main
Red Top Raw
Water Transmission
Main
Virginia Natural
Gas pipeline
Battlefield
Boulevard Pressure
Improvement
WR Black and
Associates Waste
Transfer Facility
Atlantic Coast
Pipeline Utility
Services
Atlantic Coast
Pipeline
Communications
Network'
Leidy South Project
North Carolina
Atlantic Coast
Pipeline Office
Building
Atlantic Coast
Pipeline Utility
Services `
Atlantic Coast
Pipeline
Communications
Network `
U.S. 158 Widening
Project
City of Chesapeake Chesapeake Construction of water
main
City of Chesapeake Chesapeake
Virginia Natural Gas Chesapeake
Virginia Natural Gas Chesapeake
WR Black and Chesapeake
Associates
Atlantic Coast
Pipeline, LLC
Atlantic Coast
Pipeline, LLC
Chesapeake
Chesapeake
Installation of a raw water
tank and pump station, a
1 -million gallon concrete
ground storage tank, site
piping, and other site
improvements.
Approximately 5 miles of
20 -inch outside diameter
natural gas pipeline
Install new 6 -inch -
diameter pipeline
Waste water transfer
facility
Utility services for the
Elizabeth River M&R
Station
Microwave tower at the
Elizabeth River M&R
Station
Dominion
None d
TABLE A-1 (cont'd)
Transmission, Inc.
George
Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project a'"
Runs adjacent
Anticipated phased
regulation along
Closest Distance
MPs 63.9 and
Facility/State/
66.8, <0.25 mile
Common
and Direction
the M&R Station
Project Name
Proponent
Counties/Cities Description
From Project
Status
Gilmerton Bridge
Virginia Department
Chesapeake Bridge replacement
<0.1 mile north
In progress — January
Replacement
of Transportation
Compressor Station 2
2013 to Winter 2015
I-64 High Rise
Virginia Department
Chesapeake Bridge repair and deck
0.9 mile
Anticipated Fall
Bridge Waterproof
of Transportation
replacement
southeast
2015/Spring 2016
and Repair Deck
Military Highway
36 -inch -diameter
water main
Red Top Raw
Water Transmission
Main
Virginia Natural
Gas pipeline
Battlefield
Boulevard Pressure
Improvement
WR Black and
Associates Waste
Transfer Facility
Atlantic Coast
Pipeline Utility
Services
Atlantic Coast
Pipeline
Communications
Network'
Leidy South Project
North Carolina
Atlantic Coast
Pipeline Office
Building
Atlantic Coast
Pipeline Utility
Services `
Atlantic Coast
Pipeline
Communications
Network `
U.S. 158 Widening
Project
City of Chesapeake Chesapeake Construction of water
main
City of Chesapeake Chesapeake
Virginia Natural Gas Chesapeake
Virginia Natural Gas Chesapeake
WR Black and Chesapeake
Associates
Atlantic Coast
Pipeline, LLC
Atlantic Coast
Pipeline, LLC
Chesapeake
Chesapeake
Installation of a raw water
tank and pump station, a
1 -million gallon concrete
ground storage tank, site
piping, and other site
improvements.
Approximately 5 miles of
20 -inch outside diameter
natural gas pipeline
Install new 6 -inch -
diameter pipeline
Waste water transfer
facility
Utility services for the
Elizabeth River M&R
Station
Microwave tower at the
Elizabeth River M&R
Station
Dominion
None d
Expanded compression
Transmission, Inc.
George
and new metering and
Runs adjacent
Anticipated phased
regulation along
construction between
MPs 63.9 and
Dominion Transmission,
66.8, <0.25 mile
with construction of
Inc.'s existing
the M&R Station
Within the
transmission pipeline
Atlantic Coast
Northampton
A new office building for
Pipeline, LLC
pipeline operations to be
255.6 miles
Anticipated — May
built on the same site as
2016 through October
Compressor Station 2
Atlantic Coast
Northampton
Utility services for
Pipeline, LLC
Compressor Station 3 and
office building
Atlantic Coast
Northampton
Microwave tower at
Pipeline, LLC
Compressor Station 3
North Carolina Northampton, Widening of U.S. 158
Department of Cumberland from the Interstate -
Transportation 95/North Carolina 46
interchange west of
Garysburg to the
Murfreesboro Bypass
10-A-6
<0.2 mile
Construction schedule
north
unknown (may be
George
completed)
Runs adjacent
Anticipated phased
between
construction between
MPs 63.9 and
2015 and 2017
66.8, <0.25 mile
with construction of
Unknown Anticipated 2017
2.1 miles Anticipated Winter
southeast and Spring of 2015
0.1 mile
Unknown
(opposite of
with construction of
George
the compressor
Washington
station
Highway)
Proposed, to coincide
Intersects
Proposed, to coincide
Elizabeth River
with construction of
M&R Station
the M&R Station
Within the
Proposed, to coincide
Elizabeth River
with construction of
M&R Station
ACP aboveground
facilities
255.6 miles
Anticipated — May
northeast
2016 through October
2017
Entirely within
Proposed, to coincide
Compressor
with construction of
Station 2 site
the compressor
station
Intersects
Proposed, to coincide
Compressor
with construction of
Station 3
the compressor
station
Within
Proposed, to coincide
Compressor
with construction of
Station 3
ACP aboveground
facilities
Intersects near
In development
MP 8.2
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
Wilson
TABLE A-1 (cont'd)
transmission tap
Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project a'"
Transmission Line
Closest Distance
Facility/State/
Common
and Direction
Project Name
Proponent
Counties/Cities
Description
From Project
Status
Atlantic Coast
Atlantic Coast
Northampton,
Microwave towers at
Intersects at
Proposed, to coincide
Pipeline
Pipeline, LLC
Wilson,
various sites along the
proposed
with construction of
Communications
Johnston,
Atlantic Coast Pipeline
aboveground
the compressor
Network `
Sampson,
facility sites
station
Wilson —Zebulon
Dominion
Cumberland,
Line rebuild
Unknown
In progress — Spring
230 kV Line
Robeson
2014 through
Halifax Solar Power
Duke Energy
Halifax
20 -megawatt (alternating
7.4 miles
In progress
Project
Renewables
Wilson
current) solar project
northwest
In progress — Spring
Rocky Mount —
Dominion
Nash
Construction of electric
Unknown
Anticipated Fall 2014
Wilson
transmission tap
through Spring 2016
Transmission Line
— Elm City Solar
Facility
Rocky Mount —
Dominion
Nash
Construction of electric
Unknown
Anticipated Spring
Wilson
transmission tap
2016 through
Transmission Line
Summer 2017
—Davenport Tap
Wilson —Zebulon
Dominion
Wilson
Line rebuild
Unknown
In progress — Spring
230 kV Line
2014 through
Summer 2015
Aurora -Greenville
Dominion
Wilson
Line relocation
Unknown
In progress — Spring
230 kilovolt (kV)
2012 through
Line Relocation
Summer 2015
Black Creek -Wilson
Dominion
Wilson
Install new line switch
Unknown
In progress — Spring
Line Switch
2012 through
Summer 2015
T.R. Lamm
T.R. Lamm
Wilson
Planned residential
Intersects near
Unknown
Subdivision
development
MP 67.2
Elm City Solar
Duke Energy
Wilson
Expansion of existing
10.2 mile
In progress
Facility
solar facility
southeast
Greenville V.P.
Dominion
Wilson
Line rebuild
Unknown
Anticipated — Winter
Everetts 230kV
2016 through
Line
Summer 2017
Greenville —
Dominion
Wilson
Line relocation
Intersects near
In progress — Spring
Zebulon 230 kV
MP 62.5
2012 through
Line Relocation
Summer 2015
U.S. 70 Corridor
North Carolina
Johnston
Raleigh to Morehead City
Intersects near
Future, no current
Department of
major road expansion
MP 92.2
date set
Transportation
from U.S. Highway to
Interstate Highway
Complete 540
North Carolina
Johnston
Completion of Highway
Unknown
Anticipated
Department of
540 toll road
Spring 2018 to Spring
Transportation
2022
I-40 Widening —
North Carolina
Johnston
Road widening
20.4 miles
Anticipated
Southeast Raleigh
Department of
northwest
completion 2015
to Clayton Project
Transportation
(although not yet in
progress)
Lee -Selma 115 kV
Dominion
Johnston
Line relocation
Unknown
Anticipated Spring
Line
2016 through
Summer 2017
Erwin -Selma 230
Dominion
Johnston
Line replacement
0.8 mile
Anticipated Summer
kV Line
northwest
2015 through
Winter 2016
1 O -A-7
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
Atlantic Coast
Pipeline Utility
Services `
Atlantic Coast
Pipeline
Communications
Network `
Selma -Wake 230
kV Line
Piedmont Facility
Modifications
Atlantic Coast
Pipeline, LLC
Atlantic Coast
Pipeline, LLC
Dominion
the Smithfield M&R
Station
Johnston Utility services for the
Smithfield M&R Station
and office
Johnston Microwave tower at the
Smithfield M&R Station
Johnston
Piedmont Natural Gas Johnston,
Cumberland,
Robeson
Construction of line tap
Upgrades to existing
facilities
Chemtex Cellulosic
TABLE A-1 (cont'd)
Sampson
New biofuel plant facility
Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project a'"
the M&R Station
Within the
Closest Distance
Clinton -Erwin 230
Facility/State/
Common
and Direction
kV Line
Project Name
Proponent Counties/Cities Description
From Project
Status
Atlantic Coast
Atlantic Coast Johnston A new office building for
Entirely within
Proposed, to coincide
Pipeline Office
Pipeline, LLC pipeline operations to be
the Smithfield
with construction of
Building'
built on the same site as
M&R Station
the M&R station
Atlantic Coast
Pipeline Utility
Services `
Atlantic Coast
Pipeline
Communications
Network `
Selma -Wake 230
kV Line
Piedmont Facility
Modifications
Atlantic Coast
Pipeline, LLC
Atlantic Coast
Pipeline, LLC
Dominion
the Smithfield M&R
Station
Johnston Utility services for the
Smithfield M&R Station
and office
Johnston Microwave tower at the
Smithfield M&R Station
Johnston
Piedmont Natural Gas Johnston,
Cumberland,
Robeson
Construction of line tap
Upgrades to existing
facilities
Chemtex Cellulosic
Chemtex
Sampson
New biofuel plant facility
Biolfuel Plant
the M&R Station
Within the
Proposed, to coincide
Clinton -Erwin 230
Dominion
Sampson
Line replacement
kV Line
facilities
Unknown
Anticipated Summer
Enviva Project
Enviva
Sampson
New wood pellet
Intersects at the
Anticipated Winter of
Smithfield,
production facilities
Erwin -Fayetteville
Dominion
Cumberland
Relocate structures for
115 kV — Change
Unknown
North Carolina
and Relocate
In progress — Fall
Department of
Summer 2016
Unknown
Transportation project
Fayetteville Dupont
Dominion
Cumberland
Install new tap line
115 kV Line —
2013 through Spring
135.4
2015
Cumberland Solar
In progress — Winter
2014 through Spring
City
2016
Unknown
hi progress — Spring
Fayetteville Dupont
Dominion
Cumberland
histall new tap line
115 kV Line —
Anticipated — Winter
2014 through Spring
Grays Creek Tap
2016
Unknown
In progress — Winter
Fayetteville Dupont
Dominion
Cumberland
Install line switches
115 kV Line — Line
Anticipated — Winter
MP 135.1
2014 through Spring
Switches
2016
Intersects near
In progress — Summer
Fayetteville Fort
Dominion
Cumberland
Line relocation
Bragg 230 kV Line
145.8
— Clifdale Road
hi progress — Winter
2014 through
Fayetteville Fort
Dominion
Cumberland
Line relocation
Bragg 230 kV Line
— I-295 Bypass
Fayetteville Vander
Dominion
Cumberland
Install new tap line
115 kV Line — Tap
to Vander
Fort Bragg
Woodruff Street
Loop into Raeford
Dominion Cumberland Install reconductor line
1 O -A-8
hitersects
Proposed, to coincide
Smithfield
with construction of
M&R Station
the M&R Station
Within the
Proposed, to coincide
Smithfield
with construction of
M&R Station
ACP aboveground
facilities
Unknown
Anticipated Summer
2015 through Winter
2017
Intersects at the
Anticipated Winter of
Smithfield,
2016
Fayetteville, and
Pembroke M&R
Stations
Unknown
Anticipated
Unknown
In progress — Fall
2014 through
Summer 2016
Unknown
Anticipated
completion in 2017
Intersects near
In progress — Summer
MPs 131.0 and
2013 through Spring
135.4
2015
Unknown
In progress — Winter
2014 through Spring
2016
Unknown
hi progress — Spring
2014 through
Summer 2015
Unknown
Anticipated — Winter
2014 through Spring
2016
Unknown
In progress — Winter
2014 through Winter
2015
Intersects near
Anticipated — Winter
MP 135.1
2014 through Spring
2016
Intersects near
In progress — Summer
MP 144.1; runs
2014 through Spring
parallel from
2016
MPs 144.6 to
145.8
Unknown
hi progress — Winter
2014 through
Spring 2017
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
1 O -A-9
TABLE A-1 (cont'd)
Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project a'"
Closest Distance
Facility/State/
Common
and Direction
Project Name
Proponent
Counties/Cities
Description
From Project
Status
Richmond — Fort
Dominion
Cumberland
Install transmission loop
Unknown
Anticipated —
Bragg 230 kV
Summer 2015
through Winter 2018
U.S. 401 Corridor
North Carolina
Cumberland
Road expansion study
Unknown
Anticipated
Study
Department of
environmental impact
Transportation
statement date 2015
Atlantic Coast
Atlantic Coast
Cumberland
Utility services for the
Intersects
Proposed, to coincide
Pipeline Utility
Pipeline, LLC
Fayetteville M&R Station
Fayetteville
with construction of
Services `
M&R Station
the M&R Station
Atlantic Coast
Atlantic Coast
Cumberland
Microwave tower at the
Within the
Proposed, to coincide
Pipeline
Pipeline, LLC
Fayetteville M&R Station
Fayetteville
with construction of
Communications
M&R Station
ACP aboveground
Network `
facilities
Piedmont
Piedmont Natural Gas
Cumberland,
Modifications to existing
Varies
Anticipated Winter of
Aboveground
Robeson
aboveground facilities
2018
Facilities
Piedmont Pipeline `
Piedmont Natural Gas
Robeson
26 miles of 20 -inch
Intersects at MP
Anticipated Winter of
natural gas pipeline
181.8
2018
St. Pauls Johnson
Johnson Brothers
Robeson
New asphalt plant
2.2 miles
In progress — Phase I
Brothers Facility
Utility and Paving
southeast
completed July 2014
Company
I-95 Diverging
North Carolina
Robeson
Intersection improvement
9.2 miles south-
In progress —
Diamond
Department of
project
southeast
anticipated
Interchange in
Transportation
completion Spring
Lumberton
2015
Weatherspoon —
Dominion
Robeson
Convert to remote control
Unknown
In progress — Spring
LOF 115 kV
2014 through Fall
2015
Weatherspoon Plant
Dominion
Robeson
Install tap for solar facility
Unknown
Anticipated — Spring
— Delco Bladen
2015 through Winter
Solar Farm Tap
2016
Weatherspoon Plant
Dominion
Robeson
Replace structures
Unknown
Anticipated — Spring
— Delco Replace
2015 through
Solar Tap
Summer 2016
Weatherspoon Plant
Dominion
Robeson
Install tap for solar facility
Unknown
Anticipated — Winter
— Fayetteville Solar
2014 through
Farm Tap
Summer 2016
Weatherspoon Plant
Dominion
Robeson
histall tap for solar facility
Unknown
In progress — Fall
— Fayetteville Solar
2014 through Spring
Tap
2016
Weatherspoon Plant
Dominion
Robeson
Line replacement
Unknown
Anticipated — Winter
— Latta Replace and
2016 through
Pole Transmission
Summer 2017
Weatherspoon Plant
Dominion
Robeson
Replace existing
Unknown
Anticipated — Winter
— LOF 115 kV
structures
2016 through Spring
Structure Replace
2017
Weatherspoon Plant
Dominion
Robeson
Replace existing
Unknown
Anticipated — Winter
—Marion 115 kV
structures
2015 through
Structure Replace
Summer 2016
Weatherspoon-
Dominion
Robeson
Line relocation
Unknown
Anticipated —
Raeford 115 kV
Summer 2016
Line Relocate
through Winter 2018
Weatherspoon-
Dominion
Robeson
Line replacement
Unknown
Anticipated—
Raeford 115 kV
Summer 2015
Line Replacement
through Summer
2017
1 O -A-9
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
TABLE A-1 (cont'd)
Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project a'"
Closest Distance
Facility/State/
Common
and Direction
Project Name
Proponent
Counties/Cities
Description
From Project
Status
Atlantic Coast
Atlantic Coast
Robeson
Utility services for the
Intersects
Proposed, to coincide
Pipeline Utility
Pipeline, LLC
Pembroke M&R Station
Pembroke M&R
with construction of
Services `
Station
the M&R Station
Atlantic Coast
Atlantic Coast
Robeson
Microwave tower at the
Within the
Proposed, to coincide
Pipeline
Pipeline, LLC
Pembroke M&R Station
Pembroke M&R
with construction of
Communications
Station
ACP aboveground
Network `
facilities
SUPPLY HEADER PROJECT
Pennsylvania
Jeannette to Amos
Pennsylvania
Westmoreland
Road expansion project
6.7 miles
hi progress — Winter
K. Bypass
Department of
northeast
2012 through Winter
Transportation
2014
PA 66 Beaver Run
Pennsylvania
Westmoreland
Road resurfacing and
5.3 miles
In progress — Spring
to 356
Department of
widening
northeast
2014 through
Transportation
Summer 2014
Texas Eastern
Texas Eastern
Westmoreland
FERC jurisdictional
3.5 miles
Construction in
Appalachia Market
Transmission, LP
natural gas pipeline and
northeast
progress, originally
2014 Project
associated facilities in
anticipated to be in
Pennsylvania, West
service in late 2014
Virginia, Ohio, Kentucky,
Tennessee, Alabama, and
Mississippi; includes
upgrades to Delmont
Station in Westmoreland
County
Natrium to Market
Dominion
Greene,
FERC jurisdictional
Shared facilities
Construction
Project
Transmission, Inc.
Westmoreland
natural gas facilities in
include the
completed in 2014
Pennsylvania
Crayne
Compressor
Station in
Greene County
and the JB
Tonkin
Compressor
Station in
Westmoreland
County
Leidy South Project
Dominion
None d
Expanded compression
96.5 miles
Anticipated — May
Transmission, Inc.
and new metering and
2016 through October
regulation along
2017
Dominion Transmission,
hic.'s existing
transmission pipeline
Leidy Southeast
Transcontinental Gas
None d
Construction of
227.2 miles
In progress — May
Expansion Project
Pipe Line
approximately 30 miles of
through December
Company, LLC
pipeline looping and
2015
modification of existing
pipeline facilities
West Virginia
Buckhannon — Glen
Trans -Allegheny
Harrison
New 138 kV transmission
5.0 miles east
Anticipated
Falls 138kV
Interstate Line
line from West Milford
completion December
Transmission
Company (TrAILCo),
Substation to existing
2015
Project
a FirstEnergy
Buckhannon to Glen Falls
Company
138 KV transmission line
11[o ' �,
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
TABLE A-1 (cont'd)
Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project a'"
Closest Distance
Facility/State/
Common
and Direction
Project Name
Proponent
Counties/Cities
Description
From Project
Status
Oak Mound —
Trans -Allegheny
Harrison,
An 18 -mile -long 138 kV
Intersects at
Anticipated
Waldo Run 138 kV
Interstate Line
Doddridge
transmission line from the
MP 11.8
completion in
Transmission
Company (TrAILCo),
existing Oak Mound
December 2015
Project
a FirstEnergy
Substation, located in the
company
Clark District of Harrison
County and the Waldo
Run Substation
Mountain Valley
EQT Midstream
Harrison,
FERC jurisdictional
Intersects near
FERC pre -filing in
Pipeline Project
Partners, LP
Doddridge,
natural gas pipeline
MP 0.7
progress — pipeline
Wetzel, Tyler,
system spanning 300
construction
miles from northwestern
anticipated to begin in
West Virginia to southern
December 2016
Virginia
Rover Pipeline
Rover Pipeline LLC
Doddridge,
FERC jurisdictional
Adjacent to
FERC pre -filing in
Project
Tyler
natural gas pipeline
Supply Header
process - pipeline
system spanning
Project between
construction
711 miles from
MPs 11.7 to
anticipated to begin in
northwestern West
11.9
January 2016,
Virginia to central
anticipated in-service
Michigan
date of June 2017
Monroe to Cornwell
Dominion
Doddridge,
FERC jurisdictional
Shared facility —
Anticipated
Project
Transmission, Inc.
Wetzel
natural gas facilities in
Mockingbird
West Virginia.
Hill Compressor
Station; DTI
proposes to
construct
additional gas
coolers at this
station
Hundred Littleton
Wetzel County
Wetzel
Extension of water service
13.0 miles
Anticipated
Public Service
Commission
to areas in the Hundred
northeast
District Extension
Littleton Public Service
District that currently rely
on private wells and
cisterns
Pine Grove Sewage
Town of Pine Grove
Wetzel
Improvements to the
1.2 miles north-
Anticipated
Collector Project
Town of Pine Grove
northwest
sewage collection system
Hastings
Dominion
Wetzel
Replace existing gathering
1.0 mile west of
Proposed, to coincide
Compressor Station
Transmission, Inc.
compressor units
Mockingbird
with construction at
Hill Compressor
Mockingbird Hill
Station
Clarington Project
Dominion
Marshall
FERC jurisdictional
Shared facility —
Anticipated
Transmission, Inc.
natural gas facilities in
Burch Ridge
West Virginia and Ohio;
Compressor
in West Virginia, the
Station
Project involves the
installation of a new 6,130
horsepower gas
turbine/compressor
package at Burch Ridge
Compressor Station
10-A-11
Cumulative Impacts Assessment for the
Atlantic Coast Pipeline and Supply Header Project
TABLE A-1 (cont'd)
Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project a, n
Closest Distance
Facility/State/ Common and Direction
Project Name Proponent Counties/Cities Description From Project Status
a Because the majority of potential project impacts will occur during the construction phase, the past projects included in Table A-1
primarily comprise recently completed projects (completed in 2014 or later). Projects completed prior to 2014 are considered part of
the environmental baseline and are removed from further consideration unless operational impacts would affect the same resources as
the Atlantic Coast Pipeline or Supply Header Project.
b This table lists those projects that are most likely to contribute to the cumulative impacts within the vicinity of the proposed Atlantic
Coast Pipeline and Supply Header Project; it is not intended to provide an all-inclusive listing of projects in the region.
This is a nonjurisdictional facility associated with the Atlantic Coast Pipeline or Supply Header Project.
d This project has no facilities located in a common County or City with either the Atlantic Coast Pipeline or Supply Header Project.
These projects are included in Table A-1 in response to an agency request.
10-A-12