HomeMy WebLinkAboutNC0065684_Corrected A to C_20170421April 21, 2017
Mr. Shannon V. Becker
President & CEO Aqua North Carolina, Inc.
202 MacKenan Court
Cary, North Carolina 27511
Dear Mr. Becker:
ROY COOPER
coretnoi
MICHAEL S. REGAN
Se, r e(ar7
S. JAY ZIMMERMAN
aireero,
SUBJECT: Authorization to Construct
A to C No. 065684A03 CORRECTED
Aqua North Carolina, Inc.
Country Woods WWTP
A request to modify the original Authorization to Construct permit approved design issued
August 31, 2016 was received March 30, 2017 from your representative. The Division of Water
Resources (Division) has reviewed the final plans and specifications for the subject pump
modification and found it to be satisfactory. Authorization is hereby granted for the construction
of modifications to the existing 0.48 MGD Country Woods WWTP, with discharge of treated
wastewater into Goose Creek in the Yadkin -Pee Dee River Basin. This CORRECTED permit
replaces the previous permit issued August 31, 2106. The attached Engineer's Certificate form was
amended accordingly and replaces the previous issued certificate form.
This authorization results in no increase in design or permitted capacity and is awarded for
the construction of the following specific modifications:
One (1) mechanical bar screen and grit removal system rated for 0.48 MGD average
flow; a screening lift station with dual 250 GPM pumps; the repurposing of two (2)
aeration basins at the lower plant into two (2) cross -connected 60,000 gallon flow
equalization basins with four (4) 269 GPM at 53 ft TDH transfer pumps (two
pumps per basin), piping, and controls; in conformity with the project plans,
specifications, and other supporting data subsequently filed and approved by the
Department of Environmental Quality.
This Authorization to Construct is issued in accordance with Part III, Paragraph A of
NPDES Permit No. NCO065684 to be issued effective October 1, 2016, and shall be subject to
revocation unless the wastewater treatment facilities are constructed in accordance with the
conditions and limitations specified in Permit No. NC0065684.
The sludge generated from these treatment facilities must be disposed of in accordance
with G.S. 143-215.1 and in a manner approved by the Division.
State of North Carolina I Environmental Quality 1 Water Resources
512 N. Salisbury Street ( 1612 Mail service Center ( Raleigh, North Carolina 27699-1612
Phone: 919 807 6464
Mr. Shannon V. Becker, President & CEO Aqua North Carolina, Inc.
April 21, 2017
Page 2 of 3
In the event that the facilities fail to perform satisfactorily, including the creation of
nuisance conditions, the Permittee shall take immediate corrective action, including those as may
be required by the Division, such as the construction of additional or replacement wastewater
treatment or disposal facilities.
The Mooresville Regional Office, telephone number 704-663-1699, shall be notified at
least forty-eight (48) hours in advance of operation of the installed facilities so that an on site
inspection can be made. Such notification to the regional supervisor shall be made during the
normal office hours from 8:00 a.m. until 5:00 p.m. on Monday through Friday, excluding State
Holidays.
Upon completion of construction and prior to operation of this permitted facility, a
certification must be received from a professional engineer certifying that the permitted facility
has been installed in accordance with the NPDES Permit, this Authorization to Construct and the
approved plans and specifications. Mail the Certification to: Division of Water Resources, WQ
Permitting Section — NPDES, 1617 Mail Service Center, Raleigh, NC 27699-1617.
Upon classification of the facility by the Certification Commission, the Permittee shall
employ a certified wastewater treatment plant operator to be in responsible charge (ORC) of the
wastewater treatment facilities. The operator must hold a certificate of the type and grade at least
equivalent to or greater than the classification assigned to the wastewater treatment facilities by
the Certification Commission.
The Permittee must also employ a certified back-up operator of the appropriate type and
grade to comply with the conditions of T15A:8G.0202. The ORC of the facility must visit each
Class I facility at least weekly and each Class II, III and IV facility at least daily, excluding
weekends and holidays, must properly manage the facility, must document daily operation and
maintenance of the facility, and must comply with all other conditions of T15A:8G.0202.
A copy of the approved plans and specifications shall be maintained on file by the Permittee
for the life of the facility.
During the construction of the proposed additions/modifications, the permittee shall continue to
properly maintain and operate the existing wastewater treatment facilities at all times, and in such
a manner, as necessary to comply with the effluent limits specified in the NPDES Permit.
You are reminded that it is mandatory for the project to be constructed in accordance with
the North Carolina Sedimentation Pollution Control Act, and when applicable, the North Carolina
Dam Safety Act. In addition, the specifications must clearly state what the contractor's
responsibilities shall be in complying with these Acts.
Prior to entering into any contract(s) for construction, the recipient must have obtained all
applicable permits from the State.
Mr. Shannon V. Becker, President & CEO Aqua North Carolina, Inc.
April 21, 2017
Page 3 of 3
Failure to abide by the requirements contained in this Authorization to Construct may
subject the Permittee to an enforcement action by the Division in accordance with North Carolina
General Statute 143-215.6A to 143-215.6C.
The issuance of this Authorization to Construct does not preclude the Permittee from
complying with any and all statutes, rules, regulations, or ordinances which may be imposed by
other government agencies (local, state, and federal) which have jurisdiction.
If you have any questions or need additional information, please contact Ron Berry at
telephone number (919) 807-6396.
Sincerely,
PCW &-�
Jay Zimmerman
Director, Division of Water Resources
With Engineer's Certificate attached:
cc: DWR Mooresville Regional Office, Water Quality Programs
Central Files
ecopy: Scott Haberstroh, P.E.
Freese and Nichols, Inc.
Email: Scott.Haberstroh@freese.com
NPDES File
Without Engineer's Certificate attached:
cc: Union County Health Department
Aqua North Carolina, Inc.
Country Woods WWTP
Authorization to Construct No. 065684A03 CORRECTED
Issued April 21, 2017
Engineer's Certification
I, , as a duly registered Professional Engineer in
the State of North Carolina, having been authorized to observe (periodically/weekly/full time)
the construction of the modifications and improvements to the Country Woods Wastewater
Treatment Plant, located in Union County, hereby state that, to the best of my abilities, due care
and diligence was used in the observation of the following construction:
One (1) mechanical bar screen and grit removal system rated for 0.48 MGD average
flow; a screening lift station with dual 250 GPM pumps; the repurposing of two (2)
aeration basins at the lower plant into two (2) cross -connected 60,000 gallon flow
equalization basins with four (4) 269 GPM at 53 ft TDH transfer pumps (two
pumps per basin), piping, and controls; in conformity with the project plans,
specifications, and other supporting data subsequently filed and approved by the
Department of Environmental Quality
I certify that the construction of the above referenced project was`observed to be built within
substantial compliance, intent and in conformity with all applicable regulations and statutes and
the project plans, specifications, and other supporting documentation comprising the
Authorization to Construct Permit Application package.
Signature
Date
Registration No.
Mail this Certification to: Attn: Ron Berry
Complex Permitting Unit
DEQ/DWR/Water Quality Programs
1617 Mail Service Center
Raleigh, NC 27699-1617
SEAL