HomeMy WebLinkAbout20150342 Ver 2_More Info Received - Email_20170404Homewood, Sue
From: Ashley Steele <asteele@smeinc.com>
Sent: Tuesday, April 04, 2017 9:51 AM
To: Homewood, Sue
Cc: Walter Cole; wbarber@allied-engsurv.com
Subject: RE: Smith Crossing revision
Attachments: Page 5 Smith Crossing Permit.pdf, CREEK CROSSING LENGTHS.PDF
Sue, that was my mistake. I was trying to get this back to you quickly and mistakenly typed the wrong numbers. This should be
correct. Again, my apologies. I have also attached a sketch of the crossing lengths from Wayne to help clear up any confusion.
Ashley
From: Homewood, Sue[mailto:sue.homewood@ncdenr.gov]
Sent: Tuesday, April 04, 2017 9:38 AM
To: Ashley Steele <asteele@smeinc.com>
Cc: Walter Cole <WCole@smeinc.com>; wbarber@allied-engsurv.com
Subject: RE: Smith Crossing revision
Walter,
On the phone a few minutes ago you said the relocation was somewhere around 50 feet (I think). I'm confused as to how you
came up with 117 feet?
Thanks,
Sue Homewood
Division of Water Resources, Winston Salem Regional Office
Department of Environmental Quality
336 776 9693 office
336 813 1863 mobile
Sue. Homewood@ncdenr.gov
450 W. Hanes Mill Rd, Suite 300
Winston Salem NC 27105
"Nothjng Compares.,
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Ashley Steele [mailto:asteele@smeinc.com]
Sent: Tuesday, April 04, 2017 9:28 AM
To: Homewood, Sue <sue.homewood@ncdenr.gov>
Cc: Walter Cole <WCole@smeinc.com>; wbarber@allied-engsurv.com
Subject: Smith Crossing revision
Sue,
Please see the attached word document for the revised table on page 5 for the Smith Crossing Stream Crossing permit per your
request to Wayne Barber and Walter Cole yesterday evening. Let me know if you have any questions or if you need anything else.
C. Proposed Impacts Inventory
1. Impacts Summary
la. Which sections were completed below for your project (check all that apply):
❑ Wetlands ® Streams - tributaries ® Buffers
❑ Open Waters ❑ Pond Construction
2. Wetland Impacts
If there are wetland impacts proposed on the site, then complete this question for each wetland area impacted.
2a.
2b.
2c.
2d.
2e.
2f.
Wetland impact
Type of jurisdiction
number —
Type of impact
Type of wetland
Forested
(Corps - 404, 10
Area of impact
Permanent (P) or
(if known)
DWQ — non -404, other)
(acres)
Temporary T
W1 ❑ P ❑ T
❑ Yes
❑ Corps
❑ No
❑ DWQ
W2 ❑ P ❑ T
❑ Yes
❑ Corps
❑ No
❑ DWQ
W3 ❑ P ❑ T
❑ Yes
❑ Corps
❑ No
❑ DWQ
W4 ❑ P ❑ T
❑ Yes
❑ Corps
❑ No
❑ DWQ
W5 ❑ P ❑ T
❑ Yes
❑ Corps
❑ No
❑ DWQ
W6 ❑ P ❑ T
❑ Yes
❑ Corps
❑ No
❑ DWQ
2g. Total wetland impacts
2h. Comments:
3. Stream Impacts
If there are perennial or intermittent stream impacts (including temporary impacts) proposed on the site, then complete this
question for all stream sites impacted.
3a.
3b.
3c.
3d.
3e.
3f.
3g.
Stream impact
Type of impact
Stream name
Perennial
Type of jurisdiction
Average
Impact
number -
(PER) or
(Corps - 404, 10
stream
length
Permanent (P) or
intermittent
DWQ — non -404,
width
(linear
Temporary (T)
(INT)?
other)
(feet)
feet)
S1 ®P ❑ T
Culvert Installation
UT to Abbotts
Creek
❑ PER
® INT
® Corps
® DWQ
3
117
S2 ❑ P ®T
Dewatering
UT to Abbotts
Creek
❑ PER
® INT
® Corps
® DWQ
3
25
S3 ❑ P ®T
Stream Relocation
UT to Abbotts
Creek
❑ PER
® INT
® Corps
® DWQ
3
36
S4 ❑ P ® T
Riprap Outlet
UT to Abbotts
❑ PER
® Corps
3
30
Stabilization
Creek
® INT
® DWQ
S5 ❑ P ❑ T
❑ PER
❑ Corps
❑ INT
❑ DWQ
S6 ❑ P ❑ T
❑ PER
❑ Corps
❑ INT
❑ DWQ
3h. Total stream and tributary impacts
208
3i. Comments: Impacts are the result of culvert, headwall and rip rap outlet pad installation.
Page 5 of 11