HomeMy WebLinkAbout20140957 Ver 2_ACP Meeting Agenda_20170323Burdette, Jennifer a
From: Spencer Trichell (Services - 6) < Spencer.Trichell@dom.com >
Sent: Thursday, March 23, 2017 11:03 AM
To: Burdette, Jennifer a
Cc: Linda Morrison; 'TJ Mascia'; 'Tony Nardo'
Subject: ACP Meeting Agenda
Attachments: 20170328 ACP - NCDEQ Meeting Agenda.pdf
Jennifer, I have attached a suggested agenda for our meeting on the 28t". We can also discuss any other items that you
want to cover. See you next week.
Regards,
Spencer Trichell
Environmental Consultant - Atlantic Coast Pipeline
Dominion Resources Services, Inc.
0:(804)-273-3472
M.•(804)-263-5980
5000 Dominion Blvd, Glen Allen, VA 23060
spencer. trichella dom.com
CONFIDENTIALITY NOTICE: This electronic message contains information which may be legally
confidential and or privileged and does not in any case represent a firm ENERGY COMMODITY bid or offer
relating thereto which binds the sender without an additional express written confirmation to that effect. The
information is intended solely for the individual or entity named above and access by anyone else is
unauthorized. If you are not the intended recipient, any disclosure, copying, distribution, or use of the contents
of this information is prohibited and may be unlawful. If you have received this electronic transmission in error,
please reply immediately to the sender that you have received the message in error, and delete it. Thank you.
U,a n dic
ATLANTIC COAST PROJECT PipeUne
MEETING AGENDA
MEETING WITH (COMPANY/AGENCY):
NCDEQ — Coordination Meeting
DATE: I LOCATION:
ivision of Water Resources Central Office
March 28, 2017 512 N. Salisbury Street
Raleigh, NC 27604
Archdale Building - 9th floor
Meeting Agenda:
L FERC Process and Construction Schedule Updates
a. Notice of schedule
b. November 16, 2017 construction start
IL Draft Pre -Construction Notification Materials
a. Status of:
i. Biological Assessment (January 27, 2017 draft submittal)
ii. MBTA/BGEPA Plan (January 27, 2017 draft submittal)
iii. Section 106 process
iv. Conceptual compensatory mitigation plan
b. Draft PCN Supplemental review questions and comments
c. NWP Program 2017-2022 NWP 12 Conditions
d. Discuss proposed timing for submitting final materials to NCDEQ
e. District NWP 12 Verification & NCDEQ Buffer Permit/WQC decision timetable
III. Compensatory Wetland/Stream Mitigation — Conceptual Plan Discussion
a. Update on current impact evaluation and next steps
b. Determination of impact type: temporary fill vs. conversion (permanently
maintained and temporary) vs. permanent loss
c. Compensatory mitigation ratios review
d. Bank Credit Availability and Permittee Responsible Mitigation
IV. Riparian Buffer Authorization and Mitigation