HomeMy WebLinkAbout20160587 Ver 1_More Info Received_20170207v
.r
PORTER COVE CREEKW
C0
00N
O
RESTORATION PLAN
r
V N N
O � If)
N C
�ZO Q)
x Qj N C:
CO N 00 W
BILLY GRAHAM TRAINING CENTER AT THE COVE 'Z
ou)..0
�I v > Z
CLIENT Billy Graham Training Center at the Cove
Po rte r Cove Road
Asheville, NC. 28805
Contact: Douglass P. Van Wirt
Ph: 828.298.2092
CIVIL LandWorks Engineering, PLLC
ENGINEER PO Box 1922
Asheville, NC. 28802
PH: 828.230.7958
Marty Kocot, PE
GENERAL NOTES:
(APPLICABLE TO ALL SHEETS)
1. THIS WORK IS SUBJECT TO 404 PERMIT FROM THE USACE AND THE NCDWQ. THE
SITE AND WORK AREA IS SUBJECT AT ALL TIMES TO INSPECTIONS BY
REPRESENTATIVES OF THE USACE & NCDWQ, THE OWNER AND THE ENGINEER TO
VERIFY COMPLIANCE WITH THE PLANS AND PERMIT.
2. ALL WORK SHALL BE IN COMPLIANCE WITH USACE, NCDWQ, NCDENR REQUIREMENTS.
3. CONTRACTOR SHALL FURNISH ALL LABOR, MATERIALS, EQUIPMENT, SERVICES AND
SUPERVISION NECESSARY TO COMPLETE THIS PROJECT AND SPECIFICATIONS.
4. THE CONTRACTOR SHALL AT ALL TIMES MAINTAIN VEHICULAR INGRESS/EGRESS
ACCESS TO THE PROPERTY.
5. BARRICADING AND TRAFFIC CONTROL DURING CONSTRUCTION SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR AND SHALL CONFORM TO BUNCOMBE COUNTY
STANDARD SPECIFICATIONS AND DRAWINGS. THE CONTRACTOR IS RESPONSIBLE FOR
PROVIDING TRAFFIC SAFETY MEASURES FOR WORK ON PROJECT.
6. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO: A.) PREVENT ANY
DAMAGE TO PRIVATE PROPERTY AND PROPERTY OWNER'S POLES, FENCES, SHRUBS,
ETC. B.) PROTECT ALL UNDERGROUND AND OVERHEAD UTILITIES. C.) FIELD VERIFY
HORIZONTAL AND VERTICAL LOCATION OF ALL UTILITIES PRIOR TO START OF
CONSTRUCTION. NOTIFY THE ENGINEER/OWNER OF ANY POTENTIAL CONFLICTS WHICH
MAY EXIST BETWEEN THE EXISTING UTILITIES AND CONSTRUCTION PLANS.
7. THE CONSTRUCTION WORK AREAS SHALL BE KEPT CLEAN, NEAT AND ORDERLY AT ALL
TIMES. THE CONTRACTOR SHALL COORDINATE THE STORAGE OF MATERIALS AND
EQUIPMENT WITH THE OWNERS REPRESENTATIVE AND THE ENGINEER.
8. CONTRACTOR SHALL MAINTAIN SURFACE DRAINAGE AT ALL TIMES DURING CONSTRUCTION.
PONDING OF WATER IN ROADS, PARKING LOTS AND DRIVEWAYS ETC. WILL NOT BE
PERMITTED.
9. ANY DAMAGES THAT MAY OCCUR TO REAL PROPERTY OR EXISTING IMPROVEMENTS SHALL
BE RESTORED BY THE CONTRACTOR TO AT LEAST THE SAME CONDITION THAT THE REAL
PROPERTY OR EXISTING IMPROVEMENTS WERE IN PRIOR TO THE DAMAGES. THIS
RESTORATION SHALL BE SUBJECT TO THE OWNER'S APPROVAL; MOREOVER, THIS
RESTORATION SHALL NOT BE A BASIS FOR ADDITIONAL COMPENSATION TO THE
CONTRACTOR.
10. CONTRACTOR SHALL BE SOLELY RESPONSIBLE FOR ALL CONSTRUCTION MEANS, METHODS,
TECHNIQUES, AND PROCEDURES AND SHALL AT ALL TIMES TAKE ANY REASONABLE
PRECAUTIONS FOR THE SAFETY OF ITS EMPLOYEES, AND THE PUBLIC ON THE PROJECT,
AND SHALL COMPLY WITH ALL APPLICABLE PROVISIONS OF FEDERAL, STATE, MUNICIPAL
AND LOCAL SAFETY LAWS AND BUILDING CONSTRUCTION CODES.
11. CONTRACTOR IS RESPONSIBLE FOR COMPLYING WITH ALL APPLICABLE LOCAL, STATE
AND FEDERAL STORM WATER POLLUTION PREVENTION LAWS AND ORDINANCES.
BUNCOMBE COUNTY, NC
SHEET
INDEX:
PRELIMINARY
SUBMITTAL DATE:
CVR
COVER SHEET
1/30/17
CO
OVERALL PLAN/ DRAINAGE AREAS
1/30/17
C1
GRADING, EROSION CONTROL PLAN
1/30/17
C2
CREEK SECTIONS
1/30/17
C3
PLANS AND MISC DETAILS
1/30/17
D1
EROSION CONTROL DETAILS
1/30/17
Zones
W
z
o Slopes steeper
7 days
H slopes are 10' or less in
than 3:1
U
length and are not steeper
than 21, 14 days area
Z
z
allowed
o Slopes 3:1 or
0Z
7 -days for slopes greater
Major Elements of DWQ Construction General Permit August 4, 2011
This document contains the major elements of the recently—revised North Carolina
Division of Water Quality (DWQ) Construction General Permit (NCG01) with emphasis
placed on those elements that differ from the previous permit (expiration on August
2, 2011). Since the summary list below cannot contain details of every change, the
complete Permit should be used to assure full implementation. See:
http: //portal.ncdenr.org/web/wq/ws/su/construction
The major change inthe Permit from the previous one is
1) Ground Stabilization the shorter times to apply ground stabilization such as
Site Area
Stabilization
Stabilization Time
Description
Tflne Frame
Frame Exceptions
o Perimeter dices,
COUNTY:
BUNCOMBE COUNTY
swales, ditches
7 days
None
and slopes
ZONED:
CR
o High Quality
Water (HOW)
7 days
None
Zones
W
z
o Slopes steeper
7 days
H slopes are 10' or less in
than 3:1
U
length and are not steeper
than 21, 14 days area
Z
z
allowed
o Slopes 3:1 or
0Z
7 -days for slopes greater
flatter
14 days
than 50 feet in length.
None (except far
o AN other areas
perimeters and HOW Zones)
with slopes
14 days
flatter than 4.1
W
Q
11 "Extensions of time may be approved by the permitting
authority based on weather or other site-specific conditions
that make compliance impracticable" (Section N.B(2Xb))
mulch, wheat straw, or grasses. The NC laws and rules
relating to the Sediment Act require, in most places,
ground stabilization within 21 days. Based on the new EPA
requirements and 9—months' work with a permit advisory
group, CTAG, the Division and EPA—development permit,
now contains requirements for ground cover within 14, and
in some places, 7 days.
2) Building Wastes Handling
o No paint or liquid wastes in streams or storm drains
o Dedicated areas for demolition, construction and other
wastes must be located 50' from storm drains and streams
unless no reasonable alternatives available.
o Earthen-materiol stockpiles must be located 50' from storm
drains and streams unless no reasonable alternatives
a l _et� m-erla3 must De Carralleo to ovaia car x0cl w
surface waters, wetlands, or buffers.
3) Discharges to Federally4isted Waters
o Requirements are the same as in previous permit
o The permit allows reduction from the 20 acre minimum if
the Director of DWQ determines that other BMPs provide
equivalent protection.
Elements of DWQ Construction General Permit
4) Inspections
o Sane weekly inspection requirements
o Sane rain gauge & inspections after 0.5" rain event
o Inspections are only required during "normal business hours
o Inspections reports must be available on-site during
business hours unless a site specific exemption is approved.
o Records must be kept for 3 years and available upon
request.
o Electronically - available records may be substituded under
certain conditions.
5) Implementation of New Permit Conditions
o Projects permitted under the previous permit can continue
to follow the previously - permitted conditions.
o Complete applications received prior to August 3, 2011 con
follow conditions of approved application.
o Applications received after August 2, 2011 must comply with
new permit conditions
6) Conditions in Erosion & Sedimentation Control Plans
Designation an the plans where the 7 and 14 - day ground
state zation requirements of the NPOES permit apply.
Designation on the plans where basins that comply with the surface -
withdrawal requirements of hte NPDES permit are located
7) Building Wastes Handling
o No paint or liquid wastes in streams or storm drains
o Dedicated areas for demolition, construction and other wastes must be
located 50' from storm drains and streams unless no reasonable
altemotives available.
o Earthen-moterid stockpiles must be located 50' from storm drains
unless no reosonable dtematives available.
o Concrete materials must be controlled to avoid contact with surface
waters, wetlands, or buffers.
8) Sediment Basins
o Outlet structures must withdraw from basin surface unless drainage
orea is less than 1 acre.
o Use only DWO-opproved flocculants.
• In order for the E&SC Plan to satisfy the conditions of the Construction General Permit, it must identify areas where the ground stabilization
requirements apply and the location of the basins where the surface - withdrawal requirements apply.
NPDE$ Stotmwslar Discharge Permit for GonstrucAoa A1firities (yGG011
NCDENRIDiwsm of Ener9y, fAneral and Land Resources
High Quality Water (HQ" Zones I` 7 hays I None
Slopes,steeper than 3:1 7'days If slopes are 10' or less in length and are
not steeper than 2:1,14. days are allowed.:
Slopes 3:1 or flatter 1 14 days 1 T days for slopes greater than 50' in length:
All other areas wO slopes flatter than 4:1 I 14 _days I None, except for perime*rS and HOW Zones.
PORTERS COVE
RD 10 1-40w I
TO A91ENLLE
1-4OE TO
PORTERS COVE
RO POR
COVE RD
SITE
VICINITY MAP
NOT TO SCALE
TOTAL DISTURBED
AREA = 0.52 AC.
SITE INFORMATION
OWNER:
BILLY GRAHAM EVANGELISTIC
0
ASSOCIATION
CIVIL ENGINEER:
LANDWORKS ENGINEERING, PLLC
COUNTY:
BUNCOMBE COUNTY
PIN:
9677-29-8371
DEED BK/ PAGE:
1469/0177
ZONED:
CR
i
i
li 17
o
W
0
U)
C
0
0
a
o
a -
0
U
0
o
o
Z
m
N
m
U) N
_
m
-
❑X❑❑
1--
SEAL -
17644
1�•FNGINEEEL.•GD`�:
z
Z
0
U
W
m
O
U
Z
D
in
Z
0
W
0)
Y Y N
10
C12 o 0
}'Ir�Y= o
Nmi'mQU)
ZaZZLU
�L �" •• U
QUo°�U
Q W = V Unn U60) CL
O
LO
0
I
n
0
N
O
to
C
O
W
O
U
W
2
1--
Q
W
W
Z
Q
W
z
J
W
U
�C.)
W
Z
z
>
0Z
O
-�
DC
�=
W
W
Q
Z
UNN
!!nn
V
L.L
O
W�
�..
W
>
0
L
Co
U
Z
0
W
0)
Y Y N
10
C12 o 0
}'Ir�Y= o
Nmi'mQU)
ZaZZLU
�L �" •• U
QUo°�U
Q W = V Unn U60) CL
O
LO
0
I
n
0
N
O
to
C
O
TEMPORARY 24" HDPE
AND SHIFT DAM OR ADD
UTILIZED SAND PIPE EXTENSIONS AS
BAGS TO HOLD WORK PROGRESSES.
DOWN. STABILIZE /
AS NEEDED.
FLOW
CREATE TEMPORARY
PIPE FLOW SAND BAG COFFER DAM
THROUGH w/ HDPE CULVERT IN
WORK ZONE STREAM BED.
SAND BAG •
PIPE COFFER DAM
N.T.S.
j
INSTALL NEW 24"
PAVEMENT HDPE CULVERT 30'
ENDS. LONG V 1.0%
PARALLtL-T0- - CONVERT TO
_ GATE XISTING 15" CMP. LUNGE POOL.
BURY INVERTS 6"%.,r
� 1 0
PROVIDE 1' COVER OVER
24"0 PIPES. ADD CABC /
STONE TO BUILD UP 'R D (�/ INSTALL ROX
SURFACE IF NEEDED.
> \ / PLUNGE POOL /
PER DETAIL.
X. SCOUR
EX. 15" CULVERT HOLE AREA.
(DAMAGED).\,�TO BE EX. HEADWALL.
REPAI�ED_ /
Lu INTERMITTENT /,� -�
BRANCH \�EX. 15" CULVERT
(DAMAGED). TO BE
REPLACED w/ NEW 24"0
-coo HDPE CULVERT 25' LONG
Q 1.0%. BURY INVERT 6".
Lu
" EXISTING INLET _
t -SU
NEW-D1ICH TO RUN
PARALLEL -T0 ROAD
(SEE GRASS DITCH \1).
S5 WORK AREA
CULVERT REPAIR/ REPLACEMENT
SCALE: 1"=30'
70 70
f
SCALE
HORIZ: I"=2'69 69
VERT: 1"=10'
68 --- 68
67
0,6 40,1
66— 66
_ Q100 21 5.64
65 ____._65
EAVY STONE
64 t 64
(AFTER F�OTING
REPAIR),I /
63 ; �— � 063
REPAIR AREA
BELOW FOOTING 62 1 --- -- —? 62
(JUST UPSTREAM).-- 16,624,62
1
61
\-REMOVE [)EPOSITED 61
SUBSTRATE,
BOULDER. REALIGN
60 CHANNEL. ___� 60
0 10 20 30
S1 BRIDGE CULVERT SECTION
3' 4'
27 2�
GRASS LINED CHANNEL w/C125 NAG
DITCH LINING STAPLE PATTERN D.
GRASS CHANNEL D1
1.5'
GRAVEL CENTER SHOULDER
COVE RD
2400
0
2399
2398
2397
2396
2395
2394
2393
2392
2391
2390
2389
238
238
238
238
238
238,-,
238
2400
2399
2398
2397
2396
2395
2394
2393
2392
2391
2390
2389
2388
2387
2386
2385
2384
2383
2382
70 80
2400
14,239:5
8i
5
4
W
I
75, 398.5j(`�'
1.25 f j
/
1
60,2395
0
I
W
0
r
I F I
I
W
SLUFF
AREA
I
)yr' FLOW 2385.
4
a
M LUFF
SC LE
DE OSIT
e
W
=
34,2 83.5 42,2383.5
VERT: 1"=10'
i
1W --
S
i
2--- s
0 10 20
30 40 50 60
CREEK SECTION S4
REPAIR AS OUTSIDE MEANDER DETAIL
W
W
.�
°qj
0
00
00N
W
0
0
0
W
"!
F_
a
®
Q
N
000 U
00 J
W
z
C-4 01 ()
W
1W --
,J w
x�N�
U
LL 0
m •> �
C", c
w
�
(L) 00
/
®_ Z
o�
p
v
° Q>z
U
F-
0
c
�
c
w
0
z
E
L
c
I-';�k
rncl)
o
0-
®
a`
o
v
N
^^
fW
m
t�
'a
4)
ozF71
N
N
I
I
SEAL
17640
etA.►t`®®®o�`
Z
D
O
W
caM
O
Z
m
W
0
0
W
F_
i
Q
W
z
W
1W --
,J w
U
LL 0
w
z z
U)
/
®_ Z
Lj
p
�®
U
F-
0
w
0
z
I-
I-';�k
rncl)
O
t
<
N
^^
fW
m
t�
N
c
0
s
3
v
.i
'o
a
0
1
0
v
2
U
c
0
0
0
Z
0
�
U
a)
0
v
m
z o,ILO
0
=o
g
cm
®zZ'LLI�mwW
M
LLI
u
LLB
C)04
I",
000U0'(AIL
(A
w
RESHAPE
BOULDER CHANNEL
UND
O -
1 BRIDGE
I INSTALL
NSTALL
.O.,,
1'' sIL
BELOW WK
�; -
ZO,ZOVE.
S�
0
�®ACCESS FOR
�ATE
® /-REMOVAL INLET.
o�o f- REMOVE DEPOSITED
'�° \ "� SUBSTRATE/ SEDIMENT AND
`---�� ,�, \ E \ ;•—.fes-� ``\\`."\ RUBBLE FROM THIS AREA.
\\\.,
WETLAND
100 YR. STORM V PLANT ZONE
-2 YR. STORM
NORMAL FLOW
- - - - - - - - - —
FLOOD PLAIN BENCH
LIVE STAKE - - -
ZONE
J 1 FT.
EXISTING
CREEK
CHANNEL
COIR
MATTING
INSIDE MEANDER
BANK STABILIZATION
AREA S1 BRIDGE FOUNDATION UNDERMINED AND CREEK SUBSTRATE/BOULDERS
4 \\ � BLOCKING FLOW UNDER BRIDGE: N 35° 34'31.5" E -820 27'41.4n.
®� `�,v ••�. 1. Work only in (dry weather) low flow conditions.
1. Work only in (dry weather) low flow conditions.
2. Install Rock Dam below eroded area, and small inline earthen dam below work zone.
3. Temporarily dam creek above impoundment area with the installation of sand bags and
VIEW flexible HDPE pipe culvert to temporarily divert flow around work area.
4. Slowly drain impoundment area above dam to the baseline flow.
SCALE: 1 "= 5. Utiiilizing excavator remove rocks liner and soil forming the small earthen dam.
0.02 AC.. 6. Reshape, repair and stabilize creek section and eroded embankment areas below dam,
DISTURBED AREA install channel' linings, matting, live stakes, plantings and seeding as appropriate.
e
� S
UPPER AREA
INFREQUENT FLOODING
30' VEGETATIVE
GRASSY
AREAS
sit
\--EXISTING
GRADE
CONTAINER ZONE
PLANTS
(FILTER/ BUFFER)
ON FABRIC
NOT TO SCALE
AREA S3 CREEK EMBANKMENT REPAIR WITHIN FAILED OUTSIDE CREEK MEANDERS
ALONG PORTERS COVE ROAD. N 35" 34'25.7" E -820 27'41.3". (Two Places):
1. Work only in (dry weather) low flow conditions.
2. Install sand bag coffer dam, pipe culvert and sandbags along creek confining creek flow
to center of creek through immediate work zone.
3. Excavate keyway and install filter fabric and large boulders at edge of creek and
embankment toe.
4. Reshape, repair and stabilize eroded embankment areas, install channel linings,
matting, live stakes, plantings and seeding as appropriate.
Work to be performed with track hoe excavator with a bucket thumb, loader and dump
trucks to haul materials.
AREA S3 CREEK EMBANKMENT FLOOD BENCHING AND SLOPING:
N 35' 34'25.7" E -820 27'41.3".
1. On opposite bank of roadway, cut a horizontal shelf '6 inches above existing baseflow
waterline, approximately 6 feet back, then cut slope 4:1 up to existing grade. Be careful
to avoid getting soil into the creek.
2. Reshape, repair and stabilize creek section and embankments areas, install channel
linings, matting, live stakes, plantings and seeding as appropriate.
This work occurs outside of the creek flow, and it is not an impact. Care is used to keep soil
from entering creek.
nor r\rrr
STONES
OUTSIDE MEANDER
BANK STABILIZATION
AREA S4 GRAVEL ROAD BANK STABIL12ATION:
N 350 34' 06.6" E -820 2T 30.9".
1. Work only in (dry weather) low flow conditions.
2. Install sand bag coffer dam, pipe culvert and sandbags along creek confining creek flow to center
of creek through immediate work zone.
1. Excavate keyway and "install filter fabric and large boulders at edge of creek and embankment toe.
2. Reshape, repair and stabilize eroded embankment area, install channel linings, matting, live
stakes, plantings and seeding as appropriate.
Work to be performed with track hoe excavator with a bucket thumb, loader and dump trucks to haul
materials from the existinq Center Cove Road.
AREA S5 REPLACE & ADD CULVERTS:
N 35Q 34'20.6" E -820 27'38.5".
Replace a two 15" culverts with a 24" HDPE pipe culverts, add one additional 24"
culvert to this intermittent stream crossing of Center Cove Road using a track hoe.
Imbed inverts 6". Build roadbed up with cabc stone and add provide 1 ft. of cover
over all culverts.
NOT TO SCALE
TOPOGRAPHICAL
INFORMATION PROVIDED BY
THE BGTC AT THE COVE.
EE
4�A
� blow
2hdammildit
GRAPHIC SCALE
10 20 40
1 1 1
(nNFEET )
1 inch = 20 &
.Z
�
`\\
c
oU
O
a.
it Rock Dam below work zone.
W
O
2
O (D
0
r� ••v-
1VX1
3. Using a track hoe -Remove sediment and substrate deposit on inlet side of culvert where
s\
11
Qi
indicated. Enlarge pool volume and storage capacity above culvert. Stockpile substrate
TEMPORARY
®
--
and haul away sediment to dry out/waste/spread area.
rw
ACCESS ROUTE
■
V
4. Utilizing a small skid -steer and tracked mini loader access under the bridge culvert from
®
FOR COBBLE
®
the discharge end to reshape channel, and remove river rock/substrate deposited under
CLEAN OUT.
bridge - restore channel and flow to middle of culvert. Expose. Repair undercut footing
BELOW CULVERT
X aj N
0=o0
under eroded bridge foundation along edge of culvert by fomting and placing concrete in
v
�Q>z
the dry.
ROAD
SHOULDER-
EXISTING RIP
RAP AREA.
GRASS
MEADOW
After foundation is repaired reshape channel to full section with a mix of large and
medium stones.
AREA S2 EXISTING DAM REMOVAL IN CREEK (Conformation):
N 35034'27.9" E -82" 27'41.3".
1. Work only in (dry weather) low flow conditions.
2. Install Rock Dam below eroded area, and small inline earthen dam below work zone.
3. Temporarily dam creek above impoundment area with the installation of sand bags and
VIEW flexible HDPE pipe culvert to temporarily divert flow around work area.
4. Slowly drain impoundment area above dam to the baseline flow.
SCALE: 1 "= 5. Utiiilizing excavator remove rocks liner and soil forming the small earthen dam.
0.02 AC.. 6. Reshape, repair and stabilize creek section and eroded embankment areas below dam,
DISTURBED AREA install channel' linings, matting, live stakes, plantings and seeding as appropriate.
e
� S
UPPER AREA
INFREQUENT FLOODING
30' VEGETATIVE
GRASSY
AREAS
sit
\--EXISTING
GRADE
CONTAINER ZONE
PLANTS
(FILTER/ BUFFER)
ON FABRIC
NOT TO SCALE
AREA S3 CREEK EMBANKMENT REPAIR WITHIN FAILED OUTSIDE CREEK MEANDERS
ALONG PORTERS COVE ROAD. N 35" 34'25.7" E -820 27'41.3". (Two Places):
1. Work only in (dry weather) low flow conditions.
2. Install sand bag coffer dam, pipe culvert and sandbags along creek confining creek flow
to center of creek through immediate work zone.
3. Excavate keyway and install filter fabric and large boulders at edge of creek and
embankment toe.
4. Reshape, repair and stabilize eroded embankment areas, install channel linings,
matting, live stakes, plantings and seeding as appropriate.
Work to be performed with track hoe excavator with a bucket thumb, loader and dump
trucks to haul materials.
AREA S3 CREEK EMBANKMENT FLOOD BENCHING AND SLOPING:
N 35' 34'25.7" E -820 27'41.3".
1. On opposite bank of roadway, cut a horizontal shelf '6 inches above existing baseflow
waterline, approximately 6 feet back, then cut slope 4:1 up to existing grade. Be careful
to avoid getting soil into the creek.
2. Reshape, repair and stabilize creek section and embankments areas, install channel
linings, matting, live stakes, plantings and seeding as appropriate.
This work occurs outside of the creek flow, and it is not an impact. Care is used to keep soil
from entering creek.
nor r\rrr
STONES
OUTSIDE MEANDER
BANK STABILIZATION
AREA S4 GRAVEL ROAD BANK STABIL12ATION:
N 350 34' 06.6" E -820 2T 30.9".
1. Work only in (dry weather) low flow conditions.
2. Install sand bag coffer dam, pipe culvert and sandbags along creek confining creek flow to center
of creek through immediate work zone.
1. Excavate keyway and "install filter fabric and large boulders at edge of creek and embankment toe.
2. Reshape, repair and stabilize eroded embankment area, install channel linings, matting, live
stakes, plantings and seeding as appropriate.
Work to be performed with track hoe excavator with a bucket thumb, loader and dump trucks to haul
materials from the existinq Center Cove Road.
AREA S5 REPLACE & ADD CULVERTS:
N 35Q 34'20.6" E -820 27'38.5".
Replace a two 15" culverts with a 24" HDPE pipe culverts, add one additional 24"
culvert to this intermittent stream crossing of Center Cove Road using a track hoe.
Imbed inverts 6". Build roadbed up with cabc stone and add provide 1 ft. of cover
over all culverts.
NOT TO SCALE
TOPOGRAPHICAL
INFORMATION PROVIDED BY
THE BGTC AT THE COVE.
EE
4�A
� blow
2hdammildit
GRAPHIC SCALE
10 20 40
1 1 1
(nNFEET )
1 inch = 20 &
.Z
�
C
O
v
c
_U
c
oU
O
a.
` 0 O
n- U
W
O
2
O (D
0
W
1VX1
s\
11
Qi
00
N
0
o
W
rw
a
V
a)
N N
®
00C D Ln J
N�� C'
azo a)
X aj N
0=o0
m a)00w
U
v
�Q>z
v
�
C
O
v
c
_U
c
oU
O
a.
` 0 O
n- U
O
w
o
O
2
O (D
0
11
1VX1
11
11
W
O
U
W
Z
WZw J
Q
t—
J w 0
U �0
W ZZ o
>O z c)
O-�®
�<
W O= W
U)>.
O W _j g
N
DC m
N
w
W
l
U
C
v
2
U
c
O
0
0
H �
Z
0
to �
W U
GC N
O
U
m
I
N
CD
�C%j o
i-.®2 o ® a o
so P >- i;3 00Y� ® m
�0con m<
oZUJ ZUj w `— o`_
iv0
2QU _jU
QLu LU
Lu I o
®10aUO°VU) a `n c\i
/
w
N V
N
- - - - - - - - - - - - - -
NN N I,
I - - - - - - - - - - - - - - - - - - -
e V
l
y
N
- - - - - - - - - - - - - - - -
N N
-2W,- N
N.
N, N
N N, N - - - -
- - - - - - - - - -
-N�
N
-,QFo G'Ic O�o
-34
% _x IN
_71
N N N N
- - _,:� - - - - - - - - - - -
x
- 35s� -,4e - - - - - - - - 31,Q N
- - - - - - - - - - -
20 N - - - - - - - - - - -
zzoo
- 71
N
N
-Zwo,
N.
N. ft.
A,
N
Zt!
Ge
N
_1_1 --- r-7-7- Z N - - - - - -- - - - - N.
N
N
A5
M
`71 �11
N 061 .j..
N
N.
\ \ I I *ft-* / ,, /
ZIla --a,
N
ava- - - - -
s,
N
N N
N N __.Ze40_
ZZ25� - - Sel \ N
N N. N,
;,zo- -S. HYDRAULJOAL
11 N1% '. I I
0 N
N
V,
< REM079-POINT - - - - - -
i rj I v - - - --- - - \ , - " -1� ,� \�,! -,,
N
- - - - - - - - - - - -
N -zlzo- N, N,
00 " cell A
44� -3�4, \ I 1� \ \ % - - - - - - -
N, - - - - - - - - - - - N, N,
N N - - - - - - - - - - - -- - N I lt, It f
N 300 :�bw "k, -c,, -Z�,
N yL"
____ I "' \ \ __ __ 7 - _-p , , ? I , \ \ \-V, \ I - zq4&
A - - - - - - S�"4- - - I --., -, \ �, \ \ \ \ , . _ - ---
N, N_,"N' I , 3 5
I -N
N
10 % N Opz
N N
-Ts,
N.
N, N f\
N
-2uo - - - - - -
v
N N, --- 1:40m- _�' N - , -q, , , -9,, - N/ , , V!��ActQw,
A N
N N a
"N 1, , - I T , I f , / / I , " 5 CENT"TE �AbW
_N N, _N -k 'o, N
N 7�
N -2aw
N N N, 0,
-, , '\ \ " / Z 7 �. -2s-k \ -Z�, , \ 'I\ 1, -, \ _�,I/
N I N N. - - - - - - -
N Z�
-S, Ix, %', "�,, -, I - , � % \ �� \ 1, \\,\ \ - \ , a -Z�,
N
L AP 010- — / t -
- - - @ f j 1\ - -_ - , 0 N
N.
NN
N ) , j
N t F 'P E G
3�4/06
t 221
S. -
N
la,
J- A"
0 N IN A N %1, 'N N
N N
L) N Z;zr, -N
ISO N CIO
\N 'A i
_�,-'N\XN 'c'o N -Z4004 N/
/ / I - - ,, --_ -N N�%
N N
N I o
q zs,_
<
, , " � N 'l 's s
N I 1;� � ) " \ , '?
\ , 'l , I \ \ � % I\', N N. v
N
_27zz
l:q _ue-
. 0 � I � � \ , '\ I 1�1 X/
N J-- _31 -a -
N N v4 f
N N 1z Ss,�& -2r
2SII
L _zssc,, -41--�
N �,gz lae-
sc. - \I ""SQl T I
_acAo &
N
N,
:2,
A \ \
25401, �q,
N
4
_2540�
N
- - - - - -- - - - - - - - - -
'7P
%A� N
N - — - - - - -
-zazol - CQ, N
NN N 2"zo--_ N.
N
10,
z - , � \ #, I I � I �\ � \ )�
S_ j 2�, -,� - , - N. _N "IN
f "y V/
No N N I
S -- - - - - - I ____ - I
s
< --v N , \ \ \
o,
'Z5,"o
_j 16 1 1 41 N
k
___2AV_ N N
j
150-
N I LIk
�jl " "0, - I N , " -\,\ N
N 'N N No
t
\z, t4RI �4 41,
zsga, -N
DF��IhA�OE
N
U
'N 'N _0 NN\\
-�g
L _a540' -mo- - - j
gl
p l
_%1, I . ,
-1p
____N -oa 'N
f
-2220 P
7 W
_N ---- - - - - -
0
S�za_ 'Tj `6
A
N
N E
N
N
q
rx-_ , >
�? _, / � / " / '? - "' - - , , N
ADMINIS-TRA1110
-'K
-N
'A 1 T
N
N.- m i I
\N.
Q, \ �, A \ , \ \ \ IS I
Al: It N V"S- Z'
N, - -6 AR&
uj 'bGE C/13 f Z
11y;
N
N -17 4
'N,
N.
N N.
N
N
PRIMARY
-ING AREA
PAF�K
0- \%
"s j N N
HEMLOCK,- - ' % \ - - - I -
'n
CHATIQS N
WE
VOU
N
�S4 Co
N�_ N
jgHAPEE ) J` _/ I 1�;l , I 1\ - I , \ \ f " / ,
/ / REPVACEM�N
f
�EW IN N -
-no- - - - Vssa, - -1 1 1 -1 ,_ I,— _.. �
-ARE;pk f f"11,
1110. N\ � i -
t '! � " \ \ N zo-1
"TION RQ�AD OR
's 68 AC. I f 1,2��
N. N5M8ANKAAEN1F_
_n0N
07 j It/ 'P! i
rl� - 0� I - , _ I - 'R�STOF?A
N N
N POR" �E-
COV
�55,A"G,
N. I till
_VOUSE -COVE t 'IV,
tENTf_R
'IRS R0ADI(GRP>Vt1 N.
N f I
-DOaWOOD j
N 'N N,
POR N,
V_
DGE V\
ROAD <
7 K�
Nl 7 V J
- - -
- 70,
-TRAINING
7
T CEN F. p I
TER
'2TI
-AC
14
p,
AREA-
X -CREEK
MGRM,
10
'000
N 2x- "I N,�, II&I X k - / 1 6 , I \ -, \ \
,,RESTORATION.- '7
I
p.-
4 t i I
N - - - - - -
-As N., I
A,
It
Nit.
g 4?
001,
k
o- Ak�
N
N 1 2�so-
EARTHEWIDAW
A_:
�r N, -_ 4
-/RTEMOVAL
_N 0 1 / , - I
N
T
V
t -GE-
A
-oORAR4A t
N\ \11 --------
T f t
N, A I AP
-�AREAS
_e
'4"
K
2F -Qs_ "0"
A - - - - - -
PQ
20-
\,j
_y
_y
N X1
2 --N\" N_
N,� A"
N �k i F, - - / - - - -- N
4 �O'7 - ac
'10 N. ;u 2
91 ; 10
440
LIJI"
�77 352a,
- - - - - - - - - - - -
N
UZI N
Z3.s, X - - - - - -
1z
N
-a N"_
Nn �Z, N. N
-s7sO - - - - - - - - - - - - 0
-S1
2,3 - - -
co N,
V N. - - - - - I i0i A
N-
N,
N V - - - - - - -
I I ?
uk, , Z, " / �7
) 0 A
0 No,
N NO
N -
\NN. \ 1\ I - t i I x
N I - I I . %,, , , ___ - // __ -
S A
N_ - - - - - -
-- - - - - - - - - - - - - - --
- / / /I I __ 1 t ; t
- 2_120- N - - - - - -
-v 'y
-000op/
---
N N
k
N
V" - - - - - - - - - - - - - -
-N N,
X,
f
.00'
Np
%
N,
10
N No.
V
N,,
\ \ '\ \ \ N�
-N
4.1
N \ \ \ \ - \
A - -
N
N
_N,
N"/
I x"O
N
N.
----------- ------
0 N
N N'\
N
N
N
------ -----
\N
4
N-
------
N.
X - -------
z
I N� "N\ N_
'N\,
NN
----------
071]
SITE INFORMATION
OWNER:
BILLY GRAHAM EVANGELISTIC
c
Q
ASSOCIATION
CIVIL ENGINEER:
LANDWORKS ENGINEERING, PLLC
COUNTY:
BUNCOMBE COUNTY
PIN:
9677-29-8371
DEED BK/ PAGE. 1469/0177
ZONED: CR
IM12 mil IWI!
H
wvdr.ftbelavL
Call bdm m
CREEK WORK AREAS
CREEK
PROPERTY BOUNDARY
DRAINAGE AREAS
.Z�
GRAPHIC SCAIE
( IN FENT )
I inch = 400 &
I
9
qj
00
00
C)
a_
N
00 00
00
C-4 Lo
0)
Sz C14 r-
t", or) 0 (z;
x C-4
0 od
M CZJ c
00 W
0 _c
. U) .. C)
Q_ < > z
4
0
r -mom
Of = C-4
)- s-: yco CD
c
Q
0
0
a.
L_
elp
a-
.02
0
.0-
JOR
0
z
4)
:3
4)
4)
L-1
X
F-1
El
a
(X
z
0
1 /014U
.. ........
V
A.
mo%"
w
0
0
w
U) <
Z cc (0)
<
w
z ry
<
W
Z Z
z
0 z
F -
Z> Z
0
F-
U)
W W
>
o
oj
04
co
< 3:
o
r -mom
Of = C-4
)- s-: yco CD
Lu
16M c—
cm co < ca
V-- Lou 00 a m<
azzuj
he �� u
0 u
z
17-
vi Lu
Lu
LLI
Lu
660
a U (A CL
W)
0
M
cq
- 0
C)
1.11
Q)
0
0
Q)
w
2te
0
cIll
to
0
011
C)
.Q)
0
a_
ED
0
c*4
1_�
Lii