HomeMy WebLinkAbout20080301 Ver 1_Staff Comments_20080721Re: Austin Village Subject: Re: Austin Village From: Annette Lucas <Annette.Lucas@NCMail.net> Date: Mon, 21 Jul 2008 13:44:34 -0400 To: Len Rindner <len.rindner.pws@gmail.com> CC: Annette Lucas <Annette.Lucas@NCMail.net> Len, Sorry for the slow response time. You are correct that stormwater was not required by Indian Trail for this project and therefore, a stormwater management plan must be submitted to the DWQ for our review and approval. At this point, we have not received any BMP Supplement Forms or-other information regarding stormwater management for this project. Thanks, Annette Len Rindner wrote: Hi Annette: I received this letter last week. I'm pretty sure that the Stormwater Treatment Plan is not required by Indian Trail - they only required detention. The 401 WQC triggered the stormwater management plan. Wouldn't they submit the plans to you for approval? I'm currently verifying this with the civil engineer. Did they submit the plans, worksheets, etc? Len 1 of 1 7/21/2008 1:45 PM