HomeMy WebLinkAbout20140957 Ver 1_02_PCN Supplemental Information NC_CLEAN_20170222-wjh_20170227Atlantic
CoastATLANTIC COAST PIPELINE
Pipeline.
DRAFT
Nationwide Permit 12
Pre -Construction Notification — Joint Permit Application
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Environment and Natural
Resources, Division of Water Resources
Supplemental Information
Prepared by
February 2017
Atlantic Coast Pipeline
Nationwide Permit No. 12 — Pre -Construction Notification — Joint Permit Application
U.S. Army Corps of Engineers — Wilmington District
TABLE OF CONTENTS
APPLICATION SUPPLEMENTAL INFORMATION DESIGN.............................................1
INTRODUCTION..........................................................................................................................1
PROJECT OVERALL SUPPLEMENTAL INFORMATION ON PROPOSED
FACILITIES......................................................................................................................3
A. APPLICANT INFORMATION.......................................................................................5
1.
Processing: This information is included on the PCN Form.....................................5
2.
Project Information.....................................................................................................5
3.
Owner Information......................................................................................................5
4.
Applicant Information.................................................................................................5
5.
Agent/Consultant Information....................................................................................6
B. PROJECT INFORMATION AND PRIOR PROJECT HISTORY .............................6
1.
Property Identification................................................................................................6
2.
Surface Waters............................................................................................................6
3.
Project Description......................................................................................................7
4.
Jurisdictional Determinations...................................................................................27
5.
Project History..........................................................................................................28
6.
Future Project Plans..................................................................................................29
C. PROPOSED IMPACTS INVENTORY.........................................................................29
1.
Impacts Summary.....................................................................................................32
2.
Wetland Impacts.......................................................................................................32
3.
Stream Impacts..........................................................................................................32
4.
Open Water Impacts.................................................................................................32
5.
Pond or Lake Construction.......................................................................................33
6.
Buffer Impacts (for DWQ)........................................................................................33
D. IMPACT JUSTIFICATION AND MITIGATION.......................................................36
1.
a.I Avoidance and Minimization..............................................................................36
2.
a.2 NEPA Alternatives from FERC Documentation...............................................37
No Action Alternative to the ACP.........................................................................37
Alternative Energy Sources to the ACP.................................................................38
Energy Conservation to the ACP...........................................................................3
8
System Alternatives to the ACP............................................................................39
Conceptual Route Alternatives..............................................................................39
3.
b.I Construction Minimization - Wetlands...............................................................74
4.
b.2 Construction Minimization - Waterbodies..........................................................77
5.
Compensatory Mitigation for Impacts on Waters of the U.S. or Waters of the
State...........................................................................................................................81
6.
Complete if Using a Mitigation bank........................................................................83
7.
Complete if Making a Payment to In -lieu Fee Program...........................................83
8.
Complete if Using a Permittee Responsible Mitigation Plan...................................83
9.
Buffer Mitigation (State Regulated Riparian Buffer Rules) — required by DWR ....83
Atlantic Coast Pipeline i DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
E. STORMWATER MANAGEMENT AND DIFFUSE FLOW PLAN
(REQUIRED BY DWR)..................................................................................................84
1.
Diffuse Flow Plan.....................................................................................................84
2.
Stormwater Management Plan..................................................................................84
3.
Certified Local Government Stormwater Review....................................................84
4.
DWQ Stormwater Program Review.........................................................................84
5.
DWQ 401 Unit Stormwater Review.........................................................................85
F. SUPPLEMENTARY INFORMATION.........................................................................85
1.
Environmental Documentation (DWQ Requirement)..............................................85
2.
Violations (DWQ Requirement)...............................................................................85
3.
Cumulative Impacts..................................................................................................85
4.
Sewage Disposal (DWR Requirement)....................................................................90
5.
Endangered Species and Designated Critical Habitat (USACE Requirement) ........90
6.
Essential Fish Habitat (USACE Requirement).........................................................94
7.
Historic or Prehistoric Cultural Resources (USACE Requirement) .........................94
8.
Tribal Coordination...................................................................................................95
9.
Flood Zone Designation (USACE Requirement).....................................................96
G. SECTION 408 AUTHORIZATION...............................................................................96
H. REFERENCES
.................................................................................................................98
Atlantic Coast Pipeline ii DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
LIST OF JPA TABLES
Table 1
Proposed Aboveground Facilities in North Carolina for the Atlantic Coast
Johnston County Major Route Alternative for the Atlantic Coast Pipeline ....45
Pipeline............................................................................................................12
Table 2
Permit Table for the Atlantic Coast Pipeline in North Carolina ......................
28
Table 3
HUC8 Wetland Impacts Table.........................................................................30
Table 4
HUC8 Waterbody Impacts in North Carolina................................................31
Mush Island Route Variation for the Atlantic Coast Pipeline .........................58
Table 5
North Carolina Buffer Impacts........................................................................34
Table 6
Select Route Adjustments Incorporated into the Proposed Atlantic Coast
Red Oak Route Variation for the Atlantic Coast Pipeline...............................63
Pipeline in North Carolina...............................................................................72
Table 7
Route Avoidance Locations for Wetlands in North Carolina ..........................73
Swamp Road Route Variations for the Atlantic Coast Pipeline ......................70
Table 8 Federally Listed Species and Species Proposed for Federal Listing within
the U.S. Army Corps of Engineers — WilmingtonDistrict...............................92
Table 9 State -listed Endangered and Threatened Species within the U.S. Army
Corps of Engineers — Wilmington District......................................................93
LIST OF FERC ALTERNATIVE TABLES
Table 10.8.1-1
Table 10.8.1-12
Table 10.8.1-13
Table 10.8.1-14
Table 10.8.1-15
Table 10.9.1-11
Table 10.9.1-12
Table 10.9.1-13
Table 10.9.1-14
Table 10.9.1-15
Table 10.9.1-16
Table 10.9.1-17
Table 10.9.1-18
Table 10.9.1-19
Eastern and Western Route Alternatives for the Atlantic Coast Pipeline ........
41
Johnston County Major Route Alternative for the Atlantic Coast Pipeline ....45
Progress Energy Carolinas Collocation Major Route Alternative for the
Atlantic Coast Pipeline....................................................................................48
Meherrin River Major Route Alternative for the Atlantic Coast Pipeline .......
51
Northampton Major Route Alternative for the Atlantic Coast Pipeline ..........53
Geenex Route Variation for the Atlantic Coast Pipeline.................................58
Mush Island Route Variation for the Atlantic Coast Pipeline .........................58
Halifax Route Variation for the Atlantic Coast Pipeline.................................60
Breeches Swamp Route Variation for the Atlantic Coast Pipeline..................63
Red Oak Route Variation for the Atlantic Coast Pipeline...............................63
City of Nashville Route Variation for the Atlantic Coast Pipeline..................65
Little River Route Variation for the Atlantic Coast Pipeline ...........................67
Swamp Road Route Variations for the Atlantic Coast Pipeline ......................70
Cape Fear Route Variations for the Atlantic Coast Pipeline ...........................70
Atlantic Coast Pipeline iii DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
LIST OF APPENDICES
Appendix A
Figures
Appendix B
Wetland and Waterbody Survey Report
Appendix C
Wetland and Waterbody Crossing Impact Table
Appendix D
Supplemental FERC Upland Construction Information
Appendix E
Right -Of -Way Cross Section Drawings and Select Construction Typical
Drawings
Appendix F
Section 10 Waters Site Specific Plans
Appendix G
Spill Prevention, Control, and Countermeasures Plan
Appendix H
Horizontal Directional Drill Fluid Monitoring, Operations, and
Contingency Plan
Appendix I
Agency Correspondence
Appendix J
Restoration and Rehabilitation Plan
Appendix K
General, Regional, and Special Permit Conditions Tables
Appendix L
Cumulative Impacts Analysis - FERC Resource Report 1
Appendix M
Plan for Unanticipated Discovery of Historic Properties or Human
Remains during Construction
Appendix N
Correspondence with Federally Recognized Indian Tribes
Atlantic Coast Pipeline iv DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
ACRONYMS AND ABBREVIATIONS
ACP
Atlantic Coast Pipeline
APE
Area of Potential Effects
Atlantic
Atlantic Coast Pipeline, LLC
ATWS
additional temporary workspace
BA
Biological Assessment
bcf/d
billion cubic feet per day
Columbia
Columbia Gas Transmission, LLC
Commission
Federal Energy Regulatory Commission
CWA
Clean Water Act
DE
District Engineer
DOE
U.S. Department of Energy
Dominion
Dominion Resources, Inc.
DTI
Dominion Transmission, Inc.
EFH
Essential Fish Habitat
EIA
U.S. Energy Information Administration
EIS
environmental impact statement
EPA
U.S. Environmental Protection Agency
FERC
Federal Energy Regulatory Commission
FR
Federal Register
FWS
U.S. Fish and Wildlife Service
GDS-NWR
Great Dismal Swamp National Wildlife Refuge
GIS
geographic information system
HDD Plan
Horizontal Directional Drill Fluid Monitoring, Operations, and Contingency
Plan
HDD
Horizontal Directional Drill
HUC
Hydrologic Unit Code
IPaC System
Information Planning and Conservation System
M&R
metering and regulating
MBTA
Migratory Bird Treaty Act
MP
milepost
NCDEQ
North Carolina Division of Environmental Quality
NCWRC
North Carolina Wildlife Resources Commission
NEPA
National Environmental Policy Act
NOAA Fisheries
National Oceanic and Atmospheric Administration, National Marine Fisheries
Service
NOAA
National Oceanic and Atmospheric Administration
NRCS
Natural Resources Conservation Service
NWI
National Wetland Inventory
NWP
Nationwide Permit
Atlantic Coast Pipeline v DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
PASPGP-5 Pennsylvania State Programmatic General Permit 5
PCN
Pre -Construction Notification
PEM
palustrine emergent
PFO
palustrine forested
Piedmont
Piedmont Natural Gas Co.
Plan
Upland Erosion Control, Revegetation, and Maintenance Plan
PRM
permittee responsible mitigation
Procedures
Wetland & Waterbody Construction & Mitigation Procedures
Project
Atlantic Coast Pipeline
PSS
palustrine scrub -shrub
SHP
Supply Header Project
SPCC Plan
Spill Prevention, Control, and Countermeasures Plan
TNC
The Nature Conservancy
Transco
Transcontinental Gas Pipe Line Company, LLC
USACE
United States Army Corps of Engineers
USGS
United States Geological Survey
WQC
Water Quality Certification
Atlantic Coast Pipeline vi DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
APPLICATION SUPPLEMENTAL INFORMATION DESIGN
Section numbering has been incorporated into this supplemental information documents
to match the sections of the Pre -Construction Notification (PCN) form (Version 1.4 January
2009) for a joint permit application between the U.S. Army Corps of Engineers (USAGE) and
the North Carolina Division of Environment and Natural Resources, Division Water Quality
(NCDEQ) for the proposed Atlantic Coast Pipeline (ACP or Project). Atlantic Coast Pipeline,
LLC (Atlantic) is seeking a Nationwide Permit (NWP) 12 verification under Section 404 of the
Clean Water Act and Section 10 of the Rivers and Harbors Act. The USACE Wilmington
District is responsible for permitting the North Carolina portion of the ACP. From the NCDEQ,
Atlantic is seeking approval for a project -specific 401 Water Quality Certification (WQC) should
any of the single and complete projects not be covered by the State's General 401 WQC issued
for the USACE NWP 12 for North Carolina, and Riparian Buffer Authorization. The following
sections provide the necessary information to demonstrate that the ACP will comply with the
requirements for NWP 12, 401 WQC, the Riparian Buffer Authorizations, and applicable general
and regional conditions. The ACP is a Federal Energy Regulatory Commission (FERC or
Commission) 7(c) regulated project and the USACE has agreed to participate in FERC's
National Environmental Policy Act (NEPA) process as a cooperating agency.
INTRODUCTION
Atlantic is a company formed by four major U.S. energy companies—Dominion
Resources, Inc. (Dominion); Duke Energy Corporation; Piedmont Natural Gas Co., Inc.
(Piedmont); and Southern Gas Company, Inc. The company was created to develop, own, and
operate the proposed ACP, an approximately 604.6 -mile -long interstate natural gas transmission
pipeline system designed to meet growing energy needs in Virginia and North Carolina
(Appendix A, Figure 1). The ACP will be capable of delivering up to 1.5 million dekatherms per
day of natural gas that will be used to generate electricity, heat homes, and run local businesses.
By providing access to additional low-cost natural gas supplies in Virginia and North Carolina,
the ACP will facilitate cleaner air, increase the reliability and security of natural gas supplies,
and provide a significant economic boost in West Virginia, Virginia, and North Carolina. More
information is provided at the company's website at www.dom.com/acl2il2eline. Atlantic has
contracted with Dominion Transmission, Inc. (DTI), a subsidiary of Dominion, to permit, build,
and operate the ACP on behalf of Atlantic.
DTI also proposes to construct and operate approximately 37.5 miles of pipeline loop and
modify existing compression facilities in Pennsylvania and West Virginia. This project is
referred to as the Supply Header Project (SHP) and will enable DTI to provide firm
transportation service of up to 1.5 million dekatherms per day to various customers, including
Atlantic. In addition to pursuing the appropriate USACE permits in West Virginia, DTI has
applied for authorization/verification under the Pennsylvania State Programmatic General
Permit 5 (PASPGP-5) in conjunction with the Pennsylvania Department of Environmental
Protection Chapter 105 General Permit for SHP proposed impacts on waters of the U.S and for
proposed structures or work in navigable waters of the U.S. within Pennsylvania. The
PASPGP-5 is issued pursuant to Section 404(e) of the Clean Water Act (CWA) and is based
upon and consistent with the requirements of the Clean Water Act 404(b)(1) guidelines. The
USACE administers the PASPGP-5 jointly with the Pennsylvania Department of Environmental
Atlantic Coast Pipeline 1 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Protection to authorize the placement or discharge of dredged and/or fill material into waters of
the U.S under the provisions of Section 404 of the CWA and for structures or work in or
affecting navigable waters of the U.S. under the provisions of Section 10 of the Rivers and
Harbors Act of 1899.
Atlantic has prepared the following supplemental information document to accompany
the PCN form for the ACP proposed in North Carolina used by the Wilmington District for
authorization under NWP 12 and NCDEQ for permitting purposes involving water, wetlands,
and riparian buffer permitting.
Request for USACE NWP 12 for Single and Complete Projects of Waters of the U.S.
Atlantic is providing the following information as background information regarding the
ACP and the associated SHP to assist the USACE in understanding the overall undertaking being
permitted and authorized through the FERC. On September 18, 2015, Atlantic, for ACP, and
DTI, for SHP, filed respective applications with FERC to construct, operate, and maintain
natural gas pipeline facilities in Pennsylvania, West Virginia, Virginia, and North
Carolina. FERC, through the NEPA process, is assessing the potential environmental impacts
that could result from constructing and operating the ACP and SHP; two separate, but related,
interstate natural gas transmission pipeline projects. On September 15, 2015, Atlantic submitted
PCN applications for NWP 12 for ACP to the USACE Wilmington, Norfolk, Pittsburgh, and
Huntington Districts for verification of the ACP multiple single and complete projects
(crossings) of waters of the U.S. including wetlands. On September 15, 2015, DTI submitted an
application for authorization/verification for the SHP in Pennsylvania under the PASPGP-5 and
for SHP in West Virginia within Pittsburgh District Regulatory boundaries under NWP 12 for
proposed pipeline and facilities crossings of waters of the U.S. including wetlands. This
NWP 12 PCN application and supplement is only for the ACP activity (pipeline and facilities)
proposed crossings of waters of the U.S. including wetlands located in Wilmington District
within North Carolina.
In summary, for both ACP and SHP, applications for all proposed impacts on waters of
the U.S. including wetlands have been submitted for authorization under General Permits
(i.e., NWP 12 or PASPGP-5), with none of the proposed impacts on waters of the U.S. including
wetlands requiring an Individual Permit. Atlantic understands that the USACE is a cooperating
agency on the NEPA evaluation being conducted by FERC, including FERC's preparation of an
environmental impact statement (EIS), but provides the following information to the USACE to
provide context and understanding regarding the location of the multiple single and complete
crossings proposed for verification under NWP 12. The background information provided
within the application outlining the FERC process is intended to assist the USACE in
determining that verification of the single and complete projects of this linear project under
NWP 12 is appropriate and fully consistent with USACE regulations on scope of analysis and
the NWP Program. In particular, the FERC background information is intended to provide the
necessary basis for the USACE to determine that the avoidance of impacts on waters of the
United States, mitigation for unavoidable conversion of forested wetlands to scrub -shrub and/or
emergent wetlands results in no more than minimal impact, after considering compensatory
mitigation, at each single and complete project. Furthermore, the information provided below
demonstrates that the cumulative impacts on waters of the United States, after considering
Atlantic Coast Pipeline 2 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
compensatory mitigation, is minimal based on evaluating impacts within 8 -digit Hydrologic Unit
Code (HUC 8) watersheds.
Contextual information is provided in this supplement on the ACP to provide a basis for
the USACE minimal impact determinations, understanding that the USACE's scope of analysis
under NWP 12 is limited to the single and complete projects and the uplands in the immediate
vicinity of the single and complete projects that impact the location of such crossings of waters
of the United States. Approximately 14 percent of the overall ACP pipeline length of
604.6 miles crossing West Virginia, Virginia, and North Carolina is located within waters of the
United States.
Under relevant USACE precedent (including without limitation, USACE regulations,
NEPA implementation procedures, NWP Program, and Memorandum of Understanding with
FERC), the "build/no build" decision and the overall pipeline alignment is determined through
the FERC NEPA process. The USACE serves as cooperating agency on the FERC EIS through
which the USACE can coordinate with FERC to determine that the overall pipeline alignment
properly considers avoidance of impacts to waters of the United States. Moreover, the FERC
licensing process has many policies and procedures to confirm that impacts on waters of the
United States are avoided and minimized to the extent practicable. Section D provides a
summary of the extensive avoidance and minimization that has occurred for the proposed
project.
As with any linear project, waters of the United States cannot be completely avoided
because of the extensive and reticulated nature of the aquatic resource. The USACE evaluation
under NWP 12 ensures that the unavoidable impacts on waters of the United States at each single
and complete project are mitigated in order to ensure no more than minimal individual and
cumulative impacts on waters of the United States after considering the required compensatory
mitigation for unavoidable impacts. Atlantic has worked with the USACE field staff to provide
minor adjustments of the pipeline route to avoid waters of the United States with special
ecological value, or where feasible.
Atlantic has applied for a Preliminary Jurisdictional Determination from the USAGE.
See Appendix B for a copy of the Wetland and Waterbody Survey Report.
PROJECT OVERALL SUPPLEMENTAL INFORMATION ON PROPOSED
FACILITIES
Atlantic is seeking authorization from FERC to construct, own, operate, and maintain the
following proposed facilities for the ACP and from USACE for impacts on waters of the U.S. at
each single and complete project:
Mainline Pipeline Facilities:
AP -1: approximately 333.1 miles of underground 42 -inch outside diameter
natural gas transmission pipeline in Harrison, Lewis, Upshur, Randolph, and
Pocahontas Counties, West Virginia; Highland, Bath, Augusta, Nelson,
Atlantic Coast Pipeline 3 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Buckingham, Cumberland, Prince Edward, Nottoway, Dinwiddie, Brunswick, and
Greensville Counties, Virginia; and Northampton County, North Carolina.
• AP -2: approximately 186.0 miles of underground 36 -inch outside diameter
natural gas transmission pipeline in Northampton, Halifax, Nash, Wilson,
Johnston, Sampson, Cumberland, and Robeson Counties, North Carolina.
Lateral Pipeline Facilities:
• AP -3: approximately 83.2 miles of underground 20 -inch outside diameter natural
gas lateral pipeline in Northampton County, North Carolina; and Greensville and
Southampton Counties and the Cities of Suffolk and Chesapeake, Virginia.
• AP -4: approximately 0.4 mile of underground 16 -inch outside diameter natural
gas lateral pipeline in Brunswick County, Virginia.
• AP -5: approximately 1.0 mile of underground 16 -inch outside diameter natural
gas lateral pipeline in Greensville County, Virginia.
Compressor Station Facilities:
• Compressor Station 1 (Marts Compressor Station): a new, natural gas-fired
compressor station approximately at milepost 1 (MP) 7.6 of the AP -1 mainline in
Lewis County, West Virginia.
• Compressor Station 2 (Buckingham Compressor Station): a new, natural gas-fired
compressor station approximately at MP 191.5 of the AP -1 mainline in
Buckingham County, Virginia.
• Compressor Station 3 (Northampton Compressor Station): a new natural gas-fired
compressor station approximately at MP 300.1 of the AP -1 mainline and MP 0.0
of the AP -2 mainline in Northampton County, North Carolina.
Other Aboveground Facilities:
• Nine new metering and regulating (M&R) stations at receipt and/or delivery
points along the new pipelines (including one at Compressor Station 1 and one at
Compressor Station 2).
• Thirty-eight valve sites at select points along the new pipelines, at intervals
specified by U.S. Department of Transportation regulations at Title 49 Code of
Federal Regulations Part 192.
The mileposts used in the initial FERC Application, which was filed on September 18, 2015 (FERC Accession Number 20150918-5212),
were based on three-dimensional changes in topography along the proposed pipeline routes. In areas where a pipeline route has changed
due to the adoption of an alternative, the mileposts in the affected area have been scaled to account for the resulting difference in the length
of the route. For these reasons, the straight-line distance between consecutive mileposts as indicated or depicted in tables and figures in this
updated Resource Report may be greater than or less than 5,280 feet. The mileposts should be considered as reference points only.
Atlantic Coast Pipeline 4 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
• Eight sets of pig launchers and/or receiver sites at 11 points along the new
pipelines (including launcher/receiver sites at Compressor Stations 2 and 3).
A. APPLICANT INFORMATION
1. Processing: This information is included on the PCN Form.
2. Project Information
2a. Name of Project: Atlantic Coast Pipeline (ACP, Project)
2b.Counties: Northampton, Halifax, Nash, Wilson, Johnston, Sampson, Cumberland,
Robeson, see Appendix A — Figure A-2
2c. Nearest municipality/town: Not Applicable — linear project, see Appendix A —
Figures A-1, A-2, and A-3.
2d. Subdivision name: Not Applicable
2e. NCDOT only, T.I.P. or state project number: Not Applicable
3. Owner Information
3a. Name(s) on Recorded Deed: Atlantic Coast Pipeline, LLC
3b. Deed Book and Page No. N/A
3c. Responsible Party (for LLC if applicable): Leslie Hartz
3d. Street Address: 707 E Main Street, 19th Floor
3e. City, State, Zip: Richmond, VA 23219
3f. Telephone no.: (804) 771-4468
3g. Fax no.: N/A
3h. Email address: leslie.hartz@dom.com
4. Applicant Information
4a. Applicant is: Atlantic Coast Pipeline, LLC
4b. Name: Leslie Hartz
4c. Business name (if applicable):
4d. Street address: 707 E Main Street, 19th Floor
Atlantic Coast Pipeline 5 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
4e. City, State, Zip: Richmond, VA 23219
4f. Telephone no.: (804) 771-4468
4g. Fax no.: N/A
4h. Email address:leslie.hartz@dom.com
5. Agent/Consultant Information
5a. Name: Richard Gangle
5b. Business name (if applicable): Dominion Resources Services, Inc.
5c. Street address: 5000 Dominion Blvd
5d. City, State, Zip: Glen Allen, Virginia 23060
5e. Telephone no.: (804) 273-2814
5f. Fax no.: N/A
5g. Email address: ridchard.b.ganglekdom.com
B. PROJECT INFORMATION AND PRIOR PROJECT HISTORY
1. Property Identification
Ia. Property Identification: N/A
lb. Site Coordinates: Site coordinates are included on the Waterbody and Wetland
Tables, see Appendix C.
lc. Property Size: 3,023 acres, consists of the Project work area.
2. Surface Waters I
2a. Nearest Waterbody: Waterbody and Wetland location description and classification
can be found in Appendix C for Pipeline and Aboveground Facilities.
2b. Water Quality Classification of nearest receiving water: Waterbody and Wetland
location description and classification can be found in Appendix C for Pipeline and
Aboveground Facilities.
2c. River basin: Eight -digit HUC (HUC 8) watersheds have been provided in
Appendix A - Figure 2 and the Wetland and Waterbody Impact tables included in
Appendix C for Pipeline Facilities. These codes provide the information necessary to
determine the river basin within which each wetland or waterbody crossing occurs.
Atlantic Coast Pipeline 6 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
3. Project Description
3a. Existing Site Conditions and General Land Use: Land use types within the
proposed AP -2 and AP -3 Project areas were classified according to current land
characteristics. Classifications were based on review of the U.S. Geological Survey
(USGS) National Gap Analysis Program Land Cover Data and recent digital aerial
photography (2013) augmented by field reconnaissance (2014) along the proposed
pipeline routes. Atlantic identified nine primary land use types in the ACP Project area.
These consist of the following:
• Agriculture — Cultivated Crop: actively cultivated cropland (e.g., wheat, grass
seed, alfalfa, hay, and vegetables);
• Agriculture — Pasture: uncultivated pasture lands and hay meadows;
• Agriculture — Tree Plantation/Harvested Forest: managed tree plantations and
harvested forests with shrub and grass/forb regeneration;
• Upland Forest/Woodland: conifer dominated forests and woodlands, deciduous
dominated forests and woodlands, deciduous dominated savannas and glades,
floodplain/riparian forests, and mixed deciduous/coniferous forests and
woodlands;
• Developed — Open to Low Intensity: herbaceous areas (e.g., golf courses, road
sides, parks, and air fields) and areas with a mixture of constructed materials and
vegetation where impervious surfaces account for 20 to 49 percent of total cover
(e.g., single-family housing units);
• Developed — Medium to High Intensity: areas with impervious surfaces
accounting for 50 to 100 percent of total cover, including single-family housing
units, apartment complexes, row houses, and commercial/industrial areas;
• Open Land: disturbed lands, grasslands, shrub lands, beach and shore lands, and
cliff, canyon, and talus lands;
• Wetlands: wetland areas identified by field surveys or in National Wetland
Inventory (NWI) data, including palustrine and estuarine wetlands; and
• Open Water: areas of open water, generally with less than 25 percent cover of
vegetation or soil, including inland waters of streams, river, ponds, and lakes, and
coastal and near -shore estuarine and/or marine waters.
3b. Existing wetland acreage: 558 Acres within the Project Study Area.
3c. Existing linear feet of stream: 31,701 Linear Feet within the Project Study Area.
3d. Project Purpose and Need and Background Regarding FERC NEPA Process:
Atlantic Coast Pipeline 7 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
USACE NWP 12 Purpose and Need
The purpose and need for purposes of NWP 12 verification of each single and complete
project is to cross wetlands, streams and other waters while avoiding impacts on those wetlands,
streams and other waters to the maximum extent practicable and offsetting unavoidable impacts
on the aquatic environment with compensatory mitigation. Additional details on the project
purpose and need are provided below.
FERC NEPA PROJECT PURPOSE STATEMENT
The following description of the purpose and need for the FERC NEPA process is
provided as background information. Information included has been compiled largely from
documents submitted to FERC, but is provided for the convenience of the USACE review. In
Section D of the application materials, below, within the Impact Justification and Mitigation,
Avoidance and Minimization, and FERC Alternatives sections, the numbering of many of the
referenced tables and figures has not been changed from their number in the FERC
documentation, to maintain consistency across documents (e.g., Table 3.10.5-1, Figure 10.8.1-1,
etc.).
The ACP is a proposed interstate natural gas transmission pipeline that will serve the
growing energy needs of multiple public utilities and local distribution companies in Virginia
and North Carolina. The natural gas transported by the ACP will be used as a fuel to generate
electricity for industrial, commercial, and residential uses. The natural gas will also be used
directly for residential, commercial, and industrial uses. By providing access to additional low-
cost natural gas supplies, the ACP will increase the reliability and security of natural gas supplies
in Virginia and North Carolina.
In recent years, demand for natural gas in Virginia and North Carolina has grown
significantly. Demand for natural gas for all uses grew by 37 and 50 percent, respectively, in
Virginia and North Carolina between 2008 and 2012. Demand for gas-fired electric power
generation grew by 123 percent in Virginia and 459 percent in North Carolina from 2008 to 2013
(U.S. Energy Information Administration [EIA], (EIA, 2015a, 2015b, 2015c, 2015d, and 2015e).2
Demand for natural gas in Virginia and North Carolina is expected to increase in coming
decades due to a combination of population growth and displacement of coal-fired electric power
generation. The U.S. Census Bureau predicts 2.7 million new residents in Virginia and
4.2 million new residents in North Carolina between 2000 and 2030 (U.S. Census Bureau,
U.S. Energy hiformation Administration.2015a. Annual Energy Outlook 2015.Available online at hitu://www.eia.gov/forecasts/aeo/.
Accessed June 2015.
U.S. Energy Information Administration.2015b. Market Trends; Electricity Demand. Available online at htip://www.eia.gov/forecasts/aeo/
MT electric.cfm. Accessed June 2015.
U.S. Energy Information Administration.2015c. Market Trends; Natural Gas. Available online at http://www.eia.gov/forecasts/aeo/mt nat
ural ag s.cfin. Accessed June 2015.
U.S. Energy Information Administration.2015d. Natural Gas Summary for Virginia. Available online at hitp://www.eia.gov/dnav/ng/ng
sum _lsum_dcu_SVA a.htm. Accessed June 2015.
U.S. Energy Information Administration.2015e. Natural Gas Summary for North Carolina. Available online at htW://www.cia_gov/dnav/n
ng sum Isum_dcu_SNC _a.htm. Accessed June 2015.
Atlantic Coast Pipeline 8 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
2014). At the same time, use of natural gas for power generation is expected to increase
significantly. By 2035, natural gas is expected to surpass coal as the most common fuel for
electric power generation due to coal-fired plant retirements and low natural gas prices. The EIA
(2015a) expects renewable generation to grow 1.9 percent per year, meeting a part of the demand
for power, but more than 70 percent of new generating capacity will be fueled by natural gas.
A study, prepared by ICF International (2015) for Atlantic, projects that electric power
generation in Virginia and North Carolina will increasingly rely on natural gas over the next two
decades. Between 2019 and 2038, the study predicts that approximately 9,900 megawatts of
electric generating capacity from coal and nuclear fuels will be retired, while 20,200 megawatts
of new generating capacity from natural gas will be built in Virginia and North Carolina. As a
result, demand for natural gas for power generation in Virginia and North Carolina is expected to
grow 6.3 percent annually between 2014 and 2035, increasing from 1 billion cubic feet per day
(bcf/d) to 3.7 bcf/d.
To meet the growing demand for natural gas, the EIA (2015a) projects total United States
natural gas production to increase by 56 percent from 2012 to 2040. At the same time, natural
gas transmission patterns across the United States are expected to change based on the growing
production from shale basins in the mid-Atlantic region. Historically, gas produced from the
Gulf of Mexico, Canada, and the Rocky Mountains was delivered to markets in the eastern
United States. Large increases in production from United States supply basins have created
abundant, competitively priced supplies to meet the demands of the region.
A study by the U.S. Department of Energy (DOE, 2015)3, dated February 2015,
examined the impact of increased demand for natural gas from the electric power sector on
natural gas pipeline infrastructure in the United States over a 15 year period from 2015 to
2030.4 The DOE (2015) study found that a projected 38 to 42 bcf/d of new and expanded
pipeline capacity will be necessary to meet demand over the 15 year study period. The DOE
study further found that flow reversal is projected to occur "to serve markets in the Southeast."
Furthermore, existing pipelines that historically transported natural gas from the Gulf Coast
region to points further north are expected to change the direction of flow in order to "serve the
Virginia and Carolina markets" (DOE, 2015). However, there are no existing long haul
interstate pipelines with available takeaway capacity from the Appalachian region directly
serving Virginia and North Carolina (see Figure 1 in the DOE [2015] study).
Moreover, market participants in the region have determined that their needs cannot be
adequately met by existing pipeline systems. In April 2014, Duke Energy Corporation and
Piedmont issued requests for proposals for incremental pipeline transportation service due to
their existing and future natural gas generation requirements, core load growth, and system
U.S. Department of Energy. 2015. Natural Gas Infrastructure Implications of Increased Demand from the Electric Power Section.
Available on line at: htip:Henergy.gov/sites/prod/files/2015/02/fl9/DOE%2ORgport%2ONatural%2OGas%201nfrastructure°/u20V 02-02.pdf.
Accessed February 2015.
4 In comments filed with the FERC, several individuals said that demand for natural gas in Virginia and North Carolina could be met by
existing pipeline systems citing this study by the DOE. The study did not conclude, as some suggested, that no additional pipeline capacity
is needed to meet the increased demand for natural gas. Instead, the study found that the expected increase in pipeline capacity over the
study period will be modest relative to previous expansions in pipeline capacity.
Atlantic Coast Pipeline 9 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
reliability and supply diversity goals. In June 2014, Virginia Power Services Energy Corp., Inc.
issued a request for proposals for firm transportation service to serve Virginia. Following the
request for proposals processes, these companies contracted for transportation service on the
ACP, as did other companies in the region.
To meet the natural gas demand of its customers, the ACP will connect the growing
demand areas in Virginia and North Carolina with growing supplies. Interstate natural gas
pipelines act as common carriers to transport natural gas; they are not part of natural gas
exploration or production activities. The ACP will connect growing demand areas in Virginia
and North Carolina with growing supply areas in the Appalachian region and provide access to
the Dominion South Point supply hub, consisting of abundant supplies on the DTI system that
are sourced from a wide variety of upstream pipeline interconnects and diverse production areas.
More specifically, the ACP will provide up to 1.5 bcf/d of firm natural gas transportation service
into West Virginia, Virginia, and North Carolina.
The ACP will receive gas on behalf of its customers at two new interconnections: one
between the ACP and the SHP in Harrison County, West Virginia, to be known as the Marts
Junction Interconnection; and one between the ACP and existing Transcontinental Gas Pipe Line
Company, LLC (Transco) facilities in Buckingham County, Virginia, to be known as the
Buckingham Interconnects. The natural gas will be delivered to various new customer
interconnects in West Virginia, Virginia, and North Carolina. Additionally, the ACP will lease
capacity on a pipeline owned and operated by Piedmont to enable certain deliveries in North
Carolina.
Of the new firm transportation capacity of up to 1.5 bcf/d proposed by the ACP,
1,360,000 dekatherms per day (approximately 1.33 bcf/d) is currently subscribed pursuant to
precedent agreements with six customers. These customers are major utilities and local
distribution companies in the region. The precedent agreements demonstrate the need for the
Projects, the demand for new gas supplies indicated in the studies noted above, and the desire for
access to a new supply region. The remaining unsubscribed capacity would be awarded and
contracted for in accordance with Commission policies applicable to open -access interstate
pipelines and the provisions of applicable FERC gas tariffs. The natural gas supplied to each
delivery point would be provided to local distribution companies, power generators, and other
interstate pipeline companies. 'I
3e. Project Details (Project Description and Project Facilities)
Overall Project Description for ACP
The project description of the ACP for purposes of USACE NWP 12 authorization is to
construct single and complete projects on waters of the United States that result in no more than
minimal individual and cumulative impacts on the aquatic environment and offsetting
5 The ACP and SHP are separate projects with separate applicants, but are being reviewed as connected actions by FERC through
development of a single Environmental Impact Statement.
Atlantic Coast Pipeline 10 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
unavoidable impacts on the aquatic environment with compensatory mitigation. The overall
ACP project construction and operation to be authorized by FERC is a proposed 604.6 -mile -
long, interstate natural gas transmission pipeline that will serve the growing energy needs of
multiple public utilities and local distribution companies in the region. The natural gas
transported by the ACP will be used as a fuel to generate electricity for industrial, commercial,
and residential uses. The natural gas will also be used directly for residential, commercial, and
industrial uses. By providing access to additional low-cost natural gas supplies, the ACP will
increase the reliability and security of natural gas supplies in Virginia and North Carolina.
Project Details for North Carolina
A short segment of the AP -1 mainline, approximately 200 feet in length, will occur in
North Carolina. This short segment of AP -1 will not cross wetlands or waterbodies, and will not
be discussed further in the application. The AP -2 mainline, which will consist of 36 -inch outside
diameter pipeline, will originate at the southern terminus of AP -1 at Compressor Station 3 in
Northampton County, North Carolina. From this point, the pipeline will extend to the southwest
crossing through Northampton, Halifax, Nash, Wilson, and Johnston Counties, passing west of
Rocky Mount in Nash County, west of Wilson in Wilson County, and east of Selma in Johnston
County. At the Johnston/Sampson County line, the pipeline will turn west/southwest and
continue through Sampson County and southeast of Fayetteville in Cumberland County, before
terminating at a new interconnect with an existing Piedmont distribution pipeline in Robeson
County, North Carolina. Approximately 186.4 miles of the AP -2 mainline occurs within the
USACE - Wilmington District and is a part of the proposed work under NWP 12 PCN.
The AP -3 lateral, which will consist of 20 -inch outside diameter pipeline, will originate
at Compressor Station 3 in Northampton County, North Carolina and extend to the east/northeast
to the Virginia State line. AP -3 will then continue northeast through Greensville and
Southampton Counties and the Cities of Suffolk and Chesapeake, Virginia. Approximately
12.2 miles of the AP -3 lateral occurs within the USACE— Wilmington District, all within
Northampton County, North Carolina and is a part of the proposed work under NWP 12 PCN.
In addition one compressor station, three M&R stations, 11 valve sites, and four sets of
pig launchers and receivers are planned within the Wilmington District. The location of each
aboveground facility in North Carolina, by milepost and county is listed in Table 1.
Compressor Stations
Compressor Station 3 will be located approximately at MP 300.1 in Northampton
County, North Carolina at the intersection of the AP -1 and AP -2 mainlines and the AP -3 lateral.
The station will take natural gas from the AP -1 mainline and discharge into both the AP -2
mainline and the AP -3 lateral.
Atlantic Coast Pipeline 11 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
TABLE 1
Proposed Aboveground Facilities in North Carolina for the Atlantic Coast Pipeline
Aboveground Facility County/City and State Approximate Milepost
Compressor Stations
AP -1 Mainline
Compressor Station 3
Northampton County, NC
300.1
Metering and Regulating Stations
AP -2 Mainline
Smithfield M&R Station
Johnston County, NC
92,7
Fayetteville M&R Station
Cumberland County, NC
132.9
Pembroke M&R Station
Robeson County, NC
182.9
Valves
AP -2 Mainline
Valve Site 23
Northampton County, NC
9.4
Valve Site 24
Halifax County, NC
14.9
Valve Site 25
Nash County, NC
34.7
Valve Site 26
Nash County, NC
49.5
Valve Site 27
Nash County, NC
64.3
Valve Site 28
Johnston County, NC
78.7
Valve Site 29
Johnston County, NC
108.1
Valve Site 30
Cumberland County, NC
123.0
Valve Site 31
Cumberland County, NC
136.6
Valve Site 32
Cumberland County, NC
153.7
Valve Site 33
Robeson County, NC
168.6
Pig Launcher/Receiver Sites
AP -1 Mainline
Site 4 (launcher/receiver)
Northampton County, NC
300.1
AP -2 Mainline
Site 5 (launcher/receiver)
Johnston County, NC
92.7
Site 6 (receiver)
Robeson County, NC
182.9
AP -3 Lateral
Site 4 (launcher)
Northampton County, NC
0.0
Metering and Re _ ug lating Stations
Atlantic will construct three M&R stations in North Carolina at the locations identified in
Table 1. The M&R stations will be built at receipt or delivery points along the pipelines. In
general, each M&R station will contain two dekatherm buildings (used to house equipment such
as gas chromatographs, communications equipment, etc.), a regulation building, and possibly a
meter building. Equipment at each station will include gas filter/separators, gas meters, and
regulators, and may include gas heaters and/or odorization equipment. Each station will be
surrounded by a chain-link security fence.
`%A1VA C1iAC
Eleven valves will be installed along the proposed pipelines at the locations identified in
Table 1. The valves will be installed below grade with aboveground valve operators, risers,
blowdown valves, and crossover piping connected on each side of the valve. A chain-link
Atlantic Coast Pipeline 12 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
security fence will be installed around the periphery of each valve site. The valves will allow
DTI, as operator, to segment the pipelines for safety, operations, and maintenance purposes.
Launchers/Receivers
Four sets of pig launchers and/or receivers will be installed at the locations identified in
Table 1. One set of the pig launcher/receiver assemblies and one launcher will be built on the
same sites and within the same fencelines as other aboveground facilities. These include a pig
launcher/receiver assembly and a launcher assembly at Compressor Station 3, a launcher/receiver
assembly at the Smithfield M&R Station, and a pig receiver assembly at the Pembroke M&R
Stations. The pig launchers/receivers will be used to run pipeline inspection tools, called pigs,
through the pipeline system.
Right-of-Wav Configuration
The construction right-of-way width has been minimized following FERC's "Wetland &
Waterbody Construction & Mitigation Procedures" (Procedures) as prescribed for each land
type. For the AP -2 mainline, the construction corridor in non-agricultural uplands will measure
110 feet in width, with a 35 -foot -wide temporary side cast storage side and a 75 -foot -wide
working side. In areas where full width topsoil segregation is required (e.g., agricultural areas),
an additional 25 feet of temporary construction workspace will be needed on the working side of
the corridor to provide sufficient space to store topsoil. In wetlands, the width of the
construction right-of-way will be reduced to 75 feet, with 25 feet on the temporary side cast
storage side and 50 feet on the working side. Following construction, a 50 -foot -wide permanent
easement will be maintained for operation of the pipeline.
For the AP -3 pipeline lateral section in North Carolina, the construction corridor in non-
agricultural uplands and in wetlands will measure 75 feet in width, with a 25 -foot -wide
temporary side cast storage side and 50 -foot -wide working side. In areas where full width
topsoil segregation is required (e.g., agricultural areas), an additional 25 feet of temporary
construction workspace will be needed on the working side of the corridor to provide sufficient
space to store topsoil. Following construction, a 50 -foot -wide permanent easement will be
maintained for operation of each pipeline.
Atlantic will retain a 50 -foot -wide permanent right-of-way to allow operation and
maintenance of the pipeline along the AP -2 mainline. The majority of the permanent right-of-
way will be allowed to return to preconstruction uses, although permanent structures will not be
allowed within the 50 -foot -wide permanent right-of-way. Section VI. D. of the FERC's
Procedures specifically require:
"Do not conduct routine vegetation mowing or clearing over the full width of the
permanent right-of-way in wetlands. However, to facilitate periodic corrosion/leak
surveys, a corridor centered on the pipeline and up to 10 feet wide may be cleared at a
frequency necessary to maintain the 10 -foot corridor in an herbaceous state. In addition,
trees within 15 feet of the pipeline with roots that could compromise the integrity of
pipeline coating may be selectively cut and removed from the permanent right-of-way.
Atlantic Coast Pipeline 13 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Do not conduct any routine vegetation mowing or clearing in wetlands that are between
HDD entry and exit points."
Therefore, after construction within the 50 -foot -wide permanent easement, the following
maintenance will occur:
(a) Ten feet centered over pipeline — maintained in an herbaceous state to facilitate
periodic aerial inspections. These areas will be reseeded with native wetland seed
mix.
(b) Thirty feet centered over pipeline — trees with roots that could compromise the
integrity of the pipeline coating would be selectively removed. These areas will
be reseeded with native wetland seed mix to stabilize the area within wetlands.
(c) Outside 30 -foot maintenance area in palustrine emergent (PEM) and palustrine
scrub -shrub (PSS) wetlands — vegetation allowed to regrow with no restrictions -
no vegetation maintained by Atlantic. Atlantic will reseed these temporarily
disturbed wetland areas with native wetland see mix to stabilize following
construction.
(d) Outside 30 -foot -maintenance area in non -inundated deciduous hardwood
palustrine forested (PFO) wetlands —Atlantic will replant deciduous hardwood
wetlands as part of the minimization of impacts and compensatory mitigation
plan. Where wetlands are inundated much of the growing season, Atlantic would
not replant these wetlands due to the high likelihood of sapling mortality.
NWP 12 Regional Condition 4.1.3 (January 9, 2017 Wilmington District Public Notice
for NWP Program 2017-2022 Regional Conditions) for work in North Carolina states: "The
work area authorized by this permit, including temporary and/or permanent fills, will be
minimized to the greatest extent practicable. Justification for work corridors exceeding forty
(40) feet in width is required and will be based on pipeline diameter and length, size of
equipment required to construct the utility line, and other construction information deemed
necessary to support the request. The permittee is required to provide this information to the
USACE with the initial notification package." Construction of the ACP will require additional
workspace beyond 40 feet in wetland areas. Justification for the additional workspace is as
follows: AP -2 in North Carolina will be 36 -inch diameter pipe, which requires large construction
equipment to install. The construction space in wetlands consists of a trench necessary to
accommodate the pipe at an appropriate depth (3-5 feet beneath the surface), adjacent space to
place excavated material from the trench excavation, and travel of equipment alongside the
trench for pipe installation. Soils in wetlands areas are generally less stable than those in
adjacent upland areas, therefore additional shoring is necessary to achieve the appropriate trench
depth resulting in a trench that is wider than in adjacent upland areas. In addition, the extra
material that is excavated requires more space for temporary side -casting and the instability of
the soil requires that the travel corridor adjacent to the trench be at a safe distance so that failure
of the trench walls does not occur.
The FERC's Procedures specify a maximum right-of-way width of 75 feet in wetlands,
unless prior written approval is obtained. Atlantic has reduced workspace from 110 feet to
Atlantic Coast Pipeline 14 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
75 feet in wetlands and is not requesting a variance from this right-of-way limitation. Further
consideration was made regarding a reduction in workspace in wetlands to meet the 40 feet
recommended by Wilmington District NWP Regional and NCDEQ General WQC Conditions in
North Carolina, but for reasons outlined above, Atlantic has determined that the full 75 feet,
allowed by the FERC, will be necessary to safely install the ACP.
The NCDEQ Division of Water Resources has advised that they have the ability to waive
the 40 -foot construction corridor restriction limitation associated with the General WQC
authorization for NWP 12. Atlantic is specifically requesting NCDEQ to waive WQC General
Condition 11 and Activity Specific Condition 5 for WQC No. 3884 (WQC number referenced
was issued for current 2012-2017 NWP Program so requesting same for 2017-2022 NWP
Program General WQC when issued), which state:
General WQC General Condition 11) Work in the Dry
All work in or adjacent to stream waters shall be conducted so that the flowing stream
does not come in contact with the disturbed area. Approved best management practices from the
most current version of the NC Sediment and Erosion Control Manual, or the NC DOT
Construction and Maintenance Activities Manual, such as sandbags, rock berms, cofferdams,
and other diversion structures shall be used to minimize excavation in flowing water. Exceptions
to this condition require application to and written approval from DWR.
Atlantic is requesting a waiver for General Condition 11 due to the fact that several
stream crossings are too large to feasibly work in the dry, but are not suitable for horizontal
directional drill (HDD). The smaller stream crossings will be accomplished by working in the
dry via flume, dam -and -pump, and cofferdam construction methods, as previously described.
Along the Project in North Carolina, wetland-waterbody complexes occur that require
special crossing techniques. These complexes consist of broad inundated wetlands with a
waterbody channel located within the extents of the wetlands. The water is generally not
contained within the channel of the waterbody, thus resulting in a continuum of water that
extends from the channel to the upland extend of the wetlands edge. The crossing of these
complexes cannot be accomplished utilizing a waterbody crossing technique, thus a combination
of wetland/waterbody technique is required. The crossing cannot be accomplished "in the dry"
due to the difficulty in removing water from within the wetland. The channel crossing in these
complexes would be similar to the open cut method described in this section and the wetlands
crossing would be accomplished using the push-pull wetlands crossings method described in
Wetland and Waterbody Construction Procedures section below.
The volume of water at the larger stream crossings is too great to safely and temporarily
divert the flow around the work area. Rocky Swamp and Cypress Creek are proposed to be open
cut (i.e., wet crossings). As part of Atlantic's effort to avoid and minimize impacts on waters of
the United States and associated sensitive resources, crossings of seven large waterbodies are
proposed as HDD crossings (Roanoke River, Fishing Creek, Swift Creek, Tar River, Contentnea
Creek, Little River, and Cape Fear River) due to the resources present at these crossings; see
response to 5) below.
Atlantic Coast Pipeline 15 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
General WQC Activity Specific Condition 5) 50 foot Construction Corridor
Construction corridors in wetlands and across stream channels shall be minimized to the
maximum extent practicable and shall not exceed 50 feet wide for gas utility lines and 40 feet
wide for all other utility lines. Exceptions to this condition require application to and written
approval from DWR.
Atlantic is requesting the waiver for Activity Specific Condition 5 due to the fact that a
50 foot work area through wetlands and across stream channels is not wide enough to safely
install a 36 -inch pipe. Construction of the ACP will require additional workspace beyond 50 feet
in wetland areas. Justification for the additional workspace is as follows: AP -2 in North Carolina
will be 36 -inch diameter pipe, which requires large construction equipment to install. The
construction space in wetlands consists of a trench necessary to accommodate the pipe at an
appropriate depth (3-5 feet beneath the surface), adjacent space to place excavated material from
the trench excavation, and travel of equipment alongside the trench for pipe installation. Soils in
wetlands areas are generally less stable than adjacent upland areas, therefore additional shoring is
necessary to achieve the appropriate trench depth resulting in a trench that is wider than in
adjacent upland areas. In addition, the extra material that is excavated requires more space for
temporary side -casting and the instability of the soil requires that the travel corridor adjacent to
the trench be at a safe distance so that failure of the trench walls does not occur.
In addition to the construction right-of-way, additional temporary workspace (ATWS)
will be required at various locations along the construction right-of-way, such as at the beginning
of each construction spread for mobilization of construction equipment; for stringing -truck
turnaround areas; where the pipeline crosses under buried features (e.g., foreign pipelines, utility
lines); at road crossings, railroads, wetlands, waterbodies; residential areas, and at HDD
crossings.
ATWS also will be required in areas with side slopes to create a level and safe work
surface across the width of the right-of-way for equipment operation. For the AP -2 mainline,
ATWS measuring 25 by 100 feet will typically be required on both sides of the corridor and both
sides of the crossing at wetlands, waterbodies, roads, and railroads. The FERC's Procedures
require that ATWS be set back at least 50 feet from the wetland boundaries and the water's edge
of waterbodies, except where the adjacent lands consist of croplands or other disturbed areas.
Following construction of the pipelines, ATWS will be restored to pre-existing conditions and
uses.
Atlantic has identified roads which will be used to provide access to the Project
construction rights-of-way, permanent easement, and other facilities during construction and
operation of the ACP. Atlantic will utilize existing roads to the extent practicable, but some new
roads may need to be built in remote areas. Additionally, new roads will need to be built to
provide access to aboveground facility sites (i.e., compressor and M&R stations, valves, and pig
launcher/receiver assemblies) during operations. In some cases, existing roads will require
improvement (such as grading, gravelling, replacing or installing culverts, minor widening,
and/or clearing of overhead vegetation) to safely accommodate construction equipment and
vehicles. A sufficient number of roads with regular spacing is needed to minimize congestion of
construction vehicles and equipment on the right-of-way; having fewer access roads would
Atlantic Coast Pipeline 16 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
increase the duration of construction and create unsafe work conditions for workers. If any
existing roads are damaged during construction, Atlantic will restore these roads to
preconstruction condition or better. See Appendix C for access road impacts.
General Construction Procedures
Refer to Appendix D for a discussion on general construction procedures.
Waterbody and Wetland Construction Procedures
Atlantic will use special construction techniques where warranted by site-specific
conditions, e.g., when constructing across waterbodies, and wetlands. Each of these specialized
measures is described below. Illustrations of select crossing methods are provided in
Appendix E and site-specific plans are provided in Appendix F for crossings of Section 10
waterbodies.
Waterbody Crossings
Atlantic will use the open -cut, flume, dam -and -pump, conventional bore, cofferdam, or
HDD methods to construct the pipelines across waterbodies. In each case and for each method,
Atlantic will adhere to the measures specified in the Procedures; site-specific modifications to
the Procedures as requested by Atlantic and approved by the FERC. As well as any additional
requirements identified in federal or state waterbody crossing permits, including applicable
permits and approvals from the USACE and various state agencies (see Section 135). A complete
list of the waterbodies along the proposed pipeline routes within the Wilmington Distict, and the
construction method proposed for each crossing, is provided in Appendix C. Construction
methods for waterbodies that isolate the pipeline trench from flowing water (e.g. flume, dam -
and -pump, cofferdam) will be utilized where these methods are proposed and perceptible flow is
present at the time of the crossing.
During the clearing and grading phase of construction, temporary bridges will be
installed across waterbodies in accordance with the Procedures to allow construction equipment
and personnel to cross. The bridges may include clean rock fill over culverts, timber mats
supported by flumes, railcar flatbeds, flexi-float apparatuses, or other types of spans.
Construction equipment will be required to use the bridges, except that the clearing and bridge
installation crews will be allowed one pass through waterbodies before bridges are installed. The
temporary bridges will be removed when construction and restoration activities are complete.
ATWS will be required on both sides of waterbody crossings to stage construction
equipment, fabricate the pipeline, and store construction materials. The ATWS will be located at
least 50 feet away from the water's edge at each waterbody (with the exception of site-specific
modifications as requested by Atlantic and approved by the FERC).
Clearing adjacent to waterbodies will involve the removal of trees and brush from the
construction right-of-way and ATWS areas. Woody vegetation within the construction right-of-
way will be cleared to the edge of each waterbody. Sediment barriers may be installed at the top
of the bank if no herbaceous strip exists. Initial grading of the herbaceous strip will be limited to
the extent needed to create a safe approach to the waterbody and to install temporary bridges.
Atlantic Coast Pipeline 17 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
During clearing, sediment barriers will be installed and maintained across the right-of-
way adjacent to waterbodies and within ATWS to minimize the potential for sediment runoff.
Erosion control devices located across the working side of the right-of-way will be removed
during the day when vehicle traffic is present, and will be replaced each night. Alternatively,
drivable berms may be installed and maintained across the right-of-way in lieu of silt fences
and/or straw bales.
Typically, equipment refueling and lubricating at waterbodies will take place in upland
areas that are 100 feet or more from the edge of the waterbody and any adjacent wetlands.
However, there will be certain instances where equipment refueling and lubricating may be
necessary in or near waterbodies. For example, stationary equipment, such as water pumps for
withdrawing hydrostatic test water, may need to be operated continuously on the banks of
waterbodies and may require refueling in place. Atlantic's Spill Prevention, Control, and
Countermeasures Plan (SPCC Plan) will address, among other items, the handling of fuel and
other materials associated with the ACP. As required by the Procedures, the SPCC Plan will be
available during construction on each construction spread. The SPCC Plan is provided in
Appendix G.
After the pipeline is installed across a waterbody using one of the methods described
below, the trench will be backfilled with native material excavated from the trench. If present
and moved prior to construction, larger rocks or boulders will be replaced in the stream channel
within the construction area following backfill of the trench. The streambed profile will be
restored to preconstruction contours and grade conditions to prevent scouring. The stream banks
will then be restored as near as practicable to preconstruction conditions and stabilized.
Stabilization measures will include seeding, installation of erosion control blankets, or
installation of riprap materials, as appropriate. Jute thatching or bonded fiber blankets will be
installed on banks of waterbodies or road crossings to stabilize seeded areas. Temporary erosion
controls will be installed immediately following bank restoration. The waterbody crossing area
will be inspected and maintained until restoration of vegetation is complete.
Open -Cut Method
The open -cut or wet trench crossing method will involve trenching through the
waterbody while water continues to flow through the trenching area. Prior to initiating
construction across the waterbody, the crossing section of pipeline will be fabricated (i.e., bent,
welded, and coated) in adjacent ATWS areas. Backhoe -type excavators will then be used to
excavate a trench in the flowing waterbody from one or both banks of the waterbody. Where the
waterbody is too wide to excavate the trench from the banks, equipment may operate from within
the waterbody with approval from the appropriate regulatory agencies. Equipment operating
within the waterbody will be limited to that needed to construct the crossing. During these
operations, flow will be maintained at the crossing as specified in the Procedures. Turbidity
curtains will be installed downstream of the crossing as necessary to minimize suspended solids
in the water.
Temporary sidecast excavated from the trench will be placed on the bank above the high
water mark (at least 10 feet from the edge of the water) or placed adjacent to the trench in the
stream (major waterbodies only, in accordance with the Procedures) for use as backfill. A
Atlantic Coast Pipeline 18 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
prefabricated segment of pipeline will then be placed into the trench using side -boom tractors.
Concrete coating (installed in uplands in project workspace) or bag weights will be utilized, as
necessary, to provide negative buoyancy for the pipeline. Once the trench is backfilled, the
banks will be restored as near as practicable to pre -construction contours and stabilized as
described above. Excavated material not required for backfill will be removed and disposed of at
approved upland disposal sites.
Throughout the construction process, Atlantic will follow the Procedures to avoid or
minimize impacts on water quality. Construction activities will be scheduled so that the trench is
not excavated across the waterbody until immediately prior to pipe laying activities. The
duration of in -stream construction activities (excluding blasting, if required) will be limited to
24 hours across minor waterbodies (those 10 feet in width or less) and 48 hours across
intermediate waterbodies (those between 10 and 100 feet in width).
Flume Method
The flume crossing method consists of isolating and temporarily diverting the flow of
water across the trenching area through one or more large -diameter, steel flume pipes placed in
the waterbody. This method allows for trenching activities to occur within a relatively dry
stream or riverbed (beneath the flume pipes containing the water flow), thereby minimizing
sediment and turbidity within the waterbody. The flume method is typically used to cross small
to intermediate flowing waterbodies that support coldwater or other significant fisheries.
For each waterbody where the flume method is implemented, a sufficient number of
adequately sized flume pipes will be installed in the waterbody to accommodate the highest
anticipated flows during construction. Atlantic will use stream gauge data from the USGS to
determine the highest anticipated flows during the time the flume crossing is in effect. In the
absence of stream gauge data, Atlantic's engineers and Environmental Inspectors will estimate
the highest anticipated flows based on the width of the waterbody at the ordinary high water
mark, the depth of the waterbody, existing flows at the time of the crossing, and the weather
forecast at the time of the crossing. As a contingency, Atlantic will stage additional flume pipes
at the crossing in the event that the volume of flow increases due to a precipitation event.
Prior to installation, Atlantic will inspect the flume pipes to confirm that they are free of
dirt, grease, oil, or other pollutants. After placing the pipes in the waterbody, sand- or pea
gravel -filled bags, water bladders, or metal wing deflectors will be placed in the waterbody
around the flume pipes upstream and downstream of the proposed trench. These devices will
serve to dam the stream and divert the water flow through the flume pipes, thereby isolating the
water flow from the construction work area between the dams.
After installation of the flume pipes, any remaining standing water between the dams will
be pumped out. Pump intakes will be appropriately screened to prevent entrainment of aquatic
species. Fish trapped in the dewatered area will be removed and returned to the flowing
waterbody. Leakage from the dams or subsurface flow from below the waterbody bed may
cause water to accumulate in the trench once trenching has begun. If water accumulates in this
area, it may be pumped out periodically and discharged into energy dissipation/sediment
filtration devices as required by the Procedures. Such devices include geotextile filter bags and
Atlantic Coast Pipeline 19 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
straw bale structures. Alternatively, the water will be discharged into well -vegetated areas away
from the edge of the waterbody, to prevent silt -laden water from entering the waterbody.
Backhoe -type excavators located on the banks of the waterbody will be used to excavate
a trench under the flume pipe across the dewatered streambed. Temporary side -cast material
excavated from the waterbody trench will be placed and stored on the bank above the high water
mark and a minimum of 10 feet from the edge of the waterbody. Once the trench is excavated, a
prefabricated segment of pipe will be installed beneath the flume pipes. The trench will then be
backfilled with the native material excavated from the trench across the waterbody bed. The
banks will be stabilized before removing the dams and flume pipes and returning flow to the
waterbody channel.
The flume method has proven to be an effective technique for constructing pipelines
across sensitive waterbodies. The potential for the introduction of turbidity or suspended
sediments is limited because sediment generated during trench excavation and backfilling
operations is isolated to the dewatered area between dams. When flumes are installed properly,
the operation of the flume is generally stable and can be left in place for periods prior to and
following the installation of the waterbody pipeline crossing. The flume method also provides
for continued fish passage through the construction work area via the flume pipes during the
crossing.
Dam -and -Pump Method
The dam -and -pump method generally is preferred for smaller waterbodies, where
mechanical pumps can dependably convey stream flows. In this approach, pumps and hoses are
used instead of flume pipes to isolate and transport the stream flow around the construction work
area. Similar to the flume method, the objective of the dam -and -pump method is to create a
relatively dry work area to avoid or minimize the transportation of sediment and turbidity
downstream of the crossing during in -stream work.
As the first step in implementing the dam -and -pump method, one or more pumps and
hoses of sufficient size to transport anticipated flows will be installed adjacent to the waterbody.
Additional back-up pumps will be on site at all times as a contingency, in case of pump failure.
Once the pumps are operational, the waterbody upstream and downstream of the construction
area will be dammed with sandbags and/or steel plates. As the dams are installed, the pumps
will be started to maintain continuous flow in the waterbody.
Following the installation of the dams, the pumps will be run continuously until the
pipeline is installed across the waterbody and the streambed and banks are restored. Pump
intakes above the upstream dam will be appropriately screened to prevent entrainment or
impingement of aquatic species. Energy -dissipation devices, such as splash blocks, filter bags,
or energy dissipation sleeves, will be used to prevent scouring of the streambed at the discharge
location. Water flow will be maintained through all but a short reach of the waterbody at the
actual crossing location.
Backhoe -type excavators located on the banks of the waterbody will be used to excavate
a trench across the waterbody. Temporary sidecast removed from the trench will be placed and
stored on the bank above the high water mark at a minimum of 10 feet from the edge of the
Atlantic Coast Pipeline 20 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
water. Trench plugs will be maintained between the upland trench and the waterbody crossing.
Once the trench is excavated, a prefabricated segment of pipe will be installed. The trench will
then be backfilled with the native material excavated from the trench across the waterbody bed.
After backfilling, the dams will be removed and the banks restored and stabilized as described
above.
Conventional Bore
In some cases, waterbodies may be crossed by conventional subsurface boring beneath
the waterbody. Boring involves installing pipeline through a hole bored through the substrate.
Where this method is implemented, equipment operating from pits excavated on either side of
the crossing will bore through the substrate beneath the waterbody. If dewatering of the pits is
necessary, it will be conducted in accordance with the Upland Erosion Control, Revegetation,
and Maintenance Plan (Plan) and Procedures and applicable permits in a manner that will
minimize erosion and prevent silt -laden water flowing into the waterbody or adjacent wetlands.
During a conventional bore crossing, the pipeline will be pushed through the bore hole
under the waterbody. Like the HDD method described later in this section, the conventional
bore can eliminate direct surface impacts on waterbodies, however, there are limitations to its
use. This method cannot typically be used to cross waterbodies with unconsolidated soils in the
substrate because it is not possible to maintain the integrity of the borehole in this condition.
Because conventional bores in general are installed straight along a horizontal plane, the
bore pits must be excavated to a depth sufficient to allow installation of pipe at the appropriate
depth beneath the streambed (i.e., 5 feet beneath the streambed) and to account for the height of
the boring machinery. Where waterbodies are entrenched or adjacent slopes are steep,
excavation to sufficient depths can require excessively large pits to address Occupational Safety
and Health Administration shoring requirements, which creates the potential to sink the stream or
flood the bore pits. These considerations limit the use of this crossing method for entrenched
waterbodies or those with steep slopes.
Cofferdam
Some waterbodies will be crossed using the cofferdam method. In this method, a
temporary diversion structure is installed from the bank around half the width of the crossing to
isolate that section of the stream from the rest of the waterbody. Once the temporary diversion
structure is installed, water is pumped from the isolated section to allow excavation of the pipe
trench from the bed of the waterbody in the dry. After the pipe is installed in the trench in the
isolated section of stream, the temporary diversion structure is disassembled and reinstalled from
the opposite bank of the crossing and the process is repeated. The cofferdam method allows
waterbodies to be crossed in the dry in discrete sections while water flows unimpeded around the
temporary diversion structure. The method is sometimes favored for wide, relatively shallow
waterbodies or waterbodies containing sensitive fisheries because it allows water and fish to pass
around the temporary diversion structure.
For waterbodies crossed using the cofferdam method, sections of steel frame for the
temporary diversion structure will be assembled in an upland area adjacent to the
crossing. Depending on size, the frame sections will be placed in the waterbody either manually
Atlantic Coast Pipeline 21 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
or by crane. The frame sections will be positioned around a predetermined perimeter in the
waterbody extending from one of the banks. The spacing of frame sections will be based on the
depth of the water, but a typical spacing will be 15 to 30 inches. The frame sections may be
reinforced, as necessary, with steel poles or other supports to increase stability of the structure,
especially in waterbodies with soft substrate. Fabric sheets will then be attached to the top of the
frame and unrolled down and out onto the bed of the waterbody on the exterior side of the
frame. The fabric sheets will create a liner around the frame with a seal on the bed of the
waterbody. The fabric may be covered in soft sediments or sandbags to help create the seal.
After the temporary diversion structure is installed, one or more pumps will be used to
dewater the area within the temporary diversion structure. Pump intakes will be appropriately
screened to prevent entrainment of aquatic species. Water will be discharged to the waterbody
outside the structure through an energy -dissipating device to prevent scouring of the bed at
locations of discharge.
Once dewatering is complete, any fish trapped in the temporary diversion structure will
be removed and returned to the flowing waterbody. Construction equipment will enter the
isolated section of the waterbody from the adjacent bank. This construction equipment will be
used to excavate the trench, install a pre -assembled section of pipe, backfill the trench, and
restore the bed as near as practicable to pre -construction contours. The equipment will be
removed from the temporary diversion structure via the adjacent bank.
After the section of pipeline is installed, the enclosed area within the temporary diversion
structure will be flooded. Then the fabric sheets and steel frame sections will be disassembled.
The structure will be reinstalled from the opposite bank, with enough overlap of the initial
excavation area so that the installed section is accessible for tie-in to the next section of
pipe. The dewatering and construction process is then repeated from the opposite bank, to
complete the crossing of the waterbody.
Horizontal Directional Drill Method
The HDD method allows for trenchless construction by drilling a hole beneath a surface
feature, such as a waterbody or other unique resource, and installing a prefabricated segment of
pipeline through the drill bore. The method avoids disturbance to the surface of the right of way
between the entry and exit points of the drill. The method is sometimes used to install pipelines
underneath sensitive resources or areas that present difficulties for construction or access using
typical installation methods. HDDs can provide certain advantages over typical construction
methods, such as avoidance of surface disturbance, riparian tree clearing, or in -stream
construction. Right-of-way maintenance will not occur between the HDD entry and exit points.
For each HDD crossing, electric grid guide wires will be laid by hand on the ground
along the pipeline centerline to create an electromagnetic sensor grid. The grid will be used by
the HDD operator to steer the drill head during drilling. The sensor grid will be fabricated by
installing several stakes along the drill path and wrapping them with an insulated coil wire. The
wire will be energized with a portable generator, which will create a magnetic field that can be
used to track the drill bit. No ground or surface disturbing activities will be required for
installation of the guide wires; however, in thickly vegetated areas a two- to three-foot wide path
Atlantic Coast Pipeline 22 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
may need to be cut with hand tools for the wires. Other methods such as gyroscope guidance
systems may be utilized in specific situations as an alternative to electric grid guidance to
accommodate the wires.
Prior to the final design and selection of the HDD method, geotechnical investigations
occur at each proposed crossing to ensure that the underlying geology supports the installation.
Minor disturbance may be necessary to conduct this investigation.
To complete each HDD, a drill rig will be placed on the entry side of the crossing and a
small -diameter pilot hole will be drilled along a predetermined path beneath the waterbody using
a powered drill bit. As drilling progresses, additional segments of drill pipe will be inserted into
the pilot hole to extend the length of the drill. The drill bit will be steered and monitored
throughout the process to maintain the designated path of the pilot hole. Once the pilot hole is
complete the hole will be enlarged to accept the pipeline. The HDD may require a drill rig on
both sides due to the complexity of the drill, for reasons including but not limited to, length,
substrate, noise, or duration.
To enlarge the pilot hole, a larger reaming tool will be attached to the end of the drill on
the exit side of the hole. The reamer will be drawn back through the pilot hole to the drill rig on
the entry side of the hole. Drill pipe sections will be added to the rear of the reamer as it
progresses toward the rig, allowing a string of drill pipe to remain in the drill bore at all times.
Several passes with progressively larger reaming tools will be required to enlarge the hole to a
sufficient diameter to accommodate the pipeline. The final hole will be approximately 12 inches
larger than the pipeline to be installed.
Throughout the drilling process, a fluid mixture consisting of water and bentonite clay (a
naturally occurring mineral) will be pumped into the drill hole to lubricate the bit, transport
cuttings to the surface, and maintain the integrity of the drill bore. Water for the mixture will be
pumped from the waterbody to the drill site through a hose or temporary network of irrigation -
type piping or trucked in from another source. The pump intake will be appropriately screened
to prevent entrainment of aquatic species. Small pits may be dug at or near the entry and exit
points for the HDD to temporarily store the drilling fluid and cuttings. The fluid and cuttings
will be pumped from the pits to an on-site recycling unit where the fluid will be processed for
reuse.
The pipeline segment (also called a pull section) to be installed beneath the surface
feature will be fabricated on the right of way or in the ATWS on the exit side of the crossing
while the drill hole is reamed to size. Once assembled, the girth welds of the pull section will be
coated with fusion -bonded epoxy. A sacrificial abrasion resistant overlay would be applied over
the fusion -bonded epoxy coating at the pipe mill for protection from abrasive materials that may
be encountered as the pull section is installed. These coating materials on girth welds will be
mixed in an area prepared to contain spills; splash pads, plastic or other material will be placed
on the ground in the mixing area to contain any potential spills. Activities will occur in
accordance with the SPCC Plan (see Appendix G). The pull section will be inspected and
hydrostatically tested prior to installation. A steel bullhead will be welded onto the front end of
the pull section to aid in pulling the pipe through the drill hole. After the hole is completed, the
Atlantic Coast Pipeline 23 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
pipeline segment will be attached to the drill string on the exit side of the drill bore and pulled
back toward the drill rig.
As the pipeline is being installed, excess drilling fluid will be collected and disposed of at
an approved facility or, as allowed and approved by the agencies and landowner. The HDD
drilling fluid is a mixture of bentonite clay (a naturally occurring material) and water. Excess
drilling fluid will not be incorporated into soils under any circumstances within or adjacent to
habitats with known federally listed plant species. If water is left over from the drilling process,
it will be discharged in accordance with the Plan and Procedures and applicable permits into a
well -vegetated upland area or an energy dissipation/sediment filtration device, such as a
geotextile filter bag or straw bale dewatering structure, at the site.
Successful crossings utilizing HDD will result in little to no impact on the surface feature
being crossed. If a natural fracture or weak area in the ground is encountered during drilling, an
inadvertent return of drilling fluid to the environment could occur. Substrate consisting of
unconsolidated gravel, coarse sand, or fractured bedrock could increase the likelihood of an
inadvertent return. Depending on the orientation of the natural fracture or substrate, the drilling
fluid may move laterally or vertically from the drill hole. If the drilling fluid moves laterally, the
release may not be evident on the ground. For an inadvertent return to be evident on the surface
there must be a preferential pathway extending vertically from the drill hole to the surface of the
ground. The volume of fluid released in an inadvertent return would depend on a number of
factors, including the size of the pathway, the permeability of the geologic material, the viscosity
of the fluid, and the pressure of the hydraulic drilling system. The drilling fluid is a closed
system that is monitored closely for changes in pressure and volume, which may indicate
development of an inadvertent return. If a change in pressure is identified, corrective action will
occur.
Atlantic has prepared a Horizontal Directional Drill Fluid Monitoring, Operations, and
Contingency Plan (HDD Plan) which describes the measures to be implemented in the event of
an inadvertent return and can be found in Appendix H. If a release occurs on land, including
within a wetland, a small pit will be excavated at the release site to contain the spread of the
fluid, and a pump will be used to transfer the fluid from the pit into a containment vessel. If an
inadvertent return occurs in a waterbody it will be more difficult to contain because the fluid may
be dispersed into the water and carried downstream. In this situation, thickening agents such as
additional bentonite, cottonseed hulls, or other non -hazardous materials will be added to the
drilling fluid, in order to plug the flow path. All drilling fluid additives will be non -hazardous.
Once a drilling contractor has been selected and the specific additives are identified, a list of
additives will be compiled in site-specific HDD Plans along with appropriate Material Safety
Data Sheets and product descriptions. Atlantic will consult with and obtain permission from the
appropriate state regulatory agencies regarding the use of additives during the HDD process and
confirm that additives will not violate water quality standards.
Atlantic will monitor source waters along and near the drill path, such as seeps and
springs, for inadvertent returns. Atlantic will implement the measures identified in the HDD
Plan to control and clean up the inadvertent return, test the water for water quality, and provide
an alternate supply of water to affected landowners until the inadvertent return is remediated.
Atlantic Coast Pipeline 24 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
The HDD method is proposed on the AP -2 mainline in North Carolina for the following
seven large river crossings (five additional minor tributaries of these rivers would also be crossed
via HDD of the major waterbody), pending the results of geotechnical investigations and final
engineering:
• Roanoke River at approximate MP 9.8 at the Northampton/Halifax County line;
• Fishing Creek at approximate MP 33.9 at the Halifax/Nash County line;
• Swift Creek at approximate MP 40.6 in Nash County;
• Tar River at approximate MP 59.4 in Nash County;
• Contentnea Creek at approximate MP 73.6 in Wilson County;
• Little River at approximate MP 82.5 in Johnston County; and
• Cape Fear River at approximate MP 154.2 in Cumberland County.
Atlantic explored use of the HDD method at the Rocky Swamp crossing, but based on
geotechnical results, due to heavily weathered bedrock and overlying unconsolidated materials,
the likelihood of experiencing an inadvertent release was high. Therefore, the HDD method is
not proposed for the Rocky Swamp crossing.
Wetlands
Construction across wetlands will be conducted in accordance with the Procedures, site-
specific modifications to the Procedures requested by Atlantic and approved by the FERC, and
additional requirements identified in federal or state wetland crossing permits. Typical methods
for construction across wetlands are described below. A list of wetland crossings along the
proposed pipeline route within the Wilmington Distict is provided in Appendix C.
In accordance with the Procedures, the width of the construction right-of-way will be
limited to 75 feet through wetlands, with ATWS on both sides of wetland crossings to stage
construction equipment and materials, fabricate the pipeline, and store materials and excavated
temporary sidecast material. ATWS will be located in upland areas a minimum of 50 feet from
the wetland edge (with the exception of site-specific modifications as requested by Atlantic and
approved by the FERC or where adjacent uplands consist of cultivated or rotated cropland or
other disturbed land).
Wetland boundaries will be clearly marked in the field prior to the start of construction
with signs and flagging. Construction equipment working in wetlands will be limited to what is
essential for right-of-way clearing, excavating the trench, fabricating and installing the pipeline,
backfilling the trench, and restoring the right of way. In areas where there is no reasonable
access to the right of way except through wetlands, non-essential equipment will be allowed to
travel through wetlands once, unless the ground is firm enough or has been stabilized to avoid
rutting. Stabilization may include use of rip -rap or prefabricated timber mats. Temporary
stabilization materials placed in the wetlands will be removed during the restoration of the right
of way.
Clearing of vegetation in wetlands will be limited to trees and shrubs, which will be cut
flush with the surface of the ground and removed from the wetland. To avoid excessive
disruption of wetland soils and the native seed and rootstock within the topsoil, stump removal,
Atlantic Coast Pipeline 25 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
grading, topsoil segregation, and excavation will be limited to the area immediately over the
trenchline, except a limited amount of stump removal and grading may be conducted in other
areas if required by safety-related issues. Topsoil segregation over the trenchline will only occur
if the wetland soils are not saturated at the time of construction.
As part of the land clearing process, sediment barriers, such as silt fences or other
approved sediment barriers, will be installed and maintained adjacent to wetlands and within
ATWS areas as necessary to minimize the potential for sediment runoff. Sediment barriers will
be installed across the full width of the construction right-of-way at the base of slopes adjacent to
wetland boundaries. Erosion control devices installed across the working side of the right-of-
way will be removed during the day when vehicle traffic is present, and will be replaced each
night. Alternatively, drivable berms may be installed and maintained across the right-of-way in
lieu of silt fences or straw bales. Sediment barriers will also be installed within wetlands along
the edge of the right-of-way, where necessary, to minimize the potential for sediment to run off
the construction right-of-way and into wetlands outside the work area. If trench dewatering is
necessary, it will be conducted in accordance with the Procedures and applicable permits. Silt -
laden trench water will be discharged into an energy dissipation/sediment filtration device, such
as a geotextile filter bag and straw bale structure, to minimize the potential for erosion and
sedimentation.
The method of pipeline construction used in wetlands will depend on site-specific
weather conditions, soil saturation, and soil stability at the time of construction. If wetland soils
are not excessively saturated at the time of construction and can support construction equipment
on equipment mats, they will be crossed using conventional open -trench construction. This will
occur in a manner similar to conventional upland cross-country construction techniques. In
unsaturated wetlands, topsoil from the trenchline will be stripped and stored separately from
subsoil.
Where wetland soils are saturated or in inundated lowlands areas where soils cannot
support conventional pipe -laying equipment, the pipeline may be installed using the push-pull
method. This method will involve stringing and welding the pipeline outside of the wetland and
excavating and backfilling the trench using a backhoe supported by equipment mats. A
prefabricated section of pipeline will be installed in the wetland by equipping it with buoys and
pushing or pulling it across the water -filled trench. After the pipeline is floated into place, the
floats will be removed and the pipeline will sink into place. In most cases, the pipeline will be
coated with concrete or equipped with set -on weights to provide negative buoyancy. Once the
pipeline is in place, the trench will be backfilled. The push-pull construction method minimizes
the number of equipment passes, reducing wetland impacts and soil compaction in lowland
areas.
The application of concrete coating will generally occur in contractor yards identified for
the Projects. In areas where concrete coating of pipe is required within the construction right of
way, the coating activities will occur in accordance with the SPCC Plan. Concrete coating
activities will occur a minimum of 100 feet from wetlands, waterbodies and springs, and 300 feet
from karst features. Concrete -coated pipe will be installed after the concrete is dried and will not
be dispersed when submerged in water. Concrete coating is used to create negative buoyancy
Atlantic Coast Pipeline 26 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
along the pipeline when required for waterbody or wetland crossings if necessitated by site-
specific conditions.
Because little or no grading will occur in wetlands, restoration of contours will be
accomplished during backfilling. Prior to backfilling, trench breakers will be installed, where
necessary, to prevent subsurface drainage of water from wetlands. Where topsoil is segregated,
the subsoil will be backfilled first followed by the topsoil. Topsoil will be replaced to the
original ground level leaving no crown over the trenchline. In areas where wetlands overlie
rocky soils, the pipe will be padded with rock -free soil or sand before backfilling with native
bedrock and soil. Equipment mats, gravel fill, and/or geotextile fabric will be removed from
wetlands following backfilling. In addition, trench plugs will be installed at the boundaries of
wetlands to prevent sub -surface hydrology from following the trenchline and indirectly removing
hydrology from wetlands.
Where wetlands are located at the base of slopes, permanent slope breakers will be
constructed across the right of way in upland areas adjacent to the wetland boundary. Temporary
sediment barriers will be installed where necessary until revegetation of adjacent upland areas is
successful. Once revegetation is successful, sediment barriers will be removed from the right of
way and disposed of at an approved disposal facility.
4. Jurisdictional Determinations
Natural Resource Group, LLC, on behalf of Atlantic, conducted wetland and waterbody
surveys for the proposed ACP. Natural Resource Group, LLC contracted with Duncan &
Duncan WEST, LLC, Environmental Services Inc., and Woodard & Curran to complete the field
efforts. The survey area in North Carolina consists of a 300 -foot -wide corridor approximately
198.7 miles long. Wetland and waterbody surveys have been on-going since June 2014 and will
continue until the wetland and waterbody surveys are complete on all land parcels along the
proposed pipeline route. As of January 2017, wetland and waterbody surveys in North Carolina
for AP -2 and AP -3 are 98 percent complete. Where field surveys were not able to be completed,
due to lack of access to properties, a desktop assessment was completed to delineate wetlands
and waterbodies using a combination of National Wetlands Inventory data, USGS topographic
maps, Soil Survey Geographic Database data, and high resolution aerial photography.
Figures A-3 and A-4 of Appendix A show the relative locations of delineated features along the
AP -2 and AP -3 lines within North Carolina.
The assessment of all wetlands, rivers, streams, open waterbodies (e.g., ponds), and seep
points were documented within the survey corridor and based on qualified wetland biologists'
best professional judgment and interpretation of the U.S. Army Corps of Engineers 1987
Wetlands Delineation Manual (USACE, 1987), the Regional Supplement to the Corps of
Engineers Wetland Delineation Manual: Atlantic and Gulf Coastal Plain Region (Version 2.0)
(USACE, 2010b), the USACE Regulatory Guidance Letter regarding Ordinary High Water Mark
Identification (USACE, 2005), and other applicable USACE guidance documents and
regulations.
Atlantic Coast Pipeline 27 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Atlantic has applied for a Preliminary Jurisdictional Determination from the USACE
identifying wetlands, streams and other waterbodies within the ACP project area. See
Appendix B for a copy of the Wetland and Waterbody Survey Report.
5. Project History
In addition to the NWP 12, Atlantic is applying for several federal and state permits for
ACP. A list of the permits applied for are included in Table 2 below.
TABLE 2
Permit Table for the Atlantic Coast Pipeline in North Carolina
Agency
Permit/Approval/Consultation
Filing/Anticipated
Filing Date
Anticipated
Approval Date
Federal
Federal Energy Regulatory
Certificate of Public Convenience and
September 18, 2015
September 2017
Commission
Necessity under Section 7(c) of the Natural
Gas Act
Federal Aviation Administration
Notice of Proposed Construction or
November 2016
October 2017
Authorization
Federal Aviation Administration
Supplemental Notice
November 2016
October 2017
Federal Communications Commission
Application for Wireless Telecommunications
November 2016
October 2017
Bureau Radio Service Authority
National Oceanic and Atmospheric
Consultation under Section 7 of the
Ongoing
September 2017
Administration — National Marine
Endangered Species Act and Section 305 of
Fisheries Service
the Magnuson -Stevens Act
National Oceanic and Atmospheric
Consultation under the Marine Mammal
August 22, 2014
July 1, 2016
Administration — National Marine
Protection Act
Fisheries Service
National Park Service — Blue Ridge
Right -of -Way Grant and Special Use Permit to
September 17, 2015
September 2017
Parkway
cross the Blue Ridge Parkway
U.S. Army Corps of Engineers —
Department of the Army NWP 12 Verification
September 15, 2015
September 2017
Pittsburgh, Pittsburgh, Norfolk, and
under Section 404 of the Clean Water Act and
Wilmington Districts
Section 10 of the Rivers and Harbors Act
U.S. Army Corps of Engineers —
Department of the Army Permissions under
August 2016
September 2017
Norfolk District
Section 408 of the Rivers and Harbors Act
U.S. Army Corps of Engineers —
Department of the Army Permissions under
August 2016
September 2017
Wilmington District
Section 408 of the Rivers and Harbors Act
North Carolina
North Carolina Department of
Air Permit — Stationary Source Construction
September 16, 2015
June 2017
Environment and Natural Resources
and Operation Permit for Compressor Station 3
(original)
— Division of Air Quality
December 15, 2016
(equipment change
update)
North Carolina Department of
General Permit NCG 010000 to Discharge
December 2016
3Q 2017
Environment and Natural Resources
Stormwater under the National Pollutant
— Division of Energy, Mineral, and
Discharge Elimination System
Land Resources (or approved local
government)
North Carolina Department of
Water Quality Certificate under Section 401 of
NA
3Q 2017
Environment and Natural Resources
the Clean Water Act (including permission to
— Division of Water Resources
use State-owned bottom lands)
North Carolina Department of
Isolated and Other Non -404 Jurisdictional
September 15, 2015
3Q 2017
Environment and Natural Resources
Wetlands and Waters Permit (including
— Division of Water Resources
permission to use State-owned bottom lands)
North Carolina Department of
Buffer Authorization (for riparian zone
September 15, 2015
3Q 2017
Environment and Natural Resources
disturbance)
— Division of Water Resources
Atlantic Coast Pipeline 28 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
TABLE 2
Permit Table for the Atlantic Coast Pipeline in North Carolina
Agency
Permit/Approval/Consultation
Filing/Anticipated
Filing Date
Anticipated
Approval Date
North Carolina Department of
Natural Heritage/Protected Species
Ongoing
3Q 2017
Environment and Natural Resources
Consultation
— Natural Heritage Program
North Carolina State Historic
Consultation under Section 106 of the National
Ongoing
3Q 2017
Preservation Office
Historic Preservation Act
North Carolina Wildlife Commission
Protected Species Consultation
October 13, 2014
3Q 2017
County/City/Local
Floodplain Permit (expected to be required in
2Q 2017 — 3Q 2017
2Q 2017 — 3Q 2017
all Counties and Cities along the routes)
County/City/Local
Special or Conditional Use Permit (where
2Q 2017
3Q 2017
required)
Table includes all applications for the Wilmington District.
6. Future Project Plans
See Section B.6 of the PCN Form.
C. PROPOSED IMPACTS INVENTORY
The ACP pipeline facilities, access roads, and aboveground facilities will require a total
of 549 single and complete projects across waters of the U.S. in North Carolina, detailed within
Appendix C -l. Appendix C provides details of wetlands that include location information,
HUC 8 codes, wetland type classifications, and an analysis of impacts proposed, and details of
waterbodies that include location information, HUC 8 codes, state special designations, tributary
information, and an analysis of impacts proposed. AP -2 and AP -3 cross a total of 10 HUC 8
watersheds across North Carolina. The HUC 8 watersheds and the impacts anticipated for
wetlands and waterbodies crossed by the pipeline workspace are summarized in tables 3 and 4,
below. No permanent loss to wetlands or waterbodies is anticipated for mainline pipeline
construction or associated facilities. However, permanent loss impacts to 1.72 acres of wetlands
are proposed for construction and improvements to permanent access roads in the Wilmington
District, as discussed below in the subsection on Access Roads and Aboveground Facilities.
Outside of the 30 -foot maintained right-of-way, Atlantic will replant non -inundated forested
deciduous hardwood wetlands. Temporary wetland impacts, conversion of type impacts, and
permanent losses are noted below for HUC 8 watersheds and in Appendix C-1 for individual
projects (crossings). A summary of single and complete projects can be found in Appendix C-2.
Table 3 provides a summary of the proposed wetland impacts within eight -digit HUC
watersheds crossed by the ACP in the Wilmington District.
Atlantic Coast Pipeline 29 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification - Supplemental Information DRAFT
U.S. Army Corps of Engineers - Wilmington District
Atlantic Coast Pipeline 30 DRAFT
TABLE 3
Atlantic Coast Pipeline Project - U.S. Army Corps of Engineers Wilmington District
HUC 8 Wetland Impacts Table
Cowardin
Crossing Length Temporary Impacts Conversion Impacts
Permanent Loss
HUC 8 Watershed Classification'
(feet) (acre)b
(acre)'
(acre)
03010107
PEM
374 0.84
0.00
0.00
PFO
4,118 8.43
2.87
0.00
PSS
135 0.34
0.03
0.00
Subtotal
4,626 9.60
2.91
0.00
03010204
PEM
4,003 4.33
0.00
0.00
PFO
9,983 22.05
7.99
0.01
PSS
219 0.57
0.05
0.00
Subtotal
14,204 26.96
8.04
0.01
03020101
PEM
702 1.39
0.00
0.00
PFO
23,719 40.74
16.03
0.06
PSS
116 0.21
0.03
0.00
Subtotal
24,537 42.91
16.41
0.06
03020102
PEM
1,856 3.42
0.00
0.13
PFO
19,628 34.24
13.54
0.20
PSS
3,531 6.34
0.81
0.00
Subtotal
25,015 44.00
14.36
0.32
03020201
PEM
714 1.34
0.00
0.00
PFO
44,342 81.00
30.53
0.79
PSS
2,340 4.48
0.54
0.03
Subtotal
47,396 86.82
31.06
0.82
03020203
PEM
139 0.18
0.00
0.00
PFO
24,929 44.31
17.15
0.05
PSS
360 0.65
0.08
0.00
Subtotal
25,428 45.14
17.23
0.05
03030004
PEM
91 0.57
0.00
0.00
PFO
5,196 9.83
3.57
0.06
PSS
257 0.46
0.06
0.00
Subtotal
5,545 10.86
3.63
0.06
03030005
PEM
0.00 0.43
0.00
0.00
PFO
17,571 30.37
12.03
0.00
PSS
978 1.81
0.23
0.00
Subtotal
18,549 32.61
12.25
0.00
03030006
PEM
1,518 4.67
0.00
0.03
PFO
34,727 57.77
23.40
0.00
PSS
10,342 17.84
2.37
0.37
Subtotal
46,587 80.28
25.78
0.41
03040203
PEM
1,564 2.58
0.00
0.00
PFO
30,859 55.30
21.26
0.00
PSS
10,611 18.81
2.43
0.00
Subtotal
43,035 76.12
23.35
0.00
Project Total
254,922 455.30
155.01
1.72
'
Indicates Cowardin classification.
PEM - emergent, PSS - scrub -shrub, PFO - forested.
b
Temporary impacts include all permanent, temporary, and extra temporary workspace.
°
Conversion of PFO and PSS wetlands consists of acreage that will be maintained as herbaceous/scrub-shrub wetlands following
construction to facilitate inspection and maintenance of the pipeline.
Note: The totals shown in this table may not equal the sum of addends due to rounding
Atlantic Coast Pipeline 30 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Table 4 provides a summary of the waterbody impacts by eight -digit HUC watersheds
crossed by the ACP.
TABLE 4
Atlantic Coast Pipeline Project -- U.S. Army Corps of Engineers Wilmington District
HUC 8 Waterbody Impacts in North Carolina
HUC 8 Watershed
Waterbody Type
Total Count
Approximate Crossing Width (feet)
Affected Length (feet)
03010107
Ephemeral
1
3
124
Intermittent
11
65
1,372
Perennial
11
418
944
Open Water
2
N/A
N/A
Subtotal
25
486
2,440
03010204
Ephemeral
4
19
344
Intermittent
7
27
440
Perennial
8
115
846
Subtotal
19
161
1,630
03020101
Ephemeral
1
3
767
Intermittent
9
44
900
Perennial
30
619
3,194
Open Water
1
N/A
N/A
Subtotal
41
666
4,861
03020102
Ephemeral
1
0
107
Intermittent
18
67
1,969
Perennial
12
264
1,814
Subtotal
31
332
3,890
03020201
Ephemeral
4
7
560
Intermittent
21
87
3,110
Perennial
16
348
1,549
Open Water
4
N/A
N/A
Subtotal
45
442
5,219
03020203
Ephemeral
11
33
1,296
Intermittent
12
60
1,201
Perennial
15
198
1,829
Open Water
3
N/A
N/A
Subtotal
41
291
4,326
03030004
Ephemeral
4
11
412
Intermittent
10
44
1,262
Perennial
10
147
999
Open Water
1
N/A
N/A
Subtotal
25
203
2,672
03030005
Ephemeral
5
23
1,097
Intermittent
15
81
1,677
Perennial
14
506
1,474
Subtotal
34
610
4,247
03030006
Ephemeral
7
27
835
Intermittent
11
46
901
Perennial
14
467
1,752
Open Water
2
N/A
N/A
Subtotal
34
539
3,488
03040203
Ephemeral
5
26
510
Intermittent
17
80
2,014
Perennial
7
128
724
Open Water
2
N/A
N/A
Subtotal
31
233
3,248
Project Total
326
39964
36,022
Note: The totals shown in this table may not equal the sum of addends due to
Atlantic Coast Pipeline 31 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Access Roads and Aboveground Facilities
Impacts resulting in loss of waters of the U.S. are not anticipated as a result of mainline
pipeline construction. However, loss of waters of the U.S. will occur as a result of permanent
access road construction and improvements, where necessary. Existing access roads will be
utilized where feasible. Where improvements are necessary for use, loss impacts to waters of the
U.S. have been minimized to the maximum extent practicable, and kept below 0.5 acre for each
single and complete projects.
Atlantic has designed access roads to minimize impacts on waterbody and wetlands.
Culverts will be installed to conform to NWP Regional Condition 3.6 Safe Passage
Requirements for Culvert Placement. Since the project does not cross coastal counties the
primary conditions include: proper sizing of culverts based on average historical low flow and
spring flow to minimize potential for altering the stream channel, and constructed in a manner
that minimizes destabilization and head cutting. Where culverts over 48 inches in diameter are
utilized the culvert will be buried at least one foot below the bed of the stream, and other culvers
should be placed on the stream bed or buried to maintain aquatic passage. Where these
requirements cannot be met a waiver will be requested.
Aboveground facilities (i.e., compressor stations, M&R stations, and valves) have been
sited to avoid permanent wetland loss.
1. Impacts Summary
Ia. See Section Cla of the PCN Form.
2. Wetland Impacts
Impacts on wetlands are summarized in Tables 3 above, and provided in detail in
Appendix C-1.
3. Stream Impacts
Impacts on waterbodies are summarized in Table 4 above, and provided in detail in
Appendix C -l. Site specific plans for Section 10 waters are provided in Appendix F.
Section 10 waters within the Wilmington District include:
• Roanoke River at Milepost 9.8
• Neuse River at Milepost 98.5
• Cape Fear River at Milepost 154.2
4. Open Water Impacts
Impacts on Open Waters are summarized in Tables 4 above, and provided in detail in
Appendix C-1.
Atlantic Coast Pipeline 32 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
5. Pond or Lake Construction
No pond, lake, or impoundments are proposed to be constructed as part of ACP in North
Carolina. Temporary above -ground structures designed to hold water for hydrostatic testing will
be installed adjacent to water source withdrawal areas and outside of waterbody channels. These
water holding containments will be filled by mechanical pumps from nearby waters. Therefore,
NWP 2017-2022 condition 8, which refers to impoundment of "waters of the U.S." and
NWP 2017-2022 condition 24, which refers to dam safety are not applicable to the Project.
6. Buffer Impacts (for DWQ)
AP -2 will cross riparian buffer zones within the Neuse and Tar -Pamlico river basins.
Based on coordination with NCDEQ, Waterbodies subject to the buffer rules are provided in
Table 5 below. Atlantic has worked closely with the NCDEQ staff to field verify waterbodies
that are subject to the buffer rule in the Neuse and Tar -Pamlico basins. On November 23, 2016
Atlantic submitted a compiled package of correspondence to the NCDEQ that documents
waterbodies subject to the riparian buffer rule. Subsequent to this submittal additional site visits
were completed and NCDEQ replied with an additional letter. Documentation of site visits and
subject waters determinations are compiled for NCDEQ convenience in Appendix I.
Atlantic utilized the determinations made with the NCDEQ to further evaluated impacts
within the buffers of subject waterbodies. According to 15A North Carolina Administrative
Code 2B.0233 (Neuse watershed) for waterbodies that are subject to the buffer rule, the
treatment of the buffer depends on whether or not the crossing is perpendicular to the
waterbody.6 Table 5 provides a summary of buffer Zone 1 and Zone 2 impacts for all
waterbodies subject to the rule, and provides a determination of those waterbodies that are
perpendicular versus not perpendicular.
6 Perpendicular crossings are defined as those that intersect the surface water at an angle between 75° and 105°
Atlantic Coast Pipeline 33 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification - Supplemental Information DRAFT
U.S. Army Corps of Engineers - Wilmington District
Atlantic Coast Pipeline 34 DRAFT
TABLE5
North Carolina Buffer Impacts
Zone 1
Permanent/T
Requires
Zone 2
(Square
emporary
Buffer
(Square
Required
Watershed MP
Unique M
Perpendicular
Feet)
Impact
Mitigation
Feet)
Mitigation
Tar -Pamlico 18.5
shlb050
N/A
9,723
T
N
6,800
N/A
18.5
shlg009
No
46,549
T
Y
29,311
139,647
20.0
shlh008
No
4,673
T
Y
3,120
14,020
20.5
shlh007
No
7,349
T
Y
4,996
22,048
22.8
shlh016
No
6,006
T
Y
4,678
18,018
23.1
shlh017
No
5,446
T
Y
4,422
16,337
24.0
shlg012
Yes
5,958
T
N
4,060
N/A
25.0
shlb100
Yes
5,220
T
N
3,536
N/A
26.5
shlh009
No
5,105
T
Y
3,541
15,315
27.4
shlh011
No
8,733
T
Y
5,723
26,200
27.7
shlh012
Yes
4,620
T
N
3,071
N/A
29.8
shla001
No
5,509
T
Y
3,950
16,526
31.2
shlo001
N/A
2,032
T
N
3,741
N/A
31.2
shlo002
Yes
4,543
T
N
3,216
N/A
33.4
shlh022
N/A
1,954
T
N
1,248
N/A
33.8
shlg011
No
3,053
T
Y
2,052
9,160
34.0
snag001
No
3,296
T
Y
2,207
9,887
34.8
snag002
Yes
4,514
T
N
3,553
N/A
40.4
snah002
Yes
7,708
T
N
5,343
N/A
40.6
snah003
No
3,275
T
Y
2,145
9,824
40.9
snah006
No
6,770
T
Y
4,718
20,310
41.6
snah005
Yes
5,564
T
N
3,959
N/A
41.7
snah004
No
5,661
T
Y
3,897
16,983
42.0
snah029
Yes
5,035
T
N
3,302
N/A
42.1
snah025
No
12,283
T
Y
6,166
36,849
42.2
snah026
No
7,249
T
Y
4,483
21,746
42.8
snab 103
Yes
5,429
T
N
4,081
N/A
44.0
snab104
N/A
2,053
T
N
2,942
N/A
44.4
snabl05
N/A
1,548
T
N
2,720
N/A
44.5
snac001
No
7,715
T
Y
6,780
23,145
44.8
snag012
No
5,936
T
Y
5,495
17,808
45.4
onac002
N/A
0
T
N
654
None
47.2
snah008
No
7,637
T
Y
5,024
22,912
47.6
snah010
Yes
8,433
T
N
4,857
None
48.8
snah015 a
New Feature
New Feature
New Feature
New Feature
New Feature
New Feature
49.5
snah017
No
9,351
T
Y
6,041
28,054
50.3
snag006
N/A
937
T
N
2,361
None
50.8
snag005
No
9,164
T
Y
7,834
27,491
51.5
snag009
No
12,855
T
Y
9,275
38,564
51.6
snag009
No
12,855
T
Y
9,275
38,564
52.0
onag002
N/A
505
T
N
2,098
None
52.0
snab101
N/A
1,697
T
N
1,597
None
53.3
snah021
No
6,260
T
Y
3,595
18,780
54.8
snah020
No
4,874
T
Y
3,419
14,622
56.3
snah024
Yes
7,048
T
N
3,410
None
56.7
snah022
No
21,475
T
Y
9,286
64,425
57.1
snah019
No
5,555
T
Y
4,073
16,665
58.8
snap004
Yes
5,404
T
N
4,479
None
Atlantic Coast Pipeline 34 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification - Supplemental Information DRAFT
U.S. Army Corps of Engineers - Wilmington District
Atlantic Coast Pipeline 35 DRAFT
TABLE5
North Carolina Buffer Impacts
Zone 1
Permanent/T
Requires
Zone 2
(Square
emporary
Buffer
(Square
Required
Watershed MP
Unique M
Perpendicular
Feet)
Impact
Mitigation
Feet)
Mitigation
59.4
snao011
No
4,098
T
Y
2,716
12,293
Neuse 63.3
snao004
Yes
4,740
T
N
3,274
None
66.0
swio015
No
7,326
T
Y
5,521
21,978
66.3
swio016
No
13,144
T
Y
9,232
39,433
66.9
swio014 a
New Feature
New Feature
New Feature
New Feature
New Feature
New Feature
67.8
swio002
Yes
4,850
T
N
3,129
None
69.1
swic004
N/A
522
T
N
1,820
None
69.3
swio005
No
5,981
T
Y
3,854
17,943
69.4
swio004
No
17,646
T
Y
11,908
52,939
69.7
swio007
Yes
5,030
T
N
3,923
None
70.4
swio009
Yes
5,782
T
N
4,006
None
70.5
swio008
No
6,419
T
Y
4,963
19,258
71.0
swio011
No
5,594
T
Y
3,991
16,783
71.0
swio012
Yes
4,564
T
N
3,033
None
71.0
swio013
No
17,774
T
Y
11,592
53,321
72.3
swic001
No
7,852
T
Y
5,780
23,556
73.1
swib100a
No
10,019
T
Y
8,712
30,056
73.2
swib100b
No
7,405
T
Y
4,792
22,216
73.3
swib100c
Yes
6,970
T
N
4,792
None
73.6
swic002
No
4,240
T
Y
2,776
12,719
75.8
swip009
N/A
3,040
T
N
5,050
None
75.8
swip017
No
5,057
T
Y
4,354
15,172
79.2
sjobl03
No
22,356
T
Y
18,709
67,068
79.3
sjobl03
No
22,356
T
Y
18,709
67,068
79.5
sjob104
No
5,934
T
Y
4,733
17,801
82.5
sjoe002
Yes
3,209
T
N
2,148
None
83.5
sjoe006
Yes
10,217
T
N
5,015
None
84.5
sjop001
No
8,139
T
Y
5,125
24,418
85.9
sjoo003
Yes
4,552
T
N
3,028
None
86.5
sjoo004
No
7,891
T
Y
4,914
23,674
88.9
sjop005
No
8,634
T
Y
7,744
25,901
89.8
sjop007
Yes
6,816
T
N
3,897
None
91.2
sjop009
N/A
1,740
T
N
9,187
None
92.1
sjop010
Yes
6,606
T
N
4,796
None
95.1
sjob011
No
5,412
T
Y
4,561
16,237
95.3
sjop018
N/A
13,332
T
N
10,872
None
98.5
sjob105
Yes
6,761
T
N
4,515
None
102.4
sjob006
No
8,011
T
Y
5,269
24,032
102.8
sjob004
No
5,818
T
Y
4,567
17,453
103.9
sjob003
Yes
4,897
T
N
3,143
None
107.7
sjob001
N/A
0
T
N
2,111
None
110.3
sjop017
N/A
839
T
N
2,233
None
113.1
sjoo007
No
6,670
T
Y
4,227
20,009
113.7
sjoe007
N/A
222
T
N
5,745
None
a Feature extended subsequent to agency field review, requires confinnation with NCDEQ.
Atlantic Coast Pipeline 35 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
D. IMPACT JUSTIFICATION AND MITIGATION
1. a.1 Avoidance and Minimization
For purposes of the USACE evaluation of single and complete projects, the "alternatives
analysis" is to ensure that the crossing of each wetland, stream and other waterbody is made in a
manner that avoids and minimizes impacts on the aquatic environment to the maximum extent
practicable, after considering the approach to the crossing in the uplands immediately adjacent to
the water of the United States. For example, to the extent practicable, crossings will be
perpendicular to the aquatic feature to minimize the length of the pipeline in the particular
aquatic system.
The FERC NEPA process includes the evaluation of alternative route alignments that
reduce the overall impacts on the human environment of the proposed pipeline including
avoiding and minimizing impacts to wetlands, streams, and other waterbodies. In addition all
crossings within the Wilmington District have been designed to meet NWP 12 criteria also
resulting in further avoidance and minimization of impacts. As background, information on the
FERC alternatives analysis follows, including discussion of the various alternatives FERC is
considering. The USACE is a cooperating agency on the FERC NEPA EIS and is working with
FERC to ensure that USACE comments regarding the overall pipeline alternatives analysis are
fully considered in that process. The fact that the ACP will be subject to an EIS does not
preclude the use of NWP 12 for the affected waterbody crossings. As provided for in the
USACE 2012 NWP Federal Register (FR) final NWPs:
"One commenter requested clarification that individual permits are not automatically
required for NWP 12 activities when a Corps district participates as a cooperating
agency for an environmental impact statement. [Response] "Even though an
environmental impact statement may be prepared for a particular utility line, the
National Environmental Policy Act process does not prohibit the Corps from using
NWP 12 to authorize the construction, maintenance, repair, and removal of utility lines
and associated facilities in waters of the United States, as long as the activity complies
with all applicable terms and conditions and results in minimal individual and
cumulative adverse effects on the aquatic environment. NEPA requires consideration of
all environmental impacts, not only those to aquatic resources, so there may well be
situations where aquatic impacts are minimal even though environmental impacts more
generally are not. These other environmental impacts would be addressed by the lead
agency preparing the environmental impact statement. " [77 FR, Vol 77, No. 34]
Atlantic will restore the wetlands to preconstruction elevations and will re -vegetate
emergent, scrub -shrub and forested wetlands within the 75 -foot construction corridor. In
addition, Atlantic has placed the following additional protective language into the landowner
easement agreements on parcels which contain waters of the US that are being negotiated for the
pipeline project. This language has been reviewed and approved by Wilmington District.
`7f Local, State or Federally -regulated waters or wetlands (collectively and individually
"Regulated Waters or Wetlands') within the Permanent Easement or Temporary Easement are
disturbed by Grantee, Grantor acknowledges that Grantee may be required by law to restore
Atlantic Coast Pipeline 36 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
and/or re -vegetate any such disturbed Regulated Waters or Wetlands. Additionally, Grantor
agrees to: (a) cooperate with Grantee to ensure any such restored or re -vegetated Regulated
Waters or Wetlands are maintained as required by applicable laws; (b) notify Grantee
in advance of any proposed plans to disturb any Regulated Waters or Wetlands within the
Permanent Easement or Temporary Easement; and (c) notify Grantee of Grantor's efforts to
obtain any required permits, permit modifications and/or approvals, prior to conducting any
proposed disturbance of Regulated Waters or Wetlands within the Permanent Easement or
Temporary Easement. Grantor agrees that any permitting and/or disturbance of Regulated
Waters or Wetlands by Grantor within the Permanent Easement or Temporary Easement,
including any required mitigation and/or penalties, will be at Grantor's own risk and cost. "
FERC NEPA ALTERNATIVES ANALYSIS INFORMATION
For purposes of the USACE evaluation of single and complete projects, the "alternatives
analysis" is to ensure that the crossing of each wetland, stream and/or other waterbody is made in
a manner that avoids and minimizes impacts on the aquatic environment to the maximum extent
practicable, after considering the approach to the crossing in the uplands immediately adjacent to
the water of the United States. For example, to the extent practicable, crossings will be
perpendicular to the aquatic feature to minimize the length of the pipeline in the particular
aquatic system.
As background, information on the FERC alternatives analysis follows, including
discussion of the various alternatives FERC is considering. Within the sections below, the
numbering of many of the referenced tables and figures has not been changed from their
numbering in the FERC documentation, to maintain consistency across documents
(e.g., Table 10.8.1-1, Figure 10.8.1-1, etc.).Atlantic has identified and evaluated a number of
alternatives to the proposed ACP. These include a no -action alternative; alternative energy
sources, including traditional and renewable sources; energy conservation measures; systems
alternative; and conceptual collocation route alternatives.
2. a.2 NEPA Alternatives from FERC Documentation
No Action Alternative to the ACP
Under the no -action alternative, the ACP would not be built and the environmental
impacts associated with construction and operation of the proposed facilities would not occur.
By not constructing this Project, however, Atlantic would be unable to meet its existing
customers' demands for natural gas and the projected demand by other industrial, commercial,
and domestic customers (including power -generating facilities) in Virginia and North Carolina.
The projected demand is due to a combination of population growth and displacement of coal-
fired electric power generation. In addition, other benefits from the ACP, such as future
economic development opportunities, reduced energy costs in the region, and the repowering of
coal-fired electric generation to gas-fired electric generation, would not be realized.
Under the no -action alternative, other natural gas transmission companies could propose
to construct new facilities similar to the ACP to meet the demand for new natural gas
transportation service in Virginia and North Carolina. Such actions would likely result in
Atlantic Coast Pipeline 37 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
impacts similar to or greater than those associated with the ACP, and might not meet Atlantic's
objectives to satisfy demand from existing customers within the proposed time frames. For these
reasons, the no -action alternative is not practical and provides no advantage over the Project.
Alternative Energy Sources to the ACP
The use of alternative energy sources is an option to meet some of the short-term and
long-term demands for energy in the target market areas. Potential alternative energy sources to
natural gas include traditional fuels, such as coal and oil, nuclear energy, and electricity
(including electricity generated from oil, coal, and nuclear power); and renewable energy
sources, such as wind, solar, hydroelectric, biomass, and tidal and wave. Like the ACP, all of
these alternative energy sources, depending on the location of the source, would require new
infrastructure, including transmission facilities, to connect supply and demand areas. Additional
information regarding the analysis of alternative energy sources is available in Resource
Report 10, Alternatives, filled with FERC as part of the licensing documentation, which is
available through the FERC Project Docket (No. CP 15-554-000) to all cooperating agencies,
including the USACE.
Energy Conservation to the ACP
Energy conservation could help alleviate some of the growing demand for energy in the
United States and in the states/commonwealths to be serviced by the ACP. State/
commonwealth and federal energy conservation measures will likely play an important role in
slowing the growth of energy demand in the coming decades. However, it is unlikely that these
measures will offset the demand for new natural gas sources. The EIA predicts that United
States energy use per capita will decrease by approximately 8 percent through 2040, as higher
efficiency standards for vehicles and appliances take effect. Nevertheless, the EIA indicates that,
even with the recently enacted energy efficiency policies, total primary energy consumption,
including fuels used for electricity generation, will grow by 8.9 percent from 2013 to 2040. To
meet this demand, the EIA predicts that total domestic production of natural gas in the United
States will grow from 24.4 trillion cubic feet per year in 2013 to 35.5 trillion cubic feet per year
by 2040, and that shale gas production will make up 53 percent of total United States production
in 2040, up from 40 percent in 2012. The anticipated growth in natural gas demand will be
driven primarily by its increased use for electric power generation and industrial applications.
Reduction in the need for additional energy is the preferred option wherever possible.
Conservation of energy reduces the demand for limited existing reserves. Although energy
conservation measures will be important elements in addressing future energy demands, it is
unlikely that they will be able to offset more than a fraction of anticipated demand in the
foreseeable future. As a result, energy conservation alone (or in conjunction with other
alternatives) is not a viable alternative because it does not preclude the need for natural gas
infrastructure projects like the ACP to meet the growing demand for energy.
U.S. Energy Information Administration. 2015. Annual Energy Outlook 2015 with Projections to 2040. U.S. Department of Energy,
Washington, District of Columbia.
Atlantic Coast Pipeline 38 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
System Alternatives to the ACP
System alternatives would make use of other existing, modified, or proposed pipeline
systems to meet the same objectives as the ACP. Use of a system alternative would make it
unnecessary to construct all or part of the ACP, though modifications or additions to existing or
proposed systems could be required. The modifications or additions would result in
environmental impacts that could be less than, similar to, or greater than those associated with
the ACP.
Several existing, high-pressure, high-volume natural gas pipeline systems provide
transportation services to delivery points in the Mid -Atlantic and southeast regions. These
include Transco; Columbia Gas Transmission, LLC (Columbia); and East Tennessee Natural
Gas, LLC. Additionally, several new pipeline projects have been proposed to provide natural
gas transportation service in the same regions, including the Spectra Energy Carolina Pipeline
Project; Mountain Valley, LLC Mountain Valley Pipeline Project; and Transco Appalachian
Connector Pipeline Project. Significant modifications to each of these systems would be
necessary to access the same supply areas and/or provide transportation service to the same
customers or at the same delivery points as the ACP. The environmental impacts associated with
the upgrades and new pipeline construction modifying existing or proposed systems would likely
be equal to or greater than those of the ACP. Therefore, the theoretical modifications to the
existing systems or proposed systems would provide no environmental advantage over the ACP.
For this reason, and the fact that the existing system does not meet the ACP's purpose and need,
these system alternatives are not considered viable alternatives to ACP.
Conceptual Route Alternatives
Where practical, and depending on site-specific conditions, new natural gas transmission
pipelines can sometimes be collocated with existing linear corridor facilities (e.g., other
pipelines, electric transmission lines, highways, or railroads) to minimize impacts on
environmental and other resources. A pipeline is considered collocated with an existing linear
corridor facility if the new right-of-way for the pipeline is adjacent to or very near (within a few
hundred feet) of the existing facility. A pipeline can parallel an existing linear corridor facility
without being collocated with the existing facility, but this often results in multiple clear -cuts
along similar paths with no reduction in impacts on environmental and other resources.
The three criteria listed below are generally used to identify and evaluate opportunities to
route a new natural gas transmission pipeline adjacent to existing linear corridor facilities.
• The location and orientation of existing facilities relative to the new pipeline. The
existing facilities must provide a relatively direct path between the proposed
receipt and delivery points for the new pipeline. Otherwise, routing adjacent to
these existing facilities increases the length of the pipeline, which results in
greater environmental impact and added cost to the project.
• The nature of terrain along existing facilities. In some areas, the landforms
crossed may not allow for the construction of a pipeline adjacent to an existing
Atlantic Coast Pipeline 39 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
facility due to factors such as side slope, limitations on the amount of space
available for new construction, or the orientation of landforms crossed.
• The nature of land uses along the existing facilities. Developed lands (including
residential, commercial, and industrial lands) are often found along linear corridor
facilities such as highways and railroads. Routing a new pipeline to avoid these
developed areas often results in parallel (as opposed to adjacent) alignments and
increases the length (and therefore the environmental impact and cost) of a new
pipeline.
In addition to these conceptual alternatives, Atlantic evaluated potential collocation
alternatives for the ACP in areas where existing pipelines, electric transmission lines, or roads
either intersect or run parallel to and near the proposed ACP. Potential route alternatives and
variations adjacent to existing facilities which would meet the purpose and need of the ACP and
avoid or minimize impacts are discussed below. Desktop review of other potential collocation
route alternatives identified significant impediments with the routes with regard to terrain,
existing developments, or increased length of the ACP.
Eastern and Western Conceptual Route Alternatives
During the initial planning stages for the ACP, Atlantic identified and evaluated two
conceptual route alternatives: an eastern route alternative and a western route alternative
(Figure 10.8.1-1). Both routes originate south of Clarksburg in West Virginia and terminate near
Lumberton in North Carolina, with laterals extending to Hampton Roads in Virginia and Clayton
in North Carolina. Comparative information on each route is provided in Table 10-8.1-1.
The eastern route alternative, including the laterals, measures approximately 538.0 miles
in length, of which 22.6 miles is adjacent to existing linear corridor facilities. It crosses
approximately 66.4 miles of Federal lands, including lands managed by the U.S. Forest Service,
U.S. Fish and Wildlife Service (FWS), U.S. Army, and National Park Service. The eastern route
crosses both the Blue Ridge Parkway and Appalachian Trail on Federal lands. The route crosses
2.8 miles of state/commonwealth lands, 12.2 miles of conservation easements, 328 miles of
forested land, 60.6 miles of wetland, and 362 perennial waterbodies. It additionally crosses
13.5 miles of areas identified as historic properties, historic landscapes, or historic landmarks,
consisting mostly of Civil War battlefields.
The western route alternative, including the laterals, measures approximately 607.2 miles
in length, of which 16.8 miles is adjacent to existing linear corridor facilities. The route crosses
68.4 miles of Federal lands, including lands managed by the U.S. Forest Service, FWS, U.S.
Army, USACE, and National Park Service. Like the eastern route alternative, the western route
crosses both the Blue Ridge Parkway and Appalachian Trail on Federal lands. It crosses
7.0 miles of State/Commonwealth lands, 18.3 miles of conservation easements, 414.7 miles of
forested lands, 45.7 miles of wetland, and 425 perennial waterbodies. It also crosses 10.4 miles
of areas identified as historic properties, historic landscapes, or historic landmarks, mostly Civil
War battlefields.
Relative to the eastern route alternative, the western route alternative is approximately
69.2 miles longer and crosses 2.0 more miles of Federal lands, including lands managed by the
Atlantic Coast Pipeline 40 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification - Supplemental Information DRAFT
U.S. Army Corps of Engineers - Wilmington District
USACE, which the eastern route avoids. Both routes cross the Blue Ridge Parkway and
Appalachian Trail on Federal lands. The western alternative crosses 4.2 more miles of
State/Commonwealth land and 6.1 more miles of conservation easements than the eastern
alternative. The western alternative crosses 15.0 miles less of wetland and 3.1 miles less of
historic places, but 85.9 more miles of forested land and 63 more perennial waterbodies than the
eastern route.
TABLE 10.8.1-1
Eastern and Western Route Alternatives for the Atlantic Coast Pipeline
Features
Unit
Eastern Route'
Western Route
Length
miles
538.0
607.2
Primary U.S. or State/Commonwealth highways crossed
number
115
103
Adjacent to existing linear corridor facilities
miles
22.6
16.8
Federal lands crossed (total)
miles
66.4
68.4
National Park Service
miles
0.6
0.4
U.S. Forest Service
miles
46.9
44.0
U.S. Fish and Wildlife Service
miles
72
7.2
U.S. Army
miles
11.7
14.0
U.S. Army Corps of Engineers
miles
0.0
2.8
Blue Ridge Parkway crossings
number
1
1
Appalachian Trail crossings
number
1
1
State/Commonwealth lands crossed (total)
miles
2.8
7.0
West Virginia
miles
0.0
0.0
Virginia
miles
0.2
0.0
North Carolina
miles
2.6
7.0
Conservation easements crossed
miles
12.2
18.3
Forested lands crossed
miles
328.8
414.7
National Wetland Inventory wetlands crossed (total)
miles
60.7
45.7
Forested
miles
55.0
40.1
Emergent
miles
4.7
4.0
Other
miles
1.0
1.6
Intermittent waterbodies crossed
number
342
481
Perennial waterbodies crossed
number
362
425
Historic properties, historic landscapes, and historic landmarks crossed
miles
13.5
10.4
The eastern route alternate is similar, but not identical, to the baseline route for the ACP. The eastern route alternative was refined
into the baseline route based on customer needs and identification of delivery points for the ACP.
In addition, after the receipt and delivery points were confirmed for the ACP, it was
determined that the western route alternative does not provide a direct connection to the delivery
point in Randolph, County, West Virginia (i.e., the Long Run M&R Station), or to the receipt
and delivery point in Buckingham County, Virginia (i.e., Compressor Station 2). Additional
laterals would need to be built to reach these locations if the western route was selected as the
preferred alternative. Depending on the routes selected, these laterals would add an additional 75
to 85 miles of pipeline to the ACP, which would result in greater environmental impact and
additional cost.
For all these reasons, Atlantic identified the eastern route as the preferred alternative for
the ACP. This route subsequently was refined into the baseline route for the ACP.
Atlantic Coast Pipeline 41 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Southern Conceptual Route Alternative
The southern conceptual alternative route originates approximately at MP 6.0 of the
currently proposed AP -3 lateral route in Northampton County, North Carolina (see
Figure 10.8.1-20). From this point, the conceptual route heads due east for approximately
64 miles crossing Northampton, Hertford, Gates, Pasquotank, and Camden Counties, North
Carolina, passing south of the Great Dismal Swamp National Wildlife Refuge (GDS-NWR) and
Dismal Swamp State Park. The conceptual route then heads north for approximately 20 miles,
crossing Camden County, North Carolina and the City of Chesapeake, Virginia, passing east of
the GDS-NWR. The route terminates approximately at MP 79.2, on the east side of the Southern
Branch Elizabeth River. The conceptual route is approximately 13 miles longer than the
corresponding segment of the GDS 1 route.
Although the southern conceptual route alternative avoids the GDS-NWR, construction
along this route would result in an additional 13 miles of impacts, including crossings of many
miles of wetlands along the Chowen River, in the area south of the Dismal Swamp State Park,
and along the Pasquatank River. Based on National Wetlands Inventory data, the southern
conceptual route crosses approximately 30.6 miles of wetlands, while the corresponding segment
of the currently proposed route crosses approximately 20.1 miles of wetlands. The southern
conceptual route additionally crosses large blocks of land identified by The Nature Conservancy
(TNC) as sensitive floodplain forest in areas south and east of the GDS-NWR. Also, the
southern conceptual route alternative is almost entirely a greenfield corridor, as there are no
existing pipelines, electric transmission lines, railroads, or major roads to follow in the vicinity
of the route. By contrast, the corresponding segment of the proposed route is collocated with
existing linear corridor facilities for approximately 13 miles.
Because the southern conceptual route is longer and would result in greater impacts than
the currently proposed route, particularly to wetlands, the route is not considered a viable
alternative.
MAJOR ROUTE ALTERNATIVES
Atlantic identified initial or "baseline" routes for the proposed ACP and SHP pipelines
based on locations of receipt and delivery points, engineering and constructability criteria,
terrain, and existing land use. Atlantic subsequently evaluated environmental and other
constraints along each of the routes in an effort to refine the baseline configurations. Route
alternatives, variations, and minor adjustments were identified based on a review of desktop
constraint data, consultations and discussions with agency staff or other stakeholders, and field
review in an effort to optimize the routes. The objective of the process was to identify the
shortest possible route between the proposed receipt and delivery points taking into account the
ACP purpose and need, engineering constraints, crossings of public lands, issues identified by
stakeholders, and the potential for impacts on sensitive environmental resources. 8
a The mileposts depicted on the figures in this and subsequent sections of this document are based on three-dimensional modeling of the
proposed routes, which takes into account changes in elevation along the routes. As a result, the distance between two mileposts may be
Atlantic Coast Pipeline 42 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Atlantic Coast Pipeline 43 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
�. ry
1 O
U OA r
0
a
,Y ❑
CL 10 4C�
_�` �-,r-ti8t�,rr.;!ccy�--�jl_• .:a�' "1- � �✓ I CV � C
Q L
,
o
-h• ziz a LL O
e �
H
�i ti` °jdtrrgy Y o u
♦ `a �� F 0
♦ J O `y9'♦
♦ f..,
en ems, v_ �
N `
♦ v) ao ,..i{� 6. x `� - Ss we o
's, = L's Y � 'n ._c.�/`- ,C�C � o a
�j�a ♦ ' tl 1 O ���� � C07 r� � f
0
A N
Q ♦ 1`
Atlantic Coast Pipeline 44 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Atlantic's analysis of route alternatives and variations used a geographic information
system (GIS) to characterize crossings of environmental features and other constraints along the
routes. A digital centerline for each route alternative and the corresponding segment of the
baseline was compared with a variety of datasets and map resources in the GIS. Features and
constraints considered in the analysis included: length, public lands crossed, roads crossed,
conservation easements crossed, forested lands crossed (based on the National Land Cover
Database), wetlands crossed (based on the NWI), waterbodies crossed (based on the National
Hydrography Dataset), and known cultural resources sites crossed, such as Civil War
battlefields.
Once a baseline route was determined using desktop data, a field oriented routing team
consisting of a lead construction router, civil survey staff, and an ecological specialist adjusted
the route based on site-specific conditions while weighing competing constraints associated with
environmental, tribal, and historical resource protection, constructability, available technology,
and logistical constraints. Where practicable, adjustments to the route were made to avoid and/or
minimize impacts on wetlands and waterbodies.
Johnston County, North Carolina Major Route Alternative
Atlantic identified and evaluated an alternative route for the AP -2 mainline at the request
of the Johnston County, North Carolina Economic Development Authority in an effort to move
the pipeline closer to existing industrial properties along the I-95 corridor and U.S. Highway 701
south of the town of Four Oaks. The Johnston County Economic Development Authority would
like to introduce natural gas into the industrial park. The baseline route for the AP -2 mainline in
this area crosses Johnston County east of the towns of Smithfield and Four Oaks.
Beginning at MP 92.9 near Smithfield, the alternative route follows an existing electric
transmission line southwest of the baseline for approximately 7 miles to a point just south of
Four Oaks. The route then heads to the south-southwest for approximately 14 miles, where it
rejoins the baseline west of Jumping Run Swamp at MP 114.5. The baseline and Johnston
County route alternative are depicted on Figure 10.8.1-14, and comparative information on each
route is provided in Table 10.8.1-12.
TABLE 10.8.1-12
Johnston County Major Route Alternative for the Atlantic Coast Pipeline
Features
Unit
Baseline (Proposed) Route
Johnston County Route Alternative
Length (total)
miles
21.5
20.7
Primary U.S. or State highways crossed
number
7
7
Other State or local roads crossed
number
23
22
Adjacent to existing linear corridor facilities
miles
0.0
6.1
Federal lands crossed
miles
0.0
0.0
State lands crossed
miles
0.0
0.0
Conservation easements crossed
miles
0.0
0.0
Forested land crossed
miles
8.0
5.4
Wetlands crossed — forested/shrub
miles
2.5
0.7
Intermittent waterbodies crossed
number
33
28
Perennial waterbodies crossed
number
8
8
Bentonville Battlefield (total)
miles
0.1
0.2
Atlantic Coast Pipeline 45 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
1
ops r
I -
I -
e Fls>no,
t9.
I' gun
9
5,1—
Slnilhndd
�I
I�
`I1S Tu 1'
i
fl
Q
M
t
. Newlou '' 1
® Conservation Easement
NWI Wetland
_ j Existing Industrial Properties
OMiles 6•�:'/� �y
Man& N Baseline Atlantic Coast Pipeline
CAast N Johnston County Baseline Figure 10.8.1-14
PlpeUne •• N Johnston County Alternative Major Route Alternative
Johnston County
FILE. M 1ClientslD-F}DOM}SRPM ArcGIS}R-source R-podsiRR EP 10}Figuresl_ACP RR10 Johnston County.—d, REVISED'. O6f21 M15, SCALE= 1:200000 DRAL"JN BY. GIS
Atlantic Coast Pipeline 46 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
The Johnston County route alternative is approximately 4.0 miles closer to the town of
Four Oaks than the baseline. Consistent with this proximity, the proposed alternative route
crosses 239 parcels of property, compared to the baseline route which affects 163 parcels.
The alternative route is 0.8 mile shorter and crosses 2.6 fewer miles of forested lands and
1.8 fewer miles of forested wetland than the baseline. Of particular note, the alternative route
minimizes the crossing of a forested wetland complex adjacent to the Neuse River. Both routes
cross a portion of the Bentonville Battlefield area, though the alternative crosses 0.1 mile more
than the baseline. Both routes cross similar numbers of roads and waterbodies; however, the
alternative route would involve more difficult construction with regard to crossing existing
utilities.
As noted above, the alternative route is adjacent to an existing electric transmission line
for approximately 6.1 miles. The towers for the power line are anchored by guy wires, which
could require shifting the pipeline further away from the electric transmission line. This would
reduce the benefits of collocation, such as use of previously cleared areas for workspace or
temporary sidecast storage during construction.
Representatives of the Johnston County Economic Development Authority met with
Piedmont, the local distribution company and both a partner and customer of the ACP, to discuss
the natural gas supplies that will be provided by the Project. Based on this meeting, the Johnston
County Economic Development Authority stated that it is satisfied that the current proposed
route will support the County's interests in getting new supplies of natural gas to its targeted
industrial zones.
Balancing the various considerations presented, Atlantic retained the baseline route in
this area.
Progress Energy Carolinas Collocation Major Route Alternative
Atlantic evaluated an alternative for the AP -2 mainline route adjacent to an existing
Progress Energy Carolinas 500 kV electric transmission line in Cumberland County, North
Carolina. Atlantic worked closely with the Wilmington District to evaluate alternatives
associated with the Progress Energy Carolinas route alternative. During a meeting on January
28, 2016, Atlantic introduced the general concept of the route alternative that would increase
collocation, while potentially result in crossing of additional wetlands. On February 12, 2016
Atlantic provided the Wilmington District a map depicting the route alternative and included a
table comparing routing constraints, similar to the Table 10.8.1-13, below. Based on feedback
from the Wilmington District, as well as the preferred collocation and other routing constraints,
Atlantic adopted the route alternative as the proposed ACP route in this area.
The baseline route in this area extends to the south/southeast generally parallel to the I-95
corridor on the east side of Fayetteville. Starting approximately at MP 125.3 near an intersection
with I-95, the alternative route adjacent to Progress Energy Carolinas initially heads south for
approximately 8.1 miles to a point south of U.S. Highway 13. It then heads south for
approximately 17.3 miles, crossing Clinton Road, Cedar Creek Road, and Tabor Church Road.
The route then turns to the west for approximately 5.2 miles, crossing the Cape Fear River and
North Carolina State Highway 87, reconnecting with the baseline route at MP 157.5. The
Atlantic Coast Pipeline 47 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
baseline route and the Progress Energy Carolinas Major Route Alternative are depicted on
Figure 10.8.1-15, and comparative information on each route is provided in Table 10.8.1-13.
TABLE 10.8.1-13
Progress Energy Carolinas Collocation Major Route Alternative for the Atlantic Coast Pipeline
Baseline Progress Energy Carolinas
Features Unit Route Collocation Route Alternative
Length
miles
32.0
30.3
Primary U.S. or State highway crossed
number
12
9
Other State or local roads crossed
number
37
23
Adjacent to existing linear corridor facilities
miles
1.5
30.3
Federal lands crossed
miles
0.0
0.0
State lands crossed
miles
0.0
0.0
Private lands crossed
miles
32.0
30.3
Conservation easements crossed
miles
0.0
0.0
Forested uplands crossed (not including forested wetlands)
miles
6.1
1.1
Wetlands crossed — forested/shrub
miles
3.5
7.7
Wetlands crossed — freshwater emergent
miles
<0.1
0.2
Wetlands crossed — other
miles
0.1
0.1
Intermittent waterbodies crossed
number
14
5
Perennial waterbodies crossed
number
33
27
The baseline route is 1.7 miles longer than the alternative route. Both the baseline and
alternative avoid Federal and State lands, as well as conservation easements. The baseline route
crosses 15 more waterbodies than the route alternative, six of which are perennial waterbodies.
However, the alternative route crosses 4.3 more miles of wetland (an additional 24.8 acres), most
of which is forested wetland. Many of the wetland complexes along the alternative route are
large forested wetlands greater than 100 acres in size. Collocation of the AP -2 mainline with the
Progress Energy Carolinas line would cause significant additional impacts on these forested
wetland areas, as additional tree clearing along the maintained transmission line corridor would
be required to install the pipeline adjacent to the high-voltage electric transmission line.
Even though the Progress Energy Carolinas route alternative would be collocated with an
existing corridor, it would require substantially more disturbance and permanent clearing of
forested wetlands than the baseline route. For this reason, Atlantic retained the baseline route in
this area. 11,
Meherrin River Maior Route Alternative
In a letter dated September 8, 2014, and in a meeting on November 12, 2014, The Nature
Conservancy asked Atlantic to consider an alternative route for the proposed AP -3 lateral to
avoid or minimize crossings of the Meherrin River and Fountains Creek watersheds in
southeastern Virginia. These watersheds are part of TNC's Albemarle Sound Whole System
project area, which encompasses approximately 6 million acres of freshwater -dominated
estuarine habitat in southeastern Virginia and northeastern North Carolina. TNC states that the
Albemarle Sound System contains "areas of large intact wetland forest that support high levels of
use by migratory and breeding birds and buffer some of the best migratory fish spawning and
nursery habitats on the East Coast." TNC has worked with public agencies, corporations,
landowners, and communities to protect and restore public and private lands in this area.
Atlantic Coast Pipeline 48 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Atlantic Coast Pipeline 49 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Linden
2,
'11ron
Arm
11-ld Creek
Spring state Park
;,apeArmy Lake
hade
rp
P raq g
EYIovp.
1301-alle\
Doone
,Fayetteville 0
I
,,J
S t edinan
.14
parklon
PW
0 1 2 3
ONE
Man& ~ Baseline Atlantic Coast Pipeline
Coast IV Progress Energy Carolinas Baseline Figure 10.8.1-15
P rLojilrm Progress Energy Carolinas Route Major Route Alternative
Alternative Progress Energy Carolinas Collocation
,FILe 10,Figuml_ACP PEVIS£O 08126F,s"S. SC.LE 12-°0
Atlantic Coast Pipeline 50 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
The baseline route for the AP -3 lateral crosses floodplain forest in the Meherrin River
and Fountains Creek watersheds between MPs 0.0 and 12.0, including areas which TNC has
recommended for avoidance. Atlantic identified and evaluated a route alternative which avoids
Fountains Creek altogether and minimizes crossings of floodplain forest in areas recommended
by TNC for avoidance. The baseline route and Meherrin River Route Alternative are depicted on
Figure 10.8.1-16, and comparative information on each route is provided in Table 10.8.1-14.
TABLE 10.8.1-14
Meherrin River Major Route Alternative for the Atlantic Coast Pipeline
Baseline
Meherrin River Route
Features
Unit
Route
Alternative
Length
miles
14.7
16.8
Primary U.S. or State highway crossed
number
1
2
Other State or local roads crossed
number
20
19
Adjacent to existing linear corridor facilities
miles
0.0
6.8
Federal lands crossed
miles
0.0
0.0
State lands crossed
miles
0.0
<0.1
Private lands crossed
miles
14.7
16.8
Conservation easements crossed
miles
0.0
<0.1
Forested lands crossed
miles
3.6
3.5
Wetlands crossed — freshwater emergent
miles
0.0
0.3
Wetlands crossed — freshwater forested/shrub
miles
6.5
6.2
Wetlands crossed — other
miles
0.0
0.1
Intermittent waterbodies crossed
number
9
7
Perennial waterbodies crossed
number
13
14
TNC floodplain forest recommended for avoidance
miles
4.1
1.4
The baseline route for the AP -3 lateral trends southwest to northeast across Greensville
and Southampton Counties, Virginia, crossing Fountains Creek approximately 4.7 miles from the
AP -1 mainline and the Meherrin River just north of Haley's Bridge approximately 8.4 miles
from the AP -1 mainline. Starting at Compressor Station 3, the Meherrin River Route Alternative
initially extends to the east-southeast for approximately 5.8 miles across Southampton County,
North Carolina, passing south of the Fountains Creek watershed. It then heads to the northeast
for approximately 7.6 miles, mostly adjacent to existing power lines, roads, or railroads. It
crosses the Meherrin River along the Virginia Commonwealth/North Carolina State line adjacent
to an existing railroad. The alternative route then heads north-northeast for approximately
3.4 miles, where it intersects the baseline route in Southampton County, Virginia.
Atlantic Coast Pipeline 51 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
t� 1
�mPton•PkyP
v
SUS g�.8
�1
�a5 .
ti
r
t — �
- - - - -N(,I, l it [', ROLINA - - - -
Pleasant r 4r tob to 096 1 J10
Hill f .r r �'/Zuelts}t'ie
ll
go
a? m 4* i 40
seaboard
J2 m
® Conservation Easement
The Nature Conservancy Abermarle _ _ °'t
Floodplain Forest (Recommended
Avoidance Area)
0 1 2
0 Miles
/V Baseline Atlantic Coast Pipeline
Meherrin River Baseline Figure 10.8.1-16
Meherrin River Route Alternative Major Route Alternatives.
Meherrin River
RILE: M:\CllentslD+OQM1SRM Arc✓ ISkResource_ReportslRREP 101riguresl_ACP RR10_Meherrin.mxd, REVISED: 09!0912016, SCALE: 1:150,006 OR SY: JSSuess
Atlantic Coast Pipeline 52 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification - Supplemental Information DRAFT
U.S. Army Corps of Engineers - Wilmington District
The Meherrin River Route Alternative is 2.1 miles longer than the baseline, but avoids
Fountains Creek and crosses 2.7 miles less of floodplain forest areas recommended for avoidance
by TNC. About 70 percent (1.0 mile) of the floodplain forest along the alternative route occurs
at the Meherrin River crossing, which is adjacent to an existing railroad. This will minimize
impacts in the watershed due to forest fragmentation. The alternative route additionally is
adjacent to existing linear corridor facilities (power lines and roads) for approximately 6.8 miles
(40 percent) compared to 0.0 miles for the baseline. The baseline avoids conservation
easements, while the alternative route crosses within less than 0.1 mile of a North Carolina
Department of Environmental Quality conservation easement. 9 Crossings of forested lands,
wetlands, and waterbodies are similar for both routes.
Based on the feasibility of collocation with other utility corridors in this area, and the
relative similarity of the impact on other major resource considerations, Atlantic incorporated the
Meherrin River Route Alternative into the proposed route.
Northampton Major Route Alternative
Atlantic identified and evaluated two major route alternatives (Northampton 1 and
Northampton 2) at the beginning of the AP -3 lateral in Northampton County, North Carolina,
portions of which parallel an existing DVP 115 kV electric transmission line. Northampton 1
initially follows the proposed AP -2 mainline south of Compressor Station 3 for approximately
4.3 miles, and then follows the existing electric transmission line for about 7.8 miles to the
northeast. Northampton 2 would require moving Compressor Station 3 from its current proposed
site to a new location in Northampton County near MP 4.3 of the AP -2 mainline, and then follow
the existing electric transmission line from this new site for about 7.8 miles to the northeast. The
baseline and alternative routes are depicted on Figure 10.8.1-17, and comparative information on
each route is provided in Table 10.8.1-15.
TABLE 10.8.1-15
Northampton Major Route Alternative for the Atlantic Coast Pipeline
Baseline
Northampton 1 Route
Northampton 2 Route
Features
Unit
Route
Alternative
Alternative
Length
miles
6.1
12.1
7.8
Primary U.S. or Statee highway crossed
number
0
0
0
Other State or local roads crossed
number
7
14
4
Adjacent to existing linear corridor facilities
miles
0.0
7.8
7.8
Adjacent to proposed linear corridor facilities
miles
0.0
4.2
0.0
Federal lands crossed
miles
0.0
0.0
0.0
State lands crossed
miles
0.0
0.0
0.0
Conservation easements crossed
miles
0.0
0.0
0.0
Forested lands crossed
miles
2.6
5.5
1.4
Wetlands crossed - freshwater emergent
miles
0.0
0.1
0.1
Wetlands crossed - freshwater forested/shrub
miles
0.9
1.2
0.8
Intermittent waterbodies crossed
number
4
6
3
Perennial waterbodies crossed
number
1
3
2
TNC floodplain forest recommended for avoidance
miles
0.3
0.5
0.0
9 Atlantic is current evaluating route variations to avoid this easement.
Atlantic Coast Pipeline 53 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Pleasant
Hili
. 41
seaboard
Conceptual Compressor Station 3 Location
for Northampton Route Alternative 2
VF- The Nature Conservancy Abormarlo
Floodplain Forest (Recommended
Avoidance Area)
0 1 2 w 7
/�✓ Baseline Atlantic Coast Pipeline
Man&r4orthampton Baseine Figure 10.8.1-17
')*UCqaA Northampton Route Afternative I Major Route Alternatives
rm NortnrrptDn Route AMmative 2 Northampton
FILE: M kC1jenWD-hDOW5RP Ft_ArcGISXRe source_ Re portskR R EP_1 OVIgu res4_ACP _R R 1 U_Northampton_M ajor_ RA.mxd, REVISED'0812812015, SCALE:1:70,000 DRAWN BY: TH.h,
Atlantic Coast Pipeline 54 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
At 6.1 miles in length, the baseline is the shortest of the three routes, though none of the
baseline is adjacent to existing linear corridor facilities. The baseline crosses four waterbodies,
including two perennial waterbodies, 0.9 mile of wetlands, and 2.6 miles of forested land. The
baseline additionally crosses 0.3 mile of floodplain forest areas identified by TNC, mostly along
Jacks Swamp. It avoids crossings of State lands and conservation easements.
At 12.1 miles in length, Northampton 1 is 6.0 miles longer than the baseline. About
4.2 miles of the route is adjacent to the proposed AP -2 mainline and 7.8 miles is adjacent to the
existing electric transmission line. The route crosses five waterbodies, including three perennial
waterbodies, 1.3 miles of wetlands, and 5.5 miles of forested land. Of these, one perennial and
three intermittent waterbodies, 0.4 mile of wetlands, and 4.1 miles of forested land are adjacent
to the AP -2 mainline; the remainder are along the existing electric transmission line. The route
alternative crosses 0.5 mile of floodplain forest areas identified by TNC along Jacks Swamp (all
adjacent to the AP -2 mainline). Like the baseline, the alternative route avoids State lands and
conservation easements.
In a letter filed with the Commission, the North Carolina Wildlife Resources Commission
suggested avoiding crossings of Cypress Creek by shifting the route for the AP -3 lateral farther
to the north. The proposed route for the AP -3 lateral crosses Cypress Creek at four locations.
These crossings resulted from the Meherrin River Major Route Alternative (see
Section 10.8.1.13 above), which was designed to avoid sensitive floodplain forest areas along the
Meherrin River and Fountains Creek. Relative to the baseline, Northampton I would result in
one additional crossing of Cypress Creek in addition to a crossing of a tributary (Ivy Creek)
approximately at its confluence with Cypress Creek at Jordan's Mill Pond. The baseline route
avoids both Ivy Creek and Jordan's Mill Pond.
Relative to the baseline, Northampton 1 is longer and crosses more waterbodies and more
miles of wetlands, forested land, and floodplain forest areas than the baseline (though some of
the crossings occur along the segment of the route alternative adjacent to the AP -2 mainline).
The alternative route additionally adds a crossing of Cypress Creek and a tributary relative to the
baseline. For all these reasons, Northampton 1 provides no environmental advantage over the
ACP as proposed.
As noted above, Northampton 2 would require moving the location of Compressor
Station 3 to a new site. This would require 4.3 miles of AP -2 to be upsized to 42 -inch -diameter
pipeline and an additional 2.0 miles in the length of the AP -3 lateral. These modifications could
require changes in the location or configuration of other aboveground facilities for the Project.
Additionally, the new site would be in actively cultivated farmland, which would require a
permanent conversion of farmland to developed land. In contrast, the proposed site is located on
recently replanted commercial timber land. Atlantic additionally notes that the landowner of the
preferred site has indicated a willingness to sell the property as evidenced by the execution of an
option agreement for the property.
At 7.8 miles in length, Northampton 2 is 1.7 miles longer than the baseline, though the
entire route is adjacent to the existing electric transmission line. Northampton 2 crosses five
waterbodies, including two perennial waterbodies, 0.8 mile of wetlands, and 1.4 miles of forested
land, all of which are similar to the baseline. The route avoids floodplain forest areas identified
Atlantic Coast Pipeline 55 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
by TNC, but requires an additional crossing of Cypress Creek and a tributary (Ivy Creek)
approximately at its confluence with Cypress Creek at Jordan's Mill Pond. The baseline route
avoids both Ivy Creek and Jordan's Mill Pond. Like the baseline and Northampton 1,
Northampton 2 avoids State lands and conservation easements.
Relative to the baseline, Northampton 2 is longer, crosses one additional perennial
waterbody, and results in an additional crossing of Cypress Creek and a tributary. Northampton
2 would require moving Compressor Station 3 to a new site, which would require approximately
4.3 miles of AP -2 to be upsized to 42 -inch -diameter pipeline and increase the length of the AP -3
lateral by about 2.0 miles. These changes in the configuration of the ACP potentially could
require changes in the location or configuration of other aboveground facilities. Additionally,
the new site for the compressor station would permanently encumber actively cultivated areas,
whereas the proposed site is located in a commercial timbering area. For all these reasons,
Northampton 2 provides no environmental advantage over the ACP as proposed.
Based on the above analysis and discussion, Atlantic retained the baseline route in this
area.
ROUTE VARIATIONS IN NORTH CAROLINA
Atlantic identified and evaluated a number of route variations designed to avoid or
minimize impacts on geographically distinct and localized resources, such as conservation
easements, cultural resource sites, and wetlands. Route variations were also considered to
resolve engineering or constructability issues or address stakeholder concerns, where feasible.
The route variations measured between approximately one and five miles in length and passed
within a couple miles of the baseline route. The primary criterion for comparing route variations
to the baseline route was cumulative impact avoidance relative to the objective of the route
variation. Similar to the major route alternatives described above, if a route variation was
adopted, it became part of the proposed route and the corresponding segment of the baseline
route was rejected. Descriptions of each route variation are provided in the subsections below.
Geenex Route Variation
Atlantic identified and evaluated a route variation approximately between MPs 4.3 and
7.5 of the AP -2 mainline in Northampton County, North Carolina, to avoid a property with the
option site of a future solar power generation development (see Figure 10.9.1.11 and
Table 10.9.1.11). Relative to the baseline route, the Geenex Route Variation heads southwest
from Cornwallis Road, then heads south and crosses Highway 301 where it rejoins the baseline
east of Garysburg, North Carolina. The Geenex route variation is 0.9 mile longer than the
baseline, but it avoids the option site for the future solar development. The route variation
additionally reduces wetland impacts by 0.3 mile and avoids five intermittent waterbody
crossings, but it increases crossings of forested land by 0.4 mile. Atlantic incorporated the
Geenex Route Variation into the proposed route because it avoids the option site for the future
solar development and reduces wetland and waterbody impacts.
Atlantic Coast Pipeline 56 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
NHD FlDvAre
NVVI Wetland
0 0.1 0.2
v.
Adindc
N Baseline
Atlantic Coast Pipeline
CJOCIA
Geenex Baseline
Figure 10.'9.1-11
pipeline
Geenex Roe Variation
d
Geenex
Route Variation
FILE: M:kCii.ntST-FSDOMlSRPPl_AMGISlResource—ReportslRREP_101Figuresl_ACP _RR10._Geenex
RV...d, REVISED 00124J2015, SCALE: 1Q5,000 DRAWN BY. JSS.ess
Atlantic Coast Pipeline 57 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification - Supplemental Information DRAFT
U.S. Army Corps of Engineers - Wilmington District
TABLE 10.9.1-11
Geenex Route Variation for the Atlantic Coast Pipeline
Features
Unit
Baseline Route
Geenex Route Variation (Proposed)
Length
miles
2.6
3.5
Roads crossed
number
7
5
Adjacent to existing linear corridor facilities
miles
0.0
0.0
Federal lands crossed
miles
0.0
0.0
State lands crossed
miles
0.0
0.0
Private lands crossed
miles
2.6
3.5
Conservation easements crossed
miles
0.0
0.0
Forested land crossed
miles
0.5
0.9
Wetlands crossed - freshwater forested/shrub
miles
0.3
0.0
Intermittent waterbodies crossed
number
5
0
Perennial waterbodies crossed
number
0
0
Mush Island Route Variation
Atlantic identified a route variation between MPs 11.1 and 12.5 of the AP -2 mainline
route in Halifax County, North Carolina to avoid a conservation easement enrolled in the U.S.
Department of Agriculture's Natural Resources Conservation Service's (MRCS) Wetland
Reserve Program (see Figure 10.9.1-12 and Table 10.9.1-12). Relative to the baseline route, the
Mush Island Route Variation initially extends to the southwest of the baseline route for
approximately 0.7 mile, and then turns due south for another 0.7 mile back to the baseline. The
route variation is approximately 0.2 mile longer than the baseline route, but it avoids the
conservation easement. The route variation additionally crosses approximately 0.6 mile more of
forested land, 0.2 more mile of wetland, and one more intermittent waterbody. Because it avoids
the conservation easement, however, Atlantic incorporated the Mush Island Route Variation into
the proposed route.
TABLE 10.9.1-12
Mush Island Route Variation for the Atlantic Coast Pipeline
Features
Unit
Baseline Route
Mush Island Variation (Proposed)
Length
miles
1.2
1.4
Roads crossed
number
1
1
Adjacent to existing linear corridor facilities
miles
0.0
0.0
Federal lands crossed
miles
0.0
0.0
State lands crossed
miles
0.0
0.0
Private lands crossed
miles
1.2
1.4
Conservation easements crossed
miles
0.1
0.0
Forested land crossed
miles
0.4
1.0
Wetlands crossed - freshwater forested/shrub
miles
0.2
0.4
Intermittent waterbodies crossed
miles
0.0
<0.1
Perennial waterbodies crossed
number
1
2
Cumberland Church Battlefield study area
number
1
1
Atlantic Coast Pipeline 58 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
• 90
i .
• 99.9
w ;��ry•
AR
�C" •i�!``� �•'Z! ilii••«
• O lam
ts•® ♦•die
y�;►y�'Q, �.g4gi�q/i!`°v�"�iv�i�i�l�lla
c► c� �•aa••l•i•1•!i!
b'q��y �h04s�*iq!!!illiifglq!!!q!q!
!i« a♦illtili!
S�ii•� . �iiiiiglgii•qi i�.�
+al+ `ii!••li0iq
«®.� �t, ilii.•
«l«« '►e�iililii�.
y4�1� i4t!
i•y
:gi`.glq.
. �i•qi®ii ~I
.♦!ii
�1< ►►iiil�� s� 1
3. �'Ri ,��i��1�r' 1'rili�`a► o�i� �i
Baseline•Pipeline
• 1
• - -_ Mush Island Route Variation• Route•
0• DRAWN
Atlantic Coast Pipeline 59 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification - Supplemental Information DRAFT
U.S. Army Corps of Engineers - Wilmington District
Halifax Route Variation
Atlantic evaluated a route variation (the Halifax Route Variation) approximately between
MPs 19.1 and 21.1 of the AP -2 mainline in Halifax County, North Carolina, in an effort to
reduce crossings of forested land (see Figure 10.9.1-13 and Table 10.9.1-13). Starting about
0.3 mile east of Grapevine Road, the Halifax Route Variation initially heads south for l.1 miles,
crossing State Route 561. It then heads west for 1.2 miles, crossing Marsh Swamp, and
terminating at the baseline just west of Justice Branch Road. The route variation reduces
crossings of forested land by 0.2 mile and wetlands by 0.1 mile, but is 0.4 mile longer and
crosses one more waterbody and one more road than the baseline. Because potential impacts for
both routes are similar, the route variation provides no environmental advantage over the
baseline. Therefore, Atlantic retained the baseline as the proposed route in this area.
TABLE 10.9.1-13
Halifax Route Variation for the Atlantic Coast Pipeline
Features
Unit
Baseline Route
Halifax Route Variation
Length
miles
1.9
2.3
Roads crossed
number
2
3
Adjacent to existing linear corridor facilities
miles
0.0
0.0
Federal lands crossed
miles
0.0
0.0
State lands crossed
miles
0.0
0.0
Private lands crossed
miles
1.9
2.3
Conservation easements crossed
miles
0.0
0.0
Forested land crossed
miles
0.7
0.5
Wetlands crossed - freshwater forested/shrub
miles
0.3
0.2
Intermittent waterbodies crossed
number
1
2
Perennial waterbodies crossed
number
1
1
Battlefield study areas
miles
0.0
0.0
Breeches Swamp Route Variation
Atlantic identified a route variation between MPs 28.3 and 30.4 of the AP -2 mainline
route in Halifax County, North Carolina to avoid two conservation easements enrolled in the
NRCS's Conservation Reserve Program (see Figure 10.9.1-14 and Table 10.9.1-14). Starting at
a point just south of Ringwood Road, the Breeches Swamp Route Variation extends west of the
baseline route for approximately 0.7 mile, crossing I-95. It then heads due south for
approximately 1.4 miles parallel to and west of I-95, rejoining the baseline route approximately
0.3 mile south of Sneed Road. The route variation is approximately 0.2 mile longer than the
baseline route and crosses approximately 0.1 more mile of wetland, but it avoids the
conservation easements, crosses 0.1 mile less of forested land, and crosses one less intermittent
waterbody. For these reasons, Atlantic incorporated the Breeches Swamp Route Variation into
the proposed route.
Atlantic Coast Pipeline 60 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
42,r,
` I Alen IJ'v- G1
1 Glove
Baseline Atlantic Coast Pipeline
N Halifax Baseline Figure 10.9.9-13
Pi a ine g Route Variation
p N Halifax Route Variation Halifax
FILE: M: Clients%O-FVQ WSR PPI ArcGIS%Resour ReportsXRRE P_1 OWiip-re ACP RR70 Halifax RV.mxd, REVISED: 0612472015, SCALE 1:15,000 DRAWN SY.THohn
Atlantic Coast Pipeline 61 DRAFT
N
0
0.25
os
Miles
Baseline Atlantic Coast Pipeline
N Halifax Baseline Figure 10.9.9-13
Pi a ine g Route Variation
p N Halifax Route Variation Halifax
FILE: M: Clients%O-FVQ WSR PPI ArcGIS%Resour ReportsXRRE P_1 OWiip-re ACP RR70 Halifax RV.mxd, REVISED: 0612472015, SCALE 1:15,000 DRAWN SY.THohn
Atlantic Coast Pipeline 61 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
0� �i. xe.uW � 4 ��'�oJ j`�`• � rasp ._ --�� _
l/ ti ae
a3s.s4
/-� i._J/ ��J `y � >" ___\_IS—S a�•p-�` = "���5 �
skin! 1Q • ! ! l -� � /
1794 • f- "+ •, u, .
r
x9v 4.
15
-:� .,. .^'��/gyp � • , ! !"��// ---- -�
m 15
X172 A' -
^'
Xf 124 \ l�
• \ r C lv!
,.� S rte' 1 •/' � :16—�"�—"� -- - >;--i __ � 'aa
JAY
t72x
�'s• 111 V `
Op
ight
r r (
IS
ie \` 4� _.I Y V`b I f • Ym_ g i ` y*
Conservation Easement ,n•� �� ;. 1v *� N
NWI Wetland '4
0 0. 1 �) d
'
Miles + / 40
Atlantic IV Baseline Atlantic Coast Pipeline
apst ~ Breeches Swamp Baseline Figure 10.9.1-14
Pine .. ♦'►i Breeches swamp Route Variation Breeches Swamp Route Variation
FILE, WC1ianls1D-F%DOWSRPP1 Ar,GIS%Re urea Ra rWRREP 101Fiaure 1 ACP RR10 RA Man Sg mxd. REVISED, 080412015_ SCALE124.000 DRAWN By GIS
Atlantic Coast Pipeline 62 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification - Supplemental Information DRAFT
U.S. Army Corps of Engineers - Wilmington District
TABLE 10.9.1-14
Breeches Swamp Route Variation for the Atlantic Coast Pipeline
Features
Unit
Baseline Route
Breeches Swamp Route Variation (Proposed)
Length
miles
1.9
2.1
Roads crossed
number
4
6
Adjacent to existing linear corridor facilities
miles
0.0
0.0
Federal lands crossed
miles
0.0
0.0
State lands crossed
miles
0.0
0.0
Private lands crossed
miles
1.9
2.1
Conservation easements crossed
miles
0.1
0.0
Forested land crossed
miles
0.4
0.3
Wetlands crossed - freshwater forested/shrub
miles
0.1
0.2
Intermittent waterbodies crossed
number
3
2
Perennial waterbodies crossed
number
1
1
Red Oak Route Variation
Atlantic identified a route variation (Red Oak 1) between MPs 42.5 and 45.9 of the AP -2
mainline route in Nash County, North Carolina, to avoid a former landfill (see Figure 10.9.1-15
and Table 10.9.1-15). Starting north of the town of Red Oak, Red Oak 1 initially heads southeast
for approximately 1.0 mile, and then turns south for approximately 1.5 miles, passing east of an
existing subdivision along Flat Rock Road and Red Oak Battleboro Drive. The route then heads
west for approximately 0.6 mile, rejoining the baseline at a point just north of Big Jim Road.
Atlantic Coast Pipeline 63 DRAFT
TABLE 10.9.1-15
Red Oak Route Variation for the Atlantic Coast Pipeline
Features
Unit
Baseline Route
Red Oak 1 Route Variation
Red Oak 2 Route Variation
Length
miles
2.2
3.2
3.4
Roads crossed
number
4
5
5
Adjacent to existing linear corridor
miles
0.0
0.0
0.0
facilities
Federal lands crossed
miles
0.0
0.0
0.0
State lands crossed
miles
0.0
0.0
0.0
Private lands crossed
miles
2.2
3.2
3.4
Conservation easements crossed
miles
<0.1
<0.1
0.0
Forested land crossed
miles
1.0
1.2
1.2
Wetlands crossed - forested/shrub
miles
0.2
0.2
0.2
Intermittent waterbodies crossed
number
3
4
3
Perennial waterbodies crossed
number
1
3
3
Historic landfill area
miles
0.1
0.0
0.0
Atlantic Coast Pipeline 63 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
67m
42
CO
Red 0A,
40
41
iti
or I k I I
Conservation Easement
Landfill
NWI Weiland
0 05 1
Miles
/SV Baseline
Aflandic Atlantic Coast Pipeline
cmist Red Oak Baseline Figure 10.9.1-15
P i rp x A..; n e Red Oak Route Variation 1 Red Oak Route Variation
Red Oak Route Variation 2
11FILLM:IGlienlsO-roOWSRP�l AroGISlRescume_ReportsIRREP_lOTigumsl_ACP_RRiC_Reid Oak.mxd, REVISED, 0812412015, SCALEA:XODD DRAv'dN BY
Atlantic Coast Pipeline 64 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Red Oak 1 avoids an approximately 0.1 mile long crossing of the Red Oak Landfill,
which operated from 1969 to 1977. The North Carolina Department of Environmental Quality
reported the one-time disposal of 135 pounds of pesticides and a three-year weekly disposal of
waste rags containing the solvent methyl isobutyl ketone at the landfill. Red Oak 1 is
approximately 1.1 mile longer than the baseline, but avoids the former landfill. Crossings of
other features are similar or identical for the two routes. In light of the avoidance of the former
landfill, and the similar impact on other major resource considerations, Atlantic initially
incorporated the Red Oak 1 Route Variation into the proposed route.
Subsequent to incorporation of the Red Oak 1 Route Variation, and based on the results
of civil surveys, Atlantic optimized Red Oak 1 into Red Oak 2. The optimized route is similar to
Red Oak 1, but it improves the crossing angle of Flat Rock Branch and also avoids paralleling
this creek. In addition, Red Oak 2 avoids an existing conservation easement, which is crossed by
both the baseline and Red Oak 1. Like Red Oak 1, Red Oak 2 avoids the former landfill. Other
environmental impacts are similar to the baseline and Red Oak 1. Therefore, Atlantic
incorporated the Red Oak 2 Route Variation into the proposed route.
Citv of Nashville Route Variation
Atlantic identified and evaluated a route variation for the AP -2 mainline route at the
request of the City of Nashville, in an effort to avoid the proposed route running between two
existing subdivisions on the south side of Oak Level Road (see Figure 10.9.1-16 and
Table 10.9.1-16). Starting at MP 50.3, the route variation initially heads south for approximately
1.5 miles, passing east of these subdivisions and crossing East Old Springs Hope and Oak Level
Roads. It then heads southwest for 2.2 miles, crossing North Carolina State Road 58, and
intersecting the baseline at MP 53.3. The City of Nashville Route Variation is approximately
0.7 mile longer than the baseline. It crosses 0.8 mile more of forested land, but 0.2 mile less of
forested wetland. While the route variation avoids the subdivisions west of East Old Spring
Hope Roads, it crosses between other subdivisions along Oak Level Road and Sherrod Road.
For these reasons, Atlantic retained the baseline route in this area.
TABLE 10.9.1-16
City of Nashville Route Variation for the Atlantic Coast Pipeline
City of Nashville Route
Features
Unit
Baseline Route
Variation
Length
miles
3.0
3.7
Roads crossed
number
4
5
Adjacent to existing linear corridor facilities
miles
0.0
0.0
Federal lands crossed
miles
0.0
0.0
State lands crossed
miles
0.0
0.0
Private lands crossed
miles
3.0
3.7
Conservation easements crossed
miles
0.0
0.0
Forested land crossed
miles
0.5
1.3
Wetlands crossed — freshwater forested/shrub
miles
0.3
0.1
Intermittent waterbodies crossed
number
2
1
Perennial waterbodies crossed
number
0
1
Atlantic Coast Pipeline 65 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
r
ir
i
Forest hilt
Cemetery
Nashvi lie
f!y 5�7 F)Fd
t1S =fi#'
F
454 rn,vFcvl Sr
U err
2 .67m t3rr•:tr"',
Z SJ
�irclvivood
courtry Auto
Q, u• r
NO fives.
F:35tr:rn Ave
i�oce
..PS 0 1
y tanbark 01
1 �l3 . �J°er,.ga Irl
M
Em
Atlantic Coast Pipeline 66 DRAFT
.y�r,ir. AJ
Conservation Easement
H
NO Wetland
�qti
a fly
1
Miles
7•
aunt
N Baseline
Atlantic Coast Pipeline
Coast
/�/ City of Nashville Baseline
Figure 10.9.1-16
Pi.,Aj e
,
/v City of Nashville Route
City of Nashville
Route Variation
{ �
Varlatican
FILE: M,lClients'0.F10OWSRPP1_AreGISTesmume_Reports%RREP_t
BSFiguresl_ACP_ RRIO_CitynNashAlle.m><d, REVISED: 0012412015. SCALE: 1:38,202
DRA' AN BY. GIS
Atlantic Coast Pipeline 66 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification - Supplemental Information DRAFT
U.S. Army Corps of Engineers - Wilmington District
Little River Route Variation
In response to a meeting with the FWS and North Carolina Wildlife Resources
Commission, Atlantic identified the Little River Route Variation in Johnston County, North
Carolina (see Figure 10.9.1-17 and Table 10.9.1-17). Starting at MP 82.3, the route variation
heads to the southwest, crossing Little River, and passing south of Buffalo Creek before
terminating at MP 83.8. The route variation avoids Buffalo Creek, reduces crossings of wetlands
by 0.6 mile, reduces crossings of forested land by 0.4 mile, and is 0.2 mile shorter than the
baseline route. Atlantic incorporated the Little River Route Variation into the proposed route.
TABLE 10.9.1-17
Little River Route Variation for the Atlantic Coast Pipeline
Features
Unit
Baseline Route
Little River Route Variation
Length
miles
1.5
1.3
Roads crossed
number
1
1
Adjacent to existing linear corridor facilities
miles
0.0
0.0
Federal lands crossed
miles
0.0
0.0
State lands crossed
miles
0.0
0.0
Private lands crossed
miles
1.5
1.3
Conservation easements crossed
miles
0.0
0.0
Forested land crossed
miles
1.3
.9
Wetlands crossed - freshwater forested/shrub
miles
0.9
0.3
Intermittent waterbodies crossed
number
0
0
Perennial waterbodies crossed
number
2
1
Swamp Road Route Variation
Atlantic identified a route variation between MPs 131.3 and 134.1 of the AP -2 mainline
route in Cumberland County, North Carolina to minimize crossings of forested wetland (see
Figure 10.9.1-18 and Table 10.9.1-18). Swamp Road Route Variation 1 generally parallels the
initial baseline route beginning at a point just north of River Road and extending 2.7 miles south-
southwest to Rick Walker Road. It passes east of a forested wetland near MP 131.1 and west of
a forested wetland near MP 132.0. It crosses 0.8 mile less of forested wetland, 0.6 mile less of
forested land, and three fewer perennial waterbodies than the baseline route. However, Swamp
Road Route Variation 1 reduced collocation with existing linear corridors by 0.7 mile.
Subsequent to evaluating Swamp Road Route Variation 1, Atlantic identified the Swamp
Road Route Variation 2 to avoid a planned housing development and to collocate the route with
an existing Piedmont natural gas pipeline. The route variation is 0.1 mile longer than the
baseline and Swamp Road Route Variation 1, but it is further away from a residence, avoids an
area for a planned housing development, and is collocated with an existing Piedmont pipeline for
0.6 mile. It also reduces wetland impacts by 0.4 mile compared to the baseline route (though it
would have greater impact than Swamp Road Route Variation 1). For all these reasons, Atlantic
incorporated Swamp Road Route Variation 2 into the proposed route.
Atlantic Coast Pipeline 67 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
U � _
I
r
57 m
a;G
Buffalo Creek
Ohy T-
N
fOf NHD Flowline
NWI Weiland
0 0.1 0.2
0 Miles
Awn *OV Baseline Atlantic Coast Pipeline
Coast /\VLittle River Baseline Figure 10.9.1-17
plpeUne l_ Little River Route Variation Little River GO
Route Variation
FILE: M:\ClientslD-MDOMISRPPI_AreGiMesource_Reports%RREP_%Figuresl_ACP_RR70_Little_River _RV.mxd, REVISED: 0012512015, SCALE:1:15,000 DRAWN BY: issues$
Atlantic Coast Pipeline 68 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
IIR
Waft
i I
r ;04
-
"�
Conservation Easement
t° NWI Wetland
- r/kms :N;an se iS -- y
P-
FAHes
1
Baseline
Allank Swamp Road Baseline Atlantic Coast Pipeline
coaA INV Stump Road Route Variation 1 Figure 10.9.1-18
PipeUne _ Swamp Road Route Variation
41� SLvamp Road Route' Variation 2
FILE: M:1Client3W-F%DOMlSRPPt Are6151Resaume_ReponORREP_10%Fi real ACP RR10 RA Map_Set.mxd. REV14SEO: 0812512015. SCALE: 4:40,000 DRAM BY GIS
Atlantic Coast Pipeline 69 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification - Supplemental Information DRAFT
U.S. Army Corps of Engineers - Wilmington District
TABLE 10.9.1-18
Swamp Road Route Variations for the Atlantic Coast Pipeline
Baseline
Swamp Road Route
Swamp Road
Features
Unit
Route
Variation 1
Route Variation 2
Length
miles
2.7
2.7
2.8
Roads crossed
number
3
2
2
Adjacent to existing linear corridor facilities
miles
0.7
0.0
0.6
Federal lands crossed
miles
0.0
0.0
0.0
State lands crossed
miles
0.0
0.0
0.0
Private lands crossed
miles
2.7
2.7
2.7
Conservation easements crossed
miles
0.0
0.0
0.0
Forested land crossed
miles
1.4
0.8
1.2
Wetlands crossed - freshwater forested/shrub
miles
0.9
0.1
0.5
Intermittent waterbodies crossed
number
2
2
2
Perennial waterbodies crossed
number
4
1
3
Cane Fear Route Variation
Atlantic identified and evaluated a route variation (the Cape Fear 1 Route Variation)
between MPs 146.6 and 152.2 of the AP -2 mainline in Cumberland County, North Carolina to
avoid a conservation easement enrolled in the NRCS's Wetland Reserve Program (see
Figure 10.9.1-19 and Table 10.9.1-19). From a point near Cedar Creek Road, the Cape Fear 1
Route Variation heads approximately 1.5 miles to the southwest of the baseline route to Evans
Dairy Road. It then continues to the south-southwest for approximately 3.8 miles, crossing the
Cape Fear River and rejoining the baseline route near Tyson Road. Cape Fear 1 is
approximately 0.2 mile longer than the baseline route, crosses 0.2 mile more of forested land,
and crosses two more perennial waterbodies than the baseline route. However, it avoids the
conservation easement and reduces crossings of forested wetlands by 0.1 mile.
TABLE 10.9.1-19
Cape Fear Route Variations for the Atlantic Coast Pipeline
Cape Fear Route
Cape Fear Route
Features
Unit
Baseline Route
Variation 1'
Variation 2 (Proposed)
Length
1% miles
5.2
5.4
5.5
Roads crossed
number
3
6
4
Adjacent to existing linear corridor facilities
miles
0.0
0.0
0.0
Federal lands crossed
miles
0.0
0.0
0.0
State lands crossed
miles
0.0
0.0
0.0
Private lands crossed
miles
5.2
5.4
5.5
Conservation easements crossed
miles
0.5
0.0
0.0
Forested land crossed
miles
1.7
1.9
2.0
Wetlands crossed - freshwater forested/shrub
miles
0.3
0.2
0.2
Intermittent waterbodies crossed
number
4
3
4
Perennial waterbodies crossed
number
2
4
4
Atlantic Coast Pipeline 70 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
AVf" ri,
J � Y• , C I�� ``{ � ,..
\ A.
-
1yh _
Y_ _ .._J JWIH°i t
yam, 1
3.
\\.
S.ir:R . 4Gr$VY.J1 (�
�V
4 - _Ph, 5 P Vf .
-, Gr
J
-1 r
Conservation Easement '1
I ;
NWI Wetland
*****,0Baseline
Mari& Coast /*�/ cape Fear Baseline Atlantic Coast Pipeline
� Cape Fear Route variation 1 Figure
1-19
PIpeV11� ,�Gape Fear Roouteuts Variation
♦ Cape Fear Route Variation 2
FILE. r,1. O?lents!D-FVOWSRPPI_AruGISiResource_ReptldslRREP_101Figuresl_ACP_RR10_Cape _F-r—d, REVISED, 08@42015, SCALE: 1:50,000 CRAWN 6Y: GIS
Atlantic Coast Pipeline 71 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification - Supplemental Information DRAFT
U.S. Army Corps of Engineers - Wilmington District
Subsequent to evaluating the Cape Fear 1 Route Variation, Atlantic identified and
evaluated a second route variation (Cape Fear 2) that optimizes the crossing angle of the Cape
Fear River. Cape Fear 2 is approximately 0.1 mile longer, crosses 0.1 more mile of forested
land, and crosses one more road than Cape Fear 2, but improves the crossing angle of the river.
Other environmental impacts are comparable to Cape Fear 1. For these reasons, Atlantic adopted
the Cape Fear 2 Route Variation into the proposed route.
ROUTE ADJUSTMENTS IN NORTH CAROLINA
Atlantic made a number of minor route adjustments to optimize the baseline routes as a
result of routing, biological, cultural resources, and civil field surveys. The route adjustments
generally measure less than two miles in length, pass within a quarter mile or less of the baseline
routes, and do not significantly affect the total length of the routes. The route adjustments were
adopted without a formal alternatives analysis, as the basis for the adjustment was intuitive and
practical (e.g., a slight shift in the centerline to avoid a wetland). Individually, the refinements to
the routes are small, but collectively they reduce impacts on environmental resources. Table 6
lists the route adjustments that have been incorporated into the proposed ACP pipeline route in
North Carolina and the rationale for each adjustment.
Atlantic Coast Pipeline 72 DRAFT
TABLE 6
Select Route Adjustments Incorporated into the Proposed
Atlantic Coast Pipeline in North Carolina
Approximate
Route Adjustment
Mileposts
State
Rationale
AP -2 Mainline
Jacks Swamp
0.7 to 2.4
NC
Adjustment to minimize a wetland crossing length
Big John Store Road
2.5 to 3.1
NC
Adjustment to avoid a cemetery
Cornwallis Road
3.7 to 4.2
NC
Adjustment to avoid a wetland
Quankey Creek
16.0 to 17.3
NC
Adjustment to avoid a proposed future development by the Halifax Airport Authority
Bryant Road
25.9 to 26.0
NC
Adjustment to avoid a wetland
Jacket Swamp
26.9 to 27.7
NC
Adjustment to avoid a conservation easement
Massengale Road
40.0 to 40.3
NC
Adjustment to avoid a future home site development
Wollett Mill Road
42.2 to 42.4
NC
Adjustment to avoid a cemetery
Cambridge Drive
48.8 to 49.1
NC
Adjustment to increase distance from residences
Boykin Road
70.5 to 70.8
NC
Adjustment to avoid a wetland
Contenmea Creek
73.1 to 74.4
NC
Adjustment to optimize creek crossing angle
Hales Road
80.1 to 81.5
NC
Adjustment to avoid a waterbody crossing and minimize a wetland crossing
Old Beulah Road
84.0 to 84.5
NC
Adjustment to avoid a wetland
Yelverton Grove Road
92.3 to 93.3
NC
Adjustment to connect to M&R Station
Guin Road
98.5 to 99.0
NC
Adjustment to avoid a waterbody crossing and minimize a wetland crossing
Coats Road
103.5 to 103.8
NC
Adjustment to address a landowner request
NC -50 South
109.5 to 110.0
NC
Adjustment to avoid a wetland
Godwin Lake Road
110.1 to 110.7
NC
Adjustment to avoid a blueberry farm
Holly Grove Road
112.4 to 112.7
NC
Adjustment to avoid a wetland
NC DOT Easement
113.9 to 114.4
NC
Adjustment to avoid a North Carolina Department of Transportation Nutrient Easement
Green Path Road
117.8 to 118.2
NC
Adjustment to reduce wetland impacts
Godwin Falcon Road
126.2 to 126.8
NC
Adjustment to reduce the pipeline length
Sisk Culbreth Road
129.4 to 129.7
NC
Adjustment to avoid existing structures
Jackie Lee Road
133.8 to 134.2
NC
Adjustment to reduce the pipeline length
Tobacco Road
138.6 to 139.0
NC
Adjustment to avoid a wetland
Atlantic Coast Pipeline 72 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification - Supplemental Information DRAFT
U.S. Army Corps of Engineers - Wilmington District
TABLE 6
Select Route Adjustments Incorporated into the Proposed
Atlantic Coast Pipeline in North Carolina
Route Adjustment
Approximate
Mileposts
State
Rationale
Approximate
142.0 to 142.2
NC
Adjustment to avoid a wetland
Pleasant View Drive
Unique ID
Avoided
Rationale
Sids Mill Road
143.2 to 143.5
NC
Adjustment to reduce a wetland crossing
John B Carter Road
144.5 to 145.0
NC
Adjustment to avoid being parallel to a waterbody
Clark West Road
146.7 to 148.6
NC
Adjustment to reduce road crossings
Canadian Avenue
152.9 to 153.3
NC
Adjustment to reduce wetland impacts
Highway 87
153.8 to 154.0
NC
Adjustment to optimize road crossing angle
Thrower Road
155.0 to 155.2
NC
Adjustment to avoid new residential development
Odom Road
156.6 to 157.5
NC
Adjustment to avoid a wetland crossing and reduce tree clearing
Little Marsh Swamp
162.0 to 164.8
NC
Adjustment to minimize a wetland crossing and parallel an existing utility corridor
Great Marsh Church
168.3 to 169.3
NC
Adjustment to meet a landowner request
Rennert Road
171.5 to 172.3
NC
Adjustment to reduce the length of the pipeline and address a landowner request
McQueen Road
175.0 to 175.4
NC
Adjustment to avoid a wetland
AP -3 Lateral
wcmp002f
Yes
Highway 186
9.9 to 10.3
NC
Adjustment to reduce tree clearing and optimize a railroad crossing
In addition to the route variations and adjustments, Atlantic optimized the route at a
localized scale to further minimize impacts on wetlands and waterbodies where feasible. Route
optimization efforts that have occurred to minimize impacts on wetlands and waterbodies within
the Wilmington District are listed in Table 7.
Appendix A includes detailed route maps that illustrate how Atlantic has also minimized
impacts on wetlands and waterbodies by reducing workspace at wetland crossings and in the
Atlantic Coast Pipeline 73 DRAFT
TABLE 7
Route Avoidance Locations for Wetlands in North Carolina
Approximate
Wetland
Wetland
Milepost
Unique ID
Avoided
Rationale
AP -2 Mainline
3.8
wnrg003f
Yes
4.0
wnrh015f
Yes
25.3
whlhOl3f
Yes
35.3
wnah016f
Yes
42.3
wnac001f
Yes
57.0
wnagOlOf
Yes
70.1
wwio011f
Yes
83.6
wjop00lf
Yes
108.9
wjop023f
Yes
110.4
wjoo026f
No
The proposed shift may impact a house in an adjacent parcel
131.0
wcmp002f
Yes
137.7
wcmp014f
Yes
Shift to minimize crossing
143.1
wcmo012f
No
Shift - alignment avoids power poles for high voltage lien as well as maintains a buffer from adjacent
residence (-260-ft). The proposed shift may impact existing structures on parcel 22-256
145.4
wcmp021f
No
Current alignment avoids power poles for high voltage line as well as maintains a buffer from adjacent
residence (-260-ft).
152.2
wcmp012f
Yes
Shift to minimize crossing
174.2
wroh012s
Yes
Appendix A includes detailed route maps that illustrate how Atlantic has also minimized
impacts on wetlands and waterbodies by reducing workspace at wetland crossings and in the
Atlantic Coast Pipeline 73 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
vicinity of wetlands and waterbodies, where feasible. In addition, to avoid impacts on wetlands
along the periphery of the construction workspace, modifications to workspace have been
incorporated into the project design to minimize impacts on wetlands and waterbodies.
ACP is a FERC regulated pipeline project and subject to certain procedures to avoid and
minimize impacts on wetland and waterbody crossings to satisfy FERC's own NEPA
requirements that also include minimization of environmental impacts. These procedures are
outlined in the Plan and Procedures and are applicable to all FERC regulated pipelines.
Despite Atlantics efforts to avoid and minimize impacts, there will be impacts that cannot
be avoided. These impacts will be offset with compensatory mitigation, as discussed in
Section D2.
3. b.1 Construction Minimization - Wetlands
During the routing phase of the Project, NWI data was used to provide a preliminary
analysis of wetland resources and to assess where wetland impacts could be avoided or
minimized. In addition, a field oriented routing team consisted of an ecological specialist that
assisted in identifying water resources during field routing by civil survey crews. Where
feasible, minor adjustments to the route were made to minimize impacts on wetlands.
Clearing and grading of wetlands, trenching, backfilling, and trench dewatering can affect
wetlands through the alteration of wetland vegetation and hydrology; loss or change to wildlife
habitat; deposition or erosion of sediment; and exposure to accidental spills of fuels and
lubricants.
Atlantic will minimize impacts on wetlands by following the wetland construction and
restoration guidelines contained in the Plan and Procedures. The proposed wetland mitigation
measures are intended to avoid wetland impacts to the greatest extent practicable; minimize the
area and duration of disturbance; reduce soil disturbance; and enhance wetland reestablishment
after construction. Some of the measures proposed include:
• limiting the construction right-of-way width to 75 -feet through wetlands (unless
alternative, site-specific measures are requested by Atlantic and approved by the
FERC and other applicable agencies);
• clearly marking wetland boundaries with signs and flagging in the field prior to
the start of construction;
• locating ATWS within uplands at least 50 feet away from wetland boundaries
(unless alternative, site-specific measures are requested by Atlantic and approved
by the FERC and other applicable agencies);
• installing and maintaining sediment barriers, such as silt fences or other approved
barriers during clearing
Atlantic Coast Pipeline 74 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
• limiting the operation of construction equipment within wetlands to only
equipment essential for clearing, excavation, pipe installation, backfilling, and
restoration;
• preventing the compaction and rutting of wetland soils by operating equipment on
equipment mats or timber riprap in wetlands that are not excessively saturated;
• restricting grading in wetlands to the area directly over the trenchline, except
where necessary to provide necessary safety;
• installing trench breakers or trench plugs at the boundaries of wetlands to prevent
draining of wetlands;
• segregating topsoil from the trench in non -saturated wetlands and returning
topsoil to its original location during backfilling to avoid changes in the
subsurface hydrology and to promote re-establishment of the original plant
community by replacing the seed bank found in the topsoil;
• installing temporary and permanent erosion and sediment control devices, and re-
establishing vegetation on adjacent upland areas, to avoid erosion and
sedimentation into wetlands;
• removing woody stumps only from areas directly above the trenchline, or where
they will create a safety hazard, to facilitate the re-establishment of woody species
by existing root structures;
• returning graded areas to their preconstruction contours to the greatest extent
practicable, and returning excavated soil from the trench within the wetlands back
to their original soil horizon to maintain hydrologic characteristics;
• prohibiting the storage of chemicals, fuels, hazardous materials, and lubricating
oils within 100 feet of a wetland;
• prohibiting parking and/or fueling of equipment within 100 feet of a wetland;
unless the Environmental Inspector determines there is no reasonable alternative,
and appropriate steps (such as secondary containment structure) are taken;
• prohibiting the use of live concrete as a building material so that wet concrete
does not come into contact with water;
• dewatering the trench at a controlled rate into an energy dissipation/sediment
filtration device, such as a geotextile filter bag and properly installed straw bale
structure, to minimize the potential for erosion and sedimentation;
• preventing the invasion or spread of undesirable exotic vegetation in accordance
with a project -specific invasive plant species management plan;
Atlantic Coast Pipeline 75 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
• limiting post -construction maintenance of vegetation to removal of trees with
roots that could compromise the integrity of the pipeline within 15 feet of the
pipeline centerline, and the maintenance of a 10 -foot wide corridor centered over
the pipeline as herbaceous vegetation;
• reseeding with a native wetland seed mix in both the temporary construction and
permanent right of way to stabilize wetland areas; and
• annual monitoring wetland reestablishment following construction until
reestablished wetlands achieve success. See Appendix J for the Restoration and
Rehabilitation Plan.
Prior to construction, wetland boundaries will be clearly marked in the field with signs
and flagging. Construction equipment working in wetlands will be limited to what is essential
for right-of-way clearing, excavating the trench, fabricating and installing the pipeline,
backfilling the trench, and restoring the right-of-way. In areas where there is no reasonable
access to the right-of-way except through wetlands, non-essential equipment will be allowed to
travel through wetlands only once, unless the ground is firm enough or has been stabilized to
avoid rutting.
Clearing of vegetation in wetlands will be limited to trees and shrubs, which will be cut
flush with the surface of the ground and removed from the wetland. To avoid excessive
disruption of wetland soils and the native seed and rootstock within the topsoil, stump removal,
grading, topsoil segregation, and excavation will be limited to the area immediately over the
trenchline, except a limited amount of stump removal and grading may be conducted in other
areas if required by safety-related issues. Topsoil segregation over the trenchline will only occur
if the wetland soils are not saturated at the time of construction.
During clearing, sediment barriers, such as silt fences or other approved sediment
barriers, will be installed and maintained adjacent to wetlands and within ATWS areas as
necessary to minimize the potential for sediment runoff. Sediment barriers will be installed
across the full width of the construction right-of-way at the base of slopes adjacent to wetland
boundaries. Erosion control devices installed across the working side of the right-of-way will be
removed during the day when vehicle traffic is present, and will be replaced each night.
Alternatively, drivable berms may be installed and maintained across the right-of-way in lieu of
silt fences or straw bales. Sediment barriers will also be installed within wetlands along the edge
of the right-of-way, where necessary, to minimize the potential for sediment to run off the
construction right-of-way and into wetlands outside the work area. If trench dewatering is
necessary, it will be conducted in accordance with the Procedures and applicable permits. Silt -
laden trench water will be discharged into an energy dissipation/sediment filtration device, such
as a geotextile filter bag and straw bale structure, to minimize the potential for erosion and
sedimentation.
Temporary access roads through wetlands will be provided, when necessary, by altered
for use during construction by installing timber construction mats or other removable materials
to minimize rutting in wetlands. Where intended for temporary use, the access roads
improvements within wetlands will be removed after pipeline construction and wetland
Atlantic Coast Pipeline 76 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
reestablishment is complete. Permanent access road improvements will require minor fill of
wetlands. Where feasible, Atlantic minimized impacts through necking down permanent access
roads or improving areas within adjacent uplands to minimize wetland impacts. After avoidance
and minimization to the extent practicable, 1.72 acres of permanent fill/loss wetland loss impacts
will result from the proposed permanent access roads within the Wilmington District.
The impacts associated with construction are planned to occur in an expedient and
efficient manner such that impacts on the wetlands are minimized to the extent practicable, and
long-term impacts are associated with minimal conversion of type but not loss of wetlands. In
addition, while there are a number of wetland crossings associated with across the ACP in North
Carolina are numerous, the crossings are distributed across many watersheds. Tables 3 and 4 in
section C, Proposed Impacts Inventory, summarize the impacts on wetlands by watershed
(HUC 8). Based on the short duration of construction thru wetlands, minimization of long-term
conversion by implementing FERC procedures (i.e., minimizing clearing to of a 10 feet along the
pipeline centerline to maintain a herbaceous wetland condition, and minimizing trimming to
15 feet either side of the pipeline centerline for larger trees), and providing compensatory
mitigation within both the 30 foot permanently maintained right of way (15 feet either side of the
pipeline centerline) and the temporarily disturbed 75 foot construction right of way by reseeding
with native wetland seed mix, and replanting of the temporarily disturbed right of way in non -
inundated deciduous hardwood wetlands (e.g., bottomland hardwood, hardwood riparian, and
hardwood flat wetlands) with saplings (minimization and compensatory mitigation), mitigating
at a 1:1 ratio for permanent conversion of non -inundated deciduous hardwood wetlands (e.g.,
bottomland hardwood, hardwood riparian, and hardwood flat wetlands) to scrub -shrub and
emergent wetlands, Atlantic anticipates that cumulative impacts will result in no more than no
more than minimal adverse impacts on the basin and sub -basins crossed.
4. b.2 Construction Minimization - Waterbodies
Because little or no grading will occur in wetlands, restoration of contours will be
accomplished during backfilling. Prior to backfilling, trench breakers will be installed, where
necessary, to prevent subsurface drainage of water from wetlands. Where topsoil is segregated,
the subsoil will be backfilled first followed by the topsoil. Topsoil will be replaced to the
original ground level leaving no crown over the trenchline. In areas where wetlands overlie
rocky soils, the pipe will be padded with rock -free soil or sand before backfilling with native
bedrock and soil. Equipment mats, gravel fill, and/or geotextile fabric will be removed from
wetlands following backfilling.
Where wetlands are located at the base of slopes, permanent slope breakers will be
constructed across the right-of-way in upland areas adjacent to the wetland boundary.
Temporary sediment barriers will be installed where necessary until revegetation of adjacent
upland areas is successful. Once revegetation is successful, sediment barriers will be removed
from the right-of-way and disposed of at an approved disposal facility.
Restoration/revegetation of wetlands will be considered successful when the affected
wetland satisfies the federal definition of a wetland (i.e., soils, hydrology, and vegetation); the
vegetation is at least 80 percent of the cover documented for the wetland prior to construction, or
at least 80 percent of the cover in adjacent, undisturbed areas of the wetland; or the plant species
Atlantic Coast Pipeline 77 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
composition is consistent with early successional wetland plant communities in the affected
ecoregion (if seeding is used in lieu of planting); and invasive plant species are absent, unless
they are abundant in adjacent areas that were not disturbed by construction.
Impacts on waterbodies crossed by the proposed ACP facilities could occur as a result of
construction activities in stream channels and on adjacent banks. Clearing and grading of stream
banks, in -stream trenching, trench dewatering, and backfilling could each result in temporary,
local modifications of aquatic habitat involving sedimentation, increased turbidity, and decreased
dissolved oxygen concentrations. In almost all cases, these impacts will be limited to the period
of in -stream construction, and conditions will return to normal shortly after stream restoration
activities are completed. Agency recommended time of year restrictions are listed in
Appendix C.
Vegetative clearing, grading for construction, and soil compaction by heavy equipment
near stream banks could promote erosion of the banks and the transport of sediment into
waterbodies by stormwater runoff. To minimize these potential impacts, Atlantic will install
equipment bridges, mats, and pads, as necessary. Additionally, Atlantic will locate ATWS at
least 50 feet from stream banks (with the exception of site-specific modifications requested by
Atlantic and approved by the FERC). Temporary sediment barriers will be installed around
disturbed areas as outlined in the Plan and Procedures. Upon completion of construction,
Atlantic will install permanent erosion control measures at stream crossing locations to provide
long-term protection of water quality according to the Plan and Procedures and all permit
requirements.
Sedimentation and increased turbidity can occur as a result of in -stream construction
activities, trench dewatering, or stormwater runoff from construction areas. In slow moving
waters, increases in suspended sediments (turbidity) may increase the biochemical oxygen
demand and reduce levels of dissolved oxygen in localized areas during construction. Suspended
sediments also may alter the characteristics of the water column (e.g., color and clarity) on a
temporary basis. Atlantic will use material excavated from the pipeline trench to backfill the
trench once the pipe is installed to avoid introduction of foreign substances into waterbodies.
Atlantic will install temporary equipment bridges to reduce the potential for turbidity and
sedimentation resulting from construction equipment and vehicular traffic crossing waterbodies.
Temporary bridges will be installed across waterbodies in accordance with the Procedures to
allow construction equipment and personnel to cross. The bridges may include clean rock fill
over culverts, timber mats supported by flumes, railcar flatbeds, flexi-float apparatuses, or other
types of spans. Construction equipment will be required to use the bridges, except that the
clearing and bridge installation crews will be allowed one pass through waterbodies before
bridges are installed. The temporary bridges will be removed when construction and restoration
activities are complete.
After the pipeline is installed across a waterbody using one of the methods described
above, the trench will be backfilled with native material excavated from the trench. The
streambed profile will be restored to pre-existing contours and grade conditions to prevent
scouring. The stream banks will then be restored as near as practicable to pre-existing conditions
and stabilized. Stabilization measures would include seeding, installation of erosion control
Atlantic Coast Pipeline 78 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
blankets, or installation of riprap materials, as appropriate. Temporary erosion controls will be
installed immediately following bank restoration. The waterbody crossing area will be inspected
and maintained until restoration of vegetation is complete.
During construction, the open trench may accumulate water, either from a high water
table and seepage of groundwater into the trench or from precipitation. In accordance with the
Plan and Procedures, and when necessary, trench water will be removed and discharged into an
energy dissipation/sediment filtration device, such as a geotextile filter bag and straw bale
structure, to minimize the potential for erosion and sedimentation.
In areas where concrete -coated pipe is required, and in accordance with the SPCC Plan,
concrete coating activities will occur a minimum of 100 feet from wetlands, waterbodies, and
springs. Concrete -coated pipe will be installed after the concrete is dried and will not be
dispersed when submerged in water.
The SPCC Plan for the ACP will describe measures that personnel and contractors will
implement to prevent and, if necessary control, inadvertent spill of fuels, lubricants, solvents, and
other hazardous materials that could affect water quality. As required in the Procedures and the
SPCC Plan, hazardous materials, chemicals, lubricating oils, and fuels used during construction
will be stored in upland areas at least 100 feet from wetlands and waterbodies. Refueling of
construction equipment will be conducted at least 100 feet from wetlands and waterbodies,
whenever possible. However, there will be certain instances where equipment refueling and
lubricating may be necessary in or near waterbodies. For example, stationary equipment, such as
water pumps for withdrawing hydrostatic test water, may need to be operated continuously on
the banks of waterbodies and may require refueling in place. The SPCC Plan will address the
handling of fuel and other materials associated with the ACP. As required by the Procedures, the
SPCC Plan will be available during construction on each construction spread.
It is possible that previously undocumented sites with contaminated soils or groundwater
could be discovered during construction of the ACP. Atlantic has prepared and will implement a
Contaminated Media Plan to address these circumstances. The Contaminated Media Plan
describes measures to be implemented in the event that signs of contaminated soil and/or
groundwater are encountered during construction. Signs of potential contamination could
include discoloration of soil, chemical -like odors, or sheens on soils or water. Containment
measures will be implemented to isolate and contain the suspected soil or groundwater
contamination and collect and test samples of the soil or groundwater to identify the
contaminants. Once the contaminants are identified, a response plan will be developed for
crossing or avoiding the site.
Use of the HDD method avoids impacts on waterbodies because it allows for the pipe to
be installed underneath the ground surface without disturbance of the streambed or banks.
However, a temporary, localized increase in turbidity could occur in the event of an inadvertent
release of drilling fluid to the waterbody. Drilling fluid to be used on the ACP will be composed
of water and bentonite clay (a naturally occurring mineral). The U.S. Environmental Protection
Agency (EPA) does not list bentonite as a hazardous substance, and no long-term adverse
environmental impacts are expected should an inadvertent release occur. Similarly, while native
soils may mix with the drilling fluid as a result of the drilling process, drilling fluid is still not
Atlantic Coast Pipeline 79 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
considered fill material and no adverse environmental impacts from these materials are expected
should an inadvertent return occur.
Due to the possibility of drilling fluid loss during HDD operations, Atlantic has prepared
and will implement a HDD Plan. The plan describes measures to prevent, detect, and respond to
inadvertent returns, including but not limited to, monitoring during drilling operations, the types
of equipment and materials that must be readily available to contain and clean up drilling mud,
containment and mitigation measures, notification requirements, and guidelines for abandoning
the directional drill, if necessary.
The use of HDD was considered for wetland and waterbody crossings, but was
determined to not be feasible in all crossing locations based on logistical, economic, temporal,
and engineering constraints, additional environmental impacts, and potential environmental risks.
The HDD method requires that a prefabricated segment of pipe at least the length of the bore
hole be staged in line with the drill path at the exit hole, opposite the placement of the drilling
rig. This "pullback" generally requires a false right-of-way that can deviate from the right-of-
way approaching the crossing, unless the drill alignment is directly in-line with the construction
right-of-way for the length of the prefabricated pipe segment. In many cases the drill path is not
in-line with the construction right-of-way and additional workspace that extends well outside of
the standard construction right-of-way must be cleared and graded to accommodate the
prefabrication of the pipe segment described above.
The path of the drill is constrained by the flexibility of the pipe; the depth beneath the
wetland and/or waterbody needed to achieve a successful installation; and the elevation of the
entry and exit points. The entry and exit points should be similar in elevation to prevent a
significant pressure differential that can contribute to failure of the HDD operation and by
maintaining consistent pressure this helps maintain predictable flow of drilling mud and thus
greater likelihood of a successful HDD.
As a rule of thumb used in evaluating the feasibility of the HDD method, the 36 -inch
diameter pipe requires a minimum drill path of 1,800 feet to achieve an acceptable radius of
curvature that will prevent a catastrophic "crinkling" of the pipe as it conforms to the path of the
drill hole. All proposed HDD crossings have been designed based on specific site constraints at
the crossing and geologic conditions, therefore site-specific designs may vary from the planning
guidelines.
Atlantic explored use of the HDD method at the Rocky Swamp crossing, but based on
geotechnical results, due to heavily weathered bedrock and overlying unconsolidated materials,
the likelihood of experiencing an inadvertent release was high. Therefore, the HDD method is
not proposed for the Rocky Swamp crossing.
A large drill can be more expensive than traditional crossing methods and can take as
long as several months to install. Traditional crossing methods of major waterbodies can
typically be completed in less than 30 days for major waterbody crossings, whereas typical
minor or intermediate waterbody crossings can be completed within a day or a few days. Due to
the extended time of exposure of additional workspace associated with HDD coupled with the
potential for an inadvertent return, traditional crossing methods can often reduce the
Atlantic Coast Pipeline 80 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
environmental impact when compared with HDD. Based on these constraints and design
considerations the HDD method is feasible and practicable where large, deep waterbodies are
encountered and sufficient space to place the pullback and work area for drilling equipment is
available.
Atlantic explored use of the HDD method at the Rocky Swamp crossing, but based on
geotechnical results, due to heavily weathered bedrock and overlying unconsolidated materials,
the likelihood of experiencing an inadvertent release was high. Therefore, the HDD method is
not proposed for the Rocky Swamp crossing.
The proposed HDD crossing locations on ACP constitute those where it is feasible and
the potential for a successful drill is acceptable.
Once construction is complete, the pipeline will be buried below the ground surface and,
therefore, will not impact water retention or floodplain storage within riparian corridors.
Atlantic is routing the proposed pipelines to avoid sharp angle crossings or crossing streams
where high stream energy could result in bank erosion. Atlantic will implement measures
outlined in the Procedures to minimize impacts on the waterbodies crossed, including the
installation of trench plugs to prevent water from flowing along the trenchline during and after
construction. These measures will minimize potential impacts on surface and below ground
hydrology. All waterbody crossings will be in accordance with the requirements identified in the
federal or state waterbody crossing permits obtained for the ACP.
During operations, the proposed pipelines will transport natural gas, which consist
primarily of methane. Methane is buoyant at atmospheric temperatures and pressure, and
disperses rapidly in air. The proposed pipelines will not carry liquids. Therefore, in the unlikely
event of a leak, impacts on surface waters or groundwater from methane are not anticipated.
Moreover, Atlantic will utilize a rigorous Integrity Management Plan to prevent leaks on the
system.
The impacts associate with construction are planned to occur in an expedient and
efficient manner such that impacts on the waterbody its banks are temporary in nature. In
addition, while there are numerous of waterbody crossings across the project in North Carolina,
the crossings are distributed across many watersheds. Tables 3 and 4 in section C, Proposed
Impacts Inventory, summarizes the impacts on waterbodies by sub -basin (HUC 8). Based on the
short duration and distant nature of the waterbody crossings, Atlantic anticipates that cumulative
impacts will result in no more than minimal adverse impacts on the basin and sub -basins crossed.
See Appendix K — Tables K-1 to Table K-3 for a list of General, Regional and Specific
NWP 12 permit conditions and how Atlantic will comply with the conditions.
5. Compensatory Mitigation for Impacts on Waters of the U.S. or Waters of the State
In order to authorize any activity under the NWP Program the USACE must determine
that the authorized activity in waters of the U.S. meets the terms and conditions of the relevant
NWP, in this case NWP 12, which allows no more than 0.5 acre loss at each single and complete
project (crossing). Furthermore, provided the activity meets the terms and conditions of NWP 12
USACE must determine that the activity will not result in no more than minimal individual or
Atlantic Coast Pipeline 81 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
cumulative impacts on the aquatic environment after considering proposed compensatory
mitigation. Such impacts would include the conversion impacts from one type of wetland to
another. As stated in the Preamble to 33 CFR 330/NWP Rule issued on November 22, 1991
(56 FR 59118-59119) mitigation can be used to reduce impacts on the aquatic environment to the
minimal level:
"In response to the comments concerning whether the District Engineer (DE) should
allow an activity to proceed under a relevant NWP when the mitigation reduces the adverse
environmental effects to the minimal level (the "buy down " or "write down " concept), we
believe it is indeed appropriate for the DE to consider mitigation in determining whether the
proposed activity will result in no more than a minimal level of adverse environmental effects. "
and "In summary, the net impact concept regarding the determination of minimal is consistent
with NEPA, the Army/EPA Mitigation Memorandum of Agreement and the Section 404(b)(1)
Guidelines as they pertain to general permits."
Permanent loss of wetlands is not proposed for anticipated to occur as a result of the ACP
mainline pipeline construction or associated facilities in North Carolina. However, loss of
waters of the U.S. will occur as a result of access road improvements. Existing access roads will
be utilized as much as possible where feasible. Where access road improvements are necessary
for use, impacts will be minimized to the maximum extent practicable, and, in conjunction with
other impacts will not result in more than 0.5 acre loss of waters of the U.S. at each single and
complete project. Atlantic will provide compensatory mitigation for the conversion within the
30 foot permanently maintained right of way (15 feet either side of the pipeline centerline)
reseeding with native wetland seed mix and mitigating at a 1:1 ratio for permanent conversion of
palustrine forested wetlands to scrub -shrub or to emergent wetlands, and within the temporary
disturbed construction right of way reseeding with native wetland seed mix to stabilize the area
and replanting in non -inundated deciduous hardwood wetlands (e.g., bottomland hardwood,
hardwood riparian, and hardwood flat wetlands) with saplings (minimization and compensatory
mitigation), along the ACP right-of-way.
Permanent losses of wetlands, streams, and other waters as a result of access roads are
proposed to be mitigated at a 2:1 ratio for all wetland types through the purchase of
commercially available mitigation credits from an agency -approved mitigation bank as a first
option. In-kind mitigation bank credits will be purchased from mitigation banks servicing the
areas (HUC 8 watershed, or approved service area) where the conversion or loss occurs. In the
event that a conversion or loss occurs in a service area where mitigation bank credits are not
available, Atlantic will seek authorization to participate in an agency approved In -Lieu Fee
program and/or, Atlantic will seek authorization to purchase credits from outside the service area
of the next nearest mitigation bank and/or conduct permittee responsible mitigation (PRM) under
an umbrella approach. These options will be based on practicality to replace the ecological
function of the temporal loss and amount of compensation required. Atlantic will coordinate with
Wilmington District in such cases in order to obtain approval of either option in instances where
credits are not available from an agency -approved mitigation bank.
Atlantic has completed research to identify wetland mitigation banks with available
credits, and will continue to contact wetland mitigation banks to identify available wetland
mitigation banks as the primary source of compensatory mitigation for the ACP. As a secondary
Atlantic Coast Pipeline 82 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
source of compensatory mitigation, Atlantic will pursue participation in the North Carolina In -
Lieu Fee program and/or conduct PRM if adequate wetland mitigation bank credits are not
available from an agency -approved bank. With respect to PRM, Atlantic's team is currently in
the process of identifying HUC's where an umbrella PRM approach may be applicable. Based on
this research, Atlantic's team has begun coordinating with landowners to identify suitable sites
and is in the process of negotiating with landowners in order to conduct site research and
assessments. Once suitable sites are selected and upon coordination with Wilmington District,
Atlantic's team will be available to coordinate and schedule site visits to review the selected sites
prior to final approval of the umbrella PRM approach.
Atlantic intends to complete field survey on remaining inaccessible parcels, analyze and
confirm impacts, and finally purchase adequate mitigation credits and/or secure sites to support
the umbrella PRM approach. Atlantic will pursue this sequence of steps to provide for
compensatory mitigation prior to final issuance of the JPA.
6. Complete if Using a Mitigation bank
See Section D2 above for mitigation options. Additional details will be provided in the
final application regarding Atlantic's plans for mitigation bank use and availability in North
Carolina. At the time of this draft application, Atlantic continues to plan for mitigation and has
provided a conceptual plan in Section D2 above.
7. Complete if Making a Payment to In -lieu Fee Program
See Section D2 above for mitigation options. Additional details will be provided in the
final application if Atlantic plans to utilize payment to the North Carolina in -lieu fee program as
a compensatory mitigation option.
8. Complete if Using a Permittee Responsible Mitigation Plan
See Section D2 above for mitigation options. Additional details will be provided in the
final application regarding proposed sites, if Atlantic plans to utilize permittee responsible
mitigation as a compensatory mitigation option.
9. Buffer Mitigation (State Regulated Riparian Buffer Rules) — required by DWR
Buffer rules for the Tar -Pamlico River Basin and Neuse River Basin watersheds provide
that mitigation will be required for certain surface water buffer impacts. The buffer rules define
two zones for eligible streams. Zone 1 extends 30 feet from the top of the bank landward and
Zone 2 extends another 20 feet from the end of Zone 1 landward for a total buffer of 50 feet.
Impacts to Zone 1 buffer areas may be allowed with mitigation. The buffer applies to:
intermittent streams, perennial streams, lakes, ponds, estuaries and modified natural streams that
are depicted on the most recent printed version of the soil survey map prepared by the Natural
Resources Conservation Service or the 1:24,000 scale quadrangle topographic map prepared by
the USGS. Atlantic has been consulting with NCDEQ to determine which streams in the ACP
pipeline corridor are subject to the buffer rule and to determine mitigation impacts.
Atlantic Coast Pipeline 83 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
A package was submitted to the NCDEQ in November 2016 with Atlantic's proposed
determinations for review. A response letter from NCDEQ was received by Dominion in
November 2016 (provided in Appendix I). Table 5 lists the streams that are subject to the buffer
rule, the perpendicularity of the stream, and the acreage of Zones 1 and 2 within the construction
right-of-way.
E. STORMWATER MANAGEMENT AND DIFFUSE FLOW PLAN (REQUIRED
BY DWR)
Stormwater permit applications and associated Erosion and Sediment Control plans will
be developed by Atlantic and will be submitted during late winter -spring 2017. Atlantic is
verifying the applicability a diffuse flow plan as part of the Erosion and Sediment Control plan
development and permit application submittal to NCDEQ and/or the appropriate local
government responsible for review and approval of construction stormwater permitting in North
Carolina.
1. Diffuse Flow Plan
A diffuse flow plan, is being evaluated by Atlantic, where applicable, and if necessary
will be submitted as part of the erosion and sediment control plans and stormwater permitting for
the project. Site design plans and review of aboveground facility sites is underway and
approvals of erosion and sediment control plans and construction stormwater plans will be
submitted to the appropriate agencies.
2. Stormwater Management Plan
Stormwater permit applications and associated Erosion and Sediment Control plans will
be developed by Atlantic and submitted in March 2017. Atlantic will develop a stormwater
management plan, where required, as part of the Erosion and Sediment Control plans that will be
submitted to NCDEQ and/or the appropriate local government, as applicable, responsible for
review and approval of construction stormwater permitting in North Carolina.
3. Certified Local Government Stormwater Review
Stormwater permit applications and associated Erosion and Sediment Control plans will
be developed by Atlantic and submitted in spring 2017. Atlantic will develop an Erosion and
Sediment Control plan that will be submitted to the appropriate local government and/or
NCDEQ, as applicable, responsible for review and approval of construction stormwater
permitting in North Carolina.
4. DWQ Stormwater Program Review
Atlantic does not anticipate stormwater permitting for the mainline due to the lack of
impervious surface after restoration of the pipeline right-of-way. Aboveground facilities are
being evaluated for thresholds of impervious and if required stormwater management permits
will be acquired for these facilities.
Atlantic Coast Pipeline 84 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
5. DWQ 401 Unit Stormwater Review
Atlantic does not anticipate stormwater permitting for the mainline due to the lack of
impervious surface after restoration of the pipeline right-of-way. Aboveground facilities are
being evaluated for thresholds of impervious and if required stormwater management permits
will be acquired for these facilities.
F. SUPPLEMENTARY INFORMATION
1. Environmental Documentation (DWQ Requirement)
Atlantic filed an application with FERC for a Certificate of Public Convenience and
Necessity under Section 7(c) of the Natural Gas Act on September 18, 2015. As a part of the
FERC filing process an Environmental Impact Statement will be produced by the FERC for the
ACP. A Draft Environmental Impact Statement was published by the FERC on December 30,
2016.
2. Violations (DWQ Requirement)
See Section F2 of the PCN Form
3. Cumulative Impacts
As part of the USACE evaluation of the single and complete projects of waters of the
United States for applicability of coverage under NWP 12, the USACE must determine if the
individual and cumulative impacts on the aquatic environment are no more than minimal after
considering compensatory mitigation for unavoidable impacts. The single and complete project
impacts are presented by HUC 8 watershed in Appendix C and summarized in tables 3 and 4 in
Section C. By avoiding impacts onto higher ecological value waters of the United States,
narrowing the corridor width to 75 feet in wetlands, and otherwise minimizing impacts to the
maximum extent practicable, including minimizing the duration of construction thru wetlands
and the long-term conversion by implementing FERC Procedures, Atlantic has made substantial
efforts so that impacts of single and complete projects are no more than minimal. Specific
measures to minimize impacts include: following FERC Procedures that minimize right-of-way
clearing to 10 feet along the pipeline centerline to maintain herbaceous wetland conditions;
minimizing deep rooted vegetation trimming to 15 feet either side of the pipeline centerline;
providing compensatory mitigation for permanent conversion of palustrine forested wetlands
(PFO) to scrub -shrub or emergent wetlands within the 30 foot permanently maintained right of
way (15 feet either side of the pipeline centerline) at a 1:1 ratio, and for loss of wetlands as a
result of proposed access roads at a 2:1 mitigation ratio; mitigating further by reseeding both the
temporarily disturbed and permanently maintained right of ways with native wetland seed mix,
and by replanting with saplings the temporarily impacted right-of-way in non -inundated
deciduous hardwood wetland areas (e.g., bottomland hardwood, hardwood riparian, and
hardwood flat wetlands) that will not be maintained during operations (minimization and
compensatory mitigation). As with all impact evaluation under the NWP program, the
determination whether there would be no more than minimal cumulative adverse impacts on the
aquatic environment is made after considering proposed mitigation (Preamble to
33CFR330;1991 NWPs - 56 FR 59118-59119). Furthermore, based on the level of conversion
Atlantic Coast Pipeline 85 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
impacts occurring within each HUC 8 watershed, and the fact that all conversion impacts to
palustrine forested wetlands will be have been offset by compensatory mitigation, the cumulative
impacts on the aquatic environment have been reduced to no more than minimal as described in
Section D.1., above.
"In response to the comments concerning whether the DE should allow an
activity to proceed under a relevant NWP when the mitigation reduces the adverse
environmental effects to the minimal level (the "buy down " or "write down " concept),
we believe it is indeed appropriate for the DE to consider mitigation in determining
whether the proposed activity will result in no more than a minimal level of adverse
environmental effects. " and "In summary, the net impact concept regarding the
determination of minimal is consistent with NEPA, the Army/[U.S. Environmental
Protection Agency] EPA Mitigation MOA and the Section 404(b)(1) Guidelines as they
pertain to general permits. "
The Preamble of the March 2012 NWP issuance package also indicates that cumulative
effects will normally be evaluated on a watershed basis.
Each separate and distant crossing should be evaluated to determine if it meets
the terms and conditions of the NWP, and cumulative effects of the overall utility line
should be evaluated to determine if the adverse cumulative effects on the aquatic
environment are more than minimal and therefore do not qualify for NWP
authorization. Separate utility line crossings are usually on different water bodies, and
may also be in widely separated watersheds. Such factors should be considered when
assessing cumulative impacts. " (77 FR 10196)"
"For single and complete linear projects, each separate and distant crossing of
a waterbody, as well as each crossing of other waterbodies along the corridor for the
linear project maybe permitted by separate NWP authorizations. The acreage and
other applicable limits for an NWP would be applied to each crossing, as long as those
crossings are far enough apart to be considered separate and distant. District
engineers will evaluate the cumulative effects of those linear projects when determining
whether authorization by NWP is appropriate. The approach to cumulative effects
analysis for linear projects is little different than the cumulative effects analysis for
other types of NWP activities, including those circumstances in which more than one
NWP is used to authorize a single and complete non-linear project, because cumulative
effects are evaluated on a regional basis. Cumulative effects analysis may be done on a
watershed basis, or by using a different type of geographic area, such as an
ecoregion. " (77 FR 10264)
The Preamble of the January 6, 2017 NWP Program Final Rule states in addition:
"We are retaining the Y2 -acre limit for this NWP because we believe it is an
appropriate limit for authorizing most utility line activities that have no more than
minimal individual and cumulative adverse environmental effects. Division engineers
can modify this NWP on a regional level to reduce the acreage limit if necessary to
ensure that no more than minimal adverse environmental effects occur in that region.
Atlantic Coast Pipeline 86 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
We do not agree that the acreage limit should apply to the entire utility line because the
separate and distant crossings of waters of the United States are usually at separate
waterbodies scattered along the length of the utility line, and are often in different
watersheds especially for utility lines that run through multiple counties, states, or
Corps districts. For utility lines that cross the same waterbody (e.g., a river or stream)
at separate and distant locations, the distance between those crossings will usually
dissipate the direct and indirect adverse environment effects so that the cumulative
adverse environmental effects are no more than minimal. If the district engineer
determines after reviewing the PCN that the cumulative adverse environmental effects
are more than minimal, after considering a mitigation proposal provided by the project
proponent, he or she will exercise discretionary authority and require an individual
permit. " (FR Notice, January 6, 2017 Final Rule Preamble p1885)
The USACE mitigation rule at 33 Code of Federal Regulations 332.8(d)(6)(ii)(A), and
North Carolina General Statutes § 143-214.11, provides that normally mitigation service areas
would be at the HUC 8 watershed level. HUC 8 has been used as the size of watershed in which
to present the cumulative impacts of the proposed Project.
The vast majority of the ACP impacts on waters of the U.S. would result from the
temporary discharge of earthen fill material associated with trench excavation for pipeline
installment within the rights-of-way. Furthermore, to facilitate construction equipment for
pipeline installation forested and scrub/shrub wetlands would be cleared and stumps removed
only where required for safe passage during pipeline installment. Where temporary discharges
of fill or excavation is necessary, Atlantic will immediately restore the wetland to its pre -
construction contours. The center 30 -feet of the cleared rights-of-way that previously consisted
of forested wetlands will be permanently maintained free of trees. The center 10 -feet of the
cleared rights-of-way that previously consisted of forested or scrub -shrub wetlands will be
permanently maintained in an emergent wetland state. This maintenance for the life of the
project, while not resulting in a loss of waters of the U.S., will result in a permanent impact to
wetland function and value, which would otherwise exist had the vegetative cover of the wetland
not been altered. These functional losses will be offset by proposed compensatory mitigation at
a 2:1 ratio. This has been described as permanent conversion in associated tables.
Atlantic has taken great steps to avoid permanent loss of waters of the U.S. and has
successfully avoided loss of waters of the U.S. for the pipeline and at permanent aboveground
facilities in the Wilmington District. However, loss of waters of the U.S. will occur as a result of
access road improvements totaling 1.72 acres with no loss at each single and complete crossing
exceeding the 0.5 acre NWP 12 threshold. However, the proposed pipeline will result in the
permanent conversion of 148.8 acres of palustrine forested wetlands to scrub -shrub or to
emergent wetland along with ACP construction. These impacts are included in Appendix C.
In conjunction with the offset of the functional losses mentioned above, Atlantic will
reestablish the area outside of the 30 -foot maintained corridor in deciduous hardwood forested
wetlands. This reestablishment, along with natural revegetation, will encourage the temporarily
impacted to areas to return to a more natural state faster than natural revegetation could
accomplish while lessening the time to return to the pre -construction condition. Reestablishment
will include planting saplings of deciduous hardwood species in non -inundated areas of
Atlantic Coast Pipeline 87 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
deciduous hardwood wetlands impacted by clearing for the construction right-of-way and
reseeding of these wetland areas with native wetland seed mix.
The temporary impacts and permanent conversion impacts of the proposed ACP are
provided in detail in Appendix C, and summarized by HUC 8 watershed in Section C above. A
total of 455.9 acres of temporary wetland impacts, and conversion of 148.8 acres of palustrine
forested wetland to scrub -shrub or emergent wetland impacts are planned along with ACP
construction. There will be no loss of waters of the U.S. due to mainline pipeline crossings of
waters of the U.S. Despite potential minor loss of waters of the U.S. for access road
improvements and the wetland conversion impacts, the compensatory mitigation plan will
provide for impact offsets and Atlantic does not anticipate a net loss in aquatic functions and
services of the waters of the U.S. The reestablishment of the wetland area outside of the 30 -foot
maintained corridor will assist in minimizing the temporary impacts due to clearing for
construction.
Assessment of cumulative effects also involves a general characterization of impacts on
waters of the U.S. from similar types of projects in the past and reasonably foreseeable future.
The area that the pipeline would traverse largely involves a mix of small community
development, agricultural use and open undisturbed forested land. Past impacts would be those
of typical rural development with road and various utility line crossings of streams and wetlands
in support of agriculture and dispersed human development. Reasonably foreseeable impacts
would include continued slow additional growth in the small human communities with
associated road and utility line crossings of waters of the U.S.
As provided in the USACE 2017 NWP issuance document at 77 FR 10197, cumulative
impacts on the human environment other than impacts on waters of the U.S. will be evaluated by
FERC in its NEPA EIS process.
"Even though an environmental impact statement may be prepared for a
particular utility line, the National Environmental Policy Act process does not prohibit
the Corps from using NWP 12 to authorize the construction, maintenance, repair, and
removal of utility lines and associated facilities in waters of the United States, as long as
the activity complies with all applicable terms and conditions and results in minimal
individual and cumulative adverse effects on the aquatic environment. NEPA requires
consideration of all environmental impacts, not only those to aquatic resources, so there
may well be situations where aquatic impacts are minimal even though environmental
impacts more generally are not. These other environmental impacts would be addressed
by the lead agency preparing the environmental impact statement. "
The purpose of the proposed pipeline is to transport natural gas from West Virginia and
Pennsylvania to use in areas of Virginia and North Carolina. Other pipelines, subject to future
approvals with mitigation as appropriate and practicable, may be required to transport natural gas
that may in the future be produced from the Marcellus Shale and Utica Shale formations. Other
pipeline development in the areas traversed by the Project would involve mostly temporary
impacts on waters of the U.S. that would be restored after pipeline construction is completed.
Permanent loss and wetland conversion impacts of waters of the U.S. would be mitigated to
achieve no more than minimal impact through USACE and state permit actions offsetting the
Atlantic Coast Pipeline 88 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
impacts on streams and wetlands. Moreover, USACE Headquarters evaluated the cumulative
impacts on waters of the U.S. in its decision document supporting reissuance of NWP 12 in
2017. The USACE evaluation of impacts nationwide determined that there would be no more
than minimal cumulative impacts on waters of the U.S. Part of the USACE Headquarters
evaluation of cumulative impacts identified that USACE districts would evaluate cumulative
impacts on waters of the U.S. of the "overall pipeline project" it authorized based on evaluation
of impacts on the aquatic environment on a watershed basis. The USACE Headquarters
cumulative impact evaluation was partially based on full restoration of temporary impacts,
districts requiring compensatory mitigation for permanent loss of waters and conversion impacts
such as the compensatory mitigation proposed by Atlantic for the ACP and that high ecological
value aquatic areas would be avoided as has been done on the ACP through coordination with
the USACE districts.
Based on the fact that the majority of the overall pipeline project impacts on waters of the
U.S. are temporary with restoration of aquatic areas immediately after construction and that
permanent conversion of forested and scrub -shrub wetlands to other wetland types and small
unavoidable road fills will be mitigated, the impacts at each single and complete project will
result in no more than minimal impact. Furthermore, the proposed impacts including loss of
waters of the U.S. at each single and complete project are of such minimal impact that they will
qualify for NWP 12 in North Carolina. The fact that these impacts, resulting in no more than
minimal impact on wetlands, streams and other waters of the U.S., at each single and complete
project, are spread widely over numerous watersheds and over approximately 198.7 miles in the
North Carolina, clearly indicates that the cumulative aggregate impacts of the overall pipeline
project to waters of the U.S. will be no more than minimal as well. Therefore the cumulative
impacts of the overall pipeline project on each HUC 8 watershed are not of a nature or extent that
would result in the requirement of an individual permit for the Project.
As provided in the Preamble of the January 6, 2017 USACE 2017-2022 NWP Program
Final Rule:
"We are retaining the long-standing practice articulated in the NWP regulations at
33 CFR 330.2 (i), which each separate and distant crossing of waters of the United States is
authorized by NWP. ....For the purposes of this NWP, the term "crossing" refers to regulated
activities. ...The substations, tower foundations, roads, and temporary fills that are also
authorized by NWP 12 (when those activities require DA authorization) are integral to the
fulfilling the purpose of utility lines, and thus fall within the "categories of activities that are
similar in nature" requirement for general permits stated in section 404(e) of the CWA." .... The
Corps does not regulate oil and gas pipelines, or other types of pipelines, per se. For utility lines,
including oil and gas pipelines, our legal authority is limited to regulating discharges of dredged
or fill material into waters of the United States and structures or work in navigable waters of the
United States, under section 404 of the Clean Water Act and section 10 of the Rivers and
Harbors Act of 1899, respectively. We do not have the authority to regulate the operation of oil
and gas pipelines, and we do not have the authority to address spills or leaks from oil and gas
pipelines.... In addition, we do not have the legal authority to regulate the construction,
maintenance, or repair of upland segments of pipelines or other types of utility lines. For
example, for a recent oil pipeline (e.g., the Flanagan South pipeline), the segments of the oil
pipeline that were subject to the Corps' jurisdiction (i.e., the crossings of waters of the United
Atlantic Coast Pipeline 89 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
States, including navigable waters of the United States, that were authorized by the 2012 NWP
12) was only 2.3 percent of the total length of the pipeline; the remaining 97.7 percent of the oil
pipeline was constructed in upland areas outside of the Corps' jurisdiction. Interstate natural gas
pipelines are regulated by the Federal Energy Regulatory Commission. The Federal Energy
Regulatory Commission also regulates some electric transmission projects. There are other
federal laws that address the operation of pipelines and spills and leaks of substances from
pipelines. Those laws are administered by other federal agencies." (FR Notice, January 6, 2017
Final Rule Preamble pp. 1883-1884)
The cumulative impacts analysis submitted with the FERC Resource Report 1, in support
of the project NEPA analysis, is provided in Appendix L for additional details.
4. Sewage Disposal (DWR Requirement)
See Section F4 of the PCN Form
5. Endangered Species and Designated Critical Habitat (USAGE Requirement)
The ACP is a FERC 7c regulated project and the USACE is participating in the pre -filing
process as a cooperating agency. FERC is coordinating the review of Section 7 Endangered
Species Act compliance with the FWS.
Pursuant to the General Conditions 18 and 31 for NWPs, Atlantic initiated Section 7
Endangered Species Act coordination with the FWS. In a technical assistance letter dated
August 15, 2014 Atlantic initiated the Section 7 review with the FWS North Carolina Raleigh
Ecological Field Services Office. Agency correspondence can be found in Appendix I.
Section 7 of the Endangered Species Act requires federal agencies to verify that any
actions authorized, funded, or carried out by the agencies do not jeopardize the continued
existence of a federally listed threatened or endangered species, or result in the destruction or
adverse modification of designated critical habitat for a federally listed species. The law is
jointly administered by the FWS, which is responsible for terrestrial and freshwater species, and
National Oceanic and Atmospheric Administration National Marine Fisheries Service (NOAA
Fisheries), which is responsible for marine and anadromous species. As the lead Federal agency
for authorizing the ACP, FERC is required to coordinate with the FWS and NOAA Fisheries to
determine whether federally listed endangered or threatened species or designated critical habitat
are found in the vicinity of the ACP, and to evaluate the potential effects of the proposed actions
on those species or critical habitat.
For actions involving major construction activities with the potential to affect listed
species or designated critical habitat, the FERC must report its findings to the FWS and NOAA
Fisheries in a Biological Assessment (BA) for those species that could be affected. If it is
determined that the proposed action is likely to adversely affect listed species or designated
critical habitat, the FERC is required to initiate formal consultation with the appropriate federal
agency.
Atlantic reviewed the Information Planning and Conservation System (lPaC System) to
determine which federally listed species could occur in the ACP Project area. Atlantic
Atlantic Coast Pipeline 90 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
additionally coordinated with the FWS Ecological Field Services Office in North Carolina to
introduce the Project and begin discussing and addressing potential impacts on federally listed
species and designated critical habitat. Correspondence with agencies is located in Appendix I.
For the ACP, Atlantic sent letters to the North Carolina FWS EFSO and the NOAA
Fisheries' Office of Protected Resources in August 2014 requesting early coordination and
technical assistance based on the species lists obtained through the IPaC System. These letters
requested verification of the species that could be impacted by the ACP Project as well as
direction on field survey protocols for species-specific surveys.
Atlantic requested and received National Heritage Inventory data for a two -mile -wide
corridor centered on the proposed pipeline centerlines which includes the locations of
aboveground facilities. This data identifies occurrences of state and federal -listed species as well
as sensitive or significant habitats including parks, forests, or nature preserves located along or
adjacent to the proposed pipeline routes.
Based on information obtained through IPaC System, National Heritage Inventory, and
agency consultations, Atlantic has compiled a preliminary list of 20 federally listed, proposed, or
under review species that potentially occur within the ACP Project area within the USACE —
Wilmington District (Table 8).
Atlantic has prepared a final draft BA (version 5) evaluating the potential impacts of the
Projects on federally listed species. Atlantic filed the final draft BA with FERC on January 27,
2017, and a copy was also provided to the FWS and the USACE.
State -listed species in North Carolina are separated into three categories: North Carolina
Endangered, North Carolina Threatened, and North Carolina Special Concern. Species listed in
these categories have been recognized as needing additional conservation by the North Carolina
Wildlife Resources Commission (NCWRC) under the State Endangered Species Act (G.S. 113-
331 to 113-337).
Atlantic requested and received data on known occurrences of State -listed species within
a two -mile -wide corridor centered on the proposed ACP pipeline routes from the NCDEQ.
Table 9 summarizes this data.
Atlantic Coast Pipeline 91 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Abbreviations for species federal status are as follows:
E = Endangered
T = Threatened
UR — Under review
P- Proposed
Atlantic Coast Pipeline 92 DRAFT
TABLE 8
Atlantic Coast Pipeline Project
Federally Listed Species and Species Proposed for Federal Listing within the U.S. Army Corps of Engineers — Wilmington District
Species
Status'
Areas of Potential Occurrence
Bird
Red -cockaded Woodpecker
E
All counties crossed by the Project
(Picoides borealis)
Wood Stork
E
Sampson County
(Mycteria Americana)
Fish
Atlantic Sturgeon
E
Roanoke and Neuse Rivers
(Acipenser oxyrinchusoxyrinchus)
Cape Fear Shiner
E
Cape Fear River Drainage
(Notropis mekistocholas)
Carolina madtom
UR
Tar and Neuse River Basins
(Noturus furiosus)
Shortnose Sturgeon
E
Downstream occurrences in adjacent Bladen County
(Cipenser brevirostrum)
Freshwater Mussels
Atlantic pigtoe
UR
Northampton, Halifax, Nash, Wilson, Johnston, and Cumberland Counties
(Fusconaia mason)
Dwarf Wedgemussel
E
Wilson, Johnston, and Nash Counties
(Alasmidonta heterodon)
Tar River Spinymussel
E
Halifax, Johnston, and Nash Counties
(Elliptio steinstansana)
Green floater
UR
Roanoke, Tar, and Neuse River basins
(Lasmigona subviridis)
Yellow Lance
UR
Halifax, Johnston, and Nash Counties
(Elliptio lanceolata)
Invertebrate
Saint Francis' Satyr
E
Cumberland County
(Neonympha mitchelliifrancisca)
Chowanoke crayfish
UR
Roanoke River basin
(Orconectes virginiensis)
Rusty patched bumble bee
P
Entire project area
(Bombus affznis)
Mammals
Nor -them long-eared bat
T
All counties crossed by the Project
(Myotis septentrionalis)
Plants
American Chaffseed
E
Cumberland County
(Schwalba americana)
Michaux's Sumac
E
Cumberland, Johnson, Nash, Robeson, and Wilson Counties
(Rhus michauxii)
Pondberry
E
Cumberland and Sampson Counties
(Lindera melissifolia)
Rough -leaved Loosestrife
E
Cumberland County
(Lysimachia asperulifolia)
Amphibians
Neuse River waterdog
UR
Tar and Neuse River Basins
(Necturus lewisi)
Abbreviations for species federal status are as follows:
E = Endangered
T = Threatened
UR — Under review
P- Proposed
Atlantic Coast Pipeline 92 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Abbreviations for state -listed species are as follows:
E = Endangered
T = Threatened
SC = Special Concern
SR = Significantly Rare
P = Petitioned for Federal listing
Atlantic Coast Pipeline 93 DRAFT
TABLE 9
State -listed Endangered and Threatened Species within the U.S. Army Corps of Engineers — Wilmington District
Species
Status a
Area of Potential Occurrence
Amphibians
Neuse River Waterdog
SC
Halifax, Nash, Johnston, Wilson
Mammals
Rafinesque's Big -eared Bat (Coastal Plain subspecies)
SC
All Counties Crossed
Southeastern Myotis
SC
All Counties Crossed
Birds
Bachman's Sparrow
SC
Halifax, Sampson, Cumberland, Robeson
Cerulean Warbler
SC
Halifax, Northampton
Fish
Carolina Madtom
T
Halifax, Nash, Johnston, Wilson
Crayfish
SC
Halifax, Northampton
North Carolina Spiny Crayfish
SC
Nash
Reptiles
Southern Hog -nosed Snake
SC
Robeson
Freshwater Mussels
Alewife Floater
T
Halifax, Nash, Johnston, Wilson
Atlantic Pigtoe
E
Halifax, Nash, Johnston, Wilson
Cape Fear Spike
SC
Halifax, Nash, Johnston, Wilson
Creeper
T
Halifax, Nash, Johnston, Wilson
Eastern Lampmussel
T
Halifax, Nash, Johnston, Wilson
Eastern Pondmussel
T
Halifax, Nash, Johnston, Wilson
Green Floater
E
Halifax, Nash, Johnston, Wilson
Notched Rainbow
SC
Halifax, Nash, Johnston, Wilson
Roanoke Slabshell
T
Halifax, Nash, Johnston, Wilson
Tidewater Mucket
T
Halifax, Nash, Johnston, Wilson
Triangle Floater
T
Halifax, Nash, Johnston, Wilson
Yellow Lampmussel
E
Halifax, Nash, Johnston, Wilson
Yellow Lance
E
Halifax, Nash, Johnston, Wilson
Plants
American Bluehearts
E
Sampson
Awned Meadow -beauty
SC
Cumberland, Robeson, Sampson
Bog Spicebush
P
Cumberland, Johnston, Robeson
Boykin's Lobelia
E
Cumberland, Robeson
Buffalo Clover
T
Halifax
Canby's Bulrush
SR
Cumberland, Johnston
Cape Fear Spatterdock
P
Cumberland, Nash, Robeson, Sampson
Carolina Bogmint
E
Johnston, Robeson, Sampson
Georgia Indigo -Bush ,
E
Cumberland, Robeson
Long Beach Seedbox
P
Cumberland, Johnston, Robeson, Sampson
One -flower Hardscale
SR
Cumberland, Robeson, Sampson
Raven's Seedbox
T
Sampson
Running Oak
SR
Robeson
Sandhills Lily
E
Cumberland
Sessile -flowered Trillium
T
Halifax, Northampton
Small -flower Blueberry
SR
Cumberland, Robeson
Spring -flowering Goldenrod
SR
Cumberland, Johnston, Sampson
Thin-wall Quillwort
T
Sampson
Winter Quillwort
P
Johnston, Sampson
Abbreviations for state -listed species are as follows:
E = Endangered
T = Threatened
SC = Special Concern
SR = Significantly Rare
P = Petitioned for Federal listing
Atlantic Coast Pipeline 93 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
In addition to this data, Atlantic solicited and received comments in a letter dated
November 21, 2014 from the NCWRC regarding known occurrences of State -listed aquatic
species along the proposed routes. The NCWRC requested a mussel survey in streams that are
second order or larger within the Neuse and Tar River basins. For any streams where mussels
are present at the crossing, a second mussel survey is planned to relocate mussels that could be
impacted during pipeline installation. Surveys for Carolina madtoms will be completed at the
same time as the mussel surveys in the Tar and Neuse basins. The NCWRC also requested
mussel surveys in the Roanoke and Cape Fear Rivers immediately prior to pipeline installation to
relocate mussels that will be impacted by construction.
Migratory Bird Treaty Act and Bald and Golden Eagle Protection Act
Atlantic will comply with the applicable portions of both the Migratory Bird Treaty Act
(MBTA) and the Bald and Golden Eagle Protection Act. Atlantic plans to clear the pipeline
right-of-way outside of the migratory bird nesting season to reduce potential impacts on
migratory birds and other sensitive species. Atlantic will avoid impacts on nests observed within
the construction right-of-way in accordance with the MBTA. In the event that an active bald
eagle nest is identified in the vicinity of the project, Atlantic will adhere to the requirements of
the National Bald Eagle Management guidelines to minimize potential impacts on nesting eagles.
Migratory Bird Plan to describe measures it has implemented or will implement to avoid,
minimize and mitigate potential impacts on migratory birds, including bald and golden eagles,
consistent with the MBTA and Bald and Golden Eagle Protection Act Plan to the FERC on
January 27, 2017, with a copy sent also to the FWS and the USACE.
6. Essential Fish Habitat (USACE Requirement)
Atlantic consulted with NOAA Fisheries' Southeast and Northeast Regional Offices to
introduce the ACP and request technical assistance (Dominion, 2014a; Dominion, 2014b). In
their reply, the Southeast Regional Office (NOAA Fisheries, 2014a) concurred with Atlantic that
no Essential Fish Habitat (EFH) will be affected by the proposed ACP in North Carolina because
the AP -2 mainline route does not cross or pass near EFH. In addition, the AP -3 mainline does
not cross or pass near EFH in North Carolina.
7. Historic or Prehistoric Cultural Resources (USACE Requirement)
The ACP is a FERC 7c regulated project and the USACE is participating in the FERC
NEPA process as a cooperating agency. FERC, as the lead agency for the project, will be
coordinating with the North Carolina State Historic Preservation Office for the review of
compliance with Section 106 of the National Historic Preservation Act, as well as coordinating
its government -to -government consultation with federally recognized Indian Tribes.
For the FERC process, the area of potential effect (APE) for archaeological sites was
defined horizontally as the proposed pipeline corridor and associated workspace, footprints of
aboveground facility sites, and footprints of other work areas; and vertically as the maximum
depth of trenching and other excavations or the depth to which evidence of human occupation
could be found. The APE for aboveground historic resources was defined to include the
proposed pipeline corridor and associated workspace, footprints of aboveground facility sites,
and footprints of other work areas. The APE for aboveground historic resources also included
Atlantic Coast Pipeline 94 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
viewsheds to and from historic sites along or near the proposed facilities. The linear extent of
the viewsheds varied by site depending on changes in topography, vegetation cover, and the
presence of structures or other obstructions in sight lines to and from aboveground historic
resources.
The reports presenting the results of the cultural resources surveys for the Project can be
provided to the USACE — Wilmington upon request, along with copies of documentation of State
Historic Preservation Office review and comment when they become available. See Appendix M
for the Plan for Unanticipated Discovery of Historic Properties or Human Remains During
Construction.
8. Tribal Coordination
The ACP is a FERC 7c regulated project and the USACE is participating in the pre -filing
process as a cooperating agency. FERC will be coordinating with the North Carolina State
Historic Preservation Office for the review of Section 106 of the National Historic Preservation
Act compliance, as well as coordinating its government -to -government consultation with
federally recognized Indian Tribes as part of the Section 106 consultation process. Project
introduction letters for the entire ACP/SHP were sent to 15 federally recognized Indian Tribes
that might have interest in the Project area based on historic information. See Appendix N for a
summary of communications with these Indian Tribes. The 15 federally recognized Indian tribes
that were contacted regarding the ACP and/or SHP are listed below:
• Absentee -Shawnee Tribe of Indians of Oklahoma;
• Catawba Indian Nation;
• Cherokee Nation;
• Delaware Nation;
• Delaware Tribe of Indians;
• Eastern Band of Cherokee Indians;
• Eastern Shawnee Tribe of Oklahoma;
• Pamunkey Tribe;
• Seneca -Cayuga Tribe of Oklahoma;
• Seneca Nation of Indians;
• Shawnee Tribe;
• Stockbridge Munsee Community;
• Tonawanda Band of Seneca Indians of New York;
• Tuscarora Nation of New York; and
• United Keetoowah Band of Cherokee Indians.
Atlantic contacting state recognized tribes in the ACP project area in Virginia and North
Carolina. The following seven state recognized tribes identified by the North Carolina
Commission of Indian Affairs were contacted for the ACP:
1. Coharie Tribe;
2. Haliwa-Saponi Indian Tribe;
3. Lumbee Tribe of North Carolina;
4. Meherrin Indian Tribe;
Atlantic Coast Pipeline 95 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
Occaneechi Band of the Saponi Nation;
Sappony Tribe; and
Waccamaw Siouan Tribe.
The following 10 state recognized tribes identified by the Secretary of the
Commonwealth of Virginia Commission of Indian Affairs were contacted for the ACP:
1.
Cheroenhaka (Nottoway) Tribe;
2.
Chickahominy Tribe;
3.
Eastern Chickahominy Tribe
4.
Monacan Indian Nation;
5.
Mattoponi Tribe;
6.
Nansemond Tribe;
7.
Nottoway Tribe;
8.
Patawomeck Tribe;
9.
Rappahannock Tribe; and
10.
Upper Mattaponi Tribe.
There are no state recognized Indian tribes in West Virginia.
Atlantic sent introductory Project letters to the Indian tribes which included a Project
description and location maps, and invited each tribe to comment on the Project. In addition, the
letters requested input from each of the tribes regarding the potential of the Project to affect
archaeological sites, burials, and traditional cultural properties of concern to each tribe. Atlantic
received confirmation of delivery of all of the letters. Communication with the tribes is ongoing
as part of the Section 106 consultation process.
9. Flood Zone Designation (USACE Requirement)
The ACP Project will cross several Federal Emergency Management Agency -designated
100 -year floodplains throughout North Carolina. Atlantic will apply for local permits as required
by regulations and local agencies. Federal Emergency Management Agency 100 -year
floodplains crossed by the ACP can be found in Appendix A — Figure A-5. Atlantic has been
working with the counties in North Carolina and will apply for applicable floodplain permits.
G. SECTION 408 AUTHORIZATION
Section 14 of the Rivers and Harbors Act of 1899 and codified in 33 U.S. Code 408
(commonly referred to as "Section 408") authorizes the Secretary of the Army, on the
recommendation of the Chief of Engineers of the USACE, to grant permission for the alteration
or occupation or use of a USACE Civil Works project if the Secretary determines that the
activity will not be injurious to the public interest and will not impair the usefulness of the
project.
Atlantic submitted a letter to USACE — Wilmington District on June 15, 2016 requesting
a review of USACE projects within Wilmington District Civil Works boundaries that maybe
crossed by the ACP, to determine whether or not a Section 408 permission would be required.
Wilmington District reviewed the location of proposed ACP pipeline and facilities and determined that
Atlantic Coast Pipeline 96 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
the crossing of the Cape Fear River would require a Section 408 permission. The District, in a
letter dated November 3, 2016 signed by Colonel Kevin P. Landers, Sr., Commander Wilmington
District, granted the request for the pipeline to cross the Cape Fear River for the following reasons:
"(1) the proposed action will not be injurious to the public interest, and (2) the proposed action will not
impair the usefulness of thefederalproject. As the requestor, Atlantic is solely responsible for any
remedial action needed to correct any deficiency in the design or construction of the requested
alteration. " stating that the District had reviewed the proposed alignment and determined that the
pipeline path would not encroach on any Corps property and is far enough removed from any Corps
infrastructure so as to not require a Section a Section 408 permission per the date of the design location
received and dated April 1, 2016 (second location revision). " Correspondence is included in
Appendix I.
4L
r'
Atlantic Coast Pipeline 97 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
H. REFERENCES
Council on Environmental Quality. 1997. Considering Cumulative Effects under the National
Environmental Policy Act. January 1997.
Council on Environmental Quality. 2005. Guidance on the Consideration of Past Actions in
Cumulative Effects Analysis. June 2005.
Dominion. 2014a. Letter to David Dale (NOAA Fisheries EFH Southeast Region Coordinator)
from William Scarpinato (Dominion) dated September 9, 2014.
Dominion. 2014b. Letter to Karen Greene (NOAA Fisheries EFH Northeast Region
Coordinator) from William Scarpinato (Dominion) dated September 9, 2014.
ICF International. 2014. The Economic Impacts of the Atlantic Coast Pipeline. Prepared by
ICF International for Dominion Transmission, Inc. February 9, 2015. Available online
at: https://www.dom.com/library/domcom/pdfs/lzas-transmission/atlantic-coast-pipeline/
acp-icf-study_pdf. Accessed May 2015.
Mid -Atlantic Fishery Management Council, 2014.Fishery Management Plans and Amendments
for species managed by the Mid -Atlantic Fishery Management Council. Available online
at: http://www.mafmc.or fishery-mana eg ment-plans/. Accessed September 2014.
National Oceanic and Atmospheric Administration Fisheries. 2014d. The Guide to Essential
Fish Habitat Designations in the Northeastern United States. Available online at:
http://www.greateratlantic.fisheries.noaa.gov/hcd/webintro.html. Accessed September
2014.
National Oceanic and Atmospheric Administration Fisheries. 2014a. E-mail to Sara Throndson
(NRG) from David O -Brien (NOAA Fisheries Biologist Virginia Field Office) dated
September 2014.
National Oceanic and Atmospheric Administration Fisheries. 2014b. Letter to William
Scarpinato (Dominion) from Virginia Fay (NOAA Fisheries Assistant Regional
Administrator Habitat Conservation Division) dated September 2014.
National Oceanic and Atmospheric Administration Fisheries. 2014c. NOAA Fisheries Essential
Fish Habitat Mapper. Available online at: http://www.habitat.noaa.goy/protection
/efh/habitatmapper.html. Accessed September 2014.
National Oceanic and Atmospheric Administration Fisheries. 2014e. NOAA Estuarine Living
Marine Resources. Available online at: hl�2:Hccma.nos.noaa.gov/ecosystems/
estuaries/elmr.aspx. Accessed September 2014.
Atlantic Coast Pipeline 98 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
National Oceanic and Atmospheric Administration Fisheries. 2014f. The Final Consolidated
Atlantic Highly Migratory Species Fishery Management Plan and Amendments for
species managed by the Atlantic Highly Migratory Species Management Division.
Available online at: http://www.mufs.noaa.gov/sfa/hms/documents/fmp/consolidat
ed/index.html. Accessed September 2014.
National Oceanic and Atmospheric Administration Fisheries. 2014g. The Summary of Essential
Fish Habitat (EFH) Designations for the 10x10 Square Coordinates: 370 00.0 N, 760 20.0
W, 360 50.0 N, and 76o 30.0 W. Available online at: http://www.greateratlantic.fisheries
.noaa.gov/hcd/STATES4/virginia/virginia/36507620.html. Accessed September 2014.
National Oceanic and Atmospheric Administration Fisheries. 2014h. NOAA Fisheries Greater
Atlantic Summary of Essential Fish Habitat and General Habitat Parameters for Federally
Managed Species Table. Available online at: http://www.greateratlantic.fisheries.
noaa.gov/hcd/efhtables.pdf. Accessed September 2014.
New England Fishery Management Council, 2014.Fishery Management Plans and Amendments
for species managed by the New England Fishery Management Council. Available
online at: http://www.nefmc.or /g management-plans.Accessed September 2014.
North Carolina Department of Environmental Quality. 2013. North Carolina Erosion and
Sediment Control Planning and Design Manual, revised 2009 and 2013. Available online
at: http://portal.NCDEQ.org/web/lr/publications. Accessed February 2015.
South Atlantic Fishery Management Council, 2014.Fishery Management Plans and Amendments
for species managed by the Mid -Atlantic Fishery Management Council. Available online
at: hit 2:Hsafmc.net/resource-library/fisher.. e�plans-amendments. Accessed
September 2014.
U.S. Army Corps of Engineers. 1987. Corps of Engineers Wetlands Delineation Manual.
Technical Report Y-87-1, U.S. Army Engineer Waterways Experiment Station,
Vicksburg, Miss.
U.S. Army Corps of Engineers. 2005. Ordinary High Water Mark Identification. Regulatory
Guidance Letter No. 05-05. Available online at: http://www.usace.anny.mil/Portals/2/
docs/civilworks/RGLS/r l0�pdf. Accessed January 22 2015.
U.S. Army Corps of Engineers. 2010b. Regional Supplement to the Corps of Engineers Wetland
Delineation Manual: Atlantic and Gulf Coastal Plain Region (Version 2.0). ERDC/EL
TR -10-20. Vicksburg, MS: U.S. Army Engineer Research and Development Center.
U.S. Census Bureau. 2014. 2005 Interim State Population Projections. Available online at:
https://www. census. gov/populatiopZproj ections/data/state/prof ectionsagesex.html.
Accessed October 2014.
Atlantic Coast Pipeline 99 DRAFT
Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information DRAFT
U.S. Army Corps of Engineers — Wilmington District
U.S. Department of Energy. 2015. Natural Gas Infrastructure Implications of Increased
Demand from the Electric Power Section. Available online at: http://energ_ygov/sites/
prod/files/2015/02/f l 9/DOE%20Report%20Natural%20 Gas%20Infras tructure%20 V_02-
02.pdf. Accessed February 2015.
U.S. Energy Information Administration. 2015 a. Annual Energy Outlook 2015.Available online
at: http://www.eia.gov/forecasts/aeo/. Accessed June 2015.
U.S. Energy Information Administration. 2015b. Market Trends; Electricity Demand. Available
online at: http://www.eia.gov/forecasts/aeo/MT_electric.cfm. Accessed June 2015.
U.S. Energy Information Administration.2015c. Market Trends; Natural Gas. Available online
at: http://www.eia.gov/forecasts/aeo/mt_naturalgas.cfm. Accessed June 2015.
U.S. Energy Information Administration. 2015 d. Natural Gas Summary for Virginia. Available
online at: http://www.eia.gov/dnav/ng/ng sum_lsum dcu SVA_a.htm. Accessed June
2015. _ c
U.S. Energy Information Administration.2015e. Natural Gas Summary for North Carolina.
Available online at: http://www.eia.gov/dnav/ng/ng sum _lsum_dcu_SNC _a.htm.
Accessed June 2015.
U.S. Environmental Protection Agency. 1999. Consideration of Cumulative Impacts in EPA
Review of NEPA Documents. EPA 315-R-99-002. May 1999.
14
Atlantic Coast Pipeline 100 DRAFT
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX A
FIGURES
FIGURE 3
TOPOGRAPHIC MAPS
FIGURE 4
AERIAL SHEET MAP
FIGURE 5
FEMA FLOODPLAINS
FIGURE 6
NORTH CAROLINA BUFFER
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX B
WETLAND AND WATERBODY SURVEY REPORT
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX C
WETLAND AND WATERBODY CROSSING IMPACT TABLE
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX D
SUPPLEMENTAL FERC UPLAND CONSTRUCTION INFORMATION
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX E
RIGHT-OF-WAY CROSS SECTION DRAWINGS AND SELECT
CONSTRUCTION TYPICALS
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX F
SECTION 10 WATERS SITE SPECIFIC PLANS
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX G
SPILL PREVENTION, CONTROL, AND COUNTERMEASURES PLAN
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX H
HORIZONTAL DIRECTIONAL DRILL FLUID
MONITORING, OPERATIONS, AND CONTINGENCY PLAN
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX I
AGENCY CORRESPONDENCE
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX J
RESTORATION AND REHABILITATION PLAN
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX K
GENERAL, REGIONAL, AND SPECIAL PERMIT CONDITIONS TABLES
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX L
CUMULATIVE IMPACTS ANALYSIS - FERC RESOURCE REPORT 1
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX M
PLAN FOR UNANTICIPATED DISCOVERY OF HISTORIC
PROPERTIES OR HUMAN REMAINS DURING CONSTRUCTION
ATLANTIC COAST PIPELINE, LLC
ATLANTIC COAST PIPELINE
Nationwide Permit 12
Pre -Construction Notification
U.S. Army Corps of Engineers — Wilmington District
North Carolina Department of Water Quality
APPENDIX N
CORRESPONDENCE WITH FEDERALLY RECOGNIZED INDIAN
TRIBES