HomeMy WebLinkAboutNC0020354_Permit Modification_20081201 �0 VV A.
r�9p
\Q Michael F.Easley,Governor
Cq r William G.Ross Jr.,Secretary
]_ North Carolina Department of Environment and Natural Resources
Q C Coleen H.Sullins,Director
Division of Water Quality
December 10,2008
Mr.William G. Terry
Town Manager,Town of Pittsboro
P.O. Box 759
635 East Street
Pittsboro,North Carolina 37312
SUBJECT: NPDES PERMIT MODIFICATION
Town of Pittsboro WWTP
Chatham County
NPDES #NC0020354
Dear Mr.Terry:
Division personnel have reviewed the above-referenced permit modification request submitted to
our office on December 3, 2008. This permit modification authorizes a 3-month extension to the January
1,2009 deadline for Special Condition A.(6.) Total Phosphorus Compliance Plans requiring the Town to
submit a plan by then, allowing time to finalize negotiations and ensure confidence in the developer's
commitment to this project. The new deadline shall be April 1, 2009. Please keep in mind that this
extension applies only to Special Condition A.(6.).
The attached permit page should be placed in the permit and the old page discarded. This permit
modification is issued pursuant to the requirements of North Carolina General Statute 143-215.1 and the
Memorandum of Agreement between North Carolina and the U.S.Environmental Protection Agency
dated October 15, 2007(or as subsequently amended).
If you have any questions or need additional information,please do.not hesitate to contact
Maureen Scardina of my staff at(919) 807-6388.
Sincerely,
Coleen H. Sullins
Enclosure
cc: DWQ,Raleigh Regional Office, Surface Water Protection(w/enclosures)
Central_Files(w/enclosures)
NPDES Unit Files (w/enclosures)
N
�
1617 Mail Service Center Raleigh,NC 27699-1617 (919)733-7015 Customer Service 1 800 623-7748
Permit NC
0020354
r
A. (6.) TOTAL PHOSPHOROUS COMPLIANCE PLANS
By April 1, 2009, the Town of Pittsboro will submit a plan prepared by a professional engineer
documenting how it intends to satisfy the Total Maximum Daily Load(TMDL)that has been established
for Roberson Creek and/or Total Phosphorous permit limits imposed upon the Town of Pittsboro
WWTP based upon the TMDL or other nutrient management strategies for the Cape,Fear River Basin.
The plan should include an analysis of projected growth for the Town and projected future wastewater
needs along with detailed discussion of how the Town plans to meet any needs for additional capacity
and remain in compliance with water quality regulations. The report should discuss any plans for
expansion of the WWTP, potential relocation(s)of the outfall and the effects these decisions may have
on both permitting issues and the actual water quality of the receiving stream. This report shall be
submitted to:
Point Source Branch/NPDES Unit
Division of Water Quality
1617 Mail Service Center
Raleigh,NC 27699-1617
TOWN OF
RANDOLPH VOLLER BOARD OF COMMISSIONERS
Mayor Ty
GENE BROOKS
WILLIAM G.TERRY ; �` HUGH HARRINGTON
Town Manager,, Q PAMELA BALDWIN
:ll'>
CHRIS WALKER
K,
PAUL S MESSICJR'. 'CLINTON E. BEYAN III
Town Attorney too 787
TELEPHONE
P.O. Box 759–635 EastfStreet' - (919)542-4621
PITTSBORO, N.C. 27312 FAX(919)542-7109
December 1,2008 � I •;�� •-���'– `�-��E f-�;.
; si
Mr. Gil Vinzani PAC 3 2008� } �`�
Point Source Branch/NPDES Unit t__ -�-
Division of Water Quality �•r;;� �u=-�;:',-- -----
1617 Mail Service Center ;n;;r
Raleigh,NC 27699-1617 _— -------
RE: Time Extension for Engineering Report for the Town of Pittsboro WWTP NPDES Permit
Dear Mr. Vinzani,
In the Town of Pittsboro's NPDES permit to discharge treated wastewater into Roberson Creek(Permit Number
NC0020354), Section A. (6), it specifies that the Town must submit a plan prepared by a professional engineer
documenting how the Town intends to satisfy the Total Maximum Daily Load that has been established for
Roberson Creek by January 1, 2009. The purpose of-this letter is to request a time extension to move this
deadline to April 1,2009.
As you are well aware, the Town is currently pursuing the construction of a new wastewater treatment plant
with an expected treatment capacity of 3.22 mgd. This new facility will likely discharge in two locations: the
existing location at Roberson Creek and the Haw River at the US64 bridge crossing. The Town and its
consultants have prepared an Environmental Impact Statement for this project that is currently under review by
Hanna Stallings of the Division of Water Quality.
We believe that the proposed new treatment plant is necessary to satisfy the emerging demand for new
development in and around Pittsboro that has been expressed by the development community over the past 24
months. Pittsboro currently is negotiating with multiple developers for the financing of the new plant based on
satisfying their development needs as well as the Town's expected growth rate over the next twenty years. The
Town is requesting a three month time extension beyond the January 1, 2009 deadline in order to finalize these
negotiations and to reach a higher level of confidence in the developers' commitment to the project.
The report will be prepared by a professional engineer and will cover all of the items outlined in Section A. (6.)
of the NPDES permit. If you have any questions about the Town's request,please call me at(919)542-4621 or
call our consultant,Hobbs,Upchurch&Associates,Adam Kiker, at(910)692-5616.
Sincerely,
William G.Te
,�i
Town Manager
cc: Adam Kiker,Hobbs,Upchurch&Associates,P.A.
CHARTERED 1787
' TOWN OF
RANDOLPH VOLLER �� � BOARD OF COMMISSIONERS
Mayor R
ns GENE BROOKS
WILLIAM G.TERRY �` L� HUGH HARRINGTON
Town Manager PAMELA BALDWIN
CD 0 CHRIS WALKER
PAUL S. MESSICK, JR. (n j°4 CLINTON E. BEYAN III
Town Attorney k
-/ TELEPHONE
P.O. Box 759—635 East Street �' (919)542.4621
PITTSBORO, N.C.27312 FAX(919)542-7109
December 1,2008
Mr.Gil Vinzani DEC 2 2008s
Point Source Branch/NPDES Unit ;i Lt i l
Division of Water Quality
1617 Mail Service Center
Raleigh,NC 27699-16I7
RE: Time Extension for Engineering Report for the Town of Pittsboro W WTP NPDES Permit
Dear Mr.Vinzani,
In the Town of Pittsboro's NPDES permit to discharge treated wastewater into Roberson Creek,(Permit Number -
NCW29354), Section A.(6.), it specifies that the Town must submit a plan prepared by a professional engineer
`—documenting how the Town intends to satisfy the Total Maximum Daily Load that has been established for
Roberson Creek by January 1, 2009. The purpose of this letter is to request a time extension to move-this
-deadline-to April i.3009.
As you are well aware, the Town is currently pursuing the construction of a new wastewater treatment plant
with an expected treatment capacity of 3.22 mgd. This new facility will likely discharge in two locations: the
existing location at Roberson Creek and the Haw River at the US64 bridge crossing. The Town and its
consultants have prepared an Environmental Impact Statement for this project that is currently under review by
Hanna Stallings of the Division of Water Quality.
We believe that the proposed new treatment plant is necessary to satisfy the emerging demand for new
development in and around Pittsboro that has been expressed by the development community over the past 24
months. Pittsboro currently is negotiating with multiple developers for the financing of the new plant based on
satisfying their development needs as well as the Town's expected growth rate over the next twenty years. The
Town is requesting a three month time extension beyond the January 1,2009 deadline in order to finalize these
negotiations and to reach a higher level of confidence in the developers'commitment to the project.
The report will be prepared by a professional engineer and will cover all of the items outlined in Section A. (6)
of the NPDES permit. If you have any questions about the Town's request,please call me at(919)5424621 or
call our consultant,Hobbs, Upchurch&Associates,Adam Kiker,at(910)692-5616.
Sincerely,
William G.Te
Town Manager
cc: Adam Kiker, Hobbs,Upchurch&Associates,P.A.
CHARTERED 1787