HomeMy WebLinkAbout20170127 Ver 1_Request for Additional Information_20170131
Wanucha, Dave
From:Bailey, David E CIV USARMY CESAW (US) <David.E.Bailey2@usace.army.mil>
Sent:Tuesday, January 31, 2017 11:55 AM
To:Jamison, John R.
Cc:Wanucha, Dave
Subject:Request for Additional Information: Horse Pen Creek Rd. widening, Greensboro, Guilford Co., NC;
SAW-2013-01953
John,
Thank you for your PCN and attached information, dated 10/28/2016 (received 1/27/2017 via email), for the above referenced
project. I have reviewed the information and need clarification before proceeding with verifying the use of Nationwide Permit 14
http://www.saw.usace.army.mil/Portals/59/docs/regulatory/regdocs/NWP2012/NWP14_3-23.pdf. Please submit the requested
information below (via e-mail is fine) within 30 days of receipt of this Notification, otherwise we may deny verification of the use
of the Nationwide Permit or consider your application withdrawn and close the file:
1) Is dewatering proposed as part of the temporary impacts necessary to remove the Horse Pen Creek culvert? If so, please
ensure that these impacts occur within the proposed temporary impact footprint, and include the method of dewatering. If
dewatering is not proposed, please provide information on how turbidity will be controlled within and downstream of the
project area during culvert removal;
2) Please include general information on how the Horse Pen Creek channel will be restored and stabilized following culvert
removal, as well as sequencing information with bridge construction;
2) Note that mechanized clearing impacts will be considered permanent impacts (though not a loss of waters) unless a wetland
restoration plan is included and approved;
3) Note that the bank stabilization at Stream 6 will be considered permanent impacts (though not a loss of waters) since the rip
rap will not be removed;
4) Please include information regarding the small whorled pogonia survey. Who performed the survey, what was the survey
area, when, and what were the results?
5) Please include a cross section of the outfall and rip rap pad of the Stream 6 culvert extension.
Please let me know if you have any questions.
Sincerely,
Dave Bailey
---
David E. Bailey, PWS
Regulatory Project Manager
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Phone: (919) 554-4884, Ext. 30.
Fax: (919) 562-0421
Email: David.E.Bailey2@usace.army.mil
1