HomeMy WebLinkAboutNC0005088_Preliminary Report_20150505 NCDENR
North Carolina Department of Environment and Natural Resources
Pat McCrory Donald van der Vaart
Governor Secretary
May 5, 2015
Mr. John Elnitsky RECevED�p
Vice President ENR/DW R
Duke Energy
P.O Box 1321, DEC 22C MAY — 8 2015
Charlotte,NC 28201-1007 Watery
ue
Permitt,n9 5ecfion
RE: Cliffside Inactive Ash Basin#5 Main Dam
Preliminary Report Response
Rutherford County
RUTHE-070
Dear Mr. Elnitsky:
A review has been made on the Preliminary Report entitled"Notice of Deficiency(NOD)
—Responses for Recommendations 1, 2, and 3", dated July 25,2014 and received by this office
on July 30, 2014 for the referenced dam. We concur with the conclusions outlined in this report.
This preliminary report contains a slope stability analyses report, a spillway capacity
analysis report, and a geophysical investigation report. The slope stability analyses indicate
factors of safety greater than the minimum criteria. The spillway capacity analysis indicated that
the spillway was undersized and therefore has since then been redesigned and was approved as
Scopes 1 and 3. The geophysical investigation concluded that there was no evidence that would
support the presence of pipes being buried in the embankment and were assumed to have been
removed during construction.
Before beginning repair work on the referenced dam, two (2) sets of plans and
specifications for repair work must be filed with the Division of Energy, Mineral, and Land
Resources for approval pursuant to Title 15A, Subchapter 2K of the North Carolina
Administrative Code.
Please contact Mr. Zahid Khan, Regional Supervisor, Land Quality Section, 610 East
Division of Energy, Mineral, and Land Resources
Energy Section•Geological Survey Section•Land Quality Section
1612 Mail Service Center, Raleigh,North Carolina 27699-1612.919-707-9200/FAX:919-715-8801
512 North Salisbury Street, Raleigh,North Carolina 27604•Internet:http://portal.ncdenr.orq/web/lr/
An Equal Opportunity 1 Affirmative Action Employer—50%Recycled 110%Post Consumer Paper
Mr.John Elnitsky Cliffside Inactive Ash Basin#5 Main Dam
Preliminary Report Response RUTHE-070
May 5,2015
Page 2 of 2
Center Ave., Suite 301, Mooresville,North Carolina 28115, (704) 663-1699 or me at telephone
number(919)707-9220 should you have any questions concerning this matter. We look forward
to receiving final design documents from you.
Sincerely,
7-31/"CA --
0 /-6/1--"
Brian Shauc Cook, PE
Assiitaz i State Dam Safety Engineer
Land Quality Section
1 >r
BSC
cc: Mr. Richard L. Hiner, PE
Mr.Zahid Khan, Land Quality Regional Engineer
Mr. Jeff Poupart, Division of Water Resources
Mr. Randy Hart, Duke Energy
File Name: RUTHE-070 20150505 PRR Cliffside Inactive Ash Basin#5 Main Dam