Loading...
HomeMy WebLinkAbout20080915 Ver 1_ExtensionofRepair Email_20161214 Strickland, Bev From:Oakley, Mark <Mark.Oakley@duke-energy.com> Sent:Wednesday, December 14, 2016 9:56 AM To:Higgins, Karen; Tarver, Fred; Larsen, Cory; Goudreau, Chris J.; bryan_tompkins@fws.gov Cc:Herrin, Randy C; Lewis, Greg D; Lineberger, Jeff; Fragapane, Phil; Finley, Keith A; Dunn, Lynne Subject:RE: Federal Energy Regulatory Commission Staff Request for Additional Documentation re: Advance Notification of Hydroelectric Unit Repairs at Lookout Shoals Development We have just learned bearing damage on the Junior Unit A is worse than anticipated, including a crack on the flange of the bearing and significant corrosion in the slots of the bearing. More extensive repairs are required, which will extend this maintenance outage until January 19, 2017. Duke Energy will continue its pulsing plan for the duration of the outage. I have to advise the FERC of this new date and request an extension of the January 7, 2017, report date they ordered on December 5. Please advise at your earliest convenience if any additional consultation is required as a result of this outage extension. From: Oakley, Mark Sent: Wednesday, November 30, 2016 4:20 PM To: 'Karen.higgins@ncdenr.gov'; 'fred.tarver@ncdenr.gov'; Larsen, Cory; 'chris.goudreau@ncwildlife.org'; bryan_tompkins@fws.gov; Herrin, Randy C; Lewis, Greg D; Lineberger, Jeff; Fragapane, Phil; Finley, Keith A; Rice, Garry S Subject: Federal Energy Regulatory Commission Staff Request for Additional Documentation re: Advance Notification of Hydroelectric Unit Repairs at Lookout Shoals Development This note copies you on the attached response to additional documentation requested by the FERC related to upcoming repairs to Lookout Shoals Hydro. Please contact me if there are any questions. Thanks to resource agency contacts for your rapid response to this request. 1