HomeMy WebLinkAbout20140727 Ver 3_Modifications_20161122Burdette, Jennifer a
From: Bob Zarzecki <bzarzecki@sandec.com>
Sent: Tuesday, November 29, 2016 1:43 PM
To: Alexander, Tasha L SAW; Burdette, Jennifer a
Cc: MaryAnn.Bradshaw@LehighHanson.com; Cara Conder (cconder@res.us); Williams,
Kelly
Subject: RE: Hanson Crabtree Quarry Expansion Project SAW -2014-001246 (DWR#14-0727
_Cert. No.4048)_Phase 2 Mitigation Modification Request
Attachments: Neu -Con SOA Hanson Quarry Expansion Phase II 112116.pdf
Importance: High
Tasha & Jennifer:
Just following up on this.
Any idea when we might get the modified permits/conditions back?
Hanson is eager to resolve this outstanding mitigation payment as soon as possible.
Thanks!
Bob Zarzecki
Wetlands Department Manager
Soil & Environmental Consultants, PA
-----Original Message -----
From: Bob Zarzecki
Sent: Tuesday, November 22, 2016 9:21 AM
To: 'Alexander, Tasha L SAW'; 'Jennifer. Burdette@ncdenr.gov'
Cc: MaryAnn.Bradshaw@ LehighHanson.com; Patrick Smith; Williams, Kelly (kelly.williams@ncdenr.gov)
Subject: RE: Hanson Crabtree Quarry Expansion Project SAW -2014-001246 (DWR#14-0727_Cert.
No.4048)_Phase 2 Mitigation Modification Request
Importance: High
Tasha & Jennifer:
Attached is an acceptance letter from RES to provide the remaining stream credits permitted for the Hanson
Crabtree Quarry expansion project and needed for the Phase 2 stream relocation work. This mitigation was
initially conditioned in the permit and certification to be provided via payment into DMS as RES did not have the
stream credits available at that time. RES now has these stream credits available. Hanson requests the
mitigation conditions be modified to allow the purchase of these required stream credits from RES.
Please let us know if you have any questions or require additional information.
1
PS ... The construction of the stream relocation is not anticipated to occur at this time. Hanson understands that
compliance with other permit conditions beyond just this final mitigation payment is required. Hanson will
submit any other required information and notify the agencies prior to commencing construction of the stream
relocation.
Regards.
Bob Zarzecki
Wetlands Department Manager
Soil & Environmental Consultants, PA
-----Original Message -----
From: Alexander, Tasha L SAW [mailto:Tasha.L.Alexander@usace.army.mil]
Sent: Friday, June 24, 2016 2:52 PM
To: Bob Zarzecki; Gibby, Jean B SAW
Cc: Jack H (Morrisville) USA Garvey, MaryAnn.Bradshaw@ LehighHanson.com, Lee, Toby (Morrisville) USA
(Toby. Lee@hanson.biz), Burnette, Alan C (Atlanta) USA (Alan.Burnette@ heidelbergcement.com), Patrick Smith
Subject: RE: Hanson Crabtree Quarry Expansion Project SAW -2014-001246 (DWR#14-0727_Cert.
No.4048)_Start of Construction Notification
I appreciate the coordination.
Thank you,
Tasha Alexander
Regulatory Specialist
Raleigh Regulatory Field Office
U.S. Army Corps of Engineers -Wilmington District
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Phone: 919-554-4884, extension 35
email: tasha.l.alexander@usace.army.mil The Wilmington District is committed to providing the highest level of
support to the public. To help us ensure we continue to do so, please complete the Customer Satisfaction
Survey located at our website at http://www.saw.usace.army.mil/missions/RegulatoryPermitProgram.aspx to
complete the survey online.
-----Original Message -----
From: Bob Zarzecki [mailto:bzarzecki@sandec.com]
Sent: Friday, June 24, 2016 9:31 AM
To: Gibby, Jean B SAW <Jean.B.Gibby@usace.army.mil>, Alexander, Tasha L SAW
<Tasha.L.Alexander@usace.army.mil>
Cc: Jack H (Morrisville) USA Garvey <Jack.Garvey@hanson.biz>, MaryAnn.Bradshaw@ LehighHanson.com, Lee,
Toby (Morrisville) USA (Toby. Lee@hanson.biz) <Toby.Lee@hanson.biz>, Burnette, Alan C (Atlanta) USA
(Alan.Burnette@ heidelbergcement.com) <Alan.Burnette@ heidelbergcement.com>; Patrick Smith
<psmith@sandec.com>
Subject: [EXTERNAL] RE: Hanson Crabtree Quarry Expansion Project SAW -2014-001246 (DWR#14-0727_Cert.
No.4048)_Start of Construction Notification
Jean & Tasha:
I've removed both Dave and Jennifer for the email chain, as they both said they won't be at this meeting.
I can't be there either, but you all will be fine without me. You're in good hands with Mary Ann, Jack and others.
Also, Patrick Smith may be able to attend to represent S&EC.
Please plan to meet them at the quarry office at 10 am on July 5th. 5001 Duraleigh Road
You'll need to go through site specific safety training which will take a few minutes or so.
Bob Zarzecki
Wetlands Department Manager
Soil & Environmental Consultants, PA
-----Original Message -----
From: Bob Zarzecki
Sent: Tuesday, June 21, 2016 10:27 AM
To: 'Gibby, Jean B SAW', Shaeffer, David L SAW, 'Jennifer. Burdette@ncdenr.gov', Alexander, Tasha L SAW
Cc: Jack H (Morrisville) USA Garvey, MaryAnn.Bradshaw@ LehighHanson.com, Lee, Toby (Morrisville) USA
(Toby. Lee@hanson.biz), Burnette, Alan C (Atlanta) USA (Alan.Burnette@ heidelbergcement.com)
Subject: RE: Hanson Crabtree Quarry Expansion Project SAW -2014-001246 (DWR#14-0727_Cert.
No.4048)_Start of Construction Notification
Jean & Tasha:
I can't make a site meeting on the 5th, as I'm on vacation that entire week. But, you should be fine meeting with
the Hanson folks without me. They're just making sure that they'll have the necessary people there. We'll be in
touch soon to confirm this date.
3
Thanks!
Bob Zarzecki
Wetlands Department Manager
Soil & Environmental Consultants, PA
-----Original Message -
From: Gibby, Jean B SAW [mailto:Jean.B.Gibby@usace.army.mil <mailto:Jean.B.Gibby@usace.army.mil> ]
Sent: Monday, June 20, 2016 5:05 PM
To: Bob Zarzecki, Shaeffer, David L SAW, 'Jennifer. Burdette@ncdenr.gov', Alexander, Tasha L SAW
Cc: Jack H (Morrisville) USA Garvey, MaryAnn.Bradshaw@ Lehigh Hanson.com
<mailto:MaryAnn.Bradshaw@ Lehigh Hanson.com>, Lee, Toby (Morrisville) USA (Toby. Lee@hanson.biz
<mailto:Toby.Lee@hanson.biz> ), Burnette, Alan C (Atlanta) USA (Alan.Burnette@ heidelbergcement.com
<mailto:Alan.Burnette@heidelbergcement.com> )
Subject: RE: Hanson Crabtree Quarry Expansion Project SAW -2014-001246 (DWR#14-0727_Cert.
No.4048)_Start of Construction Notification
:••
Since they plan to start construction on the 5th, would it be acceptable if we met with them around 830 to have
the pre -construction conference on the 5th and that would allow Tasha to see the site, along with me and get
the scoop, hoping to kill two birds with one stone (yep, there was a pun intended in there).
Jean
Jean B. Gibby
Chief, Raleigh Field Office
4
U.S. Army Corps of Engineers
Regulatory Division
3331 Heritage Trade Drive, Suite 105
Wake Forest, NC 27587
(919) 554-4884, Ext. 24
The Wilmington District is committed to providing the highest level of support to the public. To help us ensure
we continue to do so, please complete the Customer Satisfaction Survey located at
Blockedhttp://corpsmapu.usace.army.mil/cm_apex/f?p=136:4:0
<Blockedhttp://corpsmapu.usace.army.mil/cm_apex/f?p=136:4:0>
-----Original Message -----
From: Bob Zarzecki [mailto:bzarzecki@sandec.com <mailto:bzarzecki@sandec.com> ]
Sent: Friday, June 17, 2016 2:24 PM
To: Gibby, Jean B SAW <Jean.B.Gibby@usace.army.mil <mailto:Jean.B.Gibby@usace.army.mil> >, Shaeffer,
David L SAW<David.L.Shaeffer@usace.army.mil <maiIto: David. L.Shaeffer@usace.army.miI> >,
'Jennifer. Burdette@ncdenr.gov' <Jennifer.Burdette@ncdenr.gov <mailto:Jennifer.Burdette@ncdenr.gov> >
Cc: Jack H (Morrisville) USA Garvey <Jack.Garvey@hanson.biz <mailto:Jack.Garvey@hanson.biz> >,
MaryAnn.Bradshaw@ Lehigh Hanson.com <mailto:MaryAnn.Bradshaw@ Lehigh Hanson.com>, Lee, Toby
(Morrisville) USA (Toby. Lee@hanson.biz <mailto:Toby.Lee@hanson.biz> ) <Toby.Lee@hanson.biz
<mailto:Toby.Lee@hanson.biz> >, Burnette, Alan C (Atlanta) USA (Alan.Burnette@ heidelbergcement.com
<mailto:Alan.Burnette@heidelbergcement.com> ) <Alan.Burnette@ heidelbergcement.com
<mailto:Alan.Burnette@heidelbergcement.com> >
Subject: [EXTERNAL] Hanson Crabtree Quarry Expansion Project SAW -2014-001246 (DWR#14-0727_Cert.
No.4048)_Start of Construction Notification
Importance: High
Jean, David & Jennifer:
As required under special condition "f)" of permit SAW -2014-001246, work is scheduled to commence on July 5,
2016 at the Hanson Crabtree Quarry Expansion project. Please confirm receipt of this notification and contact
us if you desire a pre -construction meeting.
Sincerely,
Bob Zarzecki
Wetlands Department Manager
Soil & Environmental Consultants, PA
North Quarter Office Park
8412 Falls of Neuse Road, Suite 104
Raleigh, NC 27615
(919) 846-5900 Office Phone
(919) 256-4517 Direct Line
(919) 846-9467 Fax
(919) 270-2068 Mobile
bzarzecki@sandec.com <mailto:bzarzecki@sandec.com> <mailto:bzarzecki@sandec.com
<mailto:bzarzecki@sandec.com> >
Visit us at SandEC.com<BlockedBlockedhttp://www.SandEC.com> !
This electronic communication, including all attachments, is intended only for the named addressee (s) and may
contain confidential information. This electronic communication may not have passed through our standard
review/quality control process. Design data and recommendations included herein are provided as a matter of
convenience and should not be used for final design. Rely only on final, hardcopy materials bearing the
consultant's original signature and seal. If you are not the named addressee (s), any use, dissemination,
distribution or copying of this communication is prohibited. If you have received this electronic communication
in error, please notify the sender by return e-mail and delete the original communication from your system.
Thank you.
From: Garvey, Jack H (Morrisville) USA [mailto:Jack.Garvey@hanson.biz <mailto:Jack.Garvey@hanson.biz> ]
Sent: Friday, June 17, 2016 2:09 PM
To: Bob Zarzecki
Subject: FW: correction
:••
All of the credits have been purchased for Phase 1 of the Crabtree Expansion, and the supporting documents
are attached. The contractors are scheduled to start the project on July 5, 2016. This email correspondence is
intended to serve as Start of Construction Notification for Action ID: SAW -2014-01246.
Jack Garvey
Environmental Manager
Hanson Aggregates Southeast, LLC
2101 Gateway Centre Blvd, Suite 100
Morrisville, NC 27560
Tel: 919 380 2746
Cell: 336 669 7565
Fax: 919 380 2756
Jack.Garvey@hanson.com <mailto:Jack.Garvey@hanson.com> <mailto:Jack.Garvey@hanson.com
<mailto:Jack.Garvey@hanson.com> >
Blocked Blockedwww.hanson.com<BlockedBlocked http:Hwww.hanson.com>
EBX Stream and Wetland Banks
Statement of Availability November 21, 2016
NC Division of Water Resources
Ms. Jennifer Burdette
512 N. Salisbury St.
9' floor
Raleigh, NC 27604
Re Project: Hanson Crabtree Quarry Expansion Phase II
U.S. Army Corps of Engineers
Mr. David Shaeffer
Raleigh Regulatory Field Office
3331 Heritage Trade Center, Suite 105
Wake Forest, NC 27587
This document confirms that Hanson Aeereeates Southeast, LLC (Applicant) for the Hanson Crabtree
Quarry Expansion Phase II (Project) has expressed an interest to utilize 510 Stream Mitigation
Credits from the EBX-Neuse I sponsored Neu -Con Wetland & Stream Umbrella Mitigation Bank,
specifically the Selma Mill Site in Neuse HUC 03020201. As the official Bank Sponsor, EBX-Neuse I,
attests to the fact that mitigation is available for reservation at this time.
These mitigation credits are not considered secured, and consequently are eligible to be used for alternate
purposes by the Bank Sponsor, until payment in full is received from the Applicant resulting in the
issuance of a Mitigation Credit Transfer Certificate by the bank acknowledging that the Applicant has
fully secured credits from the bank and the Bank Sponsor has accepted full responsibility for the
mitigation obligation requiring the credits/units.
The Bank Sponsor will issue the Mitigation Credit Transfer Certificate within three (3) days of receipt of
the purchase price. Bank Sponsor shall provide to Applicant a copy of the Mitigation Credit Transfer
Certificate and a documented copy of the debit of credits from the Bank Official Credit Ledger(s),
indicating the permit number and the resource type secured by the Applicant. A copy of the Mitigation
Credit Transfer Certificate, with an updated Official Credit Ledger will also be sent to regulatory agencies
showing the proper documentation.
If any questions need to be answered, please contact me at 919-209-1052.
Best Regards,
Ca�
Cara S. Conder
Resource Environmental Solutions, LLC
302 Jefferson Street, Suite 110
Raleigh, NC 27605