HomeMy WebLinkAbout20140705 Ver 3_NWP 27 Authorization_SAW-2015-00710_20161014 U.S. ARMY CORPS OF ENGINEERS
WILMINGTON DISTRICT
Action ID: SAW-2015-00710 County: Johnston USGS Quad: NC-SELMA
GENERAL PERMIT (REGIONAL AND NATIONWIDE)VERIFICATION
Applicant: Resource Environmental Solutions
Attn: Mr.Daniel Ingram
Address: 302 Jefferson Street, Suite 110
Raleigh,North Carolina 27605
Size and location of property (water body, road name/number, town, etc.): The 34.2 acre Selma Mill stream mitigation
site (Neu-con UMB) is located north of the intersection of W. Chestnut St. and NC Highway 96, north of Selma,
Johnston County,North Carolina.
Site Coordinates: 35.545544°N,-78.283277°W Waterway: UT to Neuse River River Basin: Upper Neuse
Description of project area and activity: This permit authorizes mechanized land clearing, stream relocation,
excavation,and the placement of fill material associated with stream restoration activities for the Selma Mill Stream
Mitigation Site.The temporary impacts associated with this permit include 1.12 acres of riparian wetlands and 5,775
linear feet of stream channel. See page 2 for details.
Applicable Law: ® Section 404 (Clean Water Act, 33 USC 1344)
❑ Section 10(Rivers and Harbors Act, 33 USC 403)
Authorization: Nationwide or Regional General Permit Number(s): 27
SEE ATTACHED NATIONWIDE CONDITIONS AND SPECIAL CONDITIONS ON PAGE 2 OF THIS FORM
Your work is authorized by the above referenced permit provided it is accomplished in strict accordance with the attached
conditions and your submitted application and attached information dated October 5, 2016. Any violation of the attached
conditions or deviation from your submitted plans may subject the permittee to a stop work order,a restoration order and/or
appropriate legal action.
• This verification will remain valid until the expiration date identified below unless the nationwide authorization is modified,
suspended or revoked. If, prior to the expiration date identified below, the nationwide permit authorization is reissued and/or
modified,this verification will remain valid until the expiration date identified below,provided it complies with all requirements
of the modified nationwide permit. If the nationwide permit authorization expires or is suspended,revoked, or is modified, such
that the activity would no longer comply with the terms and conditions of the nationwide permit,activities which have commenced
(i.e., are under construction) or are under contract to commence in reliance upon the nationwide permit, will remain authorized
provided the activity is completed within twelve months of the date of the nationwide permit's expiration, modification or
revocation,unless discretionary authority has been exercised on a case-by-case basis to modify,suspend or revoke the authorization.
• Activities subject to Section 404(as indicated above)may also require an individual Section 401 Water Quality Certification. You
should contact the NC Division of Water Resources(telephone 919-807-6300)to determine Section 401 requirements.
• For activities occurring within the twenty coastal counties subject to regulation under the Coastal Area Management Act(CAMA),
prior to beginning work you must contact the N.C. Division of Coastal Management.
• This Department of the Army verification does not relieve the permittee of the responsibility to obtain any other required Federal,
State or local approvals/permits.
• If there are any questions regarding this verification, any of the conditions of the Permit, or the Corps of Engineers regulatory
program,please contact Kim Browning at telephone(919)554-4884 x60.
BROWNING.KIMBERLY.D DOWNING.KMBERLY.DANIELLE.15-83510
DN:r-U5,o=U.S.G—,e .m n4ou=DOD,ou=GKI,au=USA,
Corps Regulatory Official: ANIELLE.1527683510 Dah201fi.101 08B16:08-04ppLLE:152)683510 Date: October 14,2016
Expiration Date of Nationwide Permit Verification: March 18,2017
Page 1 of 3
Summa of Authorized Impacts and Required Mitigation
Open Water(ac) Wetland(ac) Streams(1f)
NWP Impact Label Permanent Impact Label Temporary Impact Type Impact Label Temporary
Type Type
27 Excavation W1 0.22 Relocation S1 Reach A 2715
27 Excavation W2 0.07 Relocation S2 Reach B 2208
27 Excavation W3 0.09 Grading S3 Reach C 852
27 Excavation W4 0.74
27
27
27
27
27
Impact 1.12 0 0 5775
Totals
Total Loss of Waters of the U.S. (ac) 0* Total Loss of Waters of the U.S. (If) 0* 0*
Required Wetland Mitigation (ac) I I Required Stream Mitigation(If)
*Impacts are associated with stream restoration activities and are expected to result in a net gain in Waters of the US.
Additional Remarks and/or Special Permit Conditions:
1. The activities will be conducted in accordance with the information submitted and meet the conditions applicable
to the NWP, as described at Part C of the NWP Program and the Wilmington District NWP Regional Conditions.
2. This Nationwide Permit verification does not imply approval of the suitability of this property for
compensatory mitigation for any particular project. The use of any portion of this site as compensatory mitigation
for a particular project will be determined during our public interest review and 404(b)(1) Guidelines analysis
during the permit review process for that project.
Copy Furnished: NCIRT(Electronic Copy)
Page 2 of 3
Determination of Jurisdiction
A. ❑ Based on preliminary information, there appear to be waters of the US including wetlands within the above
described project area. This preliminary determination is not an appealable action under the Regulatory Program
Administrative Appeal Process(Reference 33 CFR Part 331).
B. ❑ There are Navigable Waters of the United States within the above described project area subject to the permit
requirements of Section 10 of the Rivers and Harbors Act and Section 404 of the Clean Water Act. Unless there is
a change in the law or our published regulations,this determination may be relied upon for a period not to exceed
five years from the date of this notification.
C. ❑ There are waters of the US and/or wetlands within the above described project area subject to the permit
requirements of Section 404 of the Clean Water Act(CWA)(33 USC § 1344). Unless there is a change in the law
or our published regulations, this determination may be relied upon for a period not to exceed five years from the
date of this notification.
D. ® The jurisdictional areas within the above described project area have been identified under a previous action. Please
reference the jurisdictional determination issued on May 25,2016 (Action ID: SAW-2015-00710).
E. Attention USDA Program Participants: This delineation/determination has been conducted to identify the limits of
Corps' Clean Water Act jurisdiction for the particular site identified in this request. The delineation/determination
may not be valid for the wetland conservation provisions of the Food Security Act of 1985. If you or your tenant are
USDA Program participants, or anticipate participation in USDA programs,you should request a certified wetland
determination from the local office of the Natural Resources Conservation Service,prior to starting work.
F. Appeals Information (This information applies only to approved jurisdictional determinations as indicated in
B and C above): This correspondence constitutes an approved jurisdictional determination for the above described
site. If you object to this determination,you may request an administrative appeal under Corps regulations at 33 CFR
Part 331. Enclosed you will find a Notification of Appeal Process(NAP) fact sheet and request for appeal(RFA)
form. If you request to appeal this determination you must submit a completed RFA form to the following address:
US Army Corps of Engineers
South Atlantic Division
Attn: Jason Steele,Review Officer
60 Forsyth Street SW, Room 10M15
Atlanta, Georgia 30303-8801
Phone: (404) 562-5137
In order for an RFA to be accepted by the Corps, the Corps must determine that it is complete;that it meets the criteria for
appeal under 33 CFR part 331.5, and that it has been received by the Division Office within 60 days of the date of the NAP.
Should you decide to submit an RFA form,it must be received at the above address by . It is not necessary to submit
an RFA form to the District Office if you do not object to the determination in this correspondence.
BaIKiBE
BROWN ING.KIMBERLY. NwALrDANiEUE,sz>0e3s,0
;.—D,—PKI,
SA,
Corps Regulatory Official: DANIELLE.1527683510 �,b" a6Rs, �'E 'fi8510o ,—a _.0
Date:
October 14,2016 Expiration Date of Jurisdictional Determination: N/A
Page 3 of 3
WILMINGTON DISTRICT
POST-CONSTRUCTION COMPLIANCE FORM
Action ID Number: SAW-2015-00710 County: Johnston
Permittee: Resource Environmental Solutions Attn: Mr.Daniel Ingram
Date Permit Issued: October 14, 2016
Project Manager: Kim Browning
Upon completion of the activity authorized by this permit and any mitigation required by the permit, sign
this certification and return it to the address of the Regulatory Field Office indicated below:
❑ Asheville Regulatory Field Office ❑ Washington Regulatory Field Office
US Army Corps of Engineers US Army Corps of Engineers
151 Patton Avenue, Room 208 2407 West Fifth Street
Asheville,North Carolina 28801-5006 Washington,NC 27889
® Raleigh Regulatory Field Office ❑ Wilmington Regulatory Field Office
US Army Corps of Engineers US Army Corps of Engineers
3331 Heritage Trade Drive, Suite 105 69 Darlington Avenue
Wake Forest,North Carolina 27587 Wilmington, NC 28403
Please note that your permitted activity is subject to a compliance inspection by a U. S. Army Corps of
Engineers representative. If you fail to comply with this permit you are subject to permit suspension,
modification, or revocation.
I hereby certify that the work authorized by the above referenced permit has been completed in accordance
with the terms and condition of the said permit,and required mitigation was completed in accordance with
the permit conditions.
Signature of Permittee Date