From:Warren Eadus <weadus@quible.com>
Sent:Thursday, October 20, 2016 1:58 PM
To:Dunn, Maria T.; Spears, Courtney; Cynthia Rountree; Scarbraugh, Anthony; Staples,
Shane; Pelletier, Josh R SAW
Cc:Troy Murphy
Subject:RE: Doug Twiddy CAMA Major App in Dare County
Attachments:P14001.1-REVISED CAMA PLAN-10-20-2016.pdf
All,
Please see the attached revisions to the Doug Twiddy Elijah Baum CAMA Major application. We have pulled the
proposed bulkhead landward of the rip rap on the peninsula as recommended by NCWRC.
Courtney,
Please let me know if you require additional hard copies (how many) and whether or not we need to amend the
application (the attached proposal reduces the total length of bulkhead by about 15 feet).
Thanks,
Warren D. Eadus, P.G.
President
Quible & Associates, P.C.
8466 Caratoke Hwy, Bldg 400
Powells Point NC 27966
PO Drawer 870
Kitty Hawk, NC 27949
t 252.491.8147
f 252.491.8146
m 252.202.8166
www.quible.com
LEGAL DISCLAIMER
The information transmitted is intended solely for the individual or entity to which it is addressed and may contain confidential and/or privileged material.
Any review, retransmission, dissemination or other use of or taking action in reliance upon this information by persons or entities other than the intended
recipient is prohibited. If you have received this email in error please contact the sender and delete the material from any computer.
From: Dunn, Maria T. \[mailto:maria.dunn@ncwildlife.org\]
Sent: Thursday, October 20, 2016 11:45 AM
To: Spears, Courtney <courtney.spears@ncdenr.gov>; Cynthia Rountree <cynthia.rountree@ncdenr.gov>; Scarbraugh,
Anthony <anthony.scarbraugh@ncdenr.gov>; Staples, Shane <shane.staples@ncdenr.gov>; Pelletier, Josh R SAW
<Josh.R.Pelletier@usace.army.mil>
Cc: Warren Eadus <weadus@quible.com>
Subject: RE: Doug Twiddy CAMA Major App in Dare County
Courtney,
1
NCWRC has reviewed the modified plans for the Doug Twiddy project received by email on October 17, 2016. We
appreciate the removal of the proposed access channel from the project application. The removal of the access channel
addresses our main concern that was to be presented in our objection letter.
However, there is still concern with the proposed “encapsulation” of the existing riprap with a bulkhead. The
southeastern shore of the peninsula is already stabilized. The waterward bulkhead installation of an already stabilized
shoreline increases impacts to public trust waters and would likely increase shallow water habitat and SAV habitat scour
due to the waters’ interface with the vertical structure. Furthermore, a study conducted by the NCWRC determined that
fish abundance and diversity was significantly higher along riprap shorelines than along bulkhead sites. Therefore, we
recommend allowing the riprap to remain on the southeast shore of the peninsula to avoid increased scour of shallow
water and SAV habitats, to allow the existing fishery habitat opportunities to continue, and to offset the impact of filling
important fringe wetland habitats by the proposed bulkhead within the basin area. If the applicant continues to pursue a
bulkheaded shoreline, the bulkhead should be placed landward of the existing rip-rap to minimize impacts to aquatic
resources.
Thank you for the opportunity to review this permit application modification. If I can be of additional assistance, please
let me know.
Maria
------------------------------
Maria T. Dunn
Coastal Coordinator
NC Wildlife Resources Commission
943 Washington Sq. Mall
Washington, NC 27889
office: 252-948-3916
fax: 252-975-3716
www.ncwildlife.org
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.
From: Spears, Courtney
Sent: Monday, October 17, 2016 11:06 AM
To: Cynthia Rountree <cynthia.rountree@ncdenr.gov>; Scarbraugh, Anthony <anthony.scarbraugh@ncdenr.gov>; Dunn,
Maria T. <maria.dunn@ncwildlife.org>; Staples, Shane <shane.staples@ncdenr.gov>; Pelletier, Josh R SAW
<Josh.R.Pelletier@usace.army.mil>
Cc: Warren Eadus <weadus@quible.com>
Subject: Doug Twiddy CAMA Major App in Dare County
Good morning,
Mr. Warren Eadus submitted an updated workplan drawing and MP-2 reflecting the removal of the proposed access
channel from Mr. Doug Twiddy’s project in Dare County that you are currently reviewing. I have attached both
documents to this email for your consideration. Since the workplan drawing was an oversized plat I scanned the area
most relevant to the proposed excavation – everything else in the project remains unchanged. Please provide any
2
comments you may have at your earliest convenience, and if you require any additional information or have questions,
please let me know.
Kind regards,
Courtney Spears
Assistant Major Permits Coordinator
Division of Coastal Management
Department of Environmental Quality
252 808 2808 office
courtney.spears@ncdenr.gov
400 Commerce Avenue
Morehead City, NC 28557
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
3
Map