HomeMy WebLinkAbout20080788 Ver 1_401 Application_2008050811 THE WOOTEN COMPANY E N G I N E E R I N G P L A N N I N G ARCHITECTURE May 6, 2008 Ms. Cyndi Karoly Division of Water Quality 401/Wetlands Unit 1650 Mail Service Center Raleigh, NC 27699-1650 Re: Pre-Construction Notification Application Tyrrell County Water and Sewer Districts 1 &2 Pressure Sewer System Tyrrell/Washington County, North Carolina TWC No. 2876-B Dear Ms. Karoly: 0 8 0 7 8 8 COURTESY l op On behalf of Tyrrell County, please find enclosed five (5) copies of the following items regarding the above referenced project. Please note that this is a courtesy copy and we are not requesting written concurrence. • Pre-Construction Notification Application • Applicable construction drawings (reduced scale) • USGS maps and SCS Soils maps showing location of project • Other appurtenant items to the Application (stream crossing coordinates) 120 North Boylan Avenue Raleigh NC 27603-1423 919.828.0531 Please note that included is CD of the applicable construction drawings so that they can be viewed and/or printed at full scale. (on 24" x 36" scale: 1" = 50') This project proposes to construct approximately 193,400 linear feet of force main ranging in size from 2 to 8-inch diameter. Currently residents of the Scuppernong Township are being provided sewer service through failing septic systems. The proposed pressure sewer system will provide new sewer service to replace these systems. To construct this project as proposed, it is necessary to impact 32 streams in various locations as shown in the attached application package. No permanent impacts are proposed for this project and the preconstruction grade (contours) of streams will be reestablished after disturbance. I trust this information is sufficient; however, if you should have any questions or require additional information, please do not hesitate to contact us. Sincerely, THE WOOTEN COMPANY Stephanie A. Bliss, E.I. MAY 1 2008 WFLA T09HW AWA Enclosures: As stated. cc: Mr. W. Mack Carawan, Jr. - County Manager fax 919.834.3589 i i i 1 1 1 1 PRE-CONSTRUCTION NOTIFICATION SUBMITTAL FOR TYRRELL COUNTY WATER AND SEWER DISTRICTS 1 & 2 PRESSURE SEWER SYSTEM 2876-B APRIL 2008 ?, tist o? TO 0 MPS p?9L OAS PNQ SS?? ? p?10 THE WOOTEN COMPANY E: N GI NE E RING Ft A N N I N G An C H I TE C i U RE 1:?0 North Boylan Avenue Raleigh NC 21503-1423 9198'8.11531 tax i19,834,3589 1 1 t TABLE OF CONTENTS Title Pages Pre-Construction Notification Application ........................................................................ 5-14 APPENDICES Appendix A - Vicinity Maps & Site Plans ........................................................................ 1-38 Appendix B - Site Coordinates .......................................................................................... 1-1 Appendix C - Soils Maps & USGS Maps of Project Area ................................................ 1-8 Office Use Only: Form Version March 05 0 8 0 7 8 8 USACE Action ID No. DWQ No. (it any particular item is not applicable to this project, please enter "Not Applicable" or "N/A".) 1 I. Processing G ??UM,V ,E 1. Check all of the approval(s) requested for this project: COPY ® Section 404 Permit ? Riparian or Watershed Buffer Rules ? Section 10 Permit ? Isolated Wetland Permit from DWQ ? 401 Water Quality Certification ? Express 401 Water Quality Certification 2. Nationwide, Regional or General Permit Number(s) Requested: NW 12 1 1 3. If this notification is solely a courtesy copy because written approval for the 401 Certification is not required, check here: 4. If payment into the North Carolina Ecosystem Enhancement Program (NCEEP) is proposed for mitigation of impacts, attach the acceptance letter from NCEEP, complete section VIII, and check here: ? 5. If your project is located in any of North Carolina's twenty coastal counties (listed on page 4), and the project is within a North Carolina Division of Coastal Management Area of Environmental Concern (see the top of page 2 for further details), c ec he - ?: i Ell W II. Applicant Information MAY 7 2008 1. Owner/Applicant Information Name: W. Mack Carawan, Jr. D`"'` - g ?k weTFR BWC-H Mailing Address: P.O. Box 449 riesnN?sTnRti Columbia NC 27925 Telephone Number: 252-796-1371 Fax Number: 252-796-1188 E-mail Address: wmcarawann,tyrrellcounty.net 2. Agent/Consultant Information (A signed and dated copy of the Agent Authorization letter must be attached if the Agent has signatory authority for the owner/applicant.) Name: W. Brian Johnson P.E. Company Affiliation: The Wooten Company Mailing Address: 120 N. Boylan Avenue. Raleigh NC 27603 Telephone Number: 919-828-0531 Fax Number: 919-834-3589 E-mail Address: biohnson(a thewootencompany.com Page 5 of 14 III. Project Information 1 Attach a vicinity map clearly showing the location of the property with respect to local landmarks such as towns, rivers, and roads. Also provide a detailed site plan showing property boundaries and development plans in relation to surrounding properties. Both the vicinity map and site plan must include a scale and north arrow. The specific footprints of all buildings, impervious surfaces, or other facilities must be included. If possible, the maps and plans should include the appropriate USGS Topographic Quad Map and NRCS Soil Survey with the property boundaries outlined. Plan drawings, or other maps may be included at the applicant's discretion, so long as the property is clearly defined. For administrative and distribution purposes, the USACE requires information to be submitted on sheets no larger than 11 by 17-inch format; however, DWQ may accept paperwork of any size. DWQ prefers full-size construction drawings rather than a sequential sheet version of the full-size plans. If full-size plans are reduced to a small scale such that the final version is illegible, the applicant will be informed that the project has been placed on hold until decipherable maps are provided. 1. Name of project: Tyrrell County Water and Sewer District 1 & 2 - Pressure Sewer System 2. T.I.P. Project Number or State Project Number (NCDOT Only): N/A 3. Property Identification Number (Tax PIN): N/A (Linear project in NCDOT R/W and T rrell County Sewer Easement) t 4. Location County: Tyrrell/Washington Nearest Town: Creswell Subdivision name (include phase/lot number): N/A Directions to site (include road numbers/names, landmarks, etc.): From the intersection of Old NC Hwy 94 and Allizood Road (SR 1200) extendiniz northeast to the intersection of US Hwy 64 and Old Columbia Road (SR 1110) 5. Site coordinates (For linear projects, such as a road or utility line, attach a sheet that separately lists the coordinates for each crossing of a distinct waterbody.) Decimal Degrees (6 digits minimum): WI: 35° 51'54" ON 76° 23'18" °W W2: 35°55' 38" ON 76° 21' 35" °W W3: 35°55' 39" ON 76° 19' 44" °W W4: 35°55' 42" ON 76° 19' 9" °W 6. Property size (acres): 47 acres 7. Name of nearest receiving body of water: Scuppernong River/Bulls Bay 8. River Basin: Pasquotank I (Note - this must be one of North Carolina's seventeen designated major river basins. The River Basin map is available at http:/ih2o.enr.state.nc.us/admin/mgps/.) I Page 6 of 14 9. Describe the existing conditions on the site and general land use in the vicinity of the project at the time of this application: Existing Residential and Commercial establishments i 10. Describe the overall project in detail, including the type of equipment to be used: The project will involve the installation of a new water and sewer system Equipment used will include track hoes and rubber tire back hoes. 11. Explain the purpose of the proposed work: To replace ailing septic systems with a sewer i system to meet the needs of Tyrrell County IV. Prior Project History i If jurisdictional determinations and/or permits have been requested and/or obtained for this project (including all prior phases of the same subdivision) in the past, please explain. Include the USACE Action ID Number, DWQ Project Number, application date, and date permits and certifications were issued or withdrawn. Provide photocopies of previously issued permits, certifications or other useful information. Describe previously approved wetland, stream and buffer impacts, along with associated mitigation (where applicable). If this is a NCDOT project, list and describe permits issued for prior segments of the same T.I.P. project, along with construction schedules. - None I V. Future Project Plans Are any future permit requests anticipated for this project? If so, describe the anticipated work, and provide justification for the exclusion of this work from the current application. None VI. Proposed Impacts to Waters of the United States/Waters of the State It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to wetlands, open water, and stream channels associated with the project. Each impact must be listed separately in the tables below (e.g., culvert installation should be listed separately from riprap dissipater pads). Be sure to indicate if an impact is temporary. All proposed impacts, permanent and temporary, must be listed, and must be labeled and clearly identifiable on an accompanying site plan. All wetlands and waters, and all streams (intermittent and perennial) should be shown on a delineation map, whether or not impacts are proposed to these systems. Wetland and stream evaluation and delineation forms should be included as appropriate. Photographs may be included at the applicant's discretion. If this proposed impact is strictly for wetland or stream mitigation, list and describe the impact in Section VIII below. If additional space is needed for listing or description, please attach a separate sheet. I Page 7 of 14 t 1 t 1. Provide a written description of the proposed impacts: Wetlands will be impacted bx construction as outlined below. 2. Individually list wetland impacts. Types of impacts include, but are not limited to mechanized clearing, grading, fill, excavation, flooding, ditching/drainage, etc. For dams, se aratel list impacts due to both structure and flooding. *These wetlands will be Directionally Drilled. Wetland Impact Type of Wetland Located within Distance to Nearest Area of Site Number Type of Impact (e.g., forested, marsh, 100-year Floodplain Stream Impact (acres) (indicate on map) herbaceous, bog, etc.) (linear (yes/no) feet) WI Temporary Forested Yes adjacent 0.0069 Permanent None W2 * Temporary Permanent Forested Yes adjacent None None W3 * Temporary Permanent Forested Yes adjacent None None W4 * Temporary Permanent Forested Yes adjacent None None Total Wetland Impact (acres) Temp: 0.0069 Perm:O 3. List the total acreage (estimated) of all existing wetlands on the property: Linear Corridor - Total wetland acreage within construction corridor) equals total disturbed 1 1 1 t 4. Individually list all intermittent and perennial stream impacts. Be sure to identify temporary impacts. Stream impacts include, but are not limited to placement of fill or culverts, dam construction, flooding, relocation, stabilization activities (e.g., cement walls, rip-rap, crib walls, gabions, etc.), excavation, ditching/straightening, etc. If stream relocation is proposed, plans and profiles showing the linear footprint for both the original and relocated streams must be included. To calculate acreage, multiply length X width, then divide by 43.560. Stream Impact Number (indicate on ma P) Stream Name Type of Impact Intermittent. Perennial Intermittent? Average Stream Width Before Impact Impact Length (linear feet) Area of Impact ) (acres) 1-3 UT of Scuppernong River Utility crossing Perennial 2 30 0.0014 2-4 UT of Scuppernong River Utility crossing Perennial 2 30 0.0014 3-5 UT of Scuppernong River Utility crossing Perennial 2 20 0.0009 4-6 UT of Scuppernong River Utility crossing Perennial 8 30 0.0055 5-8 UT of Scuppernong River Utility crossing Perennial 3 20 0.0014 6-10 UT of Scuppernong River Utility crossing Perennial 2 10 0.0005 7-13 UT of Scuppernong River Utility crossing Perennial 10 10 0.0023 8-14 UT of Scuppernong River Utility crossing Perennial 20 10 0.0046 9-16 UT of Scuppernong River Utility crossing Perennial 3 15 0.0010 Page 8 of 14 i t 10-19 UT of Scuppernong River Utility crossing Perennial 8 10 0.0018 11-20 UT of Scuppernong River Utility crossing Perennial 2 15 0.0007 12-22 UT of Scuppernong River Utility crossing Perennial 8 10 0.0018 13-23 UT of Bunton Creek Utility crossing Perennial 12 10 0.0028 14-24 UT of Bunton Creek Utility crossing Perennial 12 10 0.0028 15-25 UT of Bunton Creek Utility crossing Perennial 4 15 0.0014 16-27 UT of Bunton Creek Utility crossing Perennial 3 10 0.0007 17-28 UT of Scuppernong River Utility crossing Perennial 3 15 0.0010 18-30 UT of Scuppernong River Utility crossing Perennial 8 10 0.0018 19-31 UT of Scuppernong River Utility crossing Perennial 6 60 0.0083 20-32 UT of Scuppernong River Utility crossing Perennial 5 25 0.0029 21-33 UT of Scuppernong River Utility crossing Perennial 7 25 0.0040 22-34 UT of Scuppernong River Utility crossing Perennial 3 50 0.0034 23-36 UT of Scuppernong River Utility crossing Perennial 3 30 0.0021 24-37 UT of Scuppernong River Utility crossing Perennial 10 10 0.0023 25-40 UT of Scuppernong River Utility crossing Perennial 3 10 0.0007 26-1 * UT of Scuppernong River Utility crossing Perennial 4 0 0 27-7* UT of Scuppernong River Utility crossing Perennial 25 0 0 28-9* UT of Scuppernong River Utility crossing Perennial 30 0 0 29-18* UT of Scuppernong River Utility crossing Perennial 30 0 0 30-46* UT of Scuppernong River Utility crossing Perennial 5 0 0 31-47* UT of Bunton Creek Utility crossing Perennial 20 0 0 32-48* UT of Bunton Creek Utility crossing Perennial 25 0 0 Total Stream Impact (by length and acreage) 490 0.0575 *These streams will be Directionally Drilled. 5. Individually list all open water impacts (including lakes, ponds, estuaries, sounds, Atlantic Ocean and any other water of the U.S.). Open water impacts include, but are not limited to fill, excavation, dredging, flooding, drainage, bulkheads, etc. 1 t Open Water Impact Site Number indicate on ma Name of Waterbody (if applicable) Type of Impact Type of Waterbody (lake, pond, estuary, sound, bay, ocean, etc. Area of Impact acres None Total Open Water Impact (acres) I Page 9 of 14 6. List the cumulative impact to all Waters of the U.S. resulting from the project: Stream Impact (acres): 0.0575 Wetland Impact (acres): Temp. 0.0069 and Perm. None 0.0069 Open Water Impact (acres): None Total Impact to Waters of the U.S. (acres) None Total Stream Impact (linear feet): 490 ** There are no permanent impacts other than the conversion of forested wetlands to herbaceous wetlands within the 10' maintenance corridor centered over the pipe alignment. No fill will be placed within jurisdictional wetlands. 7. Isolated Waters Do any isolated waters exist on the property? ? Yes ® No Describe all impacts to isolated waters, and include the type of water (wetland or stream) and the size of the proposed impact (acres or linear feet). Please note that this section only applies to waters that have specifically been determined to be isolated by the USACE. N/A 8. Pond Creation If construction of a pond is proposed, associated wetland and stream impacts should be I included above in the wetland and stream impact sections. Also, the proposed pond should be described here and illustrated on any maps included with this application. Pond to be created in (check all that apply): ? uplands ? stream ? wetlands Describe the method of construction (e.g., dam/embankment, excavation, installation of draw-down valve or spillway, etc.): Proposed use or purpose of pond (e.g., livestock watering, irrigation, aesthetic, trout pond, I local stormwater requirement, etc.): Current land use in the vicinity of the pond: Size of watershed draining to pond: Expected pond surface area: VII. Impact Justification Avoidance and Minimization ( ) 1 Specifically describe measures taken to avoid the proposed impacts. It may be useful to provide information related to site constraints such as topography, building ordinances, accessibility, and financial viability of the project. The applicant may attach drawings of alternative, lower-impact 1 site layouts, and explain why these design options were not feasible. Also discuss how impacts were minimized once the desired site plan was developed. If applicable, discuss construction techniques to be followed during construction to reduce impacts. The sewer force main has been located 5eet from the edge of pavement to minimize impact Large wetlands, as well as streams that are larger than 12 feet will be directionally drilled The sewer force main has been located to minimize the disturbance to wetlands and where possible the sewer was routed around the wetlands. I Page 10 of 14 t VIII. Mitigation DW - In accordance with 15A NCAC 2H .0500 mitigation may be required by the NC Division of Water Quality for projects involving greater than or equal to one acre of impacts to 1 freshwater wetlands or greater than or equal to 150 linear feet of total impacts to perennial streams. USACE - In accordance with the Final Notice of Issuance and Modification of Nationwide Permits, published in the Federal Register on January 15, 2002, mitigation will be required when necessary to ensure that adverse effects to the aquatic environment are minimal. Factors including size and type of proposed impact and function and relative value of the impacted aquatic resource will be considered in determining acceptability of appropriate and practicable mitigation as proposed. Examples of mitigation that may be appropriate and practicable include, but are not limited to: reducing the size of the project; establishing and maintaining wetland and/or upland vegetated buffers to protect open waters such as streams; and replacing losses of aquatic resource functions and values by creating, restoring, enhancing, or preserving similar functions and values, preferable in the same watershed. If mitigation is required for this project, a copy of the mitigation plan must be attached in order for USACE or DWQ to consider the application complete for processing. Any application lacking a required mitigation plan or NCEEP concurrence shall be placed on hold as incomplete. An applicant may also choose to review the current guidelines for stream restoration in DWQ's Draft Technical Guide for Stream Work in North Carolina, available at http://h2o.enr.state.nc.us/ncwetiands/strmgide.hti-ni. I 1 P id b i f . rov e a r e description of the proposed mitigation plan. The description should provide as much information as possible, including, but not limited to: site location (attach directions 1 and/or map, if offsite), affected stream and river basin, type and amount (acreage/linear feet) of mitigation proposed (restoration, enhancement, creation, or preservation), a plan view, preservation mechanism (e.g., deed restrictions, conservation easement, etc.), and a description of the current site conditions and proposed method of construction. Please attach a separate sheet if more space is needed. Mitikatinz through avoidance and minimization 2. Mitigation may also be made by payment into the North Carolina Ecosystem Enhancement Program (NCEEP). Please note it is the applicant's responsibility to contact the NCEEP at I (919) 715-0476 to determine availability, and written approval from the NCEEP indicating that they are will to accept payment for the mitigation must be attached to this form. For additional information regarding the application process for the NCEEP, check the NCEEP wbsite at http://h2o.enr.state.nc.us/wrp/index.htm. If use of the NCEEP is proposed, please check the appropriate box on page five and provide the following information: Amount of stream mitigation requested (linear feet): N/A Amount of buffer mitigation requested (square feet): N/A Amount of Riparian wetland mitigation requested (acres): N/A 1 Page 11 of 14 Ix. 1 1 1 t X. t t t t 1 1 1 1 Amount of Non-riparian wetland mitigation requested (acres): N/A Amount of Coastal wetland mitigation requested (acres): N/A Environmental Documentation (required by DWQ) 1. Does the project involve an expenditure of public (federal/state/local) funds or the use of public (federal/state) land? Yes ® No ? 2. If yes, does the project require preparation of an environmental document pursuant to the requirements of the National or North Carolina Environmental Policy Act (NEPA/SEPA)? Note: If you are not sure whether a NEPA/SEPA document is required, call the SEPA coordinator at (919) 733-5083 to review current thresholds for environmental documentation. Yes ® No ? 3. If yes, has the document review been finalized by the State Clearinghouse? If so, please attach a copy of the NEPA or SEPA final approval letter. Yes ? No Proposed Impacts on Riparian and Watershed Buffers (required by DWQ) It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to required state and local buffers associated with the project. The applicant must also provide justification for these impacts in Section VII above. All proposed impacts must be listed herein, and must be clearly identifiable on the accompanying site plan. All buffers must be shown on a map, whether or not impacts are proposed to the buffers. Correspondence from the DWQ Regional Office may be included as appropriate. Photographs may also be included at the applicant's discretion. 1. Will the project impact protected riparian buffers identified within 15A NCAC 2B .0233 (Neuse), 15A NCAC 2B .0259 (Tar-Pamlico), 15A NCAC 02B .0243 (Catawba) 15A NCAC 2B .0250 (Randleman Rules and Water Supply Buffer Requirements), or other (please identify ? Yes ? No 2. If "yes", identify the square feet and acreage of impact to each zone of the riparian buffers. If buffer mitigation is required calculate the required amount of mitigation by applying the buffer 3. If buffer mitigation is required, please discuss what type of mitigation is proposed (i.e., Donation of Property, Riparian Buffer Restoration / Enhancement, or Payment into the Riparian Buffer Restoration Fund). Please attach all appropriate information as identified within 15A NCAC 2B.0242 or.0244, or.0260. N/A Page 12 of 14 t XI. 1 t t 1 t t t 1 t 1 Stormwater (required by DWQ) Describe impervious acreage (existing and proposed) versus total acreage on the site. Discuss stormwater controls proposed in order to protect surface waters and wetlands downstream from the property. If percent impervious surface exceeds 20%, please provide calculations demonstrating total proposed impervious level. N/A (linear project) XII. Sewage Disposal (required by DWQ) Clearly detail the ultimate treatment methods and disposition (non-discharge or discharge) of wastewater generated from the proposed project, or available capacity of the subject facility. Wastewater collected by this protect will enter the existing Town of Creswell sewer system and be treated at the Town of Creswell Wastewater Plant XIII. Violations (required by DWQ) Is this site in violation of DWQ Wetland Rules (15A NCAC 2H .0500) or any Buffer Rules? Yes ? No Is this an after-the-fact permit application? Yes ? No XIV. Cumulative Impacts (required by DWQ) Will this project (based on past and reasonably anticipated future impacts) result in additional development, which could impact nearby downstream water quality? Yes ? No If yes, please submit a qualitative or quantitative cumulative impact analysis in accordance with the most recent North Carolina Division of Water Quality policy posted on our website at http://h2o.enr.state.nc.us/ncwetlands. If no, please provide a short narrative description: The project area is an existing rural community with failinjZ septic systems and the system is being installed to get service to these homes XV. Other Circumstances (Optional): It is the applicant's responsibility to submit the application sufficiently in advance of desired construction dates to allow processing time for these permits. However, an applicant may choose to list constraints associated with construction or sequencing that may impose limits on work schedules (e.g., draw-down schedules for lakes, dates associated with Endangered and Threatened Species, accessibility problems, or other issues outside of the applicant's control). N/A Page 13 of 14 Applicant/Agent's Signature '---I bate (Agent's signature is valid only if an authorization letter from the applicant is provided.) Page 14 of 14 t t 1 t 1 1 1 1 1 1 t 1 1 Appendix A VICINITY MAPS & SITE PLANS t WATER AND SEWER DIS NORTH CAROLINA STRICTS 1 & 2 JA PRESSURE SEWER z SYSTEM CONTRACT 1 - PRESSURE SEWER FROM CRESWELL .LL INTO WASHINGTON COUNTY CONTRACT 2 - PRESSURE SEWER FROM WASHINGTO AUGUST 20 ON COUNTY INTO TYRRELL COUNTY 007 COUNTY COMMISSIONER Tommy W. Spruill, Chairman ERS nan person Florence Bryant, Vice Chairpers Card L. Wi~~is Tony Sawyer vyer Zacharias Brickhouse COUNTY MANAGER 2 Willie Mack Carawan, Jr. r. r THE WOOTEN COMPANY a ~ FINAL DESIGN v IL NOT RELEASED FOR CONSTRUCTION 120 North Boylan Avenue Raleigh NC 27603-1423 919.828.0531 fax 919.834.3589 Sheet No. 1 of 95 Sheets o ~~:+.lL.•..YLL~41...:.~]..~u.t:.;.1:t'--L..;.,~.~::LS.n:.:.n'Lti~~.s=~-,uu..:cut x-c'.~..~-:.~~.~~If.~'Ja4:',+~',..~-'~.r...:.::i:~:rp'~wu i.~fw..:u:iS.N~iY U.::JI:.~.N'.~.i.;., c:w4iu'...~~W..w uw .w . \ « V Jn 1` ALBEMARLE SOUND - ' !Class SBJ 4 W N 'r ,*e, 22 . z ] . ~'y o .~v ~ 24 1 L 24 °j0hisl Bea°h ,~Y''~. Yq w BULL BAY 2 26 25 ° (Class SB) ~ ~ ,f OC `4,o-. ~ 23 7 5 ?.6 r' _ 74 Str om Impp°c 4-37 a . t,J r 21 ream 37) a ~ " v 25 ~ - I o (75 4 a 4 "C. y 23 SStrea 01 c SCUPPERNONG RIVER ~ v ~ 3 ~ (Class SCI ~~6~.. ~ tre0m Impp t " 11-20 ~ 4 ,r .4 ~ Streom 20) .o y 3 20 ~ ~ 74 ~ ,:1`' m Stream Impact" 1 0~ y yea. ~ ~ (Streom 22) mm 24 4, ~ ' aN ~ ~a `'i:: '"o,. r'~ 0 22 ~ 19 ~ •t~~, °,.`;T N a ~ , ti ~ g ATIO No. 20 N 19 sR w l~^ ~ t " 13 23 O 1 18 ~ . 85 - - I a 73 F,~r. W' ~ ~ 5i O .I 18 ~ N O tre°m act " -47 ` etland - $ ° 1~ iin Z U d' CSI/ L1J M jy ante t ~ amP L \ ~ ' - O _ ~ ~ r 16 17 , ` ~ ~lb C aPe i ( ~ U N ~ ~ U m " ~ Stre m Im act - 7 ~ W on 78 ~ o ¢ L ~ f` ~ tt 0 ~ 5 J V ~ z cv O~ g, _ ~ X 4 v ~ . , ~ ~r O _ ~ ~ 77 h arm ' W z 0~ ~ d 4~.~~J4 J ~ 77 ti2 ~rAar1jS . Q a m N . ~ ~ r ` ~ - ~ 15 ,~7 76 °~a Wetland 4 - W4'^ O cc 00 ~ o z m m 4,0~ a ~ - ~ O'+ . - ~ t~ S Str om Imppact " 29- D y~' dr $ (Str om 18)== m OS tr am Imp ~d9-24 ;s' ~ 4 ESL r' 1 w w z w 14 ( ecm 24) ~ 4e9 4 = z ° ~J ~ - !T r, C7 0 ~ i 7 G 45 47 Z \ ream Im act " 15- 5 1 27 trecm 2) ° - , . W q l 14 , 1 1 e~ ~ 1, 44 ~ 1 1 r~ m 70 1. y,~ r w r ~ a 9 e 45 '11 SR 1 ~r 43 ~ Q 48 ~~1 ri r sc 1 ..1 13 1 c. l 1 ":1 n' 69 J ~ ~ a U 1 ~1 a Y . 2 1 s',1 ~ 1 Bay 6 1 QO JN:Y,~,. post Office Stre Imps t " 2-3 ~ 6 42 ea 48 ~ N 1~1 3 titi sR rr~ ~s~ ) : 55 ° 1 O J~ 3 ^ ~ z ~s om ct 23-36 tr Im~pacl ' 7-13 ~ 1~.1 4 6 9 1.1 55 38 reo 131 - 45 N ~ 1~1 1 ~ 1 37 37 3 ~ U 1 ,r' . r o~ d fA Stream Imppact " 16-27 @ ' ~ (Stream 27) 1 . 41 Str am Im act • -i6 6~ R° ~ ~ 3 tin NEW PU 36 ~ 1 ti STATION 1 ~ (Str am 1~) l~mbta ~ U 0 ~ 1 Stree ~ I ~ p} t^ 8-14 6 0 ~ U Q 1 1 g~' S 36 y. 4 01 Z , 1 ~ 1 y;,u 1 1 ~ 35 56 58 57 'z, 8 5 ~ ` 1 O D ~ 1 1'.,1 ti- Streom Im act " 21-33 1 ;,1 (Streom 3p3) Z 57 SR 1113 O ~ + U CC ~ .rte-, Q ~ 35 m Streom 11 act • 32-48 -.w ~w 5treo Imppact " 20-32 ra 58 f:C 3R 1110 J W fA (Strepml4 ,,"v e 32) 67 .~a , - ~ w w c}n ~ _ 1=,1 .r ~ - - ~v. ° ~ ~ U w I~ - 1 `b 0 6 II 1•~1 u 66 63 II 1•>;1 `s;,,~~'"'- v Impact • 18-30 0 63 ~ ~ Q W JO I 11 ? r l 'k eam 30J ~ 4 i ~ o fn if i~ir ~ II. IL; h;r. 34 Stream c 10 64 I t ; „t{, g 51 (S om e~ 1 Stream Impact " 2 W ~ ~ ` (Streom 9)=• 5 Q ~ ~ ~ ~ - I 5 5 - a R0 , vis Wa r & ew ~ 11 0 ~1 W r ' ~ >.1 °°d~eyG 33 `1 ad ~ Dis 'ct o. 1 U J J 10 ::I o /i/ 1 I 53 W 'i Stre° Im act • 4 S ~ ti~ ' d ~ ~e ~ (Stre m 61 ''p 1 00 'y I jJb, sC F- pA a 1 ,i ~ 1 - 54 ~ O ll I 5tre°m Impac A~ 0 I ~ ( (Stream 8) .i ILI ti~ ?.I Stream I act • 3-5 h - .A y ti~ d I fi~ I (Streom 5 r ~ p y / ~ l 0 n I ~ V ~ b (11 31 ll~ StreO Impact " 27-7 ~ o I 45 (Stream 83 ~ 9 ~ lal 0 ~ Stream Impact " 2- 1 r`- ~ 0 (Stream 4) 1 l s e I 83 ti~ / ~ 86 d ~ 5~ 0 9 `ti o 1 3D ? 2 ~ ~ II G 0 , _ ~ 82 OJ treao~ 13poct 1 3 Q ? ? Stre Impact " 25- 0 ~ Cron ~ Q7 4'~ - ~o~ 1 .1` ~ (Str 40) - S4 s a ~ GS .y p ? ? (105 ~ BA 87 Streom Impact • -31~ e1 (Streom all ~ 28 i'.: ~ sQ _ Strew Imppact 1R-2~" ~ , 2S p (Strew 28) ?''Q ? G~' 89 `t`V// • 88 88 `Q~ ~ ® 81 ~ 81 1 1 PRESSURE SEWER SYSTEM DES~GNEDBY; WBJ O 1 1 ~ 1 1 7 - 7 80 1 t O 1 80 1 WATER & S EW E R DRAWN BY. 3 l 0 79 79 1158 ~ 1 O SR k TK l EJB " gad ti. ~ avid m Town of ° D gt, DISTRICT 1 & 2 CHECKED BY. WBJ ~ .Streom Impact • 26-1 ~°t; ~ ~ ` Creswell 6 treom ~ ' a PROJECT NO.. ro ~ ~ a~ 2a7s-B ~ ~ N,. - ~ C o C~ - _ _ o~~,o LEGEND DATE; auG 2007 ~ © ~ 41 SCALE: ' Q y5 etland 1 - W1 ° Sheet Location No, AS SHOWN C - ~ ~ g°ad ~ ~ 0 eCrY si, 5h ~ J 1 ~ . N ~ x2 ~ O Proposed Flow Meter Station ~ ~ Creswell ~ ~ 1500' 750' 0 1500' 3000' 4500' SHEET Z OF 95 1 1 A A 1~ IAI IAI T R FINAL DESIGN SCALE: 111.15001 NOT RELEASED FOR CONSTRUCTION *9T ~H€SE\.CONTRACTS)Y vv I r CONTRACT 1 CONTRACT 2 1. COVER SHEET 1. COVER SHEET 55. NEW 3" PVC FORCE MAIN -BAY POST OFFICE ROAD -STA. 0+00 TO STA, 28+24 2. LOCATION MAP 56. NEW 4" AND 3" PVC FORCE MAIN -TRAVIS ROAD -STA. 0+00 TO STA.28+00 z 2. LOCATION MAP 3. INDEX TO DRAWINGS 0 3. INDEX TO DRAWINGS 57. NEW 3" PVC FORCE MAIN -TRAVIS ROAD -STA, 28+00 TO STA. 56+00 w 4. ABBREVIATIONS, GENERAL NOTES AND LEGEND 4. ABBREVIATIONS, GENERAL NOTES AND LEGEND 58. NEW 3" PVC FORCE MAIN -TRAVIS ROAD -STA. 56+00 TO STA. 84+00 5. NEW 8" PVC FORCE MNN -CHERRY ROAD /MAIN ST -STA. 0+00 TO STA. 28+00 2+50 TO STA. 221+00 59, NEW 3" PVC FORCE MAIN -OLD COLUMBIA ROAD -STA. 84+00 TO STA. 109+00 12. NEW 6" PVC FORCE MNN - ALLIGOOD ROAD / ALBEMARLE CHURCH ROAD -STA. 192+50 TO 6. NEW 8" PVC FORCE MAIN - 1st STREET /SAINT DAVID ROAD -STA. 28+00 TO STA. 56+00 13. NEW 6" PVC FORCE MAIN - ALBEMARLE CHURCH ROAD -STA. 221*00 TO STA. 248*00 X00 60. NEW 3" PVC FORCE MAIN -OLD COLUMBIA ROAD -STA. 109+00 TO STA. 134+48 7. NEW 8" PVC FORCE MAIN -SAINT DAVID ROAD / 6th STREET -STA. 56+00 TO STA. 82*00 14. NEW 6" PVC FORCE MAIN - ALBEMARLE CHURCH ROAD -STA. 248+00 TO STA. 276+00 +00 61. NEW 3" PVC FORCE MAIN - WOODLEY ROAD STA. 0+00 TO STA, 9+84 NEW 2" PVC FORCE MAIN -OLD COLUMBIA ROAD -STA. 0+00 TO STA. 3+62 8. NEW 8" PVC FORCE MAIN - ALLIGOOD ROAD -STA. 82+00 TO STA. 109+00 15. NEW 6" PVC FORCE MAIN - ALBEMARLE CHURCH ROAD -STA. 276*00 TO STA. 303+00 +00 62. NEW 3" PVC FORCE MAIN -CHAPEL HILL ROAD -STA. 0+00 TO STA. 14+00 9. NEW 8" PVC FORCE MAIN - ALLIGOOD ROAD -STA. 109*00 TO STA. 137*00 W 16. NEW 6" PVC FORCE MAIN -STA. 303+00 TO STA. 317+24 63. NEW 3" PVC FORCE MAIN -CHAPEL HILL ROAD -STA. 14+00 TO STA. 28+00 ~ N 10. NEW 8" AND 6" PVC FORCE MAIN - ALUGOOD ROAD -STA. 137+00 TO STA. 165+00 NEW 6" PVC FORCE MAIN - STA. 0+00 TO STA. 14+00 U W ~ ~ _o 11. NEW 6" PVC FORCE MAIN - ALLIGOOD ROAD -STA. 165+00 TO STA. 192*50 17. NEW 6" AND 4" PVC FORCE MAIN - ALBEMARLE CHURCH ROAD -STA. 14+00 TO STA. 42*00 A. 42+00 64. NEW 3" PVC FORCE MAIN -CHAPEL HILL ROAD -STA. 28+00 TO STA. 56+00 ~ m U N ~ OC M ~p 65. NEW 3" PVC FORCE MAIN -CHAPEL HILL ROAD -STA. 56+00 TO STA. 69+82 ~ , Q a 12. NEW 6" PVC FORCE MAIN - ALLIGOOD ROAD / ALBEMARLE CHURCH ROAD 18. NEW 4" PVC FORCE MNN - ALBEMARLE CHURCH ROAD -STA. 42+00 TO STA. 70+00 Z ~ ~ STA. 192+50 TO STA. 22100 TA. 97+12 66. NEW 2" PVC FORCE MAIN -STA. 0+00 TO STA. 11+15 z z 19. NEW 4" AND 3" PVC FORCE MAIN - ALBEMARLE CHURCH ROAD -STA. 70*00 TO STA. 97+12 28. NEW 6" PVC FORCE MAIN - NC HWY 94 -STA. 0.00 TO STA. 28+00 H II II k~, }fir! ro n. Q o ' 67. NEW 3 AND 2 PVC FORCE MAIN -TRAVIS SCHOOL ROAD -STA. 0+00 TO STA. 17+59 ± O J 20. NEW 4" AND 3" PVC FORCE MAIN -BULLS BAY RUN -STA. 0+00 TO STA. 28*00 - N N O 29. NEW 6" PVC FORCE MAIN - NC HWY 94 -STA. 28+00 TO STA. 56+00 ~ O ~ 21. NEW 3" PVC FORCE MAIN -BULLS BAY RUN -STA. 28+00 TO STA. 55*50 68. NEW 4" PVC FORCE MAIN - ALBEMARLE CHURCH ROAD -STA. 0+00 TO STA. 14+00 ~S ? m LJJ W o wo 30. NEW 6" PVC FORCE MNN - NC HWY 94 -STA. 56+00 TO STA. 84+00 22. NEW 3" PVC FORCE MAIN -BULLS BAY RUN -STA. 55+50 TO STA. 64+20 69. NEW 4" PVC FORCE MAIN - ALBEMARLE CHURCH ROAD -STA. 14+00 TO STA. 42+00 ~ Z 79. NEW 3" PVC FORCE MAIN -SLANT DAVID ROAD -STA. 0+00 TO STA. 28*00 NEW 2" PVC FORCE MAIN -STA. 0*00 TO STA. 2+35 70. NEW 4" AND 3" PVC FORCE MAIN - ALBEMARLE CHURCH ROAD -STA. 42+00 TO STA. 70+00 W NEW 3" PVC FORCE MAIN - ALBEMARLE SHORES -STA. 00+00 TO STA. 14+00 80. NEW 3" PVC FORCE MAIN -SAINT DAVID ROAD -STA. 28+00 TO STA. 56+00 23. NEW 3" PVC FORCE MNN - ALBEMARLE SHORES / ALBEMARLE SHORES EXT.-STA. 14*00 TO .14+00 TO STA. 42+00 71. NEW 3" PVC FORCE MAIN - ALBEMARLE CHURCH ROAD -STA. 70+00 TO STA. 84+00 a z 81. NEW 3" PVC FORCE MAIN -SAINT DAVID ROAD -STA. 56*00 TO STA. 84+00 24. NEW 3" AND 2" PVC FORCE MAIN - ALBEMARLE SHORES EXT -STA. 42+00 TO STA. 47*89 f A. 47+89 72. NEW 3" PVC FORCE MAIN - ALBEMARLE CHURCH ROAD -STA. 84+00 TO STA. 98+00 4+02 ~ 86. NEW 6" WATER MAIN AND NEW 4" FORCE MAIN - NC HWY 94 -STA. 0+00 TO STA. 28*00 NEW 3" AND 2" PVC FORCE MAIN - ALBEMARLE SHORES EXT -STA. 0+00 TO STA. 4+02 NEW 3" PVC FORCE MAIN -COLONIAL BEACH -STA.0+00 TO STA. 14+00 73. NEW 3" PVC FORCE MAIN - ALBEMARLE CHURCH ROAD -STA. 98+00 TO STA. 119+67 ~ N O 87. NEW 6" WATER MAIN AND NEW 4" FORCE MWN - NC HWY 94 -STA. 28+00 TO STA. 56+00 'A.14+00 TO STA. 38+55 74. NEW 3" AND 2" PVC FORCE MAIN -NORTH BAY DRIVE -STA. 0+00 TO STA. 9+10 Z 25. NEW 3" AND 2" PVC FORCE MAIN -COLONIAL BEACH /COLONIAL BEACH EXT- STA. 14*00 88. NEW 6" WATER MAIN AND NEW 4" FORCE MAIN - NC HWY 94 -STA. 56+00 TO STA. 84*00 NEW 3" PVC FORCE MAIN -FOLLY LANDING -STA, 0+00 TO STA, 14+00 N ~ 26. NEW 3" AND 2" PVC FORCE MAIN -COLONIAL BEACH EXT -STA. 0+00 TO STA. 22*22 !+22 ~ ~ 89. NEW 6" WATER MAIN AND NEW 4" FORCE MAIN - NC HWY 94 -STA. 84*00 TO STA. 96+57± 75, NEW 3" AND 2" PVC FORCE MAIN -FOLLY LANDING -STA. 14+00 TO STA, 32+12 ~ ~ ~ ~ ~a z 27. NEW 3" AND 2" PVC FORCE MAIN -COLONIAL BEACH EXT. AND LANDING DRIVE 76. NEW 3" PVC FORCE MAIN -DAVENPORT ROAD -STA, 0+00 TO STA. 28+00 z ~ " ~ ~ Q 92. SANITARY SEWER DETAILS NEW 2" SERVICE LINES - ALBEMARLE CHURCH ROAD O oW ~ 77. NEW 3" PVC FORCE MAIN -DAVENPORT ROAD -STA. 28+00 TO STA. 55+00 ~ ~ ~ 93. EROSION CONTROL /MISC. DETAILS 30. NEW 6" PVC FORCE MAIN - NC HWY 94 -STA. 56+00 TO STA. 84+00 w ~ can ~ w F- 94. STANDARD DETAILS -MISCELLANEOUS SEPTIC TANK DETAILS 78. NEW 3" AND 2" PVC FORCE MAIN -DAVENPORT ROAD -STA. 55+00 TO STA. 71+15 ~ N ~ 31. NEW 6" PVC FORCE MAIN - NC HWY 94 -STA. 84*00 TO STA. 112+00 AND NEW 1/2" SERVICE LINE -OLD COLUMBIA ROAD ~ w aW w 0 95. STANDARD DETAILS -MISCELLANEOUS SEPTIC TANK DETAILS °C w ? 32. NEW 6" PVC FORCE MAIN - NC HWY 94 -STA. 112+00 TO STA. 137+00 81. NEW 3" PVG FORCE MAIN -SAINT ,DAVID ROAD -STA. 56+00 TO STA. 84+00 ~ ~ ~u 33. NEW 6" PVC FORCE MAIN - NC HWY 94 -STA. 137+00 TO STA. 164.50 82. NEW 3" PVC FORCE MAIN -SAINT DAVID ROAD -STA. 84+00 TO STA. 112+00 ~ z d 83. NEW 3" PVC FORCE MAIN- SAINT DAVID ROAD -STA. 112+00 TO STA. 136+50 0 34. NEW 6" PVC FORCE MAIN - NC HWY 94 -STA. 164+50 TO STA. 193+00 r 35. NEW 6" PVC FORCE MAIN - NC HWY 94 -STA. 193+00 TO NEW PUMP STATION N0. 1 0 0.1 84. NEW 3" PVC FORCE MAIN -CROSS LANDINGS ROAD -STA, 0+00 TO STA. 11+04 ~ ~ 36. NEW 6" AND 4" PVC FORCE MNN - NC HWY 94 -STA. 0+00 TO STA. 28+00 85. NEW 8" GRAVITY SEWER AT 4-H ENVIRONMENTAL CONVENTION CENTER ~ 0 37. NEW 4" PVC FORCE MAIN - NC HWY 94 -STA. 28+00 TO STA. 42*00 86. NEW 6" WATER LINE AND 4" PVG' FORCE MAIN - NC HWY 94 -STA. 0+00 TO STA. 28+00 v 0 87. NEW 6" WATER LINE AND 4" PVC FORCE MAIN - NG HWY 94 -STA. 28+00 TO STA. 56+00 ~ - T- 1 38. NEW 4" PVC FORCE MNN - NC HWY 94 -STA. 42*00 TO STA. 56+00 a - o ° o o i \ ~ ~ 39. NEW 4" AND 2" PVC FORCE MAIN - NC HWY 94 /BUTLER ROAD -STA. 56*00 TO STA. 70 ~ ~ o m - o o STA. 70+00 88. NEW 6" WATER LINE AND 4" PVC FORCE MAIN - NC HWY 94 - STA,56+00 TO STA. 84+00 0 ~ p p ~ ' f \ i m o ~ ~ , ~ ~ ~"ti, o p 40. NEW 4" PVC FORCE MAIN -BUTLER ROAD -STA. 70+00 TO STA. 84+00 89. NEW 6" WATER LINE AND 4" PVC FORCE MAIN - NC HWY 94 -STA. 84+00 TO STA. 93+57 ~ ~ ~ . a a` > ` ~ - ~ .moo `i , . 0 0~ '"^ti_~` ~ p ~ ~~m' ~ "i' mi ~ m ~ ~ ~.i 41. NEW 4" PVC FORCE MAIN -BUTLER ROAD -STA. 84+00 TO STA. 111+00 90. PUMP STATION N0.1 AND N0.2 SITE PLANS o m a ~ ~ o ; - w ~ m m } o ~ ~ o 42. NEW 4" PVC FORCE MAIN -BUTLER ROAD -STA. 111*00 TO STA. 125*00 91. PUMP STATION PLANS AND SECTIONS n pu. ° r~ ~b ° ' ~ f~ m ~ a 43. NEW 4" AND 2" PVC FORCE MAIN -BUTLER ROAD / NC HWY 94 -STA. 125*00 TO STA.13 o~ "'tom '0 STA. 139+00 92. SANITARY SEWER DETAILS ~ o ~ ca p ~ f ' i l 44. NEW 4" PVC FORCE MAIN - NC HWY 94 -STA. 139*00 TO STA. 153+00 93. EROSION CONTROL - MISCELLANEOUS DETAILS ~ r'~ p,,~ r~,_,pp~p. 45. NEW 4" PVC FORCE MAIN - NC HWY 94 -STA. 153+00 TO STA. 167*00 94. STANDARD DETAILS - MISCELLANEOUS SEPTIC TANK DETAILS DESIGNED BY; ~ NEW 3" PVC FORCE MAIN -CYPRESS ROAD -STA. 0+00 TO STA. 7+00 p 95. STANDARD DETAILS - MISCELLANEOUS SEPTIC TANK DETAILS WBJ DRAWN BY. ~ i ~ ~ i o o -,gr- o ~ ° ~ a 46. NEW 4" AND 3" PVC FORCE MAIN - NC HWY 94 -STA. 167+00 TO STA. 181*00 TK 1 EJB a~i - ~6 ~ ~ ~ ~2 ~ ' ~ ~ N r ~ o m ~ ^ y \ 47. NEW 3" PVC FORCE MAIN - NC HWY 94 AND OLD COLUMBIA ROAD -STA. 181+00 TO STA. 1 m -'j~° ~ ~ ~ o r` ~ ~ 48. NEW 3" PVC FORCE MAIN -OLD COLUMBIA ROAD -STA. 193+00 TO STA. 209+82 TO STA. 193+pp CHECKED BY. WBJ PROJECT NO.: 2876.6 DATE; N r ~ m ~ 1 ~ ~ ~ ~ ~ ~ 49. NEw 2" AND 3" PVC FORCE MAIN -RAMP ROAD -STA. 0+00 TO STA. 1400 AUG 2007 SCALE; N o o p 'a"~'- ( ~ 50. NEW 3" FORCE MAIN - WOODLEY STATION ROAD -STA. 0+00 TO STA. 28+00 NOT TO SCALE ~ o i ~ m o ~o _ ~ 51. NEW 3" FORCE MAIN - WOODLEY STATION ROAD -STA. 28+00 TO STA 55*15 «i U ~ ~ O Q ~ ~ 10 ~rr~ i, j_ _ _ D N ~ ! - ~ ~ / ~ ~ 52. NEW 3" FORCE MAIN -RACCOON ROAD -STA. 0+00 TO STA. 10+46 FINAL DESIGN SHEET 3 OF 95 ~ ~ ~ ! ~ ~ ~ ~ T~ NEW 2" PVC SERVICE LINE -CHAPEL SWAMP LANE NOT RELEASED FOR CONSTRUCTION Q VICINITY MAP 53. NEW 3" FORCE MAIN - WOODLEY STATION ROAD -STA. 0+00 TO STA. 26150 J co N ~ NOT TO SCALE 54. NEW 3" FORCE MAIN -CHAPEL HILL ROAD -STA. 26+50 TO STA. 39+28 AND STA. 0*00 TO 0+00 TO STA.3+89 ABBREVIATIONS NOTES LEGEND ADHERE TO THE FOLLOWING ITEMS IN THE CONSTRUCTION OF THE PRESSURE SEWER SYSTEM A AREA LP LIGHT POLE IMPROVEMENTS UNLESS OTHERWISE NOTED, ABAND ABANDONED LT LEFT ABC AGGREGATE BASE COURSE LWL LOW WATER LEVEL GENERAL ac ACRES 1. EXISTING UTILITIES ARE LOCATED ON PLANS APPROXIMATELY. NOTIFY UTILITY LOCATING SERVICE TO E To SURVEY SEINER z A.F.F. ABOVE FINISHED FLOOR MAX MAXIMUM MARK LOCATION OF EXISTING UTILITIES AT LEAST 48 HOURS PRIOR TO COMMENCING CONSTRUCTION TION ~ AL ALUMINUM MECH MATERIAL ACTIVITY. CONTRACTOR RESPONSIBLE FOR VERIFYING EXACT LOCATION OF THESE EXISTING UTILITIES. APPROX APPROXIMATE MATL MECHANICAL .ITIES. EXISTING NEW EXISTING NEW ~n - ~ ALT MFR. MANUFACTURER THE COST TO REPAIR THESE FACILITIES, IF DAMAGED, SHALL BE THE RESPONSIBILITY OF THE ASPH ASPH e eM BENCHMARK ~ssux MANHOLE ~ owC ASSY ASSEMBLY MH MANHOLE CONTRACTOR. AVG AVERAGE MJ MECHANICAL JOINT TEMPORARY BENCHMARK ova CLEAN OUT • r8M ARV AIR RELEASE VALVE MIN MINIMUM 2. PROTECT EXISTING PROPERTY CORNER MARKERS. REPLACE DISTURBED PROPERTY CORNERS BY A A ®~M CONCRETE MONUMENT SS SEWER LINE SS AZ AZIMUTH MON MONUMENT PROFESSIONAL LAND SURVEYOR. AWWA AMERICAN WATER WORKS ASSOCIATION o IRON PIPE • FM FORCE MAIN FM N/A NOT AVAILABLE 3. TEMPORARILY REMOVE MINOR ITEMS AS REQUIRED FOR THE INSTALLATION OF THE UTILITY. MINOR R o HUB & TACK ¦ REDUCER 1 B-B BACK OF CURB TO BACK OF CURB N NORTH ITEMS SHALL INCLUDE, BUT NOT BE LIMITED T0, EXISTING SIGNS, MAIL BOXES, STORM SEWER PIPES, BLDG BUILDING NAD 83 NORTH AMERICAN DATUM 1983 SHRUBS {UNDER 6 FT IN HEIGHT) AND TREES {UNDER 3 INCH IN DIA,>. REINSTALL ITEMS TO THEIR "S' e NAIL • AIR RELEASE MANHOLE 0 :IR BM BENCHMARK NC NORMAL CROWN ' ORIGINAL CONDITION. TREES AND SHRUBS SHALL BE REPLANTED OUTSIDE OF EASEMENT AND o NAIL & CAP • TERMINAL CLEANOUT HI BOA BLOW-OFF ASSEMBLY NC GRID NORTH CAROLINA GRID :PER ® PK NAIL • IN-LINE CLEANOUT 0 BOT BOTTOM NCGS NORTH CAROLINA GEODETIC SURVEY RIGHTS-OF-WAY AT A LOCATION AGREED TO BY THE PROPERTY OWNER, INCLUDE COST IN THE PER Bw BARB WIRE N0. NUMBER FOOT COST OF THE UTILITY BEING INSTALLED. NTS NOT TO SCALE '3~8.~ SPOT ELEVATION %ZHP PUMP,1 PUMP . ~ cs~c CURB AND GUTTER NOM NOMINAL 4. SUPPORT EXISTING POLES, FENCES, CULVERTS, PAVEMENT, UTILITIES, CURBING AND OTHER (1860 GAL. TANK) ~ ce CATCH BASIN NWL NORMAL WATER LEVEL STRUCTURES DURING CONSTRUCTION. REPAIR DAMAGED ITEMS TO THEIR ORIGINAL CONDITION AT NO +6ss.s CONTROL POINT ~ N NO %2HP PUMP , 2 PUMP . ~ Z w CL CENTERLINE ADDITIONAL COST, CURB (2800 GAL. TANK) Q ~ o CIP CAST IRON PIPE OC ON CENTER ~ _ cI CURB INLET oD OUTSIDE DIAMETER 6 INCHES OF NCDOT ABC AGGREGATE SHALL BE PROVIDED FOR THE FULL WIDTH OF UNPAVED PAVED ROADS %ZHP PUMP,2 PUMP • ~ ~ ~ (6000, 8000 & ~ a z ~r CLR CLEARANCE 0/H OVERHEAD 5' , 0 4 V - ~ OQ OSITE UNPAVED ROADS 10 000 GAL. TANK) • . ONUMENT ORIG ORIGINAL DRIVEWAYS AND ROADS FROM THE EDGE OF THE ROAD SHOULDER TO 15 FEET PAST THE OPPOSITE CM CONCRETE M cMP CORRUGATED METAL PIPE SIDE OF THE PIPE TRENCH AND OTHER AREAS OF EXISTING DRIVEWAYS AND ROADS DISTURBED BRIDGES & BOX WATER ~ ~ x CULVERT ~ CMU CONCRETE MASONARY UNIT PC POINT OF CURVATURE DURING CONSTRUCTION. ~ Z dig,, ~ CO CLEAN OUT PED PEDESTAL - - - ~ PAVED DRIVEWAYS ~~k, _ caNC CONCRETE PE PLAIN END 6. OPEN CUT PAVED DRIVEWAYS, SIDEWALKS, AND CURB AND GUTTER. REPLACE CURB AND GUTTER CONT CONTINUOUS PI POINT OF INTERSECTION WITH NEW TO MATCH THE EXISTING CROSS SECTION. PROVIDE PAVEMENT PATCHING PER DETAIL, & PARKING EXISTING NEW ~~'~r'~"'' ® C CONSTR CONSTRUCTION PIV POST INDICATOR VALVE L. ® - N N UNPAVED DRIVEWAYS ~ WATER VALVE N ~ z m CONTR CONTRACTOR P PROPERTY LINE 7, FOR NCDOT STANDARDS SEE SPECIFICATIONS. & PARKING - ~ COR CORNER RP POWER POLE Db BUTTERFLY VALVE /N W W ° GUARDRAIL = z N CP&L CAROLINA POWER AND LIGHT PRV PRESSURE REDUCING VALVE ~-~4 FIRE HYDRANT ~ F- - CULV CULVERT PSI POUNDS PER SQUARE INCH z PVC POLYVINYL CHLORIDE D DEPTH PT POINT STORM DRAINAGE a REDUCER/INCREASER 1 W aD4 BLOW-OFF ASSEMBLY •~1 DI DROP INLET PVMT PAVEMENT EROSION CONTROL EXISTING NEW DIA DIAMETER AIR RELEASE MANHOLE O Q DIP DUCTILE IRON PIPE R RADIUS iS ? CATCH BASIN /INLET o WATER METER DIM DIMENSION R/W RIGHT OF WAY 1. INSTALL SILT FENCE OVER & AROUND TOP OF EXISTING PIPES AND INLETS AT DISTURBED AREAS. DITCH DISCHARGE RCP REINFORCED CONCRETE PIPE DFfS FLARED END SECTION L PLUG E v DIST DISTANCE REF REFERENCE 2. INSTALL SILT FENCE AROUND SPOIL PILES. DOT DEPARTMENT OF TRANSPORTATION REQ'D REQUIRED ~srMx MANHOLE ~ YARD HYDRANT ~ ~ Dw DOMESTIC WATER RET RETAINING 3. PROVIDE EROSION CONTROL MEASURES AROUND STOCK /WASTE PILES AND STAGING AREAS AS STORM DRAIN PIPE O WELL z ~ ~ DELTA REV REVISED APPROVED BY ENGINEER. wFCc RPZ REDUCED PRESSURE ZONE -W WATER LINE W ~ ~ Z E EAST RPM REVOLUTIONS PER MINUTE W TH 4. PROTECT STORM PIPE INLETS FROM SEDIMENT RUNOFF FROM LAND DISTURBING ACTIVITIES I EA EACH REINF REINFORCED i EROSION CONTROL ~ ~ EFFLUENT RT RIGHT SILT FENCE, STONE CHECK DAM, OR ARC FILTER AS APPROPRIATE FOR SITE CONDITIONS. EFF UTILITIES EIP EXISTING IRON PIPE U p CA J EXISTING NEW EXISTING NEW Z ~ U Z ~ EL ELEVATION s/w SIDEWALK 5. REPLACE DISTURBED STORM PIPE OUTLET PROTECTION WITH EQUAL OR GREATER AMOUNT OF ELEC ELECTRIC SAN SANITARY RIP-RAP WITHIN 15 DAYS OF DISTURBANCE. DITCH / SWALE ~ ~ ~ POWER/LIGHT POLE ~ ~ ~ Q W EP EDGE OF PAVEMENT SCH SCHEDULE STONE CHECK DAM ~ GUY WIRE ~ ~ ~ ~ O Ew EACH WAY SDMH STORM DRAINAGE MANHOLE 6. WHERE AREA AROUND OUTLET IS DISTURBED AND NO OUTLET PROTECTION EXISTS, CLASS "1" W z EX EXISTING SF SILT FENCE RIP-RAP SHALL BE PLACED AROUND PIPE OUTLET AS DIRECTED BY ENGINEER, EXP.JT. EXPANSION JOINT SHT SHEET INLET PROTECTION ~ © CABLE TV PEDESTAL ~ uWi ~ m s souTH 7. PROVIDE EROSION CONTROL MATTING IN DITCHES AND SWALES AS DIRECTED BY ENGINEER, w F.F.E. FINISHED FLOOR ELEVATION SPECS SPECIFICATIONS ?T TELEPHONE PEDESTAL ~ Q w Q ~ FG FINISHED GRADE SQ SQUARE RIP-RAP ~ ~ ~ ~ TRANSFORMER w w Z FH FIRE HYDRANT SS STAINLESS STEEL FIN FINISH ST STREET SILT FENCE ~ MANHOLE Q ~ ''WRR fLMx ~ ~ V FLG FLANGE STA STATION FIBER OPTIC CABLE w FM FORCE MAIN STD STANDARD EROSION CONTROL CONSTRUCTION SEQUENCE TEMP. SEDIMENT TRAP r F6C WARNING POST Z ate. p~ FP FIRE PROTECTION SYM SYMBOL ~ -G GAS LINE ~ ~ FPS FEET PER SECOND 1, OBTAIN AND POST COPY OF CERTIFICATE OF EROSION CONTROL PLAN APPROVAL. ` ~ FT FEET T TANGENT -FO FIBER OPTIC LINE ~ ~ FTG FOOTING TBM TEMPORARY BENCH MARK 2, CLEAR SITE ONLY AS NECESSARY TO INSTALL EROSION CONTROL DEVICES AS INDICATED ON -T TELEPHONE LINE TCP TERRA COTTA PIPE THE DRAWINGS. INSTALL TEMPORARY EROSION CONTROL DEVICES AS SHOWN ON PLANS. ~ G GA5 TDD TEMPORARY DIVERSION DITCH ~ GA GAGE TEL TELEPHONE ~ GALV GALVANIZED TEL PED TELEPHONE PEDESTAL 3. NOTIFY ENGINEER AND NCDENR, LAND QUALITY SECTION AT (252) 946-6481 FOR SITE INSPECTION N VEGETATION o PRIOR TO COMMENCING MAIN CONSTRUCTION OPERATIONS. GM GAS METER TEMP TEMPORARY ~ GPM GALLONS PER MINUTE THK THICK EXISTING NEW o GR GRADE TOC TOP OF CURB 4. ONCE EROSION CONTROL DEVICES ARE APPROVED, BEGIN CONSTRUCTION OPERATIONS. GV GATE VALVE TOP TOP OF SLOPE Jrwn TREE LINES /WOODS I GYP GYPSUM Tow TOP OF WALL 5, MAINTAIN EROSION CONTROL DEVICES AS NECESSARY DURING INSTALLATION OF WATER SYSTEM ~Y'r' HEDGE /SCRUB LINE ~ TP TELEPHONE POLE IMPROVEMENTS, INSPECT DEVICES AFTER EVERY RAINFALL EVENT AND GLEANOUT TRAPS ~ HCP HANDICAPPED TRANS TRANSFORMER AND/OR CHECK DAMS WHEN HALF FULL, SINGLE TREE ~ HT HEIGHT TYP TYPICAL Q SHRUB ~ HOR HORIZONTAL HP HORSE POWER u/c UNDERGROUND 6. AS CONSTRUCTION PROGRESSES INSTALL ADDITIONAL EROSION CONTROL DEVICES AS HwA HIGH WATER ALARM INDICATED ON THE DRAWINGS, CALLED FOR IN SPECIFICATIONS, OR AS DIRECTED BY ENGINEER, ~ v HWL HIGH WATER LEVEL VC VERTICAL CUR E HYD HYDRANT VCP VITRIFIED CLAY PIPE 7. SEED AND MULCH DENUDED AREAS WITHIN FIFTEEN {15> WORKING DAYS ~ VERT VERTICAL A, UPON COMPLETION OF ANY PHASE OF CONSTRUCTION. (~i~ ID INSIDE DIAMETER VOL VOLUME B. WHEN WORK WILL NOT PROCEED IN AN AREA WITHIN ~ IN INCH VPC VERTICAL POINT OF CURVATURE c THE ABOVE TIME FRAME. ~ IN/HR INCHES PER HOUR VPI VERTICAL POINT OF INTERSECTION ~ E CY ~ INF INFLUENT VPT VERTICAL POINT OF TANG N $ G EER. UPON APPROVAL OF ~ INT INTERSECT AFTER SITE IS STABILIZED, REQUEST AN INSPECTION BY THE EN IN INV INVERT w/ WITH SITE STABILIZATION, REMOVE TEMPORARY EROSION CONTROL DEVICES, DRESS OUT AREA ~ IPS IRON PIPE SET WL WATER LINE AND SEED AND MULCH. PERMANENT EROSION CONTROL DEVICES SHALL BE INSTALLED AND DESIGNED BY. ~ ISL ISLAND WM WATER METER APPROVED BY ENGINEER. WBJ WT WEIGHT DRAWN BY; ~ JB JUNCTION BOX WV WATER VALVE 3 WTP WATER TREATMENT PLANT TK 1 EJB ~ KWY KEYWAY WWF WELDED WIRE FABRIC CHECKED BY; WBJ m WWTP WASTE WATER TREATMENT PLANT LF LINEAR FEET ~ L LENGTH YI YARD INLET PROJECT NO.; 2als•B N DATE; AUG 2007 N SCALE; Q AS SHOWN ~ ~ 0 ~ CJ N~ rn~ L FINAL DESIGN SHEET 4 OF 95 MM / NOT RELEASED Q ti FOR CONSTRUCTION Q ~ o ~N/ ~~ti t;_f , ~ 1 1 Nse a ~ ~ ~ 1 sJ 1 Q W M/ i' r ~ N 4 ~ 0 ~ ~ p 1 - ~ p Id 9 a ~ w ~ 1 Trlr 1 b' ~ ~ ~ , 1 - 1 Nse ~ r ~ W H ~ J 1 RAW iJ~ ~ Ex~ ~ F FM ` ` ~ N V ~ ~ ~ / ~ 1 Hse (0 I Bld ~"I- 1 Hse 'a ~ ~ 9 ~ine meat menu 3 ~ / ~ 1~ ~ W ~ ~ Pc`'e ~ ~ ~ k Q J N cn I - „ W°t It P 1 U1 i b psPh° F,,• \ ~ 3 r+- ist• X \ 1 ~ ~ I ~ - W ' \ ~h 1 ~ I 1 ~ 1 5 ~ 1 5 1 - 1 Nse 1 E~ 11 /~2 - ~ ~ ~ '~~~-4 1 v J ~ U ~ ~1 1 , R a ~S F ~ w ~ 1 \ 1 ~/~W ` ~ ~ ~ Z ~ \ 1 •v 1 \ , - ' d a ~,1 Q~~ a~P Y EASEMENT ~ X a 1 1 ~---woods-.~ ? ~ ~ 1 a o Ro ,o l ~ , ~ x ~ , 1 - II_ ~-woods ~ n 1 m A h~ t Q 1 1 ~ "`1 ~ 1 (D Jam` 11~ , ~ Nse ~ ` ~ ~ ~ 1 ~ ~ ~ a ~ 1 - , I 1 ml o Z ~ M/ 1 1 I Nse ~ o - - -P~ p ~ 11 1 1 1 1 ~ ~ ~ / / O O ~ ~ rt . . ml - - t FY 1 1 1 1 ~ t o ~ ~ ~ A l \ 1 1 AINTAIN 4' MIN. S Old' ~ ~ 1 ~ al `~1-( 0, 111 r 1 11 Hse 1 1,. B ~ ~ I ~ Co - 1 1 1 1 1 BETWEEN NEW 1 v ~~1 N c~ o ~ } 1 1 1 36' 1 2 -NEW 8"-45° ~ ~ - ' 1 Trlr 11 ~ \ BENDS ~ ~ - 1, ' 1, 1 N~~ 8" PVC FORCE MAID FORCE MAIN a Nse 15„ RCP 1 0 FN FY ~ - - (2) NEW 8 1 TYP.) o ~ , • ~u ~ • _ - ~ 45° BENDS '1 ' {7, `•OFF EOP, TYP.) 1 1 _ _ - - Woods , 0 ~ ~ ~ N '1 U d' I - -I- - - - 1 ~ 10 PERMANENT C • i ~~t Hse ~ F M 1 ¢ Q o I ~ ~o' UTILITY EASEMENT ~ ~ ~ 1 TIE TO WWTP I ~ ~ ~ ~ I ~-woods 2 -NEW 8'-45° BENDS _ ° ~-woods 5 -woods-~ Ex. 15" RCP ~oo~ ~ o`i 1 ~ ~ _ 1~~ ~ 2 NEW BENDS ~I (BEGIN STA 0+ I ~~4 a Ex. 30 RCP . 00) I ~ ~ Inv- USE CONDITION 2 ~•''"~o.E,~,/~'°' o~'~'~ ~ , R ! ~ ~ ~ ~ ~ M I, ~ ~ x~ -3.89 USE CONDITION 3 • (SEE INSTALLATION DETAIL)"~ ~ \~G ~ ~ oo~ 6° 1 ~ ~ . O ~ m I 1nv= 1 1 (SEE INSTALLATION DETAIL) ~1 , L J Nse 2 -NEW 8"-45° BENDS -3.99 ~ '1 • O ` l ~ ~ ~1 1 1 ~ 4~ U ~ 011 1 ~ ~ , 1 1 ~ ~ 1 Z \ al , _ i Nse ~ ~ 1 ~ ~,n., 2 78 CMP , USE CONDITION 3 \ 10 PERMANENT (SEE INSTALLATION DETAIL) UTILITY EASEMENT S a M ~ ~ o J~a - (p N Stiff o ~ ~ W O Z 0~ ~ t ~ ' I ~ ~ LLI ~ T W ~ y W z Z ~ N 'U ~ 5 w 5 z v - ti - Ex. rode Z ~ - ` / ~ \ ~ - - ~ - - i- ~ - ~ 0 J W 0 7 V Ex 30" R P x, 15" CP ~ ~ 8n P U ~ M N 2~_0 2 t. I- Z Z Q _ R]~BEN 2'-D" STA. 3 97± _5 N U ~ 45 VERT. END 45° ERT• B ND ' ` +I - ~ ~ o ~ o ~ a+o U U ~ N Q -~o _10 z oc~ ~ ~W oC~ 0+00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 9+00 9+00 10+00 11+00 12+00 13+00 14+00 ~ w ~ = O cn U ~ Zo I 1 Ir ~ I I I I I ~ SNEER 6 ~ Z N ~ °o I I I I I akoo ~ Sti 1~ekla~d 1 m c~- - I~ 1 ~ ~ W a ~ I ~ Scrub S~ p. 2 ~ ~ ~ v I- LLl I I rr, I I I H„ ,~SN~,INE ~ Q ~ ~ ~ W I I z I I a~ ~ I I ~-woods ~ MP ~ ~ ~ ~ l o , ^`1 N .v I i '~1 ~'E `-'Woods/Wetlonds~ ~ Ll! ~ I I ~ LLI r ° I I ~ ~ RW Z U ~I a I -1 , I~ ;woods I 1~,` r',~ 1 NCD ~ 60 8' O ~ cn ~ I 7r/r ~ a p~ o C ~ MAINTAIN 5' MIN. SEPARATION ~ 00 ~ I ~ ~ ~ _ I o ~ ~ ~ Nse V ~ BETWE EXIST. & NEW FORCE MAIN ~ ~ ' ~ Ex's ~ ~ ~ _ ist, 6 ~ w~ , ~--Woods 1'11''` N N+ NE 8"-22.5° BEND ~ Z O ter~• I ~ ~ C O ~ W o - me ~J` _ . ,1 1 ~ N 1 10' PERMANENT UTILITY EASEMENT ~ ti I° I ' ~ I p ,1~1 1 ~ ~ TEMPORARY CONSTRUCTION EASEMENT 0 0 ~ - ~I ~ 1 TEMPORARY BORE PIT Q ~~i flr ~ I o I ~ ~ ~ (APPROX. SIZE & LOCATION) ,!,i NEW 8"-45° BEND 1 ~ ~ _ Mvi (~j N ~ 0 r' W ~ ~ ~ ~ nStr o ~ ~I Ex. eet lol ~ ~ ~ rn F'!y 2 Force ~Sp ~ o ` ~ ~ Main ~T ~ o t v ~--woods-.~ 1~~, } ~ 1 .PROVIDE 40 LF OF 16" ~ ~ ~ 2~ o I ~ ~ ~ ~ 1 S I I~ ~ - F11 (Asphol - l I ~ ~ t Pavement ~ I i I ~ Woods-•1 ) I ! ~ L ENCASEMENT PIPE _ _ ~ 1 1 ~ ~ o~ WITH 8" PVC FORCE MAIN ~ 1 I ~ Ivl 10y-~_~ - i ~ N ~ ~ (BY DRY BORE & JACK) ~ V I~ 1 Nse t~ s ~ 1 -C ~ J f 1 „ 1 `il I' I - ~ ` ~ NEW 8 PVC FORCE MAIN ~ ~ ~ ~ T Q ~ ~ o Ex. 3" Force Main ~ r ~ ~ (7.5' OFF EOP, TYP.) ~ ~ ' ; I ~ - . o ~ , 0 ~ol ~ 11 ~ Hse ~ ICI F71 i 1 ? ~ ,I Spruill Bridge Road 1 U1 1 ~ ~ \ (SR 11421 EX, 15 RCP _ ~-v ~ ~ Nse ~ ~ ~ 8 ~ USE CONDITION 2 - ~ ETA +00 TRANSITION - ~ (SEE INSTALLATION DETAIL) ~ Nse " ~--woods ~ ~1 ~t0 .5 TO 5 OFF Ex. Creek •o, 4~ 0 ~ ~ _ _ ~ NEW°-8"~J~~° O ~ TEMPORARY RECEIVING PIT i~ ~ (APPROX. SIZE & LOCATION) m i' i ~--Woods--.1 In i ~ DESIGNED BY. ~ WBJ 3 DRAWN BY; TK 1 EJB CHECKED BY: ~ 5 5 WBJ PROJECT NO.; 2876-B _ - - ~ ~ r.. ~ ~ ~ DATE; Aug 2007 N 0 ~ Ex, ~ " RcP Mi • NEW 8" PV FOR E M N Ex, Grode Q SCALE; rn ~ 2'-0.. o t. VERT 1" = 50' N~ m ~ ~ -5 5 SHEET 5 OF 95 ?irw e i r n?in r~rr co ENCASEMENI Q) u (SEE DETAI ) ~o co -~o 5 10 14+00 15+00 16+00 17+00 18+00 19+00 20+00 21+00 22+00 23+00 co ,3+00 24+00 25+00 26+00 27+00 28+00 Z Z ~--Woods-~ ~ / 11 Q N 'v^ NEW AIR RELEASE MANHOLE _ . - - - _ _ ~ W w ~ Z ' W/1" VALVE ~-Woods/Wetlands ~ OWN O I ~ I 1 - I r~~' ~ > ~ J~0 ~ r' i i N ~ ~--Woods O / ~ Woods W V ~ o - - o ~ , vementl - Z 0 - ~ I m ! ~ halt Pa o - u. • ! G ' FM a m co r / - - ° LL ~ ~ / ~ m ~ T~~.- ° _ . o ~ 1 - FM ~ _ - - ~ ~ - 310 f , ~N - - ~ R 1 ~ - - lS _ - _ , Q ~-woods-.~ ~ n - o pa ~ dR __I- y ~ ~ , ~ Alligop _ I v I - - ` ' ' ~W I 'I Z Z _ R , m _ ~ ~Im x m .x 1• _ ~ _ ~ ~I'o o N ~ ~ _ ~ ~ I~ V W U U .I ~ - - ~ NEW 6" PVC FORCE MAIN I,~ I _ _ I~ ~ ~ F m z~N j ~ ^ ,k (5 OFF EOP, TYP.) I, I w~ N 10• D Zv '.n I, ~ m ~-Woods--~ ~ _ ° Q, + ~ • ' ' : f MIN. ~ ~ ~ I O Nm ~ ~ oo ~ I ~O I ~ ~o 'I 'I V N ~ ~ ~Z ~ ~ ~ ~ 1 c[ U c+7 u O Q z d' (n ~ Woods/ m N I = I v ~ I+ ~ ~I m ~O Wetlands ; ~ I Woods/Wetlands-.r M 1 f' - L W v ~ ~ ~ m v' k ~ I m N I ~ ~ ~ , ~ i y m I ; f \ W z a° ~ q~,„ ~ m R7Y`~.~.~`~'`r~~"wr o a O . ~ ~ ~ 3 STt~~ ~ 2 ~~c O N N ~ a W j O z m ~ L ~ ~ W W z W Z d N C7 ~ - - Ex. Grode ~ W - - - ~ 3 -0" NI " PV _ _ Ex• Grade i NE a z ~ C VER 0 ~ 0 U ~ f- O Ex. 72" CMP W +I Ex. 2" CMP O ~ N Z otS = 0 LF 60 F ~ o _5 ~U ~o z~+ rq~ Q2r H Z ~ U N } N s'-o' I. _ z UJa -10 +I + + 201+00 202+00 196+00 197+00 198+00 199 00 200 00 202+00 203+00 204+00 205+00 206+00 207+00 ~ w ~ ~ W O rn ~ Uo0~ d ~ ~Q + ~ 00 L OF " HD E HO IZONT L i _10 } p W - ~ N I- Z~ -1 , Q~ far i 193+00 194+00 195+00 i ~ i . i i i i W~ Z~Ia- Q p ~ ~U 1•~ ~O ~ k i k io id ~ O N , ~ 1 i iW i~ r z (3 CONTRACT 2 CONTRACTOR SHALL ~ p ' ~ p J 1 1 I W ~ J LOCATE CONTRACT 1- 6" FORCE MAIN, ~ ~ G. ~ Q I I I ~ N W J 6 PLUG VALVE, EX. TEMPORARY PLUG Q ~ p 1 , ~ & BLOCKING AND CONNECT NEW 6 Z p G 1 Q J i ~ = W < c ~ ~ ~ ~ ~ PVC FORCE MAI . ~ 1 V Z ~ n co~~ - ~ 0 . nt p(~ t3 ~ 1. - ~ (n ~ ~ k ~ ~ y .o,.~ c z w N ~ r ~ + w m I~ p _ _ i ~ _ -T R/W - m - ~ ASR ~2~~~ ~w + N ~ 3 ~ urch o o ~ Ch Church Ro ' _ _ _ - ~ , I Ex, ence_ _ x N arle v N o W ~ U o Albem (Asphalt Povementl N w Alli ood Road ASR ~ ~ - W ~ g 1310 ~ ~ fAs hot P v N y a w p t a ementl vl ~~o~ ~ U I ~ ~ Q ~ z ~ ~ - ~ ~ } M VJ . - ~ ~~tTS' W U ~ NEW 6" PVC FORCE MAIN i Z U - - - - 1 ~ (5' OFF EOP, TYPJ i ~ ~ ~ i R/W ~ ~ ~ ¢ ~ N i 1 m NEW 6" PLUG VALVE & BOX Ex. 18" RCP i U i J F- o m , ~ a ;a x i Q y (SEE INSTALLATION DETAIL) ~ ~ ;W i i , ~ ~ m N NE I FLOW METER STATION No,1 I I \ ~ ~ • w N (C NTRACT 2) woods-~ Bldg ~ ~ y Q 1•,~ v~ , , m W UIPMENT RACK i J/ ~ M NE ~Q c m ;~k o, -1 ~ (CONTRACT 2) / ~ Woods-., I I I M N 1 O ' DESIGNED BY. WBJ DRAWN BY; t TKIEJB N 3 CHECKED BY. I ~ WBJ m 5 _ Ex• Grade Ex, rode J _ _ - - _ _ _ _ _ - . PROJECT NO.; _ - 2876.6 ~ ~ _ ~ Ex. 18' RCP ' ~ „ M. DATE; auG 2007 N W 6 PVC ORCE MAIN h MIN. 0 SCALE; N 0 HORZ 1 ° = 50' ~ ~ VERT 1 ° = 50' ~ c N W 6" PLUG VALV ~ d, 3 ' 0 ~ ~ NW 5LFCNCREE ~ , E GASE ENT 5 SHEET 12 OF 95 -5 O ~ 12 N o -10 (0 ` -10 216+00 .o 207+00 208+00 209+00 210+00 211+00 212+00 213+00 214+00 215+00 ~ 216+00 217+00 218+00 219+00 220+00 221+00 D n ~C/ 2 ~ .w~; Oaf ~ ~~--woods-~ r ~ k' X11 ~ r m Z z LCI i 1 ' 1 W ~ Q ~ 1 1JJ ~ a; Lll •1 N ~ a' Z - ~k, i'` - ' ~ ~ ,~Gr~.. ~ W ~ ~ ~ ! 0, ~ ~ o z O ~ ~ E+:- o ~ - - ~ ~ ~--Woods CV k ice - ~ \~k \ ~ N ~2~~ - -R/W ~ ~ ~ Z OC ASR - - ~-Woods-.~ m Z o ~ _ , ~ k- ~ - ~ d ~ - r Ro oa ~ ~ ~ ~ ~ ~ ch x o ~ _ o, Ur o ~ _ yr ~ Ch / ' NEW 6" PLUG VALVE & BOX ~ ~ _ _ ~ _ _ em , J ~ r~ ~ <As ~ / - b . _ mJ k ~-Wood _ Phoft Pov 3 ral emen ~ m U ~ 1 ~r v ~ _ tJ ~ ~ ~ ,o' ~ ~ ~ Nse ~ ~ Q `W rv r ~ ~ - - w °m ' ~ k ~ \ ~ 0D w \s k k rl ~ p' - ~ ~ \ s , ~ I - _ ~ ORCE M W MA1N k z NEW 6 PVC F A1N _ ~ x ~ / ~ ~ \ - - _ _ - - f (5 OFF EOP, TYP.) ~ ~--Woods-~ ~ N t Ex. 48" CMP & 30" RCP z ° d. w DITION 2 ~ ~ f ~1SE CON ~ m \ Q ~ ' - o G ~ HS ~ .~°r c EE INSTALLATION DETAIL) `x m~ ~ x ~ m ~ ~ N ~ tfJ \ Q Z Ct r ~ ',o o - L pp U \~5 , z ~ ,1~ W ~ ~;,;~.;j., L Z = M r Q C ,--i o ago 1 e0~Y1 UY1 c ~D 1. , O tV N ~ T ~ O Z m Q) t ~ K ` W W z T W 1 Z O N U' W 10 Z ~o Ex. Grode _ - Q 5 o a - - 5 Ex, G ode ~ - - - 3-0' U ~ CO~ER NEW 6" PV x. x. o U Z cV NEW 6" P UG V VE 0 N v = Q . &BX Wo MIN. ~ O ~ N N W 6 F CO CRET UV Q G= E CASE ENT '5 ~ ? W m -5 + + + 226+00 227+00 228+00 229+00 230+00 221+00 222+00 223 00 224 00 225 00 :30+00 231+00 232+00 233+00 234+00 235+00 ~U w } Q O ~ oWC ww ?o Qr Q ~ cNv w ~ UQ UJ ~ W o n _ ~ ~ a U ~ ? z Z ~C! N ~ ~ ~ J fq ~ ~ , , woods--.~ i ~ 'y W W ~-Woods-.~ ~ ~ ~ Z O 0 k~ c h M ~v - - O a N ~ r; ~ N ~ ` N N r ~ ~ ~ vJ ` ~ - p 0 ~ ~ ~ + N ~ / ' ~ / ~'n D~ ' ' N - - o W J7 ~ ~ ~ ~ R/W~ 9, . ~ ~ . ~ I ~ fAspholf - - P N / 1 - - - ~ ~ Z V ~ - ~ Albem o arle C hurt Q Q ~ h Ro ad ~ lSR ~ m-' ~ 2001 rn _ ~ m o , ~ - i o - _ F1~ ~ ~ i ~ - ~ (`--Woods ,~n~ - - - - - - - ~ - ~ ` - R/W ~ ~ - 6" PVC FORCE MAIN ~ NEW AIR RELEASE (5' ~OF ~ . T ~ MANHOLE W/ 1 VALVE • , , • ~ • ~-Woods-.1 a~ D DESIGNED 8Y. WBJ DRAWN BY. TKlEJB m CHECKED BY. a~ m ~p 10 WBJ PROJECT NO,. 2876•B N - - - - ~ x. Grade _ _ _ _ _ _ - ~ ~ ~ _ _ - - - DATE; - - _ _ AUG 2007 ~ - Ex, Grade ~ 3-0' 5 SCALE: N 5 ~o~ R HORZ 1" = 50' ~ ' W " PV FOR M ~ VERT 1" = 50' ~ ~ ~ 0 ~ ~ ~ W N~ rn ~ SHEET 13 of 95 ~ ~ JN O L 1. N O ~ O ~ \ 0 13 L -5 235+00 236+00 237+00 238+00 239+00 240+00 241+00 242+00 243+00 244+00 245+00 246+00 247+00 248+00 NEW TERMINAL CLEANOUT ASSEMBLY r D r ~ rr n PROVIDE 40 LF OF 12" STEEL ENCASEMENT PIPE TEMPORARY RECEIVING PIT r r 2 r rr r WITH 6" PVG FORCE MAIN (APPROX. SIZE & LOCATION) r r N (BY DRY BORE & JACK) ti 1 f ~ m \ o 1r! 11 ~ ~ ~ Q Q ~ O \ _ O 1 r D ~WV O r ~ _ NN?V//J///' N r r N ~ u~ \ NEW 6" PLUG VALVE & BOX SR _ 13Q NEW 6"x6"x6" TEE v 8J / N 1 + rl i N WWI Z ro I p t~u + QJI- O 10~\ o f - - - ~ O W Z 3 _ _ ~ ~ ~ J~o ~ ~ ~ ~ NEW 6" PVC FORCE MAIN _ _ - - W U d• _ R ~ ~ _ _ (5 OFF EOP, TYP.) _ R_/W~ - W a~ m a z~ ~ h ~ - r~ ~ ~ ~ ~ o ~ Dad ~ ~ o , h ch R G ~ ~ Chur ' q marle e ~ ~ Albe ~ Road W ~ _ ~ _ _ ~ w w vemen t) ~ I r - \ \ ~ / . (Asphalt Po w • • q e ~ T _ ~ 1 ~ ~ Trlr I LI Nse ~ - ~ ~ i i ~ ~ ~ i C ~ ~b ~ _ - '7 ine I P 10 6" Wafer L c~ _ _ m ~ m n _ o ~ Ex. ~ 1 ~ NEW 6 45 BEND ~ _ Io - - ~ r Nse -•I S TEMPORARY BORE PIT • - - - - - - I `D ~ a Nse I ~ , (APPROX. SIZE & LOCATION) 1 I ~A ~ I I ~ ~ 7~ I I __I ~ TEMPORARY CONSTRUCTION EASEMENT X~ I I ~ 0~ _ 0 1,_, ~-Woods 2 NEW 6 22.5 BENDS woods--.~ ~ I--- I w I s F X~' x' ~ I O~ t- m F S Hse Trlr ~ Qom ~ ~ ~ ~ w~ r ' Scrub ~ _ f-~ Ex, Ditch J I ~ 00 I oaz~ ~z - U ~ . m ~--Woods z z ~ m . ~ z ~ e~ri~r• W ~ y- M c~ 0 a QO c co O N N U. T ~ O Z O] ~ - L ~ ¢ ~ 0 0 W w Z w z o N C7 .--i 10 w 10 z I; Ex. Gro e ' J 0 1~ ~ 1- ~ 5 0 3'-0" o - _ - - - - - Ex, G ode U ~ _ _ _ • COVE o U Z N ~ 0 N~ _ ~o 12" TEEL ENCA EMEN PIPE r W + ~Z J(O U ~ Q N ~ ~ _5 ? 'W mc~~n -5 248+00 249+00 250+00 251+00 252+00 253+00 254+00 255+00 256+00 257+00 57+00 258+00 259+00 260+00 261+00 262+00 ~ w ~ Q O cn I- ~ Ww ZO lMP cT 15 ' 2 SCR ~ , , °z~ ~'d Q W N EX. 42" CMP i , ' ~--woods USE CONDITION 2 i 1 : ~ (SEE INSTALLATI N DETAIL) w~ I N ~ ~w O~ r' gld9 ~ i NEW AIR ELEASE MANHOLE N R ~ ` • ' + • • W/1" VALVE ~ ~ I L N ~`--Woods-.) ~ a ~ ~ ' k~ / NEW 6" FORCE MAIN ~ c;~ ~ i-~ o NEW 6 PLUG VALVE ~ y ~ a VALVE NSe ~ O C~ ~ ~ r 1,_ (5' OFF EOP, TYP,) o r ~ I 1 Scrub - o & BOX 'p I L I - ~1 - - - - ~ ! - - I ~ - _ _ Ex. 24" RCP ~ J ~ - i ~ ON ~ ~ w W n ~ ~ ~ o ~ _ s o - ~ 3 ~~r,~~ , I (SEE N TALLATION DETAIL) o ~ ~ ~ Z < ~ ~ ~ ~ _ i ~ o woods C ~ to W Fll I ~ ~ ~ o~ ~ Scrub ~ j ~ ~ C, F- - _ ~ _ _ ~--v' ~ cop ~ u I j (`.-Scrub -.1 0~ w ~ ~ ~ N / ,o ~ w ~ W A/be ~ I mare Ch r\ ~ ~ arch Ro I-~ ~ ~ ~ I --o ____R/W - ~ O ~ I I. , w _ _ I~ Qd N ~ ~.1 _ _ lSR 1 _ _-I _ x. w 2001 lJ lei ~ ~ - I o 1 ~ ~ ~ i - . _ . , ater me (Aspho/t Pavers (Aspho/t Pavement) FlY FM 0 ~ I<I ICI w k Iq ICI Il1 I ~ 1 ~ \ \ ,n ~ O I c~` , / k) ~I~I I I - _ 101 I r _ < ~ _ Q ~ ~ , ' I , , ~ ~ N ~ ~ a II ~ ~ I / LJ ~ ~ - ~ _ ~ I. / ~ I ~ I - - 1~ ~ X0,1. j ~ ~ ~ I ~ 4567 ~ ~ 1/~ I I ~ ~ ~ 4497 Tr1r Hse c~ , ~~cj ~ R/W ro` ~ ` (S ~ ~ e/d i I NE. SER 4CE INE ~ 9 I ~ ~ 4497 Trlr y I ~w VAL E AS EMBL 4497 Trtr ~ i~ ~ WIf ~ ~o _yi_`\~\ ~ a ~ , i I i ~ ~ Dads-~.~ (SE DET TY ~ N I woods 1 . I 4497 Trlr I ~ ~y ~ II ~ ¦ N ii I ~ I ~ S I i'; . , I ~ 11/2' P C (f1 woods , ~ r I I ~ ~I~ I r r I i m ~ ~ C~ / , SEWE INE 1r rr ¦ j Q rl ~ 4329 ~ p i / 11/2" PVC ~ ~ r S.~ ~ ~ Jr Nse ~ r ' o / 11/2 PVC ~ / ~i ~ SEWER LINE ~ I W LINE SE ER C7 - a 0 11/2" PVC i ~ i SEWER LINE ; a~ i 0 NEW 11/2" PVG SERVICE LINE a~ (SEE SHEET 27) DESIGNED BY. WBJ DRAWN BY: L a~ _ TK/ EJB °S +I CHECKED BY. m ~ 10 Wrn 1 o WBJ f~ W N PROJECT NO.. ~ d 2876.8 N ' a~ DATE: I~ - _ - ~ AUG 2007 ~ - - N _ _ _ SCALE; ~ - - - ~ _ ~ Ex. rode ^ ~ _ ~ ~ ~ M 1 ~ _ _ VERT 1" = 50' ro ~ - - - ORCE .o Ex. G ode ~ V MIN. cv , E . 42" C P ~ ~ ~ ~ E Ex. 2 "RCP ~ SHEET 14 OF ~5 t O EW 6 PLU VAL E 2'-a'~ BO co co U O U NEW LF ONCR TE 14 ENCA EMEN No -ENCASEMDT -CS= IETAIL 1-- ~ (SEE DETA ) 262+00 263+00 264+00 265+00 266+00 267+00 268+00 269+00 270+00 271+00 !71+00 272+00 273+00 274+00 275+00 276+00 ~J 1 \ ~ ~ ~ n \ /J o \ 1 \1 ~ ~ ~ WF J ~ ~ N~ ~ a~ z j N ~ -y W w o ~-Scrub/Weflonds o NEW 6"x6"x3" TEE ~ ' > ~ ~ "PVG FORCE MAIN ~ NEW 6 NEW 6" PLUG VALVE (5' OFF EOP, TYP.) \ ~ ~--Woods-~ / / ~-Wetlonds-.) ~ O Z - JFo ~ ~ r /y o Q ~ ~ & BOX ti x 1 1x r• - UJ LLI ~o _ \ ~ - ~W ~ - - W ~-Woods ~ ~ - ~ W ~ ~ ~ ~ / A/b~ - _ ~ m ~ w X01'/~O ` o - Chu _ o ~ m rCh ~ _ o Ro ` z o _ Ex. 6„ ad ~ O rt11 - ~ _ - _ _ - - Water Lrne (SST ~1 Bldg ~ - - + 61 = ~ w 120 0> co ~ ~ - ~ _ ' ~ ~ EX. 15" CMP ~ ~ ~ ~ ~ RAW - ~qs N ti _ „ ~ ,Ohq~t P fil ` ~ ' o ; \ - ~ USE CONDITION 2 Q 2 EX. 36 CMP _ w o~eme _ - f'~ s,'.~ ~ o (SEE INSTALLATION DETAIL) w ~ , - ~ ' USE CONDITION 2 nt~ _ 1C9r (1 ~\o\ x ~ w ~ (SEE INSTALLATION DETAIL} OPEN CUT UT~t~/~~1J' 15~ ~9 \ ~ ~ N \ D \ U W ' ~ ~ ~ 11/2" PVG SERVICE LINE ~ Z w - - \ \ J ~ ~ ~--Woods/Wetlands 2659 ~ 1 \ 1 Q ~ o / 1 1 ~ x ~ m ~ ~'1 NEW SERVICE LINE Hse U W - Y \ \ v c~ °,n° - ~ \ ~ rt U M 1- VALVE ASSEMBLY ~ _ _i/ ~1 O Q Zd' TYP.) 0 Q (SEE DETAIL, to ~ ~ r.,. U ~ . ~ ~ - - NEW 6"-22.5° BEND -L z - rn ?•iRw.~k. t z O NEW TERMINAL CLEANOUT ASSEMBLY ~ o ss D I 10' PERMANENT UTILITY EASEMENT I-' a ~ 1~4 2 oJ4° O N N ~ ~ I A ~ W ~ T 1 ~ O Q) a a z m~ _ ~ rn . ~ LL.I w o W a z o N ~ ~ W 5 Z a 1 t~ 1 - z . ~ J _ - - - - r 0 o Q _ - 3._ n F °C O -0„ U ~ 2 = 2-Ex. 36" CM ~ U O Z N ~ SLFCNCREE _5 Uo IN.. E CASE ENT T W + UU QQ7 ~ ~ ~ W I- m 0 0~ ENG EME T (SEE DETAI } + O 285+00 2ss+oo 2s~+oo 2sa+ao 2ss+oo 2so+oo J W ~ ¢ p 285 00 ~ + O 283+00 284 0 ~Q +o0 282 0 ~ ~w Zo ~s+oo 280+00 281 277+00 2~s+oo 2 ~ ~ Qm i i 1 ~ 1 Q~W ~N ~ I ~1 1 w W I I W ~ ~ 3942 Garoge W j ~ ~ Hse Q ~ O N W i I I I ~ ~ I e ~ Hse ! G) ~ Id I ~ f 9r~d~/ ~ I _ r ~i i 11/2" PVC ~ W Bldg i I I I r-~ j i/ ~ I , ~ ! I I I Flog ~ ~ ; ~ 1 - ~ ' ~ SERVICE LINE ~ i ~ ~ ~ i I Pole' I L--_~ ~ I I I _ W ~-Woods ~ i ~ I ~ Ex. Sidewalk I ~ i o ~ W ~ ~ U C~ ~ W I ,I~ I I I ~ I I I I I i I I I ~ i NEW SERVICE LINE ~ ° ' , VALVE ASSEMBLY w W ~ I I I I~ ~ p L ~ ~ I ~-woods , I c>' ~ NE "PVC FORCE ~ 'VC FORCE MAIN ~ ~ (SEE DETAIL, TYP.) ~ Z ~ ~ Trlr I I ~ I I p I i \ - I I , o t / (5 OFF EOP, TYP.) )P, TYP.) ' I ~ c, O~ ~ ` - I I I I _ ` a - - ~ ai ~ N I,~ cal - - - - I o I ~ R/W - - - 1 Q ICI lol _ ~ - o ~ ' I-m~-' V 3 ~ G~ ~ I°~ ~ I oll ` ~ ~ W ~ I~ ~ ~ ~ w - lSR 1200 ~ M .M M \ ~ N J w Church Road (As holf Pavement) Albemarle M P M o Q ' M V ~ , w M ~ Ex. 6" Water Line ~ _ 1• \ tier Z _ w ~ Q I1ocI _ R/W I - -TI- _ ~m Q ~ ~I \ ~ ICI I I ~ I I ~ II ~ II ~ II ~ I I 5~ ~ II o' ~ I I 00 00 ~ I I 0 0 ~k~ I I ~ 0 nJ~ ~ I I ~ 00 a~ I_~ ~~P i C 0~ Hse ~G~ N ~P DESIGNED BY. WBJ O DRAWN BY. w., TK l EJB CHECKED BY. 3 5 WBJ PROJECT NO.. ~ ~ ~ ~ _ ^ - - 2876-B - - - - ~ Ex. Gro - ~ DATE: m ~ r _ _ ~ ~ AUG 2007 O SCALE; HORZ 1 ° = 50' ~ - - VERT 1" = 50' 0 ~ ~ ~ ~ N ~ S SHEET 15 OF 95 N ~ 0 N~ a~ r_ J r' l~ CIO -10 O ~ 300+00 301+00 302+00 303+00 299+00 L 296+00 297+00 298+00 299+00 291+00 292+00 293+00 294+00 295 00 290+00 m~~ I I .1 I~ s IJ _ _ - - - - - - - - Approx. Property Line i i - - - - - - - - - - - Imo' I m ~ Q o x 1 I~ i <S a GG I ~ G I r ~ ~ k ° ~ 0 o i ~WF- 4~ ~ ° O NEW A1R RELEASE MANHOL woods a 3 E ~ P ~ Q S W/ 1 VALVE A1'~ 1 ~ ' w W a ~ z lv , 1 u _ o h,,, ~ NEW 6 22.5 wetlands G i I ~ II o NEW MANHOLE N0.2 w H O P BEND w ' t o I. I >F ~ ~WN I _ Z > ~g ~ NEW 6 PVC FORCE MAIN w .E NEW 6 45 ~ I E o (2 OFF PATH TYP.) \ I o ~ _ M ,J ~ o W END o ~ ~ o ~ ~ _"_~8~= ~ M E- 6~~ yyafer-l.~ng-------------------- ~ F' V ~ x. 0 ~ I o CD 6 Ex_Property Lrne - ~ • N ~ - ~ ~ ~ --~prox_ r~e~ ne ~ Z ~ 0~ ~ - M \ M ~ - 1 ' RC ~ rw _ ~ ra Ex. 10" WoteMLme " ~ ~~I (Gravel/SorlRbadJ - • _ ~ ' ~ ~ ~ MAINTAIN 3'-0" MIN. ~I f I 1 ~ ~ ~ - - (v1 L I " ~ SEPARATION NEW MANHOLE N0.1 - ~ ~ , o'i I NEW SANITARY ~ Q th ~ _I I .I • I I I ( ~ ~ ~ I ~ ~i ~ (6._0.. I.D.) ~ SEWER ~y I Bld I ~ II ~I ~C - ~l I I o „ r` ~ Approx. Property Lr7re - ~ ~ z - - - ~ ~ / ~ ~ ~ ~ ~ (SEE SHEET 84) ~ ~ 0 wo~ds I I ~ , I NEW 6 PV ~ . ~ > o I I ~ I C FORCE MAIN o~ ~ I I I , (SEE PLAN BELOW} = o i ~ „ I M ~ ~v W = I ~ i io NEW PUMP STATION N0.2 N o , I ~ ` (SEE SHEET 90) ~ I NEW 4 PVC FO I I I ? ~ ~ N v L RCE MAIN _ _ 3556 Bldg I I ~ ~ ~ I ~ ~ I , I N ~ (SEE SHEET 17) Hse p I w~ ~ v ~-wetlands o I•~ i o h 16 .c I----- m~ I 1 . v ~ , .~I ~ ~31~ ~ ~ . C ~ ~ ~ / I ~ ~I w a~ v ~ I ~ I •oj ply I z w ~ ~ ~ k ~ ~ Q ~ c+•i ~ 3556 a I ~ Hse a I • ~rwn ~ o I w i ~ i NOTE r2 ~ o i A 30' TYRRELL COUNTY PERMANENT UTILITY EASEMENT ~ ~ • k CENTERED ON THE FORCE MAIN EXISTS ALONG THE UTILITY ~ D a ~ al ~ ~ ~ Q4 o i o i ~ WHERE IT IS OUTSIDE NCDOT ROAD RIGHT-OF-WAY. THIS ~ o U ~ Q woods I ~ j ~1 Woods Z ~ { ; i ~ EASEMENT WILL ALSO SERVE AS THE CONSTRUCTION ~Z ~ 2 ~ II ~ i a ~ ° LIMITS FOR THE WORK IN THESE AREAS. o W Z ~ tl w ' `0 i ~ a ~ Q J~ n. O - ~ ~ ~ o W z m ~ ~ ~ y Z a ~ - .c ~ ~ U y W y w Z 5 o z o C = LL' 0 ~ _ ~ r O ^p+ ~ ~ 3 W W ~ 3 _ 5 z - ~ a _ U w x, 6" W ter Ex. 18" ~ ~ - _ m W RC W ~ ~ _ _ Ex_G ade - Ex. 1 ~ - - ~ RCP N W „ 3'-O" - _ ~ - ~ O _ - ` _ f ' ± ~ Q COVE ~_0~ Ex. 36" RCP Ex. 36' CMP ~ Z TYP:) 0 ~ Qo 2'-0" V ~ O+ CV 2 I~ ~ u 6'-O" 1. EW 8' GRA ITY MIN. Z cv Q ~ i +I I E ER _5 Nv ~O I r 0 r ~ O H ~Z t-o -10 a ~ U O ~ O O 303+00 304+00 305+00 306+00 + 307 00 308+00 309+00 3 + + 10 00 311 00 312+00 2+00 313+00 314+00 315+00 316+00 _ 10 ~ ~ w M a 317 00 U ~ CA ~ ~ Q i ~ W cn Z I I EI I ~ w W°C ~Q NOTE I I v I I ~ o~ ~ g A 30 TYRRELL COUNTY PERMANENT UTILITY EASEMENT ~s I , o I ~I ~ Q~ Qw CENTERED ON THE FORCE MAIN EXISTS ALONG THE UTILITY ~ I~ I~ ~I WHERE IT IS OUTSIDE NCDOT ROAD RIGHT-OF-WAY. THIS ~ i~ i~ a U S'I'RE EASEMENT WILL ALSO SERVE AS THE CONSTRUCTION ° I , ~ AM l I 1`, ~ w~ w~ • ~-Woods-.) Woods-.) Q ~ V ~ ~ I ~ MP~}R' LIMITS FOR THE WORK IN THESE AREAS. I o I ~ 3) CA ~ } ~ ~ O j D I D I'o W T ~ v ~ ~-pttJD ~ a I I~ ~ ~v ~2a I~ I~ al I o I.a? Q ~ I~ o I ~ I ~ 13 11/ PVC TA 14+pp . ~ z > I'~ I ~--wetlonds ~ SEWER SERVICE ~ I~ I ~ I S RVICE , 3y es ,s' EE SHEET 17 ~ ~ ~ IV I~ u I ~ ~ ~ NEW SERV E LINE C i k I.~ I~ ~ I ~ VE e`E w ~ Z ' r ~ ~ NC 60' iw ~ I VALVE ASSEMBLY ~ i ~ I`° i ~ (SEE DETAIL TYP.) ~ ----II ~ 3556 ~ I ~ z - ~ I k I ~ I NEW 6" PV FORCE MAIN ' r\ r._.__.-___.._ I N I , I~ I k ~ ~ ~ (5' OFF PAT , rYP.) NEW PUMP STATION N0.2 I I I i o ~ ~ ~4 II i j Bldg Hse ~ ~ 11/2" PVC I ~ I I to co L-' ~ x (SEE SHEET 90) I ~ I m o 0 a ~ ~ SEWER SERVICE o ign, I I I I I D~? ~ =ao `c~ ~ I I I I ~ ? ~ I I I I I I , - 1 oQ I i rn - - - I z ~ III o 81dg i~a ~ I ~-Woods ii ~ li ~ ~ II o I+ ~ ,.n, ~ I ~ I. ~ NEW SANITARY ~ NEW MANHOLE N0.1 I ~ I I i oa--------------------------- ~ ~ _ wv~ i_ u ~ I I ~ _ - v ~ - ~ ~ I ~ ~;i SEWER 6 0 LD.) ' I I I ~ (SEE SHEET 85) I~ i to `I ~ - - ~ I (Gravel/SorlRoadJ ~ - - 12- NEW 6"-45° BENDS ~ ~ III r~ ^ - - ~ . - - - ~ ~ '-----I-------------------- ~ ~ w ~ _ W- . Ex. 10" Water Line - - w w ~ - \ 8.. R ~ ~ _ ~~--I'-- ~ - w 1 ~ =~-1--1- T`-- - - ~ ~ ~ II ~ Approx, Property Line - 0~ ~ • . ~ NEW 6 PVC FO - _ _ _ _ Scrub w ' 6" PVC FORGE MAIN Approx. Property Line - - ~ - - - ~C7-. II - , x. 6" Wa r Line -==fi~7- I . ABOVE) co E o ~ ABOti ~ 7 ~ \ • ~ t------- I a I NEW AIR RELEASE MANHOLE 3 ~ - - ~ I ~ ~ I I k W/ 1" VALVE ~ 1 NEW MANHOLE N0.2 ~ ' I C ~ I I~ \ I o c~ ~ ' . ' ~ ~ ~ I ~ o ~e Hands Woods ~ p \ I I '1 1 I Z \ I m 1 ~ W I 'I J I ~ I , ~ m i' Cl~ ~ , . _ ^ I o N 1 ~_1 ~ II - ~ _ o - - Approx. Propel Line = ~ p, ~ 31 w ~ ~ z a ~ _ ' w DESIGNED BY; WBJ ~ ~ o + DRAWN BY. Q~ o ~ 5 W +J w TK! EJB ~ v ~ 3 ~ Ex, Gr de _ _ ~ f ` ~ ~ CHECKED BY. r . ~ W 5 wBJ ~ - _ ~ ~ ~ PROJECT NO,; ~ I ~ ~ ~ N W 1" T (ST . 1+00 TO S . 3+25) . ~ ~ _ _ ~ ER S RVICE _ _ _ _ _ - ~ r`de 2876•B N 0 ~ 30 DATE: ~ ~ N W 6" VC FO CE MW Ex. 6" CM x. 36" RCP ~ C VER ~ C vER AUG 2007 Ex. 15" RCP Q SCALE; ~ No HORZ 1" = 50' ~o v N~ MIN. VERT 1" = 50' _ 6" RJDI 0 LF 5 ~I s' o„ NEW 6 PLU VALV & BO RJD t. m v, S suF~r 1 R nG QF O" TI U "---NEW -5 LF CONC ETE 0 00 10-co „ C\j ( d (SEE DET-Adt.) 0+00 1+00 2+00 3+00 4+00 16 5+00 6+00 7+00 8+0 0 9+00 -10 10 10+00 11+00 12+00 13+00 14+00 NEW 6" PVC FORCE MAIN ' (SEE ~ HEET 17) ~ I Z z ~ I ~ ~ ~-Wetlands 1 ~ ~1 W o I ~ I i Way Z w o I , I i ~ --Wetlonds--~ ~ W ~ I m % / j ~ ~--Woods-~.) ~ Z ~ J ~ 1 . ~ ~ ~ 0 w ~ ~ ~ 1 ~ 0 V ,o l i ~ 3120 I,a 1 _ ~ N I ~ ~ i Trlr a ~ rt ad,oti ' - NEW SERVICE LINE ~ is'1 / ~ t, I ~ 11/2 PVC k ~ 1 VALVE ASSEMBLY S WE SERVICE ~I I ii w (S AIL TYP.) E R I I (n EE DET ~ - , , I I - r I i' I I ~ I~I I o - ~ - Z • ° Imp o I ~ I / i ~ o R/W _ Y Cpl - M M 'D - - ~ _ - - - - - r - - - n M Ex. 6" Woter Line M -I^ -C ~ m W ~ 1 1 M M .J. ~ + - G rn M M m~ ~ veme~ I ~ L ~ m ~ lAsphoit Pa 'Aspholt Pavement) ~ J r o s Ba Run CSR 12021 Bull y m - a N O ~ I ~ FM ~ ~ ~ ~ O O O ~ V (j) Z VI VI - - i 0 - - - ,I NEW 4" PVC FORCE M~ NEW 4"x3" REDUCER m ~ ° _ IC FORCE MAIN ~ ~ N i ~ (5 OFF EOP, TYP.) ~ ~ ~ ~ V M TYP.) ~ O Q 1 .p ~ ~ I NEW 6x6 x4 TEE vi U p I NEW 4" PLUG VALVE & BOX 2 Z Z F~; ~ (BEGIN STA.0+00) m _ _ ~ ~ a = M II ~ a ~o O ' O N N ~ ~ O 2 0] ~ L ~ ~ W ~ W ` = W Z Z ~ N (7 ti W 10 Z Ex. Grade - - - - - ~ / IN. _ - - Z 5 5 a ~ U ~ 2 O Q Z CV m x o NU 0 J ~ ~ J NEW "x6"x " TE NEW " PL G V VE & BOX O cn0 m~ U U ~ CV ~ ~ Z Q _5 0 o W ~ ~ -5 0+00 1+00 2+00 3+00 4+00~ 5+00 6+00 7+00 8+00 9+00 9+00 10+00 11+00 12+00 13+00 14+00 J w ~ U OO ~w po au U°o W oWC ~ ~ aN 1 ~ i ,1 ~ - z d- ~ o 1 I ~--Woods 1, 1 U W 1; 1 Woods-~ 1 1 lx xl, ~ W Z I ~I 1. In '~I W ~ I, 1 to r W 'kl 0 111 ~ = I ~ ~ o , 0 o __Z (fj cn; o I _ _ m M M ~J N = - - - - -1- - z Ex. 6 Water Line M L n M M M M D ~ f M IV W M lAs holf Pavement) m ~ Ba Run CSR 12021 p Bulls y ~ W o o m- , ~ ~ ~ ~ FN +O I Cn ~ ~ t:u I , i~~i _ O ~ ~-1-~u ~ , o r ~i_ I ~ ~ O ~ ~ ~ Iii-- ~ m ;k m ~ I 1 II EW 3" PVC FORCE AIN ~ Q i N M W -LINE ~ ~io _ I - (5' OFF EOP TYP.) NE 3 IN , I ° ~ ~ - CLEANOUT ASSEMBLY ~ ~ ~ N I , i m W ~ II ~ ~ , ~ ~ Z -I a~ IV ~ J I z s`r~ _ ~A~A IMp~c ~ 1 T 12 U Ex. 30 CMP 22. ~ ~ USE CONDITION 2 Q v, ~ (SEE INSTALLATION DETAIL) 0 DESIGNED BY; WBJ DRAWN BY; TK 1 EJB CHECKED BY; 1 O WBJ m ~ PROJECT NO.; 2876-B N r - - - - - - - - - - - - - - - Ex. Gra e - _ - - - - DATE; . - AUG 2007 N 5 - 5 SCALE; ~ Ex. 30 ' CMP HORZ 1" = 50' EW 3" P C FO CE AIN ~c VERT 1" = 50' N ~ ~ 2,_~„ ~U N~ ~ u ~ ~ ~ Q CLE OUT ASSE BLY SHEET 2~ OF 95 ca (f) O" F CASE ENT O (S E DUAL) 2 -5 14+00 15+00 16+00 17+00 18+00 19+00 20+00 21+00 22+00 23+00 ?3+00 24+00 25+00 26+00 27+00 28+00 I f ` I f ~ ~ 1 ~ f 1 ~ ~ f I ` ~ f I ~ N ~ 1 ~ / ~ o - - ~ Ql l ~ l 1 NEW 3" IN-LINE ~ ~ - - - ' ' ~ ~r ~ ~ ~ Q! ~ CLEANOUT ASSEMBLY - - , ~ cal / Q I , 1 /W 7} 1 NEW SERVICE LINE R / ~ ~ 3 ~ 12 - SR ~ ~ W VALVE ASSEMBLY ~ S ~ ~ (SEE DETAIL, TYP.} bore - ~1 I_ ~gsPh S - ~ 1 _ rle _ _1-1- I ~ ~ rASAhoItPoVementJ ` O / ema , ~ I 11/2 Pvc , Alb - o - , / ~1¢ 10'1 SEWER INE I I ~ 1 ~ 1~1 1_1 . ~ ` ~ / cn~ ~ ~ - /R/Vd ~1 1 al i Iol cn N ~ O ~j 141' ~ ,C7 W + ~ j- ~~!r~~,, / m 0 ~ ~1 `t1 1 I 1 ~ 1 I ~iJ' I o m 1 1 1 1 / , ~ ~ ~ o FM lal 1 , i 1 1 < 1 ~ ~ ,m 1 , ~ I I ~ ~ ~ ~ Z Woods ~ ~ ~ ` ~ ~ ~ / I' 1~ 1 W ~x l ~ I I s _ ,1 - - 1' 1 Hse I r o f 1 1 1 ~ F11 - i , ~ 1 ~ ~ 1 1 1 1 3 2 / l i 13 ~ 1 1 I 96 / _ ~ I I ((1 ~ I ~j ~ 1 1 ~ ~'k Hse ~ 1 ~ C,, ~ 1 I 362 t 1 I ~ \ ~ ~ ~ I Hse ~ ~ 'o N . ~ ~ o l 1 1 ~1 ~ r- In ~ . o~ 1 ~ ~ ~ 0 ~ z ' ~ ~ ~ ~ '1 1 yl 1 I \ Conc 91dg ~ 1 ~ w j FM / ~ ~ ~ 1 I (i ~ ~ I , _ ~ ~ / I NEW 3 PVC FORir~ WI,2JN m 1 _ _ I , . ~ D,Sh otellrte z p 'x' i . ~ ' ' I p (5 OFF EOP, TYP.) ~ ~ la~ ~ W~ Q~~ 1~1 i N m - o x ~ m 'i ~ S'~ EWER LIN ~ o j N , r 1 ~ C V N tom[) ~-Woods-., ~ G z ~ r' m I _ eld 9 ~ 1 Cn 1 0 a ~ ~r N ' _ - . ~ l 1 U y ~ 1, • `L ~--Woods ~ ~ a' ~ 1 - ~ ? ~ ~ 'll Z~ N V W z I- a O a ¢ o N 11 - O c o0 - fp N ~ ~ 00 O Z 07 ~ L ~ ~ ` w W O T W ~ 1 z O N C7 ~ 5 W 5 Z _ - _ - Ex, rode - - - - - - - - - ----1 ~ - / - - J - - Q _z 0 OVER O 0 J a ~ ~ X ~ W W - NE Z N w -5 CLE OUT -5 N~ o A zcno ~,z ¢w + ~ -10 ' w a ~ ~W ~W~ 14+00 15+00 16+00 17+00 18+00 19+00 20+00 21+00 22+00 23+00 !3+00 24+00 25+00 26+00 27+00 28+00 ~ w ~ ~ m ~ ~ cn U¢~ NOTE )TE~ NEW 3" PVC FORCE MAIN w w ~ ) ~ o A 20'TYRRELL 20'TYRRELL COUNTY PERMANENT UTILITY EASEMENT (SEE SHEET 24> ~ ~ w a ~ o CENTERED ON WHERE IT IS C :NTERED ON THE FORCE MAIN EXISTS ALONG THE UTILITY ~ °z ~ ~ ~ dr+' HERE IT IS OUTSIDE NCDOT ROAD RIGHT-OF-WAY. THIS OPEN CUT NEW 3"x3"x3" TEE Q w ~ EASEMENT WIL ~SEMENT WILL ALSO SERVE AS THE CONSTRUCTION ~ ~ ~ = Q II I LIMITS FOR TF vIITS FOR THE WORK IN THESE AREAS. ~ NEW 3 PLUG VALVE & BOX ~ ~ Z ~ ~ 1 1 II 9 0 I I ~ 1 ° ~ I NEW 3" PVC FORCE MAIN ~ o n. Q (5' OFF EOP, TYP.) / ~2~ 9s o'~ o ~ ~ 1 I I I I I I I GGR oo. ~ = w I `J / / / soo Ex. 10" RCP HSe ~ J Q I- I ~ W I I ~ ~ ,poi, 3P USE CONDITION 2 / w I 1 W I I 1 Ex. Creek ~~~r; ~ Fro, (SEE INSTALLATI;f~N j ? ~ I T~ C W I I W Z F ~ ~ 1 DETAIL) ~ Ol ~ O I~1 Cn r' ~ (n O 110 1 *O - / ~ 5 ,gyp ~ / ~ - O Im 1 \ O Z -'7 Ot / '2 / / i '9~~ j ~ i e 5r ~ i NEW 3" IN-LINE /G ~ / ~ = o l 171 ~ I , , ~ .~~,a------ - ° W ~ --I ~t~ CLEANOUT ASSEMBL ~ /~o j / ~ l W ~ D y~ Z~ / ~ / 11/2" PVG \ Hs~ ~ lAs bolt Pavement) m ~ W I P m - Ao Albemorle Shores A CSR X2371 Q v tSj, ~b ~ ~ 3 SEWER / O ~ ~ ~ + ~ O FlI Fw FY FN - - - - - -~j O '9~ nSERVICE j/ a~ 00 I - - - ~ --~j--- - I~ ~ + O a, CV I~ I R/ ~ 11°<1 ~ I fn \v/ U Q 1~1 „ m lol NEw 3 PVC FORCE MAIN I m ° ~ 1 1 (5' OFF EOP, TYP.) O ~ ~ ~ / C~/ NEW SERVICE LINE ~ G/c/ ~ 1 I ~ ..AAAA ~ ~ I E~r? I MP~k cT 2~1 w ~ _ 3'1 VALVE ASSEMBLY s / / ~ Z ' 11 iki - (SEE DETAIL, TYP.} ~ kQQ w _I ~--woods II 1 o I EX 24" CP ~ I Irtl R s~ ~P~ ~ USE CONDITION 2 = ~ U 1, 1 iii ~ 1 , ; (SEE INSTALLATION DETAIL) m C Q 1 1 I I I'tl y~~ ~5 ~ti ~ a, ~ 1 11 i ' ~ 1 I ~ 1 5 PSG ~~5 ~ 1 1 I i t 1 ~ 5 I N k W DESIGNED BY. L WBJ 0 3 DRAWN BY: TK / EJB ~ CHECKED BY. m 5 5 WBJ Q , ~ - Ex. Gr de PROJECT NO.: N ~ _ _ _ _ Ex, Grade 2a76~B ~ - - - - _ DATE; _ ~ AUG 2007 N 0 ~ , Ex. 2 "RCP ~ ~ N• MIN. Q SCALE: HORZ 1" = 50' ~p C VERT 1" = 50' N ~ 00 V 20 ~ - L L NEW 5 LF CONC ETE ' S SHEET 23 OF 95 X x O O (SEE DET Nil N o v, t - ~ 10 ~N~ -1o 23 C) 28+00 29+00 30+00 31+00 32+00 33+00 34+00 35+00 36+00 37+00 7+00 38+00 39+00 40+00 41+00 42+00 r 1 ~ I n NEW 3 PVC FORCE MAIN-=- ~ D. . 5o J 2D (SEE SHEET 23) c~ Hse Nse ~ I I ~l ~ T~ N~ I ~ I 11/2" PVC I cD ~ N SERVICE LINE ~ ~ ~ \ \ ~ ~ ~ ~ v N 11/2" PVC 0 v 0 Ex. 1D" PVC > ~ E- END OF NCDOT ROW ~ I W SERVICE LINE AND MAINTENANCE I cD ~ I NEW 3"x2" REDUCER USE CONDITION 2 ~ w ~ ~ ~ N b ~ NEW TERMINAL CLEANOUT = N I N b fll~W 2 PVC FORCE MAIN (SEE INSTALLATION DETAIL} ~ (5 OFD, EOP, GYP,} l ~ ASSEMBLY ~~,',QQ i ~ „ o NEW SERVICE LINE W NEW 3 PVC FORCE MAIN Ex. 10 PVC ~ ~ o ( (END STA. 47+89~ W " EE ASSEMBLY ~ NE 3x3 x3 T J W (5' OFF EOP, TYP.) USE CONDITION 2 0 ~ (SEE DETAIL, TYP.} ~ C ~ NEW 3 PLUG VALVE ~ ~ _ ~Aspho/f POVemenfJ ~ _ N (SEE INSTALLATION DETAIL} o ~ Albert v o ~ & BOX Albemarle Shores Ext. ' , ~ - _ _ _ U + ~ o ~ (BEGIN STA. 0 00) CI O ~ o~ ~ ~ ~ ~o ~ I ~ I o o ~n0~elp~ I~ + ~ N ~ o~ ~ ~ I ~ I 3 ~ a ~ „ (Asphalt Povementl CE MAIN fJl p ~ ~ ~ ~ n X ~ Albemarle S NEW 3 PVC FOR pores Ext. {5 OFF EOP, TYP.) MAIN I ~ ~ ~ ~ I W l~ 0 o n NEW SERVICE LINF~ I ~ ~ I~ I~ _ o ASSEMBLY Z ~ (SEE DETAIL, TY~~) ~ ~ 250 ~I ~ ~ ~ li J NEW 3"x2" REDUCER ~ Hse NEW TERMINAL CLEANOUT F M ~ 2 Ex. 1O" PVC U USE CONDITION 2 NEW 2" PVC FORCE MAIN 11/2" PVC ~ ~ I~ ~ ASSEMBLY Z w F"' (SEE INSTALLATION DETAIL) (5' OFF EOP, TYP.) SERVICE LINE ~ ~ ~ I ~ (END STA, 4+00~ Q- m a NOTE cc U m `-V ~ ~ N ~ A 2O'TYRRELL COUNTY PERMANENT UTILITY EASEMENT CENTERED ON THE FORCE MAIN EXISTS ALONG THE UTILITY UTILITY I Hse 234 I ~ Hse U ~ ~ ~ WHERE IT IS OUTSIDE NCDOT ROAD RIGHT-OF-WAY. THIS HIS Hse I~ ~ " z ~ } ~ ~ LIJ Z EASEMENT WILL ALSO SERVE AS THE CONSTRUCTION LIMITS FOR THE WORK IN THESE AREAS, L ~ ~ J ry'Sy,~~ Z r-1 C ~ J ~ O ~ ~ - d ¢ o c o0 O N N Ur T ~ O z m rn O _ ~ w o Z LLJ T w Z ~ d J_ z o N ~ .--i Z 5 5 5 5 o W wZ WW Ex. G ade Ex. Grode .-r U _ _ _ MIN Ex. 0" PVC Ex. 70" PV ip Z ~ u 0 0 O 3 VC CE AIN - N FR 2 20 O O Q U I-pNQ H W + (n EW " x 3' x 3" TEE NE 5 F CO CRET ~ - EW " PLU VALE NEW 3"x2' NEW 2" P C EN ASEM NT z ~ ~ ~ O W ~ NEW LF ONCR TE NEW 2" P C - - - EDUC R {SE DETA L) 5 -5 N o 0 ~Oo fAZ Jpfa-~ U o ~ ~ 2 - - -10 10 -10 -10 Z m~a 10 0 oW a`~m 42+00 43+00 44+00 45+00 46+00 47+00 48+00 0+00 1+00 2+00 3+00 4+00 U c~n ~ o J w ~ ~ Q ~ Q Z ~ ~ W ~ ~ O } ~ w U ~ O 1 ~ \ I- Z c!~ pC ~n w~ oNQ 1 2 a~ ao~ ~--Woods ~'1 u NEW 4 PVC FORCE MAIN ~ ~ 1~ ~ z ~~o EE SHEET 19) . ~ ~ Wood 1~ ~ Q ~ Z !n NEW 4"x4"x3" TEE „ ~ k w c~ . (BEGIN STA.O+00) 1'~ woods ?~Woods/ ~ ~ Q ~ • NEW 4"-22.5° BEND ~ • Weflonds~ O ~ t } z 6 EW 4x3 EDUCER woods ,r~ ~ N ~1 `W c ~ 11/2" PVC '>j W 3 G VALVE BOX ~ O,~ \ SER CE LINE ¦ r\ ~ ~ ~ ~ / y N c~'- ~ - . Woods 135 ~'e ar ~ ~ ' Trlr _ i ~ ^ ,,rr~~ \ ~ G USE CONDITION 2 / ~ ~ ~ Woods ~ `c~ $E \ ~ ( (SEE INSTALLATION DETAIL) - ' ~ NEW .PVC RCE N ~ o ~ ~ (5 OFF YP.) ~ ~ Q ~ ~ 0 ~ ~ _ NEW SERVICE LINE ~ ~ / ~ ~ i'~ ~ - ~ , ~ ASSEMBLY m Q' ~ , ~ - ~ _ ~ ~ ~ ~ _ _ ,t~~ ,r~ } , (SEE DETAIL, TYP.) % ~ -C _ _ _ i 0 `cam ~ _ / I W 3 '~~r - _ _ ~ 1 I ~WOOdS ~ ~ ~ /rlQ~~~'- o ~ ~ - FM ~C i ~ 01 - _ _ _ ~ ~ i ~ ~ o ~ - - ~ r ~ ~ ~ ~ - w ~ _ _ /Woods c~ N w ~ ~w I ~ ~ w 'i ~ - ~ W Colonial Beach ,r~ lSR 120 v ~ ~ `ci..~ - Z lAs hol -c N ii _ _ P t Povement) mentJ ~ ~ ~ ~ ~ ~ NEW 3 PVC FORCE MAIN - _ w W , / (SEE SHEET 19) - _ ~ _ Ex. 6" wo w ter Line C ~ ~ _ e~9f j \ - - - o~ _ _ ~ . ~f ~ _ - - O ~ \ woos ~ ~ ~ WOOdS ~ ~ ~ ° ~ ~ \ ~ 1 #~g DESIGNED BY. WBJ DRAWN BY; L N TK 1 EJB 3 Ql CHECKED BY; m 10 1 o WBJ PROJECT NO.; 2876•B N DATE; ~ _ ~ . Grad AUG 2007 5 SCALE; N 5 - ~ ~ L ~ ~ Ex. Grade ~ ~ ~ _ - u ~ r - ~ VERT 1" = 50' - c IN. W 3 N o ~ U N. ~ ~ t Ex. 15° MP O SHEET 24 OF 95 t M / M1 v r'---NE RETE Q V NEW II II ENC SEME T 24 N 1 NEW II (SE DET L) -5 ~N~ 0+00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 9+00 +00 10+00 11+00 12+00 13+00 14+00 \ CJ ~ , I 1 ~ \ \ \ Bldg ~ I 1 \ \ ~ I I \ ~ p \X \ \ l \ E. I ~i \ `\s Conc Dr 1-' \ ~ Z I QQ `V' - / I ~ ~ ~ \ \ ~ W H ~ / / ~ ~ \ Bld I, - ! ~ ~ , I g ~ I ~ I~ ~ V) N V 7 ~ \ \ WWI O ~ . ~ ! Trlr ~ ~ , !dg 1 ~ I ~ ' I I Hse ~ ~ \ - ----I 1 \ C ~ drove I _ \ I\ \ ~ ~ I 1~ I I Conc ~ A A ~ ~ ~ z W I ~ 0 ~ - ~ 1 \ , 1 ~ \ \ , 1 ~ I _ Pavemenf 1 ~ \ 1 ~ - 1 ~ I , ~ ~ ~I _ Q Q . I I j ~ tr l X ~ ~ ~ I ~ - --i \ \ 1 ~ \ ~ ~ I ~ 1 / ~ 1 I \ ~,x \ Cn ~ O, ~ ~ V A ~ Z Hse I j . x. ~ I a~ I Bldg I ~ 1 - I ' x 1 I \ Hse I 1 el''~ I 1• 1 p I ~ 1 ~ ~ ~ \ f~~ ~ 1 ~x ~ \ o, \ns ~ ~ / \ \ W - LL OQ ICI ICI \ ~I ` ~ I I I ° ~ ~ - 1 ~ R/W ~ \ ~ _ N Ipl 101 f I~ a J ~ I _ ~ ~ _ --c' I i I ~ 0 L - - ~ - - - 1- - o --rt- ~ ~ _ - - i _ - - I -b f - - - fA ---"-~I'--- b ~ IC ~ 1m1 F- - - 161 I ° I ~a°' - o i~ ~ ` o ~ Ex• Sign ~ ~ / \ ~ ~ O W Ex. Headwall ICI ill ~ /P vement /~Q/' ~1 ~ / ~ ~ 1~'---`~~ o I\ ,1 ~ N ~ I I I ~ I Conc o `S~ I 1 ~ ~ ( }-t- ~ I I 1 FM ~ W s7 pl J o ~ _ ~ I ~!-T{ ~ Ex. 3 Force Main Fu n ,~Fy Fu Fl I r ~ / Fy ~'r ~ •u w 2 Fu r~a• - ~ e~ c N .OfM / ! w w w Ex 6" Water Line w ~ --------L----'---- / ~ W W F N D ~ - ~ W 94 (Aspholt Povementl w W NC H Y U) N W ~ O w Z O ~ 0 ~ ~ ~ O ~ FM ~ U N -F ~ ~ C ~ _ c Q z w~ 00 ~j C CV C Q ~o R/W ~ ~ = n rn a ~ U c+i NEW 6" PLUG VALVE W a z ~ Z ~ O -L~ ~ ~ NEW 6" PVC FORCE MAIN & BOX ~ U W (12' OFF EOP, TYP.) Z 2 ~ r W .Z J U z ~X _ - ane WY 64 Westbound L Q C M J Q O v US H rr- O a c o0 o _ c4 N a~ ~~O zm~ w Wo =wz z~ N C7 .--i - - - Ex. Grade ~ 5 z W 5 3' 0" C VER Q Z O J U 0 n 2 F- Z, ~ N -5 ~ } O r ~ _ ~ ~Z O v~ U ~ ~ Z _~o ~ , ~ NW ~ -10 57+p0 38+00 39+00 40+00 41+00 42+00 O W } z ~ + 34+00 35+00 36+00 37+00 + 29+00 30+00 31+00 32 00 33 00 ~ Q J ~ O 28 00 \ \ ~ W W \ \ ~ \ \ iX Ol ~ ~ o~ ' ~ ZQ fn ~ N ~ \ Trlr ~ \ \ \ ~ ~ _ Q fl I ~ Q ~ CO F- I \ ' _ I ~ 'l Nse ~ ~ ~ Cl~ ~ , ~ ~ ~ ~I i \ ~ ~ I ~ \ W I \ \ Z z ~ I \ \ ~ ~ x ~ I ~ ~ ~ l I ~ \ ~ \ I Hse \ ~ I O I \ \ \ \ 1 O U ~ Trlr ~ Trlr ~ , I f ~ ~ \ I ~ I \ \s ~•~t' ~ li I \I 1 1 I ~ ~X 1\~\\ i I- w E ~ t - 1 lrlr 1 ~ ~--Woods--.~ '1°. \ 0 W 0~}C r-_ _ ~ ~3 \ ` ~ \ ~ = I- it i} tit ~ ~ i ~ ~ ~i ~ ~ W 0~ I ~ ~ Trlr 1 / ~ I 1 ~ ~ 1 Ex. Satellife _ ~ o ~ _ ~ ° 1 ~ _ _ _ I - - - - Drsh - I - - I - - - - - , m I- 't - mom-" - - •r~ ~ ° / of LO _ of \L , ~ ~ i~0A ~~I ~I Ill Cn I v., / 0, V ~ 1 ~ Q ~ I r~ O r 1 ,1 ~ r ~ ( ~ FM I y~ FM N FM O W /1 ~ ~ ~ ~ ~ _ ~ ~ Ex. 3" Force Mo ~ I I Fu Fu 1 o w vu ~ N /Fwl ~u ~ du ~ w w \ w - i ~ I ~ w I w ,L w - - ~ Ex. 6" Water L/ne L - ~ - m W ~ - -L- ~ 0I ~ Q - / / NC Hw 9 lAspholt PavemenfJ ' W + ,D W ~ Y O f/1 a w Ex. Conc. ~o ~ ~ Neodwoll / O O a FM Z ~ ' ~ ~ Z O - / / / ~ ~ F11 ~ J CV I / ~ ~ -.~x• F Inve3.74 o \ e~0 ~ ~ E ~r~ce-x x~ X- C C C ~ \ ~ / C _ _ _ 10 MIN. ~ C 2 R/W U ~ Q ~ N Q - NEW 6 PVC FORCE MAIN dAIN ~ NEW AIR RELEASE MANHOLE CT 3 w l Pc I „ S~R~~ MP (12 OFF EOP, TYP.) ~ Z W/ 1 VALVE c J 0~ _ ~ U - W 64 Westbound Lane US H Y a I- Q ~ ~ DESIGNED BY. WBJ DRAWN BY. TK ! EJB 3 CHECKED BY: N O 10 WBJ ~ W + PROJECT NO.: m 10 W 2876-B `D d r\ DATE: ~ ~ a~ N x. ra e AUG 20D7 ~ - - co - - - - - - - - - - - - - - - - - - - - 5 SCALE: I~ ` - - - HORZ 1" = 50' N - ~ i_ u N 5 VERT 1" = 50' ~ N c ~ ~ ~ 0 O U SHEET 29 OF 95 ~ ~ co 29 O ~ -5 ~o 48+00 49+00 50+00 ,o 42 51 00 +00 43+00 44+00 45+00 46+00 47+00 51+00 52+00 53+00 54+00 55+00 56+00 Z z 1 C} W o 1 1 \ i~ \ ~ X I ~ Q. I ~ ~ W o , W a o~c Z ~ I \5 ,v ~ x ~ ~ ~ ~ \ i.. N I J x 1 F" r W ! \ ~ Ex, Bi!lboords , \ W ~ O U W 1 ' S o 1 R/W \ = ZZ~ 1 \ - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ~ 1 \ ~ ~ W I o W 0 0 . (n ~ 3 o Ex. 6" Water Line °o 0 2 o w w w ~ ~ w w w wn w w w w r- - ~ O ~ O rn w W + ~ N ~ NC Hw 94 W Y (Aspholt Pavement) (n i ~ o z ~ ' I- ~w ~ ~ ~ ~u ~u ~w- -FM Fti F11 F11\ r/ Fy ~ N g ~ i s 1 ~ I ~ ~ ~ 11 i ~ W , R/W ~ Z r ° I I J 11 ~ I = NEW 6 PLUG VALVE ~~1 cA z~N & BOX 1 I NEW 6 PVC FORCE U ' I (12' OFF EOP TYP.) "PVC FORCE MAIN ~ li W Q I"" 11 I Q , \ EOP TYP.? ' 0 1 Z ~ _ ~ 2 ~ U N~ [C V M U ~ z~ H S HWY 64 -Westbound Lane U Q U " sr-';~~~'~n~^t Z a C M ~ J ~ ~ 0 n. ¢ o c o0 O fd N Ur T W O z m L ~ ~ a'' W ~ W 2 W z 2 ~ N ~ ,--i 10 W 10 Z s a - - - - x, r e ~ - - - - - - - - - - . _ ~ - - ~ v -Ex. Grode Z 3. 0.. - 5 C VER U W 6" 2 F- N Z otS ~ NEW 6" PL G V VE 0 N r & BO U ~ O T Z V ~ _5 z z~ ~ ~ -5 ' z cn 56+00 57+00 58+00 59+00 60+00 61+00 62+00 63+00 64+00 65+00 5+00 66+00 67+00 68+00 69+00 70+00 ~ ~ w Q ~ J w} ~H ~ ~ ~ U o I ~ ~ ~ ~ ,I ~ ~ v , ~ I NEW 11/2 PVC ~ I ~ DER ICE LIE , , cn lL I' II I 1 I ,1 1 \ I ~ NEW 11/2" PVC `I ~ • , , I , SERVICE LINE ~ \ 1 ~ ~ ~ ~ I I I ~ I 7056 ~ ~ w W 1 I II. I ~ ~ ~ Z ~ I_, I l j 11 I 1 Hse CONTRACT 2 CONTRACTOR SHALL ~ 0 , I ~ , ~ u ~ woods LOCATE EX. 6 FORCE MAIN, EX. 6 ~ , ^`I ~ I j I ~ PLUG VALVE, EX. TEMPORARY ~ 7o5s ; I ~ `ti ; _ _ _ - ~ ' ~ 0 Hse ` I I ~ ~ I 1 I 1 \ J ~ J ~ ~ W PLUG & BLOCKING AND 0 • G \ I ~ , \ 1 ~ , I ~ ~ ,1 \ ~ CONNECT NEW 6" PVC FORCE MAIN. ~ ' ' 'I I \ NEW SERVICE LINE 1~ ~ , , ~ 1 I I ~ I I 4r , I I VALVE ASSEMBLY I ~ \ ~ ~ I~ I I', I (SEE DETAIL, TYPJ ' ' 1,x,11 ,0 t , ~j ~ to I 1 \ ~ I t ~ 1, la I ° 1 ~1 1 1 a ' ~ ~ < I \ o I < \ 1 01 T ~ 11 ~ ~ W ~ 1~ I ~ < I 1 1 ~ t I~ I ~ I I ~ W o ''1 1 ' ~ Igo I ~ ~ a 1 Ex. Billboards ~ 0 11 Iol ,1 ~ 1~ ~ I ~ z 1 ~ ---e- R/W - ' W ~ -~-I~--- -o- -~-T -r~- ry~ ~ \ 1 ~ I I Is I x ~ I I I I ~ 1 11 W i = N ~ 1 1 jJ I 1 ~ I ~ j.7 1 I I I ~ ~ (A ~ I ~ ~i-~ o Ex. 6" Water Line v ~ ~ 3 3 _ ~ w w w m w w w~ w w ~ w \ ~ ~ W -I- - ~ - ~-J ~ 1- W W W N ~ ~ Ex. 8' W x 4' T _ w a, ~ (Aspholt Pavement) ~ ~ Concrete Box Culvert t` ~ NC Hw 94 ~ ~ NW y o ~ O w/ headwo!leach side O O O O z o + 10' MIN. ~ ~ ~ Fu ~ ~ Z FM FM ~ ' ~ d' ~ O ~ !n v ~ ~ f.7 ~ . ~ ~7 \ ~ ~ Q C Box-2.93 C C C ~ N N .Inv 0 N N ~ i h-4 4 R/W ~ ~ ~ t~ .o EQUIPMENT RACK FOR ~ W NEW 6" PLUG ~ ~ METER ~ Q ~ NEW FLOW METER NEW 6 PVC FORCE MAIN NEW 6" PLUG VALVE Z & BOX c _Z VALVE & BOX Q ~ (CONTRACT 2) (12' OFF EOP TYP.1 °i (CONTRACT 1) ~ z MANHOLE No. 2 (SEE DETAIL) J 2 ~ 2 ~ o (CONTRACT 2) U o U F- ~ Z - - ~ US HWY 64 Westbound Lane Q W ` ~ W V~FI '1 ' , \~r , y M `iI.^i DESIGNED BY. I WBJ V)~ DRAWN BY. n' W ' TK 1 EJB n~` . 1 rWn W Vl CHECKED BY; m 10 1O WBJ ~ N PROJECT NO.: 2a7s~B N ~ w 1- DATE: f~ x, rode _ _ Ex. Gro e AUG 2007 ~ , N 5 - - - - - - - 5 SCALE: ~ HORZ 1" = 50' VERT 1" = 50' CEM N o - o~ 0 SHEET 30 of 95 NEW 6" PL G V VE & BO p~ NEW n Pi I 1c; O (CONTRACT 1) ~o -5 30 o 70+00 71+00 72+00 73+00 74+00 75+00 76+00 77+00 78+00 79+00 '9+00 80+00 81+00 82+00 83+00 84+00 i~ ~ ~ ~ I t / ~ 1 ` 1 / \ ` \ 1 1 \ ti ~ 1 ti S \ 6866 ~ ~ ~ ~ Hse ~ \ \ ~ NEW 11/2 PVC \ ~ ~ \ ' ~ SERVICE LINE Z Z \ ~ , W o ~ .a , , ~ a' \ , 1 x I (1 i S 1 fi 1 ~ I ~ ~ 1 W a ~ Z ~I w o 1 i i i ~ ~ 1 OwN \ ~ ' \ 1 I/ \ \ ` \ ~ o ~ ~ I \ \ ~ \ 0 \ ~ ~ ~ ~ \ ~ ~ U Qz~ ~ ~ ~ ~ NEW SERVICE ~iIN~ ~ ` ~ woods \ ~ , \ ~1 ~ VALVE ASSEMBLI~ \ \ \ ' ~ 'i 1~x Z ° O (SEE DETAIL, TYP;~ ` \ , 0 m \ M \ \ ,~1 ~ k I,x ~~o w ~ ~ ,y X ,~13 W a W \a ~ ~~o~ ~ ~ 1~ i° ~ N W ~l ~ - - - --=t3 ~ C~ 1 I O ~ I W N \ ~ I I ~ ~ N ~ ~ + o ~ ~ Ex, 6" Water Line 3 0 ~ i~ W w~ w w ° w ~ 1w w ' i w W _w w ° w w w W ~ ~ L ~-1-_ ~ -1- i ~ CA O ~ m ~ W IVC Hw 94 fAspholt Povement) o ~ NW Y + ° O ~ ~ O ~ ~ Z + ~ N ~ z°~ ~u ~w ~ ~ ~ ~u ~u I ~ ~--I Q , , ~r ~ i ~ ~ ~ ~ Q ~ m _ o ~ ~ ~ 0 i ~i f~ !1 = ; ° C ~ G N ~ c[ U ch O ¢ Z ~i' W Z ~ NEV cv m NEW 6" PVC FORCE MAIN Z U (12' 2 (12' OFF EOP TYP,) J ,tom Z aK ~ x U ' _ ~ fi W z ~ U ~ _ H Q O J ? ~ ~ _ Q a C c o0 G O - cp N ~r T ~ S HWY 64 Westbo nd Lane U O Z m ~ L ~ ' I D: W ~ L1J 2 W z Z ~ N C7 ti 10 W 10 Z a z 5 - - - Ex. Gro e- - - - - - - - - _ !ti ~ ~ - .Grad ~ 5 J - - - - - - - a _ U IN. I=- d' MAIN O ~ Z N 0 0 ~ U = O r~ UN cn Z Z U ~ ~ T ~ ~ _5 ~W o -5 84+00 85+00 86+00 87+00 88+00 89+00 90+00 91+00 92+00 93+00 3+00 94+00 95+00 96+00 97+00 98+00 ~U w } Z O i i ~ wo i ,l NEW 11/2" PVC ' N W 11/2" PVC ~ o w V+ i 'I SERVICE LINE .S VICE LINE Q ~ ~ ~ r~ w ~ ~ ~ , ir' ~ Q ~ _ ~ r- ~ ~ w ~ ~ ' 'I I ~ i ~ _ ~ ° ~ z ~ W ~ ~ I 6344 l~l ~ Z ~ Hse j 1 ~ ~ I j Hse ~ ~ ~ 6370 ~ I ~ 1~ Nse j _ ' NEW SERVICE LINE ~ ~ ' i i _ I ~ ~ ~ ~ VALVE ASSEMBLY ~ i I ~ \ (SEE DETAIL TYP,) ~ i I, I ~ ~ I I \ li li I ~ I ~ ~ M ~ W I I ' ~ II ~ W ~ - ~ Iii ~ ~ ~ I I ~ I v ~ i - ~ --I I ~ - -~~-~f- --T--~~ a -14t- - -Ir- ~ W \ ~ I ~ \ ~ } Im I ICI ~ 1Oi ~ W o 2 ~ ~ ~ ~ ~ \ l l ~ O I lal GI ICI o ~ o ~ ti 3 I Ex. 6" Wofer Line o ~ \ I ~ w p w ~ - w w _w w wow w ~ W m W - - - - -s . m W ~ ~ W ~ (n ~ w (Asphalt Povement) NL' Hw 94 Nw A y ~ ~ o ~ O ~ O O Z O o + ~w ~u ~u ~ ~ ~ C ~ r ~ °0 ~ o ~ ~ C C 1 i T a Q ~ a, (A EX. 24 RCP A ~ W NEW 6" PLUG VALVE USE CONDITION 2 W (SEE INSTALLATION DETAIL) NE Z & BOX c (12' 0 NEW 6" PVC FORCE MAIN W (12' OFF EOP TYP.) z ' ~l J 1 ` ~r 1 r J ~ 2 U 2 U ~ ~ - US HWY 64 Westbound Lane ~ g Q DESIGNED BY. WBJ DAAWN BY. TK 1 EJB CHECKED BY. m 10 10 WBJ h PROJECT NO.: 2876•B N DATE: AUG 2007 ~ 1 nl Ex. Grode r f-. 1 Ex_Gr de 5 SCALE: ~ i - - J ~ - - - - ~ ~ ~ _ ?Y - - - - - - - - - - HORZ1"=50' (p j MIN. VERT 1" = 50' " 0 O U " ~ , Ex. 24' RCP ~ ~ ~ MI . SHEET 31 OF 9~ ~ I I ro NEW 6 PLUG V VE co &BX N \\o -5 31 -5 (SE DET L) 98+00 99+00 100+00 101±00 102+00 103+00 104+00 105+00 106+00 107+00 7+00 108+00 109+00 110+00 111+00 112+00 U ~ o i r" ` °o NEW 11/2" PVC SERVICE LINE ~ I: J I I . of a I ~ I .o ~ ~ ~ I ~ ~ i ~ ~ ~ ~ SERVICE/LINEVC 'Z'RR 0 1 ° I. vp- ~ 6100 Trlr ~ ~Q~ x, ~ W ~ a ~ Hse IQ NEW SERVICE LINE i ~ ~,ti~"~ ~ a ~ z I I~ ~ h VALVE ASSEMBLY ~ ~I W JH I l~ a I , o ,~~r fSEE DETAIL, TYP.? o ! ~ . ~ 0 ~ Z ~ I o, I F, I ~a ~ ~ QOV ~ i c~ ~ o . ~I o. In ' ~ m ~ Woods-.t w ~ Z Woods ' . o o' _ _ _ O o. o - ~ - - - - - - - - - - - - - - - - - - - - - - - - - - - - - I~ W Io Q o ~Q~ W ~ I~ , ~ @ N Ex. Headwall I ~ ~ ~ ~ cn o = o Ex. 6" Water Line o 3 w N w w ~ w w w w W? w w w ~ w w ~ W ~ ~ ~ b UJ rn A~ io 41 (Asphalt Pavement) IvC Hw 94 NW ~ y ~ ~ c~~o CA . o O ~ O Z ~ O FM - ' FII FM FW FM FBI FII FM ' FW- ~ 0 10 MIN. Ex. NeodwaA ~ ~ ~ N ~ ~0 Ex. Fence W - x x N T T ~ H M LQ r vALVE ~ z ~ M N NEW fi" PLUG VALVE & BOX Q ' ~ -o W NEW 6 PVC FORCE MAIN z (12' OFF EOP, TYP.) PP M ,y1 w ' S~IV { { Z ~ U N W _ OC M J 2 J ~s O a z M v -Westbound Lane U U ~ z ~ US HW Y 64 ~'~~f~~ Z - ~ X Q ~:i~~~ W ~ ~ z Q ~ M O J > lf7 ~ Q O C 00 O cv N ~ T ~ O Z CD ~ r Q7 ~ ` W 'L z 2 W Z ~ N r ,-a / ~ 5 _ Ex. G ade _ _ ~ . _ - x, roe 5 z MI . NEW 6" ~ 6" Z 0 0 J a U NE fi" LUG ALVE ALVE _ & OX Z N ~ -5 N~ o ~ o T~ _ ~ U ~ Z r -10 ,d -10 ~ O oW 112+00 113+00 114+00 ~ 115+00 116+00 117+00 118+00 119+00 120+00 121+00 21+00 122+00 123+00 124+00 125+00 126+00 J w ~ Q ~ ~ ~ ~ ~ o~ Uo `'3, ~ ~ w ~ N ~~o. ~ w LL r w ~ Q ~ CO ~ tr" 0! ~ a ~ ~ E~' ~ ~ Z ~ z i Woods-.1 o ~ J J ~ ~ -Woods c" f \o. _ ~ ~ \°s ' 2 ~ W ~ w ~ w a N o~ .y ai W ~ , ~ ~,o, fro p ~ ~ ~ Woods ~ w o W o ~ N w + ~ o ~ = 3 Ex. 6" Woter Line o N w w w ~ w Abandoned 6" Water wine w ~ 0 ~ ~ O I W ~ m W o W ~ NEW AIR RELEASE M. RELEASE MANHOLE ~ c~ N w NC Hw 94 )Asphalt Pavement! ~ W/1" VALVE y a~ ~ o ~ _VE ~(1 i ~ O z N ~ O ~ Fll FY FM Fu FM y o N ~ ~ r C c ~ Q SITION FROM TRAN N FROM W a~ - ~ 12' TO 5' OFF EOP, TYI a~ ~ EX. 30" RCP )FF EOP, TYP. ~ W NEW fi" PVC FORCE MAIN USE CONDITION 2 _Z (12' OFF EOP, TYP.) CB (SEE INSTALLATION DETAIL) ,0~ J ~ _ U ~ US HWY 64 -Westbound Lane Q ~ g DESIGNED BY. WBJ DRAWN BY: TK 1 EJB _ _ . ~ CHECKED BY; - - 5 WBJ m E . Grode 5 - - - - PROJECT NO.. - _ c~ MIN. 2876-B ~ x.30" CP DATE: ~ AUG 2007 N 0 . W +I Q scaLE: ~ ~ ~ HORZ 1 ° = 50' N ~ ~ VERT 1 ° = 50' N 3 .o o~ -5 (EE D TAIL) - 5 SHEET 32 OF 95 CIO O ~ ~ o 3 2 -10 -10 N 126+00 127+00 128+00 129+00 130+00 131+00 132+00 133+00 134+00 135+00 35+00 136+00 137+00 NEW 11/2" PVC '2" PVC SERVICE LINE ~--woods LINE ~ NEW 11/2" PVC NEW 11/2" PVC ~ SERVICE LIN E Z Z NEW 11/2" PVC SERVICE LINE SERVICE LINE NEW SERVICE LINE ~ Ex. 24" RCP ~--scrub ¦ ~ ~ ~ W O V E .ASSEMBLY ,,a. USE CONDITION 2 1`, (EE L; TYP (SEE INSTALLATIO DET L) Woods Ex, So !life ~s ~ Q ~ 94 Drsh WQ~ z I~ '`i Nse i~•' ~-woods-~.1 Q J N ~ 'hi'p 4 ~ Q-Ex, Sate!}ite d5 ~ W ~ 5298 Dish \ boo , 5360 Trlr JFO W J ~ Trlr ~ o / ~ M Nse ~ + ~ M °o ' ` ~ NEW 6" PL G VALVE- o NEW 6" : VC FORCE MAIN Q Z ~ G VALVE ° (5' OFF P, TYP.) Z 0 ~ L o L ij' ~ & BOX R/W ~ W _ ° ~ - ° - - - W - - ~ - - - ~ ~ T o = o o ~ 0 ~ c~ ~--c ~ 0 W Fw Fw ~ ~ ~ p FM FM FM 3 FlI W ~ ~ N ~ w O NC Hw 94 lAspholt Pavement) ' ~ Y N W O O o w w d' w w Ex. 8" Water Line w -w w w U w ~ ~ L1J D ~ (j('~ T ~ ~ Y`-~ ~ 0 ~f r W ~ Ex, Fence Q = ~ - R/W z Q Ex. Fence _ W ~ wz Q ~ o W z~ ~ _ U N ~ _Z tC M 2 W ~ a J U I- ~ ' U ~ ~ Q Z ~ - one WY 64 Westbound L US H C Z pV,Y~75~ z ~ ~ X F.yy~ Z a M a ¢ ~ V J ' ~ c co O N N ~ ~ ~ O Z CD ~ .C ~ ~ ` W W O 2 W ~ 2 O N ~ ti I 10 10 Z W Q Z Ex. Gr e r f 5 _ _ ~ _ _ _ Ex. rode 5 3' 0" - - - Q U C VER x, 24° cP NEW 6" PV FOREMAN S H ~ d' Z N O) MIN. 0 N~ ~o ~ o T & BC &BO U~ zr (SEE ETAIL _5 z ~ ~ -5 0 ow Z~ + + + + + 70+00 171+00 172+00 173+00 174+00 165 00 16fi 00 167 00 168 00 169 DO 1 4+00 175+00 176+00 177+00 178+00 179+00 U ~ ~ Q O w ~ ~ H J W ~ UJ O GL ~ W ~ ~ II 1- Z ~ ~ O r Q ~ ~ ~ s TEAM 1 Ex: 36 RCP 1~1~C~ 2~ 32 USE CONDITION 2 ~ o. w (SEE INSTALLATION DETAIL) Z z /yJry Q\ W o ~ V+1 D J W °o °o ! NEW 6" PVC FORCE MAIN W (5' OFF EOP, TYP.) p J M i! ~ ~ o ~ _ ~ _ ~ ~ _ 3 - LL! ~ W Q ~ ~ ~ W o W ~ ~ N FN (n a w NC Hw 94 lAspholt Pavement! Y H ~ O W ro ' o W w w W W w U W ~ ~ Ex, 8" Wafer Lrne I .I" Vafer Lrne ~ i m o ~a ~ ~ ~ Ex, Fence ~ ~ ~ ~ w r w O ~ Q Q~ ~ ~ R/W M rn ~ ~ ~Q T ~ G o W rl O ~ Z ~ J ~ _ a U _ Z US HWY 64 Westbound Lane ~l ~ Q J ~l ~ ll II 0 DESIGNED BY: WBJ DRAWN BY. TK l EJB a~ CHECKED BY: 1 O WBJ m 10 PROJECT NO.. 2a1s~6 N DATE; AUG 2007 _ _ _ _ _ r 1 _ Ex. rode ~ N 5 Ex. Grade - - 5 SCALE. HORZ 1 ° = 50' ~ ~ M N, VERT 1 ° = 50' N o MAI ~ V Ex, 36" RC ~ ~ SHEET 34 of 95 0 IN Q) NEW 5 F CONCRETE ENCASEMENT 34 -5 179+00 180+00 181+00 182+00 183+00 184+00 185+00 186+00 187+00 188+00 ~ ~ 8+00 189+00 190+00 191+00 192+00 193+00 i Z z ~w~ NEW 6" PLUG VALVE N ~ NEW AIR RELEASE MANHOLE & BOX o D r o W a ~ Z ~ ~ W/ 1 VALVE r o NEW 6" NEW 6" PVC FORCE MAIN woods-,1 0 ~ N p Riw - - - - - - (5 OFF = o E~:- (5' OFF EOP, TYP.) r ~ ~ Z ~ Gr - _ - x, r ~ ~G-- J a W _-__--~~o, o w ao~ ~ - - Z = Zzo ¢ C~ ~ LL m N Nli HW 94 (Asphalf Povementl v ~ y m - N ~ ~ (D w _ W w w w w O Ex, g" Water Line w ~ O ce x X ~ - ~ Ex. Fen ~ - Ex, Fence ~ p D ~ O N m m ) ~ a - m o ~ ~O w C~ ~ ~ a ~ P ~ IQ ~ ~ N ~ ~ ~ ~ w~ m Q ~ - o m US HWY 64 -Westbound Lane W Z = cc U m i J ~ U N ~ w .P = oaz~ U ~ U ~ Q z ~ Z ~ x .r Z ~ Q ~N ~ 0 a ¢ o c o0 O (Q N ~ T ~ O Z CD ~ L ~ ~ ~ w W O ~ O 'L z N ~ ~ 10 1~ Z w Ex. Gra e - - - - _ Q - - Z ~ 5 MIN, 0 5 NEW " PV FOR E M N Q U T Z N ~ Z ° NEW G V VE w + & BO ~ N~ O w~ d a~ ~z v~ Z~ _5 ~ ~ ~ ' ~ -5 z 193+00 194+00 195+00 196+00 197+00 198+00 199+00 200+00 201+00 202+00 12+00 203+00 204+00 205+00 206+00 207+00 ~ ~ } Q J ~cn ~w w w w Z ~-Woods-~ A rt Line ~ 0 ~ J - ~ Pprox. ProPerfY Line APPr ~P PAY ~ ~ ~ Q ~ Q I J w w o ~ l~~ - NEW 11/2" PVC ~ Q ~ ~ ~ NEW PUMP STATION No.1 ~ w rn ~ ~ ~ SERVICE LINE ~--Woods-.) a I (SEE SHEET 90) a W T l ST2EAt~l IMP~~T 21- l ~ x~ ~ Z ~ ~.S Ex, 24" RCP ~ crab ~ USE CONDITION 2 J W SERVIGE NE ~ ~ ~ °I U (SEE INSTALLATION DETAIL) Ex. Cemetery l~ j J a3s8 VALVE ASSE ~Y f xse (SEE DET ~ TYP.) ~ x w Ex. 24 RCP F"' N W USE CONDITION 2 ra ~ o ; , ~--woods ~ W (SEE INSTALLATION DETAIL) o 1 } ~ , 1 ~0 ~ ~ _ ~ ~ o NEW 6 PVG FORCE MAIN ,W °o ' NEW 6" PVC FORCE MAIN ~ (A , (5' OFF EOP, TYP.) r ~ i' ~ , I 2- NEW 6"-45° BENDS (SEE SHEET 36) ~ , o ~ ~ R/W ~ ~ - L-- _ 1 _ ~Ex. Satellite I° I _ _ _ _ _ _ _ _ _ _ _ o = i o rum- Dish - ~m I . ~f I~~j , F- ~ ~ ~ ~ 3 1'~ ~ 1 ~ W r ~ ~ ~ FN- ~ FlI F11 I ~ , ~ ~ m ~ 10 MIN. rn ~ w ~ ~ w NC Hw 94 (Asphalt Pavement) N Y a ~ ~ O O a~ O - - - ~ w w w w w w- w w w ~ ~ ~ Z i ~ Ex. 8" Wofer Line O ; ~ i ~ }-k N I• I ~ i o n ~ 0 ,I ~ ~ Ex. Fe e ~ - - - - ~ Q R/W o 0 ~ ~ I a~ N a~ ~ W I Z C J 0~ _ v WY 64 -Westbound Lane US H o I-- a ~ ~ F- DESIGNED BY. J WBJ DRAWN BY: o TK 1 EJB + CHECKED BY. N Q WBJ m 10 PROJECT NO.: 2s7s~B N ` _ - - DATE; tp ~ - - - - ~ MI . _ _ _ _ _ _ _ _ AUG 2007 N 5 W FO CE M N Ex. 2° RcP ~ ~ NE 6 P C 5 SCALE: HORZ 1" = 50' I VERT 1" = 50' ~ j x.24" C N o O V ~ MIN. SHEET 35 OF 95 0 L virtu ~ i G rnnir ~'T~ ENC SEME T 4 v (SEE DET L) ENCASE !ENT (SEE DETAII ~o -5 35 -5 ~NCL o 207+00 208+00 209+00 210+00 211+00 212+00 213+00 214+00 215+00 216+00 16+00 217+00 218+00 219+00 220+00 221+00 L / I/ / / ~ / / t ,i' ' / ' / Ex. Satellite ~ ish / ~ / ~R, (Aban oned/Demolshed / / / NseJ ~ ~ / / Z Z ~ ~ / / ~ / i C~ W • I ~ I ~ / 3j' / ~ ~ ~\o Way Z w o ~ ` DWG / Q~~' J~o ,'d / aJ. ~ - / HV QZ~ h / Y/ Z Q / LL / / 1 ~ / W TERMINAL CLEANOUT ASSEMBLY I i + (END STA. 4+60± - NC HWY 94) / ~ / ~ s~° r / W / ~ ~ cmV z ~ ~ W~ Q~' ff'~~ M LPL - o S I~ ~ U N ~ ~ U M O Q z ~ - .c pMp U ' z .~~.;,:,;~;m Z Z / EX. STORM DRAIN ~ USE CONDITION 2 i (SEE INSTALLATION DETAIL) ~ Q ~ d o / ~ O J ' - tp N / O ~ ~ Ur ~ O / ~ NE'GJ 2" PVC FORCE MAIN Z 07 ~ - .C ~ / ,~5' OFF EOP, TYP.) r ~ ' I I 2 W ~ W ~ w Z I r•-~ / i z O _ - f i , \ / W ~ i Z W / ~ % ~--wetlands NE . ?/"-11,25° BEND ~'1 ~l / i Wi'21f_ ° / 22,5 BEND Q 30 LF OF 2" VC SERVICE L E ~ i Woods ~ .~P z J W/OUT ENCASEMENT BY ~ EMPORARY BORE PIT / DRY BORE & JACK i i4PPROX. SIZE & LOCATION) ~ , / r; Q U ~ 'i NEW 4 PLUG;'~RCV~~ ~ ~ ° ~ ~ ~ W 4"x4"~~'' TEE ~ ~ ° ~ ~ NEW 4" PVC FORCE MAIN . 'i NEW •~"~LUG VAL & OX ° ~ , z N J ' (BEGIN STA. 0+00 - NC/HWY 4 fk, s-- ` ~ ~ (5 OFF EOP, TYP.) H N V l ) ~°t / e ~Q er ~-Woods/Wetlands--.~ e m ~ ~ ~ O II I ~c ~ w ~ i o,~2 ~ ~ k ~ ~ 1~ Z / 6 U ~ } ~ / - f j" ~ w ~-Woods--.~ ~ ~ ~ Q e U 3 ~ t`/ W ~ ~ ' ~°r r' itch ~ ~ RQ Ex. ~ a O UO c~ ~ w cn Z ~ / R ~ ~ 1 0 ~ , < p w w~ ~ \ 11 ~ 2~ o 3320 „ ° ~ o to ~ . Hse ~ 2 -NEW 4 -22.5 ~ N ~ ,r 1i W I- Z w Q C~ 1N , ~ L1J Q ~ ~ ~ ~ BEND ~ o w - - .~/W OJ S ~ ~ . - / / ~ Ex. 18" CMP l i. Ex. Headwall ~ ~ I t ~ NJ Q ~ ~ L ' ~ ~ / ~ ~ USE CONDITON 2 l ~ , ~ ras C,, ~ U Pho/ ov ~ / (SEE INSTALLAT ~ 2 ~ f P ement; ~ ION DETAIL) W I \iw f W W o,. G ~o,.~,\ ~ Ex. 18" CMP ~ 3295 EMPORARY RECEIVING PITT ~ (n ~ ~ ~ \ ~ Hse PROX. SIZE & LOCATIO ~ USE CONDITON 2 - - ` ~ ~ W /2" PVC ~ ~ i NE 11 / / ~ (SEE INSTALLATION DETAIL) ~ _ ~ ~ z d. \ ' O =O SERVICE LINE ~;l i - _ _ ~'c ~ - ~ o ~ ~ i ~-ScruE pp, \~'4 ~`--Woods ~-Scrub o ~ II ~II ~ W Z 0 ~ lo, a / 2 ~ ~ ~1 r~- ~ o , ly / C / F. ~ h ~ ~ F S ~ ~NI / IM 3 ~ ~Acc-~' 3(0 % ~--woods ~ NEW SERVICE LINE ~ ~ 1 I "block' Insuronce" W ~ NEW 11/2 PVC , VALVE ASSEMBLY SERVICE LINE ice/ I Z ~ i~ ` I ~ / (SEE DETAIL TYP.) ~ ~ I o J / eF / ~ oa / ~ ~ 2 ~ ~ N ~ Q ~ o~ ~ l~/ I I ~ m yQr ~ Ex. Headwall Woods-~.~ ~ ~ ~ ~ Q ~t ~ ` ti ~ ~ r~~ ~ ~ ~ .h ~ ~ o~ ~ I 1 ~i 1 I ti ~ i ~ ~ i ~ . ~ ~ ~ ~ ~ ~ ~ ~ S I Nse / ~ ' ~ I' .i ~ ~ ~ 9 / ~ ti l ~ ti S ~ ~ 6' ~ ~ ~ 1 S ~ '`0 0 1 ! r , 6 ~ ~ ~ ~ ~ 1 ~ ~ 1 z s F F s ti F F a ~ ~ ~ DESIGNED BY. WBJ 3 DRAWN BY. ~ T TKIEJB CHECKED BY. ~ ~ ~ ~ 5 WBJ f~ ~ ` ~ Ex. G ode PROJECT NO.. ~ - - - nl _ _ _ _ _ _ Ex, Grade _ / ~ 2876-B - DATE: AUG 2007 N O EX. 18 ' CMP Q SCALE: ~ ~ W 4' PVC FORC MAIN 2~.p~~ Ex. 18" CMP x. 78" MP HORZ1"=50' ~ ~ ~ VERT 1 ° = 50' 1 N ~ ~ i_ u Q U 0 ~ , I. ~ ~ -5 II ~ NE 4 PLUG VALV & B X NE 4" 4"x2" TEE SHEET 39 of 95 I['IIf I ~ n AIl~D T[' 6 6F CX3 S ENT NE 6 F CONCRETE'. °o SEE ETAIL) ENCASEMENT N ~ i ~o -10 _10 39 56+00 57+00 58+00 59+00 60+.00 61+00 62+00 63+00 64+00 65+00 X00 66+00 67+00 68+00 69+00 70+00 O Z . ~ ~Q~ W ~ W C/~ ~ ~-Woods ~ N O Wad z l,~ o W p ~ w ` . ~-Wood s-.) r ~ ~WN N Q 0 J~0 ~ O \ ,0' U ~ w d' ~ ~ ~ az°~ ~--woods-.r ~ ~ 0 - ~ 1~ ` i w _ 1 ~ LL ~ o ~ ° ~ o ~ ~ 0 ~ ~ ~ ~ - ° - R/W o _ Z . ~ ~ ~ 3 Ex, fi" Water Line w w W m p ~ w ~ w w cn !o`, _ V ~ ~ ~ ~ W ut/er Rood lSR 77721 (Asphalt Pavement) shalt Pavement) ~ ~ B ~ W D ~ ~ ~ ~ Q ~ ~ ~ t o0 U C i ~ r + w NEW 4" PVC FORCE MNN C Z C C , (5' OFF EOP, TYP.) R/W ~ ~ 00~ ~ m i ~ O ~ i Ex, Headwall v Ex, Headwall Ex. Heodwol! ~ ~ ~ z w w m Q ~m ~4 . m ~ Ex. 24" RCP = USE CONDITION 2 _ ~ ~ ~ (SEE INSTALLATION DETAIL) Q a z ~ M V! ~ ~ U ~ WY 6 US H S HWY 64 -Westbound Lone = t~:= z Z ~:~~~~r: J H ¢ a ~l O J Q O c eo ~ T W O cv N O Z m ~ - .c ~ ~ i w W O W ~ Z ~ N CS .--a 5 W 5 z Ex. rode ~ ~ _ ~ - - ~ J a Ex. 24' RCP Z 0 ° 3 NE 4 VC F RCE AIN o J x, o er me CO~ER ~r me Q U MIN MIN. _ I- O Q Z N -5 _5 ~ ~ o 0 NEW LF ONCR TE r ~ ~ O N z W T J U O ? r -10 _10 j ~ W m 84+00 85+00 86+00 87+00 88+00 89+00 90+00 91+00 92+00 93+00 3+00 94+00 95+00 96+00 97+00 98+00 ~ w } Z ~ ~u' ~ ~ ~ O ~ ~-woods--,) Z ~ U + Q ~ ~ ~ : 1, ~ ~ O ao 1,_, / \ Scrub I r . 1 0 ~ ~ ' ~ w d• > ~ oc o.. I o Woods I Q ~ 350 ~ ~ ~ ~ ~ ~~0 Hse / '~1 ~ Z W ~ ~ 11/2" PVC / i ~ o Z I- - - ~ _ ~ SERVICE LINE i' % ~ ~ ~ ~ ~ (.-.Scrub--.) l f' S ~ C W ~ ~ ~ Q NEW SERVICE LINE i i ~ ` 2 ~ ~ VALVE ASSEMBLY i i ~-woods m ~ W ~ 2 ~ ~ I/ ~ ~ (SEE DETAIL) ~ ~ ~ ~ 1/ ~ I I o cn O 1 ~~~tttlll"''~" o 2 'm v o > o I c l I ~ I ~ ~ lI I ~ ~ _ ° ~ N - ~ ~ ' - R/W ° - I W w w Q W )--~----+-C 3 fx. 6" Water Lr'ne Ql ~ ~ w w w w ~ w w rn W ~ Butler Rood lSR 11121 (Asphalt Povementl ~ ~w ~ O ~ Fw Fw Fw ~u Fw ~ ~ N ~ O ~ , ~ ~ ~ - m o ~ C C ~ r C ~ _ ~y N ~ f m ~ R/W L N ~ Q ° ~ m o , a~ ~ ~ (A NEW 4 PVC FORCE MAIN 5~-E~IM 1'MP~I' h- i3 m NEW 4" IN-LINE (5' OFF EOP, TYP.) ~ W Ex. 36"FRCP N Z CLEANOUT ASSEMBLY USE CONDITION 2 o, J (SEE INSTALLATION DETAIL) ~ _ ~ U o ~ US HWY 64 - Westbo ~ g - Wess{bound Lane DESIGNED BY: WBJ DRAWN BY. t TK 1 EJB CHECKED BY: m 5 5 WBJ PROJECT NO.. ~ Ex. Grade _ ~ ~ _ t - . _ ~ _ \ 2876•B N - - - - - - ~ DATE; ~ M N. Ex 36" R P AUG 2007 ~ N N 0 _ „ 0 SCALE; HORZ 1" = 50' O C VERT 1" = 50' ~ ~ . 0 OV ~ ~ - ~ ~ , t -5 a - 5 SHEET 41 of 95 NE 5 L CO RETE ffVV/ EN ASEM NT 0 ~ ME E. DE. I AjLT-- -10 O ~ ~o 41 -10 N Q- 98+00 98+00 99+00 100+00 101+00 102+00 103+00 104+00 105+00 106+00 107+00 7+00 108+00 109+00 110+00 111+00 V V ~ NEW 6"x6"x3" TEE NEW 3" PLUG VALVE & BOX V1' / (BEGIN STA. 0 00) Z z ~o ~ ~ o _W~ V ~ ~ N NEW 3"-45° BEND ' ' N I` I O 101 Q ~ o, NE TERMINAL CLEANOUT ASSEMBLY W J H O o I~ EX. 18 RCP 1 ~ I ~ ( ~ 0+46~ ~ 0 W N ~ USE CONDITION 2 1 I~1 , Z ISEE INSTALLATION DETT~J~} _ ~ m NEW 3" PVC FORCE MAIN _ _R/W--+-"I I / ,1~ ~ ~ Q Z ~ 2 _ - (5' OFF EOP, TYP.) - ya z I~11 ~ O I 1 ~ ~ _ ~ / I Gl 3 ti ti ~ 372 ~ ~ .oo, Fw ~lol 11/2"PVC ~ I+ ° I - FM m N 'I i I< 1 "PVC ti Hse ~ 11/2 , ~ ~ ~ ~ I m ~ m ~ w c~ I SERVICE LI \ _ ~ R 1117) a o - n CS . , SERVICE LINE , Fk Road W ccoon 1 ~ 8" It Pavement) Ra / . lyofe (Aspha ~ w ~ 1 ~ w ~ / w - ~ ~ ~ ~11G> 1 B ~/SIN _ ~ 1 V , Tq ~ R ~ w x, o er me w Line _ _ - _ I ~ m ~~`~Ex, Satellite OK ap ~ Ex.B Water ~ I 1 01 D~ 0/ w w 1 1 1~ 1 Y 191 Dlsh ~ ,,rr~~ 0 ~ t o 1 1 1 Hse 0 _ ~ ~ 1 1 1 xy _ ' o ' NEW SERVICE' IN - ~ ~ 0 0 0 VALVE ASSEMB Y ~1 Bldq W EE DETAIL Tl^ (s P 1 ~ ~ 1 - . , ~ Cm( 7 ~ N d N 11 W ` U ~ c/' W ~ 1 (T7 ti ` \ , 1 ~'ly NEW 6 PVC FORCE MAIN O _ ^ 07 9 1 ~ ~ (SEE SHEET 33) , , U N W rt U m qeo ~ ' ' 11/2" PVC 1/2" PVC z ~ Sao \ 1 1 p yea ~ 1 1 SERVICE LINE gbonao oter ` 1 11 SERVICE LINE ~ ~ ~ U ~Pa 'oe \ 1 Z ~ ~ x wR~~+s~.> ~ z ca 1 1 ~0te~ ~ ~ . 1 1 ~~~e t 7 \ 1 1 w ~ 1 1 ~-Woods-~ W ~ ¢ ~ ~ 1 1 U 0 a ¢o C 00 O N N ~ \ 1 1 1 1 1 W T ~ cyl O Z Cfl - L Q~ ~ c~ LJJ ~ w o W + = W o r ~ ~ N C7 .--i u u n 3Z 5 Z W NE 3" LUG ALVE & BO Z 5 _ ~ Ex. Grade _ - - - - - - - - - - - - - ~ - - - - - I ~ 011 x. aer re Q Z x, 18" CP o ~ z a Q U J o - MIN. . _ ~ 0.. 45° VE T. BEND 45° V RT. BE STA. 0+ g± STA. +50± z N O Q z z -5 °C m+I m I E CASE ENT ~~o~J - cj ~ + ~ (S E DE AIL) w +I o ~ > +I a ~z ~oa. o ~ o Ur2 a -10 ~ ~ ~ ¢ U ~ ~ ~ ~W ~ -10 + )+00 10+00 11+00 12+00 13+00 14+00 ~ w ~ Z O Z + + 6+oa ~+oo g+aa s ao + 1+00 2+00 3±00 4 00 5 00 0 00 ~ Q~J ~ wW ~o or= o w W ~ U ~ ~ ~ I I a~ ~ ~ I I ~ EW 7-fiI2" PVC I I w ~ ~-Shrubs I I ~1 ERVI~ LINE , , o o Bldg NEW 2~~ x 2" x 11/2" TEE NEW 11/2" PVC w ~ ~ ~ N 1 I I I 1 NEW 2 x 11/2 REDUCER SERVICE LINE Q I I I I I I - _ ~ ~ ~ n. I I I I Trlr o I I I I' ~ °o I I Bldg I I _ ~ ~ - , G~o~%~'~ Brdg ~ Z N I I I I ~ ~ I I I I t~ _ ~ _ ~ _ . J . I ~ ~1 , I I I 1~y I I I I to I I I 11 I~ I - I I 1 1 11 I I I,O ~ - ~ - _ r , ~ I ~ I I 1 I 11 ~ _ ~ ~ ~ I p I 1 - ~ . ~ I 1 1 I l - ~ . • ' ~ y``.°~P,~~ ti ° i NEW 11/2" P~Ci Nse ~ 1 I m I ~ , 1 ~ 1= - ~ I rte- ~ C O I ~ + _ r • ~ ~ ` I SERVICE LINE ~ I I I ~ 1 ~ - ~ ~ Woods / ~ ~ , , = - _ _ ~ , , • NEW SERVICE LI LINE ~ 1Q' PERMANENT x ~i j ' ~ Q ~ ~ ~ nds ~ ~ ~ ` o' ~ - ` VE ASSEMBLY ~ 3LY UTILITY EASEMENT ~ x ~ ~ ~ a I i ~ ~ ~ ~ I ~ _ ~ , ~ • , r X SEE DETAIL, TY p ~ ~ / l \ a ~ 1 I ~ Y ~ \ I i' / ~ I ~ ~ M^M'YYYYVVVYI ~ 0`~\`~ 0 it I ~ - 0 , ~ \ I I / , / , 1 ~ ~ ~ ~ Ex. ~ence , ~ ' • ~ ~ ~ ~ i , • NEW 2 PVG SERV CE LINE 1 m I ~ (5' OFF EDGE OF G AVEL ROAD, TYP.) , I ~ ` ~ Ex. Satellite rrr-, I I I I ~ ~ ~ 1.~ `~~~0 1 I NEW 1 /2" PVC PVC ~ ~ - Dish ~3 I i N , ~ °ye~ . ~ Bldg 1 1 SERVIC LINE 5~~, ~ i~ I I I I _INE ~ ~ ~ ~ I ~ N Ex. Storm Drain 1 5 ~ w/ Headwall ~ , ce ~ 2 ~ ~ 'I I I 0 ~ Bldg ~ I I P° \k \ 1 ~ 1 (each side) ' g5 Hse 1 I I c 0 1 ~ ~ (E ' ~ ~ J` I I ~ o NEW 60 LF ~ O I I Brdg ? I bi y I k u ~ ~ ~ ~ OF 2 RJDI ~ ~1 ~ ~ I ~-Scrt, ? ~ ~ '~J ~-Scrub ~-Woods--.~ ~ 0 S ~ ~ 1, ,C v 1 `I ~ ~ 1 / ~ / \ I - -1 I , ~,e , ? ~ II 1 I ~ ~ I I I I ~ . 0 dam, • / E=ce X I I I I 5 • . , ~ -X 1 X L J DESIGNED BY; dP ' a9d ~ ~'1 , 9 ? II WBJ 0 ~ ' ~ Ir) i' ! X ~ "x2" TEE NEW 195 LF OF 3" HDPE SERVICE LINE DRAWN BY; TKIEJB ~ NEW 3x3 d~ I NEW 2" PLUG VALVE , Ro°,' m ~ (BY HORIZONTAL DIRECTIONAL DRILL) ~ ,,'Soil, ~'~~c woods / MAINTAIN 6' MIN. CLEARANCE BENEATH x & BOX ' ~ del.' ~ 9 ~ 1 ~ Wetlands ' X CHECKED BY; ~ ~r° , ~ y CREEK/STORM DRAIN AND 3 MIN. COVER ~ Aso OTHERWISE. WBJ PROJECT NO.; m c ~ 9 2 ~-.-X~X_-X X 2876~B t0 / 1 v DATE; ~`--woods-~ AUG 2007 ~ \ ~i~~ ~-Woods-~ SCALE; ~ ~ NEW 60 LF ~ ro OF 2" RJDI 'r~E HORZ 1" = 50' M ~?ry`? Pfd} R ~'"•1 ~1 r N C~"' ~ 30 VERT 1" = 50' ~ ' ~ ~ ~ W ~ ~ ~ OPEN CUT o ~ o ~ co ~ SHEET 52 of 95 ~ p^ ~ 'A m ~ NEW 3" PVC FORCE MAIN (SEE SHEET 73) o ~ G-~ 52 ~ ~ I~ 11/2" PVC ~ NEW 6" FORCE MAIN •,c~ ~ ` 11/2" PVC v ~ 1 I f (SEE SHEET 33) c ~ ~ 3292 l i E SERVICE LINE ~ tie ~ v ~ se SERVICE LIN 0 ~ 1 N I I °0 0 ~ ~ ~ a a V II ~ ~ ~ o0 0 l acs ~ f a 0000 Z V ca ~ I ' / 0 f '0 V v ~WOOdS 41k % I I ~1 P 0 f I ~ f 3294 ~ ° o ~p0 H a ~ r r \ ~ ~ ~ ! Nse r 1 0o NN ~ U r / ~ ~ ~ 1~ 1 1 I ~ ' ~~0 WWI p A, 1 I f / R I I I r i - 1 ! ~W SERVICE LINE ~ - ~@- f I p, O p ~ OWN N i ' ' AL ASSEMBLY I / f~ r I ~ J~o W / / ~ ! SEE AIL TYP.) ~ Scrub / / II ! m f ~1 ~ / r / ~ I Q°~ Inv- 1 / / ! ~ ~--Woods ~ I / / + ~I w w ! 0 ~ I J ~ ~ z o -1,59 Inv--].o8 / o / ~~~e ~ ~ I / v t v= 4 ~ 0 / o Wote In D. 5 w I ~ ! i~~ ~ ~ LL Ex.4 Water ine w d v e ~ I \ w and n ! o' ! L1! ~ ~ o ~ LL? e Water LI / b _ ~ ~ ! Q Abandon d w ~ - - ~J I 10 w Q - - - - ~ ~ / ~ Z _i ° , v~ ~ ~ ~ Oad / 6 MIN. / tSR ~~16~ f ~ Woodle Station R / ~ y / FROM EOP / ~ FW-F~--FM EX. 4„ - Z ~ofer Lr~` ~ , ! p ~ ~ ' ~ i Ex. Guardrail / tl Riyy `m ~0 0 °o ~ / / o M II rA - r o ~U spho/t P°vemeotJ _ ~ I ~ ~ / _ NEW 3 PVC FORCE MAIN J I _ 48" RCP ,~"+1 = ~ / Inv=-1.33 _ ~ ~ N / r ~ a I~ ' I _ ~ -i,GO o w ~ Ex. Piers Ex. Conc / Ex. Piers w v~i 1 _ I 1 W I Inv- nv- NEW 3 -22,5 BEND m rn / / Walt ~00d1 S~a ~ ` 11 0 F- m / / I -0.28 -o.sr / / / ` ~ _ ~ Road ~ . W ~ ~ 3 - ~ z W ~ II / / (3) EX. 48 RCP / / I ~ / ~wS Q ~ M I / USE CONDITION 2 / / ~ ~ ~ ~ ~ R1116 0 Q p_ ~--Scrub ti ~ ~ C ~ N ~ NST CATION DEIf'AIL) / ~ .c / / F EX. 15 RC ~1 a ~ RAW ~ o° ~ ~ ~ M ~ - / t~+ USE CONDITION 2 o' ~ _ 2 Coi W O ¢ z -L OMO v NEW 3 45 ND / ~ NOTE - - {SEE INSTALLATION DETAIL) ~ o II II II - - ~ ~ NEW x 6 x 6 TEE ' NE 6"x3" REDUCER CONTRACTOR TO NOTIFY NCDOT PRIOR TO `01 a II DRILLING BENEATH BRIDGE. COORDINATE " PVC ORCE MAIN ~-woods - ~ ~ ~ V W Z = k• ~ N 3 PLUG VALVE ~ O + INSTALLATION CLOSELY WITH NCDOT TO ~ BOX ~1 Ex. 18" RCP ~ O > (5' OF P, YP.) USE CONDITION 2 ¢ ° (BEGIN STA. 0+00) / ENSURE NO DAMAGE TO BRIDGE STRUCTURE. • ~ / (SEE INSTALLATION DETAIL) ~ O ~ z m LLJ W o = W z z ° N C7 ~ 5 roe _ r~ ~ _ _ - _ 5 w _ _ _ _ - _ - _ _ _ - - , ~ 1 Q Z x, 48" RCP - IN. 0 _ C ORCE lnv- 0.91 I AIN Ex. 18 'RCP ~ 0 J II 6 LF r ~ - „ nv 1,33 Q ~ U Q MIN. ~ ~ u~ Ex. onc. Pi rs ltyp 1 m o N + I I Z N Z 'S ~ d _5 N ~ o NE 5 F CO CRET o NE 6" 6" x 6" T E x OC cn z ~ ~ U ~ N _10 ~ , ~ a SEE D TAIL) _~O ° ~ W o 9+00 10+00 11+00 12+00 13+00 14+DO ~ w ~ ~ O 0+00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 9+00 ~ ~ ~ F- uwi w Z o ~ ~ Q~ ~ o 54 ~ W ~ ,SEE SHEET ~ ~ c E STA 26~5~ ~ ~ o A1~HI.~N M NC T 6D iw ~ ~ m x 18' ~ W ~ E-E ~ ~ , ~ L ~ z W ~-woods 1 1 W I 1 ~ o ~ ~ 2 C (n I 1 i ~ I r- ? 1 11 NEW 3"-22.5° BEND ~ ~ O ~ i N .NEW 3"-22. ~ f ~ ~ NEW 3' . 1.~ - + ~ rn = o i o , NEW 3'1.25° B~D ~ 0 - --I--- - R/W-- , - ? l uJ 3 ~ Ex. 4" Wafer Line ~ ~J,J w w w w w w w w w - 1 N ~ _ w . w ~ - ~ ~ ' Woodle Station Road CSR 1116 (Asphait Pavemenfl W Y m o ~ 2-Ex. 24" CMP O Gravel Dr p ~w ~w ~ ~w ~ ~u ~u- I a - USE CONDITION 2 ~ + U ~ d' - Z ~ I I w ~ ~ (SEE INSTALLATION DETAIL) - < 0 r R/W f • ~ o ~ 24., P r1- ~ Q . • ~ ii o ~ ~ ~~NEW 3"-45° BEND r i° BEND ~ • ~ W l`, II m x ~ Z woods-.~ NEW 3 PVC FORCE MAIN ASE - ~ {5' OFF EOP TYP.) PERMANENT UTILITY E JTILITY EASEMENT ~ ~ OPEN CUT a~ ~ ~ Ex. 18 RCP I o ~ I = 0 USE CONDITI N 2 ~ U (SEE INSTALLATION DETAIL) I- Ex. 18 RCP Q USE CONDITION 2 I NEW 3" PVC FORCE MAIN ~ (SEE INSTALLATION DETAIL) (SEE SHEET 54) Cn STCZ, A o 1`+1 IMPF~CS" 58 v DESIGNED BY. WBJ L a ~ ° ~ DRAWN BY. ~ ~ ~ TK l EJB ? ~ uZ~ CHECKED BY. m 5 5 WBJ U, ~ ~ . ^ Ex. Grade PROJECT NO.. v 2876•B N _ ~ - - - x. roe - - - - - - - - - - - _ ~ DATE; p~ i n ~ - AUG 2007 N 0 ' ~ Ex. 18" RCP MI , Ex. 18 RCP Q SCALE; ~ ~o ~ MIN ; - ~ MIN. MIN. , ~ ~ 0 OV 4~ ~ t, - _ ~ SHEET 53 OF 95 L NE 8 L CON RETE N W 5 LF C NCRE E _ _ _ LNUAtiLML CIO E CASE ENT Q U O N o v, t -10 53 -1o N ' 14+00 15+00 16+00 17+00 18+00 19+00 20+00 21+00 22+00 23+00 ~ ~ ~ !3+00 24+00 25+00 26+00 \y ~ ~ \ Y\' I ~I ~ I I 1\\ 3 ; ~ ~ NEW 6" PVC FORCE MAIN w (SEE SHEET 33} Z Z V ~ ~ ~ p _ ~ ro ,x \ WV I NN ~ ~ l 24"RCP ~ s ~ WWI O i D \ ~--woods-.1 i ~ Q W N ~ R /W \ " f - _ \ `x \;a I1 x I i r JFZO ~ ,.a _ a o ~ r - I - _ ~ z Z O M 1 I - I x \ ',\i ~ m Z ~ ~ ~ III _ M - III I Abo \ N I ndoned Wote I \ - I r me M ~ 36 RCP I m ~ ~ W _ _ - - - - - - _ n M M O M _ _ _ ~ o M ~ !Asphalt Pavement) ~ ~ ~ ~I _ FMI ;r. o ~ Ex. 6" Water Lfne 2.90 _ _ I _ _ - M Z Road ti ~ lSR 1113) ~ m _ - ~ ~ ~ m N st Office / --_I o BO PO OPEN CUT o ~ Y / I f' _ - O 8 MIN. Abondoned O m ~ - - ~ ~ ' ` ` m j ~ Z OFF EOP Wofer Line ~ T ~ i I R/W` _ _ - _ _ ~ i - _ i ? _ _ o ~ o `;o cn Z w i - i 1 - - - - ; ~ NEW 3" PVC FORCE MAIN I N ~ ,1 ~ o Q x ~ m i Ex. 24" RCP - ~ _ 3s' RCP r` I ~ I ~ , .r - _ ~ C) (5 OFF EOP, TYP.) _ ,x 01 USE CONDITION 2 a ~ • C I . _ _ - - r•'i • ? (SEE INSTALLATION DETAIL) k? ~ - _ r - "`I ( _ _ ~ - - - ' 1'1 m a z d ~ ~N -I ~ O ik Ex. 48" RCP a a U / ! - - - 1 I A R/W ~ _ / ~I I~ ~ .o USE CONDITION 2 z ~ NEW 6" x 6" x 3" TEE :J -n o u I ~--Woods 1,_, (SEE INSTALLATION DETAIL) E,~,~Y~_ Z z Woods-~ ~ W z ~ it A C i r~--I / NEW 3 -45 BEND 6 , ~j ~ ~1 C i NEW 3" PLUG VALVE & BOX k~ j 0 (BEGIN STA.0+00) 0 ,~Grf~ ~~T ~ V 1 fii~ ~ 1 t~ ' ~ O a c co ? ~ 4 O (0 N ~ ~ ~ O Z CD ~ L ~ ~ 'F'' 0 w w o = w Z Z ~ N 0 C7 .--i \ qd 5 Z ~ ~ ~ ^ ~ 5 Ex. G ode W r•-- ' MIN. Abando ed Ex. 48" RCP Q Z NEW " PV FOR E MAI O J z -o 20 IN. U ~ a x.8 ofer me 2' 0" MIN. ~ ~ IN. N W 5 F CO CRET Z N U E CASE ENT -5 N ~ -5 EW 6 LF C NCRE E N ~ O + + U U (n CV o -~O NE 3 PLUG VALV & B X a+00 10+00 11+00 12+00 13+00 14+00 ~ ~ ~ m O + 4+00 5+00 6+00 7+00 8+00 9+00 0+00 1+00 2 00 3 00 J w ~ J ~-Woods-~ - / ' ~ ~ ~ Q NEW TERMIINAL CLEANOUT ~ ~ z N ~ o ASSEMBLY ~ ~ W (END STA. 28+24~ W = U ~ ¢ ~ .j a n O o. ~ + ~ ~--woods z i~ ~ o ~ I / ~ U W I , 1 • Z o _ I '1 I I ~ 1 ' I ~ ~ ~ I / ~ \ ~ ~ ~ ` ' I I / S ~ ~ I 1 ~ ~ ~ ~ ~ I 1 1 ~-Woods--.) / ~ 1 S 1 0~ W ~I ~`-Woods ~ 0~ I ~-V~oods W ,I a / l t / t 1 ~ = WI x I 1 . . 1 l ~ ~ / ' ~ ~ I WI 1 l ~ ~ l I ~ 1 ' I I 0 ~ ; , I I = a I Woad: I o ~ i 1 `--Woods-~ 1 m 1 N ~ ~~-,c ~ / / ~ ~ n ~ j ~ I o I ~ 1 ' o / r Cv I I~ ~ o I x' + f p , ~ I m W ~ ~ ~ R/w I ~I-~-- - - - - - ~ - -1-1~ - - ~ ...Woods Bldg ' W --I---- ---I--- v, ~ - - - I ~ / I ' ~ ~ . . _ / \ ~I M M-- ~ , I }-I-{ Ex, 6" Water Line ~ I M M M M M 1 (n O ~ O lAs half Pavement) BD Posf Office Road lSR 1113 P y o _ ~ - 1 1 I 11 I -c S . ~ - _ , R/W 1 - - - - - - - - EX. 42" CMP Q - - - - - - - - - - - - - - - - - - - - - - c~T - - - - - - 1 ~ I ~-Woods I;~ I ~ I-' 1101 to I ~ lal USE CONDITION 2 • ~ ~ III 1 m I Iml ~ ~ (SEE INSTALLATION DETAIL? Q, ~ 101 W ORCE MAIN 11 0 l i o l W 1, NE 3 PVC F , ~ c Z ~ 1 11(5' OFF EOP, TYP.) '1 1 ' ~ J 1 1 1 1 I ~m ~ ~ ~x ~`--Woods--.r ~~cc??--~~ 11m 1 1 I I i n~ 1x ,x 1 1 `Cry ~ la , W ~ 1' 1~ 1 1 I 1 O V '1~ 10 1 1 1 1 I' 1 1 1 1i~ ~ ~ ~ Q 1 1 1 1 ~ ~ 1 1 1. 1 Hse Hs~e ~ ~i ~I ,cti, DESIGNED BY. N WBJ z 00 DRAWN BY: ~ TK 1 EJB W ~ ~ CHECKED BY: 5 wBJ 41 5 r WJZ PROJECT NO.. ~ Ex. G ade co . ~ ? ~ J ~ _ _ _ - 2876•B - - DATE: N MIN. AUG 2007 EW " Ex. 4 "CMP r\ ~ O Q SCALE HORZ 1" = 50' N ~ ~ ~ ~c o' .o NV _ 5 SHEET 55 of 95 -5 L 6 F CO CRET a GI lrl1JG GIV I ~r- r% r- All O ~ 55 ~o -1o -10 N 23+00 14 22 00 +00 15+00 16+00 17+00 18+00 19+00 20+00 21+00 ~ 23+00 24+00 25+00 26+00 27+00 28+00 G~ Z Z 1 ~t~e .1 5 '1 0 ('WO ~ C . N ~ C E ~ I / Nc . o • an S oti' t I Tq 9S,~ W ~ ~ g ~aa , to~~ t, I P ~~'SE ~WZ ~I 1 F THIS J ~ o I I I I 1 U '1 ~ ~1 ~ I I 1 l~ i ~~r ~ Z ~ 00 ~ Woods t ~ ~ ~ Z 0 ~ I 1 I ~~X ~ '1 ~ I , ~ ~ 11 t ~ I , g ' ~ ~ ~ ~ ~ LL W I t ~I~ / 11 I ~ / W Im I I, _ .x 1 ~'m tm / (n 'I'a x I, x x l I ~ , ~ 1, ; ~ W I~ '.n In n ~ W I,~ ~ I~ NEW 3 PVC FORCE MAIN ~ '~t , / ' ~ i (n I, 't (5' OFF EDGE OF GRAVEL/SOIL ~ I ,I '1 , / 'i '1 ROAD, TYP.) ~ ~ O o ° ~ ~ W o R/W o - ~ ~ i d- - i ~ i ~ ~ Ex. 4" Water Line ~ i F- m / ~ U N V' Q w w w w _ - 0------------ ,i w i~ / ~ F ~ M cn lGrave,/salri Old Columbio Rood CSR 1110 ~ a r;, ° m - O _ ~ O~ U N ~ ~ U m W - - - ~ Z_ ~ o az~ - - • ' U ~ J - = R/W - z ~ 3-NEW 3"-22.5° BENDS Z U NEW 3" IN-LINE i+.~yy.:yY Z a woods/wetlands CLEANOUT ASSEMBLY a 0 d ¢ o c o0 O c9 N ~ j~ 00 O Z 0~ ~ - .C ~ ~ L W UJ O S W z Z ~ N U' .-r 5 5 Z w Q _ l 'l 1 - - - Z Z - _ _ _ Ex, rode O J 0 - ~ _ Ex. o ~ - - - - - \ - - - ~ O • MI . Q U ~ NE 3" VC ORCE MAIN 2 Q ~ Q O ~ Z CV -5 _5 N~ a NE 3" I -LINE U ~p CL ANOU ASSE BLY ~ ~ O ~ Z J ~ U ~ ~ OT -10 -10 ~ ~ W o ~ 84+00 85+00 86+00 87+00 88+00 89+00 90+00 91+00 92+00 93+00 13+00 94+00 95+00 ~ ~ ~ o w~ ~ O ~ ~ ~ Z I'" ~ 1 of " I 1 1 YV ~ O 1 1 ~ o~ O I n) 1 t k, woods ~ I 11 ~ a~ w~ WI I 1a1 I 1 11~ 1\ / l0 1 I w ~ ~ Ia- _ I a~ ~w I 1 ~ ~ ~ Ij I 1 ~ ~ ' 1 ~ j Ex. Pond } ~ C+') w J 1----- w 3 ~ Z ~t I ~ ____a , - o ~ Z ~ w - co -z_.. 41 ~ ,ne _ _ - ~ +I to v w'- - _ cn t J \ = -p-_ J /rub ~ el/Soil) v -a - Q~~r w 'SC roe _ _ - _ w (G - - - CO ~ 1 ' _ _ a Ro o, i ad ~ Approx. Locotion of Ex. Gas Llhe ~ - , - ~ - ` ~ ~ ~ ~ II ~ ASR w 1~1 , , ~ r ~ EX. 24 CMP 0~ ~ - ~ ~ USE CONDITION 2 0 ~ ' ~ . ~ ~ (SEE INSTALLATION DETAIL) \ ~ ~ Scrub . \ ~ ~ ~ w ,f ~ ~ ~ ' ~ Woods/We lands ~ ski / NEW 3 PVC FORCE MAID FORCE MAIN I i ~ m i ~ l5 OFF OF GRAVEL/SOIL RAVEL/SOIL ROAD, TYP.) ' ~ i cn ~ ~ RiW ~ , ~ \ \\.\~w~ \ \ ~M 1M ~~c.T ~ s ~ c~ B ~ Woods/Wetlands ~ \ 0 o ~ ~ ~ ~ ~O ~ i ~ i / oCOfi~7 ` ~ ~ \ ~ ~ O ~ Q~. ~ 9 ~ , ~ ~ ~ s ti ~ , F ~ , o, v ~ ~ ~ ti s , ~ ~ , o s 9 s V~ 'i ~ ~ ti ~ s, ~ ~ X ~Q' F o ~o DESIGNED BY; WBJ DRAWN BY; a, TK 1 EJB CHECKED BY. m 5 5 WBJ PROJECT NO.; N 2876-B ~ DATE; ~ Ex, Gr de ~ ~ ~ ~ ~ _ - ~ _ - _ ~ _ Ex, rode AUG 2007 _ - _ _ - - - - - - 0 SCALE; ~ ~ - - - - _ - ~ ~ - ~ 3' 0~~ HORZ 1" = 50' E.24"C P j C VER NEW 3" PV FO CE M N VERT 1" = 50' 00 , NV 2'-0" „MIN. -5 L _ 5 SHEET 59 OF 95 O -NEW -5-tF CON RETE- O U ~o (SEE DETAU - 10 N -59- -10 95+00 96+0 97+00 98+00 99+00 100+00 101+00 102+00 103+00 104+00 )4+00 105+00 106+00 107+00 108+00 109+00 O 'W i \ Woo ds 1 Z Z ~ ~ ~ (boo o ~ wv ~ ~ Scrub ~7 _ _ R/W a ~ W a ~ o \ ~ O \o - r QJ~, o ~ ~ ~ l - m _ f O ~ ~ ~x - Z wN _ - ~w _ , _ RI 1~ O ~ ~I ` wWpf ~~O X- ~ ~ _ - lGrovel/ Soil Rood) - fx. 4~. oter Llne ~ - - ~I ~Aprc e~~in ~o I N - ~ a~Q aX hoc e ~ . z ~ X . - w - _ _ ~ Qo~ ~ _ z~ otia ` l p O - _ fib ~ ` o f,~ ~ ` - - _ 10} _ _ x , ~ ~ 11 _ - ~ _ - - w (SR - ~S~ - ~ a ~ ~ w -1-~-- ad ~ - - c- - ~ ~ ~ ~'I ,0 ro W ~ _ o ~ R - a _ - _ i ~ a 3 _ 1111? _ ~ _ _ _ w _ _ - < N ~olu _ r ~ Lo~oto ~ n of=Line ~ + ~ - _ ~ Old ~ . - o io ? I+ - ~ h r~ ~ _ ~ - - - Q r r ~ ~ - ~ I r ~ r ~ ~ NEW 3 PVC FORCE MAIN °r _ ~ _ - ~ (5'OFF EDGE OF GRAVEL/ 1x~ ~ ~ I~ o Shed ~ m S''CRERWI ~ I ' < ti m woods i'i - - _ _ - ~ SOIL ROAD, TYP.) i°i I~ i I NEW 2" PVC SERVICE LINE i i (SEE SHEET 78) ss 1-~ ~ I I '11 ~ ~ V N I~ rn zw~ _ , _ ~ rn ti~ ~ ° ~1 cc U M 1 ~ NSe ¢ ~ M s ` U ~ ~ 1~~, - _ ~ i - I i ti ~ ~ a ~ r" m i ~ 0 S ~ ~ ~~1 Q ~ 11 J , ~ ~ O a c o0 i ~ J 0 ~ m cv °O. o z m ,°-i - ~ ~ w w z w z O N C7 ~--I 5 z W 5 Ex, G de ~ Q _ - Z - - MI x. Grod MI . O O - ~ EW "PVC FOR E MAI 0 U 2 Q r Z ~ _ 5 N Q U m ~ -5 ~ Z ~ O ~ r Uv U i Q z ~ g ? la- i O Q N -10 8+00 ~ 119+00 120+00 121+00 122+00 123+00 v ~ ~ ~ O + + + 112+00 113+00 114+00 115+00 116+00 117+00 118+00 109 00 110 00 111 00 J w~ ~ ~ Z p kr ~ o ~ ~ o rn i a~ w° Nse ~ ~ ~ Q ~ I I 0 W ~ i I I Q ~ ~ f~ ~i ~ QI I ~ ~ a ~ ~ II ~ i W ~ I woody II ~ W 'W II O Woods w ~ ~ o pi v Z ~ I~ I ~ 0 ° ; O to I NEW TERMINAL CLEANOUT w NEW 3 90 ,BEND NEW 3" PVC FORCE MAIN ~ i (END STA. 134+48~ °C ~ N (5' OFF EOP, TYP.) ~ I II ~ ~ C~ _ o NEW 3"-45° BEND R/W i ~ ~ _ R/W II Z rte! f _ , . . o, lU - ° - - ~ ~ ~ ~ Z N w ~ w ~ ~ ~ FM ~ ~ O +I N ~ w i ~ ~ (Asphalt PovementJ o O o~ 110) w rn - lGravel/ Sal RoadJl OPEN CUT Old Columbia Road lSR 7 . - N 3 0 O 0 nj ~ w O (V w'-; w w ~ w Ex. 4" Woter Line ~ ~ ~ c c c c c c I Ex. Gas Line ~ - - - I - - ' _ _ Ex, Gos Linee c m - - - - - - I p f Q - r R/W I m I r~ ~ I v ~ ~ ~ ~ T c I ~ I~ ° ERMANEN I p I _ _ ~ 2 -NEW 3 45 BENDS UTILITY EASEMENT ~ ~'S ~ I I Nse ~ ~ ~ ~ NEW 3" 0° BEND ~ Hse a ~ ~ V ~ ~ Woods ~ o OPEN CUT ~ Q k a~ I ~ "PLUG ALVE & BOX ~ ~ 0 'E 3"x x3"TEE ~ 0 I \ EW 3"-45 ~ BEND _ ~ ~ N ~ I , ~ ~ \ ~ \ x x X x, Fen X - cn ~ i~ ~ ~ ` X X Woods Ll ~ ~ ~ . p r ; ~ ~NEW~ 3" F MAIN r ~1 I 0 (SEE SHE ) ~ ~ rr p ~ DESIGNED BY. ~ r--------~ / 1 t a 0 WBJ (n~ o +I DRAWN BY. ~ ~ .o ~ ~ ~ TK 1 EJB 3 N i z CHECKED BY. r WBJ ~ ~ o ~ ~ ~ I~ m G I , I ~ W~ 5 PROJECT NO.. tiJ I o I 2876.6 ~ I ~ ~ I - - - - - - - - - - - ~ Ex, G de i - - - - - - - ` I ~I _ ' i_ n Ex. G ode ~ w Z DATE; - AUG 2007 ~ IN. ~ O 0 SCALE; HORZ 1 ° = 50' N E 3" P C ~ ~ ~ x, Gas ine E . 4" Wa er VERT 1" = 50' ~ C L he ~ ~ ~ MI . n~ ~ IN. MI . - 5 SHEET 60 OF 95 -5 L NEW 3"x3" 3" TEE--J NE 3" P UG VALVE BOX o~ 60 ~ o -10 -10 N Cj_ 130+00 131+00 132+00 ~ . 123+00 124+00 125+00 126+00 127+00 128+00 129+00 32+00 133+00 134+00 135+00 -X 0 . . 1 - ~ Wetlands ~ /dg Bldg ' . B/ Woods v ~ _ I X X dg Bldq 0 ~r ~ ~ woods . ~ _ ~ I ~ 1 J/ I I ~ i it i 0 j 11/2" PVC --1 I ~ Q IOW 11/2 PVC II r , Z ~ ~Wo ERVICE LINE NEW 11/a PVC 1 ~ I ~ SERVICE LINE L~ ~ SERVICE LINE ~ ~ o 1 co I ~ ¦ NEW 3" x 3" x 3" TEE ¦ ~ r mj ~ I 1 NEW "PLUG VALVE ~ w W Q ~ z & B~ Hse = W ~ I- v, r ~ n I W NEW 11/2 PVC o x l' o I ~ ~ I 681 Ex. Satellite Hse m U~ Q W N W SERVICE LINE ~ I I Hse ~ 5'C'R~E~11M CT - W ~ ~ ~ s2~ ~ ~ o Ex. 24 PIR to D ~ ~ C~ N Ex. 24" RCP Dish ~ ~ ~ Z > _ ~ I ~ ~ Hse 1 o , ~ 595 - 613 Hse 101 U$E C ~ o ~ I Hse Nse Hse I v USE CONDITION 2 0 = J ~ 0 ~ I ~ ~ ~ I o (SEE II o - ~ ~ 1 0l (SEE INSTALLATION ~ o ~ 0 U W ~ rc; ~ " ~ ~ ~ I r ~ ~ DETAIL I ~I _ o , p C~ J Ex, Headwall p DETAIL} ~ IQ ~ ~7 w ~ Z ~ W NEW 3" PVC FORCE MAIN ~ ~I lal r~ I ~ ~ I I (eoch side) ~ ~ ~ t 1~ I a~mti I 2' m i0~ I I ~ 0 m~ I (5 OFF EOP, TYP.) 1\ of ,-ti i o I ~o ~ . ~ . ' a, I_ ~ ~ J Z col ~ la, W ~ LL - I - ~ - ~ ~ r r r-- , a~ ~ ~ . I I , I cn I LL. o , I I T or I ~ a o ~ ~ ~ ~ ~ o 0 ~ ~ w Ex, Foot- ~ x Foot- Cha el Hill Road lSR 1114) bride lAsphalt Pavemen( N ~ w bridge g sphalt Pavemenfl ~ ChOpel Nill Road CSR 77751 P 0 M M , Q L_ M M M M M M M M I- 1 I ° _x. Gpas Like c c cLt., c ~ 0 I 0 I 0 ~r ` ! ~ ~ ~ ~ I~I ~Oi~ _ - - I I- -r ~e~, - ~ - - - ~ ~ 1 ~ I ~ ~ ~ ! ~ Ex. 24 RGP o _ I poi II v Z to n ~ I o ~ G - ~ I ~ t o j USE CONDITION 2 - ti , r .J ~ ~ ~ I ~ ~ o ~ NEW SERVICE LINE ii NEW 3" PVC FORCE MAIN \ ~ I`'~~--____-' fate/~t'~'~ Z I l a l ~ a. I ~ (SEE INSTALLATION DETAIL) ~ I r VALVE ASSEMBLY ~ I ~ ~ o I ~ ! Ex. SateOite 1 ~ ii (SEE SHEET 67) I i~~_-------G ~ _ ~ M U ' I I. o I ~ m ~ m' w! IDish ~ (SEE DETAIL, TYP.) ~ I I II vl ~ ~ I II I V Z"~ I w ~ I Q ~ I ' L - o' I i -J •I kl ~ o~ II ~ ' 0 r J I ~ k ~ , WI NEW 11/2 PVC tul ~ N II II C Q ~ - ~ j ' ~ej ~ ~ I` ~ ~ N ono I I 1 I I 850 CE LINE ~ ~ SERVI ' I I I Hse Tr/r I 1 I I p'~ ~i~OJ . ~ ~ U m Hse I I ~ I a I ki C~~~ ~ a z m W ~ Nse ~ I `.0 1 ~ O o0 00• ~ ~k I k~ o W~ ~ Hse I i ~ ~ ~ ~n ~ I , r Hse ;a ~ z z 'n - I / ' I~ ~ ~ I I I ~ J I Llli ~ ~ a ~ M i I I I I ~ I ~ I - I ~ P J ~ Ln I '~~JJ" o ~ a o I I _ I I I I r-I o - N N i z 0] .-I I ~ OT ~ - .G ~ ~ y w a W ` Z w Z Z N U' ~ Ex. Grade 5 Z w ~ ~ - _ - -_J r CO ER Ex. 4" RC NEW 3" PV FOR V/ - ` Z i J ~ 0 - MI . E,24"R P O ~ Q U 0 '-0" _ i O ~ EW 5 LF C NCRE E i Z N it _5 NEW ~~x3"x " TE -5 N v o NEW PL G V VE & BOX ~ = p W ~ Z J ~ ENCA MEN v ~ ~ ~ _14 z -10 O o~ V ~ 28+00 29+00 30+00 31+00 32+00 33+00 34+00 35+00 36+00 37+00 ~+00 38+00 39+00 40+00 41+00 42+00 ~ ZO ~ ~ I ik I' I ZJ ~ l II V ~ ~W a° ~ + ~ Z ~ o0 . ~ I ~ Ex. 15 RCP W Chopel Hill Church ~ 1p TION2 ! o wCV W ~ ~ ~ USE CONDITION 2 Ceme ter I I ~.LATION DETAIL) ~ \ woods ~ w oWC ~ Q _ Y woods ~ (SEE INSTALLATION DEl (n cn I o ~ ~ Cp Q ~ ~ f~ Trlr I o ~ o ~ ° I ~ Ex. SoteJlite " NEW 3" PVC FORCE MAIN = oisn ~ ~ ~ ~ W ~ d CM ~ ^ e~p~ n ~ (5 OFF EOP, TYP.) ~ to'r~ R/W ~ ~ ~ , ° ~ o I • Z cn o w ~ W r ~ - , cn ~ ~ ~ ~ ~ Fu Irv ~w ~u J o ~ ~ ~ Cho el Hill Road lSR 11151 !Asphalt Povement) ~ ~ w ~ p 0 0 M M M M Q 0~ N c / c I c~ c G ~ ~ C C ~ ~ G ~ ~ p~~ ~ \ • m , x{ Gos Line f I r r 1 I _ _ - - - -----~~--'r - I - I 1 Te--- - - - - - - - I I Ex. Satellite ~ Q R/w I ~ 11 ~ ~ I i 1`I ! " ~ ~ ~ N I ~7 I - - ~ ~ I Dish cr' ~ 11 ~ ~a~ r I r! 1~1 j I ~ NEW SERVICE LINE i o i~E~S%ae k VALVE ASSEMBLY ,v, - ~ ' '~'1 , to / ~ i psi 101 ~I (SEE DETAIL, TYP.) ~ ~ o ~ ~ Z I'I'I ~ fro ~ ~ p I 1 a~ ~I I " ~ Ios4 NEW 11/2" PVC ~ t~ Hse ~ - - - I I SERVICE LINE i ~ i , U 11, ~ `t' ~ , i 1 , I I 0 Q 1 ~ ~ '1 11 ~ C ~ I Woods I i c 1I I 1 ~ I ~ I 1 I I ` ` I a v., ' ~1 ~ I I 0 1,~ ,QO I~ I I l oo ~ ~ i~l 0000° ~ 1~ 1 o ~ , I 0 ~ 1 1 I 0 1 ~ "Chopel Ndl 1 I r I• LOT Chapel Hill Church i 1 ~ X11 ~ Churcn" 1 ! V) I r 't ZONE ~ ~ J r ~ 11 ~ i J 1 1 -GROUND ELF ~ 11 ~ ~ 1 r 11 ~ r r 1'~ -TOP SEPTIC TANK r ? ~ ICI t r q 1 rr ~''I r r •,~'1 PUMP MODEL"~ I'~ ~ r 0 X11 ~ ~'1 CAPACITY 1,860 GAL. ~ DESIGNED BY: ~ ~ r • ~1 ~ 1 i WBJ 0 DRAWN BY: ~I TK 1 EJB 3 m CHECKED BY. m 5 5 wBJ PROJECT NO.: ~ Ex_G odes ~i - - - ~ 2876.6 - - - - _ _ _ _ _ _ _ - ` ~ ~ Ex. ade DATE: r\ ~ MIN. - _ _ - - AUG 2007 0 N " Q SCALE: I ~ Ex. 15" RCP HORZ 1 ° = 50' ~ 2._ N~ VERT 1 ° = 50' O 0 ~0 U 5 SHEET 64 aF 95 i -5 i P, cr hjrpp,-r F* C~o ° E CASEMENT ° (SEE D TAIL) ~o 64. -10 -10 N 51+00 o 42+00 43+00 44+00 45+00 46+00 47+00 48+00 49+00 50+00 1+00 52+00 53+00 54+00 55+00 56+00 ~ ~ Z o ~W~ O NEW 11/2" PVC (n N V O O SERVICE LINE W Q ~ z i y Woods 0 ~ ~ ~ QJy ~ / Q~ W ~ Q ~ / ' ~ ~ ~o J~o~ w ~ Qo~ / r ~y 0, ~ r ~,rr f- Z ~ ~ ~ ! r V rr 1303 ~ j ~ ~ LL Hse ~ ~r ,l r i ~ I li V ~ ri ~ ~ / f ~ I ~ I Y Q' ! ! I c~ I I ~ 4„ i . \ NEW SERVICE LINE ' ~ I tv VALVE ASSEMBLY II°i ~ (SEE DETAIL, TYP,) ' fli ate~Ci ~ R/ F ne w NEw 3"x3"x2" TEE ~ x cos w " v v d9 ~ ~ NE 3 PLUG ALE & BOX woods 6~ ~ e ~ M - ~ ,r?~ i t ~0 ~ O y SQ ~ ~o woods 'tip ~ - W ~ s~ ` \ h ~l O~ I NEW 3" PVC FORCE MAIN - ~ ~ - ~ O 1 t~P -CY o a ~ ' (5' OFF EOP, TYP,) ~ _ ~ ` z M ~ ? p ! j O ,0' RiW . w z Nse ~ ~ / ~ Woter Line W _ c+i ~ ~ o / 2~0 /~~1: ~ EX'4 _ Q - ~ ~ _ ^ rn • ~ ~ ~ he / G~ l; ~ ~ 0 ~ ~ M ~ ~ U N ~ - ~ ent) - ~ ' ~ tt U M 1 +I ~ rn L~ ~ (Asphalt Pavem a z r 0 o ~ ~ + ~ ~ I 0, ~ ~ 1 0 ~ L a \ z~ . " ~ - ` i ` NEW TERMINAL CLEANOUT U ~ 0 ! hI ~ I 1 Y( ~ ~ - i (END STA. 69+82±) K4 ~ Z v~, Z Z Z H I~ ~ - W ~ ro _ 15) I ~ I 11 e I - _ - ~ SR I ~a 9 ~ ~ 1 pl -~I of ~ a ~o '-ti ` ~ k!V ~ I ~ ' a~ I l ~ IIRo M o. I N~ r r - c co ~Ir ~I ~ WI 0 ~ o N / e ! + Chap _ ~ ,o, ~ ~ lol j I I z m~ ! ~ M , ~ r~ I~ 0 C5 I ~ ~ ~ ~ n+ r i, I I 1 0 I I I I Ll.l w z° 1 1 ~ ~ = w ly.!" i ~ ICI I I ~ Z N Hse ~ ~ ' ~ ' - - - I ~ c~ Hse NEW 2 PVC FORCE MAIN 5 ; i~~ ! , o ~ i ~ p z (SEE SHEET 66) ~ ! ~ I ~ Hse ~ ~ I ~ , I roi- I W (J ~ ~ I P~O~ Q G ~ ~ , I_,-~, , ~ Q ~~-J f~ ~ ~ O I c~ ~I o ; m ~ c ~ Hse t 01 ~ Z W Hse WI m O Woods i i a ;~~o I i' U ~ ' = Q JG ~ I I~ • T I 1 ~ ~ O ~ y~ M 11M r c P~L o T 2~ era ~ G ~ 9 z CV Bldg N ~ J 'W t - U J c y a `J 2 aND • I rn Z J ~ U O ~ C~ ' I I Woods Z ~ ~ 2 Ia- O off V ~ U ~ to , ~ ~ ~ ~ Z ~ rz o ~ g z~ w~ U ~ ~ a~ oWc - ~ ~ M z 20 20 ~ z J J W }Q} F- C 15 15 0 0 m 1 10 Z 0 5 _ _ - - ~ Ex, G ade ~ ~ r IN. ~ ~ 0 NEW 3"x3" 2" T E ~ r o, MAI 0 m O Ex, 36" CMP N _ 5 DESIGNED BY: -5 WBJ DRAWN BY: TK / EJB ~ +I +i N t~ CHECKED BY; _ 1 O WBJ m -10 ~ 15 LF F 3" DPE ORIZO TAL ~ PROJECT NO.. ro N 2876-B DATE; AUG 2007 -15 ~N -15 SCALE; HORZ 1" = 50' "1 ~ VERT 1" = 50' O ~ .o ~v "1 - 20 20 sHEEr 65 of 95 O ~ ~o -2 65 -25 N o 56+00 57+00 58+00 59+00 60+00 61+00 62+00 63+00 64+00 65+00 5+00 66+00 67+00 68+00 69+00 70+00 (GravelDriveJ X ~ I \ v ~ i ~ ~ ~ ~0 NEW 2" x 11/2" ri \~ti W ~ REDUCER ' I ~ N V cn l NEW 11/2" PVC W W F p ~ ~ SERVICE LINE , I Q W N cn ~ > J ~ o ~ I' Q o ~ I Z ~ NEW 3" PVC .FORCE MAIN I i ~x_ I X11 ~ ~ SEE SHEET NEW 2" PVC ~ ~ ~ X ¦ , LI. I I SERVICE LINE i ~ I- I -X~ ~ ~ I x ~ I C ~ Ex. Creek _ _ ~ ~ fx, Cr - - _ eek ~ I Mother's 18' ~ x Playground Qelper I ~ w I E-E I ycare X I I x , I ~ Z E N l i I ~ 0 w~ ~ "1 Woods / Wetlonds .Fence o i j ~ x X~X~X ~ X H- ~ ~ x rn + I I ~ Q ~ N~ I ~ ~h side) O I ~ I ~ 0 ~ cc U m I'r ~ I ~ ~ p ¢ zM ~ i ~i00 ~ y_ ~ i 4 U Z- OPEN Cl]'F___ oad ~ ~ ~ ~ .r.,~ M x - ss R - _ - avel Acce _ - w ~r Q -,I ~ o J - _ _ !Grovel Parking) X ~ ¢ Ne _ c o0 11,E ~ - m cv a ~ ~ - o ? f ~ ~ ~ o ~ 0 _ . , END PROFILE i i' - - _ x ~ ~ ~ ' N ~ _ ' , ~ ~ _ , \ o ~ NEW 2 PVC FORCE MAIN V NEW SERVICE LINE , , - W w z .c NEW 3"x3"x2" TEE ~~-o z¢-.' (5' OFF GRAVEL/SOIL ROAD, TYP.) I VALVE ASSEMBLY NEW IN-LINE CLEANOUT II I I ~ = z N (SEE DETAIL, TYP,I ASSEMBLY , ~ x ~ , NEW 2 PLUG VALVE & BOX 3¢., (STA 11+06~ I ~ z ~ ~ (BEGIN STA, 0+00) ~ s ~ 0 1 I ~ I w I Q ~ 0 ~ Fk ' ~ NEW 2" PVC I ~ ~C a W 5 _ ood l eek - ~ _ ~ ' - - /1 SERVICE LINE ; ~ NE1 NEW 11/2" PVC ~ i Charity Q Nc SEf SERVICE LINE ~ ~ NEW 2" x 11/2" ~ ~ 1'emP/e x O T s0 ~w ~ r REDUCER I I I a ~ 3 2-Ex, 24" STEEL PIPE ~ ~3 i I I U r I ~ ~ USE CONDITION 2 ~ ~ (SEE INSTALLATION DETAIL) NEW 11/2" PVG i i ' ~ r _ _ _ _ _ _ _ SERVICE LINE , ~ ~ T _ ~ I z CV Q _ ~ I N U ~ Woods /Wetlands Ptah (GravelDriveJ I N ~ p NOTE S'r~, r ~~M 1~I4P~cT 1~b 0 3 A 20 TYRRELL COUNTY PERMANENT UTILITY EASEMENT CENTERED ON THE FORCE MAIN EXISTS ALONG THE UTILITY _ - ~ ~g O WHERE IT IS OUTSIDE NCDOT ROAD RIGHT-OF-WAY. THIS ~ ~ ~ H EASEMENT WILL ALSO SERVE AS THE CONSTRUCTION _ OC } {n LIMITS FOR THE WORK IN THESE AREAS. J w i ~ ~W z Q Z ~ U a p ~ Z ~ N 20 20 W J Z J W c 15 15 0 a 10 m 1 I b ~ ~ Z~ s 4 ~ o ~ ,I., U 5 ~ 5 Ex. rode ~ ~ ade 1-~-- - ~ ~ ~ I ~ J ~ - ~ I 11 Ql . - y - .C ~ MIN ~ ~ 1 - x, feel c O o, ORCE .r^ ~ 1-011 0 Val 0 2•-011 NE IN- INE C EANO T AS EMBL _ 5 DESIGNED BY. N -5 WBJ L (SE DET U DRAWN BY: a~ TKIEJB 3 a~ N W 3'x3"x2' TEE CHECKED BY. _ 1 O WBJ m -10 PROJECT NO.. 2876-B N DATE: AUG 2007 -15 ~N -15 SCALE: ~I HORZ 1" = 50' ~ ~ VERT1°=50' ~ ~ ,o ~v ~ -2~ 2 O SHEET 66 OF 95 M / `o co O O ~ o -66- -25 -25 o 0+00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 9+00 co )+00 10+00 11+00 12+00 13+00 14+00 \ ~ .c w u 1 X ~ IJ ~ I ~ . ti .C o ~ I~ vl O~ ~ ~ I ~ ~\3 ? k i 14 W I ° o NEW 11/2" PVC Q; . a o ~I, Z Z I k SERVICE LINE n ; ~ o 0 0 I~ o ~ ~ kl 1 ! a ~ ~ o -w~ la ~ I-. ~ QII ~ ~ Q 835 1 I , NQ~ z ~ 0 Hse I Q~' I I ~ I ~ I II ~ f W ~ w o N~h~~ 11/2" P ~ I ~ ~I" ~ 0 I I ~ I S RVICE LINE I I I I 0 ~ ~ 835 I QWz ~ 4 ~ I~1 II ~ 767 ~ ICI p, Hse ;I 1 I w J~~ ~ ~ Hse I ~ ~ I~I kl ~JI I F- ~ o ICI ~;I I ~ I I W I ~I` ~ I I 6!I, = Qz~ ~ Z o W ~ ~ ~ I o - ~ ' I ~ I NEW SERVICE LINE I / k I I ' ICI ~ ~ ~ ~ ~ ~ W!I I ~k Im ~ LL ~ I~ v, ~ VALVE ASSEMBLY, of I N ~ I~ I ! ` ~ ~ i ' ~ I (SEE DETAIL TYP.) ,o ~k cn ~ ~ to = I I I; ~ / ~ ;101 I ' to I I / / ~ O W ~ I to ~ 4/ II~1 la ~Is o n ~ I ~I~ ~ ~ do ~ sl I + W ~ ICI' I j Ex. Headwall f 4 F l o °o I I leach srdel I lI~I ~ _ _ _ _ _ _ _ - ~ - - R/W I ° --I--- W I I ~ I 1 --~j I I ~ Ex, 6" Water Lrnr ~ ~ ~ W . `lNl -x, 6" Woter Line (n •M M 1 O M M M ~ W N lAs halt Pavement) Albemarle Church Road lSR 1200 ,d. P ~ N W O Q ~ ~ r~--I ~ Ili I9~ ~ CO ~ ~ ~ ~ w `~•~~cb (n cv z~~ W Z I NEW 4" IN-LINE . F J i NEW 4" PVC FORCE MAIN w ~ m t Woods Z ~ - o = CLEANOUT Bch ASSEMBLY ~ (5 OFF EOP, TYP.) ~ _ U F- J ~ U N ~ rc U m Q ~ o az~ M F- U ~ Q z ~ ~ r~ Z - ~ x b,Tj~,S~'+~,~',{~t S, Z tO ~t W~ Q C M d ¢ O O ~ ~ ~ C 00 O N N ~ T ~ O Z m ~ _ t ~ ~ ~ W ~ W ` 2 W z ~ O N U' ~ 5 - - - - - Ex. Grode 5 w Ex, Grode - - - - - - 3' 3• #I . C VER C VER N W 4" PVC 0 a z_ 0 0 J a U 2 O Z N -5 -5 Zoo T~ ~~o Nz ~ o H~ W ~ U U ~ V F-- -10 -~o + + 53+00 54+00 55+00 56+00 ~ ~ W O ~ ~ 42+00 43+00 44+00 45+00 46+00 47+00 48+00 49+00 50+00 51+00 ~1 00 52 00 U ~ _ _ ~ mUO~ w o~ Q~°o ~ a~ I W I T F 5 ~r~+ v~ a II :I W (n ~ m STKF~'M 1MP~ CT 2~ j~ ~ m o f ~ w z a cn Ik .k k. T W to W ~n ~s I Z = I~ I I I I i ~ W ~ ~ ~ ~ ICI ~ ~ - ~ O I I ICI I N J ~ a = ~ J Z 1 ~ I ~ ICI ~ rn E- 0 c o l ! i a l EW o I ~ ~ [1 ~ i0 W ~ l ~ I C I ~ ~I N 11,25 BEND ~ o o, W cr ~ I ~ I I NEW 22,5 BEND i-- ~ z Ex. 6"Water Line M ~-I,x ~ 6; -M M M M I M M Ex. 6" Wafer Line M ~ ~ M O ~ i I~ 0 O + ~ Albemarle Church Road tSR 1200 o O OPEN CUT lAspholt PovementJ o N w O + ~ ~ ~ ~ n~ ~ ~ >-r,--c M~ Ili ~ 11~ I~i Q ~ i _ I - - - .~~,o~ to ~ ~ `o ~ of ~ W NEW 4" PVC FORCE MAIN o \ ~~,,o, I ~ I I o~ ~ NEW 3" PVG FORCE MAIN Z ~ NEW SERVICE LINE J - ° w I-- ~ ~ ~ PERM ENT ti ~ ~ ~I m Z (5 OFF EOP, TYP.) 3 NEW 22.5 BENDS p ~ ~ ~ ~ .J 4 \ EASE NT, TYP~~ , woods ~ ~ ~ ~ VALVE ASSEMBLY. (5' OFF EOP, TYP.) _ ~ o ~ (SEE DETAIL,TYP.} ~ = NEW 4" x 4" x3" TEE co ~ • o U ~ - Hse Q NEW 3" PLUG VALVE & BOX ~ Hse X Hse Q ~ Woods \ \ ~ ~ ~ 2 fi p woods ~ ~ p ~ ' ' o ~ o~ ~ ~ -c p ~ ~ s`~~. NEW 2" Pvc ` ` ~ SERVICE LINE ~ O 0 0 ~ ~ o (Approx. 900 LF ~ ~ to house} woods N W ~ ~ ~ , ~ ~ ~ NEW 3" PVC FORCE MAIN 1224 (SEE SHEET 76) N Nse a, O DESIGNED BY. ~ ~ WBJ DRAWN BY. a~ TK 1 EJB 3 0 ~ a 0 CHECKED BY: 1 O WBJ m 10 ~ ~ g PROJECT NO.. 2a1s~6 ~ ~ i N ~ ~ ~ i DATE: _ / ~ _Ex. rode AUG 2007 ~ i - - 5 - - - - 5 SCALE: ~ N Ex ade '1 ~ - " M N. HORZ 1" = 50' ~p C x. er m n VERT 1 ° = 50' NW ~ ~ MIN. ~ ~ 0 O SHEET OF 95 ~ 70 LF 0 DI PI E NE 4" x " x3" EE Q) Q, NEW 3" LUG VALVE & BO o Q) ~ o -5 70 -5 ~NCl- 56+00 57+00 58+00 59+00 60+00 61+00 62+00 63+00 64+00 65+00 ~5+00 66+00 67+00 68+00 69+00 70+00 ~ I I ~ NEW 3 P~'C FORC MAIN ~ ~ ~ I ~ I~ EE SHEET 21) /~J f - - I ` , ~ r - I , Woods _ I I~ I~ I ~ . ~ 0 ~ r ~ ~ NEW 2 PVC FORCE MAIN NEW TERMINAL CLEANOUT Z ' ~ /y~ ~I 1 r (5' OFF EDGE OF GRAVEL/ . `V ~ 53 ~ 1 I ASSEMBLY Z 3 Hse / SOIL R TYP.) ~ I N (END STA.9+10±) 0 1 y ~ ~ ~ l 11/2" PVC ~ o I ! ~ WER S V ° ~ 2 - NE ' 3 -4 . BENDS I / NEW 3x2 RED CER o . ~ ~ 1 o ~I i ??^^yV V~ N~ a I NEW "PVC FORGE M N 1 EW 3"x3"x3 TEE s I ~ r r r N o , c l ? ~ 5' OF : EDG OF GRAY W SERVICE LIN / NEW 3" PL VALV I w , , o / ~ O ,1 ill W W ~ Z ~ t QJy cn 1 r I SOIL YP.) ~ ALVE ASSEMBLY ,~o, & BOX 1 ~ I r (SEE DE L TYP.) / ~i0~~oi Woods ~ Z t~' BEGIN S A , I / W /G`r ~ ~ id J~V oC II ~,r Gro1e/Dr` QZ~ ~ ~ 10 ~ - (Gravel/Sorl Roodl - - - _ 1~ I ~ l ~ ~ n+ O i - a a ~ ~ D_ M -o~E CUT ~ , ~ I q , - M a ~ ~ , ~ . ~ N_ _ _ B a ~ ~ / C~ LL _ I c~ ~ lh 1 I ,ti o I . ~ - ~ Nor ~h I ~ ~ o~< o o ~ \ I ~ , C~ I li 1 - Ex' 6 it / \ Io I ~ ~ ~ O ~ 1 _4,~~ ~ T ` . / _ o i ~ I / / ~ _ - `iii i~ ~ \ I I ~ END OF ASPHALT / 1 ~ ~ M , 1/2 P1~G___ l a ~ ~ ~ ~ ~ 11/2"~PV~'~ A 20' TYRRELL COUNTY PERMANENT UTILITY EASEMENT a SEWER ~ERVICE CENTERED ON THE FORCE MAIN EXISTS ALONG THE UTILITY ~ Hse / t l ~ ~ I PAVEMENT & / 1 ,~z ~ a r ~ ' EW R SERVICE ` I I 1• o kl NCDOT R/W / ~ ICI ~ Hse I r ~ H / o ~ I p tis° ard9 WHERE IT IS OUTSIDE NCDOT ROAD RIGHT-OF-WAY. THIS ~ ~ ~ ~ I 1m ~ I ~1/2 VC I 1 ~ ~ i + EASEMENT WILL ALSO SERVE AS THE CONSTRUCTION ~ ~ +'1 10~ 773 X ~ ~ ~ ~ ~ 1 EWE SERVIC Hse I r ~ c~ 1 I ~ ~ I Hse /y~/'~(7 LIMITS FOR THE WORK IN THESE AREAS. ~ ~ ~ ~ L~ ~ ~ ~ ~ r ~ p Hse ~ 3 1.7 W ~ ~ 1 I ~ ~ ~ Bld ~ g ~ ~ ~ ~ i' ~ r I \ 112 n ~ , ~ ~ ~ 773 ~ 81dg Hse 11/2 PVC ~ 1 1/2" PVC 1~~/ ~ ~ N `3 ~ ~ 1 ~ `J 1'rlr ~ \ SEWER SERVICE ~ Q ~ ~ ~ ~ z W ~ 1 T ~ / ~ ~ 11/2" PVG ~ ~ ~ ?ti ~ SEWER SERVI ' 1 ~ ! ER SERVICE ~ - - f _ m 1 ~ J' ~ ~ ~ ~ ~ ~ 1 ll~' I~ ~ V N W ~,(1~{ ` Hse ~ 1 1 ~ l1' IL ~ v M -~omo (l-' Cl-~ I O a z ~ • l ~ U ~ ~ - J - / ~ ~ ` ~ ~ ' I ~ Q a ¢ o . . _ 1 . / - ~ 1 I r ~ J i 1 1 '\'/f Q c co O tQ N 1 C7 ~ O Z CJ ~ L ~ K W ~ W ~ = W Z z ° N ~ J _ (7 ~ w z 10 _ - - ~ 3~-0° U W rode r ~ CAVE ~ ~ Z D7 + ORC ~w Q i NW ~ w Z ~ - - - 5 a U W 2 ~ AIN AIN o o ~ Z N Z Q E N ~ °z 0 ~ N W 3'x2" R DUCE W NEW 3" PL G V VE ~ ~ = J r ~ pQ~o VU ZoO~. Z ~ ~ Z ~ ~ ~ NW QQZIa- -5 0+00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 3+00 9+ao 10+00 ° W } w ~ ~ o cn U p ~ i • ~ NW ~o~o I oW UoOo Z~> UQ x ~ ~ m ~ 3 l ~ ~ 4. ~ ~ ~ H- ~ N (n 0" ~ ~ o i o a~ ? M ~ ~ - ~ ~ oW[ Q ~ i ~ ~ o II ~ F- ~ Z ~ ~ Iii o SDI ~ ~ C ~ ~ ~ ~i C7 ~ z ~i 2 ~ ~ ~ ~ 1 ~ r w elPf ~ NEW 3"x 3"x3" TEE J era ~ NEW 3" PLUG VALVE & BOX ii Z ~ 0 -R/W N - m °C --A - ; ~ f - o- cn ° w w ~ w ---I ~ d 3 ° Ex• 6" Woter Line w w- a w w w ~ w w D ~ 1 0 , ~ 1 ~ ° w Foll Landin SR X204 (Asphalt Pavement) ~ NW Y 9 o ~ ~ .P ~ -I- ~ ~ FY , ? --F11 U FII Fll Fll FW ~ ~ ~ ~ a T o ~ Grovel D ~ , , Z ~ N - 1 ` I 1 _ I I 0-- i - . ~ T ~T. R/W ~ ~ m ~ 4 o a o~ l a \`~^o~ Woods ~ ~ ~ ~ CDC ~ I ~ I i i I 81dg I o _ , NEW 3 PVC FORCE MAIN a.~ a` . . . ~ / ~ o I ~ ~ o - (5' OFF EOP TYP.) m ~ I z ~ I ~ 0 `ch \ ~ ` ~ . ` ~ l i I 0 , rn gld9 i _ I 0 ~ m ~ 1 Woods woods ~ EX. 36" CMP Cn ~ I USE CONDITION 2 ~ ' Apr _ ~ Gr°ve ' S !w ~ (SEE INSTALLATION DETAIL) ~ C ~ 60 ~ - N gid9 ~ Grovel O STR~~M iMP~c't' l0- l°l N ~ , . DESIGNED BY: WBJ DRAWN BY: TK/EJB CHECKED BY. 5 wBJ m 5 _ \ ~ Ex. Gra e PROJECT NO.. - - - - - - - - - - 2876.8 ~ - - - N " ~ IN. Ex. 36' CMP DATE: ~ W 3" PVC ORCE MAI N ORCE MAIN AUG 2007 0 ~N - Q SCALE; ~ ~ MAN. HOAZ 1" = 50' rn~ VERT 1" = 50' ~ ~ .o ~ U u n n W V O EW 5 LF C NCRE E _ 5 SHEET 74 of 95 -5 NCAS MENT C) O ~ ~o c~ -10 74 -10 .o 0+00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 9+00 C,) 9+00 10+00 11+00 12+00 13+00 14+00 Z 'n Z Vp~ WV Scrub 'C ~ Q ~ N Woods ~ W W F ZO W ~WN ~ Woods " L~ J H ~ ~ Woods O Woods Woods V ~ ~ a~~ Scrub = Z Q n ~ w . ~ o I- ~ LL s W i O p ~ i O ~ V. R/W W - W m - 3 w i w ~ w w Ex, 6" t water Lfne w N w w ~ - w ° Doven ort Road ASR '20 ~ p f PovemenfJ v N w p 5 IAS ha. O O N ~ ~ ~ ~w ~u ~ -I- o~ Z FN FM ' o - - - - ~ w 0 i R/w g- Q ~ cn NEW 3" PVC FORCE MAIN N (5' OFF EOP TYP,) • ~ ~ ~ • • • • . , R1 ~ . m ~ ~ ~ W N Z ~ ~ z w ~ Q ~o _ ~ _ m U ~ ~ ~ M li WOOdS U N ~ m Q O Q Z ~ -L Om0 ~ U ~ ~:~~:~~~T,. Z z ~;;rr;..,,ti~,~ Q C M o ~~o O tCU N Ur T ~ O Z 00 ~ L ~ ~ ` W W ~ ' w z z o N C7 .--i 10 10 z W a z 5 _ ~a------- - 5 J - IN. 1 ~ ~ - - - - r-- - ~ - - - x_r 2 ~ C F - OCEM ~ p O ~ z N i 0 0 N~ ~ 0 0 O a. ~ z z ~n U~ W ~ -10 _5 ~ 'a 0 oW 28+00 29+00 30+00 31+00 32+00 33+DO 34+00 35+00 36+00 37+00 '+00 38+00 39+00 40+00 41+00 U ~ c~n ~ p ~ w~ ~ ~W QcW W N U S w~ ~Q S ~ ~ ¢ ~ ~ c~n - n a M S ~k W P ~ , S o m ~ z ~ z t~ .E ~ woods w ~ , G ~ 60 N ~ P ~ . ~ ~G 0~ N fJ? ~ i ~ o • Woods /Wetlands ~ o ~ -NEW ~ ,22.5 R/W _ k ~ BENDS ~ _ ~ ~ o ~ \ ~n 0 co ~ p ~ ~ ~ ~ NCDOT STATE ~ ~ w ~ . ~ MAINTENANCE 1~ ~ - ~ w - - ~ " m ~ I ENDS ~ _ R o ~ c (Soil o _ ` "j/Soil Rood - - ~y1 m m - odJ w o _ - ~ ~ w Woter Line _ _ " (Gr_°ve ' (,J) OPEN ~ ~ w 1 ~ ° woods ~ CUT oo ~ -D------------------ _ - _ _ - " m ~ ~ a~e ~ ~ ~ ~ ~ c~ Q - _ - o NEW 3 -90 BEND ro w~ N G\ ~ ~ ~ ~enport R°ad o Da EW 3" PLUG VALVE ~ m ' ' ~ O ~Q` ~ &BX ~ I \ a` . . 0 m W ° ~ • _ .t NE 3 PVC FORCE MAIN ~ (5' OFF EOR, TYP.) Q '~o. i Woods /Wetlands ~ ,\c C ~,h NOTE 0~ A 20'TYRRELL COUNTY PERMANENT UTILITY EASEMENT CENTERED ON THE FORCE MAIN EXISTS ALONG THE UTILITY N ~ WHERE IT IS OUTSIDE NCDOT ROAD RIGHT-OF-WAY. THIS O EASEMENT WILL ALSO SERVE AS THE CONSTRUCTION LIMITS FOR THE WORK IN THESE AREAS. a~ DESIGNED BY. ' ~ O~f1 MP~c.T WBJ DRAWN BY; TK/ EJB CHECKED BY. m 5 5 WBJ Ex, Gr de ~ ~ - - ~ ~ Ex. rode r\ - PROJECT NO.: ~ _ - ~ ~ 2876•B N - DATE; ~0 _ - ~ - II C AUG 2007 0 3 P ~ N NEW 3~~ p C 0 SCALE, HORZ 1" = 50' VERT 1" = 50' ~o ~ ~ & OX i I SHEET OF g5 ' -5 0 M cO -~2 5 86 LF F 3" HDPE HORIZONTAL DIRECTION RILL O N cn O ~ ~ o 77 -10 -10 41+00 42+00 43+00 44+00 45+00 46+00 47+00 48+00 49+00 50+00 )+00 51+00 52+00 53+00 54+00 55+00 I I I ~ 9 I ~ I 1 I ~ ~ ~ ! ~ ~~y I C I I I I / y~~ z Z I I n- ~ I I woods-.~ 2- W 3 22.59 BENDS I I j ~-Woods-.1 / ~ ~9 Q ~ W 3'~ • G V BOX ' ' I l • I l i ~ ~ 1 , ` i I I ~ ~ ~k° Way Z o W o pWN N I I ~I_ ~ I I I I ~ ~--Woods . / ~Z J o ~ ~ I I ~ I ~-Woods ~ I I . • - I I Z o 1 I ~ I ~ I 1 _ _ r fly + I , I J ~ I m I o ~ I h , o ~ aunt D ~ ~ Raw I , r Fy aV/q~ _ o l. r- Ro I o ad -ems _ 1' ~ 1 I ~1 ~ CS / 'I' to. _ R , ~ l~ ~ _ 115 , I 1 I ~ 8~ 1 3 _ ~ o I a NEW 8" x 8"x 8" TEE I ~ ~ _ \ .y I I NEW 8 45 BEND , , ~ o w NEW 8"x3" REDUCER 1 I I NEW 3 PVC FORCE MAIN ~ I- N W ' ~ (5' OFF EOP, TYP.) ~ ~ a (BEGIN STA, 0+00) f _ (Asphalt PovementJ ~ ' w ~ ' ~ ~ I o R/W ` Fw ~ 1 t- m I~ I ~ ~~S - ~ - z U N I ~ ~ Hse _ _ I u ~ \x a~, M I ~ NEW 8 PVC FORCE MAIN ~ Iv ~ o U N ~ I (SEE SHEET 6) 1 v I ~ x~x \ ~ U M 1 l ~-woods-.~ _ ~ - 1 ~ r_ _ _ _ _ x Scrub ~ _ ! z z E~iri~j;'~ ~ y- Z ~ ~ Q ~ m x x \ 0 J Qo a ~\k~ r..r. 1 nra.., G CO O t0 N ~ ji o0 O 2 0] ~ - L ~ ~ i w W O w Z 2 d N C7 ~ 10 w ~o z Q z - - 5 CO ER _ _ Ex. ~ _ - 5 ~ . - a U p a NEW 3" P UG V VE BOX o o ~ T x Nv p ~a jo r ~ Q z p 0 U U ~ N -5 _5 ' Z d ~ ~ W ¢ 0+00 1+00 2+00 3+00 4+00 5+00 6+00 0+00 8+00 A+00 i+00 10+00 11+00 12+00 13+00 14+00 ~ ~ cn ~ O ~ W ~ Z H 1 w u '~I ,1 oC N~ ~ o '~I '1 '1 Q ~ ~ 0 ~ ~ ~ Q 1, . , 'i, Q ~ O frn . 1 1 \ \ . \ '1 ~ Nse ~ W - ~ (h 4. i 1 1 `1 ~-Woods 1 1 ,1 1 1 / ~1 1 1 ~ ~ ~ L _ ~--Woods-~ p Z 1 , '1 ~ \ ° ° ~ ~~yy ~ ~ i ' 4? ( J ~ ~ W 1 1 ,1 i 11 / p ~ ~ 1 1 Trlr i ' 1 \ i ~ c W I 1 \ \ ~ W 1 \ Woods '1 / / ~ 1 \ / ~ ~ ~i 1 \ ~ 1 / i 2 ~ ~4 i ~ ~ ~ ~ p ~ ~ W I W ~K - - }~-1-< - - - - - - - - - - - )-y----I~ - -~~r~~ ~ ~-x~~~Xx. Fence~~-x x - - - - - - - - - - W U / 1 3 r \ I I v \ ~ ~ ' ~ o ~ ~ O n - 0 ~ O t0 o w ~ ~v ~ ~ ~ lAs halt Pavement) N w ~ ~ Saint David Road CSR 11581 p ~ + ~ ~ 7enf) + N r U Fu Fu vw _ _ _ Q ~ I- tl ~ tl - - • , ~ ~ ~ o o ( ! W _ ~ `I i o M NEW 3" IN-LINE ~ Z Z , i CLEANOUT Z ~ J W ~ z ASSEMBLY ~ NEW 3 PVC FORCE MAIN m 'i 'i ~-Scrub w ~ 2 ~-woods (5 OFF EOP, TYP.) ~ ~-Woods-~ _ U c U ~i ~ ,1 '1 1~ ~ Woods-~ Q '1 a o ~ 1 '1 \ r~, ~A~1 1 MP~CT 2l~ DESIGNED BY. WBJ DRAWN BY. TK l EJB CLE OUT CHECKED BY. m 5 - - - - - - _ a - ASSE BLY i - !n 1, 0 5 wBJ ~ IN. ~ - - - - _ - - - - - - - - ~ x. rods PROJECT NO,. ' N - - - - - 2876-B N ~ ~ a 48' CMP ~ In 0.04 u DATE; ~ - . AUG 2007 ~I 0 Q SCALE; ~ ' ~ HORZ 1" = 50' OLFF VERT 1" = 50' ^o of ~ ~ ; s~-o~~ ~ I. _ 5 SHEET 79 OF 95 -5 n +I co + + O ~ O N 'o 95 L OF HDP HOR ZONT - _79- 10 N o 14+00 15+00 16+00 17+00 18+00 19+00 20+00 21+00 22+00 23+00 3+00 24+00 25+00 26+00 27+00 28+00 ~ ~ Z ti ('Wo 0 ao 2~ ~ a ~ Z W OJT W 2 CA ~--Woods o J~a c W W c~ ?~-Woods-.~ k°o a z ~ Z o _ a, ~ 3 o. O ~ - -I- ° ~ - - CO ~ ~w ~ Saint David - ~ _ _ a _ _ ~ ~ Road - - - ~ ~ , ~ ~ Z ASR 1 - 158) ~ ~ ° ~ ~ - _ _ (Aspho/f Poveme I ~ ~ ~ qtJ ~ Rte" ' _ W W - - _ Flu ~ ~ J ~ (~--woods - _ ~ W _ ~ ~ ~ NEW 3" IN-LINE - _ ~ ~u . ~ I- M V i i Ex. Gofes CLEANOUT I- i - - - . . . U N G d. W Q ~ ' ASSEMBLY ~ ~ - ~ ~ I m ~ ~ . ~ ~ ~ ~ ~ NE ~--Woods ~ ~ ~1 i i (5 NEW 3" PVC FORCE MAIN ~ ~ N (5' OFF EOP, TYP.) ~ ~ " M Q i ~ ~ ~ Z . ~ ~ ~ , ~ woods--.~ ~-Woods--.1 ~~~~~sr^'~ z - ~ ~ : W Z I- Q ~ ~ a ~o o _~N Ur T ~ O 2 m ~ - L ~ ~ ` w 111 O = LU z Z O N CS ti 10 W 10 z a - - - - x, roe Z - - - - - 5 a Q 3._ U Q CO ER H ~ N Z o2S 0 0 N > °i~ U ~ O N W 3' IN-LI E r~ UZ Z~ _5 ~ NQ ~ cn ~ ~ j -5 Z 56+00 57+00 58+00 59+00 60+00 61+00 62+00 63+00 64+00 65+00 5+00 66+00 67+00 68+00 69+00 70+00 ~U w ~ Q ~ N ~ t'y ~ ~cr W ~ ~ W o `-~'~J ~ .~G ~ Q ~ ~ Z~ ~Q ~ U /O~i ~ woods-.~ CONTRACT 2 CONTRACTOR SHALL tr Z Z LOCATE EX. 3" FORCE MAIN, EX. 3" z o ~ PLUG VALVE, EX. TEMPORARY PLUG o o NEW FLOW -NEW FLOW METER ~ ~ _ ~ ~ , ~ ~ ~ ~ U ~ & BLOCKING AND CONNECT NEW 3" ~ ? (STA. 77+8~ / NEW 3 IN LINE ~ p Q cn (STA. 77+88±) ~ / CLE OUT ~ ~ ~ ~ ~ w ~ o c~ ~ PVG FORCE MAIN. Z w (CONTRACT (CONTRACT 2) AS MBLY l~ w m J N ~-Woods * I ~ (V ~1 o.. ~ R/W ~ ~ ~ Woter (rne ~~F <1 _ _ ~ ` ~ `_~i ~ w ~ ° ~ 1158) 0 0 lSR vid Rodd ~ ~t, Saint Da C ° F11 m N ~ (Asphalt Poveme o, ~ o ~hape~ ~ r r ~ rr ~ H~IIRaa o ~ _ _ _ . _ ~ r . d ASR 1115) - w a' Q ~ . F1~ ~ ~ - ? r~ w 1 Vj ~ - t _ ~ _ _ _ _ ~ , a ~ NEW 3" PLUG o _ _ _ - - _ _ _ i ~ , NEW EQUIPMENT 1 BENT ~ o j r a l~_ ~ ~ ' ~ i o ~ VALVE & BOX RACK FOR METE uIETE r ~ r ~ i rr ~ r~ i ~ i ~ o ~ ~ NEW 3" PVC FORCE MA1N , ~ (SEE DETAJL) ~ ' O j' Bldg r- ~ ~ ~ - t _ , •I- i ~ ~ ~ , (CONTRACT 1) v (5 OFF EOP, TYP.) , ~ ~ / ~ Z ~ ~ ~ j' Bldg Nse ~ 1. ~--woods^y ~ 0 2 Ex. 42 CMP ~ ; 1 ~ r' ~ ~ / V j ~ ~ ~ 81d9 ~T ~ ~ ~ USE CONDITION 2 0.; Q~ ~ Q Tr/r ~ ? ~ ~ ~ ' ' 0 DETAIL) • / 0 (SEE INSTALLATI N , } , ~ ~ I I / X30 w ~ 1 ~ ~ ~--Woods l ~ o ~ _z ~ I I 1~~ I i ~ I S / ~ l~ ~-Woods-.1 J ~ , a~ 1 t (1 I ~ ~ , a~ x I' i 11 Q s ~ ~.i I r of ~ ~ C I Wooc ~ Ex, Gofes ~--woods--.~ a ~ Wi ,i 1 ~ r, I ~ ~K~ o IN1Q~cT h 1 2g IW ~ i IU~ . ~I ~OI ~-Woods I I ' ~ ~ W ~ DESIGNED BY. ~ w WBJ ~ w DRAWN BY. TK I EJB Jr CHECKED BY: 5 wBJ m ~ x. a e _ ~ - ~0 PROJECT NO.. 2876•B N IN. ~ - DATE: ~ - - - - Ex, c oa AUG 2007 ~ NE 3" VC F RCE AIN i - - ~ - x. N Q - x. O SCALE: HORZ 1" = 50' ~ VERT 1" = 50' 0 2. 0~~ 2~ o~~ ~V C EANO T ~ A SEMB Y - ~ SHEET 81 OF 95 -5 M / `IO Q O m CN o ENBASEMENT CSEE DE 81 10 -10 70+00 71+00 72+00 73+00 74+00 75+00 76+00 77+00 78+00 79+00 9+00 80+00 81+00 82+00 83+00 84+00 I j i i i I I I ~ I ~ j I I I f.~ ~ ~ns+ I I I I I I ~ I I ~ I I ' j I I I Nse ~ ~ I I ~ I I I I ' j l l I Z I I I ' O I i i j ~Q~ I I ,I I I - ~ j 0 I I I o. I I L- a I I ,il I ~ I I I I I ~//W~ I ~ ~ ~ ~ ~ ~ I I ~ I I WI t I ~ I ~ I - i o ~ ~ II ~ , I I o. i p I I I Q' ~ I I II I-'---_, Q I I j ~ I - j ~ ~ ~ O 's, ~ I I I j W I~- I 1 I I i ~ I I ~ I t ! 0 I I 0 1 I j I ~ 1'rlr I 0 1 J N N >•rlr I I I I I ~ Z W ~ ! I I 1 1 ~ ff ~ I ~ ! ~-woods I ~ 1 ~ I I h ~ / ~ I I ~ I~ I I I j I r I I I I C I L I ~ ~ I i i I ~FV ~ I-' i y p 0 0 ~ p ~j I I I~ QQ i ' I I I I I I I ~ ~ I j ~ I ~ I r I 11 I I I I j I I I I 1 ~ I I I ~ _ I ICI 1 I ~ I I I I I ~ ~ ~ i I I 10 Z Z 0 I ICI ~ ~-I I I x ~ I I I I I I ~ 11 I L I I I I I I I I kl I I IW ~ ~ ~1. ~ I ~ I I ~ I I~ ~ W; I I . I I I I I I I I I I I I I~ I I ~ I I Q I I ~ I r ~ I I ! I I ~ I I r I I Vi I I I I 0 I I 0 I I v' I II I I I I I I w I I ~,I I I I l~_ I I ' I I I I I ~ 11 Q I I I I ~ I I I I I I o. I I I o I i t l i = 1 1 I I I I I ~ O~ I I t; I I kl I I I I; I I I I I W' W I I kj I I I I I I I I W' I I l~ l I I I I ~ I a I I ' W ~ ~i I ~ >CI I I I I j W I I I I I--_ ! i to W~ I I o. I I I I I f ~ I I o I I I I kl I I ICI I I I I ICI I I ICjI a ~ I ILI I I ~ ~ / ~ I I 1 i I C I I C ~ I l ! 0 101 W' 101 ~ ~ I I `,1 I~ ! O I I I I ~ I I ~I ~ j I~I I I o ~ I~I it ~ III ml I°I It01 1<I ~ I I;I I N 14 I ~ rry~, o! I~ 1 0/ j ~ V I I ~ I I m I I ~ I I IoI I I~ I I~ I ~ I~ I I of W w Ivl ~ Ilml I' I 1 ~o r ~ o I lol Wt' lol lol ~ l o l o ! + ~ I ICI ~ ICI IC1 I N ~-Woods ` I ~ ~ I W 101 + '-`t 101 I I l / I ~ ! ~ -X X ~ R/W - ICI - ICI - - - I I - - ICI ~ IOI Ip~ I I~~ ~ I ~~II I W I I ~ I I I -~`-r-~'-j 1I o I I 1 1 I --n- ~ 1 - - - - - I ~.1 j T- I I Z )--~--I-( I i I T'T t r I ~ ' 1 ~ 1 ~ O i ~ I I Ex, 4" Water Line I ~ I I n w I 1 I w , ~ W 1 l ! ~ W ~ o 1 ~ F N O ! ~ ~ ` I w w W ~ U ~ ~ d- (Asphalt PovementJ ~ m o Cha el Hill Road fSR 77751 m _ W •-i ~ Q ~ m ~o P o Fw ~w ~ CL = - _ ~ ~ " N ~ M - - - - - - - - - - - - - - - _ O a z ~ W -.c omo• R/w w Z ~ z ~ ~ NEW 3" PVC FORCE MAIN J . {~T. _ J ~--scrub b ~-woods (5' OFF EOP, TYP.) _ ~--Woods ~ ~ 2 .TL~h ~ ~ ~ ~-Woods-~ ~~~~f' x W Z a~ y- a ~ M ~ ~-Scrub ~ U , O d Q O F- I Q I ~ C W I it ~ O ca N i ~ W O Z O] ~ - L ~ ~ a"i W O W 2 W z ~I z O L7 ~ W 5 Z 5 - - _ Ex, rode - Q _ - - - - Z it Ex. rade - J - - J - - r_ 0 0 o U Q 0 OR E M N ~ ~ Z N ~ ' _5 ao -5 ~ o + I, T N ~O Zr U _~o z -10 3+00 94+00 95+00 96+DO 97+00 98+00 ~ w } Q O + + 90+00 91+00 92+00 93+00 + 85+00 86+00 87+00 88 00 89 00 84 00 ~ ~ I I ~ N w W O I r } p W U+ I f i- Z~ mod' I I Q ~ 00 ~ oC u- w~ Q I I ~ ~ Q ~ ~ ~ I ~ ~ ~ II a - ~ I I i ! I Z M fl ~ I~ i I I O rl U W m ~ x ~ f I I ,0~ f l W Z ~ W I 1 I ~U ~ ~ o '1 ~ - _ _ _ _ - - - - - Ex, 4" Woter Line w ? - _ ~ 2-NEW 3"-22.5° BENDS rl r ~ 'W, ~ (7 ~ 1 0~ O _ - - w al _II o~ ~r_ w N N I II ~W ~O !I Ir ~L 0~ J ~T Z w ~ ~ W v Oo ~ ~ ~ Ir ~ r _ ~ J ~ w vemenf) _ - ~ - I ~ lSR 1115 lAspholt Pa ~ z ~ el Hill Road ~ ~ m N Cha I ~ 0o fn m o ty OPEN CUT ex, 8„ ' ' ~ ~ Woter ~;Re - .r ~ w o; o ~ 0 ~ ~ F11 - - _ ~ I ' ~ I O ~ ~ - ~ R/w . . rn ~ . p ~ ~ `may. _ _ _ _ - - - , . . . I ~ N U k ~--Woods /Wetlands ~ - p ~ : - 1 NEW 3 PVC FORCE MAIN ~ 2-Ex. 2~ ~ 2-Ex. 24" CMP \ 1 ~ ~ ~ ' I (5' OFF EOP, TYP.} I _ USE CONDI NEW 3 IN LINE USE CONDITION 2 ~ \ \ I ~~--scrub ~ Q N iQi (SEE INSTALLATION [ ~ m CLEANOUT ~ ~TALLATION DETAIL) \ I ~ ~ - . ~ ~ i W Woods 'w! ~ ASSEMBLY Woods /Wetlands--.1 i m I " 3"x3" TEI o ~1 NEW 3 x 3 x3 x3 TEE \ ~ ~--Woods /Wetlands I ~ NEW 3"-45° BENT ~ ~ x. 24" RCP ~ ~I NEW 3 PLUG 3"-45° BEND ~ \ o ~ ~ 3" PLUG VALVE & BOX ~ ~ \X N USE CONDITION 2 ~ (J) (SEE INSTALLATION DETAIL) a~ _ . N~ a~ ~ m m NEW 3" PVC FORCE MAIN \ ~ (SEE SHEET 84) N ST ~N1 plc s o IIM ~ O- \ ~ DESIGNED BY; WBJ o DRAWN BY: TK 1 EJB L a' CHECKED BY. 0 5 wBJ PROJECT NO.: m 2sls-B - DATE: N Ex Grade - - - - - - - - - - - - - _ _ 1- ~ ` - - - - - AUG 2007 - - ~ SCALE: 0 x' HORZ 1" = 50' of - N O MIN. W VERT 1" = 50' ~_o,~ ~ ' x.24" GP NE 3" VC ORCE MAIN ~ z~_ o a~ ~ 5 SHEET SZ OF 95 ~ - N W '3" IN-LIN NCAS MENT ~ ~.„~,.T I NCASI MEI 4 CPoVV ~ SEE ETP SEE DETAIL) LUG-VALVE & B N' NEW O 82 Q1 1o \ 0 -10 N +00 100+00 101+00 102+00 103+00 104+00 105+00 106+00 107+00 107+00 108+00 109+00 110+00 111+00 112+00 98+00 99 .o ~ I i I ~ Z Z I C~ W o I i i ~N~ I z W~~ ° ~ N ~ I rn O W cn ~k J~p ~ I' W 'O W I ,a ~ I fI) NEW 3" IN-LINE _ ~ ~ q ~ Z ~ W I CLEANOUT ~ _ - ~ ~ + ~ u~. ASSEMBLY , ~ - ' ~ LL W - - -6;_. _ f _ ~ - ~ I _ _ R/W cn - _ _ w ~ Q 1-_ _ O N ~ - ~ r (n w ~ I m Q - - ~ ~ r - - ~ _ _ ~ ~ , 8" Water ~ _ i, 1 ~ Goo/~, N i ~ ~i Q - ~ ~ w Lrne Cho ~ W W ' - - _ ~ pel Hill ~ o , i ~ _ T _ Roo w , ~ ~ d ement - Fw ASR _ '~'S~ (Asphalt Pav W R/W ' ~ m 2 ~ U N I ~ ~ ~ Hse z w ~ J - Fw ' ~ ~ Q F ~ 1 ~ ~ ~ _ o - •'Woods _ U ~ _ _ . _ ~ Woods J' ~-woods-.~ ~ ; ~ _ ~ ~ ,i ~ ~ NEW 3" PVC FORCE MAIN Q ~ Ex. 24 C 1 ~ U N ~ (5 OFF EOP, TYP.) USE CON[ Im USE CONDITION 2 !W~ Ex. Sateuite ~ a (SEE INSl to (SEE INSTALLATION DETAIL) i ~ Dish ~ Q; U ~ ~--Scrub 'I~ I ! '~~'Fr'~.''y ~ Z ~ m ~1 z ~s»- 1 ~ Q a ¢ o ~ O _ccv ~ V. T ~ O Z CO ~ L ~ ~ W w o T W ~ y Z o N (7 ~ w 5 Z 5 1 Ex. Gr de ~ ~ Z Ex. Gra e _ ~ ~ - - - - .r - - - - - _ - Y 1 O O LJ. ~ - Q U Q Q IN. ~ MIN. °C O EW PV FORE M _ Z N ~ _5 N~ o~ - NEW 5 l NEW 5 LF CON RETE ~ + ENC SEM ENC SEME T ~ ~ ~ r I- U U -1O ~ , z d ~ ~W acn -10 + 118+00 119+00 120+00 121+00 + 113+00 114+00 115+00 116 00 117 00 21+00 122+00 123+00 124+00 125+00 126+00 ~ w ~ ~ ~ cn Z I- J 112 00 ~ ~w ~O i ~ ~ + ow ~ ~ Ur > > ~-•Wetlands ~ w ~ r ~ ~ ~ ~ I- , m ~ i i ~ ~ / ~ ~ ~ W ~ ~ f ~ W '.fo ~ / ~ ~ ~ ~-woods i~ i / ~ \ , Q ~ ~ H _ ~ I ~ ~ ~t ~ l ~ ! ~ ~ ~ ~ ~ ~ ~`-"Woods-~ ~ ~ ~ ~ ~ i f!3 a ~ r _ ,o~ ~ ~ ~ w ~ ~ ~ ~ - / I / o W ~ c~ ~~T - - _ _ R/W - - o ~ `o ~ ~ J ~ J W ° _ ~ ~~J ~ ~ \ cWn ~-Scrub -.,1 _ ~ ~ W Ex. 6 Water Line 3 o -T}-~~ ~ i~ w i ~ ; ~ Q W \ ~ 1\ n w - I / ~ + Cho el Hill Ro 4 - w ° P od lSR 77 FM 15~ (As halt Povem ~ ~ ~ ~ w A entJ N U V V V ~ / r _ - ~ ~ FM <h ~ ~ o~ h ~ < I I o ~ r \ ` ~ tD • _ _ - ~ o 0 ~ I ~ I ~ o Iol j o+ ~ W ~-Woods / Wetlonds I ` I = ~ ~ Z ' ~ I i 1 r NEW 3" PVC FORCE MAIN z • ~ ' ~ ~-woods ~ s , l of ~ NEW 3" TERMINAL I J I I m ~ ~ Q v ~ , I j I (5 OFF EOP, TYPJ w ~ r ~ ~ ~ w ° ; ~ I CLEANOUT ASSEMBLY 2 I ~ m I U x. 24" CMP ~ I I I ~ N ~ ~ ~ J 1 ' (END STA. 136+50~ f - ~ I I 0 ~ I I ~ W ~-Woods ~ ~ I~ : o / ~ I ~I Q USE CONDITION 2 I , r .I ~ ~ ~ (SEE INSTALLATION DETAIL) ' I ~ I 1 ~ ~ ~ ~ i I j ~ I `l ~ / ~ ~ I II 0 1 I I ,i \ 1 ~ I ~ J ~ G~ 2 ti'~P ~ s4 I I I I ~1 I I • \ l I I ~ ~ ~ I ~ ~ ~ I ~ ~ I TAI( 1\ \ ~ ~ o DESIGNED BY. WBJ a~ ' DRAWN BY; TK / EJB ~ n3, x. a e. ~ - - - - - (EN STA, 136+5 ~ CHECKED BY. ~ ~ r O WBJ V1 PROJECT NO.; ~l O MI . 54' CMP 2 Ex. 54" CMP 2876.8 ~ N W 3" PVC ORCE MAIN -Ex.54 cMP r\ DATE; ~ MIN. N 60 AUG 2007 ~ 3° ~ - 5 SCALE; HORZ 1" = 50' ~I -5 VERT 1" = 50' ~ 6._ ~ ~ E CASE ENT (T ~P.) o (S E DE AIL) -10 rn~ ~ r SHEET S3 OF 95 °i - 10 L M Q 240 T UV O ~ O ~ N o -15 ce) c' QL- 131+00 132+00 133+00 134+00 N 126+00 127+00 128+00 129+00 130+00 134+00 135+00 136+00 137+00 o~~ 125+00 Z Z ~Wo Way z W p ~~z > J o W ~ ~ aZ~ zo - / / ~ / 1 , i l I ~ ,/l~~! ~ 1 / W ~ NEW 6 PVC FORCE MAIN 1 ~i-~ ~ ,l ~ r ~ (SEE SHEET 16) ~ i ~i~li i~ lll~ I ~ N U d' W ~ ~ r ~-i~%, i ~ l ' i ~ MANHOLE N0.3 F I m - o ~ ~ ~ i ~ ~'/i ~i i h I ~ MANHOLE N0, 4 _ ~ m C V N ~ ~ ~ OLE N0.2 ~ _ I ;~i ~ r; ~ ° l f 1 STA, 3+92,6, ~ ~ ; G cc V m C z ~ i ~ ~ s'TEMPORARY ~ ~ X185 485 ~ STA~5+78,65 STA. 0+49,15 ~ i ra ~ ~ { ~ ~ ` ~ TION ~~i''i /io l 1 ~ ~ ~ 67 30 33 ~ i , „ CONSTRUC „w, ~ i/ ~ n ~ i - L OMO I ~ X270 23 05 , , / f ~ ~h, , ~ ~ EASEMENT ~ ~ ~ / ti _ U ~ CH SIDE Ex. 6 Water Li----M /i / ~ MAINTAIN 10' MIN• ~ I ~ ~ ' _ ~ - - 1 i- v I I r M _ _ -1~ / E I SEP TION ~ ii a. st~~ z ~ ~Y ~A I - lGravel/Soil PofhJ _ •t • - • ~ . ~ / / ~ a.Y.~~ z M C ~ a ¢ o O J ' c o0 G.,~,.,._ - - - ~ vel/Soil -1. O tQ N ~ T ~ _ - - _d'_, ~ I '1=~ ._l~ --t- - -Ex ep~ie-~anlc ~ ~6iG = - ~ _ 11 III I ~ X~x x_L x. Fenc O Z m ,~.I - rr ,I- L' 1 •.~:.y_,_... a u+ r x ~ ~ x _ 0 L ~ ~ i~ W ~ ~ J I ~ ~~IlI - 11 I ~ I O W = W Z '"III ~ ~ i I tll! 1 I / ~ I i~~(( ,illi I f 1 N0.1 20 PERMANENT ~I MANHOLE ~ ,r I ~ ~ Ex. Valve Vaulty Z O N C7 .-i + ~~~,~p ~ UTILITY EASEMENT . ~ ~~llr ~Illi ~ Ix ~ ~ ~ I , STA. 0 10.00 ,iii i I Z I ~ ~ ,lf ur I 1 Ex. LPP Pump Tonk i , ~ ~ i I (6 0 l Da l~ ~ I llll l u ~ ~ 1 i _ - ~~~p ~ ~ , ~i r ~ ~ STA. 5 88.65 W ~ ICI X ~ ~ ~r r111 I I ~ ! ~ i m rll 1n1 Im ~ ~ I ~ ~ x Ex• Spray Fields Ex. ControlPanel \ NEW PUMP STATIpN ~ ! I I 1. I ~ STA, 0+00,00 I I ~ ~I ~o Q Z (SEE SITEPLAN SHEET N0.90) i k x J ~W i ° U NEW 4" PVC FORCE MAIN 2 (SEE SHEET 16) ~ 1'INQ C. ~T1 3 3 2 O Z N N ~ Q ~ J W N Z W Z 0 W U N~ ~ k 0 w Z ~ W} ~o 4 QI >z ~ wW ~w I rr o w C'3 Z ~ Z cn O ~U a ~ _ w ~ z z C U U 20 ° J 20 J W 0 ~ Z 15 a 15 o~ ~ ~ ~ ~ + J ~ (0 fd Z O 00 ~ I 10 0 10 W ~o ~ o~nw W d a. a~ w ~ z ~ rn ~ w ~ _ a ~ I- - - = r PIPE INST LATI N. PR VIDE INK S AL 5 ° ~ ~ TO AKE ATER IGHT. 5 - . ~ FOFB P , ~ SE ~ O E .Star Drain Ex, 6' Water ne ~ I 0 ~ ~ u ~ N ~ For e Moin IN. z - ~ 12~, VC AVI - ~ MIN. o o z _ ~ DESIGNED BY. ~ ~ N O 5 WBJ DRAWN BY. L . TK 1 EJB 3 N Z ~ ~ ~ - CHECKED BY: i• _ 1 O WBJ 10 LF OF 8' GRA ITY ~ z z ~ ° z- PROJECT NO,: 2876•B ~ > N z DATE; ~ o o AUG 2007 ~ N ~i RAVIT SE R ~ .0% -15 SCALE: N -1 , HORZ 1" = 50' ~ w ? ~ ~ > VERT 1" = 50' N o m- o~ 20 SHEET 85 OF 95 L -20 O ~ CNa 85 -25 -25 +00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 0 i Z Z ~WO Way Z 11' MIN. W p SEPARATION I- ~WN > ~ 2 -NEW 4"-45° BENDS W J~o w ~ U 00 Ex. 5'x5' CULVERT ~ USE CONDITION 3 c= QZ~ W (SEE INSTALLATION DETAIL) Tr/r NEW 6" PVC WATER LINE ~ Z LL W ~ W = 15 LF OF SILT FENCE w woods-~ N (APPROX. 20' SEPARATION, TYP.) o ~ ~ ~ Q, 0 48" Oak 48" Oak 48" Oak o °o W W - - - - - - - - - - - - W W i i ~ ioi W ~ , W W ' ~ Ex, Difch r Ex, Ditch W W O O i i O FM F FM FM FM - FAI FM FM FM ~ 00 q p N• N (Asphalt Pavement) Nl~ 1-74{ 94 ~l~Ol11~W~ Y Q ~ W (A ~ AIR RELEASE W NEW 4" PVC FORCE MAIN W ~N _ z~~ Z 2 -NEW 4"-45° BENDS MANHOLE No. 2 , Z W~ .J ~ ~ o J (5 OFF EOP, TYP.) = Ex, Heodwall _ ~ m U U N ~ U 5 LF OF SILT FENCE ~ U n7 ~ 1 Q „ 4 Z d' a iuiintl~~rrty' W Z ~ ~ Q C M O J a ~7 t! d Q O C 00 O ca N N C7 T W O Z m ~ Zp t ~ CC i WW~+ W W O W O r~ 2 W z 2 O N d C7 1 ~ a 10 Z W - - - C VER Q NEW 4" P C FO CE M I Z 5 o z 5 a U 2 0 W 0 0 ZN~p o ~ ~ LL ~ r~ ~ ~ ° d- Q U _5 Z ~wZ~ -5 28+00 29+00 30+00 31+00 32+00 33+00 34+00 35+00 36+00 37+00 ~+00 38+00 39+00 40+00 41+00 42+00 ~ w } ~ _ ~ w ~~WVo ~ ~wZZo ~ ~ W J o+0 ~ N Z fn ~ S w ~ F' Q r ~~Q ~ 2 a ~ m Z T E cT ~9 - 31 5 ~ i~PAc 0 o~ ~ ~ _ ~ w ~ ~ W ~ ° ~ ~ Z o ~ ~ w d~ ~ a 2 , PROVIDE NEW FIRE 2 -NEW 6 •2 -NEW 6"-45° BENDS ~ HYDRANT ASSEMBLY ~ ~ ° NEW 6" GATE VALVE o = 2 NEW 4 -45 BENDS 2 2 -NEW 6" ` ~ ~ W FM N I- _ W ° 45' ~ 2 NE 6 45 BENDS „ 45° BENDS Ex,.o~t~-"-~~"~~~ J ~ ~ W NEW 6 PVC WATER LINE ~ W (APPROX.11' SEPARATION, TYP.) ~ ~ - ~ 15 LF o ~-~_----=-~~'w FM N 3 ~ OF SILT ~ • ~ g _ _ - a o FENCE ~ o - - - - - - m Q o o - w- W FM ~ I + • W N Ex. Di~~h------------------•--------------------------------------------------------------•---------------------------------------- ~ ~ - - w w w w FM N Q - ~ FM FM ~ ~ FM FM FM A ~ ' ~ W (Asphalt PovementJ NC Hw 94 R/W1 30 LF OF SILT FENCE _ Y o z ~ J 30 LF OF 2 - = 30 LF OF SILT FENCE 2 -NEW 4"-45° BENDS V ° NEW 4" PLUG VALVE SILT FENCE ~ 2 -NEW 4 45 BENDS NEW 4" PVC FORCE MAIN ~ ~ 2 _ E _ ° Q Ex, Headwall 11' MIN. (5 OFF EOP, TYP.) ~ ~ SEPARATION Ex. 5'x5' CULVERT Ex. 5'x5' CULVERT USE CONDITION 3 USE CONDITION 3 (SEE INSTALLATION DETAIL) (SEE INSTALLATION DETAIL) 0 DESIGNED BY; WBJ L DRAWN BY; TK/EJB 3 N Grcde CHECKED BY; EX. ~ WBJ m 10 r~ - _ - J PROJECT NO.; - - - - - - - - 2876-B N ~ 3' p~~ DATE; co VER ~ AUG 2007 N 5 5 SCALE; ~ HORZ 1 ° = 50' VERT 1 ° = 50' rn 3 N W 4" PLUG VALV 00 0 SHEET 87 OF 95 "V co V O -5 87 -5 N 42+00 43+00 44+00 45+00 46+00 47+00 48+00 49+00 50+00 51+00 1+00 52+00 53+00 54+00 55+00 56+00 t 1 Appendix B Site Coordinates 1 t Stream Coordinates County Stream # Stream Name Latitude Longitude Washington Co. 1-3 UT of Scuppernong River N 35° 52.830' W 76° 22.574' Washington Co. 2-4 UT of Scuppernong River N 35° 53.000' W 76° 22.192' Tyrrell Co. 3-5 UT of Scuppernong River N 35° 53.273' W 76° 21.624' Tyrrell Co. 4-6 UT of Scuppernong River N 35° 53.444' W 76° 21.303' Tyrrell Co. 5-8 UT of Scuppernong River N 35° 53.428' W 76° 20.604' Tyrrell Co. 6-10 UT of Scuppernong River N 35° 53.855' W 76° 19.638' Tyrrell Co. 7-13 UT of Scuppernong River N 35° 54.411' W 76° 17.630' Tyrrell Co. 8-14 UT of Scuppernong River N 35° 54.173' W 76° 17.349' Tyrrell Co. 9-16 UT of Scuppernong River N 35° 54.182' W 76° 16.976' Tyrrell Co. 10-19 UT of Scuppernong River N 35° 55.982' W 76° 19.787' Tyrrell Co. 11-20 UT of Scuppernong River N 35° 55.006' W 76° 20.084' Tyrrell Co. 12-22 UT of Scuppernong River N 35° 55.894' W 76° 21.086' Tyrrell Co. 13-23 UT of Bunton Creek N 35° 55.760' W 76° 21.656' Tyrrell Co. 14-24 UT of Bunton Creek N 35° 55.138' W 76° 21.712' Tyrrell Co. 15-25 UT of Bunton Creek N 35° 55.050' W 76° 21.959' Tyrrell Co. 16-27 UT of Bunton Creek N 35° 54.528' W 76° 22.385' Tyrrell Co. 17-28 UT of Scuppernong River N 35° 52.543' W 76° 21.592' Tyrrell Co. 18-30 UT of Scuppernong River N 35° 53.933' W 76° 19.859' Washington Co. 19-31 UT of Scuppernong River N 35° 52.655' W 76° 24.365' Tyrrell Co. 20-32 UT of Scuppernong River N 35° 54.001' W 76° 20.260' Tyrrell Co. 21-33 UT of Scuppernong River N 35° 54.131' W 76° 19.861' Tyrrell Co. 22-34 UT of Scuppernong River N 35° 54.433' W 76° 19.409' Tyrrell Co. 23-36 UT of Scuppernong River N 35° 54.405' W 76° 18.506' Tyrrell Co. 24-37 UT of Scuppernong River N 35° 56.284' W 76° 20.622' Tyrrell Co. 25-40 UT of Scuppernong River N 35° 52.641' W 76° 21.484' Washington Co. 26-1 * UT of Scuppernong River N 35° 52.234' W 76° 22.722' Tyrrell Co. 27-7* UT of Scuppernong River N 35° 53.155' W 76° 20.746' Tyrrell Co. 28-9* UT of Scuppernong River N 35° 56.859' W 76° 19.861' Tyrrell Co. 29-18* UT of Scuppernong River N 35° 55.554' W 76° 19.555' Tyrrell Co. 30-46* UT of Scuppernong River N 35° 55.663' W 76° 19.746' Tyrrell Co. 31-47* UT of Bunton Creek N 35° 55.644' W 76° 21.603' Washington Co. 32-48* UT of Bunton Creek N 35° 54.125' W 76° 22.722' Streams to be directional! drilled t Appendix C SOILS MAPS & USGS MAPS OF PROJECT AREA ' I` `? r { LEGEND Al- 2" FORCE MAIN f': = 3" FORCE MAIN ff J?= ?- 4" FORCE MAIN ?._. 6" FORCE MAIN 8 FORCE MAIN 7 ` 6" WATER LINE s tree 'io,ict • 16-2 s le{>?sant , _ ? / tree Impo,t • STREAM IMPACTS •• STREAMS TO BE DIRECTIONALLY DRILLED'.': ( f .` ma=,< ?.?..?. COUNTY LINE ?'• - (Sre :Gem f , °r I f? I`? S C U P P E ? N (? -? (x ?'?? f - Stream. Imp t ? 2- (Stream -47 ? 64 -Stream Imrct • 1-3? . •Q --_ (Stream 3, \\ - 9 I • •> tream Imppact • 19-31 r (Stream 31> ? j Ft Karl.' ?Cet}? .• > '' ! -. St Davids tream Im r y, . C;em Ch (Stream 1)• Hlgh .. ? ( c ?. ! • • .? n i. -? -yi. .yL•- k *j s• I Bland 1 Wi - s o.x W) { - - y 00 SCa1 e 1 -.24 X 1 t t t 1 t t '? - LEGEND I 2" FORCE MAIN ? j 3" FORCE MAIN 4" FORCE MAIN j µ 6" FORCE MAIN ?? - 8" FORCE MAIN 4 6" WATER LINE STR EAM IM PACTS n?t -,ON ALLY DRILLED I V COUNTY LINE ati i r? t f f U L If iI 4 1 ? J1 _? C light - ol?Ot M1 4PA?h II Poia Llaht ?. 4 l ?@ of I,a I I Oui •ti•_...?_?.._? ?.._- S edm Im act 24737 rte.. . 1 `J ct • 10-19 -- _ ;76 (Stream.`.] -?' ly r Strea Imppact • 11-20 ?- f pp (Stream 20) `l- `., -r? (Streanl22)ct•12-2 ??- J Stream Impact • 13-23 = f r _ x ?SStr_am- `. _ .f 4-.t,74 2 W2 - ?h ``.. ,. - ? .Z ? r7 ?•r rte. _ - -+- ! _ f ( 1 ? -- - -? -_- / -Str m Impact • 30- ` _ - _ - • • x ...f -. (Stl 'am 46)•• - -' - - 4 4 Wetland 3 W3 as < act • 29-18 -?rlm !` h - _ 1 +% (Sere 1?)•• am tmp • 14-24 / s -`c (CtrearsJ- 74) 1 117) h f *?? Stream np?ct ,,,-2L -`::. - i. ?` _ 6 _ Z` .•; ` - • 1 (Stream • ?V`?;,? • _. 99 as - ` <? - Sc 113 -1:24.000 71 LEGEND j?pea2 2=3 - r. l y?%str?eam"'S4? - ? -- 2 " FORCE MAIN I 1f 7/?;Fj_r ? 3 " FORCE MAIN °` 4i 4" FORCE MAIN _?- 6" FORCE MAIN r 8 " FORCE MAIN 1 g •; . 6" WATER LINE ?pp sc °m?°Ca•a2cardenc 4trea( 132)ct • 0-?? ?E1L - ..,.?- •a n: ` x?? ?S teem 8M Impact • --STREAM IMPACTS _ . •• STREAMS TO BE DIRECTIONALLY DRILLED _ll ',hl - I?ji5; ?j --?- yi PIT6 Im 307 p act • 18-30 !,`Sf eetm n TY$Sr1S COUNTY LINE Stream Im aaE o ..' 1 1117 (Stream f s S 'y' am act • 28-9 _ ,R It' t t 5 .,- - S. I. f f/• 0 k N ' t Ch?AP L HILL'F10AD- SIR .t rq E 1 040 -- _ Woodle. f StYk am Impact • 4-6 learn 6 J -?6? p _ L Sstreeam 8)act • 5-? (Stream Stream Im act • ! - ?, - _ -- ?,,, ,??i _ _ _ __ - _ G '- 5) Stream `? ba I pa= ct • 27.7 (Stream r4 Str e ?m I.4499))?at'• 25-40-?` ??- - _ - -y- _ ?RTjj c 71 `5 tebm Impact;? ; # {Y y y _ ?- .c _ Y its., A k, Y ?? >4t sr ? ? .,t. / I :9 S s c dp # t fs..t p CTxove , 'Ch r Cr _JY 1 r sa r_ T' ,.- y fLr Sc.'Qle 1:??0 QtJ4. • - - L i .4 t 1 1 1 1 1 i 1 1 1 1 1 1 1 LEGEND - - 2" FORCE MAIN Pilin6, 3" FORCE MAIN 4" FORCE MAIN 6" FORCE MAIN 8" FORCE MAIN 6" WATER LINE I?stee m" °-t' -STREAM IMPACTS Tower - 1 ,I n u I? ? I Or- iveer ?% - eck} _ i I /% I II :! p 1( 44 ry Impact • 116 into 1 5 _ •C? , 76 JS Stream Imppac.,• 8- _/_ •. . (Stream 14)X 0L 111,4 E, SR 111 9 Sc I Is :"24 ? 0-00 1 1 t 1 t 1 r r t t 1 1 t 1 1 t 1 1 1 t t t 1 t t t 1 1 1 1 1 I 1 1