HomeMy WebLinkAbout20080545 Ver 1_Approval Letter_20080415O~O~ W AT ~9QG
r
~_ .~
D ~
14fichael F. Easley, Governor
William G. Ross Jr., Secretary
North Carolina Department of Environment and Natural Resources
Coleen H. Sullins, Director
Division of Water Quality
Apri115, 2008
Chowan County
TIP B-4073
DWQ Project No. 20080545
APPROVAL of 401 WATER QUALITY CERTIFICATION with ADDITIONAL CONDITIONS
Mr. Jerry Jennings, P.E.
NCDOT, Division 1
113 Airport Drive Suite 100
Edenton, NC 27932
Deaz Mr. Jennings:
You have our approval, in accordance with the attached conditions and those listed below, for the following impacts:
Site Number Wetland Fill
acres
1 0.027
2 0.003
Net Total Im acts 0.030 acres
The project shall be constructed in accordance with your application dated March 18, 2008 for the purpose of replacing
Bridge Number 13 over Indian Creek on SR 1226 (Dillazds Mill Rd) in Chowan County. After reviewing your application,
we have decided that these impacts aze covered by General Water Quality Certification Number 3704. This certification
corresponds to the Nationwide Permit 14 issued by the Corps of Engineers. In addition, you should acquire any other federal,
state or local pen7tits before you proceed with your project including (but not limited to) Sediment and Erosion Control, Non-
Discharge and Water Supply Watershed regulations. This approval will expire with the accompanying 404 permit issued by
the US Army Corps of Engineers.
This approval is valid solely for the purpose and design described in your application (unless modified below). Should your
project change, you must notify the DWQ and submit a new application. If the property is sold, the new owner must be given
a copy of this Certification and approval letter, and is thereby responsible for complying with all the conditions. If total
wetland fills for this project (now or in the future) exceed one acre, or of total impacts to streams (now or in the future)
exceed 150 linear feet, compensatory mitigation maybe required as described in 15A NCAC 2H .0506 (h) (6) and (7). For
this approval to remain valid, you must adhere to the conditions listed in the attached certification.
1.) The pennittee and its authorized agents shall conduct its activities in a manner consistent with state water quality
standazds (including any requirements resulting from compliance with §303(d) of the Clean Water Act) and any other
appropriate requirements of State and Federal law. If DWQ determines that such standazds or laws are not being met
(including the failure to sustain a designated or achieved use) or that State or federal law is being violated, or that fiuther
conditions are necessary to assure compliance, DWQ may reevaluate and modify this certification.
2.) The outside buffer, wetland or water boundary located within the construction corridor approved by this authorization
shall be cleazly mazked by highly visible fencing prior to any land disturbing activities. Impacts to azeas within the
fencing are prohibited unless otherwise authorized by this certification.
3.) All mechanized equipment operated near surface waters must be regularly inspected and maintained to prevent
contamination of stream waters from fuels, lubricants, hydraulic fluids, or other toxic materials.
Nom` Carolina
N. C. Division of Water Quality 943 Washington Square Mall Washington, N.C. 27889 Telephone (252) 946-6481 ~tllra~~~
FAX (252) 946-9215 Internet: www.ncwaterquality.org
An Equal OpportunilylAffim~ative Acton Empbyer-5096 Rerydedll0% Post Ca~sumer Paper
4.) No rock, sand or other materials shall be dredged from the stream channel except where authorized by this certification.
5.) There shall be no waste disposal into jurisdictional wetlands or waters associated with this permit without appropriate
modification. Should waste or borrow sites be located in wetlands or stream, compensatory mitigation will be required
since it is a direct impact from road construction activities.
6.) The dimension, pattern and profile of the stream above and below the crossing should not be modified. Disturbed
floodplains and streams should be restored to natural geomorphic conditions.
7.) The use of rip-rap above the Normal High Water Mark shall be minimized. Anyrip-rap placed for stream stabilization
shall be placed in stream channels in such a manner that it does not impede aquatic life passage.
8.) Heavy equipment must be operated from the banks rather than in the stream channel in order to minimise sedimentation
and reduce the likelihood of introducing other pollutants into the stream.
9.) During the construction of the project, no staging of equipment of any kind is permitted in waters of the U.S., or
protected riparian buffers.
10.) The post-construction removal of any temporary bridge structures must return the project site to its preconstruction
contours and elevations. The impacted areas shall be revegetated with appropriate native species.
11.) Strict adherence to the most recent version of NCDOTs Best Management Practices For Bridge Demolition and
Removal approved by the US Army Corps of Engineers is a condition of the 401 Water Quality Certification.
12.) Bridge deck drains shall not discharge directly into the stream. Stormwater shall be directed across the bridge and pre-
treated through site-appropriate means (grassed swales, pre-formed scour holes, vegetated buffers, etc.) before entering
the stream. Please refer to the most current version of Stormwater Best Management Practices.
13.) All fill slopes located in jurisdictional wetlands shall be placed at slopes no flatter than 3:1.
14.) Native riparian vegetation must be reestablished within the construction limits of the project by the end of the growing
season following completion of construction.
15.) Discharging hydroseed mixtures and washing out hydroseeders and other equipment in or adjace~ to surface waters is
prohibited.
16 J The permittee will need to adhere to all appropriate in-water work moratoriums (including the use of pile driving or
vibration techniques) prescribed by the NC Wildlife Resources Commission, the US Fish and Wildlife Service, and
National Marine Fisheries Service. No in-water work is permitted between February 15 and June 30of any year, without
prior approval from the NC Division of Water Quality and the NC Wildlife Resources Commission. In addition, the
permittee shall conform with the NCDOT policy entitled "Stream Crossing Guidelines for Anadromous Fish Passage
(May 12, 1997) at all times.
17.) A copy of this Water Quality Certification shall be posted on the construction site at all times. In addition, the Water
Quality Certification and all subsequent modifications, if any, shall be maintained with the Division Engineer and the on-
site project manager.
18.) Upon completion of the project, the NCDOT shall complete and return the enclosed "Certification of Completion Form"
to notify DWQ when all work included in the 401 Certification has been completed. The responsible party shall
complete the attached form and return it to the 401/VJetlands Unit of the Division of Water Quality upon completion of
the project.
If you do not accept any of the conditions of this certification, you may ask for an adjudicatory hearing. You must act within
60 days of the date that you receive this letter. To ask for a hearing, send a written petition that conforms to Chapter 150B of
the North Carolina General Statutes to the Office of Administrative Hearings, P.O. Box 27447, Raleigh. N.C. 276 1 1-744'x.
This certification and its conditions are final and binding unless you ask for a hearing.
This letter completes the review of the Division of Water Quality under Section 401 of the Clean Water Act If you have any
questions, please contact Garry Ward at (252) 948-3922.
' cerel ,
AI Hodge/Supervisor .-___
Division of Water Quality
Surface Water Protection
Washington Regional Office
Attachment
cc: Mr. Bill Biddlecome, US Army Corps of Engineers, Washington Field Office
Mr. Clay Willis, Division 1 Environmental Officer, NCDOT
Mr. Jun Hoadley, DCM, Elizabeth City
Cathy Brittingham, DCM, 1638 Mail Service Center, Raleigh
Sonia Gregory, DWQ, 401/Wetlands Unit
Central Files
File Copy
Water Quality .Certification N°. 37Q4
Water Quality Certification Number 3704 is issued in conformity with. the requirements of Section
401, Public Laws 92-500 and 95-217 of the United States and subject to the North Carolina
Division of Water Quality (DWCl) Regulations in 15A NCAC 2H, Section .0500 and 15A NCAC 2B
.0200 for the discharge of fill material to waters and adjacent wetland areas or to wetland areas
that are hot a part of the surface tributary system to interstate waters or navigable waters of the
United States (as described' in 33 CFR 330 Appendix A (B) (14) of the Corps of Engineers
regulations {Nationwide Permit No. 14 and Regional General Permit 198200031) and. for the
Riparian Area Protection Rules (Buffer Rules) in 15A NCAC 2B .0200.
The State of North Carolina certifies that~the specified category of activity will not violate
appl'~cable portions of Sections 301, 302, 303, 306 and 307 of the Public laws 92-500 and, 95-217
if conducted in accordance with the conditions hereinafter set forth.
Any proposed fill or modification of wetlands and/or waters, including streams, under this General
Certfication requires application to, and written approval from the Division of Water Quality (the
"Division') except for the single family lot exemption described below.
Application and written approval is not required for construction of a driveway to a single family lot
as long as the driveway involves less than- 25 feet of temporary andlor permanent stream channel
impacts, including any in-stream stabilization needed for the crossing. This activity must meet all
of the Conditions of Certification listed below. If any of these Conditions cannot be met,.or if the
activity is associated with or in response to a Notice of Violation from the Division of
Water Quality or the NC Division of Land Resources, then written approval from the
Division is required.
In accordance with North Carolina General Statute Section 143 215.3D(e), written approval for a
401 Water Quality General Certification must include the appropriate fee. If a project also
requires a CAMA Permit, one payment to both .agencies shall be submitted and will be the higher
of the two fees.
Conditions of Certification:
1. No Impacts Beyond those Authorized in the Written Approval or Beyond the Threshold for
Use. of this Certification
No waste, spoil, solids, or fill of any kind shall occur in wetlands, waters, or riparian areas
beyond the footprint of the impacts authorized in the written approval or beyond the
thresholds for use of this Certification, including incidental impacts. All construction activities,
including the design, installation, operation, and maintenance of sediment and erosion control
Best Management Practices, shall be performed so that no violations of state water quality
standards, statutes, or rules occur.
2. Standard Erosion and Sediment Control Practices
Erosion and sediment control practices must be in full compliance with all specifications
governing the proper design, installation and operation and maintenance of such Best
Management Practices:
Water Quality Certification Nv. 3704
Water Quality Certification N°. 3704
a. Design, installation, operation, and maintenance of the sediment and. erosion control
measures must tae such that they equal, or exceed, the requirements specified in the
most recent version. of the North Carolina. Sediment and. Erosion Control Manual. The
devices shall be maintained on alt construction sites, borrow sites, and waste pile {spoiq
projects, including contractor-owned or leased borrow pits associated with the project.
b. For borrow pit sites, the erosion and sediment control measures must be designed,
installed, operated, and maintained in accordance with the most recent version of the
North Carolina Surface Mining Manual.
c. Reclamation measures.and implementation -must comply with the reclamation in
accordance with the requirements of the Sedimentation Pollution Control Act and the
Mining Act of 1971.
d. Sufficient materials required for stabilization and/or repairof erosion control measures
and stormwater routing and treatment shall be on site at all times, except for publiGy
funded linear transportation projects when materials can be accessed offske in a timely
manner.
e. If the project occurs in waters or watersheds classified as Primary Nursery Areas
(PNA's), Trout (Tr), SA, WS-I, WS-II, High Quality (HQW), or Outstanding-Resource
(ORW) waters, then the sediment and erosion control requirements contained within
Design Standards in Sensitive Watersheds (15A NCAC 04B .0124) supersede all other
sediment and erosion control requirements.
3. Na Sediment and Erosion Control Measures in Wetlands or Waters
Sediment and erosion control measures should not be placed in wetlands or waters outside
of the permitted impact areas without prior approval by the Division. If placement of sediment
and erosion control devices in wetlands and waters is unavoidable, design and placement of
temporary erosion control measures shall not be conducted in a manner that may result in
dis-equilibrium of wetlands or stream beds or banks, adjacent to or upstream and down
stream of the above structures. All sediment and erosion control devices shall lie removed
and the natural grade restored within two (2) months of the date that the Division of Land
Resources or locally delegated program has released the project.
4. Construction stormwater Permit NCG010000
Upon the approval of an Erosion and Sedimentation Control Plan issued by the Division of
Land Resources (DLR) or a DLR delegated bcal erosion and sedimentation control program,
an NPDES General stormwater permit (NCG010000) administered by the Division is
automatically issued to the project. This General Permit allows stormwater to be discharged
during land disturbing construction activities as stipulated by conditions in the permit. If your
project is covered by this permit [applicable to construction projects that disturb one (1) or
more acres], full compliance with permit conditions inGuding the sedimentation control plan,
self-monitoring, record keeping and reporting requirements are required. A copy of this
permit and monitoring report forms may be found at
http//h2o enrstate nc.us/su/Forms Documents.htm.
The North Carolina Department of Transportation (NCDOT) shall be required to be in fult
compliance with the conditions related.to construction activities within the most recent version
of their individual NPDES (NCS000250) stormwater permit.
Water Quality Certification No. 3704 2
Water Quality Certifcation N°. 3704
5. Work in the Dry
All work in or adjacent to stream waters shall be conducted in a dry work area: Approved
best management practices from the most current version of the NC Sediment and Erosion
Control Manual, or the NC DOT Construction and Maintenance Activities Manual, such as
sandbags, rock berms, cofferdams, and other diversion structures shall be used to minimize.
excavation in flowing water. Exceptions to this condition require submittal to, and approval .
by, the Division of Water Quality.
6. Construction Moratoriums and Coordination
If activities must occur during periods of high biological activity (i.e. sea turtle or bird nesting),
then biological monitoring may be required at the request of other state or federal agencies
and coordinated with these activities. This condition can be waived through written
concurrence on a case-by-case basis upon reasonable justifcaBon.
All moratoriums on construction activities established by the NC Wildlife Resources
Commission (WRC}, US Fish and Wildlife Service. (USFWS}, NC Division of Marine Fisheries
(OMF); or National Marine Fisheries Service (NMFS) to lessen. impacts on trout, anadromous
fish, IarvaUpost-larval fishes and crustaceans, or other. aquatic species of concern shall be
implemented. This condition can be waived through written concurrence on a case-by-case
basis upon reasonable justification.
Work within the twenty-five. (25) designated- trout counties or identified state or federal
endangered or threatened species habitat shalt be coordinated with the appropriate WRC,
USFWS, NMFS, and/or DMF personnel.
7. Riparian Area Protection (Buffer) Rules
Activities located in the protected 50-foot wide riparian areas (whether jurisdictional wetlands
or not}, within the Neuse, Tar-Pamlico, Catawba, or Randleman (or any other basin. with
buffer rules), shall be limited to "uses" identified within and constructed in accordance with
15A .NCAC 2B .0233, .0259, .0250 and .0243, and shall be located, designed, constructed,
and maintained to have minimal disturbance to protect water quality to the maximum extent
practicable through the use of best management practices. All buffer rule requirements,
including diffuse flow requirements, must be met.
8. Water Supply Watershed Buffers
The 100-foot wide vegetative buffer (high-density development) or the 30-foot wide
vegetative buffer (low density development) shall be maintained adjacent to all perennial
waters except for allowances as provided. in the Water Supply Watershed Protection Rules
[15A NCAC 2B .0212 through .0215].
9. If concrete is used during the construction, then a dry work area should be maintained to
prevent direct contact between curing concrete and stream water. Water that inadvertently
contacts uncured concrete should not be discharged to surface waters due to the potential for
elevated pH and possible aquatic life/fish kills.
10. Compensatory Mitigation
In accordance with 15A NCAC 2H .0506 (h), compensatory mitigation may be required for
losses of 150 linear feet or more of streams and/or one (1) acre or more of wetlands. For
linear, public transportation projects, impacts equal to or exceeding 150 linear feet per stream
may require mitigation.
Water Quality Certification No. 3704
Water Quality Certification N°. 3704
In watersheds classified as: ORW, HQW, Tr, WS-I, and WS-II, compensatory stream
mitigation may be required at a 1:1 ratio for not only perennial but also intermittent stream
impacts equal to or exceeding 150 feet, unless the project is a linear, publicly-funded
transportation project, which has a 150 foot per-stream impact allowance.
Buffer mitigation may be required for any project with Buffer Rules in effect at the time of
application for buffer impacts resulting from activities classfied as "Allowable with Mitigation"
within the Buffer Rules or require a variance under the Buffer Rules.
A determination of buffer, wetland and stream mitigation requirements shall be made by the
Division for any application to use this Certification. Design and- monitoring protocols shall
follow the US Army Corps of Engineers Wilmington District Stream Mitigation Guidelines
(April 2003), or its subsequent updates. Compensatory mitigation plans shall be submitted
for written Division approval as required in those protocols. Alternatively, the Division will
accept payment into an in-lieu fee program or credit purchase from a mitigation bank.
Finally, the mitigation plan must be implemented and/or constructed before any permanent
building or structure on site is occupied. In the case of public road projects, the mitigation
plan must be implemented before the road is opened tothe public whenever practical or at
the eariiest reasonable time during the construction of the project. Proof of payment to an in-
lieu fee program or mitigation bank must be provided to the Division to satisfy this
requirement.
11. For all activities requiring re-alignment of streams, a stream relocation plan must be included
for written Division approval. Relocated stream designs should include the same dimensions,
patterns and profiles as the existing channel (or a stable reference reach if the existing
channel is unstable), to the maximum extent practical. The new channel should be
constructed in the dry and water shalt not be fumed into the new channel until the banks are
stabilized. Vegetation used for permanent bank stabilization shall be limited to native woody
species, and should include establishment of a 30-foot wide wooded and an adjacent 20-foot
wide vegetated buffer on both sides of the relocated channel to the maximum extent
practical. A transitional phase incorporating appropriate erosion control matting materials
and seedling establishment is allowable. Rip-rap, A-Jacks, concrete, gabions or other hard
structures may be allowed if it is necessary to maintain the physical integrity of the stream,
however, the applicant must provide written justfication and any calculations used to
determine the extent of rip-rap coverage. Please note that if the stream relocation is
conducted as a stream restoration as defined in the US Army Corps of Engineers Wilmington
District, April 2003 Stream Mitigation Guidelines, the restored length can be used as
compensatory mitigation for the impacts resulting from the relocation.
12. Stormwater Management Plan Requirements
A. For applicants other than the North Carolina Department of Transportation, a
Stormwater Management Plan in accordance with the version of Storrrrwater
Management Plan (SMP) Requirements for Applicants other than the North
Carolina Department of Transportation posted on the Division web site at the time
of application shall be provided for any project that meets both of the following two
criteria:
i. Requires this 401 Water Quality Certification, (regardless of whether
written authorization is required by the Division}, AND
Water Quality Certification No. 3704
Water Quality Certification N°. 3704
ii. Contains one or more drinage areas that are anticipated to have
impervious surface cover of equal to or greater than 24 percent. When
drainage areas are difficult to delineate or when a pocket of high density
exists within a drainage area, the Division shall use best professional
judgment to apply the SMP requirement ~s appropriate. Use of this
Certification to construct a private driveway. to one single-family
residential lot will not trigger the stormwater management plan
requirement
B. For the North Carolina Department of Transportation, compliance with NCDOT's
Individual NPDES permit NCS000250 shall serve to satisfy this condition.
13. If this Water Quality Certification is used to access building sites, all lots owned by the
applicant must be buildable without. additional fill. For road construction purposes, this
General Water Quality Certification shall only be utilized from natural. high ground to natural
high ground.
14. Placement of Culverts and Other Structures in Waters and Wetlands
The application must include construction plans. with cross-sectional details in order to
indicate that the current stability of the stream wilt be maintained or enhanced (i.e.; not result
in head cuts).
Culverts required for this project shall be designed and installed in such a.manner that the
original .stream profiles are not altered and allow foraquatic life movement during low flows:;:
Existing stream dimensions (including the cross section dimensions, pattern, and longitudinal
profile) must be maintained above and below locations of each culvert. Placement of culverts
and other structures in waters, streams, and wetlands must be placed below the elevation of
the streambed by one foot for all culverts with a diameter greater than 48 inches, and 20
percent of the culvert diameter for culverts having a diameter less than or equal to 48 inches,
to allow low flow passage of water and. aquatic life unless otherwise justified and approved by
the Division
Installation of culverts in wetlands must ensure continuity of water movement and be
designed to adequately accommodate high water or flood conditions. Additionally, when
roadways, causeways or other fill projects are constructed across FEMA-designated
floodways or wetlands, openings such as culverts or bridges must be provided to maintain
the natural hydrology of the system as well as prevent constriction of the floodway that may
result in destabilization, of streams or wetlands.
Any rip rap required for normal pipe burial and stabilization shall be buried such that the
original stream elevation is restored and maintained.
The establishment of native, woody vegetation and other soft stream bank stabilization
techniques must be used where practicable instead of rip-rap or other bank. hardening
methods.
15. Additional site-specific.conditions may be added to the written approval in order to ensure
compliance with all applicable water quality and effluent standards.
16. If an environmental document is required under the National or State Environmental Policy
Act (NEPA or SEPA), then this General Certification is not valid until a Finding of No
Significant Impact (EONS!} or Record of Decision (ROD) is issued by the State
Clearinghouse.
Water Quality Certification No. 3704 5
Water Quality Certification N°. 3704
17. Deed notifications or similar mechanisms shall be placed on all retained jurisdictional
wetlands, waters and protective buffers in order to assure compliance for future wetland,
water and buffer impact. These mechanisms shall be put in place at the time of recording of
the property, or of individual lots, whichever is appropriate. A sample -deed notification can
be downloaded from the 401IWetiands Unit web site at http://h2o.enr:state.nc.us/ncwetiands.
The text of the sample deed notification may be mod~ed as appropriate to suit to a specific
project.
18. Certificate of Completion
When written authorization is required for use of this certification; upon completion of all
permitted impacts included within the approval and any subsequent modifications, the
applicant shall be required to return the certificate of completion attached #o the approval.
One copy of the certificate shalt be sent to the DWQ Central Office in Raleigh at 1650 Mail
Service Center, Raleigh, NC, 27699-1650.
19. This General Certification shall expire three (3) years from the date of issuance of the written
approval from the Division or on the same day as the expiration date of the corresponding
Nationwide Permit 14 or Regional General Permit 198200031. In accordance with General
Statute 136.44.76, certifications issued to the NCDOT shall expire onty upon expiration of the
federal 404 Permit. The conditions in effect on the date of issuance of Certification for a
specfic project shall remain in effect for the life of the project, regardless of the expiration
date of this Certification. If the construction process for approved activities will overlap the
expiration and renewal date of the corresponding 404 Permit and the Corps allows for
continued use of the 404 Permit, then the General Certification shall also remain in effect
without requiring re-application and re-approval to use this Certification for the specific
impacts already approved.
20. The applicant/permittee and their author'~zed agents shall conduct all activities in a manner
consistent with State water quality standards (including any requirements resulting from
compliance with §303(d) of the Clean Water Act), and any other appropriate requirements of
State and Federal Law. If the Division determines that such standards or laws are not being
met, including failure to sustain a designated or achieved use, or that State or Federal law is
being violated, or that further conditions are necessary to assure compliance, then the
Division may reevaluate and modify this General Water Quality Certification.
Non-compliance with or violation of the conditions herein set forth by a specific fill project may
result in revocation of this Certification for the project and may also result in criminal and/or civil
penalties.
The Director of the North Carolina Division of Water Quality may require submission of a formal
application for Individual Certfication for any project in this category of activity , if it is determined
that the project is likely to have a significant adverse effect upon water quality including state or
federally listed endangered or threatened aquatic species or degrade the waters so that existing
uses of the wetland or downstream waters are precluded.
Public hearings may be held for specific applications or group of applications prior to a
Certification decision if deemed in the public's best interest by the Directorof the North Carolina
Division of Water Quality.
Water Quality Certification No. 3704
Water Quality Certification N°. 3704
Effective date: November 1, 2007
DIVISION Of WATER QUALITY
~/~
Coleen H. Sullins
Director
r/~`_
History Note: Water Quality Cerkification Number 3704 replaces Water Quality Certfication
Number 2177 issued on November 5, 1987; Water Quality Certification Number 2fi6fi issued on
January 21, 1992; Water Quality Certification Number 2732 issued on May 1, 1992; Water Quality
Certification Number 3103 issued on February 11, 1997; Water Quality Certification Number 3289
issued on June 1, 2000; Water Quality Certification Number 3375 issued March 18, 2002, Water
Quality Certification Number 3404 issued March 2003 and Water Quality Certification Number
3627 issued March 2007. This W(1C is rescinded when the Corps of Engineers re-authorizes
Nationwide Permit 14 or Regional General Permit 198200031or when deemed appropriate by the
Director of the Division of Water Quality.
Water Quality Certification No. 3704 7
warFR
QG
~~
`~
Michael F. Easley, Governor
William G. Ross Jr., Secretary
North Carolina Departrnent of Environment and Natural Resources
Coleen H. Sullins Director
Division of Water Quality
DWQ Project No.: County:
Applicant:
Project Name:
Date of Issuance of 401 Water Quality Certification:
Certificate of Completion
Upon completion of all work approved within the 401 Water Quality Certification or applicable Buffer Rules, and
any subsequent modifications, the applicant is required to return this certificate to the 4O1/Wetlands Unit, North
Carolina Division of Water Quality, 1621 Mail Service Center, Raleigh, NC, 27699-1621. This form may be
returned to DWQ by the applicant, the applicant's authorized agent, or the project engineer. It is not necessary to
send certificates from all of these.
AppQcant's Certification
I,
hereby state that, to the best of my abilities, due care and diligence
was used in the observation of the construction such that the construction was observed to be built within substantial
compliance and intent of the 401 Water Quality Certification and Buffer Rules, the approved plans and
specifications, and other supporting materials.
Signature:
Agent's Certification
Date:
1, hereby state that, to the best of my abilities, due care and diligence
was used in the observation of the construction such that the construction was observed to be built within substantial
compliance and intent of the 401 Water Quality Certification and Buffer Rules, the approved places and
specifications, and other supporting materials.
Signature:
Engineer's Certification
Partial Final
Date:
1, , as a duly registered Professional Engineer in the State of North
Carolina, having been authorized to observe (periodically, weekly, full time) the construction of the project, for the
Permittee hereby state that, to the best of my abilities, due care and diligence was used in the observation of the
construction such that the construction was observed to be built within substantial compliance and intent of the 401
Water Quality Certification and Buffer Rules, the approved plans and specifications, and other supporting materials.
Signature
Date
Registration No.
Transportation Permitting Unit
1650 Mail Service Center, Rategh, North Carolina 27699-1650
2321 Crabtree Boulevard, Suite 250, Raleigh, North Carolina 27604
Phone: 919-733-17861FAX919-733-689311ntemet httu://h2o.enr.state.nc.us/ncwetlands
An Equal C+pportunity/Affimrafive Action Employer - 50°6 Recydedl1096 Post Consumer Paper