HomeMy WebLinkAboutSR 1660 and SR 1662 (8)NC-DOT
Project Services Unit
Preliminary Estimate Section
August 28, 2006 Revised Copy
Memo To: Liz Kovasckitz, AICP
Mulkey Engineers & Consultants
From: Doug Lane
Preliminary Estimate Engineer
Subject: Preliminary Construction Alternatives for the New Connector between SR 1660
and SR 1662 just South of US 441 in Franklin, TIP Project R-4748, Macon County.
ALTERNATE LENGTH CONSTR.COST
Miles
A 1.41 $6,700,000.
A
Roundabout 1.41 $6,400,000
Option
B 1.47 $8,100,000
B
Roundabout 1.47 $7,900,000
Option
C 1.32 $7,400,000
C
Roundabout 1.32 $7,200,000
Option
D 0.68 $4,600,000
Note: Right-of-Way and R/W Utility Cost are not included in above costs.
cc: Undrea Major
James Bridges
Tim Jordan
Gary Covering, PE
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 ALTA County: Macon
Route New Location
From Between SR 1660 (Siler Road) And SR 1662 (Wiley Brown Road) CONSTR. COST
Typical Section New Location 2-Lane w/ 4' Paved Shoulder $6,700,000
Priced By: Doug Lane 8/21/06 Revised Quantities Only
Requested By: Mulkey Engineers & Consultants 7/6/06
Line
Item
Des
Sec No.
Description
Quantity
Unit
Price
Amount
Clearin and Grubbin 9.0 ACR $ 20000.00: $ 180,000.00
Unclassified Excavation 117,100 CY $ ''8.00 $ 936,800.00
Fine Gradin 27,210 SY $ 2.00 $ 54,420.00
Draina e 1.41 MI $ 150,000.00 $ 211,500.00
60" RC Pi e Culverts, Class III 1,062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Mason Draina e Structures w / G & F 2 EA $ 3,000.00 $ 6,000.00
New Full De th Pavement 30,300 SY $ 40.00 $ 1,212,000.00
Resurface Pavement 3,200 SY $ 8.00 $ 25,600.00
Sub rade Stabilization 28,050 SY $ 5.00 $ 140,250.00
Pavement Removal 3,060 SY $ 3.00 $ 9,180.00
Pavement Break u 225 SY $ 2.00 $ 450.00
Steel Beam Guardrail 3,200 LF $ 15.00 $ 48,000.00
Sho Curve Steel Beam Guardrail 75 LF $ 25.00 $ 1,875.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e III 4 EA $ 1,300.00 $ 5,200.00
Guardrail Anchor Unit, T e 350 9 EA $ 1,800.00 $ 16,200.00
Guardrail Anchor Unit, T e CAT-1 1 EA $ 600.00 $ 600.00
SP Traffic Control 1 LS $ 25,000.00 $ 25,000.00
Thermo and Markers 1.41 Miles $ 20,000.00 $ 28,200.00
SP Erosion Control 10.5 ACR $ 15,000.00 $ 157,500.00
SP Traffic Si als at -64- & -ALTA- (Revised) 1 LS $ 70,000.00 $ 70,000.00
SP Traffic Si als at -ALTA- & -ALTAY2- (New) 1 LS $ 100,000.00 $ 100,000.00
SP New Structure over Water
360' x 32', ht = 21', Curve 90° Skew, Vert. Curve 11,520 SF $ 95.00' $ 1,094,400.00
Unlit Construction
Water Line 630 LF `~ 7ti.(~C3 $ 31,500.00
Misc. & Mob (10% Str & Utilities) 1 LS $ 112,527.00
Misc. & Mob (35% Rdwy) 1 LS $ 1,187,000.00
Lgth 1.41 Miles Contract Cost ..................................... $ 5,818,000.00
E. & C. 15% ...................................... $ 882,000.00
Construction Cost ..................................... $ 6,700,000.00
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 ALT B
Route New Location
From Between SR 1660 (Sher Road) And SR 1662 (Wiley Brown Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder
Priced By: Doug Lane
Requested By: Mulkey Engineers & Consultants
County: Macon
CONSTR. COST
$8,100,000
8/21/06 Revised Quantities Only
7/6/06
Line
Item
Des
Sec No.
Description
Quantity
Unit
Price
Amount
Clearin and Grubbin 8.0 ACR $ 15OOQ.00 : $ 120,000.00
Unclassified Excavation 321,400 CY $ _6.04 $ 1,928,400.00
Fine Gradin 25,300 SY $ 2.00 $ 50,600.00
Draina e 1.47 MI $ 150,000.00 $ 220,500.00
60" RC Pi e Culverts, Class III 1,062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Mason Draina e Structures w / G & F 2 EA $ ' 3,000.00 $ 6,000.00
New Full De th Pavement 28,700 SY $ 40.00 $ 1,148,000.00
Resurface Pavement 3,750 SY $ 8.00 $ 30,000.00
Sub ade Stabilization 25,900 SY $ ' 5.00 $ 129,500.00
Pavement Removal 3,070 SY $ 3.00 $ 9,210.00
Pavement Break u 1,020 SY $ 2.00 $ 2,040.00
Steel Beam Guardrail 3,350 LF $ 15.00 $ 50,250.00
Sho Curve Steel Beam Guardrail 150 LF $ 25.00 $ 3,750.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e III 4 EA $ 1,300.00 $ 5,200.00
Guardrail Anchor Unit, T e 350 13 EA $ 1,800.00 $ 23,400.00
Guardrail Anchor Unit, T e CAT-1 1 EA $ 600.00 $ 600.00
SP Traffic Control 1 LS $ ' 25,000.00 $ 25,000.00
Thermo and Markers 1.47 Miles $ 20,000.00 $ 29,400.00
SP Erosion Control 15.5 ACR $ 15,000.00 $ 232,500.00
SP Traffic Si als at -64- & -ALTB- (Revised 1 LS $ 70,000.00 $ 70,000.00
SP Traffic Si nals at -ALTO- & -ALTBY4- (New) 1 LS $ 100,000.00 $ 100,000.00
SP New Structure over Water
345' x 32', ht = 49', Tan ent 90° Skew, Vert. Curve 11,040 SF $ 90.00 $ 993,600.00
Utilit Construction
Water Line 550 LF `~ SO.Oi7 $ 27,500.00
Sewer Line 250 LF r>SO:Of~ $ 12,500.00
Misc. & Mob (10% Str & Utilities) 1 LS $ 103,252.00
Misc. & Mob (35% Rd ) 1 LS $ 1,522,000.00
Lgth 1.47 Miles
Contract t;ost ...................................... a i,vv i,vvv.vv
E. & C. 15% ...................................... $ 1,093,000.00
Construction Cost ...................................... $ 8,100,000.00
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 ALT C
Route New Location
From Between SR 1660 (Sher Road) And SR 1662 (Wiley Brown Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder
Priced By: Doug Lane
ReallP,CtP.Cl RV' 1Vtiillrav Pnvinavrc R, (~nnc>>ltor~fc
County: Macon
CONSTR.COST
$7,400,000
8/21/06 Revised Quantities Only
~ is inc
Line
Item
Des
Sec No.
Description
Quantity
Unit
Price
Amount
Clearin and Grubbin 3.5 ACR $ 25,000.00 , $ 87,500.00
Unclassified Excavation 203,200 CY $ -.7.00 ~ $ 1,422,400.00
Fine Gradin 27,460 SY $ 2.00 $ 54,920.00
Draina e 1.43 MI $ 150,000.00 $ 214,500.00
60" RC Pi e Culverts, Class III 1,062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Mason Draina e Structures w / G & F 2 EA $ 3,000.00 $ 6,000.00
New Full De th Pavement 26,300 SY $ 40.00 $ 1,052,000.00
Resurface Pavement 4,225 SY $ 8.00 $ 33,800.00
Sub ade Stabilization 27,930 SY $ 5.00 $ 139,650.00
Pavement Removal 6,800 SY $ 4.00; $ 27,200.00
Pavement Break u 940 SY $ 3.00 $ 2,820.00
Steel Beam Guardrail 2,850 LF $ 15.00 $ 42,750.00
Sho Curve Steel Beam Guardrail 75 LF $ 25.00 $ 1,875.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e III 4 EA $ 1,300.00 $ 5,200.00
Guardrail Anchor Unit, T e 350 11 EA $ 1,800.00 $ 19,800.00
Guardrail Anchor Unit, T e CAT-1 1 EA $ 600.00 $ 600.00
Greenwa Trail Relocation (10' W x 470' L BST) 4,700 SF $ 5.00 $ 23,500.00
SP Traffic Contro] 1 LS $ 25,000.00 $ 25,000.00
Thermo and Markers 1.43 Miles $ 20,000.00 $ 28,600.00
SP Erosion Control 13.5 ACR $ 15,000.00 $ 202,500.00
SP Traffic Si als at -64- & -ALTO- Revised) 1 LS $ 70,000.00 $ 70,000.00
SP Traffic Si als at -ALTC- & -ALTCY4- (New) 2 LS $ 100,000.00 $ 200,000.00
New Structure over Water
380' x 32', ht = 55', Tan ent 90° Skew, Vert. Curve 12,160 SF $ 90.00 $ 1,094,400.00
Utilit Construction
Water Line 770 LF 5 5O.Of) $ 38,500.00
Sewer Line 400 LF ~ 0.; $ 20,000.00
Misc. & Mob (10% Str & Utilities) 1 LS $ 115,687.00
Misc. & Mob (25% Rdwy) 1 LS $ 1,339,000.00
L~lll I.YJ 1~1IICJ
~:ontract ~:ost ...................................... ~ 6,43'1,000.00
E. & C. 15% ........................ .............. $ 968,000.00
Construction Cost ........................ .............. $ 7,400,000.00
North Carolina Department of Transportation
Preliminaty Estimate
TIP No. R-4748
Route New Location
From Between US 441 and SR 1660 (Sher Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder
Priced By: Doug Lane
Requested By: Mulkey Engineers & Consultants
ALT D
County: Macon
CONSTR. COST
$4,600,000
8/28/06 Revised Quantities Only
7/6/06
Line
Item
Des
Sec No.
Description
Quantity
Unit
Price
Amount
Clearin and Grubbin 6.0 ACR $ 15,000.00 $ 90,000.00
Unclassified Excavation 14,900 CY $ ~ ~. $ 134,100.00
Borrow 223,900 CY $ 8.00 $ 1,791,200.00
Fine Gradin 9,100 SY $ 2.00 $ 18,200.00
Drama e 0.68 MI $ 150,000.00 $ 102,000.00
New Full De th Pavement 10,000 SY $ 40.00 $ 400,000.00
Resurface Pavement 3,000 SY $ 8.00 $ 24,000.00
Sub ade Stabilization 10,500 SY $ 5.00 $ 52,500.00
Pavement Remova] 950' SY $ `4.On" $ 3,800.00
Pavement Break u .100. SY $ 3.00 $ 300.00
Steel Beam Guardrail 3,225 LF $ 15.00 $ 48,375.00
Sho Curve Steel Beam Guardrail 75 LF $ 25.00 $ 1,875.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e 350 8 EA $ 1,800.00 $ 14,400.00
SP Traffic Control 1 LS $ 25,000.00 $ 25,000.00
Thermo and Markers 0.68 Miles $ 20,000.00 $ 13,600.00
SP Erosion Control 6.5 ACR $ 15,000.00 $ 97,500.00
SP Traffic Si als at -ALTD- & US 441 (New 1 LS $ 100,000.00 $ 100,000.00
Utilit Construction
Water Line 950 LF ~ St).{a{) $ 47,500.00
Misc. & Mob (10% Str & Utilities) 1 LS $ 4,400.00
Misc. & Mob (25% Rd ) 1 LS $ 1,021,000.00
Lgth U.68 Miles t/ontract host ...................................... ~ s,yyu,uvv.vv
E. & C. 15% ........................ .............. $ 610,000.00
Construction Cost ....................... . .............. $ 4,600,000.00
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 A Roundabout
Route New Location
From Between SR 1660 (Sher Road) And SR 1662 (Wiley Brown Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder
Priced By: Doug Lane
Renue~terl Rv' Mnikev Fnainaarc R, ('nncnltantc
County: Macon
CONSTR. COST
$6,400,000
8/21/06 Revised Quantities Only
~i~m~
Item Des Sec No. Description Quantity Unit Price Amount
Clearin and Grubbin 9.0 ACR $ 15,000.00 $ 135,000.00
Unclassified Excavation 128,000 CY $ 8.00 $ 1,024,000.00
Fine Gradin 23,700 SY $ 2.00 $ 47,400.00
Draina e 1.41 MI $ 150,000.00 $ 211,500.00
60" RC Pi e Culverts, Class III 1,062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Mason Draina e Structures w / G & F 2 EA $ 3,000.00 $ 6,000.00
New Full De th Pavement 26,430 SY $ 40.00 $ 1,057,200.00
Resurface Pavement 3,200 SY $ 8.00 $ 25,600.00
Sub ade Stabilization 23,940 SY $ 5.00 $ 119,700.00
Pavement Removal 3,150 SY $ 3.00 $ 9,450.00
Pavement Break u 215 SY $ 2.00 $ 430.00
Steel Beam Guardrail 3,275 LF $ 15.00 $ 49,125.00
Sho Curve Steel Beam Guardrail 75 LF $ 25.00 $ 1,875.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e III 4 EA $ 1,300.00 $ 5,200.00
Guardrail Anchor Unit, T e 350 9 EA $ 1,800.00 $ 16,200.00
Guardrail Anchor Unit, T e CAT-1 1 EA $ 600.00 $ 600.00
Concrete Island 600 SY $ 55.00 $ 33,000.00
9" x 18" C&G 200 LF $ 35.00 $ 7,000.00
1' x 6" C&G 250 LF $ 30.00 $ 7,500.00
SP Traffic Control 1 LS $ 25,000.00 $ 25,000.00
Therom and Markers 1.41 Miles $ 20,000.00 $ 28,200.00
SP Erosion Control 10.5 ACR $ 15,000.00 $ 157,500.00
SP Traffic Si als at -64- & -ALTA- (Revised) 1 LS $ 70,000.00 $ 70,000.00
New Structure over Water
360'x 32', ht=21',Curve 90° Skew, Vert. Curve 11,520 SF $ 95.00 $ 1,094,400.00
Unlit Construction
Water Line 630 LF ~ 5{1.f1{} $ 31,500.00
Misc. & Mob (10% Str & Utilities) 1 LS $ 112,822.00
Misc. & Mob (25% Rd ) 1 LS $ 1,120,000.00
Lgth 1.41 Miles Contract Cost .............. ........., .............. $ 5,560,000.00
E. & C. 15% .............. ........................ $ 840,000.00
Construction Cost .............. ........................ $ 6,400,000.00
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 B Roundabout
Route New Location
From Between SR 1660 (Sher Road) And SR 1662 (Wiley Brown Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder and Roundabout Intersection
Priced By: Doug Lane
Rerniesterl Rv• Mulkev Rnuineers Rr ('nn~ultants
County: Macon
CONSTR. COST
$7,900,000
7/6/06 Revised Quantities Only
7/6/06
Line
Item
Des
Sec No.
Description
Quantity
Unit
Price
Amount
Clearin and Grubbin 8.0 ACR $ 15,000.00 $ 120,000.00
Unclassified Excavation 333,200 CY $ 6.00 $ 1,999,200.00
Fine Gradin 23,100 SY $ 2.00 $ 46,200.00
Draina e 1.47 MI $ 150,000.00 $ 220,500.00
60" RC Pi e Culverts, Class III 1,062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Mason Draina e Structures w / G & F 2 EA $ 3,000.00 $ 6,000.00
New Full De th Pavement 25,260 SY $ 40.00 $ 1,010,400.00
Resurface Pavement 3,650 SY $ 8.00 $ 29,200.00
Sub ade Stabilization 22,300 SY $ 5.00 $ 111,500.00
Pavement Removal 3,170 SY $ 3.00 $ 9,510.00
Pavement Break u 1,020 SY $ 2.00 $ 2,040.00
Steel Beam Guardrail 3,350 LF $ 15.00 $ 50,250.00
Sho Curve Steel Beam Guardrail 150 LF $ .25.00 $ 3,750.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e III 4 EA $ .1,300.00 $ 5,200.00
Guardrail Anchor Unit, T e 350 13 EA $ 1,800.00 $ 23,400.00
Guardrail Anchor Unit, T e CAT-1 1 EA $ 600.00 $ 600.00
Concrete Island 600 SY $ 55.00 $ 33,000.00
9" x 18" C&G 200 LF $ 35.00 $ 7,000.00
1' x 6" C&G 250 LF $ 30.00 $ 7,500.00
SP Traffic Control 1 LS $ 25,000.00 $ 25,000.00
Thermo and Markers 1.47 Miles $ 20,000.00 $ 29,400.00
SP Erosion Control 15.5 ACR $ 15,000.00 $ 232,500.00
SP Traffic Si als at -64- & -ALTA- (Revised) 1 LS $ 70,000.00 $ 70,000.00
New Structure over Water
345' x 32', ht = 49', Tan ent 90° Skew, Vert. C 11,040 SF $ 90.00 $ 993,600.00
Utilit Construction
Water Line 550 LF `~ ~!=,~t? $ 27,500.00
Sewer Line 250 LF `3 50:f~0 $ 12,500.00
Misc. & Mob (10% Str & Utilities) 1 LS $ 103,452.00
Misc. & Mob (25% Rd ) 1 LS $ 1,472,000.00
Lath 1.47 M iles Contract Cost .............. ........., .............. $ 6.815.000.00
E. & C. 15%
Construction Cost
......... .............. $ 1,085,000.00
....................... $ 7,900,000.00
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 C Roundabout
Route New Location
From Between SR 1660 (Sher Road) And SR 1662 (Wiley Brown Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder and Roundabout Intersection
Priced By: Doug Lane
Requested Rv: Mulkev F.nuineerc Rr C"~ncnltantc
County: Macon
CONSTR. COST
$7,200,000
7/12/06 Revised Quantities Only
~i~in~
me
Item
Des
Sec No.
Description
Quantity
Unit
Price
Amount
Clearin and Grubbin 3.5 ACR $ :25,000.OQ $ 87,500.00
Unclassified Excavation 215,000 CY $ 7.00 $ 1,505,000.00
Fine Gradin 26,750 SY $ 2.00 $ 53,500.00
Draina e 1.43 MI $ 150,000.00 $ 214,500.00
60" RC Pi e Culverts, Class III 1,062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Mason Draina e Structures w / G & F 2 EA $ 3,000.00 $ 6,000.00
New Full De th Pavement 25,600 SY $ 40.00 $ 1,024,000.00
Resurface Pavement 4,125 SY $ 8.00 $ 33,000.00
Sub ade Stabilization 27,230 SY $ 5.00 $ 136,150.00
Pavement Removal 6,900 SY $ 4.00 $ 27,600.00
Pavement Break u 940 SY $ 3.00 $ 2,820.00
Steel Beam Guardrail 2,850 LF $ 15.00 $ 42,750.00
Sho Curve Steel Beam Guardrail 75 LF $ 25.00 $ 1,875.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e III 4 EA $ 1,300.00 $ 5,200.00
Guardrail Anchor Unit, T e 350 I1 EA $ 1,800.00 $ 19,800.00
Guardrail Anchor Unit, T e CAT-1 l EA $ 600.00 $ 600.00
Concrete Island 600 SY $ 55.00 $ 33,000.00
9" x 18" C&G 200 LF $ 35.00 $ 7,000.00
1' x 6" C&G 250 LF $ 30.00 $ 7,500.00
Greenwa Trail Relocation (10' W x 470' L BS 4,700 SF $ 5.00 $ 23,500.00
SP Traffic Control 1 LS $ 25,000.00 $ 25,000.00
Therom and Markers 1.43 Miles $ 20,000.00 $ 28,600.00
SP Erosion Control 13.0 ACR $ 15,000.00 $ 195,000.00
SP Traffic Si als at -64- & -ALTA- (Revised) 1 LS $ 70,000.00 $ 70,000.00
New Structure over Water
380' x 32', ht = 55', Tan ent 90° Skew, Vert. C 12,160 SF $ 90.00 $ 1,094,400.00
Utilit Construction
Water Line 770 LF 5 5fi.£)t) $ 38,500.00
Sewer Line 400 LF `;> >(3.~)t? $ 20,000.00
Misc. & Mob 10% Str & Utilities 1 LS $ 115,407.00
Misc. & Mob (25% Rd ) 1 LS $ 1,300,000.00
Lgth 1.43 Miles Contract Cost .............. ........................ $ 6,282,000.00
E. & C. 15% .............. ........................ $ 918,000.00
Construction Cost .............. ........................ $ 7,200,000.00
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 ALT D REV County:
Route New Location
From Vicinity of SR 1660 (Siler Road) And SR 1662 (Wiley Brown Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder
Priced By: Doug Lane
Requested By: Ron McCollum, PE
1 / 16/2007
1 / 16/2007
Macon
CONSTR. COST
$7,700,000
Line
Item
Des Sec
No.
Description
Quantity
Unit
Price
Amount
Clearin and Grubbin 8.5 ACR $ 15,000.00 $ 127,500.00
Unclassified Excavation 216,300 CY $ 7.00 $ 1,514,100.00
Fine Gradin 38,600 SY $ 2.00 $ 77,200.00
Borrow 54,400 CY $ 10.00. $ 544,000.00
Drama e 2 Lanes w/ Paved Shld 1.26 MI
1 00.00
' $ 239,400.00
Drama e 2 Lanes w/ no Paved Shld 0.56 MI $ 1~Q,QQ.p.00 ; $ 106,400.00
60" RC Pi e Culverts, Class III 1,062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Masonry Draina e Structures w / G & F 2 EA $ 3,000.00 $ 6,000.00
New Full De th Pavement 37,500 SY $ 40.00 $ 1,500,000.00
Resurface Pavement 5,000 SY $ 8.00 $ 40,000.00
Sub rade Stabilization 40,635 SY $ 5.00 $ 203,175.00
Pavement Removal 3,300 SY $ 4.00 $ 13,200.00
Pavement Break u 1,040 SY $ 3.00 $ 3,120.00
Steel Beam Guardrail 4,850 LF $ 15.00 $ 72,750.00
Sho Curve Steel Beam Guardrail 150 LF $ 25.00 $ 3,750.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e 350 15 EA $ 1,800.00 $ 27,000.00.
Guardrail Anchor Unit, T e CAT-1 5 EA $ 600.00 $ 3,000.00
SP Traffic Control I LS $ 25,000.00 $ 25,000.00
Thermo and Markers 1.82 Miles $ 20,000.00 $ 36,400.00
SP Erosion Control 16.5 ACR $ 15,000.00 $ 247,500.00
SP Traffic Si als at -ALTD- & US 441 (New) 1 LS $ 100,000.00 $ 100,000.00
SP Traffic Si als at -64- & -ALTD2- Revised 1 LS $ 75,000.00 $ 75,000.00
SP Traffic Si als at -ALTD2- & -ALTDY6- New 1 LS $ 100,000.00 $ 100,000.00
Utilities 1 LS $ 150,000.00 $ 150,000.00
Misc. & Mob (10% Str & Utilities) LS $ 15,000.00
Misc. & Mob (25% Rdw) LS $ 1,306,707.00
Lgth 1.82 Miles
Contract Cost ...................................... $ 6,700,OOOA0
E. & C.15% .............. ......... . .............. $ 1,000,000.00
Construction Cost ...................................... $ 7,700,000.00
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 D REV Roundabou County:
Route New Location
From Vicinity of SR 1660 (Siler Road) And SR 1662 (Wiley Brown Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder
Priced By: Doug Lane
Requested By: Ron McCollum, PE
1 / 16/2007
1 / 16/2007
Macon
CONSTR.COST
$7,900,000
Line
Item
Des Sec
No.
Description
Quantit
Unit
Price
Amount
Clearin and Grubbin 8.5 ACR $ 15,000.00 $ 127,500.00
Unclassified Excavation 228,100 CY $ 7.00 $ 1,596,700.00
Fine Gradin 37,890 SY $ 2.00 $ 75,780.00
Borrow 54,400 CY $ 10.00 $ 544,000.00
Draina e 2 Lanes w/ Paved Shld 1.26 MI $ 190,000.00 $ 239,400.00
Draina e 2 Lanes w/ no Paved Shld 0.56 MI $ 190,000.00 $ 106,400.00
60" RC Pi e Culverts, Class III 1,062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Masonry Draina e Structures w / G & F 2 EA $ 3,000.00 $ 6,000.00
New Full De th Pavement 36,800 SY $ 40.00 $ 1,472,000.00
Resurface Pavement 4,900 SY $ 8.00 $ 39,200.00
Sub rade Stabilization 39,935 SY $ 5.00 $ 199,675.00
Pavement Removal .3,200 SY $ 4.00 $ 12,800.00
Pavement Break u 1,040 SY $ 3.00 $ 3,120.00
Steel Beam Guardrail 4,850 LF $ 15.00 $ 72,750.00
Sho Curve Steel Beam Guardrail 150 LF $ 25.00 $ 3,750.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e 350 15 EA $ 1,800.00 $ 27,000.00
Guardrail Anchor Unit, T e CAT-1 5 EA $ 600.00 $ 3,000.00
Concrete Island 600 SY $ 55.00 $ 33,000.00
9" x 18" C&G 200 LF $ 35.00 $ 7,000.00
1' x 6" C&G 250 LF $ 30.00 $ 7,500.00
SP Traffic Control 1 LS $ 25,000.00 $ 25,000.00
Thermo and Markers 1.82 Miles $ 20,000.00 $ 36,400.00
SP Erosion Control 16 ACR $ 15,000.00 $ 240,000.00
SP Traffic Si als at -ALTD- & US 441 (New) 1 LS $ 100,000.00 $ 100,000.00
SP Traffic Si als at -64- & -ALTD2- (Revised) 1 LS $ 70,000.00 $ 70,000.00
SP Traffic Si als at -ALTD2- & -ALTDY6- (New) 1 LS $ 100,000.00 $ 100,000.00
Utilities 1 LS $ 150,000.00 $ 150,000.00
Misc. & Mob (10% Str & Utilities) LS $ 15,000.00
Misc. & Mob (25% Rdw) LS $ 1,328,227.00
Lgth 1.tS2 Miles
Contract Cost ....................................... $ 6,805,OOO.U0
E. & C. 15% ....................................... $ 1,095,000.00
Construction Cost ....................................... $ 7,900,000.00
REQUEST FOR R/W COST ESTIMATE
DATE RECEIVED: 10-26-06 DISTRIBUTED: 10-26-06
LD
NO./
. DESCRIPTION
BREAK
NEW ROUTE FROM SR 1660 (SILER RD) TO SR 1662 R/W FY2009
R-4748 (WILEY BROWN RD WILEY BROWN EXT) SOUTH OF CONST FY2010
US 441 NEAR FRANKLIN
R/VV FY
CONST FY
R/W FY_
CONST FY
ACCESS: FULL C/A ^ PARTIAL C/A ^ NO CONTROL ^
REVISION: NO
SCHEDULE
UNFUND ^ POST YRS ^
UNFUND ^ POST YRS ^
UNFUND ^ POST YRS ^
WBS ELEMENT NUMBER: 40118.1.1 COUNTY: MACON
ENGINEER: RON McCOLLUM /ROADWAY
SPECIAL INSTRUCTIONS:
NONE
TYPE OF PLANS FURNISHED FOR ESTIMATE: PRELIMINARY
DATE DUE: 01-02-07
PRIOR ESTIMATES OF LAND AND DAMAGES (WITH DATES):
N/A
IF INCREASES OR DECREASES ARE SIGNIFICANT, PLEASE EXPLAIN:
N/A
BASED ON PAST PROJECT HISTORICAL DATA, THE LAND AND DAMAGE FIGURES HAVE BEEN ADJUSTED BY A
FACTOR OF 50% TO INCLUDE CONDEMNATION AND ADMINISTRATIVE INCREASES THAT OCCUR DURING
SETTLEMNT OF ALL PARCELS. THESE FIGURES PROJECT THE MOST ACCURATE ACQUISITION ESTIMATES FOR 2
YEARS FROM THE DATE OF THIS ESTIMATE.
ESTIMATED BY: FORREST PONDER COMPLETED DATE: 01-02-07
A1.TF,RNATF,R
A B C D
ESTIMATED NO. OF PARCELS: 6 11 12 9
RESIDENTIAL RELOCATIONS: 0 / 0 0 / 0 2 / 30,000 2 / 30,000
BUSINESS RELOCATIONS: 0/ 0 0/ 0 0/ 0 0/ 0
LAND AND DAMAGE: 888,000 1,665,000 1,546,500 1,239,000
ACQUISTION: 35,000 65,000 80,000 62,000
TOTAL ESTIMATED R/W COST: £}2:3,(}(}(} I,~73(},I}(}(} 1,Ii ,(~,~;{}(} 1,:3:3I,0(}(}
THERE ARE NO FIGURES FOR UTILITY INVOLVEMENT ON THIS ESTIMATE.
REQUEST FOR R/W COST ESTIMATE
DATE RECEIVED: Ol-O8-07 DISTRIBUTED: 01-08-07
LD.NOJ
DESCRIPTION
BREAK
NEW ROUTE FROM SR 1660 (SILER RD) TO SR 1662 R/W FY2009
R-4748 (WILEY BROWN RD WILEY BROWN EXT) SOUTH OF CONST FY2010
US 441 NEAR FRANKLIN
R/W FY_
CONST FY
R/W FY_
CONST FY
ACCESS: FULL C/A ^ PARTIAL C/A ^ NO CONTROL ^
REVISION: YES
SCHEDULE
UNFUND ^ POST YRS ^
UNFUND ^ POST YRS ^
UNFUND ^ POST YRS ^
WBS ELEMENT NUMBER: 40118.1.] COUNTY: MACON
ENGINEER: RON McCOLLUM /ROADWAY
SPECIAL INSTRUCTIONS:
NONE
TYPE OF PLANS FURNISHED FOR ESTIMATE: PRELIMINARY
DATE DUE: 01-09-07
PRIOR ESTIMATES OF LAND AND DAMAGES (WITH DATES):
10-26-06
IF INCREASES OR DECREASES ARE SIGNIFICANT, PLEASE EXPLAIN:
N/A
BASED ON PAST PROJECT HISTORICAL DATA, THE LAND AND DAMAGE FIGURES HAVE BEEN ADJUSTED BY A
FACTOR OF 50% TO INCLUDE CONDEMNATION AND ADMINISTRATIVE INCREASES THAT OCCUR DURING
SETTLEMNT OF ALL PARCELS. THESE FIGURES PROJECT THE MOST ACCURATE ACQUISITION ESTIMATES FOR 2
YEARS FROM THE DATE OF THIS ESTIMATE.
ESTIMATED BY: FORREST PONDER COMPLETED DATE: Ol-O8-07
ALTF.RNATF..C
D
ESTIMATED NO. OF PARCELS: 19
RESIDENTIAL RELOCATIONS: 4 / 60,000
BUSINESS RELOCATIONS: 0 / 0
LAND AND DAMAGE: 2,205,000
ACQUISTION: 120,000
TOTAL ESTIMATED R/W COST: '3,~5>,IIt)()
THERE ARE NO FIGURES FOR UTILITY INVOLVEMENT ON THIS ESTIMATE.
NC-DOT
Project Services Unit
Preliminary Estimate Section
January 23, 2007 Revised Copy
Memo To: Paddy Jordan
Mulkey Engineers & Consultants
From: Doug Lane
Preliminary Estimate Engineer
Subject: Preliminary Construction Alternatives for the New Connector between SR 1660
and SR 1662 just South of US 441 in Franklin, TIP Project R-4748, Macon County.
ALTERNATE LENGTH CONSTR.COST
Miles
A 1.41 $6,800,000
A
Roundabout 1.41 $6,500,000
Option
B 1.47 $8,100,000
B
Roundabout 1.47 $7,900,000
Option
C 1.32 $7,400,000
C
Roundabout 1.32 $7,400,000
Option
D 0.68 $4,650,000
Note: Right-of-Way and RIW Utility Cost are not included in above costs.
cc:
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 ALTA County:
Route New Location
From Between SR 1660 (Sher Road) And SR 1662 (Wiley Brown Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder
Priced By: Doug Lane 1 /23/07 Revised Prices Only
Requested By: Mulkey Engineers & Consultants 8/21/06
Macon
CONSTR. COST
$6,800,000
Line
Item
Des
Sec No.
Description
Quantity
Unit
Price
Amount
Clearin and Grubbin 9.0 ACR $ 20,000.00 $ 180,000.00
Unclassified Excavation 117,100 CY $ 8.00 $ 936,800.00
Fine Gradin 27,210 SY $ 2.00 $ 54,420.00
Draina e 1.41 MI $ 150,000.00 $ 211,500.00
60" RC Pi e Culverts, Class III ],062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Mason Draina e Structures w / G & F 2 EA $ 3,000.00 $ 6,000.00
New Full De th Pavement 30,300 SY $ 40.00 $ 1,212,000.00
Resurface Pavement 3,200 SY $ 8.00 $ 25,600.00
Sub ade Stabilization 28,050 SY $ 5.00 $ 140,250.00
Pavement Removal 3,060 SY $ 3.00 $ 9,180.00
Pavement Break u 225 SY $ 2.00 $ 450.00
Steel Beam Guardrail 3,200 LF $ 15.00 $ 48,000.00
Sho Curve Steel Beam Guardrail 75 LF $ 25.00 $ 1,875.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e III 4 EA $ 1,300.00 $ 5,200.00
Guardrail Anchor Unit, T e 350 9 EA $ 1,800.00 $ 16,200.00
Guardrail Anchor Unit, T e CAT-1 1 EA $ 600.00 $ 600.00
SP Traffic Control 1 LS $ 25,000.00 $ 25,000.00
Thermo and Markers 1.41 Miles $ 20,000.00 $ 28,200.00
SP Erosion Control 10.5 ACR $ 15,000.00 $ 157,500.00
SP Traffic Si als at -64- & -ALTA- (Revised) 1 LS $ 70,000.00 $ 70,000.00
SP Traffic Si als at -ALTA- & -ALTAY2- (New) 1 LS $ 100,000.00 $ 100,000.00
SP New Structure over Water
360' x 32', ht = 21', Curve 90° Skew, Vert. Curve 11,520 SF $ 95.00 $ 1,094,400.00
Utilit Construction
Per Utilities Coordination Section 1 LS `~ t)£?,CiCiU.Oti $ 90,000.00
Misc. & Mob (10% Str & Utilities) 1 LS $ 118,627.00
Misc. & Mob (35% Rdwy) 1 LS $ 1,187,400.00
Lgth 1.41 Miles Contract Cost ...................................... $ 5,883,000.00
E. & C. 15% ...................................... $ 917,000.00
Construction Cost ...................................... $ 6,800,000.00
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 ALT B County
Route New Location
From Between SR 1660 (Sher Road) And SR 1662 (W iley Brown Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder
Priced By: Doug Lane 1/23/07 Revised Prices Only
Requested By: Mulkey Engineers & Consultants 8/21/06
Macon
CONSTR. COST
$8,100,000
Line
Item
Des
Sec No.
Description
Quantity
Unit
Price
Amount
Clearin and Grubbin 8.0 ACR $ 15,000.00 $ 120,000.00
Unclassified Excavation 321,400 CY $ 6.00 $ 1,928,400.00
Fine Gradin 25,300 SY $ 2.00 $ 50,600.00
Draina e 1.47 MI $ 150,000.00 $ 220,500.00
60" RC Pi e Culverts, Class III 1,062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Mason Draina e Structures w / G & F 2 EA $ 3,000.00 $ 6,000.00
New Full De th Pavement 28,700 SY $ 40.00 $ 1,148,000.00
Resurface Pavement 3,750 SY $ 8.00 $ 30,000.00
Sub ade Stabilization 25,900 SY $ 5.00 $ 129,500.00
Pavement Removal 3,070 SY $ 3.00 $ 9,21-0.00
Pavement Break u 1,020 SY $ 2.00 $ 2,040.00
Steel Beam Guardrail 3,350 LF $ 15.00 $ 50,250.00
Sho Curve Steel Beam Guardrail 150 LF $ 25.00 $ 3,750.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e III 4 EA $ 1,300.00 $ 5,200.00
Guardrail Anchor Unit, T e 350 13 EA $ 1,800.00 $ 23,400.00
Guardrail Anchor Unit, T e CAT-1 1 EA $ 600.00 $ 600.00
SP Traffic Control 1 LS $ 25,000.00 $ 25,000.00
Thermo and Markers 1.47 Miles $ 20,000.00 $ 29,400.00
SP Erosion Control 15.5 ACR $ 15,000.00 $ 232,500.00
SP Traffic Si als at -64- & -ALTB- (Revised) 1 LS $ 70,000.00 $ 70,000.00
SP Traffic Si als at -ALTO- & -ALTBY4- ew) 1 LS $ 100,000.00 $ 100,000.00
SP New Structure over Water
345' x 32', ht = 49', Tan ent 90° Skew, Vert. Curve 11,040 SF $ 90.00 $ 993,600.00
Utilit Construction
Per Utilities Coordination Section 1 LS `~ ~ti,000.{~t) $ 80,000.00
Misc. & Mob (10% Str & Utilities) 1 LS $ 107,252.00
Misc. & Mob (35% Rd ) 1 LS $ 1,522,000.00
Lgth 1.47 Miles Contract Cost ...................................... $ 7,051,000.00
E. & C. 15% ...................................... $ 1,049,000.00
Construction Cost ...................................... $ 8,100,000.00
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 ALTC County:
Route New Location
From Between SR 1660 (Sher Road) And SR 1662 (Wiley Brown Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder
Priced By: Doug Lane 1/23/07 Revised Prices Only
Requested Bv: Mulkev F.nuineerc Rr. ('nncnltant.c R/71 /(1F
Macon
CONSTR. COST
$7,400,000
Line
Item
Des
Sec No.
Description
Quantity
Unit
Price
Amount
Clearin and Grubbin 3.5 ACR $ 25,000.00 $ 87,500.00
Unclassified Excavation 203,200 CY $ 7.00 $ 1,422,400.00
Fine Gradin 27,460 SY $ 2.00 $ 54,920.00
Draina e 1.43 MI $ 150,000.00 $ 214,500.00
60" RC Pi e Culverts, Class III 1,062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Mason Draina e Structures w / G & F 2 EA $ 3,000.00 $ 6,000.00
New Full De th Pavement 26,300 SY $ 40.00 $ 1,052,000.00
Resurface Pavement 4,225 SY $ 8.00 $ 33,800.00
Sub rade Stabilization 27,930 SY $ 5.00 $ 139,650.00
Pavement Removal 6,800 SY $ 4.00 $ 27,200.00
Pavement Break u 940 SY $ 3.00 $ 2,820.00
Steel Beam Guardrail 2,850 LF $ 15.00 $ 42,750.00
Sho Curve Steel Beam Guardrail 75 LF $ 25.00 $ 1,875.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e III 4 EA $ 1,300.00 $ 5,200.00
Guardrail Anchor Unit, T e 350 11 EA $ 1,800.00 $ 19,800.00
Guardrail Anchor Unit, T e CAT-1 1 EA $ 600.00 $ 600.00
Greenway Trail Relocation (10' W x 470' L BST) 4,700 SF $ 5.00 $ 23,500.00
SP Traffic Control 1 LS $ 25,000.00 $ 25,000.00
Thermo and Markers 1.43 Miles $ 20,000.00 $ 28,600.00
SP Erosion Control 13.5 ACR $ 15,000.00 $ 202,500.00
SP Traffic Si nals at -64- & -ALTC- (Revised) 1 LS $ 70,000.00 $ 70,000.00
SP Traffic Si als at -ALTC- & -ALTCY4- (New) 1 LS $ 100,000.00 $ 100,000.00
New Structure over Water
380' x 32', ht = 55', Tan ent 90° Skew, Vert. Curve 12,160 SF $ 90.00 $ 1,094,400.00
Utilit Construction
Per Utilities Coordination Section 1 LS `~ 1 i~U.~i)~J.~)i) $ 160,000.00
Misc. & Mob (10% Str & Utilities) 1 LS $ 125,687.00
Misc. & Mob (35% Rd ) I LS $ 1,303,500.00
Lgth 1.43 Miles Contract Cost ...................................... $ 6,408,000.00
E. & C. 15% ...................................... $ 992,000.00
Construction Cost ........................ .............. $ 7,400,000.00
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748
Route New Location
From Between US 441 and SR 1660 (Sher Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder
Priced By: Doug Lane
Requested By: Mulkey Engineers & Consultants
ALT D
County: Macon
CONSTR. COST
$4,650,000
1/23/07 Revised Prices Only
8/26/06
Line
Item
Des
Sec No.
Description
Quantity
Unit
Price
Amount
Clearin and Grubbin 6.0 ACR $ 15,000.00 $ 90,000.00
Unclassified Excavation 14,900 CY $ 9.00 $ 134,100.00
Borrow 223,900 CY $ 8.00 $ 1,791,200.00
Fine Gradin 9,100 SY $ 2.00 $ 18,200.00
Draina e 0.68 MI $ 150,000.00 $ 102,000.00
New Full De th Pavement 10,000 SY $ 40.00 $ 400,000.00
Resurface Pavement 3,000 SY $ 8.00 $ 24,000.00
Sub ade Stabilization 10,500 SY $ 5.00 $ 52,500.00
Pavement Removal 950 SY $ 4.00 $ 3,800.00
Pavement Break u 100 SY $ 3.00 $ 300.00
Steel Beam Guardrail 3,225 LF $ 15.00 $ 48,375.00
Sho Curve Steel Beam Guardrail 75 LF $ 25.00 $ 1,875.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e 350 8 EA $ 1,800.00 $ 14,400.00
SP Traffic Control 1 LS $ 25,000.00 $ 25,000.00
Thermo and Markers 0.68 Miles $ 20,000.00 $ 13,600.00
SP Erosion Control 6.5 ACR $ 15,000.00 $ 97,500.00
SP Traffic Si nals at -ALTD- & US 441 (New) 1 LS $ 100,000.00 $ 100,000.00
Utilit Construction
Per Utilities Coordination Section 1 LS ~; i?(~,#}(?t~.~:i(} $ 80,000.00
Misc. & Mob 10% Str & Utilities) 1 LS $ 8,000.00
Misc. & Mob (35% Rd ) 1 LS $ 1,020,900.00
Lgth 0.68 Miles Contract Cost ...................................... $ 4,026,000.00
E. & C. l5% ...................................... $ 624,000.00
Construction Cost ...................................... $ 4,650,000.00
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 A Roundabout
Route New Location
From Between SR 1660 (Sher Road) And SR 1662 (Wiley Brown Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder
Priced By: Doug Lane
Requested Bv: Mulkev F.nQineers Sc ('~nsultantc
County: Macon
CONSTR.COST
$6,500,000
1/23/07 Revised Prices Only
R/71 /(1F
Item Des Sec No. Description Quantity Unit Price Amount
Clearin and Grubbin 9.0 ACR $ 15,000.00 $ 135,000.00
Unclassified Excavation 128,000 CY $ 8.00 $ 1,024,000.00
Fine Gradin 23,700 SY $ 2.00 $ 47,400.00
Draina e 1.41 MI $ 150,000.00 $ 211,500.00
60" RC Pi e Culverts, Class III 1,062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Mason Draina e Structures w / G & F 2 EA $ 3,000.00 $ 6,000.00
New Full De th Pavement 26,430 SY $ 40.00 $ 1,057,200.00
Resurface Pavement 3,200 SY $ 8.00 $ 25,600.00
Sub ade Stabilization 23,940 SY $ 5.00 $ 119,700.00
Pavement Removal 3,150 SY $ 3.00 $ 9,450.00
Pavement Break u 215 SY $ 2.00 $ 430.00
Steel Beam Guardrail 3,275 LF $ 15.00 $ 49,125.00
Sho Curve Steel Beam Guardrail 75 LF $ 25.00 $ 1,875.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e III 4 EA $ 1,300.00 $ 5,200.00
Guardrail Anchor Unit, T e 350 9 EA $ 1,800.00 $ 16,200.00
Guardrail Anchor Unit, T e CAT-1 1 EA $ 600.00 $ 600.00
Concrete Island 600 SY $ 55.00 $ 33,000.00
9" x 18" C&G 200 LF $ 35.00 $ 7,000.00
1' x 6" C&G 250 LF $ 30.00 $ 7,500.00
SP Traffic Control 1 LS $ 25,000.00 $ 25,000.00
Therom and Markers 1.41 Miles $ 20,000.00 $ 28,200.00
SP Erosion Control 10.5 ACR $ 15,000.00 $ 157,500.00
SP Traffic Si als at -64- & -ALTA- (Revised) 1 LS $ 70,000.00 $ 70,000.00
New Structure over Water
360'x 32', ht=21',Curve 90° Skew, Vert. Curve 11,520 SF $ 95.00 $ 1,094,400.00
Utilit Construction
Per Utilities Coordination Section 1 LS ~ 9~1,iit)(}.E}f) $ 90,000.00
Misc. & Mob (10% Str & Utilities) 1 LS $ 118,322.00
Misc. & Mob (35% Rd ) I LS $ 1,121,000.00
Lgtn 1.41 Miles Contract Cost .............. ........., .............. ~ 5,625,000.00
E. & C. 15% .............. ........................ $ 875,000.00
Construction Cost .............. ........., .............. $ 6,500,000.00
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 B Roundabout County:
Route New Location
From Between SR 1660 (Sher Road) And SR 1662 (Wiley Brown Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder and Roundabout Intersection
Priced By: Doug Lane 1/23/07 Revised Prices Only
Requested Bv: Mulkev Engineers & Consultants 7/12/06
Macon
CONSTR. COST
$7,900,000
Line
Item
Des
Sec No.
Description
Quantity
Unit
Price
Amount
Clearin and Grubbin 8.0 ACR $ 15,000.00 $ 120,000.00
Unclassified Excavation 333,200 CY $ 6.00 $ 1,999,200.00
Fine Gradin 23,100 SY $ 2.00 $ 46,200.00
Draina e 1.47 MI $ 150,000.00 $ 220,500.00
60" RC Pi e Culverts, Class III 1,062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Mason Draina e Structures w / G & F 2 EA $ 3,000.00 $ 6,000.00
New Full De th Pavement 25,260 SY $ 40.00 $ 1,010,400.00
Resurface Pavement 3,650 SY $ 8.00 $ 29,200.00
Sub ade Stabilization 22,300 SY $ 5.00 $ 111,500.00
Pavement Removal 3,170 SY $ 3.00 $ 9,510.00
Pavement Break u 1,020 SY $ 2.00 $ 2,040.00
Steel Beam Guardrail 3,350 LF $ 15.00 $ 50,250.00
Sho Curve Steel Beam Guardrail 150 LF $ 25.00 $ 3,750.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e III 4 EA $ 1,300.00 $ 5,200.00
Guardrail Anchor Unit, T e 350 13 EA $ 1,800.00 $ 23,400.00
Guardrail Anchor Unit, T e CAT-1 1 EA $ 600.00 $ 600.00
Concrete Island 600 SY $ 55.00 $ 33,000.00
9" x 18" C&G 200 LF $ 35.00 $ 7,000.00
1' x 6" C&G 250 LF $ 30.00 $ 7,500.00
SP Traffic Control 1 LS $ 25,000.00 $ 25,000.00
Thermo and Markers 1.47 Miles $ 20,000.00 $ 29,400.00
SP Erosion Control 15.5 ACR $ 15,000.00 $ 232,500.00
SP Traffic Si als at -64- & -ALTA- (Revised) 1 LS $ 70,000.00 $ 70,000.00
New Structure over Water
345' x 32', ht = 49', Tan ent 90° Skew, Vert. C 11,040 SF $ 90.00 $ 993,600.00
Utilit Construction
Per Utilities Coordination Section 1 LS ~ ~O,~Ot).JEI $ 80,000.00
Misc. & Mob (10% Str & Utilities) 1 LS $ 107,452.00
Misc. & Mob (35% Rd ) 1 LS $ 1,472,000.00
Lgth 1.47 Miles Contract Cost .............. ........................ $ 6,859,000.00
E. & C. 15% .............. ........................ $ 1,041,000.00
Construction Cost .............. ........................ $ 7,900,000.00
North Carolina Department of Transportation
Preliminary Estimate
TIP No. R-4748 C Roundabout County:
Route New Location
From Between SR 1660 (Siler Road) And SR 1662 (Wiley Brown Road)
Typical Section New Location 2-Lane w/ 4' Paved Shoulder and Roundabout Intersection
Priced By: Doug Lane 1/23/07 Revised Prices Only
Requested Bv: Mulkev Eneineers & Consultants 7/12/06
Macon
CONSTR.COST
$7,400,000
me
Item
Des
Sec No.
Description
Quantity
Unit
Price
Amount
Clearin and Grubbin 3.5 ACR $ 25,000.00 $ 87,500.00
Unclassified Excavation 215,000 CY $ 7.00 $ 1,505,000.00
Fine Gradin 26,750 SY $ 2.00 $ 53,500.00
Draina e 1.43 MI $ 150,000.00 $ 214,500.00
60" RC Pi e Culverts, Class III 1,062 LF $ 140.00 $ 148,680.00
Pi e Removal 1,062 LF $ 14.00 $ 14,868.00
Mason Draina eStructures w / G & F 2 EA $ 3,000.00 $ 6,000.00
New Full De th Pavement 25,600 SY $ 40.00 $ 1,024,000.00
Resurface Pavement 4,125 SY $ 8.00 $ 33,000.00
Sub rade Stabilization 27,230 SY $ 5.00 $ 136,150.00
Pavement Removal 6,900 SY $ 4.00 $ 27,600.00
Pavement Break u 940 SY $ 3.00 $ 2,820.00
Steel Beam Guardrail 2,850 LF $ 15.00 $ 42,750'.00
Sho Curve Steel Beam Guardrail 75 LF $ 25.00 $ 1,875.00
Additional Guardrail Posts 5 EA $ 50.00 $ 250.00
Guardrail Anchor Unit, T e III 4 EA $ 1,300.00 $ 5,200.00
Guardrail Anchor Unit, T e 350 11 EA $ 1,800.00 $ 19,800.00
Guardrail Anchor Unit, T e CAT-1 1 EA $ 600.00 $ 600.00
Concrete Island 600 SY $ 55.00 $ 33,000.00
9" x 18" C&G 200 LF $ 35.00 $ 7,000.00
1' x 6" C&G 250 LF $ 30.00 $ 7,500.00
Greenwa Trail Relocation 10' W x 470' L BS 4,700 SF $ 5.00 $ 23,500.00
SP Traffic Control 1 LS $ 25,000.00 $ 25,000.00
Therom and Markers 1.43 Miles $ 20,000.00 $ 28,600.00
SP Erosion Control 13.0 ACR $ 15,000.00 $ 195,000.00
SP Traffic Si als at -64- & -ALTA- Revised 1 LS $ 70,000.00 $ 70,000.00
New Structure over Water
380' x 32', ht = 55', Tan ent 90° Skew, Vert. C 12,160 SF $ 90.00 $ 1,094,400.00
Utilit Constructiou
Per Utilities Coordination Section 1 LS ~ '1 !;C~,~)(:~~.~}0 $ 160,000.00
Misc. & Mob 10% Str & Utilities 1 LS $ 124,907.00
Misc. & Mob (35% Rd ) 1 LS $ 1,300,000.00
Lgth 1.43 Miles Contract Cost .............. ........................ $ 6,393,000.00
E. & C. 15% .............. ........................ $ 1,007,000.00
Construction Cost .............. ........................ $ 7,400,000.00