ORANGE COUNTY
34'-ll" X 10'-4" ALUMINUM BOX
STA. 13+75 -L-
LICK CREEK
CULVERT PHASING
1.) 1NSTALL ALL SEDIMENT CONTROL DEVICES NECESSARY FOR CULVERT
CONSTRUCTION.
2.) INSTALL IMPERVIOUS DIKES. PUMP ALL EFFLUENT 1NT0 DIRT BAG.
1NSTALL PUMP AROUND.
3.) CONSTRUCT 34'-11" X 10'-4'' ALUMINUM BOX PER PLANS AND
SPECIFICATIONS.
4.) REMOVE IMPERVIOUS DIKES. CONSTRUCT NEW ROADWAY. COMPLETE
BANK STABILIZATION.
5.) UPON STABILIZATION OF ALL DISTURBED AREAS, REMOVE ALL
TEMPORARY SEDIMENT CONTROL DEVICES.
/
IMPERVIOUS DIKE