HomeMy WebLinkAbout20150615 Ver 1_SCM Calculations_20160625SCM Summary and Calculations
Project: Rockingham Grocery
704 U.S. 74 Business
City of Rockingham
Richmond County, NC
Project
Number: NCR151000
Client: GRDI, LLC
1500 Sunday Drive, STE. 101
Raleigh, NC 27607
Date: 2016.06.24
CA R�
° 0 FEssi°
4 _
GINE��°
Professional
Engineer: Mike Roselli, PE A • °R 201�o.O�o.24
NC License #040768
BOHLER ENGINEERING ♦ 4000 WESTCHASE BLVD ♦ SUITE 290 ♦ RALEIGH, NC 27607 ♦ 919.578.9000
Wet Pond Calculations
AVIIA
NCDENR
Permit No.
STORMWATER MANAGEMENT PERMIT APPLICATION FORM
401 CERTIFICATION APPLICATION FORM
WET DETENTION BASIN SUPPLEMENT
This form must be filled out, printed and submitted.
The Required Items Checklist (Part 111) must be printed, filled out and submitted along with all of the required information.
I. PROJECT INFORMATION
Project name Rockingham Grocery
Contact person Mike Roselli, PE
Phone number 919-578-9000
Date 6/24/2016
Drainage area number 1
(to be provided by DWQ)
��F \NA
_0A
oNiii�-c
II. DESIGN INFORMATION
Site Characteristics
Drainage area
111,514 ft2
Impervious area, post -development
90,169 ft2
% impervious
80.86 %
Design rainfall depth
1.0 in
Storage Volume: Non -SA Waters
Minimum volume required
Volume provided
Storage Volume: SA Waters
1.5" runoff volume
Pre -development 1 -yr, 24 -hr runoff
Post -development 1 -yr, 24 -hr runoff
Minimum volume required
Volume provided
Peak Flow Calculations
Is the prelpost control of the lyr 24hr storm peak flow required?
1 -yr, 24 -hr rainfall depth
Rational C, pre -development
Rational C, post -development
Rainfall intensity: 1 -yr, 24 -hr storm
Pre -development 1 -yr, 24 -hr peak flow
Post -development 1 -yr, 24 -hr peak flow
Pre/Post 1 -yr, 24 -hr peak flow control
Elevations
Temporary pool elevation
Permanent pool elevation
SHWT elevation (approx. at the perm. pool elevation)
Top of 1 Oft vegetated shelf elevation
Bottom of 1 Oft vegetated shelf elevation
Sediment cleanout, top elevation (bottom of pond)
Sediment cleanout, bottom elevation
Sediment storage provided
Is there additional volume stored above the state -required temp. pool?
Elevation of the top of the additional volume
7,227 ft3
7,461 ft3
OK, volume provided is equal to or in excess of volume required.
ft3
ft3
ft3
ft3
ft3
N (Y or N)
3.1 in
0.35 (unitless)
0.84 (unitless)
0.13 in/hr OK
N/A ft3/sec
N/A ft3/sec
#VALUE! ft3/sec
260.40 fmsl
259.00 fmsl
259.50 fmsl
259.50 fmsl
258.50 fmsl
254.00 fmsl
253.00 fmsl
1.00 ft
N (Y or N)
260.4 fmsl OK
Form SW401-Wet Detention Basin-Rev.9-4/18/12 Parts I. & II. Design Summary, Page 1 of 3
Permit No.
II. DESIGN INFORMATION
Surface Areas
Area, temporary pool 6,383 ft2
Area REQUIRED, permanent pool 3,791 ft2
SAIDA ratio 3.40 (unitless)
Area PROVIDED, permanent pool, Aperm_pool 4,298 ft2 OK
Area, bottom of 1 Oft vegetated shelf, Abot shelf 2,188 ft2
Area, sediment cleanout, top elevation (bottom of pond), Ayot_,nd 444 ft2
Volumes
ft
Length of flowpath to width ratio
Volume, temporary pool
OK
7,461 ft3
OK
Volume, permanent pool, Vpsnpool
Trash rack for overflow & orifice?
8,871 ft3
OK
Volume, forebay (sum of forebays if more than one forebay)
2.8 ft
1,614 ft3
Vegetated filter provided?
Forebay % of permanent pool volume
18.2% %
OK
SAIDA Table Data
Capures all runoff at ultimate build -out?
Y (Y or N)
OK
Design TSS removal
Pump
85 %
Coastal SAIDA Table Used?
N
(Y or N)
Mountain/Piedmont SAIDA Table Used?
Y
(Y or N)
SAIDA ratio
3.40 (unitless)
Average depth (used in SAIDA table):
Calculation option 1 used? (See Figure 10-2b)
N
(Y or N)
Volume, permanent pool, Vpertnyool
8,871 ft3
Area provided, permanent pool, Ape._p�l
4,298 ft2
Average depth calculated
ft
Need 3 ft min.
Average depth used in SAIDA, dav, (Round to nearest 0.5ft)
ft
Calculation option 2 used? (See Figure 10-2b)
Y
(Y or N)
Area provided, permanent pool, Ape,m_pool
4,298 ft2
Area, bottom of 1 Oft vegetated shelf, Abot shelf
2,188 ft2
Area, sediment cleanout, top elevation (bottom of pond), Ahot_pund
444 ft2
"Depth" (distance b/w bottom of 1Oft shelf and top of sediment)
4.50 ft
Average depth calculated
3.07 ft
OK
Average depth used in SAIDA, deV, (Round to down to nearest 0.5ft)
3.0 ft
OK
Drawdown Calculations
Drawdown through orifice?
Y
(Y or N)
Diameter of orifice (if circular)
1.50 in
Area of orifice (if -non -circular)
int
Coefficient of discharge (Co)
0.60 (unitless)
Driving head (Ho)
0.41 ft
Drawdown through weir?
N
(Y or N)
Weir type
N/A
(unitless)
Coefficient of discharge (CW)
N/A
(unitless)
Length of weir (L)
N/A
ft
Driving head (H)
N/A
ft
Pre -development 1 -yr, 24 -hr peak flow
N/A ft3/sec
Post -development 1 -yr, 24 -hr peak flow
N/A ft3 /sec
Storage volume discharge rate (through discharge orifice or weir)
0.04 ft3 /sec
Storage volume drawdown time
2.20 days
OK, draws down in 2-5 days.
Additional Information
Vegetated side slopes
Vegetated shelf slope
Vegetated shelf width
ft
Length of flowpath to width ratio
3 :1
OK
Length to width ratio
3.0 :1
OK
Trash rack for overflow & orifice?
Y (Y or N)
OK
Freeboard provided
2.8 ft
OK
Vegetated filter provided?
(Y or N)
Recorded drainage easement provided?
Y (Y or N)
OK
Capures all runoff at ultimate build -out?
Y (Y or N)
OK
Drain mechanism for maintenance or emergencies is:
Pump
(to be provided by DWQ)
Form SW401-Wet Detention Basin-Rev.9-4/18/12 Parts I. & II. Design Summary, Page 2 of 3
Permit No
III. REQUIRED ITEMS CHECKLIST
(to be provided by DWQ)
Please indicate the page or plan sheet numbers where the supporting documentation can be found. An incomplete submittal package will
result in a request for additional information. This will delay final review and approval of the project. Initial in the space provided to
indicate the following design requirements have been met. If the applicant has designated an agent, the agent may initial below.lf a
requirement has not been met, attach justification.
Pagel Plan
Initials Sheet No.
MR C-6.0.
1. Plans (1" 50' or larger) of the entire site showing:
See Sheet
Design at ultimate build -out,
C-3.1 for
Off-site drainage (if applicable),
Drainage
Delineated drainage basins (include Rational C coefficient per basin),
Areas
Basin dimensions,
Pretreatment system,
High flow bypass system,
Maintenance access,
Proposed drainage easement and public right of way (ROW),
Overflow device, and
Boundaries of drainage easement.
MR C-6.0
2. Partial plan (1" = 30' or larger) and details for the wet detention basin showing:
Outlet structure with trash rack or similar,
Maintenance access,
Permanent pool dimensions,
Forebay and main pond with hardened emergency spillway,
Basin cross-section,
Vegetation specification for planting shelf, and
Filter strip.
MR C-6.0
3. Section view of the wet detention basin 0" = 20' or larger) showing:
Side slopes, 3:1 or lower,
Pretreatment and treatment areas, and
Inlet and outlet structures.
MR C-5.1 4. If the basin is used for sediment and erosion control during construction, clean out of the basin is specified
on the plans prior to use as a wet detention basin.
MR REPORT 5. A table of elevations, areas, incremental volumes & accumulated volumes for overall pond and for forebay,
to verify volume provided.
MR C-5.1 6. A construction sequence that shows how the wet detention basin will be protected from sediment until the
entire drainage area is stabilized.
MR REPORT 7. The supporting calculations.
MR REPORT 8. A copy of the signed and notarized operation and maintenance (0&M) agreement.
N/A 9. A copy of the deed restrictions (if required).
MR REPORT 10. A soils report that is based upon an actual field investigation, soil borings, and infiltration tests. County
soil maps are not an acceptable source of soils information.
Form SW401-Wet Detention Basin-Rev.9-4/18/12 Part III. Required Items Checklist, Page 3 of 3
BOHLER
Project Information
Wet Detention Basin Design
Project: Rockingham Grocery
Location: 705 U.S. 74 Business
Project Number: NCR151000
Date: Jun -24-2016
Designed: MAR
Checked: WLB
Site Information
Sub Area Location: Wet Detention Basin 1
Drainage Area (DA) = 111,514 sf
Impervious Area (IA) = 90,169 sf
Percent Impervious (1) = 80.9 %
Elevations
Top of Bank Elevation =
264.00 ft
Emergency Elevation =
263.00 ft
Temporary Pool Elevation =
260.40 ft
Permanent Pool Elevation =
259.00 ft
Bottom of Pond Elevation =
254.00 ft
Sediment Cleanout, Bottom Elevation =
253.00 ft
Basin Areas/Volumes
Area of Permanent Pool =
4,298 sf
Area of Bottom of Shelf =
3,156 sf
Area of Bottom of Pond =
106 sf
Area of Temporary Pool =
6,432 sf
Volume, main pool =
7,257 cf
Volume, forebay (sum of forebays) =
1,614 cf
Volume, permanent pool =
8,871 cf
Forebay % of permanent pool volume =
18.2 %
Average Depth
Depth of Pond =
4.5 ft
Average Depth =
ft
Use Average Depth of =
0.00 ft
Required Surface Area
Aperm pooh (includes main pond & forebays) (Elev = 259.00 )
A bot shelf (includes main pond & forebays) (Elev = 258.50 )
Abot_pond (excluding sediment storage & forebays)
A tew_p-d (includes main pond and forebays) (Elev = 260.40 )
V malnl,00l (from Hydraflow)
V forebay (from Hydraflow)
V perm_,00l (Vforebay+Vmainyool)
OK
Depth (dist. btwn. bot. of shelf & btm. of pond, excludes sediment)
See Wet Basin Supplement
SA/DA = 3.4 (85% TSS Removal via Pond)
Min Req'd Surface Area = 3,791 sf (at Permanent Pool)
Required Storage Volume - Using Simple Method
Design Storm = 1.0 inch (Project Does Not Drain to SA Waters)
Determine Rv Value = 0.05 + 0.009 (1) = 0.78 in/in
Storage Volume Required = 7,227 cf (above Permanent Pool)
Side Slopes of Pond = 3 :1
Is Permenant Pool Surface Area Sufficient (yes/no)? Yes ( 4298 > 3791 ) sf
BOH LER
Wet Detention Basin Design
1.0 inch Volume Elevation
Required Temporary Pool Volume = 7,227
Elev (fmsl)
Permanent Pool Elevation = 259.00
Frustrum* Bottom Elevation = 260.00
Temporary Pool = 260.40
Frustrum* Top Elevation = 261.00
Temporary Pool Volume = 7,461
cu ft
Area (so
4,298
6,045
6,432
7,036
cu ft
*Frustrum bounds in which Temporary Pool will ultimately reside
Orifice Sizing - Wet Detention
Q2 Days =
0.0432
cfs
Q5 Days =
0.0173
cfs
Orifice Size =
1 1/2
in
259.00
Driving Head (He) =
0.44
ft
Q Orifice =
0.039
cfs
Drawdown Time =
2.2
days
less than 5 days (yes/no) ?
Yes
2,905
greater than 2 days (yes/no) ?
Yes
261.00
Anti -Flotation Device
6,534
11,901
Outside Length =
5.00
ft
Outside Width =
5.00
ft
Inside Length =
4.00
ft
Inside Width =
4.00
ft
Bottom Thickness =
0.50
ft
Top of Riser =
260.40
ft
Invert of Riser =
257.97
ft
Area =
25.0
sf
Volume =
73
cf
Weight=
4,571
lbs
Factor of Safety =
1.10
WT Req'd of Anti -Flotation Device =
5,028
lbs
Volume of Concrete Req'd =
57.4
cf
Depth Provided =
1.00
ft
Volume Provided =
59.4
cf
WT of Anti -Flotation Device Provided =
5,201
lbs
Contour
Contour
Area
Incremental Accumulated
Volume Volume, S
Stage, Z
sq ft
cu ft
cu ft
ft
259.00
4,298
0
0
0.0
259.50
5,577
2,462
2,462
0.5
260.00
6,045
2,905
5,367
1.0
261.00
7,036
6,534
11,901
2.0
262.00
7,798
7,414
19,315
3.0
263.00
8,595
8,193
27,508
4.0
264.00
9,428
9,008
36,516
5.0
(Flowrate required for a 2 day drawdown)
(Flowrate required for a 5 day drawdown)
(Diameter)
(Water Displaced - Top of Riser to Bottom of Riser)
(Weight Water Displaced)
(Unit WT of Concrete = 150 pcf) Submerged Concrete Unit Weight 87.6 pcf
Ce7P
)rebav volume
Contour
Area
al Volume
Accumulat
Stage, Z
Contour
Increment
ed
ft
Contour
Area
al Volume
Volume, S
Stage, Z
254.00
sq ft
cu ft
cu ft
ft
255.00
99
0
0
0.0
256.00
222
161
161
1.0
257.00
379
301
461
2.0
258.00
569
474
935
3.0
259.00
789
679
1,614
4.0
Contour
Area
al Volume
ed
Stage, Z
sq ft
cu ft
cu ft
ft
253.00
106
0
0
0.0
254.00
301
204
204
1.0
255.00
590
446
649
2.0
256.00
962
776
1,425
3.0
257.00
1,600
1,281
2,706
4.0
258.00
2,176
1,888
4,594
5.0
258.50
2,481
1,164
5,758
5.5
259.00
3,513
1,499
7,257
6.0
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2016 by Autodesk, Inc. v10.5
Hyd. No. 2
Wet Pond Routed
Hydrograph type
= Reservoir
Peak discharge
Storm frequency
= 10 yrs
Time to peak
Time interval
= 2 min
Hyd. volume
Inflow hyd. No.
= 1 - Wet Pond Inflow
Max. Elevation
Reservoir name
= Wet Pond Overall
Max. Storage
Storage Indication method used.
Q (cfs)
14.00
12.00
10.00
.m
4.00
2.00
0.00 ' 1-
0 120 240
Hyd No. 2
Wet Pond Routed
Hyd. No. 2 -- 10 Year
4
Friday, 06 / 24 / 2016
= 9.478 cfs
= 728 min
= 39,073 cuft
= 261.39 ft
= 15,110 cuft
Q (cfs)
14.00
12.00
10.00
4.00
f►a[iIi�
0.00
360 480 600 720 840 960 1080 1200 1320 1440 1560
Time (min)
Hyd No. 1 1111111 Total storage used = 15,110 cuft
10 -Year Velocity Exiting SCMS
Wetpond
CFS 9.48 ftA3/s (See routing)
Cross sectional area 7.07 ftA2 (Area of 18in pipe. Conservative, as flow is directed to wider dissipator pad)
Velocity 1.34 ft/s
Less than 2 ft/s? OK
Bioretention
CFS 2.86 ftA3/s (See routing)
Cross sectional area 3.60 ftA2 (0.24' depth in 10 -year storm x 15' spillway)
Velocity 0.79 ft/s
Less than 2 ft/s? OK
Permit Number:
(to be provided by DWQ)
Drainage Area Number:
Wet Detention Basin Operation and Maintenance Agreement
I will keep a maintenance record on this BMP. This maintenance record will be kept in a
log in a known set location. Any deficient BMP elements noted in the inspection will be
corrected, repaired or replaced immediately. These deficiencies can affect the integrity
of structures, safety of the public, and the removal efficiency of the BMP.
The wet detention basin system is defined as the wet detention basin,
pretreatment including forebays and the vegetated filter if one is provided.
This system (check one):
❑ does ® does not incorporate a vegetated filter at the outlet.
This system (check one):
❑ does ® does not incorporate pretreatment other than a forebay.
Important maintenance procedures:
— Immediately after the wet detention basin is established, the plants on the
vegetated shelf and perimeter of the basin should be watered twice weekly if
needed, until the plants become established (commonly six weeks).
— No portion of the wet detention pond should be fertilized after the first initial
fertilization that is required to establish the plants on the vegetated shelf.
— Stable groundcover should be maintained in the drainage area to reduce the
sediment load to the wet detention basin.
— If the basin must be drained for an emergency or to perform maintenance, the
flushing of sediment through the emergency drain should be minimized to the
maximum extent practical.
— Once a year, a dam safety expert should inspect the embankment.
After the wet detention pond is established, it should be inspected once a month and
within 24 hours after every storm event greater than 1.0 inches (or 1.5 inches if in a
Coastal County). Records of operation and maintenance should be kept in a known set
location and must be available upon request.
Inspection activities shall be performed as follows. Any problems that are found shall
be repaired immediately.
BMP element:
Potentialproblem:
How I will remediate theproblem:
The entire BMP
Trash/ debris is present.
Remove the trash/ debris.
The perimeter of the wet
Areas of bare soil and/or
Regrade the soil if necessary to
detention basin
erosive gullies have formed.
remove the gully, and then plant a
ground cover and water until it is
established. Provide lime and a
one-time fertilizer application.
Vegetation is too short or too
Maintain vegetation at a height of
long.
approximately six inches.
Form SW401-Wet Detention Basin O&M-Rev.4 Page 1 of 5
Permit Number:
(to be provided by DWQ)
Drainage Area Number:
BMP element:
Potentialproblem:
How I will remediate theproblem:
The inlet device: pipe or
The pipe is clogged.
Unclog the pipe. Dispose of the
swale
sediment off-site.
The pipe is cracked or
Replace the pipe.
otherwise damaged.
Erosion is occurring in the
Regrade the swale if necessary to
swale.
smooth it over and provide erosion
control devices such as reinforced
turf matting or riprap to avoid
future problems with erosion.
The forebay
Sediment has accumulated to
Search for the source of the
a depth greater than the
sediment and remedy the problem if
original design depth for
possible. Remove the sediment and
sediment storage.
dispose of it in a location where it
will not cause impacts to streams or
the BMP.
Erosion has occurred.
Provide additional erosion
protection such as reinforced turf
matting or riprap if needed to
prevent future erosion problems.
Weeds are present.
Remove the weeds, preferably by
hand. If pesticide is used, wipe it on
the plants rather than spraying.
The vegetated shelf
Best professional practices
Prune according to best professional
show that pruning is needed
practices
to maintain optimal plant
health.
Plants are dead, diseased or
Determine the source of the
dying.
problem: soils, hydrology, disease,
etc. Remedy the problem and
replace plants. Provide a one-time
fertilizer application to establish the
ground cover if a soil test indicates
it is necessary.
Weeds are present.
Remove the weeds, preferably by
hand. If pesticide is used, wipe it on
the plants rather than spraying.
The main treatment area
Sediment has accumulated to
Search for the source of the
a depth greater than the
sediment and remedy the problem if
original design sediment
possible. Remove the sediment and
storage depth.
dispose of it in a location where it
will not cause impacts to streams or
the BMP.
Algal growth covers over
Consult a professional to remove
50% of the area.
and control the algal growth.
Cattails, phragmites or other
Remove the plants by wiping them
invasive plants cover 50% of
with pesticide (do not spray).
the basin surface.
Form SW401-Wet Detention Basin O&M-Rev.4 Page 2 of 5
Permit Number:
(to be provided by DWQ)
Drainage Area Number:
BMP element:
Potentialproblem:
How I will remediate theproblem:
The embankment
Shrubs have started to grow
Remove shrubs immediately.
on the embankment.
Evidence of muskrat or
Use traps to remove muskrats and
beaver activity is present.
consult a professional to remove
beavers.
A tree has started to grow on
Consult a dam safety specialist to
the embankment.
remove the tree.
An annual inspection by an
Make all needed repairs.
appropriate professional
shows that the embankment
needs repair. if applicable)
The outlet device
Clogging has occurred.
Clean out the outlet device. Dispose
of the sediment off-site.
The outlet device is damaged
Repair or replace the outlet device.
The receiving water
Erosion or other signs of
Contact the local NC Division of
damage have occurred at the
Water Quality Regional Office, or
outlet.
the 401 Oversight Unit at 919-733-
1786.
The measuring device used to determine the sediment elevation shall be such
that it will give an accurate depth reading and not readily penetrate into
accumulated sediments.
When the permanent pool depth reads 5 feet in the main pond, the sediment
shall be removed.
When the permanent pool depth reads 3 feet in the forebay, the sediment shall
be removed.
BASIN DIAGRAM
ill in the blanks)
Permanent Pool Elevation 259
Sediment Removal q. 256 Pe anen Pool
-
----------------
- Volume Sediment Removal Elevation 254
----- ------
Toume
-----------------------
Bottom Elevation`255
1 -ft Min.
Sediment
Storage
FOREBAY
Bottom Elevation 253 1 -ft Min.
Sediment
Storage
MAIN POND
Form SW401-Wet Detention Basin O&M-Rev.4 Page 3 of 5
Permit Number:
(to be provided by DWQ)
Drainage Area Number:
Form SW401-Wet Detention Basin O&M-Rev.4 Page 4 of 5
Permit Number:
(to be provided by DWQ)
I acknowledge and agree by my signature below that I am responsible for the
performance of the maintenance procedures listed above. I agree to notify DWQ of any
problems with the system or prior to any changes to the system or responsible party.
Project name:LIDL Grocery Store - Rockingham, NC
BMP drainage area number: l
Print name:Ryan Wehmann
Title:Real Estate Manager - Development
Address: 1500 Sunday Drive, Suite 101, Raleigh, NC 27607
Note: The legally responsible party should not be a homeowners association unless more than 50% of
the lots have been sold and a resident of the subdivision has been named the president.
I, w'�_�P,u M, r^ul(p U q h , a Notary Public for the State of
N oh ✓ v()linc. ,County of W a ke , do hereby certify that
L y an W P h Mc,, n r\ personally appeared before me this -2- 1
day of An VI 1 7 Cl (� , and acknowledge the due execution of the
forgoing wet detention basin maintenance requirements. Witness my hand and official
seal, O -
PURL 'COU
_
X11111111\\
a W.11I
My commission expires hJpyrfflhe r 201 cl
Form SW401-Wet Detention Basin O&M-Rev.4 Page 5 of 5
Bioretention Calculations
Permit Number:
(to be provided by DWQ)
AUII'Ar
t r
NCDENR
STORMWATER MANAGEMENT PERMIT APPLICATION FORM
401 CERTIFICATION APPLICATION FORM
BIORETENTION CELL SUPPLEMENT
This form must be filled out, printed and submitted.
The Required Items Checklist (Part III) must be printed, filled out and submitted along with all of the required information.
I. PROJECT INFORMATION
10.9 hr
Project name
Rockingham
Contact name
Bohler Engineering NC, PLLC - Mike Roselli, PE
Phone number
919-578-9000
Date
2016.06.23
Drainage area number
2
II. DESIGN INFORMATION
N/A ft3/sec
Site Characteristics
Post -development 1 -yr, 24 -hr peak flow
Drainage area
46,827 ft2
Impervious area
36,810 ft2
Percent impervious
78.6% %
Design rainfall depth
1.0 inch
Peak Flow Calculations
10.9 hr
OK
Is pre/post control of the 1 -yr, 24 -hr peak flow required?
N (Y or N)
OK
1 -yr, 24 -hr runoff depth
3.1 in
1 -yr, 24 -hr intensity
0.35 in/hr
Pre -development 1 -yr, 24 -hr peak flow
N/A ft3/sec
OK
Post -development 1 -yr, 24 -hr peak flow
N/A ft3/sec
Pre/Post 1 -yr, 24 -hr peak control
#VALUE! ft3 /sec
OK
Storage Volume: Non -SA Waters
Minimum volume required
2,269.0 ft3
OK
Volume provided
2,285.0 ft3
OK
Storage Volume: SA Waters
1.5 runoff volume
ft3
Parts I and 11. Design Summary, Page 1 of 4
Pre -development 1 -yr, 24 -hr runoff
ft3
Post -development 1 -yr, 24 -hr runoff
ft3
Minimum volume required
0 ft3
Volume provided
ft3
Cell Dimensions
Ponding depth of water
10 inches
OK
Ponding depth of water
0.83 ft
Surface area of the top of the bioretention cell
2,385 ft'
OK
Length:
120 ft
OK
Width:
20 ft
OK
-or- Radius
ft
Media and Soils Summary
Drawdown time, ponded volume
10.9 hr
OK
Drawdown time, to 24 inches below surface
22 hr
OK
Drawdown time, total:
32.9 hr
In-situ soil:
Soil permeability
UNDERDRAINS in/hr
OK
Planting media soil:
Soil permeability
1.00 in/hr
OK
Soil composition
% Sand (by volume)
85%
OK
% Fines (by volume)
10%
OK
Form SW401-Bioretention-Rev.8
June 25, 2010
Parts I and 11. Design Summary, Page 1 of 4
% Organic (by volume) 5% OK
Total: 100%
Phosphorus Index (P -Index) of media
20 (unitless) OK
Permit Number:
(to be provided by DWQ)
Form SW401-Bioretention-Rev.8
June 25, 2010 Parts I and It. Design Summary, Page 2 of 4
Basin Elevations
Temporary pool elevation
Type of bioretention cell (answer "Y" to only one of the two following
questions):
Is this a grassed cell?
Is this a cell with trees/shrubs?
Planting elevation (top of the mulch or grass sod layer)
Depth of mulch
Bottom of the planting media soil
Planting media depth
Depth of washed sand below planting media soil
Are underdrains being installed?
How many clean out pipes are being installed?
What factor of safety is used for sizing the underdrains? (See
BMP Manual Section 12.3.6)
Additional distance between the bottom of the planting media and
the bottom of the cell to account for underdrains
Bottom of the cell required
SHWT elevation
Distance from bottom to SHWT
Internal Water Storage Zone (IWS)
Does the design include IWS
Elevation of the top of the upturned elbow
Separation of IWS and Surface
Planting Plan
Number of tree species
Number of shrub species
Number of herbaceous groundcover species
Additional Information
Does volume in excess of the design volume bypass the
bioretention cell?
Does volume in excess of the design volume flow evenly distributed
through a vegetated filter?
What is the length of the vegetated filter?
Does the design use a level spreader to evenly distribute flow?
Is the BMP located at least 30 feet from surface waters (50 feet if
SA waters)?
Is the BMP localed at least 100 feet from water supply wells?
Are the vegetated side slopes equal to or less than 3:1?
Is the BMP located in a proposed drainage easement with access
to a public Right of Way (ROW)?
Inlet velocity (from treatment system)
Is the area surrounding the cell likely to undergo development in the
future?
Are the slopes draining to the bioretention cell greater than 20%?
Is the drainage area permanently stabilized?
Pretreatment Used
(Indicate Type Used with an "X" in the shaded cell)
Gravel and grass
(8'inches gravel followed by 3-5 ft of grass)
Grassed swale
Forebay
Other
Form SW401-Bioretention-Rev.8
June 25, 2010
Permit Number:
(to be provided by DWQ)
269.33 fmsl
Y (Y or N) OK
N (Y or N)
268.5 fmsl
GRASSED inches Insufficient mulch depth, unless installing grassed cell.
265.5 fmsl
3 f
A474
Y (Y or N)
(2) 6" Drains OK
10 OK
1 f
264.33 fmsl
USING LINER fmsl
#VALUE! ft
N (Y or N)
fmsl
268.5 ft
0
0
SOD
Y (Y or N) OK
N/A
(Y or N)
Enter Data
N/A ft
N/A
(Y or N)
Enter Data
Y
(Y or N)
OK
Y
(Y or N)
OK
Y
(Y or N)
OK
Y
(Y or N)
OK
1 ft/sec OK
N (Y or N) OK
N (Y or N) OK
Y (Y or N) OK
X
OK
#VALUE!
#VALUE!
Parts I and It. Design Summary, Page 3 of 4
Permit No:
(to be assigned by DWQ)
Please indicate the page or plan sheet numbers where the supporting documentation can be found. An incomplete submittal package will
result in a request for additional information. This will delay final review and approval of the project. Initial in the space provided to
indicate the following design requirements have been met. If the applicant has designated an agent, the agent may initial below. If a
requirement has not been met, attach justification.
Pagel Plan
Initials Sheet No.
1. Plans (1" - 50' or larger) of the entire site showing:
Design at ultimate build -out,
Off-site drainage (if applicable),
Delineated drainage basins (include Rational C coefficient per basin),
Cell dimensions,
Pretreatment system,
High flow bypass system,
Maintenance access,
Recorded drainage easement and public right of way (ROW),
Clean out pipe locations,
Overflow device, and
Boundaries of drainage easement.
2. Plan details (1" = 30' or larger) for the bioretention cell showing:
- Cell dimensions
Pretreatment system,
High flow bypass system,
Maintenance access,
Recorded drainage easement and public right of way (ROW),
Design at ultimate build -out,
Off-site drainage (if applicable),
Clean out pipe locations,
Overflow device, and
Boundaries of drainage easement.
Indicate the P -Index between 10 and 30
3. Section view of the bioretention cell (1" = 20' or larger) showing:
- Side slopes, 3:1 or lower
Underdrain system (if applicable), and
Bioretention cell layers [ground level and slope, pre-treatment, ponding depth, mulch depth, fill media
depth, washed sand, filter fabric (or choking stone if applicable), #57 stone, underdrains (if applicable),
SHWT level(s), and overflow structure]
4. A soils report that is based upon an actual field investigation, soil borings, and infiltration tests. The
results of the soils report must be verified in the field by DWQ, by completing & submitting the soils
investigation request form. County soil maps are not an acceptable source of soils information. All
elevations shall be in feet mean sea level (fmsl). Results of soils tests of both the planting soil and the in
situ soil must include:
Soil permeability,
Soil composition (% sand, % fines, % organic), and
P -index.
5. A detailed planting plan (1" = 20' or larger) prepared by a qualified individual showing:
A variety of suitable species,
Sizes, spacing and locations of plantings,
Total quantity of each type of plant specified,
A planting detail,
The source nursery for the plants, and
Fertilizer and watering requirements to establish vegetation.
6. A construction sequence that shows how the bioretention cell will be protected from sediment until the
entire drainage area is stabilized.
7. The supporting calculations (including underdrain calculations, if applicable).
8. A copy of the signed and notarized inspection and maintenance (AM) agreement.
9. A copy of the deed restriction.
Form SW401-Bioretention-Rev.7 Part III, Page 4 of 4
® B O I LER
Bioretention Basin 1
Project Information
7.81 ?
Ql/2D,=
Project Name:
Rockingham
(Flowrate for a 12 hr drawdown)
Project #:
NCR151000
in
Designed by:
MAR
Date: 6/24/2016
Checked by:
WLB
Date: 6/24/2016
Site Information
cfs
Sub Area Location:
Bioretention
Basin 1
Drainage Area (DA) =
46,827
at
Impervious Area (IA) =
36,810
at
Percent Impervious (I) =
78.6
Submerged Concrete Unit Weight 87.6
Elevations
24
in
Top of Bank Elevation =
270.70
ft
Top of Spillway Elevation =
269.33
ft
Top of Cell Elevation =
268.50
ft
Bottom of Cell Elevation =
264.50
ft
Invert Elevation =
264.00
ft
Basin AreaslVolumes
less than 12 hours (yes/no) ?
Area of Bottom of Cell=
2,385
sf
Volume of Basin=
2,285
cf
Required Storage Volume - Using Simple Method
1
Design Storm =
1
inch (Project Does Not Drain to SA waters)
Determine Rv Value =
0.05 + 0.009 (I)
= 0.76 in/in
Storage Volume Required =
2,956
cf
Required Storage Volume - Using Discrete SCS Method
Flow (Q) =
Impervious Area
cfs
CN =
98
S= 0.20 P = 1.43
Q =
0.74
in
Storage =
2,269
cf (above Permanent Pool)
Pervious Area
5.60
USE 2, 6" underdrains
CN =
39
S= 15.64 P = 1.43
Q =
N/A
in
Storage =
N/A
Storage Volume Required = 2,269
Orifice Sizing - Drawdown
If D is less than R of o"
5.13 2
7.81 ?
Ql/2D,=
0.0529
cfs
(Flowrate for a 12 hr drawdown)
Orifice Size =
1 1/2
in
(Diameter)
Driving Head (Ho) =
1.76
ft
(Weight of Water Displaced)
Go-=
0.078
cfs
Drawdown Time =
8.1
hours
less than 12 hours (yes/no) ?
Yes
(Unit WT of Concrete = 150 pcf)
Media Drawdown
0.0
cf
Submerged Concrete Unit Weight 87.6
Inches Below Surface =
24
in
Q1/2 D-=
0.0596
cfs
(Flowrate for a 12 hr drawdown)
Driving Head (Ho) =
1.48
ft
concrete)
Q oma =
0.072
cfs
INCORRECT
Drawdown Time =
10.0
hours
less than 12 hours (yes/no) ?
Yes
Underdrain Sizing
D=16((Q-N)/SA.5))A(3/8)
Media Infiltration Rate =
1
in/hr
Flow Rate Through Media =
0.0552
cfs
Factor of Safety
10
Flow (Q) =
0.5521
cfs
Roughness Coefficient (n) =
0.011
Slope =
0.01
D =
5.60
USE 2, 6" underdrains
BMP Manual. Cheater 5 - Table 5-1
If D is less than N of {"
If D is less than R of o"
5.13 2
7.81 ?
5.95 3
9.11 3
o.tab 4
10.1? d
Displaced Volume =
0
7.75
Bottom of Riser)
8.'17
0
Anti -Flotation Device N/A - no outlet structure proposed
Outside Length = ft
Outside Width = ft
Inside Length = It
Inside Width = ft
Bottom Thickness = ft
Top of Riser = sf
Invert of Riser = ft
Displaced Area =
0.0
sf
(Outside Dim. = x, Inside Dim. = x)
(Water Displaced - Top of Riser to
Displaced Volume =
0
cf
Bottom of Riser)
Displaced Weight=
0
lbs
(Weight of Water Displaced)
Factor of Safety =
1.10
WT Req'd of Anti -Flotation Device =
0
lbs
(Unit WT of Concrete = 150 pcf)
Volume of Concrete Req'd =
0.0
cf
Submerged Concrete Unit Weight 87.6
Depth Provided =
2.00
ft
(4 -ft x 4 -ft Box filled 2 -ft deep vrith
Volume Provided =
0.0
cf
concrete)
WT of Anti -Flotation Device Provided =
0
lbs
INCORRECT
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2016 by Autodesk, Inc. v10.5
Hyd. No. 4
Bioretention Routed
Hydrograph type
= Reservoir
Peak discharge
Storm frequency
= 10 yrs
Time to peak
Time interval
= 2 min
Hyd. volume
Inflow hyd. No.
= 3 - Bioretention Inflow
Max. Elevation
Reservoir name
= Bioretention
Max. Storage
Storage Indication method used.
Q (cfs)
4.00
3.00
2.00
1.00
Bioretention Routed
Hyd. No. 4 -- 10 Year
1
Friday, 06 / 24 / 2016
= 2.859 cfs
= 728 min
= 11,184 cuft
= 269.57 ft
= 3,199 cuft
0.00 ' '
0 240 480 720 960 1200 1440 1680 1920
Hyd No. 4 Hyd No. 3 1111111 Total storage used = 3,199 cuft
Q (cfs)
4.00
3.00
2.00
1.00
---.4 0.00
2160
Time (min)
10 -Year Velocity Exiting SCMS
Wetpond
CFS 9.48 ftA3/s (See routing)
Cross sectional area 7.07 ftA2 (Area of 18in pipe. Conservative, as flow is directed to wider dissipator pad)
Velocity 1.34 ft/s
Less than 2 ft/s? OK
Bioretention
CFS 2.86 ftA3/s (See routing)
Cross sectional area 3.60 ftA2 (0.24' depth in 10 -year storm x 15' spillway)
Velocity 0.79 ft/s
Less than 2 ft/s? OK
Permit Number:
(to be provided by DWQ)
Drainage Area Number:
Bioretention Operation and Maintenance Agreement
I will keep a maintenance record on this BMP. This maintenance record will be kept in a
log in a known set Iocation. Any deficient BMP elements noted in the inspection will be
corrected, repaired or replaced immediately. These deficiencies can affect the integrity
of structures, safety of the public, and the removal efficiency of the BMP.
Important operation and maintenance procedures:
Immediately after the bioretention cell is established, the plants will be watered
twice weekly if needed until the plants become established (commonly six
weeks).
Snow, mulch or any other material will NEVER be piled on the surface of the
bioretention cell.
— Heavy equipment will NEVER be driven over the bioretention cell.
— Special care will be taken to prevent sediment from entering the bioretention cell.
— Once a year, a soil test of the soil media will be conducted.
After the bioretention cell is established, I will inspect it once a month and within 24
hours after every storm event greater than 1.0 inches (or 1.5 inches if in a Coastal
County). Records of operation and maintenance will be kept in a known set location
and will be available upon request.
Inspection activities shall be performed as follows. Any problems that are found shall
be repaired immediately.
BMP element:
Potentialproblems:
How I will remediate theproblem:
The entire BMP
Trash/debris is present.
Remove the trash/ debris.
The perimeter of the
Areas of bare soil and/or
Regrade the soil if necessary to
bioretention cell
erosive gullies have formed.
remove the gully, and then plant a
ground cover and water until it is
established. Provide lime and a
one-time fertilizer application.
The inlet device: pipe,
The pipe is clogged (if
Unclog the pipe. Dispose of the
stone verge or swale
applicable).
sediment off-site.
The pipe is cracked or
Replace the pipe.
otherwise damaged (if
applicable).
Erosion is occurring in the
Regrade the swale if necessary to
swale (if applicable).
smooth it over and provide erosion
control devices such as reinforced
turf matting or riprap to avoid
future problems with erosion.
Stone verge is clogged or
Remove sediment and clogged
covered in sediment (i£
stone and replace with clean stone.
applicable).
Form SW40 I -Bioretention O&M-Rev.3 Page 1 of 4
SMP element:
Potentialproblems:
How I will remediate theproblem:
The pretreatment area
Flow is bypassing
Regrade if necessary to route all
pretreatment area and/or
flow to the pretreatment area.
allies have formed.
Restabilize the area after grading.
Sediment has accumulated to
Search for the source of the
a depth greater than three
sediment and remedy the problem if
inches.
possible. Remove the sediment and
restabiIize the pretreatment area.
Erosion has occurred.
Provide additional erosion
protection such as reinforced turf
matting or riprap if needed to
prevent future erosion problems.
Weeds are present.
Remove the weeds, preferably by
hand.
The bioretention cell:
Best professional practices
Prune according to best professional
vegetation
show that pruning is needed
practices.
to maintain optimal plant
health.
Plants are dead, diseased or
Determine the source of the
dying.
problem: soils, hydrology, disease,
etc. Remedy the problem and
replace plants. Provide a one-time
fertilizer application to establish the
ground cover if a soil test indicates
it is necessary.
Tree stakes/wires are present
Remove tree stake/ wires (which
six months after planting.
can kill the tree if not removed).
The bioretention cell:
Mulch is breaking down or
Spot mulch if there are only random
soils and mulch
has floated away.
void areas. Replace whole mulch
Iayer if necessary. Remove the
remaining much and replace with
triple shredded hard wood mulch at
a maximum depth of three inches.
Soils and/or mulch are
Determine the extent of the clogging
clogged with sediment.
- remove and replace either just the
top layers or the entire media as
needed. Dispose of the spoil in an
appropriate off-site location. Use
triple shredded hard wood mulch at
a maximum depth of three inches.
Search for the source of the
sediment and remedy the problem if
possible.
An annual soil test shows that
Dolomitic lime shall be applied as
pH has dropped or heavy
recommended per the soil test and
metals have accumulated in
toxic soils shall be removed,
the soil media,
disposed of properly and replaced
with new planting media.
Form SW401-Bioretention O&M-Rev.3 Page 2 of 4
BMP element:
Potentialproblems:
How I will remediate theproblem:
The underdrain system
Clogging has occurred.
Wash out the underdrain system.
if applicable)
The drop inlet
Clogging has occurred.
Clean out the drop inlet. Dispose of
the sediment off-site.
The drop inlet is damaged
Repair or replace the drop inlet.
The receiving water
Erosion or other signs of
Contact the NC Division of Water
damage have occurred at the
Quality 401 Oversight Unit at 919 -
outlet.
733-1786.
Form SW401 -Bioretention O&M-Rev.3 Page 3 of 4
Permit Number:
(to be provided by DWQ)
I acknowledge and agree by my signature below that I am responsible for the
performance of the maintenance procedures listed above. I agree to notify DWQ of any
problems with the system or prior to any changes to the system or responsible party.
Project name:LIDL Grocery Store - Rockingham, NC
BMP drainage area number:2
Print name: Joseph Gallo
Title: Development - Construction Manager
Address: 1500 Sunday Drive, Suite 101, Raleigh, NC 27607
Phone: (703) 408-5643
Si
Date:
Note: The legally responsible party should not be a homeowners association unless more than 50% of
the lots have been sold and a resident of the subdivision has been named the president.
I, s&nX'2A R. C41.5 et n , a Notary Public for the State of
NO (kk) (911 Y)OLCounty of W CLZ--Z , do hereby certify that
Jo 5i G-� OL 1 I U personally appeared before me this L,401
day of J"-[, , U i �, and acknowledge the due execution of the
forgoing bioretention maintenance requirements. Witness my hand and official seal,
EN
SEAL„
My commission expires r
Form SW401-Bioretention I&M-Rev. 2 Page 4 of 4
Geotechnical Reports
GEOTECHNICAL EXPLORATION REPORT
PROPOSED RETAIL DEVELOPMENT
MGP PROJECT #P000339 / BOHLER PROJECT #NCC142080
HAMLET AVENUE (US 7413)
ROCKINGHAM, NORTH CAROLINA
S&ME, INC. PROJECT NO. 1305-15-022
Prepared for:
Bohler Engineering, NC, PLLC
4011 WestChase Boulevard, Suite 290
Raleigh, North Carolina 27607
MGP Retail Consulting, LLC
1500 Sunday Drive, Suite 101
Raleigh, North Carolina 27607
Prepared By:
S&ME, Inc.
3201 Spring Forest Road
Raleigh, North Carolina 27616
N.C. Firm License No. F-0176
April 2, 2015
April 2, 2015
Bohler Engineering, NC, PLLC
4011 WestChase Boulevard
Raleigh, North Carolina 27607
Attention: Mr. Chris Capellini
ccapellini(a,bohlerenp—com
Reference: Geotechnical Exploration Report
Proposed Retail Development
Hamlet Avenue (US 74B)
Rockingham, North Carolina
S&ME Project No. 1305-15-022
Bohler Project No. NCC142080
MGP Retail Project No. P000339
Dear Mr. Capellini,
S&ME, Inc. (S&ME) is pleased to submit this geotechnical exploration report for the referenced
project. Our services were performed in general accordance with executed WA#1 dated March
16, 2015 and the "Subconsultant Master Agreement" between Bohler Engineering and S&ME,
Inc. dated June 20, 2014. This report presents a summary of our understanding of the project, the
findings of our field exploration, laboratory test results, and our geotechnical conclusions and
recommendations regarding site grading and building/pavement support. Our exploration was
performed in general accordance with item 9 of the MGP Retail Environmental and Geotechnical
Scope of work.
We appreciate the
If you have any qt
Sincerely,
S& Inc.
Keith Brown, P.E.
,Work with Bohler Engineering during this phase of the project.
gpisxeport, please contact us.
n,
9°
e
S L <g -
0
.s•• 0
%Ari ti
Senior Geotechnical EngineerNice President
NC Registration No. 022540
Adam Browning, P.E.
Project Manager
TAProjects\2015\GE0\1305-15-022 MGP Realty-Rockingham\Deliverables\1305-15-022 MGP Rockingham Initial Report.doc
S&ME, INC. / 3201 Spring Forest Road / Raleigh, NC 27616 / p 919.872.2660 / IF 919.876.3958 / www.smeinc.com
Geotechnical Exploration Report S&ME Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
TABLE OF CONTENTS
PAGE
1.
PROJECT INFORMATION.................................................................................... 1
2.
EXPLORATION PROGRAM................................................................................. 2
2.1 Field....................................................................................................................
2
2.2 Laboratory...........................................................................................................3
3.
AREA GEOLOGY.................................................................................................... 3
4.
SUBSURFACE CONDITIONS................................................................................ 3
4.1 Laboratory Testing.............................................................................................. 4
5.
CONCLUSIONS AND RECOMMENDATIONS.................................................. 5
5.1 Site Preparation................................................................................................... 6
5.2 Structural Fill...................................................................................................... 7
5.2.1 Structural Fill.......................................................................................... 7
5.2.2 Fill Placement......................................................................................... 7
5.3 Subgrade Evaluation and Repair......................................................................... 8
5.4 Excavations.........................................................................................................
8
6.
BUILDING FOUNDATION DESIGN AND CONSTRUCTION ......................... 8
6.1 Bearing Pressure................................................................................................. 8
6.2 Bearing Depth and Dimension............................................................................
9
6.3 Settlement...........................................................................................................
9
7.
FLOOR SLAB............................................................................................................ 9
8.
RETAINING WALL PARAMETERS..................................................................
10
8.1 Retaining Walls - General.................................................................................
10
8.2 Cast -In -Place Concrete Walls...........................................................................
10
8.3 Mechanically Stabilized Earth (MSE) Walls ....................................................
11
9.
SEISMIC CONSIDERATIONS.............................................................................
12
10.
PAVEMENTS.................................................................................................12
11.
LIMITATIONS OF REPORT.......................................................................
13
FIGURES
Figure 1 Exploration Location Plan
Figure 2 Alta Survey
Figure 3 Generalized Subsurface Conditions
APPENDICES
Appendix I Legend
Boring Logs
Appendix II
Laboratory Test Results Summary Table
Laboratory Test Results
Geotechnical Exploration Report S&ME Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
1. PROJECT INFORMATION
Information for this project is based on the following:
Section 9 MGP Geotechnical Scope of Work, undated, provided by Bohler
Engineering via email on January 20, 2015.
Bohler Engineering email requesting geotechnical services on March 3, 2015 with
attachments including a site plan prepared by Bohler Engineering, dated February
24, 2015.
Alta survey provided by Bohler Engineering.
Google Earth aerial image.
We understand that a retail development is planned north of US 74 Business and west of
an existing Zaxby's in Rockingham, North Carolina. The 5.15 +/- acre site is currently
moderately to heavily wooded. Portions of the site appears to have been previously
developed and has also been used as a dumping area. A stockpile of soil was observed in
the vicinity of boring P-2. Miscellaneous construction debris was observed randomly
across the site. An apartment complex is currently under construction, just north of the
proposed site. A sedimentation basin is located immediately adjacent to the northern
property line, just north of the building. The basin discharges water onto the site in the
vicinity of the northern most proposed detention pond.
*Based map obtained from Google Earth (Imagery Date 11/30/2014).
Geotechnical Exploration Report SWE Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
The retail building will have a plan area of about 36,000 square feet with 175 space
parking lot with associated drive areas. We understand that two BMP's were to be
located on the site, one in the southwest corner of the site and another east of the access
drive off US 74 B. The northern most BMP has been eliminated due to its proximity to
existing wetland areas. The finished floor elevation is estimated at 272 feet by Bohler.
No grading plans are currently available.
We understand the building will consist of a pre-engineered metal structure with concrete
slab -on -grade floor. No structural loading was provided, but we have assumed maximum
column and wall loads of 100 kips and 3 kips per linear foot, respectively. Estimated
maximum uniform floor slab live load is 125 pounds per square foot (psf) and the
maximum floor slab concentrated load is 5 kips.
The site is moderately to heavily wooded. Wetland areas have been identified onsite but
not confirmed with the Army Corps of Engineers. The existing wetland areas are shown
on the attached Figure 1. Existing site elevations range from 275 feet along the eastern
property line to 259 feet along the western property line.
2. EXPLORATION PROGRAM
2.1 Field
The subsurface exploration program for this project included a visual site reconnaissance
by representatives of S&ME and performance of 11 Standard Penetration Test (SPT)
borings. Test locations were selected by S&ME and located in the field by estimating
distances from existing site features. Approximate test locations are shown on Figure 1
in the Appendix. Elevations were estimated from an Alta Survey provided by Bohler
Engineering (Figure 2) and should be considered approximate.
SPT = Standard Penetration Test
Standard Penetration Test borings were performed using an ATV -mounted CME 550X drill
rig. A 3-t/4 inch hollow stem auger was used to advance the borings. Split -spoon samples
of subsurface soils were taken at approximate 2.5 foot intervals above a depth of 10 feet and
at 5 foot intervals below 10 feet. Standard penetration tests were conducted in conjunction
with split -spoon sampling in general accordance with ASTM D 1586-11. The drill rig is
equipped with an autohammer.
Depths
Exploration
Explored
Test Locations Location
Method
Below Existing
Grade (feet)
B-1 — B-5 Retail Building
SPT
20 to 40
P-1 through P-3 Parking/Access Drive Areas
SPT
10
D-1 through
BMP's
D-3
SPT
10
SPT = Standard Penetration Test
Standard Penetration Test borings were performed using an ATV -mounted CME 550X drill
rig. A 3-t/4 inch hollow stem auger was used to advance the borings. Split -spoon samples
of subsurface soils were taken at approximate 2.5 foot intervals above a depth of 10 feet and
at 5 foot intervals below 10 feet. Standard penetration tests were conducted in conjunction
with split -spoon sampling in general accordance with ASTM D 1586-11. The drill rig is
equipped with an autohammer.
Geotechnical Exploration Report SWE Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
Three bulk samples of auger cuttings were collected from boring B-4 from 1 to 5 feet and D-
2 from 1 to 5 feet and 5 to 10 feet. Boreholes were observed for groundwater at completion
of drilling and in selected boreholes after a period of 24 hours. At completion of drilling
operations, representative soil samples were returned to our laboratory for quantitative
testing and visual classification in general accordance with Unified Soil Classification
System guidelines. Soil samples will be stored in our Greensboro laboratory for a
minimum of 6 months, and can be stored for a longer period, if requested.
A Profile of Generalized Subsurface Conditions (Figure 3) along with Boring Log
records are included in the Appendix. Stratification lines shown on Boring Logs and
profile are intended to represent approximate depths of changes in soil types. Naturally,
transitional changes in soil types are often gradual and cannot be defined at particular
depths.
2.2 Laboratory
Laboratory testing was performed on bulk and split -spoon samples obtained from
selected boreholes and depths. Laboratory testing included natural moisture content,
standard Proctor compaction, California Bearing Ratio (CBR), Atterberg Limits, and
grain size distribution. All laboratory testing was performed in general accordance with
applicable ASTM standards.
3. AREA GEOLOGY
The site is located within the Coastal Plain Physiographic Province of North Carolina.
The Coastal Plain Province is typically characterized by marine and eolian sediments that
were deposited during periods of fluctuating sea levels and moving shore lines. As such,
the Coastal Plain Province is characterized by subdued topographic features and flat low-
lying terrain. Near surface soils often consist of more recent undifferentiated deposits of
interbedded sand, silts and clays. Deeper deposits also consist of sand, silts and clays but
can be defined as particular formations with distinguishable characteristics and
engineering properties. The primary geologic formation within the area of the site is the
Middendorf Formation. The Middendorf Formation is typically sand, sandstone and
mudstone that is gray to pale gray with an orange cast. Clay balls and iron -cemented
concentrations are common, beds laterally discontinuous and cross -bedding is common.
4. SUBSURFACE CONDITIONS
The description of subsurface conditions provided below is relatively brief and general.
More detailed descriptions of conditions at each location are included on individual
Boring Logs in Appendix II.
Topsoil was encountered in all of the soil test borings to depths ranging from 3 to 6
inches below the existing ground surface. The near surface soils were significantly wet
as you move toward and into the approximate wetland areas. Several hand auger borings
were performed in the wetland areas. Topsoil thicknesses of 12 inches were observed in
this area along with near surface groundwater conditions.
Geotechnical Exploration Report S&ME Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
Fill soil was encountered in borings B-3 and P-2 to a depth of 3 feet below existing
ground surface. The fill was generally comprised of silty and clayey sands (Unified Soil
Classifications SM and SC) with a Standard Penetration Test (SPT) N -value of 2 to 6
blows per foot (bpf). The SPT N -values are indicative of poorly compacted materials.
Coastal Plain soils were encountered underlying the fill at the above mentioned borings
and below the topsoil in the remaining borings. The natural soils generally consisted of
very loose to dense silty sands (SM) and clayey sands (SC), and soft to very stiff sandy
clays and silty clays (CL). SPT N -values in the Coastal Plain soils ranged from 2 to 51
bp£ Each boring was terminated in coastal plain soils at depths of 10 to 40 feet below the
existing ground surface.
No partially weathered rock (PWR) or auger refusal was encountered in the performed
borings.
Water level measurements were attempted in open boreholes at the termination of drilling
and in several borings following a period of 24 hours. Groundwater was encountered in
borings B-1 through B-4, D-1 through D-3 and P-2 and P-3 at depths ranging from the
ground surface to 8 feet below the existing ground surface. Boreholes B-5 and P-1 caved
at depths of 6 to 11 feet below existing ground surface. Borehole cave depths are
typically an indication groundwater is present. It is important to realize that groundwater
levels will fluctuate with changes in rainfall and evaporation rates. Additionally, perched
water conditions may exist during the typically wetter winter months above less
permeable fine-grained soils. Past experience with similar soil conditions indicates that
perched water will be present during wet periods of the year.
4.1 Laboratory Testing
Laboratory testing included natural moisture content, standard Proctor compaction,
California Bearing Ratio (CBR), consolidation, Atterberg Limits, and grain size
distribution.
Natural moisture content testing was performed on selected split -spoon and bulk samples.
Natural moisture content testing indicated moisture contents ranging from 12.3 to 22.1
percent.
Atterberg limits testing was performed on split -spoon and bulk samples obtained from B-
5 (3.5-5 feet), D-1 (1-2.5 feet) and D-2 (1-5 feet). Testing indicated liquid limits ranging
from 28 to 52 percent, plastic limits ranging from 13 to 21 percent, and plasticity indices
ranging from 15 to 31 percent. These values are indicative of low to moderate plasticity
soils.
Geotechnical Exploration Report SWE Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
Grain size analysis testing was performed on samples obtained from B-1 (1-2.5 feet) and
B-4 (3.5-5 feet). Testing indicated soils that contained 12.8 to 42.5 to percent fines
(percent passing #200 sieve) and 57.4 to 85.8 percent sand.
A standard Proctor compaction test was performed on a bulk sample obtained from B-4
(5-10 feet). Testing indicated a maximum dry density of 116.8 pounds per cubic foot
(pcf) with corresponding optimum moisture content of 13.3 percent. The natural moisture
content of the bulk sample tested was 15 percent indicating the bulk sample tested is 1.7
percent wet of optimum.
A California Bearing Ratio (CBR) test was performed on a specimen from the bulk
sample obtained from B-4 (5-10 feet). The specimen was recompacted to approximately
98 percent of its maximum dry density at a moisture content 3 percent dry of optimum.
The sample was soaked for 96 hours and a swell value of 2 percent was recorded. CBR
testing on the soaked sample indicated a CBR value of 3.2 percent.
A tabular summary and individual lab results are provided in Appendix II of this report.
5. CONCLUSIONS AND RECOMMENDATIONS
The following conclusions recommendations are based upon review of exploration data,
our understanding of the proposed construction, and past experience with similar projects
and subsurface conditions. If structural loads or site grades are significantly different
from those anticipated, we request the opportunity to review and comment upon the
recommendations of this report so that they may be confirmed, extended, or modified as
necessary. If subsurface conditions adverse to those indicated by this report are
encountered during construction, those differences should be reported to us for review
and comment.
The subsurface exploration findings indicate the site is suitable for the proposed
construction following remedial measures.
Portions of the parking lot will be constructed within existing wetland areas. Depending
upon design finished grades, undercutting and stabilization with fabric and stone could be
required to properly prepare the subgrade soils to allow for placement of compacted
structural fill. The majority of soils excavated from proposed pond locations, utility
excavations within low-lying portions of the site, and in general any soils excavated from
below the groundwater table will require significant drying prior to reuse as compacted
structural fill.
Foundations for the building may be designed as conventional spread footings bearing in
approved existing soils and well -compacted structural fill.
The following paragraphs present more detailed conclusions and geotechnical
recommendations regarding site development and building and pavement construction.
Geotechnical Exploration Report S&ME Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
5.1 Site Preparation
Our experience with previously graded sites indicates unexpected conditions often exist
between soil test boring locations. These may include active or abandoned utility lines,
areas of low consistency fill, buried debris, and others. Such conditions, if encountered,
can be handled by engineering evaluations at the time of construction.
Prior to initiating the earthwork, all vegetation should be cleared, roots grubbed, and topsoil
stripped from the proposed building, parking, and retaining wall areas, extending a
minimum of 10 feet beyond the outside edges of the building/pavement footprints.
Demolition should include removal of any foundations, slabs, utilities, etc. All debris
associated with the demolition should be removed from the development area. Cavities
created by demolition should be backfilled with structural fill placed and compacted in
accordance with the recommendations in this report.
Topsoil stripping depths of 6 inches are anticipated in areas outside the designated
wetland areas. These areas can be cleared and stripped with conventional equipment.
Within and around wetland areas, rubber -tired equipment will rut near surface soils,
mixing topsoil with underlying materials. Wetland areas should be cleared and stripped
with wide -track equipment. Heavy rubber -tired equipment should not be allowed to
operate on exposed subgrade soils. After stripping of surficial materials has been
completed, and following excavation to final grade in cut areas, the exposed subgrade
should be evaluated by the project Geotechnical Engineer (or his representative) by
proofrolling with a loaded dump truck or similar pneumatic tire vehicle (minimum loaded
weight of 20 tons) to identify unstable soils requiring remediation.
The proofrolling procedure should consist of two complete passes of the equipment over the
subgrade. Areas of the subgrade that rut or deflect excessively in the opinion of the project
Geotechnical Engineer, considering the depth below finished grade and proposed
construction at the specific location, should be repaired. Repair may consist of undercut and
replacement or scarifying, moisture conditioning, and recompacting.
In parking lot areas receiving greater than 4 feet of structural fill, a geotextile stabilization
fabric (i.e. Mirafi 500x or equivalent) followed by an initial bridge lift of no greater than 18
inches of off-site borrow soils with less than 15% passing the No. 200 sieve may be
considered. Bridge lifts should be recommended in the field at the time of construction by a
representative of the geotechnical engineer. Bridge lifts should be kept as thin as possible
and may not be practical based on amount of proposed structural fill, prevailing weather
conditions and type of bridge lift material.
Geotechnical Exploration Report S&ME Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
5.2 Structural Fill
After initial site preparation has been completed and the subgrade is determined to be
stable, site grading should proceed immediately.
5.2.1 Structural Fill
After proper site preparation, areas requiring fill may be raised to their design subgrade
levels using approved off-site borrow materials. The majority of site fill materials are
anticipated to be from an off-site location (or locations). A shrinkage factor of 15 percent
from excavation to compaction is typically assumed for natural soils in this region based
on NCDOT guidelines. We recommend that borrow soils consist of the following
characteristics:
General Site Grading:
Less than 3 percent organics and no deleterious materials.
USCS classification of SW, SP, SM, SC, ML, CL or some combination of these.
Low plasticity soil (with a liquid limit less than 50% and a plasticity index less
than 20%).
A standard Proctor maximum dry density of at least 100 pcf.
Maximum particle size of 3 inches in any dimension.
Backfill for loading dock walls and MSE retaining:
Less than 3 percent organics and no deleterious materials.
USCS classification of SW, SP, or SM with less than 15% passing the #200 sieve.
A standard Proctor maximum dry density of at least 100 pcf.
Maximum particle size of 3 inches in any dimension.
5.2.2 Fill Placement
Each lift of structural fill should be placed in maximum 8 -inch loose lifts. All structural
fill should compacted to at least 95 percent of the standard Proctor maximum dry density
(ASTM D 698) except for the final 12 inches which should be increased to 98 percent.
Fill moisture should be maintained within 3 percent of optimum moisture during
compaction. Field density tests should be performed on the structural fill to evaluate
whether the specified compaction is achieved. One -point Proctor tests should also be
performed on the fill at a frequency determined by the project Geotechnical Engineer to
evaluate whether the laboratory Proctor data is appropriate
Samples of the proposed fill soils should be tested for moisture content and moisture -
density relationship (standard Proctor) to establish their compaction properties. Moisture
adjustment may be needed to achieve a compactable soil moisture content. The extent of
soil moisture adjustments will be affected by the weather conditions prior to and during
grading. Drying may be accomplished by spreading and discing to maximize exposure to
sun and wind during favorable weather conditions. Favorable weather conditions are
Geotechnical Exploration Report S&ME Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
typical of the late Spring, Summer, and early Fall. During unfavorable weather
conditions, drying may require chemical additives (i.e. lime or cement amendment).
5.3 Subgrade Evaluation and Repair
The exposed subgrade can deteriorate and lose support when exposed to construction
traffic and adverse weather conditions. Deterioration can occur in the form or rutting,
pumping, freezing, or erosion. We recommend that during construction, exposed
subgrade surfaces be sealed at the end of each day or when wet weather is forecast. Water
should not be allowed to pond on exposed subgrades. Immediately prior to floor slab or
pavement construction, exposed subgrade soils should be evaluated by proofrolling to
determine their stability. Soils which rut, pump, or deflect under proofrolling should be
repaired prior to crushed stone placement. Repair measures may include
scarifying/drying/recompacting, undercutting, placement of geotextiles, or some
combination of these. Actual repair measures will be influenced by project schedule and
weather conditions and can only be determined in the field.
5.4 Excavations
This exploration encountered low to moderate consistency soils within the anticipated
construction excavation depths. Past experience indicates that these materials can be
excavated by routine earth -moving equipment. Local excavations for shallow utility
trenches and foundations within site soils and fill can likely be accomplished by a
conventional rubber -tired backhoe.
Groundwater was encountered at the ground surface in wetland areas and typically within 3
to 5 feet of existing ground surface. Depending on design subgrade elevations, groundwater
could be encountered within excavation limits. Groundwater should be maintained 2 feet
below the bottom of any mass or confined excavation.
For confined excavations, trench safety must be evaluated on a case-by-case basis. The
contractor will be responsible for all site safety, including the determination of
appropriate trench safety measures according to OSHA guidelines.
6. BUILDING FOUNDATION DESIGN AND CONSTRUCTION
Based on the borings and provided structural loads, the MGP building may be supported
on shallow spread footings. The following sections provide our geotechnical conclusions
and recommendations regarding structural support.
6.1 Bearing Pressure
Shallow foundations for the MGP building may be designed using a net allowable
bearing pressure of up to 2,500 pounds per square foot, provided the earthwork
procedures and recommendations outlined in this report are implemented. Please note
that this bearing pressure assumes a final floor elevation of 272 feet. S&ME should be
Geotechnical Exploration Report S&ME Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
contacted to review this recommendation if the finished floor elevation is different than
stated above.
All foundation excavations should be evaluated by the geotechnical engineer or his
representative prior to concrete placement to confirm the suitability of underlying
materials. If soft or otherwise unsuitable soils are encountered, these soils should be
overexcavated and backfilled with washed stone (NCDOT No. 57) or lean concrete. The
backfill material should be readily available to backfill immediately after overexcavation in
order to prevent sloughing of sidewalls.
If water collects in any excavations it should be removed promptly. Care should be
exercised during construction of foundations in order not to disturb bearing soils and reduce
their bearing strength. Concrete for the footings should be placed as soon as practical
following excavation. If concrete placement is delayed, placement of a concrete "mud
mat" on exposed bearing soils should be considered.
6.2 Bearing Depth and Dimension
Footings should bear at least 18 inches below exterior grade to avoid frost penetration
and develop the design bearing capacity. Continuous wall footings should be at least 18
inches wide and isolated column footings should be at least 24 inches wide. This
recommendation is made to prevent a localized or "punching" shear failure condition
which can occur with very narrow footings.
6.3 Settlement
Based on conditions encountered by this exploration, anticipated structural loads, and
provided the earthwork procedures and recommendations outlined in this report are
implemented, we expect that maximum total settlements beneath footings will be 1 inch
or less. Differential settlements are expected to be'/2 inch or less for footings bearing on
similar materials.
7. FLOOR SLAB
The building floor slab may be grade -supported provided that our site preparation and fill
placement recommendations are implemented. We recommend that 4 inches of aggregate
base course (ABC) stone be placed beneath the floor slab. ABC stone should conform to
the 2012 edition of the NCDOT "Standard Specifications for Roads and Structures." ABC
stone should meet requirements under Section 520 and Section 1010. The ABC stone
should be compacted to at least 98 percent of its modified Proctor maximum dry density
(AASHTO T-180, as modified by NCDOT).
We recommend a subgrade modulus value of 150 pci for subgrades prepared in
accordance with the recommendations of this report.
Geotechnical Exploration Report SWE Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
8. RETAINING WALL PARAMETERS
General recommendations with respect to retaining wall design and construction are
provided below along with specific recommendations for cast -in-place concrete and
mechanically stabilized earth (MSE) walls. As previously noted, additional geotechnical
evaluation and analysis is required in order to provide recommendations and parameters
related to any proposed retaining structures along the east building wall. Once additional
information is available, we should be contacted for any additions or revisions to the
recommendations that may be appropriate.
8.1 Retaining Walls - General
Retaining walls must be designed to resist lateral earth pressures from the backfill. In
addition to the lateral stresses from backfill, the walls may be subjected to surcharge
loading from adjacent traffic, stockpiled materials, or stresses from nearby footings or
floor slabs. If present, these surcharge stresses should be resolved into appropriate lateral
stress distributions and added to the earth pressures outlined below. Walls should have
adequate factors of safety against overturning, sliding, and global failure.
We recommend placing a drainage medium, such as clean stone (NCDOT No. 57)
wrapped in geotextile fabric or a prefabricated geocomposite drain, behind the wall. The
drainage medium should be connected to a footing drain or weep holes to reduce
potential buildup of hydrostatic pressure due to surface water, perched water, or utility
leaks.
Backfill soils placed behind retaining walls should meet the requirements described in
section 5.2.1 and be compacted to at least 95 percent of the soil's standard Proctor
maximum dry density (ASTM D 698) within 3 percent of optimum moisture. Operating
heavy compaction equipment within 5 feet behind the retaining structures can create
lateral earth pressures far in excess of those recommended for design. As such, we
recommend that hand -operated equipment be used within 5 feet from walls. A reduced
lift height of 4 inches (loose measure) should be used in conjunction with hand -operated
equipment.
8.2 Cast -In -Place Concrete Walls
Structural fill meeting the requirements of Section 5.2.1 is recommended for use as
backfill behind cast -in-place concrete walls. Recommended backfill parameters for silty
sands behind cast -in-place concrete retaining walls are summarized in the table below.
The lateral earth pressure coefficients presented below assume no wall friction between
the wall and soil backfill ( = 0 degrees) and are based on placement of properly
compacted backfill and a level backfill surface.
10
Geotechnical Exploration Report SWE Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
Recommended Parameters for Cast -In Place Wall Backfill
Parameter
Value
Friction Angle, (degrees)
30
At -Rest Earth Pressure Coefficient (K))
0.50
Active Coefficient Earth Pressure (Ka)
0.33
Ultimate Passive Earth Pressure Coefficient (K)
3.00
Moist Unit Weight of Backfill c
120
Ultimate Friction Coefficient Between Wall Foundations and Bearing
Soil
0.35
8.3 Mechanically Stabilized Earth (MSE) Walls
Select off-site borrow as described in section 5.2.1 is recommended for use as reinforced
backfill (backfill containing mechanical reinforcement or geogrid) behind MSE walls.
Depending on several factors (i.e., geogrid length, compaction conditions of backfill, and
others), use of silts, clays, and clayey sands as backfill could cause wall instability. It is
our opinion that silt, clay and clayey sand backfill causes more long term lateral
deflection of the backfill mass (and wall face) when compared to a granular soil backfill
with low fines contents. Excessive lateral deflection could cause leaning of the wall face
and development of cracks behind the wall (e.g., cracking of ground surface or asphalt
behind the wall). Cracks behind the wall can create a path for surface water infiltration
into the backfill. Water infiltration into the backfill can create loss of backfill strength
(i.e., soil strength lower than the design strength) and lead to wall instability (i.e.,
possible wall failure).
It is our opinion that use of granular backfill soils will result in less long-term lateral
deflection because most of the deflection occurs during the construction process. As a
result, MSE walls with granular soils as backfill tend to experience less cracking behind
the wall.
Provided that select off-site borrow as described in section 5.2.1 with a maximum of 15%
passing the #200 sieve is used as reinforced backfill, a friction angle of at least 30
degrees should be available for reinforced backfill, provided that the backfill is properly
compacted in accordance with our recommendations. The above friction angle would
correspond to an active earth pressure coefficient Ka of 0.33. This coefficient assumes a
level backfill surface behind the wall. A unit weight of 120 pounds per cubic foot (pcf)
may be used for this material.
Once a backfill material is selected, sufficient laboratory testing including grain size
analysis and triaxial testing of the backfill should be performed prior to construction to
verify design soil parameters for reinforced fill.
The parameters in the table below are applicable for on-site retained soils (i.e. soils behind
11
Geotechnical Exploration Report S&ME Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
the reinforced zone). The parameters assume that retained soils are properly compacted in
accordance with recommendations presented previously.
Recommended Parameters for Retained Soils
Parameter
Value
Friction Angle, (degrees)
26
Cohesion (c)
0
Active Coefficient Earth Pressure (Ka)
0.39
Moist Unit Weight of Backfill (pcf)
120
9. SEISMIC CONSIDERATIONS
Based on the subsurface conditions encountered and experience with the area geology, we
recommend Site Class D for use in seismic design at this site in accordance with the 2012
North Carolina Building Code (2009 IBC with North Carolina Amendments).
10. PAVEMENTS
S&ME was not provided traffic frequency or vehicle weight information and thus a
detailed pavement design was not conducted. However, for parking areas that receive
only car traffic, we generally recommend a minimum pavement section consisting of 2 -
inches of Type 5-9.5B surface mixture underlain by 6 -inches of aggregate base course
stone. In the main access drives and truck (dumpster) routes, we generally recommend a
minimum of 4 -inches of asphalt (2.5 inches of I -19B underlying 1.5 inches of 5-9.5B)
underlain by a minimum of 8 -inches of aggregate base course. These thicknesses are
based on our experience and assume that a compacted, stable subgrade was developed at
the time of construction. The asphalt pavement should not be deficient by more than 1/4
inch in any area.
All materials and workmanship should meet the North Carolina Department of
Transportation's Standard Specifications for Roads and Structures, latest edition. The
aggregate base course should consist of Aggregate Base Course (Refer to NCDOT's
Standard Specifications for Roads and Structures, Section 520). This base course should
be compacted to at least 98 percent of the maximum dry density, as determined by the
modified Proctor compaction test (ASTM D1557). To confirm that the base course has
been uniformly compacted, in-place field density tests should be performed by a qualified
Materials Technician and the area should be methodically proofrolled under his
evaluation.
The condition of the subgrade is critical for the performance of the pavement. The soil
subgrade should be proofrolled immediately prior to placement of base course stone. The
stone subgrade should be proofrolled immediately prior to placement of asphalt.
Unstable areas identified should be repaired. Sufficient testing and evaluation should be
12
Geotechnical Exploration Report SWE Project No. 1305-15-022
Proposed MGP Retail # P000339 — Rockingham, North Carolina April 2, 2015
performed during pavement installation to confirm that the required thickness, density,
and quality requirements of the specifications are followed.
Also, the pavement subgrade should be sloped to allow rainwater to properly drain away.
Areas adjacent to pavements (embankments, landscape islands, ditching, etc.) which can
drain water should be designed so that water does not seep below or surface drain onto
pavements. Adequate drainage is very important for the long-term performance of the
pavement.
11. LIMITATIONS OF REPORT
This report has been prepared in accordance with generally accepted geotechnical
engineering practice for specific application to this project. The conclusions and
recommendations contained in this report were based on the applicable standards of our
profession at the time this report was prepared. No other warranty, express or implied, is
made.
Analysis and recommendations submitted in this report are based, in part, upon the data
obtained from the geotechnical exploration. The nature and extent of variations between
and outside of the borings made may not become evident until construction. If variations
appear evident, then it will be necessary to re-evaluate the recommendations of this
report. In the event that any changes in the grades, nature, design, or location of the
proposed development are planned, the recommendations contained in this report should
be reviewed and modified or verified in writing. We recommend that our firm be
provided the opportunity for general review of final design specifications to verify that
geotechnical recommendations are properly interpreted and implemented.
13
APPENDIX
FIGURES
P-3
RE 7
D-2' y P-2
P-1
CAtwy
B-5
Cx 3uA 01 hTFw-ECw*'.---A
TURPILRE
NOTE: DRAWING PROVIDED BY BOHLER ENGINEERING AND MODIFIED BY
S&ME TO SHOW TEST LOCATIONS. DO NOT USE DRAW ING TO
DETERMINE DISTANCES OR QUANTITIES.
w_vfr
PROP.
4NMmmy
STCRE
Tex �IF
Rm
1%-3
JJJ
-F-v
� I 1 LSF ;1 Dw
-�j
LEGEND
APPROXIMATE BORING LOCATION
SCALE:
Not to Scale
DATE:
3/30/15
ing Forest Road
Re PH:sigh, NC 27616
S&ME (919) 872-2660
FAX: (919) 8 6-3958
ENOINEERING - VESTING wvww.SmEINC.00m
BORING LOCATION PLAN
ROCKINGAM SITE
US 74B
ROCKINGHAM, NORTH CAROLINA
FIGURE NO.
PROJECT NO
1305-15-022
DRAWN BY
KCB
CHECKED BY:
KHH
EINYRONMENTAL SERVICE -5
J.
? � � + � r 1�1 7YRI9I PRVF NLWYP P �L 9NtlFk rr.+rrt
. r 4 wr-,..,.,_�
niuraf� . _ I yy
PL up
II:
mc
FURr
�A '{
`I FF� { .
1 'i-
�ff J I ggg-
�✓� �,�. � ��k AGlafR ara�araR i I '"x+�.y. �'. �e. � ,1� °b, �yd
'� 11 � } ooxiner�i rinir{amaao� o�ie Yr' J{ i1rrF � �'F� es % + - Z
■ :. r1 x.� �:� rte•~ .-,.I. y� l ���� ._
1
+,lk� w er •� �' .�„ : ,' e:. armor
r
I aiPir - •-• '.' .r � Ell ldl A'R
NOTE: DRAWING PROVIDE c - i.,nrow map +--� r
ff2 amen ffl�m.,.
SCALE: DATE: FIGURE NO.
Not to Scale 3/30/15 EXISTING GROUND SURFACE ELEVATIONS
3201 Spring Forest Road
(PROJECT NO: DRAWN BY::#S&ME Raleigh, )$ 27616 ^
1305-15-022 KCB PH: (919)872-2660 ROCKINGAM SITE L
FAX: (919) 876-3958 US 74B
CHECKED BY: ENGINEER NG • VESTING WWW.SMEINC.COM
ENVIRONMENTAL SERVICES ROCKINGHAM, NORTH CAROLINA
JOB NO
DATE
■ Topsoil
FACL, Low Plasticity Clay
Clayey Sand
Sandy Clay
Silty Sand
Clay
El Sand
N = Standard Penetration Test resistance value (blows per foot). The depicted stratigraphy is shown for illustrative purposes only. The actual subsurface conditions will vary between boring locations.
1305-15-022 S&ME
MARCH 2015
Diagram: Generalized Subsurface Profile
Project: MGP Retail - Rockingham
Location: Rockingham, North Carolina
Figure
3
B-2
Finished Floor Elevation
= 272 feet
275
- N ...
- - ..... B-4......
.
270
B-1
---- -N
;.'.
4B-3
N
--- N-- -- - --
B-5
---- -
- - - - - - -
------P-1-
----
---- ----
------
9
8
N
N
6
-
18
6
�7
28
r 7
D-1
D-3
Z
i.
4
P-2
P-3
265
27
_
21
18 -
'.
22-
- N
- N -
N- -
N
17
17
D-2
9
HC
19
7
2
6
260
HC -
46
_
15 - _
6
-
_
- 47
1
-
3
_ N
HC
24
45
- 2 -
46
J
—
41
10HC
51
28
-
%'
32
W4
37
40
44
'.'-
2728
BT @ 10'
255
-
-
;'
------
28-
----
-
,'. ,
,.
-13
--
27
---- ------
-23 ----
28
23
16
20
23
BT @ 10'
BT @ 10'
BT @ 10-
Z
BT @ 20'
BT @ 10
27
p
16
I
250
.14 .
9 BT @ 20'-
.:',
. 15
. . . . . .
�
BT @ 20'
BT @ 20'
BT @ 1020
LU
245
—
10 -
240
24
-
235
22
230
-
19
BT@40'
JOB NO
DATE
■ Topsoil
FACL, Low Plasticity Clay
Clayey Sand
Sandy Clay
Silty Sand
Clay
El Sand
N = Standard Penetration Test resistance value (blows per foot). The depicted stratigraphy is shown for illustrative purposes only. The actual subsurface conditions will vary between boring locations.
1305-15-022 S&ME
MARCH 2015
Diagram: Generalized Subsurface Profile
Project: MGP Retail - Rockingham
Location: Rockingham, North Carolina
Figure
3
APPENDIX I
LEGEND TO SOIL CLASSIFICATION AND SYMBOLS
SOIL TYPES
(Shown in Graphic Log)
Fill
Asphalt
Concrete
■ Topsoil
®Partially Weathered
Rock
Cored Rock
WELL -GRADED GRAVELS, GRAVEL -
�' GW SAND MIXTURES, LITTLE OR NO
FINES
pp POORLY -GRADED GRAVELS,
P GRAVEL -SAND MIXTURES, LITTLE
OR NO FINES
�p o GM SILTY GRAVELS, GRAVEL- SAND -
n SILT MIXTURES
GC CLAYEY GRAVELS, GRAVEL - SAND -
CLAY MIXTURES
WATER LEVELS
(Shown in Water Level Column)
= Water Level At Termination of Boring
1 = Water Level Taken After 24 Hours
= Loss of Drilling Water
HC = Hole Cave
CONSISTENCY OF COHESIVE SOILS
STD. PENETRATION
Shelby Tube
RESISTANCE
SW
SANDS, LIGRAVELLY
Very Soft
0 to 2
LITTLE OR NO FINES
3 to 4
SP
POORLY-GRADED SANDS,
GRAVELLY SAND, LITTLE OR NO
Stiff
9 to 15
FINES
16 to 30
Hard
31 to 50
Very Hard
SM
SILTY SANDS, SAND -SILT
MIXTURES
`SC'
CLAYEY SANDS, SAND - CLAY
MIXTURES
INORGANIC SILTS AND VERY FINE
❑
M L
SANDS, ROCK FLOUR, SILTY OR
CLAYEY FINE SANDS OR CLAYEY
SILTS WITH SLIGHT PLASTICITY
INORGANIC CLAYS OF LOW TO
CL
MEDIUM PLASTICITY,GRAVELLY
CLAYS, SANDY CLAYS, SILTY
CLAYS, LEAN CLAYS
OL
ORGANIC SILTS AND ORGANIC
SILTY CLAYS OF LOW PLASTICITY
®
MH
INORGANIC SILTS, MICACEOUS OR
DIATOMACEOUS FINE SAND OR
SILTY SOILS
®
CH
INORGANIC CLAYS OF HIGH
PLASTICITY
OH
ORGANIC CLAYS OF MEDIUM TO
HIGH PLASTICITY, ORGANIC SILTS
WATER LEVELS
(Shown in Water Level Column)
= Water Level At Termination of Boring
1 = Water Level Taken After 24 Hours
= Loss of Drilling Water
HC = Hole Cave
CONSISTENCY OF COHESIVE SOILS
RELATIVE DENSITY OF COHESIONLESS SOILS
RELATIVE DENSITY
Very Loose
Loose
Medium Dense
Dense
Very Dense
STD. PENETRATION
RESISTANCE
BLOWS/FOOT
0to4
5to10
11 to 30
31 to 50
Over 50
UA IN 4 IM WO WIIIIIIIIII
(Shown in Samples Column)
STD. PENETRATION
Shelby Tube
RESISTANCE
CONSISTENCY
BLOWS/FOOT
Very Soft
0 to 2
Soft
3 to 4
Firm
5 to 8
Stiff
9 to 15
Very Stiff
16 to 30
Hard
31 to 50
Very Hard
Over 50
RELATIVE DENSITY OF COHESIONLESS SOILS
RELATIVE DENSITY
Very Loose
Loose
Medium Dense
Dense
Very Dense
STD. PENETRATION
RESISTANCE
BLOWS/FOOT
0to4
5to10
11 to 30
31 to 50
Over 50
UA IN 4 IM WO WIIIIIIIIII
(Shown in Samples Column)
Shelby Tube
®
Split Spoon
I
Rock Core
❑
No Recovery
TERMS
Standard - The Number of Blows of 140 Ib. Hammer Falling
Penetration 30 in. Required to Drive 1.4 in. I.D. Split Spoon
Resistance Sampler 1 Foot. As Specified in ASTM D-1586.
REC - Total Length of Rock Recovered in the Core
Barrel Divided by the Total Length of the Core
Run Times 100%.
RQD - Total Length of Sound Rock Segments
Recovered that are Longer Than or Equal to 4"
(mechanical breaks excluded) Divided by the
Total Length of the Core Run Times 100%.
*,.S&ME
ENGINEERING • TESTING
ENVIRONMENTAL SERVICES
PROJECT: MGP Retail - Rockingham
Rockingham, North Carolina
BORING LOG B-1
S&ME Project No. 1305-15-022
DATE DRILLED: 3/18/15 ELEVATION: 269.0 ft
NOTES: Borehole backfilled with auger cuttings
and a commercial hole closure device placed
near the surface. PP = Pocket Penetrometer
DRILL RIG: Diedrich D-50 BORING DEPTH: 20.0 ft
DRILLER: J. Wino WATER LEVEL: Water at 5' @ 24 hours
HAMMER TYPE: Auto LOGGED BY: F. Lloyd
SAMPLING METHOD: Split soon
NORTHING: 0 EASTING: 1
DRILLING METHOD: 21/4' H.S.A.
w
BLOW
COUNT
U
w
Oz
/CORE
DATA
STANDARD PENETRATION TEST DATA
w
=
_ (D
w ~
z
C)
w
(blows/ft)
a w
W
a o
MATERIAL DESCRIPTION
0
a w
-1 J
>
w
F
w-
a_ a
/REMARKS
(D
Jo
W
U)<
N
M
10 20 30 6080
z
TOPSOIL
3
2
3
3
1
6
COASTAL PLAIN: CLAYEY SAND (SC)
loose, gray red, fine to medium, moist to wet,
-
PP = 1.0 tsf
_.
9
12
15
_
2
27
5—
COASTAL PLAIN: CLAYEY SAND (SC)
264.0
medium dense to dense, gray tan, fine to
medium, moist, with mica below 8', PP = 4.5+
3
8
18
28
46
tsf
4
11
15
26
41
10-
HC
259.0
COASTAL PLAIN: CLAYEY SAND -(UC
medium dense, gray tan, fine to coarse, moist to
wet, with white clay vein, PP = 2.0 tsf
10
11
12
5
23
15
254.0
_
COASTAL PLAIN: SILTY SAND (SM)
medium dense, gray white, fine to medium, wet,
with clay and trace mica, PP = 1.0 tsf
6
7
8
6
14
20
249.0
Boring terminated at 20 ft
VOTES:
1. THIS LOG IS ONLY A PORTION OFA REPORT PREPARED FOR THE NAMED
PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
2. BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL
ACCORDANCE WITH ASTM D-1586.
3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
4. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
Page 1 of 1
PROJECT: MGP Retail - Rockingham
Rockingham, North Carolina
BORING LOG B-2
S&ME Project No. 1305-15-022
DATE DRILLED: 3/18/15 ELEVATION: 274.0 ft
NOTES: Borehole backfilled with auger cuttings
and a commercial hole closure device placed
near the surface. PP = Pocket Penetrometer
DRILL RIG: Diedrich D-50 BORING DEPTH: 20.0 ft
DRILLER: J. Wino WATER LEVEL: Water at 8' after drilling
HAMMER TYPE: Auto LOGGED BY: F. Lloyd
SAMPLING METHOD: Split soon
NORTHING: 0 EASTING: 2
DRILLING METHOD: 21/4' H.S.A.
w
BLOW
COUNT
U
w
Oz
/CORE
DATA
STANDARD PENETRATION TEST DATA
w
=
_ (D
w ~
z
C)
(blows/ft)
a w
a o
MATERIAL DESCRIPTION
0
a w
-� J
w
>
o
w
F
w-
a_ a
/REMARKS
(D
-io
W
can
N
M
10 20 30 6080
z
TOPSOIL
4"
2
2
2
1
4
ALLUVIUM: SAND (SP)
very loose, tan, fine, moist
.�
COASTAL PLAIN: SILTY SAND (SM)
2
3
3
6
_
9
5
loose to medium dense, gray tan, fine to coarse,
269.0
moist to wet, with trace fine rounded gravel, PP
= 1.0 tsf
3
7
9
9
18
COASTAL PLAIN: CLAY (CH)
very stiff, white tan, moist, with some fine sand,
4
6
9
12
21
10
PP = 3.5 tsf
264.0
COASTAL PLAIN: CLAYEY SAND (SCS
loose, gray tan, fine, moist to wet, with trace
mica, PP = 1.0 tsf
_.
2
4
6
5
10
15
259.0
COASTAL PLAIN: SAND (SM
medium dense, gray, fine to medium, saturated,
with trace fine subrounded gravel
6
8
7
9
16
20
254.0
Boring terminated at 20 ft
NOTES:
1. THIS LOG IS ONLY A PORTION OFA REPORT PREPARED FOR THE NAMED
PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
2. BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL
ACCORDANCE WITH ASTM D-1586.
3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
4. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
Page 1 of 1
PROJECT: MGP Retail - Rockingham
Rockingham, North Carolina
BORING LOG B-3
S&ME Project No. 1305-15-022
NOTES: Borehole backfilled with auger cuttings
DATE DRILLED: 3/18/15 ELEVATION: 270.0 ft
and a commercial hole closure device placed
near the surface. PP = Pocket Penetrometer
DRILL RIG: Diedrich D-50 BORING DEPTH: 40.0 ft
DRILLER: J. Wino WATER LEVEL: Water at 10' after drilling
HAMMER TYPE: Auto LOGGED BY: F. Lloyd
SAMPLING METHOD: Split soon
NORTHING: 0 EASTING: 3
DRILLING METHOD: 21/4' H.S.A.
w
BLOW
COUNT
U
w
Oz
/CORE
DATA
STANDARD PENETRATION TEST DATA
w
=
_ (D
w ~
z
C)
(blows/ft)
a w
W
a o
MATERIAL DESCRIPTION
0
a w
-1 J
w
>
w
w-
a_ a
/REMARKS
(D
F
Jo
W
can
N
M
10 20 30 6080
Z
TOPSOIL
3"
2
3
3
1
6
FILL: CLAYEY SAND (SC)
loose, tan, fine, moist to wet, with trace organics
POSSIBLE ALLUVIUM: SILTY SAND (SMS
2
7
9
9
18
5
medium dense, gray, fine to medium, wet
265.0
3
7
8
9
17
COASTAL PLAIN: SANDY CLAY (CL)
stiff, white tan, fine, moist to wet, PP = 0.5 tsf
5
7
8
15
10
V
260.0--4
COASTAL PLAIN: CLAYEY SAND (SCS
medium dense, gray tan, fine to medium, moist,
with trace mica, PP = 4.5+ tsf
8
12
16
5
28
15
255.0
COASTAL PLAIN: CLAYEY SAND (SC)
loose to medium dense, gray white, fine to
medium, wet, with trace mica and silty sand
3
4
5
20
layers, PP = 2.0 tsf
250.0
6
9
7 4 4 6 10
25 245.0-
COASTAL
45.0 COASTAL PLAIN: SILTY SAND (SM) _
medium dense, blue tan, fine to medium, wet,
with trace rounded quartz gravel 8 8 12 12 24
30 240.0
COASTAL PLAIN: SANDY CLAY (CHS
very stiff, red purple, fine, moist, PP = 3.0 tsf
9 6 9 13 22
VOTES:
1. THIS LOG IS ONLY A PORTION OFA REPORT PREPARED FOR THE NAMED
PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
2. BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL
ACCORDANCE WITH ASTM D-1586.
3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
4. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
Page 1 of 2
PROJECT: MGP Retail - Rockingham
Rockingham, North Carolina
BORING LOG B-3
S&ME Project No. 1305-15-022
NOTES: Borehole backfilled with auger cuttings
DATE DRILLED: 3/18/15 ELEVATION: 270.0 ft
and a commercial hole closure device placed
near the surface. PP = Pocket Penetrometer
DRILL RIG: Diedrich D-50 BORING DEPTH: 40.0 ft
DRILLER: J. Wino WATER LEVEL: Water at 10' after drilling
HAMMER TYPE: Auto LOGGED BY: F. Lloyd
SAMPLING METHOD: Split soon
NORTHING: 0 EASTING: 3
DRILLING METHOD: 2'/4' H.S.A.
J
w
BLOW
COUNT
U
w
0 }
CORE
DATA
STANDARD PENETRATION TEST DATA
w
=
= c�
H
w ~
z
c)
0
(blows/ft)
J
Q 0
MATERIAL DESCRIPTION
rr
-1 w
"
LU
o
w
w --
a_ a
�
/REMARKS
>
(�
Q
J
w<
Q
io
co
-2
Z
COASTAL PLAIN: SANDY CLAY (CH)
N
10 20 30 6080
very stiff, red purple, fine, moist, PP = 3.0 tsf
(continued)
COASTAL PLAIN: CLAYEY SAND (SCS
medium dense, gray tan, fine to medium, moist
4
8
11
40
to wet, PP = 1.5 tsf
230.0
10
19
Boring terminated at 40 ft
NOTES.
1. THIS LOG IS ONLY PORTION OFA REPORT PREPARED FOR THE NAMED
PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
2. BORING, SAMPLING AND PENETRATION TEST DATA IN GENERAL
ACCORDANCE WITH ASTM D-1586.
3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
4. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
Page 2 of 2
PROJECT: MGP Retail - Rockingham
Rockingham, North Carolina
BORING LOG B-4
S&ME Project No. 1305-15-022
DATE DRILLED: 3/18/15 ELEVATION: 271.0 ft
NOTES: Borehole backfilled with auger cuttings
and a commercial hole closure device placed
near the surface. Bulk samples obtained from 1' to
5' and T to 10'. PP = Pocket Penetrometer
DRILL RIG: Diedrich D-50 BORING DEPTH: 20.0 ft
DRILLER: J. Wino WATER LEVEL: Water at 6' after drilling
HAMMER TYPE: Auto LOGGED BY: F. Lloyd
SAMPLING METHOD: Split soon
NORTHING: 0 EASTING: 4
DRILLING METHOD: 21/4' H.S.A.
w
BLOW
COUNT
U
w
ZO
Oz 0-
/CORE
DATA
STANDARD PENETRATION TEST DATA
w
=
_ (D
w ~
z
C)
w
(blows/ft)
a w
a o
MATERIAL DESCRIPTION
0
a w
-� J
>
o
w
F
w-
a_ a
/REMARKS
(D
�
-i
w
can
N
o
M
10 20 30 6080
z
TOPSOIL
6
4
4
4
1
8
COASTAL PLAIN: CLAYEY SAND (SC)
loose, tan, fine to medium, moist, PP = 4.0 tsf
COASTAL PLAIN: SAND (SM
2
9
13
15
-
28
5
medium dense, tan orange, fine to medium,
266.0
moist, with thin gray clayey sand layer j
77
COASTAL PLAIN: SAND (SM
3
9
9
8
17
medium dense, tan orange, fine to coarse, wet
COASTAL PLAIN: CLAYEY SAND (SC)
3
2
4
10-
loose, white, fine to medium, wet, PP = 0.5 tsf
261.0
4
6
COASTAL PLAIN: CLAYEY SAND (SCS
medium dense, gray, fine to medium, moist,
with trace mica, PP = 4.5 tsf
8
12
15
5
27
15
256.0
6
6
7
9
16
20
251.0
Boring terminated at 20 ft
NOTES:
1. THIS LOG IS ONLY A PORTION OFA REPORT PREPARED FOR THE NAMED
PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
2. BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL
ACCORDANCE WITH ASTM D-1586.
3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
4. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
Page 1 of 1
PROJECT: MGP Retail - Rockingham
Rockingham, North Carolina
BORING LOG B-5
S&ME Project No. 1305-15-022
NOTES: Borehole backfilled with auger cuttings
DATE DRILLED: 3/18/15 ELEVATION: 269.0 ft
and a commercial hole closure device placed
near the surface. PP = Pocket Penetrometer
DRILL RIG: Diedrich D-50 BORING DEPTH: 20.0 ft
DRILLER: J. Wino WATER LEVEL: Dry to 11'@ TOB
HAMMER TYPE: Auto LOGGED BY: F. Lloyd
SAMPLING METHOD: Split soon
NORTHING: 0 EASTING: 5
DRILLING METHOD: 21/4' H.S.A.
w
BLOW
COUNT
U
w
Oz
/CORE
DATA
STANDARD PENETRATION TEST DATA
w
=
_ (D
w ~
z
C)
(blows/ft)
a w
a o
MATERIAL DESCRIPTION
0
a w
-� J
w
>
o
w
w-
a_ a
/REMARKS
(D
F
-io
W
U)<
N
M
10 20 30 6080
z
TOPSOIL
6
3
3
4
1
7
COASTAL PLAIN: CLAYEY SAND (SC)
loose, gray tan, fine to medium, moist
COASTAL PLAIN: SANDY CLAY (CLI
2
4
8
14
_
22
5—
very stiff, gray tan, fine to medium, moist, PP =
264.0
4.5+ tsf
3
11
20
27
47
COASTAL PLAIN: CLAYEY SAND (SC)
dense to very dense, gray tan, fine to medium,
moist, with trace mica, PP = 4.5+ tsf
4
15
21
30
51
10-
253.0
_
HC
_
COASTAL PLAIN: SILTY SAND (SM)
medium dense, gray, fine to medium, wet, with
trace mica and some clay, PP = 2.0 tsf
_.
8
9
11
5
20
15
i
254.0
6
7
7
8
15
20
249.0
Boring terminated at 20 ft
NOTES:
1. THIS LOG IS ONLY A PORTION OFA REPORT PREPARED FOR THE NAMED
PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
2. BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL
ACCORDANCE WITH ASTM D-1586.
3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
4. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
Page 1 of 1
PROJECT: MGP Retail - Rockingham
Rockingham, North Carolina
BORING LOG D-1
S&ME Project No. 1305-15-022
DATE DRILLED: 3/18/15 ELEVATION: 264.0 ft
NOTES: Borehole backfilled with auger cuttings
and a commercial hole closure device placed
near the surface. PP = Pocket Penetrometer
DRILL RIG: Diedrich D-50 BORING DEPTH: 10.0 ft
DRILLER: J. Wino WATER LEVEL: Water at 3.5'@ 24 hours
HAMMER TYPE: Auto LOGGED BY: F. Lloyd
SAMPLING METHOD: Split soon
NORTHING: 0 EASTING: 6
DRILLING METHOD: 21/4' H.S.A.
w
BLOW COUNT
U
w
Oz
/CORE DATA
STANDARD PENETRATION TEST DATA
w
=
_ (D
w ~
z C)
(blows/ft)
a w
W
a o
MATERIAL DESCRIPTION
0
a w
-1 J
w
>
w
F
w-
a_ a
/REMARKS
(D
Jo
W
U)<
N M
10 20 30 6080
z
TOPSOIL
4"
2 1 2
1
3
POSSIBLE ALLUVIUM: SANDY CLAY (CH)
_
soft, tan, fine, wet, PP = 0.5 tsf `
1
COASTAL PLAIN: CLAYEY SAND (S CS
2
9 12 16
_
28
5
medium dense, gray red, fine to medium, moist,
259.0
with trace mica, PP = 4.5+ tsf
3
11 12 16
28
COASTAL PLAIN: CLAYEY SAND (SCS
medium dense, gray, fine to medium, moist,
highly micaceous, PP = 4.5+ tsf
10-
--
254.0
4
9 10 13
23
COASTAL PLAIN: SILTY SAND (SM)
� medium dense, gray tan, fine to medium, moist,
with clay and trace mica, PP = 4.5 tsf
Boring terminated at 10 ft
VOTES:
1. THIS LOG IS ONLY A PORTION OFA REPORT PREPARED FOR THE NAMED
PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
2. BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL
ACCORDANCE WITH ASTM D-1586.
3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
4. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
Page 1 of 1
PROJECT: MGP Retail - Rockingham
Rockingham, North Carolina
BORING LOG D-2
S&ME Project No. 1305-15-022
DATE DRILLED: 3/18/15 ELEVATION: 260.0 ft
NOTES: Borehole backfilled with auger cuttings
and a commercial hole closure device placed
near the surface. Bulk sample obtained from V to
5'. PP = Pocket Penetrometer
DRILL RIG: Diedrich D-50 BORING DEPTH: 10.0 ft
DRILLER: J. Wino WATER LEVEL: Water at 1' @ 24 hours
HAMMER TYPE: Auto LOGGED BY: F. Lloyd
SAMPLING METHOD: Split soon
NORTHING: 0 EASTING: 7
DRILLING METHOD: 21/4' H.S.A.
w
BLOW
COUNT
U
w
ZO
Oz 0-
/CORE
DATA
STANDARD PENETRATION TEST DATA
w
=
_ (D
w ~
z
C)
w
(blows/ft)
a w
a o
MATERIAL DESCRIPTION
0
a w
-� J
>
o
w
F
w-
a_ a
/REMARKS
(D
-io
W
can
N
M
10 20 30 6080
z
TOPSOIL
1
6"
1
2
2
1
4
COASTAL PLAIN: SANDY CLAY (CHS
soft, tan orange, fine to medium, wet, PP = 1.0
-
tsf
_
2
4
5
8
13
COASTAL PLAIN: CLAYEY SAND (SC)
5
255.0
medium dense, gray tan, fine to medium, moist
to wet, PP = 1.5 tsf
3
8
12
15
27
COASTAL PLAIN: SILTY SAND (SM)
medium dense, gray, fine to medium, moist,
with clay and trace mica, PP = 4.5+ tsf
4
7
9
11
20
10-
250.0
—
COASTAL PLAIN: CLAYEY SAND (SC)
medium dense, gray, fine to medium, moist,
with trace mica and trace fine rounded gravel,
PIP =4.5tsf
Boring terminated at 10 ft
NOTES:
1. THIS LOG /S ONLY A PORTION OFA REPORT PREPARED FOR THE NAMED
PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
2. BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL
ACCORDANCE WITH ASTM D-1586.
3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
4. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
Page 1 of 1
PROJECT: MGP Retail - Rockingham
Rockingham, North Carolina
BORING LOG D-3
S&ME Project No. 1305-15-022
NOTES: Borehole backfilled with auger cuttings
DATE DRILLED: 3/18/15 ELEVATION: 265.0 ft
and a commercial hole closure device placed
near the surface. PP = Pocket Penetrometer
DRILL RIG: Diedrich D-50 BORING DEPTH: 10.0 ft
DRILLER: J. Wino WATER LEVEL: Water at 0' @ 24 hours
HAMMER TYPE: Auto LOGGED BY: F. Lloyd
SAMPLING METHOD: Split soon
NORTHING: 0 EASTING: 8
DRILLING METHOD: 21/4' H.S.A.
W
w
BLOW COUNT
U
w
ZO
z O
/CORE DATA
STANDARD PENETRATION TEST DATA
w
=
_ (7
w ~
z C)
(blows/ft)
a w
W
a o
MATERIAL DESCRIPTION
a w
-� J
w
>
w
W -
� a
/REMARKS
(7
Q
w
Q Q
U) U)
a -
M
10 20 30 6080
Z
TOPSOIL
5
2 3 6
1
9
COASTAL PLAIN: CLAYEY SAND (SC)
loose, tan gray, fine to medium, moist, PP =
4.5+ tsf
-
4 7 17
-
5—
HC
—
260.0
2
24
COASTAL PLAIN: CLAYEY SAND (SC)
medium dense to dense, gray tan, fine to
medium, moist, with trace mica, PP = 4.5+ tsf
3
8 15 22
37
4
7 11 16
27
COASTAL PLAIN: CLAY (CH)
10
very soft, white, moist, with fine to medium sand
255.0
layer, PP = 3.0 tsf
Boring terminated at 10 ft
VOTES:
1. THIS LOG IS ONLY A PORTION OFA REPORT PREPARED FOR THE NAMED
PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
2. BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL
ACCORDANCE WITH ASTM D-1586.
3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
4. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
Page 1 of 1
IPROJECT
DATE DRILLED:
DRILL RIG: Diec
DRILLER: J. Wir
HAMMER TYPE:
SAMPLING MET
DRILLING METH
= U
w w a J
v
MGP Retail - Rockingham
Rockingham, North Carolina
S&ME Project No. 1305-15-022
5 ELEVATION: 268.0 ft
•50 BORING DEPTH: 10.0 ft
WATER LEVEL: Dry to 6'@ TOB
LOGGED BY: F. Llovd
BORING LOG P-1
NOTES: Borehole backfilled with auger cuttings
and a commercial hole closure device placed
near the surface. PP = Pocket Penetrometer
t s oon
NORTHING: 0 EASTING: 9
Q.S.A.
W
w
BLOW COUNT
W
ZO
>-
Oz
/CORE DATA
STANDARD PENETRATION TEST DATA
w
W
(blows/ft)
MATERIAL DESCRIPTION
a w
J
Of Ir
W
w —
0-
fr
/REMARKS
>
F-
J
w
2
can
c -
N M
10 20 30 6080
Z
\TOPSOIL
3 1 2 1 3 4
COASTAL PLAIN: CLAYEY SAND (SC)
very loose, tan orange, fine to medium, wet, PP
1.5 tsf - 2 3 8 11 19
5 COASTAL PLAIN: CLAYEY SAND (SC) 263.0
medium dense, gray red, fine to medium, moist, He
with trace mica, PP = 4.5+ tsf 3 12 19 26 45
10
Boring terminated at 10 ft
NOTES:
1. THIS LOG IS ONLY A PORTION OFA REPORT PREPARED FOR THE NAMED
PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
2. BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL
ACCORDANCE WITH ASTM D-1586.
3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
4. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
258.0 ] 4 A 1 14 1 18
32 1
Page 1 of 1
PROJECT:
MGP Retail - Rockingham
Rockingham, North Carolina
BORING LOG P-2
S&ME Project No. 1305-15-022
NOTES: Borehole backfilled with auger cuttings
DATE DRILLED: 3/18/15
ELEVATION: 265.0 ft
and a commercial hole closure device placed
near the surface. PP = Pocket Penetrometer
DRILL RIG: Diedrich D-50 BORING DEPTH: 10.0
ft
DRILLER: J. Wino WATER LEVEL: Water T@ TOB and 24 hours
HAMMER TYPE: Auto LOGGED BY: F. Lloyd
SAMPLING METHOD:
Split soon
NORTHING: 0 EASTING: 10
DRILLING METHOD: 21/4'
H.S.A.
w
BLOW COUNT
U
w
Oz
/CORE DATA
STANDARD PENETRATION TEST DATA
w
=
_ (D
w
~
z C)
(blows/ft)
a w
a o
MATERIAL DESCRIPTION
0
a w
-1
J
w
W
w
w-
a_
a
/REMARKS
>
(D
F
Jo
W
z
U)<
N M
10 20 30 6080
TOPSOIL
6„
1 1 1 1 * 2
X - FILL: SILTY SAND (SM) 1
very loose, black gray, fine to medium, moist to -
wet, with trace roots, with silt layers
5 POSSIBLE ALLUVIUM: CLAYEY SAND (SC)
very loose, gray, wet j
COASTAL PLAIN: CLAYEY SAND (SC)
dense, gray tan, fine to medium, moist, with
mica, PP = 4.5+ tsf
10- COASTAL PLAIN: CLAYEY SAND (SC)
medium dense, gray, fine to medium, moist to
wet, highly micaceous, PP = 4.0 tsf
Boring terminated at 10 ft
NOTES:
1. THIS LOG IS ONLY A PORTION OFA REPORT PREPARED FOR THE NAMED
PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
2. BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL
ACCORDANCE WITH ASTM D-1586.
3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
4. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
2 111211111 i, 1 21
3 11 9 116 124 I -�-v -1 40
4 I11 8 1 11113 I 4 1 23 1
Page 1 of 1
PROJECT: MGP Retail - Rockingham
Rockingham, North Carolina
BORING LOG P-3
S&ME Project No. 1305-15-022
DATE DRILLED: 3/18/15 ELEVATION: 265.0 ft
NOTES: Borehole backfilled with auger cuttings
and a commercial hole closure device placed
near the surface. Moved boring 15' toward B-1.
PP = Pocket Penetrometer
DRILL RIG: Diedrich D-50 BORING DEPTH: 10.0 ft
DRILLER: J. Wino WATER LEVEL: Dry to 5'@ TOB
HAMMER TYPE: Auto LOGGED BY: F. Lloyd
SAMPLING METHOD: Split soon
NORTHING: 0 EASTING: 11
DRILLING METHOD: 21/4' H.S.A.
w
BLOW
COUNT
U
w
ZO
Oz 0-
/CORE
DATA
STANDARD PENETRATION TEST DATA
w
=
_ (D
w ~
z
C)
w
(blows/ft)
a w
a o
MATERIAL DESCRIPTION
0
a w
-� J
>
o
w
F
w-
a_ a
/REMARKS
(D
-io
W
can
N
M
10 20 30 6080
z
TOPSOIL
5
2
2
4
1
6
COASTAL PLAIN: CLAYEY SAND (S CS
loose, gray tan, fine to medium, moist to wet,
-
with trace fine rounded gravel, PP = 1.0 tsf
-
10
19
27
-
2
46
5
COASTAL PLAIN: CLAYEY SAND (SCS
260.0
dense, gray red, fine to medium, moist, PP =
4.5+ tsf
3
11
18
26
44
COASTAL PLAIN: CLAYEY SAND (SCS
dense, gray, fine to medium, moist, with trace
mica and trace fine rounded gravel, PP = 4.5+
4
8
12
16
28
10
tsf
255.0
COASTAL PLAIN: CLAYEY SAND (SCS
medium dense, gray, fine to medium, moist,
with trace mica, PP = 4.5+ tsf
Boring terminated at 10 ft
NOTES:
1. THIS LOG /S ONLY A PORTION OFA REPORT PREPARED FOR THE NAMED
PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT.
2. BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL
ACCORDANCE WITH ASTM D-1586.
3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT.
4. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY.
Page 1 of 1
APPENDIX 11
MGP Retail
Rockingham, North Carolina *S&ME
S&ME Project Number 1051-15-022
TABLE 1
Summary of Laboratory Test Results
Standard Proctor, CBR
1) - indicates test not performed
* Soaked Condition
TABLE 2
Summary of Laboratory Test Results
Natural Moisture Content, Atterberg Limits, Grain Size Analysis, USCS Classification
BORING
NUMBER
SAMPLE
DEPTH (ft.)
NATURAL
MOISTURE
CONTENT (%)
STANDARD PROCTOR TEST RESULTS
CALIFORNIA BEARING RATIO (CBR) TEST RESULTS (corrected)
USCS
CLASSIFICATION
Liquid Limit
(LL)
Plastic Index (PI)
% SiItlClay
%Sand
CBR Value*
1.0-2.5
15.9
-
-
BORING
NUMBER
SAMPLE
DEPTH (ft.)
USCS CLASSIFICATION
Maximum Dry
Density (pcf)
Optimum
Moisture
Content (%)
Natural
Moisture
Content (%)
Compaction
Moisture (%)
Percent Compaction
ON
12.8
Percent Swell (%)
0.1"
0.2"
B-4
5-10
SM
116.8
13.3
15.0
13.3
97.6
2.7
3.2
2
1) - indicates test not performed
* Soaked Condition
TABLE 2
Summary of Laboratory Test Results
Natural Moisture Content, Atterberg Limits, Grain Size Analysis, USCS Classification
BORING
NUMBER
SAMPLE
DEPTH (ft.)
NATURAL
MOISTURE
CONTENT (%)
ATTERBERG LIMITS
GRAIN SIZE ANALYSIS
USCS
CLASSIFICATION
Liquid Limit
(LL)
Plastic Index (PI)
% SiItlClay
%Sand
B-1
1.0-2.5
15.9
-
-
42.5
57.5
Sc
B-4
3.5-5.0
12.3
-
-
12.8
87.2
ML
B-5
3.5-5.0
13.2
42
26
-
-
CL
D-1
1.0-2.5
22.1
52
31
-
-
CH
D-2
1.0-5.0
15.9
28
15
-
-
CL
1) - indicates test not performed
2) % silt/clay indicates percent passing the no. 200 sieve
Form No: TR-D2216-T265-1
Revision No. 0 ,..SE
Revision Date: 02122108 Laboratory Determination of Water Content
ASTMD 2216 0 AASHTO T265 ❑ Quality Assurance
S&ME, Inc. - Greensboro 8646 West Market St. Suite 105, Greensboro NC 27409
Project #: 1305-15-022 Report Date: 4-1-15
Project Name: MGP Retail Site - Greensboro Test Date(s): 3-23-15
Client Address:
Sample by: J. Wingo Sample Date(s): 3-18-15
Sampling Method: NA Drill Rig: NA
Method: A (1%) ❑ B (o.l%) 0 Balance ID. 5544 Calibration Date: 2-26-15
Boring
No.
Sample
No.
Sample
Depth
Tare #
Tare Weight
Tare Wt.+
Wet Wt
Tare Wt. +
Dry Wt
Water
Weight
Percent
Moisture
N
o
t
ft. or m.
grams
grams
grams
grams
%
e
B-1
1
1.0'-2.5'
7
117.67
344.61
313.47
31.14
15.9%
B-4
2
3.5'-5.0'
22
139.77
395.94
367.79
28.15
12.3%
B-5
2
3.5'-5.0'
30
9.33
70.80
63.63
7.17
13.2%
D-1
1
1.0'-2.5'
3
7.92
70.34
59.05
11.29
22.1%
D-2
Bulk
1.0'-5.0'
7.87
70.75
62.11
8.64
15.9%
Notes /Deviations /References
AASHTO T 265: Laboratory Determination of Moisture Content of Soils
ASTM D 2216: Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass
Jimmy Thomasson Nicet #119392
Technician Name Signature Certification Type /No. Date
Finley Lloyd, PE Project Engineer 4/1/2015
Technical Responsibility Signature Position Date
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
3718 Old Battleground Rd., Greensboro, NC. 27410
Form No: TR -D2216 -T265-1
Revision No. 0
Revision Date: 02/22/08
Laboratory Determination of Water Content
ASTM D 2216 0 AASHTO T265 ❑
*S&ME
Quality Assurance
S&ME, Inc. - Greensboro 8646 West Market St. Suite 105, Greensboro NC 27409
Project #: 1305-15-022
Project Name: MGP Retail Site - Greensboro
Report Date: 4-1-15
Boring
No.
Sample
No.
Sample
Depth
Tare #
Tare Weight
Tare Wt.+
Wet Wt
Tare Wt. +
Dry Wt
Water
Weight
Percent
Moisture
N
o
t
ft, or m.
grams
grams
grams
grams
%
e
1
2
Notes / Deviations / References
3718 Old Battleground Rd., Greensboro, NC. 27410
Form No. TR -D4318 -T89-90 #S&ME
Revision No. 0
Revision Date: 11120107 Liquid Limit, Plastic Limit, and Plastic Index
Another code ASTMD 4318 [K AASHTO T 89 ❑ AASHTO T 90 ❑ Quality Assurance
S & ME, Inc.- Greensboro 8646 West Market St. Suite 105, Greensboro NC 27409 ad
Project #: 1305-15-022 Report Date: 3-28-15
Project Name: MGP Retail Site - Rockingham Test Date(s) 3-27-15
Client Name:
Client Address:
Boring #: B-5 Sample #: 2 Sample Date: 3-18-15
Location: NA Offset: NA Elevation: 3.5'-5.0'
Sample Description:
Gray Tan Sandy CLAY
16
Type and Specification
S&ME ID # Cal Date:
Type and Specification S&ME ID # Cal Date:
Balance (0.01 g)
5544 2/26/2015
Grooving tool 5788 2/28/2015
LL Apparatus
5571 2/28/2015
Grooving tool
Oven
5470 12/1/2014
Grooving tool
Pan #
Tare #:
16
19
Liquid Limit
24 4
5 6
Plastic Limit
114
121
9
A
Tare Weight
15.98
15.93
15.77
11.13
11.34
B
Wet Soil Weight + A
23.84
23.39
23.83
17.18
17.94
C
Dry Soil Weight + A
21.59
21.21
21.33
16.34
17.03
D
Water Weight (B -C)
2.25
2.18
2.50
0.84
0.91
E
Dry Soil Weight (C -A)
5.61
5.28
5.56
5.21
5.69
F
% Moisture (D/E)* 100
40.1%
41.3%
45.0%
16.1%
16.0%
N
# OF DROPS
34
28
15
Moisture Contents determined
by ASTMD 2216
LL LL = F * FACTOR
Ave.
Average
16.1%
50.0
One Point Liquid Limit
N
Factor N Factor
20
0.974 26 1.005
21
0.979 27 1.009
45.0
22
0.985 28 1.014
23
0.99 29 1.018
C
0
U
24
0.995 30 1.022
0
40.0
25
1.000
h
NP, Non -Plastic ❑
Liquid Limit 42
Plastic Limit 16
Plastic Index 26
Group Symbol CL
0
35.0
30.0
10
15 20
25 30
35 40
100
Multipoint Method "❑
M h d
One -pont et o
Wet Preparation Lj Dry Preparation Lj Air Dried r
Notes /Deviations /References:
ASTMD 4318: Liquid Limit, Plastic Limit, & Plastic Index of Soils
Jimmy Thomasson Finley Lloyd, PE 3/31/2015
Technician Name Date Technical Responsibility Date
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
3718 Old Battleground Rd., Greensboro, NC. 27410
Form No. TR -D4318 -T89-90 #S&ME
Revision No. 0
Revision Date: 11120107 Liquid Limit, Plastic Limit, and Plastic Index
Another code ASTMD 4318 [K AASHTO T 89 ❑ AASHTO T 90 ❑ Quality Assurance
S & ME, Inc.- Greensboro 8646 West Market St. Suite 105, Greensboro NC 27409 ad
Project #: 1305-15-022 Report Date: 3-28-15
Project Name: MGP Retail Site - Rockingham Test Date(s) 3-27-15
Client Name:
Client Address:
Boring #: D-1 Sample #: 1 Sample Date: 3-18-15
Location: NA Offset: NA Elevation: 1.0'-2.5'
Sample Description: Tan Sandy CLAY
Type and Specification S&ME ID # Cal Date: Type and Specification S&ME ID # Cal Date:
Balance (0.01 g) 5544 2/26/2015 Grooving tool 5788 2/28/2015
LL Apparatus 5571 2/28/2015 Grooving tool
Oven 5470 12/1/2014 Grooving tool
Pan #
Tare #:
25
23
Liquid Limit
18 4
5 6
Plastic Limit
101
123
9
A
Tare Weight
15.89
15.83
15.98
11.43
11.38
B
Wet Soil Weight + A
23.36
23.11
23.18
17.32
17.63
C
Dry Soil Weight + A
20.93
20.59
20.64
16.31
16.53
D
Water Weight (B -C)
2.43
2.52
2.54
1.01
1.10
E
Dry Soil Weight (C -A)
5.04
4.76
4.66
4.88
5.15
F
% Moisture (D/E)* 100
48.2%
52.9%
54.5%
20.7%
21.4%
N
# OF DROPS
35
22
15
Moisture Contents determined
by ASTMD 2216
LL LL = F * FACTOR
Ave.
Average
21.1%
60.0
One Point Liquid Limit
N
Factor N Factor
20
0.974 26 1.005
21
0.979 27 1.009
55.0
22
0.985 28 1.014
23
0.99 29 1.018
C
0
U
24
0.995 30 1.022
0
50.0
25
1.000
h
NP, Non -Plastic ❑
Liquid Limit 52
Plastic Limit 21
Plastic Index 31
Group Symbol CH
0
45.0
40.0
10
15 20
25 30
35 40
100
Multipoint Method "❑
M h d
One -pont et o
Wet Preparation Lj Dry Preparation Lj Air Dried r
Notes /Deviations /References:
ASTMD 4318: Liquid Limit, Plastic Limit, & Plastic Index of Soils
Jimmy Thomasson Finley Lloyd, PE 3/31/2015
Technician Name Date Technical Responsibility Date
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
3718 Old Battleground Rd., Greensboro, NC. 27410
Form No. TR -D4318 -T89-90 #S&ME
Revision No. 0
Revision Date: 11120107 Liquid Limit, Plastic Limit, and Plastic Index
Another code ASTMD 4318 [K AASHTO T 89 ❑ AASHTO T 90 ❑ Quality Assurance
S & ME, Inc.- Greensboro 8646 West Market St. Suite 105, Greensboro NC 27409 ad
Project #: 1305-15-022 Report Date: 3-28-15
Project Name: MGP Retail Site - Rockingham Test Date(s) 3-27-15
Client Name:
Client Address:
Boring #: D-2 Sample #: Bulk Sample Date: 3-18-15
Location: NA Offset: NA Elevation: 1.0'-5.0'
Sample Description:
Tan Orange Sandy CLAY
8
Type and Specification
S&ME ID # Cal Date:
Type and Specification S&ME ID # Cal Date:
Balance (0.01 g)
5544 2/26/2015
Grooving tool 5788 2/28/2015
LL Apparatus
5571 2/28/2015
Grooving tool
Oven
5470 12/1/2014
Grooving tool
Pan #
Tare #:
8
22
Liquid Limit
15 4
5 6
Plastic Limit
120
118 9
A
Tare Weight
15.75
16.03
15.70
11.39
11.20
B
Wet Soil Weight + A
23.82
23.54
23.01
17.40
17.17
C
Dry Soil Weight + A
22.14
21.88
21.33
16.71
16.50
D
Water Weight (B -C)
1.68
1.66
1.68
0.69
0.67
E
Dry Soil Weight (C -A)
6.39
5.85
5.63
5.32
5.30
F
%Moisture (D/E)*100
26.3%
28.4%
29.8%
13.0%
12.6%
N
# OF DROPS
32
26
17
Moisture Contents determined
by ASTMD 2216
LL LL = F * FACTOR
Ave.
Average
12.8%
40.0
One Point Liquid Limit
N
Factor N Factor
20
0.974 26 1.005
21
0.979 27 1.009
35.0
22
0.985 28 1.014
23
0.99 29 1.018
C
0
U
24
0.995 30 1.022
0
30.0
25
1.000
h
NP, Non -Plastic ❑
Liquid Limit 28
Plastic Limit 13
Plastic Index 15
Group Symbol CL
0
25.0
20.o
10
15 20
25 30
35 40
100
Multipoint Method "❑
M h d
One -pont et o
Wet Preparation Lj Dry Preparation Lj Air Dried r
Notes /Deviations /References:
ASTMD 4318: Liquid Limit, Plastic Limit, & Plastic Index of Soils
Jimmy Thomasson Finley Lloyd, PE 3/31/2015
Technician Name Date Technical Responsibility Date
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
3718 Old Battleground Rd., Greensboro, NC. 27410
Form No: TR -D422 -WH -1 Ga
Revision No. 0
Revision Date: 07114108
Sieve Analysis of Soils
p —s: a
ASTM D 422 Quality Assurance
S&ME, Inc. - Greensboro 8646 west market St. Suite 105 Greensboro NC 27409
Project #: 1305-15-022 Report Date: 4-1-15
Project Name: MGP Retail Site - Rockingham Test Date(s): 3-27-15
Client Name:
Client Address:
Sample Id. B-1 Type: NA Sample Date: 3-18-15
Location: NA Sample: I Elevation: 1.0'-2.5'
Cobbles
< 300 nun (12") and > 75 mm (311)
Fine Sand
< 0.425 mm and > 0.075 nun (#200)
Gravel
< 75 mm and > 4.75 mm (#4)
Silt
< 0.075 and > 0.005 mm
Coarse Sand
< 4.75 mm and >2.00 mm (#10)
Clay
< 0.005 mm
Medium Sand
< 2.00 mm and > 0.425 mm (#40)
Colloids
< 0.001 mm
Maximum Particle Size
3/8"
Coarse Sand 1.3%
Fine Sand 31.6%
Gravel
0.1%
Medium Sand 24.5%
Silt & Clay 42.5%
Liquid Limit
Plastic Limit
Plastic Index
Specific Gravity
Cc =
###### Cu = ######
Moisture Content
Coarse Sand
1.3%
Medium Sand 24.5%
Fine Sand 31.6%
Description of Sand & Gravel Particles:
Rounded
❑ Angular ❑
Hard & Durable
❑
Soft ❑
Weathered & Friable ❑
Notes /Deviations /References:
Finley Lloyd, PE Project En ig neer 4/1/2015
Technical Responsibility Signature Position Date
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
3718 Old Battleground Rd., Greensboro, NC. 27410
Form No: TR -D422 -WH -1 Ga
Revision No. 0
Revision Date: 07114108
Sieve Analysis of Soils
p —s: a
ASTM D 422 Quality Assurance
S&ME, Inc. - Greensboro 8646 west market St. Suite 105 Greensboro NC 27409
Project #: 1305-15-022 Report Date: 4-1-15
Project Name: MGP Retail Site - Rockingham Test Date(s): 3-27-15
Client Name:
Client Address:
Sample Id. B-4 Type: NA Sample Date: 3-18-15
Location: NA Sample: 2 Elevation: 3.5'-5.0'
Cobbles
< 300 nun (12") and > 75 mm (311)
Fine Sand
< 0.425 mm and > 0.075 nun (#200)
Gravel
< 75 mm and > 4.75 mm (#4)
Silt
< 0.075 and > 0.005 mm
Coarse Sand
< 4.75 mm and >2.00 mm (#10)
Clay
< 0.005 mm
Medium Sand
< 2.00 mm and > 0.425 mm (#40)
Colloids
< 0.001 mm
Maximum Particle Size
3/8"
Coarse Sand 4.4%
Fine Sand 49.2%
Gravel
1.4%
Medium Sand 32.2%
Silt & Clay 12.8%
Liquid Limit
Plastic Limit
Plastic Index
Specific Gravity
Cc =
###### Cu = ######
Moisture Content
Coarse Sand
4.4%
Medium Sand 32.2%
Fine Sand 49.2%
Description of Sand & Gravel Particles:
Rounded
❑ Angular ❑
Hard & Durable
❑
Soft ❑
Weathered & Friable ❑
Notes /Deviations /References:
Finley Lloyd, PE Project En ig neer 4/1/2015
Technical Responsibility Signature Position Date
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
3718 Old Battleground Rd., Greensboro, NC. 27410
Form No. TR -D698-2
Revision No.: 0
Revision Date: 11121107
Moisture - Density Report #S&ME
Quality Assurance
S&ME, Inc. Raleigh, 3201 Spring Forest Road, Raleigh, North Carolina 27616
S&ME Project #: 1305-15-022 Report Date: 3/27/15
Project Name: MGP Retail Site - Rockingham Test Date(s): 3/24 - 3/27/15
Client Name:
Client Address:
Boring #: B-4 Sample #: Bulk Sample Date: 3/18/2015
Location: Borehole Offset: N/A Depth: 5 - 10 ft
Sample Description: Tan -Brown Silty SAND
Maximum Dry Density 116.8 PCF. Optimum Moisture Content 13.3%
ASTMD 698 -- Method A
Moisture -Density Curve Displayed: Fine Fraction ❑x Corrected for Oversize Fraction (ASTM D 4718) ❑
Sieve Size used to separate the Oversize Fraction: #4 Sieve ❑x 3/8 inch Sieve ❑ 3/4 inch Sieve ❑
Mechanical Rammer ❑ Manual Rammer ❑x Moist Preparation ❑ Dry Preparation ❑x
References/Comments/Deviations: ND=Not Determined.
ASTM D 422: Particle Size Analysis of Soils
ASTM D 2216: Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass
ASTM D 698: Laboratory Compaction Characteristics of Soil Using Standard Effort
Mal Kraj an, ET Laboratory Manager 3/27/2015
Technical Responsibility Signature Position Date
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
S&ME,Inc. - Corporate 3201 Spring Forest Road 15-022 B-4 (5 - ]Oft) Proctor.xls
Raleigh, NC. 27616 Page 1 of I
71
■0000■■■
I I ' MMMEMM■■
■0000010M<
■■■
ICurve NOME■MMMMMMMMMMMMNMMMMMMMMMMMM
,
■NOMMOMMON■OMMOMMOMMENNOM
■MMMMMMMMM■MMIC■MMMMM■MMM■
■MMMMMMMMM■MMr■MMMMM■MMM■
1
, Passing
■MMMMMMMMM■MMM■MMMMM■MMM■
■MMMMMMMMM■MMS■OMMMM■MMM■
NMMMMMMMMMWMMMMWWM0MMMMMM
314 100.0%
31811 100.0%
OMMMM
MMMMM I/MMaO O\\MIM MMMMM
#10 ND
#40 ND
■MMMMMMMMI/■MMF■■MM\\MM■MMM■
#60 ND
#200 ND
■MMMMMMMMMMMMMMMMMMMM0MMM
Oversize Fraction
■MMM■MMMMM■MMF�■NMMMM■MM�i1OBulk
Gravity
III MMMMMM■■■MMMMhM■■MMMMM■MA
, , Moisture
I I
I I I I I I I
% Oversize
ii
i,
Moisture -Density Curve Displayed: Fine Fraction ❑x Corrected for Oversize Fraction (ASTM D 4718) ❑
Sieve Size used to separate the Oversize Fraction: #4 Sieve ❑x 3/8 inch Sieve ❑ 3/4 inch Sieve ❑
Mechanical Rammer ❑ Manual Rammer ❑x Moist Preparation ❑ Dry Preparation ❑x
References/Comments/Deviations: ND=Not Determined.
ASTM D 422: Particle Size Analysis of Soils
ASTM D 2216: Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass
ASTM D 698: Laboratory Compaction Characteristics of Soil Using Standard Effort
Mal Kraj an, ET Laboratory Manager 3/27/2015
Technical Responsibility Signature Position Date
This report shall not be reproduced, except in full, without the written approval of S&ME, Inc.
S&ME,Inc. - Corporate 3201 Spring Forest Road 15-022 B-4 (5 - ]Oft) Proctor.xls
Raleigh, NC. 27616 Page 1 of I
Form No. TR -D1883 -T193-3 *S&ME
Revision No. 0 CBR (California Bearing Ratio) of Laboratory
Revision Date: 216108 Compacted Soil
ASTMD 1883 Quality Assurance
S&ME, Inc.Raleigh, 3201 Spring Forest Road, Raleigh, North Carolina 27616
Project #: 1305-15-022 Report Date: 4/1/15
Project Name: MGP Retail Site - Rockingham Test Date(s) 3/24 - 4/1/15
Client Name:
Client Address:
Boring #: B-4 Sample #: Bulk Sample Date: 3/18/15
Location: Borehole Offset: N/A Depth (ft): 5 - 10 ft
Sample Description: Tan -Brown Silty SAND
ASTMD 698 MethodA Maximum Dry Density: 116.8 PCF Optimum Moisture Content: 13.2%
Compaction Test performed on grading complying with CBR spec.
% Retained on the 3/4" sieve: 0.01%
Uncorrected' Values
: '
B' at I
:' at I
I I I I
I I I I I I
i
Before IISoaking
Effort (Blows per Layer)
Final Dry Density (PCF)
DensityCompactive
Initial Dry (PCF)
Average FinalMoisture Content 1 1
Moisture Content oftheCompacted Specimen�1
MoistureContent•/soaking) . 1
Percent Compaction
Percent Swell
Soak Time: 96 -hr Surcharge Weight 20.0 Surcharge Wt. per sq. Ft. 101.9
Liquid Limit ND Plastic Index ND
Notes/Deviations/References: ND=Not Determined.
Test specimen was compacted to 98% at 3% dry of optimum moisture.
Mal Krajan, ET
Technical Responsibility
Signature
Laboratory Manager 4/1/2015
Position Date
This report shall not be reproduced, except in full without the written approval of S&ME, Inc.
S&ME, Inc. - Corporate 3201 Spring Forest Road 15-022 B-4 (5 - ]Oft) CBR.xIs
Raleigh, NC. 27616 Page 1 of I
*S&ME
March 27, 2015
Bohler Engineering, NC, PLLC
4011 WestChase Boulevard
Raleigh, North Carolina 27607
Attention: Mr. Justin Brown
Via email: fibrown(a,bohlereng-com
Reference: Report for Soil Evaluation / Seasonal High Water Table (SHWT)
Estimation for Stormwater Best Management Practices (BMP's)
Proposed Retail Development
Hamlet Avenue (US 74B)
Rockingham, North Carolina
S&ME Project No. 4335-15-061
Bohler Engineering Project No. NCC142080
Dear Mr. Brown:
S&ME, Inc. (S&ME) has conducted a soil evaluation including Seasonal High Water
Table (SHWT) estimation in general accordance with S&ME Proposal No. 43-1500281,
dated March 3, 2015 and Bohler Engineering WA#2 dated March 5, 2015. Our
evaluation was conducted to provide information for the design of an appropriate
stormwater Best Management Practice (BMP) device and a Stormwater Management
Permit Application to the North Carolina Department of Environment and Natural
Resources (NCDENR) — Division of Energy, Minerals, & Land Resources (DEMLR). A
soil scientist evaluated the soil conditions within the proposed stormwater BMP area.
PROJECT BACKGROUND
We understand that a retail development is planned north of US 74 Business and west of
an existing Zaxby's in Rockingham, North Carolina. The 5.15 +/- acre site is currently
moderately to heavily wooded. The site appears to have been previously developed and
has also been used as a dumping area. Miscellaneous construction debris was observed
randomly across the site. An apartment complex is currently under construction, just
north of the proposed site. A sedimentation basin is located immediately adjacent to the
northern property line, just north of the building. The basin discharges water onto the site
in the vicinity of the northern most proposed detention pond.
S&ME, INC. / 3201 Spring Forest Road / Raleigh, NC 27616 / p 919.872.2260 f 919.790.8909 / www.smeinc.com
Soil Evaluation for Stormwater BMP S&ME Project No. 4335-15-061
MGP Retail Site, Rockingham, North Carolina March 27, 2015
*Based map obtained from Google Earth (Imagery Date 11 /30/2014).
The retail building will have a plan area of about 36,000 square feet with 175 space
parking lot with associated drive areas.
As a result of the proposed construction and associated impervious surface, stormwater
BMP's are required to treat stormwater generated from the site to comply with State
stormwater management requirements. Use of stormwater BMP's are subject to the
suitability of site soils and regulatory approval. Regulatory guidance on requirements for
permitting of stormwater BMP's are provided in the DEMLR— Stormwater BMP Manual
(NCDENR-SW-BMP), dated July 2007 (Revised September, 2009).
Based on the site plan two BMP's will be located on the site, one in the southwest corner
along US 74 B and the other along the northern property line in the vicinity of Boring
Locations B 1 through B-3 which are depicted on the attached Stormwater Soil Evaluation
Map (Figure 1).
FINDINGS
The soil evaluation was performed with hand auger borings at three locations (B-1
through B-3) within the proposed BMP areas as shown on the attached Figure 1. Our
evaluation consisted of identifying and recording the soil morphological conditions at
these locations in order to develop soil profile descriptions, which are also shown on the
attached Figure 1.
2
Soil Evaluation for Stormwater BMP S&ME Project No. 4335-15-061
MGP Retail Site, Rockingham, North Carolina March 27, 2015
Permeability/Hydraulic Conductivity Estimation
Under current DEMLR requirements for various stormwater devices, the in-situ soil
permeability/conductivity is an important design factor. Therefore, the soil profile
descriptions on the attached Figure 1 show the soil morphological conditions including
texture, estimated United States Department of Agriculture (USDA) permeability and
estimated USDA hydraulic conductivity (Ksat) for the different soil horizons found on-
site.
In the area of Boring Location B-1 within the proposed stormwater BMP area, the soil
surface layer to a depth of 12 inches consisted of sandy loam material which has an
estimated USDA permeability range of 2 to 6 inches per hour and USDA estimated Ksat
range of 0.14 to 1.4 inches per hour. The underlying soil material from a depth of 12 to 18
inches consisted of sandy clay loam which has an estimated USDA permeability range of
0.6 to 2 inches per hour and USDA estimated Ksat range of 0.14 to 1.4 inches per hour,
and sandy clay from a depth of 18 to 34+ inches which has an estimated USDA
permeability range of 0.06 to 0.2 inches per hour and USDA estimated Ksat range of
0.014 to 0.14 inches per hour.
In the area of Boring Location B-2 within the proposed stormwater BMP area, the soil
surface layer to a depth of 14 inches consisted of sandy loam material which has an
estimated USDA permeability range of 2 to 6 inches per hour and USDA estimated Ksat
range of 0.14 to 1.4 inches per hour. The underlying soil material from a depth of 14 to 22
inches consisted of sandy clay loam which has an estimated USDA permeability range of
0.6 to 2 inches per hour and USDA estimated Ksat range of 0.14 to 1.4 inches per hour,
and sandy clay from a depth of 22 to 36 inches which has an estimated USDA
permeability range of 0.06 to 0.2 inches per hour and USDA estimated Ksat range of
0.014 to 0.14 inches per hour, and sandy clay loam from a depth of 36 to 42+ inches
which has an estimated USDA permeability range of 0.6 to 2 inches per hour and USDA
estimated Ksat range of 0.14 to 1.4 inches per hour.
In the area of Boring Location B-3 within the proposed stormwater BMP area, the soil
surface layer to a depth of 18+ inches consisted of sandy loam material which has an
estimated USDA permeability range of 2 to 6 inches per hour and USDA estimated Ksat
range of 0.14 to 1.4 inches per hour.
Please refer to the enclosed map and soil profile descriptions, for more information.
These estimates were obtained from one or more of the following: Rockingham County
Soil Survey "Physical & Chemical Properties of the Soil - Permeability"; and/or USDA-
NRCS (United States Department of Agriculture - Natural Resource Conservation
Service) official series description, and/or "NRCS Field Book for Describing & Sampling
Soils" the permeability estimates were converted to conductivity on the profile
description tables.
3
Soil Evaluation for Stormwater BMP SAME Project No. 4335-15-061
MGP Retail Site, Rockingham, North Carolina March 27, 2015
SHWT Estimation and OWT Measurement
Under current DEMLR regulations, the depth of various stormwater BMP devices from
the SHWT is an important design consideration. For example, current regulations for wet
detention basins require that the permanent pool elevation (PPE) shall be no more than
six inches above or below the SHWT in order to maintain a permanent pool of water and
to avoid doing a hydrogeologic analysis. Therefore, S&ME evaluated the SHWT by
advancing hand auger borings and evaluating the soil for evidence of SHWT influence.
This evaluation involved looking at the actual moisture content in the soil and observing
the matrix and mottle colors. Depending on the soil texture, the soil color will indicate
processes that are driven by SHWT fluctuations, such as iron reduction and oxidation and
organic matter staining. See Table 1 below and the soil profile descriptions on Figure 1
for the estimated SHWT depths based on soil color.
In addition, S&ME recorded the observed water table (OWT) level below existing ground
level (EGL) at each indicated hand auger boring location if applicable. The OWT was
measured as the static water level in each of the temporary hand auger boring locations. It
should be noted that the static water level/OWT measured in the auger holes is a
measurement of the water table at that moment and does not represent an average water
level or the highest point at which the water table may rise to. Furthermore, it is expected
that groundwater elevations in the study area will likely be influenced by factors such as
precipitation and proximity to surface water discharge/recharge features.
See Table 1 below and the attached soil profile descriptions for the estimated SHWT
depths based on soil color and measured OWT depths.
Table 1: SHWT & OWT Information
Boring
Location
SHWT
inches below EGL
OWT
(inches below EGL)
B-1
30
12
B-2
36
30
B-3
<12
8
LIMITATIONS
• Data and conclusions presented herein are based on materials encountered at the
hand auger boring locations only. Conditions may vary between hand auger boring
locations and in other areas of the proposed stormwater BMP's.
4
Soil Evaluation for Stormwater BMP S&ME Project No. 4335-15-061
MGP Retail Site, Rockingham, North Carolina March 27, 2015
CLOSING
S&ME appreciates the opportunity to provide these services to you. If you have any
questions, please contact us.
Sincerely,
S&ME, Inc.
Walter Cole, L.S.S.
Environmental Scientist
(919) 801-3798
wcole@smeinc.com
alp*
Rob Willcox, L.S.S. z -
Natural Resources Team Leader
Attachments: Figure 1: Stormwater Soil Evaluation Map
SAProjects\4335-15-061\Rockingham MGP Retail Site\Reports\Storrnwater Soil Evaluation.doc
Rockingham MGP Site
S&ME Project No, 4305-15-061
Boring B-1
Seasonal High Water Table from existing ground surface: 30 Inches (2.5 feet)
Observed Water Table from existing ground surface: 12 Inches ( 1.0 feet)
Boring B-2
lor
Color
USDA Estimated USDA Estimated
Horizon
Moist
Consistence
USDA Estimated
USDA Estimated
Horizon
Depth (in)
Texture
Grade
Structure
Consistence
Notes
Permeability (INhr)
Conductivity (In/hr)
Matrix Mottles
Al
0-3
10YR 3/1
sandy
weak
' subangular
may, made
2 - 6 1 4 -14
loam
block
2 - 6
1 4 - 14
A2
3.12
10YR 4/3
sandy
weak
subangular
very friableloam
2 - 6
14 .14
Btl
12-18
10YR 5/6 5YR 5/8
sandy
weak
subangular
Irm -enable
clay loam
blocky
06-2
0 14 .14
Bt2
18-30
10YR 5/6 SYR 518
sandy
weak
subangular
In"
06-2
0 14. 14
Bt2
22-28
10YR 5/3
clay
I
blocky 1
Armclay
1
006-02
0014-014
Bt3
30-34.
10YR 5/6 10YR 6/1
1 sandy
weak
subangular
Irm
006 - 02
0 014 -0 14
10R4/8
clay
I
blocky
Bt3
2832
006-02
0014-014
Seasonal High Water Table from existing ground surface: 30 Inches (2.5 feet)
Observed Water Table from existing ground surface: 12 Inches ( 1.0 feet)
Boring B-2
aessonai nIgn vvaler iaDm nom eauung grouno sunace: oo inches (a.0 reef I
Obseryed Water Table from exlstl ng ground surface: 30 Inches ( 2.5 feet)
Boring B-3
lor
Color
USDA Estimated USDA Estimated
Horizon
Moist
Consistence
USDA Estimated
USDA Estimated
Horizon
Depth (in)
Texture
Grade
Structure
Consistence
Notes
Permeability (INhr)
Conductivity (INhr)
Matrix Mottles
Al
03
10YR 3/1
weak
subayar
very, made
2 - 6 1 4 -14
loam
2 - 6
1 4 - 14
A2
314
tOYR 4/3
sandy
amm
weak
subangular
very made
2 - 6
1 4 - 14
Bl1
14,22
10YR 5/4
sandy
weak
subangular
Ann - enable
clay loam
06-2
0 14. 14
Bt2
22-28
10YR 5/4
sandy
weak
subangular
Armclay
006 - 02
0 014 -0 14
sarrdy
subangular
Bt3
2832
tOYR 5/8 5YR 5/8
Clay
weak
blocky
Am
006-02
0.014 -0 14
10Y
sandy
subangular
B14
3236
10YR 5/6 5YR 5/88 1
5YR
clay
weak
blocky
Am
006-02
0.014 -0 14
Bis
36.42*
10YR 6/1
10YR 516
sandy
weak
subangular
Arm
1 O 418
clay loam
blocky
0 6 - 2
0 14. 14
aessonai nIgn vvaler iaDm nom eauung grouno sunace: oo inches (a.0 reef I
Obseryed Water Table from exlstl ng ground surface: 30 Inches ( 2.5 feet)
Boring B-3
seasonal nrgn water [a D18 from existing ground surface: <12 Inches (<1.0 toot)
Observed Water Table from existing ground surface: a inches ( 0.07 foot)
LEGEND
B-# APPROXIMATE SOIL AUGER BORING LOCATION
At. Ar WITH ASSOCIATED PROFILE DESCRIPTION ABOVE
! HIS MAP IS ONLY A PORTION OF A REPORT FOR THE NAMED PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT
'BACKGROUND AUTOCAD MAP FROM FILE SUPPLIED BY BOHLER ENGINNERING NAMED ARS ALTA 150319.DWG
ch
0
C14
= Y
U > m
tr to O
W
Y
Q < S
0 U
w
to R m
D U7 i
UJ Z z
Z I to
Lli O
aZ 'oma a
U w w
In a o
co
LIJN
O z
U =
z nw
LIJ R
>o
V) W�
Cl)F
U�
n
UL
W C7
W Z
y Z lY
CD C-
1` Z rn
U.1
U�
Z rr)
I
O Q
_Z
Q J
� U �
LL, U
Q O =
W d
-JO
J Q Z
O w�
U _
a 0
2iZ
LLj leU
O
U)
FIGURE N0.
1
lor
Moist
USDA Estimated USDA Estimated
Horizon
Depth (in) Moores Texture Grade Structure
Consistence
Notes
Permeablllty (In/hr) Conductivity (INhr)
At
weak subangular
0.6 sandy
r
� made
loam
2-6 a - 1a
A2
8.18+ ganm' weak subaylar
very trade
2 - 6 1 4 -14
seasonal nrgn water [a D18 from existing ground surface: <12 Inches (<1.0 toot)
Observed Water Table from existing ground surface: a inches ( 0.07 foot)
LEGEND
B-# APPROXIMATE SOIL AUGER BORING LOCATION
At. Ar WITH ASSOCIATED PROFILE DESCRIPTION ABOVE
! HIS MAP IS ONLY A PORTION OF A REPORT FOR THE NAMED PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT
'BACKGROUND AUTOCAD MAP FROM FILE SUPPLIED BY BOHLER ENGINNERING NAMED ARS ALTA 150319.DWG
ch
0
C14
= Y
U > m
tr to O
W
Y
Q < S
0 U
w
to R m
D U7 i
UJ Z z
Z I to
Lli O
aZ 'oma a
U w w
In a o
co
LIJN
O z
U =
z nw
LIJ R
>o
V) W�
Cl)F
U�
n
UL
W C7
W Z
y Z lY
CD C-
1` Z rn
U.1
U�
Z rr)
I
O Q
_Z
Q J
� U �
LL, U
Q O =
W d
-JO
J Q Z
O w�
U _
a 0
2iZ
LLj leU
O
U)
FIGURE N0.
1