Vance County
NCDWR Project No. 20160316
Bridge 52 on SR 1518
State Project No. 17BP.S.R.63
APPROVAL of 401 WATER QL'ALITY CERTIFICATION and TAR-PAMLICO BUFFER
AUTHORIZATION, with ADDITIONAL CONDITIONS
Mr. J. R. Hopkins, P.E., Division Engineer
NCDOT, Division 5
2612 North Duke Street
Durham, NC 27704
Dear Mr. Hopkins:
You have our approval, in accordance with the conditions listed below, for the following impacts for the purpose of
replacing Bridge 52 with a culvert in Vance County:
Stream Im acts in the Tar-Pamlico River Basin
Permanent N ill to Perennial Bank Stabilization to Temporary Dewatering to Total Stream
___ StrParr�_�near ft1 _ � Peren�ial S±rearr� (linear ftl_Y_ PPrennial StrQam (!inear ftl _,_1 �a_ct _(linear ft1
Total � 54
64
Total Stream Impact for Project: 118 linear feet.
Site I Temaorarv Fill
Total I 0.01
Site
Totals
71 (Concurrent)
Wetland Im acts in the Tar-Pamlico River Basin
, Excavation (ac) Mechanized Clearin� (ac) , Total Wetland I
0.02
Total Wetland Impact for Project: 0.10 acres.
0.07
0.10
118
Tar-Pamlico Riparian Buffer Impacts_
Zone 1 Impact Zone 1 Buffer Mitigation Required Zone 2 Impact Zone 2 Buffer Mitigation
s ft usin 3:1 ratio s ft Re uired usin 1.5:1 ratio
4383 N/A 2818 N/A
* n/a = Total for Site is less than 1/3 acre and 150 linear feet of impact, no mitigation required
Total Buffer Impact for Project: 7201 square feet.
The proiect shall be constructed in accordance with your application received March 30, 2016. After reviewing your
application, we have decided that these impacts are covered by General Water Quality Certification Number 3886.
This certification corresponds to the Nationwide Permit 14 issued by the Corps of Engineers. This approval is also
valid ior the Tar-Pamlico Riparian Buffer Rules (l�fi NCAC .02B .0295). In addition, you should acquire any otner
federal, state or local permits before you proceed with your project including (but not limited to) Sediment and
Erosion Control, Non-Discharge and Water Supply Watershed regulations. Th�s approval will expire with the
accampanying 404 permit.
State o: NortL- Carolina IEr,vironmentai i?aality � �Va!er Resoures
1617 ivlail Service Cznter; Raleigh, Nurin Carolina 2i699-1517
?hore:9?9-807-�3QG
T'his approval is valid solely for the purpose and design described in your application (unless modified below).
Should your nroject change, you must notify the NCDWR and submit a new application. If the pronerty is sold, the
new owner must be given a copy of this Certiiication and approval letter, and is thereby responsible for complying
with all the conditions. If total wetland flls for this project (now or in the fizture) exceed one acre, or of total•
impacts to streams (now or in the future) exceed 1501inear feet, compensatory mitigation may be required as
described 'm 15A NCAC 2H .0506 (h) (6) and (7). Additional buffer impacts may require compensatory mitigation
as described in 15A NCAC 2B.0259. For this approval to remain valid, you must adhere to the conditions listed in
the atiached ce�iification and any additional conditians lisied below.
Conditions of Certification: .
1. As a condition of this 401 Water Quality Certification, the bridge demolition must be accomplished in strict
compliance with the most recent version of NCDOT's Best Management Practices for Construction and
Maintenance Activities. [15A NCAC 02H .0507(d)(2) and 15A NCAC 02H .0506(b)(5)]
2. Unless otherwise approved in this certification, placement of culverts and other structures in open waters and
streams, shall be placed below the elevation of the streambed by one foot for all culverts with a diameter greater than
48 inches, and 20 percent of the culvert diameter for culverts having a diameter less than 48 inches, to allow low flow _
passage of water and aquatic life. Design and placement of culverts and other structures including temnorary erosion
control measures shall not be conducted in a manner that may result in dis-equilibrium of wetlands or streambeds or
banks, adjacent to or upstream and down stream of the above structures. The applicant is required to provide evidence
that the equilibrium is being maintained if requested in writing by the NCDWR. If this condition is unable to be met
due to bedrock or other limiting features encountered during construction, please contact the NCDWR for guidance on
how to proceed and to determine whether or not a permit modification will be required. [15A NCAC 02H.0506(b)(2)]
3. If multiple pipes or barrels are required, they shall be designed to mimic natural stream cross section as closely as
possible including pipes or barrels at flood plain elevation and/or sills where appropriate. Widening the stream
channel should be avoided. Stream channel widening at the inlet or outlet end of structures typically decreases water
vel�city causing sediment deposition that reauires increased maint�na�nce and disrupts aquatic life passage. f 15A
TI(�A� �J2H.�505(b;(21� - - -- - - -
4. Riprap shall not be p:aced in the active thalweg channel or placed in the streambed in a ma.�ner that precludes
aquatic life passage. Bioengineering boulders or structures should be properly designed, sized and installed. [15A
NCAC 02H.0506(b)(2)]
5. For any streams being impacted due to site dewatering activities, the site shall be graded to its preconstruction
contours and revegetated with appropriate native species. [15A NCAC 02H.0506(b)(2)]
6. All stormwater runoff shall be directed as sheetflow through stream buffers at non-erosive velocities, un?ess
otherwise approved by this certification. [15A NCAC 2B.0259]
7. All riparian buffers impacted by the placement of temporary fill or clearing activities shall be restored to the
preconstruction contours and revegetated. Maintained buffers shall be permanently revegetated with non-woody
species by the end of the growing season following completion of construction. For the purpose of this conditior.,
maintained buffer areas are defined as areas within the transportation corridar that will be subject to regular NCDOT
maintenance activities including mowing. The area with non-maintained buffers shall be permanently revegetated with
native woody species before the next gowing season following completion of construction. [15A NCAC 2B.0259 j
8. Pursuant to 15A NCAC 2B.0259(6), sediment and erosion control devices shall not be placed in Zone 1 of any
Tar-Pamlico Buffer without priar approval by the NCDWR. At this time, the NCDWR has approved no sediment and
erosion control devices in Zone 1, outside of the approved project impacts, anywhere on this project. Moreover,
sediment and erosion control devices shall be allowed in Zone 2 of the buffers provided that Zone 1 is not
c�mpromised and that discharge is released as difi�.�se flow.
9. If concrete is used during construction, a dry work area shall be maintained to prevent direct contact between
�uring cancretz and str�ain ;�at�r. Wate� that inadvertently cont�cts uncured concrete shall not be dischargzd to
surface waters due to trie potential for eleyated pH and possihle aquatic life and fsh kiils. [15A NCAC 02BA200]
10. During the construction of the project, no staging of equipment of any kind is permitted in waters of the U.S., ar
protected riparian buffers. [15A NCAC 02H.0506(b)(2)] �
11. The dimension, pattern and profile of the stream above and below the crossing shall not be modified. Disturbed
floodplains and streams shall be restored to natural geomorphic conditions. [15A NCAC 02H.0506(b)(2)]
12. The use of rip-rap above the Normal High Water Mark shall be minimized. Any rip-rap placed for stream
stabilization shall be p?aced in stream cnannels in such a manne: that it does not impede aquatia ?ife passage. [15A
NCAC 02H.0506(b}(2)]
13. The Permittee shall ensure that the fmal design drawings adhere to the permit and to the permit drawinas
submitted for approval. [15A NCAC 02H .0�07 (c) and 15.4 NCAC 02H .0506 (b)(2) and (cj(2)]
14. All work in or adjacent to stream wate:s shall be conducted in a dry work area. Approved BMP measures from
the most current version of NCDOT Construction and Maintenance Activities manual such as sandbags, rock berms,
cofferdams and other diversion structures shall be used to prevent excavation in flowing water. [15A NCAC
02H.0506(b)(3) and (c)(3)]
15. Heavy equipment shall be operated from the banks rather than in the stream channel in order to minimize
sedimentation and reduce the introduction of other pollutants into the stream. [15A NCAC 02H.0506(b)(3)]
16. All mechanized eauipment operated near surface waters must be regularly inspected and maintained to prevent
contamination of stream waters from fuels, lubricants, hydraulic fluids, or other toxic materials. [15A NCAC
02H.0506(b)(3)] ' ,
17. No rock, sand or other materials shall be dredged from the stream channel except where authorized by this
certification. [15A NCAC 02H.0506(b)(3)]
18. Discharging hydroseed mixtures and washing out hydroseeders and other equipment in or adjacent to surface waters
is prohibited. [15A NCAC 02H.0506(b)(3)]
19, 'I'hP p�rmit±PP an� its at�thorize:i agents shal_l c�ndur,t its activ�ties in a manner censistent with St�te �*.�atPr q�ality
standards (including any requirements resulting from compliance with §303(d) of the Clean Water Act) and any other
appropriate requirements of State ar.d Federal law. If the NCD WR determines that such standards or laws are not being
met (including the failure to sustain a designated or achieved use) or that State or federal law is being violated, or that
further conditions are necessary to assure compliance, the NCDWR may reevaluate and modify this certification. [15A
NCAC 02B.U200]
20. All fill slopes located in iurisdictional wetlands shall be placed at slopes no flatter than 3:1, unless otherwise
authorized by this certification. [15A NCAC 02H.0506(b)(2)]
21. A copy of this Water Quality Certification shall be maintained on the construction site at all times. In addition, the
Water Quality Certification and all subsequent modifications, if any, shall be maintained with the Division Engineer and
the on-site project manager. [15A NCAC 02H .0507(c) and 15A NCAC 02H .0506 (b)(2) and (c)(2)]
22. T'he outside b�.�ffer, wetland or water boundary located within the construction corridor approved by this autharization
shall be clearly marked by highly visible fencing prior to any land disturbing activities. Impacts te areas within the
fencing are prohibited unless otherwise authorized by this certification. [15A NCAC 02H.0501 and .0502]
23. The issuance of this certification does not exempt the Permittee from complying with any and all statutes, rules,
regulations, or ordinances that may be imposed by other government agencies (i.e. local, state, and federal) having
jurisdiction, including but not limited to applicable buffer rules, stormwater management rules, soil erosion and
sedimentation control requirements, etc.
24. The Permittee sha11 report any viaiations of this certification to the i7ivision of Water I��sources within 24 haurs of
discovery. [15ANCAC 02B.0506(b)(2)] .
25. Upon cam�letion af the project (including any impacts at associated b�rrow� of waste sites), tr�e NCDOT Bivisian
Engineer snall corriplete and return the enclosed "Certificatian of Completion Form" to notify t.he NCDWI� wnen alt
work included in the 401 Certification has been completed. [i5A NCAC 02H.0502(fl]
26. Native riparian vegetation (ex. list herbaceous, trees, and shrubs native to your geographic region) must be
reestablished in the riparian areas within the construction limits of the project by the end of the growing season following
completion of construction.[15A NCAC 02B.0259(10)] and'[15A NCAC 02B.0506(b)(2)]
27. There shall be no excavation from, or waste disposal into, jurisdictional wetlands or waters associated with this
permit without appropriate modification. Should waste or borrow sites, or access roads to waste or borrow sites, be
located in wetlands or streams, compensatory mitigation will be required since that is a direct impact from road
construction activities.[15A NCAC 02H.0506(b)(3) and (c)(3)]
28. Erosion and sediment control practices must be in full compliance with all specifications governing the proper design,
installation and operation and maintenance of such Best Management Practices in order to protect surface waters
standards [15A NCAC 02H.0�06(b)(3) and (c)(3)]:
a. The erosion and sediment control measures for the project must be designed, installed, operated, and
maintained in accordance with the most recent version of the North Carolina Sediment and Erosion
Control Planning and Design Manual.
b. T'he design, installation, operation, and maintenance of the sediment and erosion control measures must
be such that they equal, or exceed, the requirements specified in the most recent version of the North
Carolina Sediment and Erosion Control Manual. The devices shall be maintained on all construction
sites, borrow sites, and waste pile (spoil) projects, including contractor-owned or leased borrow pits
associated with the project.
c. For borrow pit sites, the erosion and sediment control measures must be designed, installed, operated,
and maintained in accardance with the most recent version of the North Carolina Surface Mining
Manual.
d. The reclamation measures and implementation must comply with the reclamation in accordance with the
requirements of the Sedimentation Pollution Control Act.
29. Sediment and erosion control measures shall not be placed in wetlands or waters unless otherwise approved by this
Certification. [15A NCAC 02H.0506(b)(3) and (c)(3)]
If you wish to contest any statement in the attached Certification you must file a petition for an administrativz
hearing. You may obtain the petition form from the office of Administrative hearings. You must file the petition
with the office of Administrative Hearings within sixty (60) days of receipt of this notice. A petition is considered
filed when it is received in the office of Administrative Hearings during normal office hours. The Office of
�Administrative Hearings accepts filings Monday through Friday between the hours of B:OOam and S:OOpm, except
for official state holidays. The original and one (1) copy of the perition must be filed with the Office of
Administrative Eearings.
The petition may be faxed-provided the original and one copy of the document is received by the Office of
Administrative Hearings within five (5) business days following the faxed transmission.
The mailing address for the Office of Administrative Hearings is:
Office of Administrative Hearings
6714 Mail Service Center
Raleigh, NC 27699-6714
Telephone: (919) 431-30U0, Facsimile: (919j 431-3100
A copy of the petition must also be served on DEQ as follows:
Mr. Sam M. Hayes, General Counsel
Department of Environmental Quality
160 i Mail Service Center
This letter completes the review of the Division of Water Resources under Section 401 of the Clean Water Act. If you
have any questions, please contact Rob Ridings at 919-707-8786.
Sincerely,
� �
S. Jay Zimmerman, Director
Division of Water Resources
Electronic copy only distribution:
Eric Alsmeyer, US Army Corps of Engineers, Raleigh Field Office
Chris Murray, Division 5 Environmental Officer
File Copy
Water Resources
ENVIRONMENTAI OUALII Y
NCDWR Project No.:
Applicant:
Project Name:
Date of Issuance of 401 Water Quality Certification:
County:
F',��I� :��1CCROkY
I)ON�1L[) R. VAN DER VAART
;��,�, ,
S. JAY 'Z,IMMERMAN
Il:�.,.i..
Certificate of Completion
Upon completion of all work approved within the 401 Water Quality Certification or applicable Buffer Rules, and
any subsequent modifications, the applicant is required to return this certificate to the 401 Transportation Permitting
Unit, North Carolina Division of Water Resources, 1617 Mail Service Center, Raleigh, NC, 27699-1617. This form
m«y �e rcturned tc NCDWR b-y thz applicart, the apNlica7t's authar�zed agc�t, ar thc prcject engineer. It is not
necessary to send certificates from all of these.
Applicant's Certification
I, , hereby state that, to the best of my abilities, due care and diligence
was used in the observation of the construction such that the construction was observed to be built within substantial
compliance and intent of the 401 Water Quality Certification and Buffer Rules, the approved plans and
specifications, and other supporting materials.
Si��ature: Date:
���era�'� C�;tifcut:osz
[, , hereby state that, to the best of my abilities, due care and diligence
was used in the observation of the construction such that the construction was observed to be built within substantial
compliance and intent of the 401 Water Quality Certification and Buffer Rules, the approved plans and
specifications, and other supporting materials.
Signature: Date:
Engineer's Certifccation
Partial Final
I, , as a duly registered Professional Engineer in the State of North
Carolina, having been authorized to observe (periodically, weekly, full time) the construction of the project for the
Permittee hereby state that, to tne best of my abilities, due care and diligence was used in the observation of the
construction such that the construction was observed to be built within substantial compliance and intent of the 40l
Water Quality Certification and Buffer Rules, the approved plans aiid specifications, and other supporting materials.
Signature Registration No.
I�ate
State of North Ca:clina !Em•i;onmzntal Quality I �Vatcr Resou:ces