LETTER OF APPROVAL WITH MODIFICATIONS
Gray Wolf Investments
Attn: Ben Mathis, Chief Operating Officer
325 US Hwy 70W
Clayton,NC 27520
RE: Project Name: Kelly Farms
Acres: 43.5
Project ID: HARNE-2024-758
County: Harnett, City: Lillington, Address: US 421
River Basin: Cape Fear
Stream Classification: Other
Submitted By: Kimley Horn and Associates, Inc.
Date Received by LQS: December 14,2023
Plan Type: New
Dear Mr. Mathis:
This office has reviewed the subject erosion and sedimentation control plan and hereby issues this Letter
of Approval. This plan approval shall expire three (3) years following the date of approval, if no land-
disturbing activity has been undertaken,as is required by Title 15A NCAC 4B .0129. Should the plan not
perform adequately, a revised plan will be required(G.S. 113A-54.1)(b).
As of April 1,2019,all new construction activities are required to complete and submit an electronic Notice
of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the NCG010000 Construction
General Permit. After the form is reviewed and found to be complete,you will receive a link with payment
instructions for the $100 annual permit fee. After the fee is processed, you will receive the COC via
email. As the Financially Responsible Party shown on the FRO form submitted for this project,you MUST
obtain the COC prior to commencement of any land disturbing activity. The eNOI form may be
accessed at deq.nc.gov/NCG01. Please direct questions about the NOI form to Paul Clark at
Paul.clark@ncdenr.gov.After you submit a complete and correct NOI Form,a COC will be emailed to you
within three business days. A $120 fee will be charged annually until a Notice of Termination is issued.
This fee is to be sent to the DEMLR Stormwater Central Office staff in Raleigh. If the owner/operator of
this project changes in the future,the new responsible party must obtain a new COC.
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following documentation be kept on
file at the job site:
1. The approved E&SC plan as well as any approved deviation.
D
E North Carolina Department of Environmental Quality I Division of Energy,Mineral and Land Resources
Fayetteville Regional Office 1225 Green Street,Suite 714 I Fayetteville,North Carolina 28301
NORTH CAROLINA
uepanmem m Environmental Quality 910.433.3300
Letter of Approval with Modifications
Gray Wolf Investments
January 12,2024
Page 2 of 3
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
Also,this letter gives the notice required by G.S. 113A-61.1(a)of our right of periodic inspection to ensure
compliance with the approved plan.
Title 15A NCAC 4B .0118(a)requires that a copy of the approved erosion control plan be on file at the job
site. Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to
ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance-oriented, requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project, it is
determined that the erosion and sedimentation control plan is inadequate to meet the requirements of the
Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66), this
office may require revisions to the plan and implementation of the revisions to ensure compliance with the
Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws,regulations, and rules. In addition, local city or county ordinances or rules may also apply to
this land-disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the Financial
Responsibility Form,which you provided.You are requested to file an amended form if there is any change
in the information included on the form. This permit allows for a land-disturbance, as called for on the
application plan,not to exceed the approved acres. Exceeding the acreage will be a violation of this permit
and would require a revised plan and additional application fee.In addition,it would be helpful if you notify
this office of the proposed starting date for this project.
Your cooperation is appreciated.
Sincerely
odi Pace,EI
Regional Engineering Associate
DEMLR
Enclosures: Certificate of Approval
Modifications Required for Approval
NPDES NCGO1 Fact Sheet
cc: Katie Witt,Kimley Horn and Associates,Inc. (electronic copy)
Jay Sikes,Building Inspector(electronic copy)
DEMLR-Fayetteville Regional Office
Letter of Approval with Modifications
Gray Wolf Investments
January 12,2024
Page 3 of 3
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: KELLY FARMS
Project Number: HARNE-2024-758
County: HARNETT
Specify the type of matting to be used in the Clean Water Diversions. It must be more robust than straw
w/net. The Curly Wood or Coir Fiber mattings are both acceptable.
All temporary diversions with a velocity greater than 2 ft/sec must have a temporary liner. Specify which
diversions need which liner.
Provide a time of concentration calculation for the basin.
Construction Sequence#6—silt fence must be placed around the stockpile immediately and it must be
seeded within 14 days.
Provide two full size copies each of revised plan sheets, showing all the Modifications required for
approval,prior to beginning any land-disturbing activity.
Ref: G.S. 113A-54.1 through G.S. 113A-57
Sections 15A NCAC 04A.0101 through 15A NCAC 04E.0504
General Permit NCG 010000 NPDES for Construction Activities