HomeMy WebLinkAboutSW5240202_Emails_20241018 Beeker, Jacob I
From: Beeker, Jacob I
Sent: Friday, October 18, 2024 3:34 PM
To: Ryan Wadsworth; Tim Hess; Mike Zaccardo; Brent Wood
Cc: Valentine, Thad; svc_post_construction_stormwater
Subject: Re: [External] RE: SW5240202; Wrenn Villas (Franklin)
Good afternoon,
The Division of Energy, Mineral, and Land Resources (DEMLR) received a complete Stormwater Management
Permit Application for the subject project on October 14th, 2024.Staff review of the plans and specifications
has determined that the project, as proposed,will comply with the Stormwater Regulations set forth in Title 15A
NCAC 21-1.1000 - 1062 rules.We are forwarding Permit No.SW5240201, dated October 18th, 2024,for the
construction,operation and maintenance of the built-upon areas (BUA)and vegetated conveyances or areas
associated with the subject project.This permit shall be effective from the date of issuance and shall be subject
to the conditions and limitations as specified therein and does not supersede any other agency permit that may
be required.
The original signed permit package and approved plans are being mailed to the permittee,ARS Wrenn Estates,
LLC, at the following address(NOTE:An electronic version of this permit can be found in our online repository:
https://edocs.deq.nc.gov/WaterResources/Browse.aspx?id=494276&dbid=0&repo=WaterResources):
ARS Wrenn Estates, LLC
Attn: Brent Wood, Manager
1524 Canterbury Road
Raleigh, NC 27608
1 will hold onto our hard copies of these projects for 30 days (in case any issues/typos with the permit are
noticed and corrections need to be made) after which point,they will be kept on file at the Raleigh Regional
Office. If you have any questions, or need additional information concerning this matter, please contact Jacob
Beeker at postconstruction(a)deq.nc.gov.
Thankyou,
Jacob Beeker(He/Him)
Environmental Engineer
Division of Energy, Mineral, and Land Resources
North Carolina Department of Environmental Quality
Office:(919) 707-9214
iacob.beeker(-)deq.nc.gov
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
From: Ryan Wadsworth <Ryan.Wadsworth@timmons.com>
Sent: Friday, October 11, 2024 9:04 AM
To: Beeker,Jacob I <jacob.beeker@deq.nc.gov>;Tim Hess<Tim.Hess@timmons.com>; Mike Zaccardo
<Mike.Zaccardo@timmons.com>;Valentine,Thad <thad.valentine@deq.nc.gov>
Cc: svc_post_construction_stormwater<postconstruction@deq.nc.gov>; Holland, Brianna
1
<brianna.holland@deq.nc.gov>; Lawyer, Mike<mike.lawyer@deq.nc.gov>
Subject: RE: [External] RE: SW5240202; Wrenn Villas (Franklin)
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Jacob,
Thanks for looking through the submittal. Gave you a call but missed you. Since the last remaining comment for
Villas is just correcting the elevations on the O&M for bottom and sediment storage elevations, and similarly for
Farms, if we get these back to you today/Monday will this need to go through the whole review cycle or can this just
be checked off and approval given next week?
Ryan Wadsworth, PE
Project Engineer
TIMMONS GROUP I www.timmons.com
5410 Trinity Rd, Suite 102 1 Raleigh, NC 27607
Office:919.866.4516 1 Fax: 919.859.5663
Ryan.Wadsworth(o)timmons.com
Your Vision Achieved Through Ours
To send me files greater than 20MB click here.
From: Beeker,Jacob I <jacob.beeker@deq.nc.gov>
Sent:Thursday, October 10, 2024 4:10 PM
To:Tim Hess<Tim.Hess@timmons.com>; Mike Zaccardo<Mike.Zaccardo@timmons.com>; Brent Wood
<brent.earl.wood@gmail.com>; Ryan Wadsworth <Ryan.Wadsworth@timmons.com>
Cc: svc_post_construction_stormwater<postconstruction@deq.nc.gov>;Valentine,Thad <thad.valentine@deq.nc.gov>
Subject: Re: [External] RE: SW5240202;Wrenn Villas (Franklin)
Good afternoon,
I looked over the additional information you provided on September 10th, 2024.There is an issue still
outstanding.
Please correct the following:
•The revision to the entrance and exit of the forebay meets Wet Pond MDC 5, but the O&M
Agreement is now inconsistent with what is shown in the provided plan sheets. In addition,the
sediment storage is shown to be below the forebay's proposed grading. Please revise the O&M
Agreement to be consistent with the rest of the project package, and revise the provided plans to
indicate the proper sediment storage elevation.
Please provide one hard copy and one electronic copy of any items(two copies of revised plan sheets, if those
are needed) needed to address these comments, unless specified otherwise.
Hard copies should be mailed to me at the following address:
For FedEx/UPS:
Jacob Beeker
512 N.Salisbury Street, Office 625Z
Raleigh, NC 27604
For USPS:
Jacob Beeker
1612 Mail Service Center
Raleigh, NC 27699-1612
For Hand Delivery:
Please reach out to me prior to hand delivering a submission to make sure that I (or someone else in my group)
will be able to receive the submission. Do not leave the package in the foyer with the security guard.
NOTE: Hard copies should not be sent to a Regional Office. Doing so will delay the review process and the
submission package may be lost while being sent from the Regional Office to us in the Central Office.
2
Electronic copies should be uploaded at the following location:
https://edocs.deq.nc.gov/Forms/SW-Supplemental-Upload
Please note that this project was set to be returned with this submission, per Division policy. Due to the
relatively minor nature of this comment,another submission has been granted.Please reach out to me
with any questions regarding the comment provided. If there are issues that remain unresolved in the next
resubmission,your project will be returned.
Let me know if you have any questions.
Jacob Beeker(He/Him)
Environmental Engineer
North Carolina Department of Environmental Quality
(919) 707-9214
Jacob.Beeker(a)deq.nc.gov
oeaa�..a,EpDe Q
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
From:Tim Hess<Tim.Hess@timmons.com>
Sent: Friday, October 4, 2024 9:59 AM
To: Holland, Brianna <brianna.holland@deg.nc.gov>; Mike Zaccardo<Mike.Zaccardo@timmons.com>; Hampton Smith
<hampton@canterburyconstruction.co>; Brent Wood <brent.earl.wood@gmail.com>; Ryan Wadsworth
<Ryan.Wadsworth@timmons.com>; Lawyer, Mike<mike.lawyer@deq.nc.gov>
Cc: svc_post_construction_stormwater<postconstruction@deg.nc.gov>
Subject: RE: [External] RE: SW5240202; Wrenn Villas (Franklin)
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Brianna,We resubmitted them today.—Todays submission matches the 9/10 submission.
Does this all work.
Tim Hess, RLA
Sr. Project Manager
TIMMONS GROUP I http://www.timmons.com
5410 Trinity Rd., Suite 102 1 Raleigh, NC 27607
Office: 984-255-2367 Fax: 919.859.5663
Mobile: 919-349-0174 tim.hessa-timmons.com
Your Vision Achieved Through Ours
To send me files greater than 20MB click here
From: Holland, Brianna <brianna.holland@deq.nc.gov>
Sent: Friday, October 4, 2024 9:56 AM
To:Tim Hess<Tim.Hess@timmons.com>; Mike Zaccardo<Mike.Zaccardo@timmons.com>; Hampton Smith
<hampton@canterburyconstruction.co>; Brent Wood <brent.earl.wood@gmail.com>; Ryan Wadsworth
<Ryan.Wadsworth@timmons.com>; Lawyer, Mike<mike.lawyer@deq.nc.gov>
Cc: svc_post_construction_stormwater<postconstruction@deg.nc.gov>
Subject: RE: [External] RE: SW5240202; Wrenn Villas (Franklin)
Ti m,
Sorry for the confusion, I saw that SW5240201 was last updated 7/26/24(see below), and since the copies were
received to the office on the same day,that the electronic files would have been uploaded at the same time.
Please update the repository for SW5240201,to ensure it matches what was submitted to our office on 9/10/2024.
3
SW5240201_Wetland Detem7ination:Report_20240219 4 SW5240... 2/19/2024
SW5240201_Construction Sequence_20240627 1 SW5240... 6/27/2024
SW5240201_0&M Agreement/PIan_20240627 6 SW5240... 6/27/2024
SW5240201_ResponseTo Comments_20240627 1 SW5240... 6/27/2024
SW5240201_Application Form_20240726 6 SW5240... 7/26/2024
SW5240201_D eed Re=trictionlProtective Covenant Form_20240726 2 SW5240... 7/26/2024
SW5240201_P I a n sh eet- Cover Sheet_20240726 SW5240... 7/26/2024
SW5240201_Plansheet- Existing Conditionse'Surre r_20240726 SW5240... 7/26/2024
SW5240201_P I a n sh eet- Existing DrainageArea_20240726 SW5240... 7/26/2024
SW5240201_Plansheet- Grading/Drainage Plan_20240726 SW5240... 7/26/2024
SW5240201_Plansheet- Landscape/Planting Plan_20240726 SW5240... 7/26/2024
SW5240201_P I a n sh eet- Misc. D eta il_20240726 SW5240... 7/26/2024
SW5240201_P I a n sh eet- Proposed ConditionslSite PI an_20240726 SW5240... 7/26/2024
SW5240201_P I a n sh eet- Proposed DrainageArea_20240726 SW5240... 7/26/2024
SW5240201_P I a n sh eet- SC D eta il_20240726 SW5240... 7/26/2024
SW5240201_Property Deed_20240726 5 SW5240... 7/26/2024
SW5240201_ResponseTo Comments_20240726 1 SW5240... 7/26/2024
SW5240201—Si 9nin9 Official Title&Position Information_20240726 1 SW5240... 7/26/2024
SW5240201_Stormwater Narrative_20240726 1 SW5240... 7/26/2024
SW5240201_Stormwater Rep ort_20240726 1,30 SW5240... 7/26/2024
SW5240201_Supplement-EZ Fom7_20240726 4 SW5240... 7/26/2024
SW5240201_U SG S To p o g ra p h i c Site Map_20240726 1 SW5240... 7/26/2024
Thanks!
Brianna Holland
Environmental Engineer
North Carolina Department of Environmental Quality
Office: (919)707-9218
brianna.holland@deq.nc.9ov(email preferred)
Mailing address: 1612 Mail Service Center, Raleigh, NC 27699-1612
Physical address:512 North Salisbury Street, Raleigh, NC 27604
D E
NORTH CAROLINA -
Department o1 Environmental Quality
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
Please direct all post-construction permitting questions and correspondences to our
new group email address, postconstruction@deq.nc.gov
From:Tim Hess<Tim.Hess@timmons.com>
Sent: Friday, October 4, 2024 9:51 AM
To: Holland, Brianna <brianna.holland@deg.nc.gov>; Mike Zaccardo<Mike.Zaccardo@timmons.com>; Hampton Smith
<hampton@canterburyconstruction.co>; Brent Wood <brent.earl.wood@gmail.com>; Ryan Wadsworth
<Ryan.Wadsworth@timmons.com>; Lawyer, Mike<mike.lawyer@deg.nc.gov>
4
Cc: svc_post_construction_stormwater<postconstruction@deg.nc.gov>
Subject: [External] RE: SW5240202;Wrenn Villas (Franklin)
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Brianna,Trying to figure out the confusion.These files were uploaded By Ryan Wadsworth on 9/10. Mike Lawyer
confirmed their upload on 9/25
1 will send a copy of an email chain with Mike Lawyer.
Ryan has resubmitted the plans today to make sure you have them.
In the future, please remove Colie Crosby from the email chain and include Ryan Ryan.wadsworth@timmons.com
Thank you.
I will follow up with a call within the next hour if you can please take the call.
With Kindest Regards,
Tim Hess, RLA
Sr. Project Manager
TIMMONS GROUP I http://www.timmons.com
5410 Trinity Rd., Suite 102 1 Raleigh, NC 27607
Office: 984-255-2367 Fax: 919.859.5663
Mobile: 919-349-0174 tim.hessa-timmons.com
Your Vision Achieved Through Ours
To send me files greater than 20MB click here
From: Holland, Brianna <brianna.holland@deg.nc.gov>
Sent: Friday, October 4, 2024 8:24 AM
To: Colie Crosby<Colie.Crosbv@timmons.com>;Tim Hess<Tim.Hess@timmons.com>; Mike Zaccardo
<Mike.Zaccardo@timmons.com>; Hampton Smith <hampton@canterburyconstruction.co>; Brent Wood
<brent.earl.wood@gmail.com>
Cc: svc_post_construction_stormwater<postconstruction@deg.nc.gov>
Subject: RE: SW5240202; Wrenn Villas (Franklin)
Please follow the instructions provided below to upload electronic copies of the submission for Wrenn Farms
(SW5240201) and Wrenn Villas.
Thanks,
Brianna Holland
Environmental Engineer
North Carolina Department of Environmental Quality
Office: (919)707-9218
brianna.holland@deq.nc.gov(email preferred)
Mailing address: 1612 Mail Service Center, Raleigh, NC 27699-1612
Physical address:512 North Salisbury Street, Raleigh, NC 27604
D_ E
�
NORTH CAROLINA7AM Q
kipi
Department of Environmental Quality
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
Please direct all post-construction permitting questions and correspondences to our
new group email address, postconstruction@deq.nc.gov
From: Holland, Brianna
Sent:Wednesday, August 28, 2024 4:57 PM
To: Colie Crosby<Colie.Crosbv@timmons.com>;Tim Hess<Tim.Hess@timmons.com>; Mike Zaccardo
5
<Mike.Zaccardo@timmons.com>; Hampton Smith <hampton@canterbu ryconstruction.co>; Brent Wood
<brent.earl.wood@gmail.com>
Cc: svc_post_construction_stormwater<postconstruction@deg.nc.gov>;Valentine,Thad<thad.valentine@deg.nc.gov>
Subject: RE: SW5240202; Wrenn Villas (Franklin)
Good afternoon,
The Division of Energy, Mineral and Land Resources (DEMLR), received additional information for a Stormwater
Management Permit Application for SW5240202 on July 29, 2024. A review of that information has determined that the
application is not complete. Attached is a letter describing the items that need to be submitted.
Please only provide the items that have changed when resubmitting hard and electronic copies.
Note: Per Division policy, the next review will be the final review. Failure to address comments will result in the return of
the project.
Electronic copies should be uploaded at the following location:
https://edocs.deg.nc.gov/Forms/SW-Supplemental-Upload
To view the electronic repository, please see the following link:
https://edocs.deg.nc.gov/WaterResources/Browse.aspx?id=494276&dbid=0&repo=WaterResources
Thank you,
Brianna Holland
Environmental Engineer
North Carolina Department of Environmental Quality
Office: (919) 707-9218
brianna.holland@deg.nc.gov(email preferred)
Mailing address: 1612 Mail Service Center, Raleigh, NC 27699-1612
Physical address: 512 North Salisbury Street, Raleigh, NC 27604
D_ E
kj /�
NORTH CAROLINA 7AM Q
Department of Environmental Duality
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
Please direct all post-construction permitting questions and correspondences to our new
group email address, postconstruction@deq.nc.gov
From: Holland, Brianna
Sent: Sunday, May 19, 2024 8:27 PM
To: Peck, Kaitlin <kaitlin.peck@deg.nc.gov>; Colie Crosby<Colie.Crosby@timmons.com>;Tim Hess
<Tim.Hess@timmons.com>; Mike Zaccardo<Mike.Zaccardo@timmons.com>; Hampton Smith
<hampton@canterburyconstruction.co>; Brent Wood <brent.earl.wood@gmail.com>
Cc: svc_post_construction_stormwater<postconstruction@deg.nc.gov>; Farkas,Jim J <Jim.Farkas@deg.nc.gov>;
Valentine,Thad <thad.valentine@deg.nc.gov>
Subject: RE: SW5240202; Wrenn Villas (Franklin)
Good evening,
The Division of Energy, Mineral and Land Resources (DEMLR), received additional information for a Stormwater
Management Permit Application for SW5240202 on February 19, 2024. A review of that information has determined
that the application is not complete. Attached is a letter describing the items that need to be submitted.
Electronic copies should be uploaded at the following location:
https://edocs.deg.nc.gov/Forms/SW-Supplemental-Upload
To view the electronic repository, please see the following link:
https://edocs.deg.nc.gov/WaterResources/Browse.aspx?id=494276&dbid=0&repo=WaterResources
Thank you,
6
Brianna Holland
Environmental Engineer
North Carolina Department of Environmental Quality
Office: (919) 707-9218
brianna.holland@deq.nc.gov(email preferred)
Mailing address: 1612 Mail Service Center, Raleigh, NC 27699-1612
Physical address: 512 North Salisbury Street, Raleigh, NC 27604
D_ E
kj /�
NORTH CAROLINA 7AM Q
Department of Environmental Duality
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
Please direct all post-construction permitting questions and correspondences to our new
group email address, postconstruction@deq.nc.gov
From: Peck, Kaitlin <kaitlin.peck@deg.nc.gov>
Sent: Monday, February 19, 2024 12:02 PM
To: Colie Crosby<Colie.Crosby@timmons.com>;Tim Hess<Tim.Hess@timmons.com>; Mike Zaccardo
<Mike.Zaccardo@timmons.com>; Hampton Smith <hampton@canterburyconstruction.co>; Brent Wood
<brent.earl.wood@gmail.com>
Cc: svc_post_construction_stormwater<postconstruction@deq.nc.gov>; Farkas,Jim J <Jim.Farkas@deq.nc.gov>;
Valentine,Thad <thad.valentine@deg.nc.gov>; Holland, Brianna <brianna.holland@deq.nc.gov>
Subject: SW5240202; Wrenn Villas (Franklin)
Good Morning,
We received your post-construction stormwater permit application for the subject project on 2/19/24. Reviews under
the Standard permitting process can take up to 90 calendar days to complete. You can see where this project stands in
the review queue by emailing postconstruction@deg.nc.gov(We have an autoreply set up that has the review queue on
it). Please upload all documents that you mailed into our office through the link provided below. Be sure to choose the
Central Office as the Primary Contact office.
https://edocs.deg.nc.gov/Forms/SW-Supplemental-Upload
IMPORTANT NOTE: Please ensure that each file is uploaded under its appropriate file type. Additional file types can be
entered into the electronic form by clicking on the "Add Another Post-Construction File Upload" link directly below the
"State Stormwater Information Uploads" section of the form. YOU MUST CLICK ON THE"ADD ANOTHER POST-
CONSTRUCTION FILE UPLOAD"TO ADD ADDITIONAL FILE TYPES TO THE SUBMISSION. Merely changing the file type
dropdown as you upload the various files (without adding additional file uploads)will upload all of the files as the last
file type selected, the submission will get flagged during review, and you will need to resubmit the files. Please do not
upload entire plan sets through this form, but rather upload the relevant individual sheets under the appropriate file
type. Selecting the correct file type ensures that the files are properly named in the electronic repository and it helps
expedite the review process. NOTE:We do not require and we discourage the upload/submission of extraneous plan
sheets (such as lighting plans, utility plans, striping plans, sight distance plans, etc...) as these files are not needed for
review.
Please type in permit#: SW5240202
This project will be reviewed by Brianna Holland, if you have any questions, please contact them at
postconstruction@deg.nc.gov or at 919-707-9218.
Thank you,
Kaitlin Peck
Environmental Specialist
Post-Construction Stormwater Permitting Group
North Carolina Department of Environmental Quality
postconstruction@deq.nc.gov
NORTH CAROLINA
Department of Environmental Quality
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
From: Peck, Kaitlin
Sent: Monday, February 19, 2024 11:02 AM
To: Colie Crosby<Colie.Crosby@timmons.com>;Tim Hess<Tim.Hess@timmons.com>; Mike Zaccardo
<Mike.Zaccardo@timmons.com>; Hampton Smith <hampton@canterbu ryconstruction.co>; Brent Wood
<brent.earl.wood@gmail.com>
Cc: svc_post_construction_stormwater<postconstruction@deg.nc.gov>; Farkas,Jim J <Jim.Farkas@deq.nc.gov>;
Valentine,Thad <thad.valentine@deq.nc.gov>
Subject: RE: [External] RE:Wrenn Villas;Youngsville, Franklin County
Colie,
In the application, you have 432,233 sf listed, not 472,773 sf. Please revise.
Take care,
Kaitlin Peck
Environmental Specialist
North Carolina Department of Environmental Quality
Office: (919) 707-9209
Kaitlin.Peck@deg.nc.gov
,7���D7 E
NORTH CAROLINA
Department of Environmental Quality
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
From: Colie Crosby<Colie.Crosby@timmons.com>
Sent: Monday, February 19, 2024 10:58 AM
To: Peck, Kaitlin <kaitlin.peck@deq.nc.gov>;Tim Hess<Tim.Hess@timmons.com>; Mike Zaccardo
<Mike.Zaccardo@timmons.com>; Hampton Smith <hampton@canterbu ryconstruction.co>; Brent Wood
<brent.earl.wood@gmail.com>
Cc: svc_post_construction_stormwater<postconstruction@deg.nc.gov>; Farkas,Jim J <Jim.Farkas@deq.nc.gov>;
Valentine,Thad <thad.valentine@deq.nc.gov>
Subject: RE: [External] RE:Wrenn Villas;Youngsville, Franklin County
Importance: High
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Katilin,
Similar to the Wrenn Farms permit, please see the attached application and response to comment letter for the Villas
permit.
8
Per the SNAP tool nitrogen calculations, provided in the stormwater impact report, there should be 10.85 ac (472,773 sf)
of proposed impervious for the subdivision site (33.67 acres); 10.85 ac/33.67 ac=32.23%
Please let me know if there is anything else you need.
Thanks,
Collie Crosby, El
Senior Project Engineer
TIMMONS GROUP I http://www.timmons.com
Office: 919.866.4936 1 Fax: 919.859.5663
colie.crosby(o)timmons.com
To send me files greater than 20MB Click Here
From: Peck, Kaitlin <kaitlin.peck@deg.nc.gov>
Sent: Monday, February 12, 2024 12:59 PM
To: Colie Crosby<Colie.Crosbv@timmons.com>;Tim Hess<Tim.Hess@timmons.com>; Mike Zaccardo
<Mike.Zaccardo@timmons.com>; Hampton Smith <hampton@canterburyconstruction.co>; Brent Wood
<brent.earl.wood@gmail.com>
Cc: svc_post_construction_stormwater<postconstruction@deg.nc.gov>; Farkas,Jim J <Jim.Farkas@deg.nc.gov>;
Valentine,Thad <thad.valentine@deg.nc.gov>
Subject: RE: [External] RE:Wrenn Villas;Youngsville, Franklin County
Good Afternoon,
We received your application for a new post-construction stormwater permit on 2/9/24. At this time, the submission is
not administratively complete and cannot be accepted for review in its current condition. Please provide the following
submittal items by close of business on 2/21/24, so that we may accept the project and begin the review process,
otherwise, the project will be returned as administratively incomplete.
• 2x hard copies of the Application with the following corrections made (These items are required per 15A NCAC
02H .1042(2)(a) and per Section VI, 1 of the Application):
• Section IV, 8—The percent impervious area for the project area does not appear to be calculated
correctly. Project density calculation information can be found in 15A NCAC 02H .1003(1).There is a
discrepancy between what is listed on your application and what is listed on your response to
comments for your value of proposed impervious area which is affecting this calculation. Please
review this.
• This can be emailed in so I can add it to your existing application.
NOTE:This is an administrative completeness review, not a detailed engineering review, there may be other issues that
may be brough up during the engineering review.
If these items are received within the stipulated timeframe, we can accept the project and begin the review process.
Once accepted, reviews under the standard permitting process can take up to 90 calendar days per statute (one of our
two reviewer positions is currently vacant).
Hard copies should be mailed to the following address:
For USPS:
Jim Farkas
1612 Mail Service Center
Raleigh, NC 27699-1612
For Fed Ex/UPS:
Jim Farkas
512 N. Salisbury Street, Office 640E
9
Raleigh, NC 27604
If you have any questions, please contact Kaitlin Peck at post-construction@nc.deq.gov or at(919) 707-9209.
Thank you,
Kaitlin Peck
Environmental Specialist
Post-Construction Stormwater Permitting Group
North Carolina Department of Environmental Quality
postconstruction@deq.nc.gov
NORTH CAROL NA
Department of Environmental Quality
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
From: Colie Crosby<Colie.Crosbv@timmons.com>
Sent:Thursday, February 8, 2024 9:21 AM
To: Peck, Kaitlin <kaitlin.peck@deq.nc.gov>
Cc:Tim Hess<Tim.Hess@timmons.com>; svc_post_construction_stormwater<postconstruction@deg.nc.gov>; Farkas,
Jim J <Jim.Farkas@deq.nc.gov>; Hampton Smith <hampton@canterburyconstruction.co>;Valentine,Thad
<thad.valentine@deq.nc.gov>; Brent Wood <brent.earl.wood@gmail.com>; Mike Zaccardo
<Mike.Zaccardo@timmons.com>
Subject: [External] RE:Wrenn Villas;Youngsville, Franklin County
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Kaitlin,
Regarding Wrenn Villas, we have sent hard copies, of the revised documents noted in your comments, to your office
today 08 Feb. Below and attached electronic copies of those documents, for your reference.
Click the following link to download your file(s).
Click to Retrieve File(s)
02 Wrenn Villas SIA 3rd.pdf
03_SuppEZ- Wrenn Villas.pdf
04 Wrenn Villas Deed Restriction Convenanc_Signed.pdf
11_Stream Buffer Delineation.pdf
20240206 Wrenn Villas Signed.pdf
If the above link is not clickable, copy and paste the following URL into your browser.
https.-Ilwww.sendthisfile.com/DrwYu/EHlkSSvOPfFNdPXW4W
Note: These files will expire in 14 days from the time this email was generated.
Collie Crosby, Ell
Senior Project Engineer
TIMMONS GROUP I http://www.timmons.com
Office: 919.866.4936 1 Fax: 919.859.5663
colie.crosby(catimmons.com
10
To send me files greater than 20MB Click Here
From: Mike Zaccardo<mike.zaccardo@timmons.com>
Sent: Monday,January 22, 2024 3:39 PM
To: Colie Crosby<Colie.Crosbv@timmons.com>; Dexter Howell <Dexter.HowelI@timmons.com>; Gibson Blakeslee
<Gibson.Blakeslee@timmons.com>
Cc:Tim Hess<Tim.Hess@timmons.com>
Subject: FW:Wrenn Villas;Youngsville, Franklin County
Another comment to answer
Mike Zaccardo, PE
Senior Project Manager
TIMMONS GROUP I www.timmons.com
5410 Trinity Rd., Suite 102 1 Raleigh, NC 27607
Office: 919.532.3281 1 Fax: 919.859.5663 1 Cell: 919.624.4927
mike.zaccardoa-timmons.com
Your Vision Achieved Through Ours
To send me files greater than 20MB click here.
From: Peck, Kaitlin <kaitlin.peck@deq.nc.gov>
Sent: Monday,January 22, 2024 3:09 PM
To: brent.earl.wood@gmail.com; Mike Zaccardo<mike.zaccardo@timmons.com>
Cc: Farkas,Jim J <Jim.Farkas@deq.nc.gov>; svc_post_construction_stormwater<postconstruction@deg.nc.gov>;
Valentine,Thad <thad.valentine@deq.nc.gov>
Subject: RE:Wrenn Villas;Youngsville, Franklin County
CAUTION:This email originated from outside of the organization. Do not click links or open attachments unless you recognize the
sender and know the content is safe.
My apologies, a comment was left off the request for additional information sent earlier this afternoon.The revised add
info is below with the revision made in RED.Thank you.
We received your application for a new post-construction stormwater permit on 1/22/24. At this time, the submission is
not administratively complete and cannot be accepted for review in its current condition. Please provide the following
submittal items within 30 calendar days (by close of business on 2/21/24) so that we may accept the project and begin
the review process, otherwise, the project will be returned as administratively incomplete.
• 2x hard copies of the Application with the following corrections made (These items are required per 15A NCAC
02H .1042(2)(a) and per Section VI, 1 of the Application):
• Section IV, 2—You indicated that you intended to claim vested rights, please provide supporting
documents and an explanation why this is applicable to this project submission, or this remove this
indication.
• Section IV, 8—The percent impervious area for the project area does not appear to be calculated
correctly. Project density calculation information can be found in 15A NCAC 02H .1003(1).
• Section IV, 10—The "% Impervious Area" (total)" calculated is incorrect based off of the values
provided for"Total Drainage Area (sf)" and "Proposed Impervious Area" (sf)". Please revise.
• Section IV, 10—The table for"Impervious" Surface Area"was left blank. Please revise.
• 2x hard copies (one original) of the deed restriction document(This item is required per 15A NCAC 02H .1003(7),
15A NCAC 02H .1042(2)(k), and Sections VI, 2 &VII). More information can be found on our website:
https://deg.nc.gov/about/divisions/energy-mineral-and-land-resources/stormwater/stormwater-program/post-
construction-program/post-construction-forms
• 2x signed &sealed hard copies of a plan sheet showing the following corrected additions:
• Wetland delineation or a note on the plans stating that there are no wetlands located on-site.This item
is required per 15A NCAC 02H .1042(2)(g)(iii) &Section VI, 8m of the Application. Please also list the
11
name of the individual that made this determination in a note on the plans. Wetlands was listed as an
item in the legend, but not shown clearly on the plan sheet. Please label them more clearly on the site
plans.
NOTE:This is an administrative completeness review, not a detailed engineering review, there may be other issues that
may be brough up during the engineering review.
If these items are received within the stipulated timeframe, we can accept the project and begin the review process.
Once accepted, reviews under the standard permitting process can take up to 90 calendar days per statute (one of our
two reviewer positions is currently vacant).
Hard copies should be mailed to the following address:
For USPS:
Jim Farkas
1612 Mail Service Center
Raleigh, NC 27699-1612
For Fed Ex/UPS:
Jim Farkas
512 N. Salisbury Street, Office 640E
Raleigh, NC 27604
If you have any questions, please contact Kaitlin Peck at post-construction@nc.deg.gov or at(919) 707-9209.
Thank you,
Kaitlin Peck
Environmental Specialist
Post-Construction Stormwater Permitting Group
North Carolina Department of Environmental Quality
postconstruction@deg.nc.gov
NORTH CAROLINA
Department of Environmental Quality
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
From: Peck, Kaitlin
Sent: Monday,January 22, 2024 1:44 PM
To: brent.earl.wood@gmail.com; mike.zaccardo@timmons.com
Cc: Farkas,Jim J <Jim.Farkas@deg.nc.gov>; svc_post_construction_stormwater<postconstruction@deg.nc.gov>;
Valentine,Thad <thad.valentine@deg.nc.gov>
Subject:Wrenn Villas;Youngsville, Franklin County
Good Afternoon,
We received your application for a new post-construction stormwater permit on 1/22/24. At this time, the submission is
not administratively complete and cannot be accepted for review in its current condition. Please provide the following
12
submittal items within 30 calendar days (by close of business on 2/21/24) so that we may accept the project and begin
the review process, otherwise, the project will be returned as administratively incomplete.
• 2x hard copies of the Application with the following corrections made (These items are required per 15A NCAC
02H .1042(2)(a) and per Section VI, 1 of the Application):
• Section IV, 2—You indicated that you intended to claim vested rights, please provide supporting
documents and an explanation why this is applicable to this project submission.
• Section IV, 8—The percent impervious area for the project area does not appear to be calculated
correctly. Project density calculation information can be found in 15A NCAC 02H .1003(1).
• Section IV, 10—The "% Impervious Area** (total)" calculated is incorrect based off of the values
provided for"Total Drainage Area (sf)" and "Proposed Impervious Area** (sf)". Please revise.
• Section IV, 10—The table for"Impervious** Surface Area"was left blank. Please revise.
• 2x hard copies (one original) of the deed restriction document(This item is required per 15A NCAC 02H .1003(7),
15A NCAC 02H .1042(2)(k), and Sections VI, 2 &VII). More information can be found on our website:
https://deg.nc.gov/about/divisions/energy-mineral-and-land-resources/stormwater/stormwater-program/post-
construction-program/post-construction-forms
• 2x signed &sealed hard copies of a plan sheet showing the following corrected additions:
• Wetland delineation or a note on the plans stating that there are no wetlands located on-site.This item
is required per 15A NCAC 02H .1042(2)(g)(iii) &Section VI, 8m of the Application. Please also list the
name of the individual that made this determination in a note on the plans. Wetlands was listed as an
item in the legend, but not shown clearly on the plan sheet. Please label them more clearly on the site
plans.
NOTE:This is an administrative completeness review, not a detailed engineering review, there may be other issues that
may be brough up during the engineering review.
If these items are received within the stipulated timeframe, we can accept the project and begin the review process.
Once accepted, reviews under the standard permitting process can take up to 90 calendar days per statute (one of our
two reviewer positions is currently vacant).
Hard copies should be mailed to the following address:
For USPS:
Jim Farkas
1612 Mail Service Center
Raleigh, NC 27699-1612
For Fed Ex/UPS:
Jim Farkas
512 N. Salisbury Street, Office 640E
Raleigh, NC 27604
If you have any questions, please contact Kaitlin Peck at post-construction@nc.deg.gov or at(919) 707-9209.
Thank you,
Kaitlin Peck
Environmental Specialist
13
Post-Construction Stormwater Permitting Group
North Carolina Department of Environmental Quality
postconstruction@deg.nc.gov
z:���D_ E
NORTH CAROLINA :.� Q
Department of Environmental Quality
Email correspondence to and from this address is subject to the North
Carolina Public Records Law and may be disclosed to third parties.
Email correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to third parties by an authorized
state official.