HomeMy WebLinkAboutModification Approval Letter_RES Neu-Con_Hannah Bridge SAW-2015-01799DEPARTMENT OF THE ARMY
WILMINGTON DISTRICT, CORPS OF ENGINEERS
69 DARLINGTON AVENUE
WILMINGTON, NORTH CAROLINA 28403-1343
September 16, 2024
Regulatory Division
SUBJECT: Modification Approval of the RES Neu-con- Hannah Bridge Mitigation Site,
Action ID SAW-2015-01799
Ms. Jamey McEachran
EBX-Neuse I, LLC
302 Jefferson Street, Suite 110
Raleigh, North Carolina 27605
Dear Ms. McEachran:
Please reference the correspondence received by the United States Army Corps of
Engineers (USACE) on May 16, 2024, regarding the proposal to modify the RES Neu-
Con, Hannah Bridge (SAW-2015-01799) Final Mitigation Plan, the correspondence
received by the USACE on September 11, 2024, providing clarification on credit totals.
Based on the information submitted with this request, the Wetland Credit Total will
change from 10.743 credits to 6.670 credits due to several wetland gauges not meeting
success criteria across the site. The submittal package requested removal of 4.073
Wetland Mitigation Credits (6.95 acres of riparian wetland) from the Hannah Bridge
Mitigation Project Credit totals as reflected in the attached Credit Release Schedule for
the Site. The wetland credit loss is associated with Wetland 1 (1.192 acres of
restoration, 1.192 Wetland Credits) and Wetland 14 (5.761 acres of enhancement,
2.881 Wetland Credits).
As bank sponsor you are required to comply with the approved RES Neu-Con UMB
Instrument and Hannah Bridge Site Final Mitigation Plan and this Modification, and the
Corps’ regulations regarding compensatory mitigation (33 CFR 332). Please note that
no credit release is approved with this correspondence. When credits are debited from
the mitigation site, the bank sponsor must provide the Corps with an updated ledger
form identifying the purchaser of the credits, the project name, the permit number, and
the number and type of credits to be debited. When all stream and/or wetland credits
have been consumed, no more credits may be sold from this mitigation site.
-2-
Please note that this electronic copy provided to you via email is your official
copy. Should you wish to receive a paper copy of this correspondence, please contact
us. Thank you for your time and cooperation. If you have any questions, please contact
me by email at Casey.M.Haywood@usace.army.mil or by phone at (919) 799-0536.
Sincerely,
Casey Haywood
Project Manager
Wilmington District, Mitigation Branch
Enclosure
cc (by email):
NCIRT Distribution List
Project Name:
Sponsor Name:
USACE Action ID:
NCDWQ Action ID:
Warm
Water
Cool
Water
Cold
Water
Riparian
Riverine
Riparian
Non-Riverine Non-Riparian
4,643.00 10.743
4,643.00 10.743
4,643.00 6.670
Scheduled
Releases
Warm
Water
Cool
Water
Cold
Water
Scheduled
Releases
Riparian
Riverine
Adjusted Schedule
with updated Credit
Totals
Non-Riparian Scheduled
Releases Coastal
1 (Bank/Site Establishment)1, 2 15%846.90 15%2.23 1.621 15%10/11/2018
2 (Year 0/As-Built)3 15%670.00 15%1.50 0.891 15%8/12/2019
3 (Year 1 Monitoring)10%446.600 10%1.00 0.594 10%12/19/2019
4 (Year 2 Monitoring)10%446.600 10%1.00 0.594 15%11/20/2020
5 (Year 3 Monitoring)10%446.600 15%1.50 0.891 20%11/31/2021 11/16/2021
6 (Year 4 Monitoring)5%223.300 5%0.50 0.297 10%12/31/2022 2/3/2023
7 (Year 5 Monitoring)10%446.600 15%1.50 0.891 15%12/31/2023 12/22/2023
8 (Year 6 Monitoring)5%446.600 5%0.50 0.346 NA NA 12/31/2024
9 (Year 7 Monitoring)10%223.300 10%1.00 0.594 NA NA 12/31/2025
Stream Bankfull Standard4 10%446.500 NA NA NA NA NA NA Dec-22
Total Credits Release to Date 2856.70 4643 5.73 6.670
Date
Johnston
3020201
6/27/2018
5/16/2024
County:
8-Digit HUC:
Year Project Instituted:
Date Prepared:
Actual Release
Date
Potential Credits from As-Built Survey
Stream Credits
Credit Classification
Non-Forested Wetland
CreditsForested Wetland CreditsStream Credits
Current and Future Credit Releases
Credit Release Milestone
Potential Credits from Mitigation Plan
Modification (Wetland reduction)
Non-Forested Wetland
Credits
Coastal
Wilmington District Mitigation Bank Credit Release Schedule
4 - A 15% reserve of credits to be held back until the bankfull event performance standard has been met.
1 - The first credit release milestone is based on the potential credits stated in the approved mitigation plan.
2 - The first credit release shall occur upon establishment of the mitigation bank, which includes the following criteria:
1) Execution of the MBI or UMBI by the Sponsor and the USACE;
2) Approval of the final Mitigation Plan;
3) Mitigation bank site must be secured;
4) Delivery of the financial assurances described in the Mitigation Plan;
5) Recordation of the long-term protection mechanism and title opinion acceptable to the USACE;
6) 404 permit verification for construction of the site, if required.
3 - The second credit release is based on the credit totals from the as-built survey, and may differ slightly from the credit totals stated in the mitigation plan.
Contingencies (if any): Wetland Credits are on hold until further information is provided
Signature of Wilmington District Official Approving Credit Release
Hannah Bridge
EBX-Nesue I
SAW-2015-01799
2017-0537v1
Potential Credits from Mitigation Plan
Forested Wetland Credits
Total Potential Credits
Projected
Release Date