Loading...
HomeMy WebLinkAbout820217_30 day poa_20240809PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES Facility Number: 82-217 County: Sampson Facility Name: Brewer Hog Farm (1-8) Certified operator Name: 17804 Operator Number: Ronnie Brewer 1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the lowest point on the top of the dam for lagoons without spillways; and from the current liquid level in the lagoon to the bottom of the spillway for lagoons with spillways. Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5 Lagoon Name/ID: #1 #2 Spillway(Y or N): N N Level(inches): 28 16 2. Check all applicable items Liquid level is within the designed structural freeboard elevations of one or more structures. Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are within acceptable ranges. X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A 30 day Plan of Action is attached. Agronomic balance is within acceptable range. Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste to be pumped and hauled is reflected in section III tables. Included within this plan is a list of the proposed sites with related facility numbers, number of acres and receiving crop information. Contact and secure approval from the DWQ prior to transfer of waste to a site not covered in the facility's CAWMP. Operation will be partially or fully depopulated. *Attach a complete schedule with corresponding animal units and dates fro depopulation *if animals are to be moved to another permitted facility, provide facility number, lagoon freeboard levels and herd population for the receiving facility 3. Earliest possible date to begin land application of waste: 8/12/24 Weather Permiting. I hereby certify that I have reviewed the information listed above and included within the attached Plan of Action, and to the best of my knowledge and ability, the information is accurate and correct. Ronnie Brewer Phone: 910-590-6229 Facility Owner/Manager (print) ! -w� 43A � Date: 8/9/2024 Facility Owner/Manager (signature) PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/Identifier (ID): I Brewer Hog Farm (1-8) #1 2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard a. current liquid level according to marker b. designed 25 yr./24 hr. storm & structural freeboard c. line b - line a (inches in red zone) _ top of dike surface area according to design d. (area at below structural freeboard elevation) e. line c/12 x line d x 7.48 gallons/ft3 3. Projected volume of waste liquid produced during draw down period f. temporary storage period according to structural design 28.0 inches 19.0 inches -9 inches 75250 ft2 -422153 gallons 180 days g. volume of waste produced according to structural design 96925 ft3 h. current herd # F-2-9-4-01 certified herd # 2940 actual waste produced = current herd # x line g = certified herd # i. volume of wash water according to structural design j. excess rainfall over evaporation according to design k. (lines h + i + j) x 7.48 x 30 days/line f= 4. Total PAN to be land applied during draw down period I. current waste analysis dated 6/4/2024 m. ((lines e + k)/1000) x line I = REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) 96925 ft' Oft3 43895 ft3 175556 gallons 2.13 Ibs/1000 gal. -525 Ibs. PAN PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/Identifier (ID): I Brewer Hog Farm (1-8) 1 #2 2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard a. current liquid level according to marker b. designed 25 yr./24 hr. storm & structural freeboard c. line b - line a (inches in red zone) _ d. top of dike surface area according to design (area at below structural freeboard elevation) e. line c/12 x line d x 7.48 gallons/ft' 3. Projected volume of waste liquid produced during draw down period f. temporary storage period according to structural design 16.0 inches 19.0 inches 3.0 inches 74175 ft2 138707 gallons 180 days g. volume of waste produced according to structural design 96925 ft' h. current herd # 2940 certified herd # 2940 actual waste produced = current herd # x line g = certified herd # i. volume of wash water according to structural design j. excess rainfall over evaporation according to design k. (lines h + i + j) x 7.48 x 30 days/line f= 4. Total PAN to be land applied during draw down period I. current waste analysis dated 6/4/2024 m. ((lines e + k)/1000) x line I = REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) 96925 ft' ft3 43268 ft3 174774 gallons 2.13 Ibs/1000 gal. 667.7 Ibs. PAN PoA (30 Day) 2/21100 II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARDAND/OR 25 YR./24 HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY 1. Structure ID: #1 line m = -525 lb PAN 2. Structure ID: #2 line m = 667.7 lb PAN 3. Structure ID: line m = lb PAN 4. Structure ID: line m = lb PAN 5. Structure ID: line m = lb PAN 6. Structure ID: line m = lb PAN n. lines 1+2+3+4+5+6= 142.5 lb PAN III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN PFRIon nO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD. M.-lll Total PAN available Tor all nelas (sum oT column T) = IV. FACILITY'S PoA OVERALL PAN BALANCE w. Total PAN to be land applied (line n from section II) _ x. Crop's remaining PAN balance (line v from section III) _ y. Overall PAN balance (w - x) _ i i uo. i ID. r'Am 142.5 lb. PAN 1706.1 lb. PAN 1563.64 lb. PAN NARRATIVE: Self reported to DWR on 8/8/24.