Loading...
HomeMy WebLinkAboutSW1240603_Stormwater Narrative_20240830 Section 1 PROJECT OVERVIEW 1.1 Narrative The Greater Asheville Regional Airport Authority ATCT and TRACON project includes the construction of a perimeter road, a new parking lot, a TRACON building, and associated grading, drainage, landscaping, and erosion control. This report includes the computations that show compliance with the NCDEQ High-Density Project.A Primary SCM (Bioretention cell) will be used to treat the stormwater runoff from the proposed site. 1.2 Introduction and Site Description The site is located at Greater Asheville Regional Airport in Fletcher, NC, south of Asheville, North Carolina near Airport Road(35°26' 17.43" N,82°32' 13.40"W). The area that includes airport-related operations encompasses approximately 580 acres. For a larger vicinity map,see Appendix A. The Greater Asheville Regional Airport Authority ATCT and TRACON Asheville project site is located on an undeveloped area in Regional the western portion of the airport, located at the Airport end of Westfeldt Drive. f For hydrologic planning purposes, the site is comprised of Hydrologic Soil Group (HSG) B soils. Appendix A contains the NRCS Soil Survey Maps for the parking lot.The existing land use of the project is grass,gravel,forest,and impervious.The proposed land use is impervious(perimeter road,TRACON building, and parking lot) with some grassed area for landscaping and bioretention. As shown in FEMA FIRM 3700964300K(January 6, 2010) in Appendix A,the disturbance is not located within 200ft of a FEMA floodplain. 1.3 Construction Sequence and Cost As explained later in the report, a bioretention cell is proposed as a primary stormwater conveyance measure (SCM). The rough outline of the permanent bioretention area will occur during the grading phase of the project and a portion of it will be used as a temporary sediment trap to protect downstream receiving stormwater systems from construction activity.After the site is stabilized, the sediment trap will be cleaned out and re-graded to final bioretention design grades. No mechanical stabilization will occur. The cost of the bioretention cell is unknown at this time and will be finalized during bidding. The Asheville Regional Airport will be the end-user and responsible for annual inspection, maintenance, and repairs of the system. Section 2.3 discusses the operation and maintenance of the cell. 3 ASHEVILLE REGIONAL AIRPORT-ATCT AND TRACON PROJECT INITIAL SUBMITTAL:MAY 2024 STORMWATER MANAGEMENT REPORT Section 2 HYDROLOGY 2.1 Project Methodology In order to qualify for a primary Stormwater Conveyance Measure (SCM) for Bioretention, several minimum design criteria (MDC) must be met.The recommendations will also be met to the maximum extent practical. MDC 1 Separation from the SHWT Boring logs for the project area observed SHWT 7ft to 10ft below the existing grade surface. The lowest point of the bioretention cell will be a minimum of two feet above the SHWT. MDC 2 Maximum Ponding Depth for Design Volume The maximum ponding depth for the bioretention cell is 12 inches. MDC 3 Peak Attenuation Volume The maximum depth of the entire cell is 18 inches for peak attenuation. See plans with outlet control structure weirs at 12-inch and 18-inch depths. MDC 4 Underdrain An underdrain with internal water storage is designed. See the plan view on SW-01 and details on SW-02 and SW-03 showing the underdrain location and details. MDC 5 Media Depth The media depth is 36 inches, see detail on SW-02 showing media depth. MDC 6 Media Mix The media shall be a homogeneous soil mix engineered media blend with approximate volumes of: (a) 75 to 85 percent medium to coarse washed sand (ASTM C33,AASHTO M 6/M 80, ASTM C330,AASHTO M195, or the equivalent) (b) 8 to 15 percent fines (silt and clay); and (c) 5 to 10 percent organic matter (such as pine bark fines). See detail on SW-02 showing media mix. MDC 7 Media P-Index The phosphorus index(P-index) for the media shall not exceed 30 in NSW waters as defined in 15A NCAC 02B .0202 and shall not exceed 50 elsewhere. MDC 8 No Mechanical Compaction The media shall not be mechanically compacted. It is recommended to either water it or walk on it as it is placed.This note is on the detail, sheet SW-02. 4 ASHEVILLE REGIONAL AIRPORT-ATCT AND TRACON PROJECT INITIAL SUBMITTAL:MAY 2024 STORMWATER MANAGEMENT REPORT MDC 9 Maintenance of Media The bioretention cell shall be maintained in a manner that results in a drawdown of at least one inch per hour at the planting surface. This is accomplished by not installing until the end of the project phase, installing the correct soil type as outlined above,and not mechanically compacting. MDC 10 Planting Plan A planting plan can be found in Appendix C2 by Landart. MDC 11 Mulch Water will enter the bioretention at less than 3 fps (see Recommendation 1 narrative below). Therefore, sod is proposed in the bioretention area. MDC 12 Clean-Out Pipes A minimum of one clean-out pipe shall be provided on each underdrain line.Clean-out pipes shall be capped. As seen on the plan and details, sheets SW-01 through SW-03, a cleanout is provided in the bioretention cell. Recommendation 1 Dispersed Flow or Energy Dissipation The parking lot, building, and associated impervious runoff will enter the bioretention via pipe flow into two proposed forebays.The forebays are flat settling areas with spillways to spread the flow evenly into the bioretention portion, at an outlet velocity of less than 3 fps. Recommendation 2 Pretreatment The parking lot, building, and associated impervious runoff will enter the bioretention via pipe flow into a proposed forebay. The forebay will be 18 inches deep. The Rational Method was used for the parking lot design on the development.The Intensity Duration Frequency(IDF) curve for Fletcher, NC below was used for the calculations: mac• 21_00 21.00 1st Yr 1s-00 15_00 \ - - _ 15.00 25 Yt 1200 12 00 1 Lri 9.00 9.00 yri 6m 6_00 n 3m 3.00 OAO I I I 10 00 0 5 10 15 20 25 30 35 40 45 50 55 60 Tie(moo) 5 ASHEVILLE REGIONAL AIRPORT-ATCT AND TRACON PROJECT INITIAL SUBMITTAL:MAY 2024 STORMWATER MANAGEMENT REPORT The following runoff coefficients were also used for hydraulic (storm inlet, pipe) analysis of this project: c=0.30 (Grass, HSG B) c=0.95 (Impervious area) The bioretention was designed to treat a total of 6.13 acres. See below for volume calculations, the proposed bioretention cell will provide adequate volume per the tables below: Design Volume-Required Drainage Impervious Rv RD(Design Design Volume Area Area IA(Impervious Fraction) (0.05*0.9 Storm Depth) (3630*RD*Rv*A) (ac) (ac) *IA) (in) (cf) Bioretention 1 6.13 1.12 0.18 0.21 1.0 4,772 Design Volume-Provided Design Volume Surface Area Surface Area Design Volume Depth Provided Required (ft) Required Provided Provided (cf) (sf) (sf) (cf) Bioretention 1 4,772 1.0 4,772 5,899.0 7,251 2.2 Drainage & Erosion Control Design On the northeastern side of the project area, 54" RCP is proposed in the ditch on the southwest side of the existing gravel road. The 54" RCP line continues south along the ditch and eventually turns south under Perimeter Road after the proposed Westfeldt round-a-bout. 15" and 18" RCP systems are proposed along the eastern side of Perimeter Road and west of the proposed building and parking area. Each of the lines collects water via curb inlets and travels south. At the southeastern corner of the parking lot, the 18" eastern line turns west and outfalls into the bioretention area. The 15" RCP from the western side of the project site travels south and outfalls into the northwestern side of the bioretention area.Additionally, a 36" RCP is proposed from the bioretention outlet control structure. This 36" RCP flows southwest and ties into the 54" RCP line, which continues along the proposed Westfeldt Drive. These pipes have been designed to safely convey the 25-year storm. Pipe profiles and Pipe capacity computations can be found on sheet SW-01 of the stormwater plans(Appendix C1). 2.3 Operation and Maintenance Manual The bioretention area requires maintenance to work properly. An O&M plan has been developed and can be found in Appendix D. 2.4 Design Software and Manuals The following design software programs were used in the analysis and development of the stormwater and documents: • Hydraflow Hydrographs for AutoCAD Civil 3D 2021 • AutoCAD Civil 3D 2023 • Microsoft Office 2021 6 ASHEVILLE REGIONAL AIRPORT-ATCT AND TRACON PROJECT INITIAL SUBMITTAL:MAY 2024 STORMWATER MANAGEMENT REPORT The following design manuals and literature were used in the analysis and development of the stormwater documents: • NCDEQ Storm water Design Manual—2017 Edition 7 ASHEVILLE REGIONAL AIRPORT-ATCT AND TRACON PROJECT INITIAL SUBMITTAL:MAY 2024 STORMWATER MANAGEMENT REPORT