HomeMy WebLinkAboutSW6210302_Recorded Document_20240826 (2) I rOperation . . reern nt
Project Name: Utility Improvements to Serve Maxwell Ridge
Project Location: Calloway Road, Hoke County
Cover Page
Maintenance records shall be kept on the following SCM(s). This maintenance record shall be kept in a log in a known set location.
Any deficient SCM elements noted in the inspection will be corrected, repaired, or replaced immediately. These deficiencies can
affect the integrity of structures, safety of the public, and the pollutant removal efficiency of the SCM(s).
The SCM(s) on this project include (check all that apply& corresponding O&M sheets will be added automatically):
Infiltration Basin Quantity:_ 1 Location(s):
Infiltration Trench Quantity: Location(s):
Bioretention Cell Quantity: Location(s):
Wet Pond Quantity: Location(s):
Stormwater Wetland Quantity: Location(s):
Permeable Pavement Quantity: Location(s):
Sand Filter Quantity: Location(s):
Rainwater Harvesting Quantity: Location(s):
Green Roof Quantity: Location(s):
Level Spreader- Filter Strip Quantity: Location(s):
Proprietary System Quantity: Location(s):
Treatment Swale Quantity: Location(s):
Dry Pond Quantity: Location(s):
Disconnected Impervious Surface Present: No Location(s):
User Defined SCM Present: No Location(s):
Low Density Present: No Type:
I acknowledge and agree by my signature below that I am responsible for the performance of the maintenance procedures listed for
each SCM above, and attached O&M tables. I agree to notify NCDEQ of any problems with the system or prior to any changes to
the system or responsible party.
Responsible Party: Huff Rokoski Development, LLC
Title& Organization: Ralph Huff-Managing Partner
Street address: 2919 Breezewood Avenue
City, state, zip: Fayetteville, NC 28303
Phone number(s): 910-30 -3608
Email: DRhuff ufffamilyoffice.com
Signature: Date: 3) 1 3I aU
I, 'AM1 (j&( Q.. Notary Public for the State of NC
County of CUmbe_n 0,.0' , do hereby certify that .b. Rat ft,, 1-1 i ___aL
personally appeared before me this j 3 day of march o)0 au and
acknowledge the due execution of the Operation aintenance Agreement .
Witness my hand and official seal,
.,,,j,�( JARA yy FILED Jun 24, 2024 02:54:06 pm
P' `�ileS BOOK 01539 FILED
4.= NOTARy Sz PAGE 0961 THRU 0965 HOKE COUNTY,NC
INSTRUMENT# 04185 ELAINE BRAYBOY
COMMISSION s = RECORDING REGISTER
EXCISE TAX (None) OF DDIL
EEDS
11' (None)
S<9 '°UREIC arm
'9'4ND ccOLA �
Seal '""+►m+1feo My commission expires liqi
STORM-EZ 3/17/2021
Version 1.5 O&M Agreement Page 1 of 1
Infiltration Elalinlriallikeliad2944uirements
Important operation and maintenance procedures:
- The drainage area will be carefully managed to reduce the sediment load to the infiltration basin.
No portion of the infiltration basin will be fertilized after the initial fertilization that is required to establish
- the vegetation. Lime may be allowed if vegetation is planted on the surface of the infiltration basin and a
soil test shows that it is needed.
- The vegetation in and around the basin will be maintained at a height of four to six inches.
After the infiltration basin is established, it will be inspected quarterly and within 24 hours after every storm event
greater than 1.0 inches (or 1.5 inches if in a Coastal County). Records of operation and maintenance shall be kept in
a known set location and shall be available upon request.
Inspection activities shall be performed as follows. Any problems that are found shall be repaired immediately.
SCM element: Potential problem: How to remediate the problem:
The entire infiltration Trash/debris is present. Remove the trash/debris.
basin
Areas of bare soil and/or Regrade the soil if necessary to remove the gully, plant ground
erosive gullies have cover and water until it is established. Provide lime and a one-
The grass filter strip or formed. time fertilizer application.
other pretreatment area Sediment has accumulated Search for the source of the sediment and remedy the problem if
to a depth of greater than possible. Remove the sediment and dispose of it in a location
three inches. where it will not cause impacts to streams or the SCM.
The structure is clogged. Unclog the conveyance and dispose of any sediment in a location
The flow diversion where it will not cause impacts to streams or the SCM.
structure (if applicable) Make any necessary repairs or replace if damage is too much for
The structure is damaged. repair.
The inlet pipe is clogged (if Unclog the pipe and dispose of any sediment in a location where
applicable). it will not cause impacts to streams or the SCM.
The inlet pipe is cracked or
otherwise damaged (if Repair or replace the pipe.
applicable).
The inlet device Regrade the swale if necessary and provide erosion control
Erosion is occurring in the devices such as reinforced turf matting or riprap to avoid future
swale (if applicable).
erosion problems.
Stone verge is clogged or Remove sediment and clogged stone and replace with clean
covered in sediment (if
stone.
applicable).
More than four inches of Search for the source of the sediment and remedy the problem if
sediment has accumulated. possible. Remove the sediment and dispose of it in a location
where it will not cause impacts to streams or the SCM.
Erosion of the basin
The basin Provide additional erosion protection such as reinforced turf
surface has occurred or matting or riprap if needed to prevent future erosion problems.
riprap is displaced.
Water is standing more Replace the top few inches of soil to see if this corrects the
than three days after a standing water problem. If not, consult an appropriate
storm event. professional for a more extensive repair.
Infiltration Basin ifi1t1 Qi ilnts (continued)
SCM element: Potential problem: How to remediate the problem:
Shrubs or trees are
growing on the Remove shrubs and trees immediately.
embankment.
The embankment An annual inspection by an
appropriate professional Make needed repairs immediately.
shows that the
embankment needs repair.
Clogging has occurred. Clean out the outlet device and dispose of sediment in a location
gg g where it will not cause impacts to streams or the SCM.
The outlet device
The outlet device is Repair or replace the outlet device.
damaged
Erosion or other signs of
damage have occurred at Repair the damage and improve the flow dissipation structure.
the outlet.
The receiving water Discharges from the
infiltration basin are
causing erosion or Contact the local NCDEQ Regional Office.
sedimentation in the
receiving water.