HomeMy WebLinkAboutWQ0035784_Final O&M Plan_20240724OPERATIONS AND MAINTENANCE MANUAL DYNALIFT ULTRAFILTER (UF) WASTEWATER TREATMENT SYSTEM Prepared for: Cottages of Boone Water Reuse Project Boone, NC Prepared by: DYNATEC SYSTEMS INC. 909 Jacksonville Road Burlington, NJ 08016 609 387 0330 August, 2013 Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -4- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Table of Contents Table of Contents ........................................................................................................... 4 Safety Notes: .................................................................................................................. 7 Precautions ..................................................................................................................... 8 Water Quality Guidelines ............................................................................................... 9 Membrane Preservation and Storage ........................................................................... 10 Short-Term Shutdown: Less Than 8 Hours .......................................................................... 10 Intermediate Shutdown: Less than 1 Week .......................................................................... 10 Long-Term Shutdown: More Than 1 Week .......................................................................... 10 Controls ........................................................................................................................ 11 PLC Controls ........................................................................................................................ 11 Operation ...................................................................................................................... 12 Membrane Cleaning ..................................................................................................... 14 Introduction ........................................................................................................................... 14 When Cleaning is Required .................................................................................................. 14 Types of Fouling ................................................................................................................... 14 Automatic Cleaning Process ................................................................................................. 14 Cleaning Time ....................................................................................................................... 16 Cleaning Solutions ....................................................................................................... 17 Cleaning Chemicals ...................................................................................................... 17 Memcleen A .......................................................................................................................... 17 Chemical Calculation: ........................................................................................................... 17 Chlorine................................................................................................................................. 17 Chemical Calculation: ........................................................................................................... 18 Factory Assistance ....................................................................................................... 18 Membrane Chemical Compatibility ............................................................................. 19 Appendix A. UF System Specifications ...................................................................... 20 Appendix B. Operator Interface Screens ..................................................................... 24 Main Menu ................................................................................................................... 25 Alarm History .............................................................................................................. 26 Raw Waste ................................................................................................................... 28 System Feed Pumps ..................................................................................................... 29 Screen Effluent Tank Level Set Points ........................................................................ 30 Rotary ScreenSetup ...................................................................................................... 32 UV Setup Screen .......................................................................................................... 34 Screen Transfer Pumps ................................................................................................ 35 Aeration Blowers ......................................................................................................... 37 Blowers Setup .............................................................................................................. 39 Blower PID Tuning ...................................................................................................... 42 Circulation Pumps ........................................................................................................ 43 Circulation Pumps Setup .............................................................................................. 44 Permeate & Backwash ................................................................................................. 46 Backwash Pumps Setup ............................................................................................... 48 Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -5- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Effluent Transfer Pumps Setup .................................................................................... 50 Backwash Tank Level Set Points ................................................................................. 51 Chemical Feed .............................................................................................................. 53 Carbon Dosing Pumps Setup ....................................................................................... 54 Caustic Dosing Pumps Setup ....................................................................................... 55 PAC Dosing Pumps Setup ........................................................................................... 57 Membrane Cleaning System ........................................................................................ 58 Cleaning System Valves Setup .................................................................................... 59 Cleaning System Set Points ......................................................................................... 61 Maintenance ................................................................................................................. 63 UF Master Control ....................................................................................................... 67 UF Operational Set Points ............................................................................................ 69 UF Data Logging ......................................................................................................... 71 UF Flush Pumps Setup ................................................................................................. 72 UF Sludge Valve Setup ................................................................................................ 73 UF Permeate Pump Setup ............................................................................................ 74 UF Permeate Pumps PID Tuning ................................................................................. 76 UF Valves Setup .......................................................................................................... 77 Anoxic Tank & Aeration .............................................................................................. 80 Anoxic Tanks Mix/RAS Pumps Setup ......................................................................... 81 System Tanks Level Set Points .................................................................................... 82 Appendix D. Alarm List and Troubleshooting ............................................................ 85 1 Rotary Brush Screen Tank High Level ................................................................. 85 2 Bioreactor A High Level ....................................................................................... 85 3 Bioreactor B High Level ....................................................................................... 85 4 Anoxic Tank A High Level................................................................................... 85 5 Anoxic Tank B High Level ................................................................................... 86 6 Backwash Tank High Level .................................................................................. 86 7 Backwash Tank Low Level .................................................................................. 86 8 EQ Tank Low Level.............................................................................................. 86 9 Aeration Blowes Cooling Fan Overload ............................................................... 86 10 Aeration Blower Cooling Fan Failure................................................................... 87 11 Process Blower Overheat ..................................................................................... 87 12 Process Air Bioreactors High Temperature .......................................................... 87 13 Process Air Membranes High Temperature .......................................................... 88 14 Circulation Pump Failure to Run .......................................................................... 88 15 Circulation Pump Overload .................................................................................. 88 16 Circulation Pump Low Suction Pressure .............................................................. 88 17 Drum Screen Failure to Run ................................................................................. 89 18 Dynalift Feed Valve Failure.................................................................................. 89 19 Test ........................................................................................................................ 90 20 Dynalift Air Flow High ......................................................................................... 90 21 Dynalift Drain Valve Failure ............................................................................... 90 22 Dynalift Air Flow Low ........................................................................................ 90 23 Dynalift SHUTDOWN! High Trans-Membrane Pressure .................................... 90 Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -6- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 24 Backwash Pumps Overload .................................................................................. 91 25 Backwash Pump Failure to Run ............................................................................ 91 26 Dynalift SHUTDOWN! Low Permeate Flow....................................................... 91 27 System feed Pumps Overload ............................................................................... 92 28 System feed Pump Seal Failure ............................................................................ 92 29 System feed Pump Failure to Run ........................................................................ 92 30 Screen Transfer Pumps Overload ......................................................................... 92 31 Screen Transfer Pump Failure to Run ................................................................... 93 32 Dynalift SHUTDOWN! Bioreactor Low Level .................................................... 93 33 Dynalift High Permeate Flow .............................................................................. 94 34 Bioreactor A High Air Flow ................................................................................. 94 35 Dynalift Low Trans-Membrane Pressure.............................................................. 94 36 Bioreactor Low Air Flow ...................................................................................... 94 37 Anoxic Tank High ORP ........................................................................................ 95 38 Bioreactor Low Level ........................................................................................... 95 39 Anoxic Tank Low ORP ........................................................................................ 95 40 Bioreactor Low Dissolved Oxygen ....................................................................... 96 41 Bioreactor High pH ............................................................................................... 96 42 Dynalift Circulation Pump Low Suction Pressure ................................................ 96 43 Bioreactor High Dissolved Oxygen ...................................................................... 97 44 Dynalift SHUTDOWN! High Feed Pressure ........................................................ 97 45 Dynalift Low Feed Pressure.................................................................................. 97 46 Dynalift High Permeate Pressure .......................................................................... 98 47 Dynalift Low Permeate Pressure .......................................................................... 98 48 Permeate Pump High Pressure .............................................................................. 98 49 Permeate Pump Low Pressure .............................................................................. 99 50 Process Air Bioreactor High Pressure................................................................... 99 51 Process Air Membrane High Pressure .................................................................. 99 52 Process Air Bioreactor Low Pressure ................................................................... 99 53 Process Air Bioreactor Low Pressure ................................................................. 100 54 Effluent Pump Failure to Run ............................................................................ 100 55 E-STOP Pressed .................................................................................................. 100 Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -7- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Safety Notes: WARNING! Pumps used in this system start and stop automatically during normal operation. Always stop the drive unit before beginning any repair work on it. Make sure that the motor cannot accidentally be started by any means during repairs. Refer to individual manufacturers’ instruction manuals (see separate binder) for more specific information. Failure to follow the above procedure may result in personal injury and/or property damage! WARNING! Chemical metering pumps and feeders that convey hazardous media must be decontaminated prior to any maintenance work on them. Refer to individual manufacturers’ instruction manuals (see separate binder) for more specific information. Failure to follow the above procedure may result in personal injury and/or property damage! WARNING! Cleaning and pH adjusting chemicals used in this installation may be harmful. Manufacturer’s material safety data sheets (MSDS) and handling instructions should always be followed. Use eye and skin protection when handling chemicals. Failure to follow the above procedure may result in personal injury and/or property damage! Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -8- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Precautions No silicone-containing agents are to be introduced into the system. Use of these materials in any quantity will cause irreversible membrane fouling. NOTE: Antifreeze and defoamers may contain silicone and should therefore never be allowed into the system. Refer to Appendix A. System Specifications for maximum temperature to which the standard membrane elements should be subjected. Do not exceed this temperature or irreversible damage can occur. Refer to Appendix A. System Specifications for the pH range over which the membranes may be subjected during normal operations, and during cleaning. The system must be protected from freezing. Failure to do so will cause damage to the membrane elements and will cause damage to other system components. Membrane elements should never be allowed to dry out. At all times the membrane elements must remain wet. Damage from membrane dry out is irreversible. Do not process any solvents or chemicals harmful to the membranes. Consult factory prior to introducing any solvent. Abnormal concentrations of strong oxidizers (chlorine, hydrogen peroxide, etc.) must not be present in process water on a continuous basis. Consult factory for allowable concentrations. Coarse or abrasive particles should be prevented from entering the system, since they may damage system components. A 1/8-inch screen in the process pump suction line (by others) generally provides sufficient protection. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -9- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Water Quality Guidelines Incoming water quality (process water) will affect membrane performance. High water hardness is often identified as a major source of excessive membrane fouling. Water containing salts of hardness or other sparingly soluble salts must not be used for cleaning membranes. Soft or deionized water must be used. Both hot and cold water supplies to the cleaning tank must contain less than 3 grains of hardness (51 parts per million (ppm) of CaCO3). Note: We do not recommend the use of permeate for either cleaning of the membrane system. Iron, aluminum, and manganese in cleaning water will reduce the performance of the cleaning solution. Generally, iron concentrations should be less than 0.3 ppm, aluminum less than 1 ppm, and manganese less than 0.05 ppm. At no time during process operations should the pH of process fluid be below pH 3.0 or above pH 11.0. Operation outside of these parameters will compromise membrane life. Silica compounds naturally occur in many waters. Please check your water source for the compounds listed in the table below: Table 1. Silica Compounds Name Formula Occurrence Effect on Membrane Soluble silica SiO2 Naturally in many waters Does not foul Suspended silica SiO2 Naturally in many waters Does not foul Silicates M2O xSiO2 yH20 Water treatment, food additives, detergents Forms fouling films quickly, but is cleanable with caustic soda Microcrystalline silica (diatomaceous earth) SiO2 Filter aid Irreversible pore plugging Colloidal silica SiO2 Common in rivers and well waters At pH below 7.0 gels and fouls membranes irreversibly. At pH above 7.0 fouls in presence of salts (non-fouling without salts). Silicones Polysiloxanes Antifoamers Irreversible fouling by adsorption and film formation. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -10- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Membrane Preservation and Storage All membranes are shipped with small amounts of deionized water and a preservative. Modules can be initially stored in a sheltered area, protected from freezing and sealed as shipped until ready for use. Do not allow the membranes to dry out. After installation, the elements must be preserved, as recommended below, if the system must be shutdown. Short-Term Shutdown: Less Than 8 Hours The Dynalift system drains and backwashes at every shutdown. It is safe to leave it this condition for up to 8 hours. The membranes will be filled only on the permeate and will slowly permeate out much of the water until the membranes are dry. Intermediate Shutdown: Less than 1 Week If the Dynalift s ystem is to be shut down for an extended period it MUST be kept filled to prevent drying out. It must be cleaned using the standard cleaning process before refilling with potable water. The manual drain valve should be closed to prevent loss of the water due to a power failure. The system can then be filled from the chemical feed system potable water valve by manually activating it from the HMI screen. Long-Term Shutdown: More Than 1 Week For long-term shut-down, the following steps are recommended: 1. A thorough chemical cleaning of the membranes. 2. Impregnation of the membranes in 1,000 ppm sodium metabisulfite and replace every three months. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -11- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Controls PLC Controls All controls are located in the Motor Control Center (MCC) and the attached Main Control Panel (MCP) section. The MCP section houses the programmable logic controller (PLC), and associated I/O components for the MCC motor controls. All other skids and sub-systems are controlled via Ethernet remote I/O panels located on each skid, or near the instrumentation. The PLC performs all the logic required for the automatic operation of the components. The Human/Machine Interface (HMI) panel provides all control and status for the entire system. The workstation is installed in the door of the Main Control Panel. Specific operation of the PLC program is described in the Appendices for this job. User manuals for the individual controls are enclosed in the Manufacturer’s literature section of this manual. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -12- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Operation The following is a general description of the wastewater treatment process based on the Dynalift MBR system. The effluent from the Equalization Tank is processed through a series of treatment units prior to being discharged as reuse water. The process can be broken down into the following steps: 1. Solids Separation – The wastewater from the Equalization Tank pump passes through a rotary brush screen with a 1mm mesh to remove large solids. The solids removed are directed back to the sewer. The brush screen is equipped with an intermittent water flush on the discharge chute to prevent solids from building up there. The screen and the holding tank beneath it have large overflow pipes to prevent any possibility of an overflow out of the screen. In addition the sludge wasting back to the sewer is directed into the screen discharge to help flush solids to the sewer. Three transfer pumps, one for each biological train and a common installed spare, located outside the screen room, send the filtrate to the Anoxic Tanks for each train. 2. Anoxic Zone – Wastewater from the transfer pumps flows into the Anoxic Tanks and mixes with the mixed liquor circulating in the system. A mix/recycle pump recirculates the mixed liquor through a circular slot at the bottom of the tank. The high velocity flow sweeps the bottom from the center out and causes circulation up the side of the tank and down through the center again. A proportioning valve in the pump suction allows sludge from the Aeration tank to be returned to the anoxic zone bringing the Nitrates produced by oxidation back into the anoxic tank. The anoxic tank is kept in a low oxygen condition. Bacteria in the wastewater are starved for oxygen so they break down the Nitrates (NO3) to get the oxygen they need. This process releases Nitrogen into the air. The tank is sealed and vented to the outside of the building. The anoxic zone is also provided with a supplemental carbon feed to provide a food source for the bacteria for low flow conditions, or if not enough BOD is available. 3. Aerobic Zone – Most of the mixed liquor returns directly from the membranes into the Bioreactor. The mixed liquor passing through the Anoxic tank also overflows into the Bioreactor. Most of the aeration for the bioreactor comes from the air introduced into the membranes. DO control is provided by a DO sensor and additional aeration of the bioreactor. Aeration is by cylindrical EPDM fine bubble diffusers radiating from a common header at the center of the tank. The design is such that maintenance of the diffusers can be performed from the top of the tank without entering the tank. 4. Membrane Separation – The mixed liquor is circulated from the bioreactor through the membrane skids and returning into the Anoxic Tank and Bioreactor by a low head centrifugal pump. The membranes are a tubular style consisting of many small tubes contained in a number of 8" diameter PVC housings. The mixed liquor flows inside of all of the small tubes and clean water permeates through the walls of the tubing into the outer shell. A pump on each membrane skid collects the permeate and sends it into the common backwash tank. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -13- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com An air diffuser at the bottom of each membrane module introduces air into the mixed liquor to cause turbulence which helps scour the membrane surfaces to reduce fouling. 5. Backwash System – The permeate in the backwash tank goes out through an overflow pipe to the qualitative instrumentation final UV disinfection system. Permeate is stored in the tank to be used periodically to backwash the membrane to prevent fouling. After a set number of backwashes a flush is also performed. During the flush the mixed liquor in the membranes is pumped back into the bioreactor a backwash is performed along with water flushing of the air diffusers at the bottom of each membrane. If sludge wasting is enabled then some mixed liquor will also be diverted back to the sewer. 6. Chemical Cleaning – Occasionally the membranes need to be chemically cleaned to remove scaling and other foulants that regular backwashing cannot remove. This process is completely automatic, except for filling the chemical tanks, and is initiated by the operator. The Dynalift to be cleaned is first stopped, which always initiated an extended backwash. Then the operator presses the cleaning button and the system cycles through a multi-step process of draining, filling, adding chemical, refreshing chemical, and then performing a second cleaning with a different chemical. A button on the HMI allows the operator to determine whether the membrane skid goes back on line automatically at the end of a cleaning cycle, or simply sits empty in a cleaned condition. Note that if it is to remain off for more than 8 hours or so it should at the very least be filled with potable water and not left dry. 7. Final Disinfection – The permeate discharge passes through an enclosed UV (Ultraviolet) light disinfection unit then out to discharge. This UV is nothing more than a backup safety system as Ultrafiltration membranes have pores that are too small for bacteria or viruses to pass through. So unless there is a serious membrane breach there is nothing for it to kill. Note that in this system qualitative instrumentation has been installed upstream of the final UV that the operator can use to determine whether the water produces is suitable for reuse. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -14- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Membrane Cleaning Introduction The early establishment of an effective cleaning regime for the membrane is fundamental to the long-term successful operation of the treatment system. If successful cleanings are not carried out when the system is new and maintained over the life of the system, the system will not operate to satisfactory performance. In addition, cleaning will be required more frequently. When Cleaning is Required There are two occasions when a cleaning cycle should be carried out. 1. When TMP has risen to the point which has been determined to indicate t he system is excessively fouled. This TMP value will be different for every jobsite, as it is based on the characteristics of the wastewater, and not the performance of the membrane. 2. Whenever the system will be shut down for more than a few hours. Types of Fouling There are two basic types of fouling that may normally occur: 1. Organic, where typically oil or other organic material has fouled the membrane by causing a gel layer to form on the surface of the membrane, preventing or slowing the flow of water through the membrane. 2. Inorganic, where salts and/or metals are present in the waste, or have precipitated in the waste, and have plugged the pore structure of the membrane, reducing permeate flow. Automatic Cleaning Process This system features an Automatic Cleaning process that is initiated by the operator. The operator starts the process by first pressing the Stop button for the Dynalift A or B, to be cleaned. Then the operator presses the Clean button, which sends you to the Cleaning Screen Pressing the Start touch button on the cleaning screen begins the automated process. The steps in this process are as follows: 1. If the backwash tank is not filled then the Potable Water Valve opens and fills the Cleaning Tank with potable water to the Full Level. 2. The Membrane Drain Valve closes and the membrane skid fills Pump starts to circulate water through the membranes to flush out any remaining mixed liquor. The Cleaning Pump stops and the Membrane Drain Valve again opens and allows the membranes to drain for a time period. Then the Cleaning Pump restarts to remove the last of the dirty water from the cleaning tank. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -15- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 3. The Backwash Tank fills with water from the potable water source, and permeate from the other Dynalift if it is in operation. If this process takes too long (greater than 30 minutes), an alarm sounds, the operator is shown the failed step number, and the cleaning process aborts. 4. The normal backwashes for both Dynalifts are inhibited. The appropriate Dynalift drain valve opens, the backwash valve opens, and a long backwash occurs until the Backwash Tank has reached the Reuse Low Level. If this process takes too long (greater than 30 minutes), an alarm sounds, the operator is shown the failed step number, and the cleaning process aborts. 5. Repeat step 1 (fill backwash tank). 6. Repeat step 2 (backwash). 7. The Bleach Valve opens and fills the cleaning tank with the bleach solution. If this process takes too long, an alarm sounds, the operator is shown the failed step number, and the cleaning process aborts. 8. The Cleaning Pump starts and bleach is circulated through the membranes for the specified cleaning time. During this time the Backwash Tank is also being refilled. During the circulation the Membrane Air Valve opens briefly at the specified intervals and for the specified length of time to provide additional agitation. If the level in the Cleaning Tank should drop too low an alarm will sound, and the operator will be shown the failed step number, and the cleaning process will abort. 9. Stop the Cleaning Pump and open the Membrane Drain Valve and drain the Dynalift completely for a timed period. Then restart the Cleaning Pump to remove all the bleach solution. 10. Inhibit the normal backwashes and backwash the Dynalift to drain until the Backwash Tank reaches the Reuse Low Level point. 11. Refill the Backwash tank with potable water and permeate if the other Dynalift is running. 12. Open the Clean Water Valve and fill the cleaning tank to the Flush Level. Start the Cleaning Pump and pump the contents of the cleaning tank to drain. 13. The Citric Valve opens and fills the Cleaning Tank with the citric solution. If this process takes too long, an alarm sounds, the operator is shown the failed step number, and the cleaning process aborts. 14. The Cleaning Pump starts and citric solution is circulated through the membranes for the specified cleaning time. During this time the Backwash Tank is also being refilled. During the circulation the Membrane Air Valve opens briefly at the specified intervals and for the specified length of time to provide additional agitation. If the level in the Cleaning Tank should drop too low an alarm will sound, and the operator will be shown the failed step number, and the cleaning process will abort. 15. The Cleaning Pump stops and the Membrane Drain Valve opens to drain the cleaning solution out completely. Then the Cleaning Pump restarts to drain the rest of the Cleaning Tank. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -16- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 16. The normal backwashes for both Dynalifts are inhibited. The appropriate Dynalift drain valve opens, the backwash valve opens, and a long backwash occurs until the Backwash Tank has reached the Reuse Low Level. If this process takes too long (greater than 30 minutes), an alarm sounds, the operator is shown the failed step number, and the cleaning process aborts. 17. Repeat step 1 (fill backwash tank). 18. Repeat step 16 (backwash). 19. Open the Clean Water Valve and fill the Cleaning Tank to the Flush Level. Start the Cleaning Pump and pump the contents of the cleaning tank to drain. 20. Show the operator that the cleaning was successful, and indicate that the manual valves ALL need to be returned to their normal positions before starting the system. Change the manual valves for the Dynalift that was cleaned. a. For Dynalift A i. Throttle V107, V108 as required ii. Open V603 iii. Close V109, V602 b. For Dynalift B i. Throttle V207, V208 as required ii. Open V703 iii. Close V209, V702 Cleaning Time The time that a cleaning procedure is left to run depends on the process being carried out. Water temperature plays a large part in the time required for a successful cleaning. It may be necessary to increase cleaning times during cold weather. Additional cleaning time beyond two hours or so is usually not very helpful for Chlorine or Caustic cleaning. Additional cleaning time may very helpful for acid cleaning when trying to remove scaling. Overnight is a very good idea if possible. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -17- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Cleaning Solutions Warning: Most of the chemicals listed are hazardous in some way. ALWAYS, carefully observe the manufacturers recommendations, and take appropriate safety steps such as the use of gloves, goggles, protective clothing, etc. Always follow the recommended concentrations and other directions for each chemical found later in this chapter. There are a wide variety of cleaning chemicals available, but the most commonly used are the following: Cleaning Chemicals Memcleen A This acidic wash chemical is used to remove scaling from the membrane. Note: Memcleen A is a mild acid and as such care should be taken in handling, using gloves and safety glasses where appropriate Chemical Calculation: (Desired Memcleen A Concentration % by volume) = Injector Ratio Setting 100 Example: Recommended Memcleen rate is 3%, then the calculation is as follows: 3 = 33.33 = 33:1 100 Chlorine This wash procedure is used to remove stubborn organic material. Ensure that the chemicals are measured accurately or membrane damage could occur. Do not exceed five hundred parts per million (500 PPM) total Chlorine. Note: Sodium hypochlorite is an extremely strong oxidizer and as such care should be taken in handling, using gloves and safety glasses where appropriate Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -18- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Chemical Calculation: (Chlorine Concentration in %) x 10,000 = Injector Ratio Desired Parts Per Million 1. Example: If the Chlorine concentration as supplied is 12.5%, then the calculation is as follows: (12.5) x 10,000 = 250 = 250:1 500 Factory Assistance If after carrying out all the above steps, the system still cannot be cleaned, submit the records of all the steps that you have carried out, along with the results of each to the factory, and assistance will be provided in further work to determine the best method for system cleaning. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -19- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Membrane Chemical Compatibility Please refer to the attached compatibility chart for information on chemical compatibility with the materials of construction of your Dynatec Systems Inc. system. Table 2. Chemical Compatibility Chemical Compatibility G – good F – fair, N – Not recommended Aliphatic hydrocarbons G Aromatic hydrocarbons G Chlorinated solvents N Aprotic solvents N Alcohols G Organic acids G Esters F Aldehydes F Ethers G Ketons N Cellosolves G Salts and buffers G Sodium hypochlorite N Hydrogen peroxide, less than 0.5% concentration F Phenols G Silicones N Alkali, temperature, and pH dependent G Inorganic acids G Amines F If you suspect any of the above chemicals that received an F or N rating are present in the waste stream, please contact Dynatec Systems Inc. for further direction. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -20- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Appendix A. UF System Specifications Table A- 1. System Specifications Item Qty Description Parameter 1 DRAWINGS 1.1 System P&I 211113I00 1.1.1 Membrane Skid P&I 211113I10 1.2 Electrical 211113E00 2 2 SYSTEM FEED GRINDER PUMPS 2.1 Manufacturer Wilo 2.2 Model # MTC 32 F76.75/30-3-460-60-2 2.3 Type Submersible grinder 2.4 Rating 75 GPM @ 25 ft. 2.5 Speed 3480 2.6 Motor 3 HP 2.7 Power 460v/3ph/60hz 2 1 ROTARY SCREEN 3.1 Manufacturer Or-Tec 3.2 Model # ODS8 3.3 Type Mechanical Brush 3.4 Perforation 1 mm 3.5 Motor ½ HP 3.6 Power 460v/3ph/60hz 3 3 SCREEN WASTE TRANSFER PUMP 4.1 Manufacturer G&L 4.2 Model # 9SH4C45C5 4.3 Type Centrifugal 4.4 Housing Stainless Steel 4.5 Seal Silicon Carbide / Silicon Carbide 4.6 Speed 1750 4.7 HP 1/2 4.8 Rating 50 GPM @ 22 ft. 4.9 Power 460v/3ph/60hz 4 3 UF MEMBRANE CIRCULATION PUMP 4.1 Manufacturer Sulzer 4.2 Model # CPT22-4 4.3 Type Centrifugal 4.4 Impeller Duplex Stainless Steel 4.5 Seal Dynamic 4.6 Housing Duplex Stainless Steel 4.7 Speed 1160 Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -21- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Table A- 1. System Specifications Item Qty Description Parameter 5.8 Hp 5 5.9 Rating 660 GPM @ 15 ft. 5.10 Power 460v/3ph/60hz 5 12 AIRLIFT MEMBRANE MODULES 6.1 Type Xflow F4385-38PRV 6.2 Arrangement 2 pass, 6 in parallel 6.3 Feed Pressure 5 psi 6.4 Pressure differential (TMP) 2 psi typical 6.5 pH range – process 3.0 – 10.5 6.6 pH range – clean 2.0 – 11.0 6.7 Maximum Operating Temperature 120° F (Note: Continuous operation at combined high temperature and high or low pH will shorten membrane life) 6 2 ANOXIC TANK RAS MIX PUMP 7.1 Manufacturer Paco 7.2 Type Centrifugal 7.3 Housing Cast Iron 7.4 Seal Double with Seal Pressurizer 7.5 Speed 900 7.6 HP 3 7.7 Rating 600 GPM @ 15 ft. 7.8 Power 460v/3ph/60hz 8 2 PROCESS BLOWER 8.1 Manufacturer Kaeser 8.2 Model Number CB 131C 8.3 Type Positive Displacement 8.4 Rating 560 scfm @ 8.5 psi 8.5 Motor HP 40 8.6 Power 460v/3ph/60hz 8 2 UV SYSTEM 9.1 Manufacturer Severn Trent 9.2 Model Number 8102-HO-100 9.3 Intensity 2.2 Kw 9.4 Material 316 Stainless Steel 9.5 Power 120v/1ph/60hz 10 2 BIOREACTOR TANK 10.1 Tank Size & Type 10,500 gallon HDPE 11 2 ANOXIC TANK 11.1 Tank Size & Type 9,150 gallon HDPE Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -22- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Table A- 1. System Specifications Item Qty Description Parameter 12 1 POST-ANOXIC TANK 12.1 Tank Size & Type 10,500 gallon HDPE 13 1 PERMEATE BACKWASH TANK 13.1 Tank Size & Type 600 gallon HDPE 14 3 BACKWASH PUMP 14.1 Manufacturer G & L 14.2 Model # 23SH4J52J5 14.3 Type Centrifugal 14.4 Impeller Stainless Steel 14.5 Seal Silicon Carbide / Silicon Carbide 14.6 Housing Stainless Steel 14.7 Speed 1750 14.8 Hp 5 14.9 Rating 400 GPM @ 22 ft. 14.10 Power 460v/3ph/60hz 15 2 CHEMICAL FEED PUMP 15.1 Manufacturer LMI 15.2 Model # AA961-363SI 15.3 Type Diaphragm 15.4 Rating 2 gph @ 50 psi 15.5 Power 120v/1ph/60hz 16 5 CHEMICAL FEED PUMP 16.1 Manufacturer LMI 16.2 Model # P161-363SI 16.3 Type Diaphragm 16.4 Rating 2 gph @ 50 psi 16.5 Power 120v/1ph/60hz 17 2 CHEMICAL FEED PUMP 17.1 Manufacturer Dosatron 17.2 Model # D14MZ2AFPII 17.3 Type Water Powered 17.4 Rating 0.05 – 14 gpm @ 7 – 85 psi 18 2 CHEMICAL FEED PUMP 18.1 Manufacturer Dosatron 18.2 Model # D14MZ10VFPII 18.3 Type Water Powered 18.4 Rating 0.05 – 14 gpm @ 7 – 85 psi Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -23- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Table A- 1. System Specifications Item Qty Description Parameter 19 CONTROLS 19.1 1 Control Cabinet/Motor Control Motor Control Center 19.2 Location Local 19.3 Type Allen Bradley Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -24- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Appendix B. Operator Interface Screens This chapter describes the Human/Machine Interface (HMI) as supplied with this project. This installation has one touch screen HMI which controls both trains. CAUTION! When looking at the HMI you must be very careful not to accidently push any buttons that start or stop processes or change set points. In the case of set points if you suddenly find yourself at a screen asking for a numerical input ALWAYS PRESS CANCEL TO EXIT! SYSTEM OPERATIONAL HMI SCREENS The following HMI screens are used to control the common operations of the Dynalift System shared by membranes A & B. These include the screen, waste transfer pumps, blowers, backwash pumps, reuse pump, and chemical feed skid. All screens are touch screens and you should NEVER use anything but clean fingers to operate the screen. Pencils and other objects will permanently damage the screen. When leaving the system unattended it is a very good idea to always leave a screen showing which has a pictorial view on it. These screens only have navigational buttons on them. Someone curiously touching the screen will see it suddenly change, but no harm will be done. This is not true of screens which have pushbuttons or set points. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -25- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Main Menu This screen is the main screen that takes you to all other screens for the Dynalift system. This screen is always reached by the Main Menu key from any other screen. Figure 1. Main Menu The Alarm Indicator in the upper right corner shows if there are any alarms currently active for both A and B Dynalifts. If there are it turns red and blinks. When an alarm is active the Alarm Indicator will appear on every screen. The Active Alarms button on the left side will show you which alarms are still active. All setup screens, all setpoints and tank level setpoints can be accessed from this screen by pressing the corresponding blue buttons. As a button is pressed a list of available screens will pop-up. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -26- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Alarm History The Alarm History screen pops up every time an alarm occurs. Figure 2. Alarm History The Acknowledge & Silence button on this screen silences the alarm horn and also acknowledges the alarm. Alarms that are brief and latch up so they are not missed will not be cleared though. The Reset All Alarms button will clear any alarms not currently active. Note that if an alarm won’t clear by using Reset All Alarms it means the alarm condition still exists. The alarm list is in order by occurrence, newest alarms on top. Pressing reset causes alarms that no longer are active to be removed from the list. The Alarm History button on the upper left allows you to scroll through the entire history of alarms, or clear out them all. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -27- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com The large blank indicator on the upper right of the screen is a warning that pops up if you try to enter a set point that that is out of range. For instance a high level that is lower than a low level set point. You can silence this alarm simply by using the Previous Screen button. The Main Menu takes you back to the main menu. Note that all other screens have most of these navigation buttons and function the same way. The Alarm indicator in the upper right corner shows if there are any alarms currentl y active for both A and B Dynalifts. If there are, it turns red and blinks. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -28- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Raw Waste This screen shows the Equalization Tank, feed pump, brush screen, chute flush and transfer pumps. Figure 3. Raw Waste Screen The status indicators show whether the pumps are on or off and whether the chute flush solenoid is open. The level indicators show the level in the Equalization Tank and the screen tank. The navigation buttons on the right take you to the main menu or back to the previous screen. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -29- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com System Feed Pumps This screen controls the Equalization Tank pumps. Figure 4. System Feed Pumps The status indicator shows whether the pump is running. The feed pumps run continuously as long as either train is in operation The navigation buttons on the right take you to the main menu or back to the previous screen. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -30- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Screen Effluent Tank Level Set Points This screen can be accessed by pressing the Tank Level Setpoints button on the Main Menu screen. It controls the starting and stopping of the Equalization Tank feed pump (if connected) and the waste water transfer pumps P5001A, B, and S. Figure 5. Screen Effluent Tank Level Set Points Both of the A and B Dynalifts are fed by a pump in the Equalization Tank. Influent is pumped up to the Brush Screen where screened liquid falls into the screening pump tank. The set point buttons on the left control the start, stop and alarming of the feed pump operation. As long as the level in the brush screen tank is between the start and stop set points, the wet pump will continue to run. Note that the buttons are arranged vertically according to how the set points values would be. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -31- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com The two buttons to the right permit the waste water transfer pumps to run if either train A or B is calling for feed. The buttons are arranged vertically according to how the set points values would be. The navigation buttons on the right take you to the main menu or back to the previous screen. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -32- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Rotary ScreenSetup This screen controls the brush screen and its chute flush solenoid. Figure 6. Brush Screen Setup Both of the A and B Dynalifts are fed by the Brush Screen. The HOA switches here and on the drawer of the Motor Control Center are for TESTING only! Be sure to return the HOA switch to Auto when done testing. No part of a Dynalift system should ever be attempted to run in a manual mode. Great damage can occur. The screen run time totalizer can be reset from the Maintenance screen if major repairs have been performed. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -33- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com The Screen Off Delay button allows the operator to set how long the screen continues to run after the demand for feed to the system has stopped. This keeps solids from remaining in the screen. The navigation buttons on the right take you to the main menu or back to the screen that you came from. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -34- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com UV Setup Screen This screen controls the brush UV units. Figure 7. UV Units Setup The status indicator shows whether the UV unit is on or off. The off delay timer set point button controls how long the lamps remain on after flow stops. Turning lamps on and off greatly shortens their life. Leaving them on without flow may cause them to overheat. The time was set by Dynatec for 1 hour as this was tested to be a safe time. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -35- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Screen Transfer Pumps This screen controls the operation of the three screenings pumps located outside the screen room. This spare pump is common to both the A and B Dynalifts. Figure 8. Screen Transfer Pumps The transfer pumps A & B are dedicated to the A & B trains respectively. A cannot feed B, and vice versa. The S pump is an installed spare for both the A & B pumps. The level indicator at the top shows the level in the screen tank. Refer to the level set points screen to see what levels actually allow these pumps to run. The HOA switches here and on the drawer of the Motor Control Center are for TESTING only! Be sure to return the HOA switch to Auto when done testing. No part of a Dynalift system should ever be attempted to run in a manual mode. Great damage can occur. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -36- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com When the S pump is selected for Auto A or Auto B operation then the A or B pump is automatically disabled. Note the warning label that pops up over the HOA control telling you that the manual valves MUST be adjusted to direct the flow appropriately. The run time totalizers can be reset from the maintenance screen in the event of major repairs. The navigation buttons on the right take you to the main menu or back to the previous screen. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -37- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Aeration Blowers This screen shows the operation of the blowers which supply air to the Membrane Skids and the Bioreactors for both the A and B Dynalifts. Figure 9. Aeration Blowers There are three blowers installed in this system. Each blower can operate independently. Each blower has a start and stop button on the blower control screen. The status indicator shows which blower is actually running. The blowers are controlled by the pressure transmitter located on the Process Air Header. The blower speed is controlled by a VFD (variable frequency drive) such that the pressure in the header remains constant at all times. With a constant air pressure a simple globe valve controls the air flow to each membrane skid at a constant design flow of 60 CFM. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -38- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Air to the Bioreactors is controlled by the DO probe in each Bioreactor and the associated pinch valve. The Setup Screen navigation button takes you to the blower controls and set points. The navigation buttons on the right take you to the main menu or back to the previous screen. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -39- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Blowers Setup This screen controls the blowers which supply air to the Membrane Racks and the Bioreactors for both the A and B Dynalifts. Figure 10. Blower Setup There are three blowers installed in this system. Each blower has a start and stop button. The status indicators show which blowers are actually running. Each blower has a cooling fan. The blowers cannot operate in Auto without a cooling fan running. Operating the blower in Hand without a cooling fan running may damage the blower through overheating. The HOA switches and manual speed control for fans and blowers here and on the drawer of the Motor Control Center are for TESTING only! Be sure to return the HOA switch to Auto when done testing. No part of the Dynalift system should be run in a manual mode. Great damage can occur. All three blowers came equipped with check valves on the discharge. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -40- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com The off line blower should always be shut down, it’s filter cleaned, and fogged with oil immediately to prevent seizing due to corrosion. The blowers are controlled by the pressure transmitter located on the Process Air Header. The blower speed is controlled by a VFD (variable frequency drive) such that the pressure in the header remains constant at all times. Positive Displacement blowers have a minimum operational speed due to lubrication issues. This means you may here the relief valves pop o ff when the demand for air falls very low. The indicators at the top of this screen show the current speed for each blower and the current header pressure. The pressure alarm set point buttons allow you to adjust the where the alarms occur. These alarms have time delays on them that keep short term pressure changes from causing nuisance alarms. The manual speed set point buttons allow the blowers to be speed controlled while in the Forced On mode. Blowers should NEVER be operated on line this way. All blowers must be operated in Auto or damage may occur. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -41- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Dissolved Oxygen setpoints for the bioreactors can be accessed from this screen. Figure 11. Dissolved Oxygen Setpoints Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -42- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Blower PID Tuning Figure 12. Blower PID Tuning The speed of the blowers is controlled by a single PID loop. The Discharge Pressure Setpoint button allows you the change the header pressure. Raising or lowering the discharge pressure will immediately change the air flow to the membrane skids. A set point change requires changing the globe valve opening to maintain 60 cfm to the membranes. It is very important that the system have enough pressure to overcome the static head in the membranes and the bioreactor, plus all pressure losses due to valves and piping etc. If there is not enough pressure the flow to the membranes or bioreactors can suddenly stop, with a big risk of plugging the membranes. Reducing air pressure to optimize energy efficiency can be very risky and should only be done with very close monitoring. The Kp, Ki, Kd, and DB set points control how the PID loop functions in controlling the blower speed. PID loop tuning is more art than science. Adjusting these set points should be left to someone skilled in the art of PID tuning. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -43- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Circulation Pumps This screen shows the operation of the circulation pumps for both the A and B Dynalifts. Figure 13. Circulation Pumps The circulation pumps are set up similarly to the waste transfer pumps, in that the middle pump is a spare for both the A and B Dynalifts. Pump A and Pump B can only be enabled for Dynalift A and Dynalift B respectively. Pump S can be enabled for either Dynalift. The status indicators show which automatic valves are opened or closed and which pumps are running. The two pressure indicators show the suction pressure to each pump. Since the level in the bioreactors varies over a range of just a few inches the pressure transmitters are a good indicator of whether the strainers are fouled and are alarmed for that purpose. Using the spare pump for either train A or train B requires the repositioning of multiple manually operated valves. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -44- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Circulation Pumps Setup This screen controls the circulation pumps for both the A and B Dynalifts. Figure 14. Circulation Pumps Setup Pump S is a spare for both the A & B trains. If pump S is selected by Auto A or Auto B the A or B pumps are automatically disabled. Note the warning banners that pop up over the HOA buttons for the disabled pump telling you to reposition the manual valves. CAUTION! Selecting a circulation pump also involves changing manual valves to direct flow through the selected pumps. The indicators at the top show which pumps are operating. The pressure indicators on both sides of the screen show the current suction pressure. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -45- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com The pressure set point buttons on each side of the screen are for the suction pressure for the A & B trains respectively. The upper buttons set warning alarms while the lower buttons set alarms that also shut the respective trains down to avoid damage. The pressure transmitters are compound and can read vacuum, so a value of zero for shutdown is acceptable. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -46- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Permeate & Backwash This screen shows the operation of the backwash and reuse pumps, for both A and B Dynalifts. Figure 15. Permeate & Backwash Only one backwash pump is used at a time with the other one turned off. Manual valves direct the flow through the appropriate pump. The Dynalifts are backwashed independently, and can have different schedules. The PLC handles conflicts in the schedules automatically, by inhibiting one or the other backwash briefly. The effluent transfer pumps operate from high and low setpoints in the permeate tank. The 3-way valve AV-3006 in the discharge of the reuse pumps normally directs permeate to the dosing tank. High level in the dosing tank will redirect the permeate flow to the 14-day storage tank. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -47- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com CAUTION! Selecting a Backwash Pump also involves changing manual valves to direct flow through the selected pump. The indicators show which automatic valves and pumps are currently operating. The flow indicators show the gross permeate flow from each membrane skid. This flow will always be greater than the net flow from the plant because some permeate is used for backwash and diffusers flush. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -48- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Backwash Pumps Setup This screen controls the operation of the backwash pumps for both A and B Dynalifts. Figure 16. Backwash Pumps Setup The service backwash pump is selected by the selector switch shown here. Manual control of the potable water fill valve and the reuse pump are also located here. Backwash pumps can NEVER be safely operated in manual mode! Membrane damage can easily occur by running the backwash pumps at the wrong time. These buttons are only for testing purposes and must be used with great care. CAUTION! Selecting a Backwash Pump also involves changing manual valves to direct flow through the selected pump. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -49- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com The indicators show which pump is operating. The potable water fill valve provides water to the backwash for cleaning a train if the other train is also shutdown and not providing permeate. Its operation is automatic during the cleaning cycles. The run time indicators can be reset from the maintenance screen. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -50- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Effluent Transfer Pumps Setup This screen controls the operation of the effluent transfer pumps and permeate diverter valve. Figure 17. Effluent Transfer Setup The effluent transfer pumps P-3002 and P-3003 operate from high and low setpoints in the permeate tank. The 3-way valve AV-3006 in the discharge of the reuse pumps normally directs permeate to the dosing tank. High level in the dosing tank will redirect the permeate flow to the 14-day storage tank. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -51- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Backwash Tank Level Set Points This screen can be accessed by pressing the Tank Level Setpoints button on the Main Menu screen. It controls the operation of the backwash and reuse pumps based on Backwash tank level. Figure 18. Backwash Tank Level Set Points The indicator at the top middle of the screen shows the level of water in the backwash tank from the transmitter mounting level. The High Level Alarm warns of a problem of permeate not leaving the tank at the rate required. The Make Up Water Shutoff Level controls the potable water fill valve when it is in Auto. This level is used to ensure water is available for backwashes during the cleaning process even if neither train is operating. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -52- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com The Backwash Pump Start Level is the minimum level at which the pumps will be allowed to start. The Backwash Pump Stop Level shuts off the backwash and reuse pumps if the level falls too low in the tank. The backwash pumps operating level should always be set higher than the cleaning make-up level in the tank. The low level alarm warns of the low level condition. The Reuse Pump Start & Stop levels allow the reuse pump to operate if water is available in the backwash tank. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -53- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Chemical Feed This following screens control the operation of the dosing pumps used to add chemicals to both the A & B Dynalift trains. Figure 19. Chemical Feed Screen The status indicators show which pumps are actually running (green) or if it is currently off (red). CAUTION! When leaving this screen be SURE that each pump is left in the appropriate mode! Do NOT leave any pump in hand mode, it will NOT stop running! Each train has its own chemical feed pumps (except for the Post-anoxic tank ORP control). The navigation buttons take you to the appropriate screens for both trains. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -54- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Carbon Dosing Pumps Setup Figure 20. Carbon Dosing Pumps Setup The Supplemental Carbon dosing pumps are turned on and off by the ORP probe in the Anoxic and Post-anoxic Tanks respectively. A high ORP can be reduced by dosing carbon. The amount of carbon is set manually by the speed and stoke of the pumps. The pumps can operate even if a train is not operating. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -55- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Pressing the ORP Setpoints button will bring up this screen: Figure 21. ORP Setpoints Caustic Dosing Pumps Setup Figure 22. Caustic Dosing Pumps Setup Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -56- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com The Caustic Pumps are controlled by the pH probe in the bioreactor. A PID loop proportionally operates the pump speed to keep the pH at the set point value. The pump can operate even if a train is not operating. Pushing the Pumps PID Tuning button will bring up the PID tuning screen: Figure 23. Caustic Pumps PID Tuning Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -57- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com PAC Dosing Pumps Setup Figure 24. PAC Dosing Pumps Setup The Poly Aluminum Chloride pumps are used to remove phosphorus if required. It operates whenever the waste transfer pump for that train operates. The amount dosed in is set by manually adjusting the speed and stroke of each pump. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -58- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Membrane Cleaning System This screen shows the valves and pumps located on the chemical feed skid that are used for the automatic cleaning process. Figure 25. Membrane Cleaning System The status indicators show whether the valves are open or closed. The chemical pumps are water powered and started and stopped automatically by the solenoid valves. The manual valves in front of the chemical pumps control the speed of the pumps. The pumps should not click more than 30 times per minute. The navigation buttons return you to where you were, or take you to the cleaning valves screen for A or B. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -59- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Cleaning System Valves Setup This screen controls the valves located on the chemical feed skid that are used for the automatic cleaning process. Even though not a part of the chemical feed skid, the Backwash Water Make-up Valve is included on this screen, since it is mostly used during cleaning. Figure 26. Cleaning System Valves Setup The status indicators show whether the valves are open or closed. The valves cannot be opened simultaneously. However care should be exercised to avoid mixing chemicals. Always use the water valve to flush the lines between chemicals if the valves are operated manually. The cleaning process performs this task automatically. The navigation buttons on the right take you to the main menu or back to the previous screen. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -60- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com The status indicators show which valves actually open (green) or closed (red). CAUTION! When leaving this screen be SURE that each valve is left in the AUTO mode! Do NOT leave any valve in hand mode. These valves only open during the automatic cleaning cycle to fill the system with cleaning chemicals. The two chemical valves start the water powered dosing pumps to pull chemicals from the supply tanks. The water valve may be used manually, along with the chemical feed valve on the membrane skid to fill a membrane with clean water for short term storage. The Backwash Tank Make Up Valve is also only used during the cleaning cycle if no permeate is available for flushes because both trains are down. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -61- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Cleaning System Set Points This screen controls the operation of the cleaning process and cleaning skid valves for trains A and B. Each train has separate setpoints, but the screens are identical for either train with exception of train designation (A or B) or screen background color (pink for train A and yellow for train B). Figure 27. Cleaning System Set Points The set point buttons for Cleaning are common to both trains. The cleaning fill level set point is used to set the bottom header pressure that correlates to the membranes being full of water or chemicals. It is desirable to fill them until the permeate level is up into the tee at the top of the membrane where you can no longer see it. Setting this value too high though will cause the water or chemicals to overflow into the top header and the set point value will never be reached, causing a cleaning alarm. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -62- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com The empty level set point is used to determine that water or chemicals have been successfully drained so the next step can proceed. It should be slightly above zero to reduce nuisance problems. The Maximum cleaning temperature only come into play if a very long cleaning is carried out and the membrane heats up from flush pump energy. In the event the maximum temperature is reached in any step the cleaning process will automatically proceed to the next step. The Flush Pump Set Points control the operation of the flush pump only during cleaning. Flush circulation time is used to ensure a thorough flush before moving to the next cleaning step. The drain time is how long the pump can run when pumping water out of the membrane back into the bioreactor. The Chemicals Set Points control how long each chemical stays in the membrane. The indicators also show how much time remains before the chemical step completes. The final Backwash time sets how much backwashing is done after a chemical cleaning. Be sure that the time is not so long that the low level in the backwash tank set point shuts down the cleaning process and prevents it from completing! The two duration indicators show the duration that the each chemical was in the membranes during the previous cleaning, not this one. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -63- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Maintenance The Maintenance screen allows you to disable certain functions while doing maintenance on the system. Figure 28. Maintenance This screen can only be reached by someone with the system password. The Horn Enabled button enables or disables the horn and light when pressed. This also disables the output of remote alarms. The Alarm Indicator in the upper right corner of all operational screens still indicates when an alarm occurs. Pressing the button again re-enables the horn and light. The system should NOT be left with the horn and light disabled. The Pushbutton For Panel Settings takes you to internal settings for the HMI display. These include setting the brightness, setting whether the screen goes blank when unattended, etc. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -64- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com The Alarm Horn Test button forces an alarm condition which will sound the horn and light, and cause the remote alarms if enabled. This alarm condition will also show up in the Alarm Indicator in the upper right corner of the display, and also will get logged on the Alarm History screen. The Current Time buttons allow you to adjust for daylight savings time if desired. The system flow totalizers show the total permeate and sludge flows since the system was started up. In the case of the permeate these are gross flows from each membrane and this number will be considerably larger than the net flow shown by the effluent flow meter. These totals can be reset here. The Pump & Equipment Hours totalizers may all be reset here if desired. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -65- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Dynalift Train This screen shows all of the operating parameters for the Dynalift membrane skid. Note that the screens are identical for either train with exception of train designation (A or B) or screen background color (pink for train A and yellow for train B). Figure 29. Dynalift Train The light blue buttons are navigation buttons that take you to other screens as indicated by their title. The numbers in titled grey boxes are real-time data displaying their current values. 1. Time Until next Backwash - indicates the time until the next backwash and how many backwashes must occur before a flush occurs. 2. Backwashes Until Next Flush – Shows the number of backwashes until a more aggressive flush and backwash will occur. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -66- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 3. FT1002A GPM – Current permeate flow rate from the A membrane skid. Note that is gross flow, and the actual flow leaving the system is less because some permeate is used for backwashes, diffuser flushing, and screen chute flushing. 4. FT1001A CFM – Air flow into the A membrane diffusers. This flow is set by the Red handled brass globe valve located on the end of the skid. It remains relatively constant at around the design flow of 60 CFM. 5. PT1001A PSI – Feed pressure to the bottom membrane header. 6. PT1002A PSI – Permeate pressure in the membranes 7. TMP PSI – Trans Membrane Pressure, the differential pressure across the membranes. There is a mounting height correction applied so it will not exactly equal PT1001A- PT1002A. 8. TT1001A F – Temperature of the mixed liquor in the membrane. 9. FT7800A GPM – Flow rate of sludge leaving the system during sludge wasting. The pump and valve tags are either red or green, indicating Closed/Off or Open/Running. The orange indicators showing here only appear on the actual screen when that function is active. The gray numerical indicators on the upper left show the time remaining until the next automatic backwash cycle and how many backwashes until a more aggressive flush and backwash will occur. The indicator on the upper right shows three possible modes, Stopped (in red), Running (in green), Cleaning (in green). The yellow button at the lower right takes you to the same screen for the B membrane skid. This is a very good screen to leave displayed when the plant is unattended. The only buttons on this screen are navigation buttons. Touching a button by accident will not start or stop anything, it will only take you to another screen. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -67- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com UF Master Control This screen controls the operation of the A train, including cleaning. Figure 30. UF Master Control The picture above shows all indicators and buttons that can appear on this screen. Some of them are hidden during operation (Cleaning operation buttons are hidden during process mode). Starting and stopping the train is done from here, and all the important data points are shown. The TMP graph helps to understand how the train is running by letting you see how the TMP changes between backwashes and flushes. The Process/Cleaning selector chooses what is being done. While both A and B train can run together, they can NOT be cleaned at the same time! When cleaning has been selected some additional indicators and buttons become visible. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -68- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com One button advances the cleaning step manually. This is useful if a cleaning was interrupted and you need to restart in the middle. The Restart Mode button lets you tell the train to go back on line after the cleaning, if the cleaning was successful. If you don’t press the button the system will sit empty following the cleaning. The indicator at the bottom left shows what step the cleaning is in. The orange warning banner over the TMP graph pops up after a power failure if automatic restart was selected on the maintenance screen. The navigation buttons take you to where you were, to set up, or the membrane screen. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -69- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com UF Operational Set Points This screen controls the normal operation of train A. Figure 31. UF Operational Set Points The feed pressure set points on the left are critical to the safe operation of the membranes. For this reason you have high and low warning alarms as well as high and low shutdown alarms. The warning alarms should be set close to the normal operation values as possible without causing nuisance alarms. The shutdown alarms should be set only a little higher and lower. The TMP set points in the center are critical to the safe operation of the membranes. For this reason you have high and low warning alarms as well as high and low shutdown alarms. The warning alarms should be set close to the normal operation values as possible without causing nuisance alarms. The shutdown alarms should be set only a little higher and lower. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -70- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com The TMP offset value set point accounts for the mounting height difference between the Feed pressure transmitter and the permeate pressure transmitter. TMP should read zero with the membranes sitting partially filled with water. Membrane Air flow is critical if it stays high or low for a long period of time (1 hour). Both of these set points shut the train down if they are reached. The permeate pump delay set point provides time for permeate flow to be established by gravity flow alone before the permeate pump tries to increase the flow. The flush pump run time set point is the maximum amount of time the flush pump can run in the event it doesn’t go off automatically by the pressure sensor indicating the membrane is empty. The low cutoff pressure set point is used to tell the flush pump the header is empty. The Backwash Interval Timer set point sets the time between backwashes. The Backwash Duration timer set point sets how long the backwash pump runs during each backwash. The Backwash Flush Counter set point determines how many backwashes will occur before the flush step in added into the backwash sequence. The Backwash Stop Duration timer set point allows a longer or shorter backwash to be used whenever the train shuts down. The Process Temperature High set point provides a warning if the mixed liquor is getting too hot. The Process Temperature Low set point provides a warning if the mixed liquor is getting too cold for the biology to work correctly. The Power Fail Auto Restart Button allows you choose whether the train auto-restarts after a power failure or waits for the operator to restart it. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -71- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com UF Data Logging This screen shows all the analog data for the membrane train. Figure 32. UF Data Logging The data shown on this screen is also being logged to the USB memory. Each day at Midnight a new file is started. The file can be opened using Excel and graphing al the data. This can be useful for troubleshooting in the future. The 16 GB USB stick holds about 3 years worth of data and the HMI puts up an alarm message if it fills up. Press UP or DOWN arrows to view available trends. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -72- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com UF Flush Pum ps Setup This screen controls Flush Pump for both trains A and B. Figure 33. UF Flush Pumps Setup The indicator shows whether the pumps are running. They only run for less than a minute about once an hour typically. The HOA buttons are for testing only. Be sure to put the pump back in auto or the train will not run. The hour meter can be reset from the maintenance screen. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -73- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com UF Sludge Valve Setup This screen controls wasting of sludge from the membrane train. Figure 34. UF A Sludge Valve Setup The sludge flow indicator shows the flow through the flow meter common to both trains. Sludge totals from the flow meter are accumulated by the PLC separately for each train. The start and stop buttons determine whether sludge wasting will occur each day. Once started sludge wasting will start every day, unless stopped. Sludge wasting starts each day at the time set on this screen. Some sludge is wasted during each flush until the Desired Sludge Waste amount is reached. This reduces the impact on the Biomass as only a small percentage of the total for each day is wasted at any one time. There are two accumulator totals, one for the current day, and one for the total for this train. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -74- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com UF Permeate Pump Setup This screen controls the permeate pump only for the membrane train. Figure 35. UF A Permeate Pump Setup The permeate pumps is driven by a VFD and the pump is controlled by a flow meter and PID loop to operate at a constant flow rate, set by the flow set point on this screen. The permeate pump is run against a constant restriction provided by a V-Port ball valve on the pump discharge. Without this restriction the membrane would gravity permeate out at a rate high than might be required. This valve must be carefully adjusted to provide a wide range of flows over the normal operating speed of the pump. The pump can be programmed to achieve three different permeate flow rates, depending on the level in the Equalization Tank. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -75- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com At low level the permeate flow rate will slow down, and at high level the pump will speed up, producing higher permeate flow rate. The runtime indicator can be reset from the maintenance screen. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -76- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com UF Permeate Pumps PID Tuning This screen controls the permeate pump only for both trains A and B. Figure 36. UF Permeate Pumps PID Tuning Either permeate pump is driven by a VFD and the pump is controlled by a flow meter and PID loop to operate The Kp, Ki, Kd, and DB set points control how the PID loop functions in controlling the pump flow. PID loop tuning is more art than science. Adjusting these set points should be left to someone skilled in the art of PID tuning. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -77- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com UF Valves Setup This screen controls the automatic valves for the Dynalift unit. Figure 37. UF Valves Setup, Page 1 Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -78- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Figure 38. UF Valves Setup, Page 2 All the valves on these screens have an indicator to show whether they are open or closed. Valves that have limit switches get this status from the limit switches. Valves that do not have limit switches indicate whether they are in the energized position or not. If a valve with limit switches is not either fully open or fully closed it will indicate an error. Be sure to always return all valves to the correct operating mode (auto) before exiting from this screen! The Bioreactor Isolation valve is located at the bottom of the Bioreactor before the strainer. It spring closes in the event of a power failure as a backup to the Membrane Feed Valve so that the biomass is not accidentally lost into the sewer. The Dynalift Feed Valve is located between the circulation pump and the membrane rack. It is spring closed and held open during normal operation. During a flush dump cycle this valve closes briefly while the membranes are drained. It operates typically once an hour. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -79- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com The Concentrate Return Valve is held open during normal operation. It only closes during the cleaning cycle to retain the cleaning chemicals in the membranes. The Dynalift Drain Valve is a spring opened valve. It is normally held closed, and opens during a power failure or when the system is stopped to drain the membranes. Note that a manual valve is provided for long term shutdowns where you don’t want a power failure draining the preservative out of the membranes. The Chemical Valve is normally closed and only opens during portions of the cleaning cycle to allow chemicals or flush water to fill the membranes. The Drain Flush valve is normally closed and opens briefly during the flush cycle to direct mixed liquor from the flush pump back into the Bioreactor. The Cleaning Valve is normally closed and opens during the cleaning cycle to direct cleaning solution circulated by the flush pump into the top of the membranes. The Vent Valve is spring closed and normally stays that way. During a backwash cycle it is opened briefly to purge air out of the permeate side of the membranes to ensure the permeate side of the membranes stay full. The Diffuser Flush valve is normally closed and opens during the backwash portion of the flush dump cycle. This allows permeate water to be forced into the diffusers to flush out any solids that may be forming. The Backwash Valve is normally closed. During a backwash the valve opens briefly to allow the backwash pump to pump permeate back through the membrane. The Permeate Valve is held open during normal operation. During each backwash cycle it closes briefly to prevent the backwash pump from pushing permeate back through the permeate pump. The Membrane Air Valve is normally closed and held open during normal operation to provide air to the membrane air diffusers. Do NOT leave this valve open with empty membranes! The air will quickly dry out the membranes doing permanent damage to them. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -80- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Anoxic Tank & Aeration This screen depicts the anoxic tank and bioreactor system. Systems A and B are identical with exception of nomenclature. Figure 39. Anoxic Tank & Aeration ORP, pH and DO setpoints can be accessed from the Main Menu screen. In addition, ORP setpoints can be accessed from the Carbon Dosing Pumps setup screen, pH setpoints can be accessed from the Caustic Dosing Pump setup screen and DO setpoints link can be found on the Blowers setup screen. Setup of the RAS pumps can be accessed from the Main Menu screen. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -81- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Anoxic Tanks Mix/RAS Pumps Setup Figure 40. Anoxic Tanks Mix.RAS Pumps Setup The Recycle Activated Sludge (RAS) pumps operate all the time, regardless whether their corresponding Dynalift train is running or not. Position of the RAS valve is determined empirically, based on ORP level in the anoxic tank. Position is set manually. Currentl y operation of the valves in HAND and AUTO position is identical. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -82- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com System Tanks Level Set Points The following setpoint screens can be accessed from the Main Menu: Figure 41. Equalization Tank Level Setpoints Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -83- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Figure 42. Post-anoxic Tank Level Setpoints Figure 43. Sludge Tank Level Setpoints Figure 44. Dosing Tank Level Setpoints Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -84- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -85- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Appendix D. Alarm List and Troubleshooting The following is a list of the alarm codes the system can generate, what they mean, and possible corrective action. 1 Rotary Brush Screen Tank High Level This alarm can be activated by both the level transmitter and the redundant high level float switch in the screenings tank for both the A and B Dynalifts. This alarm indicates that the tank is being filled by the feed pumps faster than the screenings pumps are removing the wastewater. Possible causes for this alarm are: Failure of the drum screen tank level transmitter. Failure of one or more of the screenings pumps. Check alarm history for pump related failure messages. 2 Bioreactor A High Level This alarm is activated by the level transmitter in the bioreactor. This alarm is unlikely to happen in normal operation. This alarm affects both the A and B Dynalifts as they share a split feed flow. It shuts off the screenings pumps, except if the pumps are running in hand from the HOA switch on the MCC. It could happen if: One or more of the system feed pumps in EQ tank 1 are left running in Hand from the HOA switch on the MCC. The set point for pump shutoff is set too high. 3 Bioreactor B High Level Same as bioreactor A high level above. 4 Anoxic Tank A High Level This alarm is activated by a non adjustable float switch in the anoxic tank. It is very unlikely to occur in normal operation. This alarm affects both the A and B Dynalifts as they share a split flow from EQ tank 1. It shuts off both the system feed pumps in EQ tank 1 and the screenings pumps, except if the pumps are running in hand from the HOA switch on the MCC. It might occur if: The level set points for the bioreactor were to be set to a very high level. The level transmitter in the bioreactor failed and was showing a low level when in fact the level was high. This would keep the system feed pumps running. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -86- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 5 Anoxic Tank B High Level Same as tanks A above. 6 Backwash Tank High Level This alarm is activated by both the level transmitter in the backwash tank and a redundant float switch. It is highly unlikely in normal operation since the tank overflows to discharge permeate. This alarm would indicate a blockage in the discharge pipe, or a closed valve. 7 Backwash Tank Low Level This alarm is activated by the level transmitter in the backwash tank. This alarm shuts off the backwash pump to prevent seal damage. The pump will be used again when the level rises to the Backwash Tank Reuse Level Low set point (figure 36). However this would indicate that the membranes are not being properly backwashed, which could lead to serious plugging in a short time. It can be caused by: A backwash rate greater than the permeate production rate from the membranes. A permeate reuse rate greater than the permeate production rate from the membranes. 8 EQ Tank Low Level This alarm is activated by the level transmitter in EQ tank. It would most likely be caused by leaving the system feed pump(s) in Hand position. 9 Aeration Blowes Cooling Fan Overload This alarm is activated by any overload contacts on each of the cooling fan starters in the MCC. It indicates a problem with one of the cooling fans, and the fan will be shutdown. In a short time the affected blower will overheat. Holding your hand over the cooling air outlet of running blower will identify the one that has failed. You should switch to the backup blower immediately. Opening the noise cover on the blower also may allow you to keep the blower running without overheating. If nothing is done the blower overheat switch will eventually shut the blower down, which could cause serious membrane plugging and loss of the biomass in the bioreactor. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -87- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 10 Aeration Blower Cooling Fan Failure This alarm is activated by the auxiliary contact on the motor starter in the MCC. . It can be caused by: The HOA switch being left in the Off position. The overload relay tripped in the MCC. A blown fuse on the control transformer in the MCC bucket. A burned out contactor coil A broken wire A bad output relay on the PLC IFM card A blown fuse in the IFM card, A bad output in the PLC output module itself. See the previous alarm for immediate actions to take. 11 Process Blower Overheat This alarm is activated by the overheat switch which is part of the temperature gauge mounted on top of the blower. It can be caused by failure of the blower cooling fan as described above, or by a restriction in the airflow through the blower, as would happen if the filter was very dirty. This alarm is the last defense against the blower being destroyed so it will shut the blower down. This will lead to many other alarms due to a lack of process air. 12 Process Air Bioreactors High Temperature This alarm is activated by the temperature transmitter located on the process blower air header between blowers 1 and 2. This alarm is a warning, it does not stop the blower. However if the temperature continues to rise the blower will stop when the temperature reaches the Blower Temperature High Stop set point. Blowers compress the air raising its temperature. Possible causes for this alarm are: High ambient air temperature. Significant obstruction in the air intake duct work to the blower. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -88- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 13 Process Air Membranes High Temperature Same a process air temperature A above. 14 Circulation Pump Failure to Run This alarm is activated by the auxiliary contact on the motor starter contactor in the MCC. This alarm puts the A Dynalift into Stop, to prevent the membranes from plugging. It can be caused by: The HOA switch being left in the Off position. The overload relay tripped in the MCC. A blown fuse on the control transformer in the MCC bucket. A burned out contactor coil. A broken wire. A bad output relay on the PLC IFM card. A blown fuse in the IFM card. A bad output in the PLC output module itself. This alarm functions the same as the previous alarm for circulation pump 1, except that it stops the A or B Dynalift based on which Dynalift the pump has been selected for. 15 Circulation Pump Overload This alarm is activated by any of the overloads on the circulation pumps tripping. It is informational only. The affected pump will be stopped by the Circulation Pump Failure alarm. This alarm lets you know why. 16 Circulation Pump Low Suction Pressure This alarm is activated by the suction pressure switch located between the circulation pumps and the strainer. It works for pumps 1 and 2. The causes for this alarm are: Suction strainer is clogged. One of the three valves in the suction line are closed. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -89- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 17 Drum Screen Failure to Run This alarm is activated by the current sensor located in the Safety Relay panel on the wall in the screenings room. This alarm shuts down the system feed pumps to keep them from continuing to send wastewater to the drum screen and overflowing on to the floor. The system will soon run out of wastewater and a low level in the bioreactors will shut both the A and B Dynalifts off. It indicates the drum screen is not running because: The E-stop on the Safety Panel has been pressed. The Safety Panel Start button has NOT been pressed. One of the safety switches on the drum screen doors is not detecting the magnet. The HOA switch on the MCC is in the Off position. The overload relay tripped in the MCC. A blown fuse on the control transformer in the MCC bucket. A burned out contactor coil in the MCC A burned out contactor coil in the safety control cabinet A broken wire A bad output relay on the PLC IFM card A blown fuse in the IFM card, A bad output in the PLC output module itself. The UPS in the PLC cabinet is off. A fuse in the UPS output is blown. 18 Dynalift Feed Valve Failure This alarm is activated by the limit switches in the Open/Close beacon on top of the fee d valve. It indicates that the rotation of the valve has failed to reach one of the limit switches, either open or closed. The system does not stop running. The valve should be examined immediately for problems. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -90- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 19 Test This alarm is activated by the Alarm Test touch button on the Maintenance screen. Its purpose is to test that the alarms work properly and that the horn and light can sound. The switch is a toggle, you must press it a second time to clear the alarm. 20 Dynalift Air Flow High This alarm is activated by the pitot tube differential pressure sensor located in the galvanized pipe that feeds air to the A Dynalift membranes. It is informational only. It just tells you that for some reason you are using more air than previously. This may indicate a valve has been adjusted differently. 21 Dynalift Drain Valve Failure This alarm is activated by the limit switch on top of the valve actuator. It indicates that the drain valve has not properly closed. This could result in the loss of all the biomass in the bioreactor back into EQ tank 1. For this reason this alarm shuts down the A Dynalift and closes the Bioreactor Isolation valve. 22 Dynalift Air Flow Low This alarm is activated by the pitot tube differential pressure sensor located in the galvanized pipe that feeds air to the A Dynalift membranes. It indicates that the membranes are not getting enough air and plugging may be occurring. The rotameters near the blowers indicate the actual air flow in CFM. This condition may be caused by: Low process blower pressure. A closed valve. Plugging of the membrane air diffusers. 23 Dynalift SHUTDOWN! High Trans-Membrane Pressure This alarm is sensed by the PLC calculating the difference between the membrane feed pressure and the membrane permeate pressure. This pressure difference is what drives the permeate through the membrane. A high TMP indicates fouling of the membrane, and can lead quickly to plugging. The usual course of action is to chemically clean the membranes using the automated cleaning process. This alarm puts the A Dynalift into stop. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -91- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 24 Backwash Pumps Overload This alarm is activated by the overload relay located in the MCC. It indicates that the backwash pump has overloaded. Since the backwash pump actually pumps only very clean permeate and runs for just 5 seconds it is unlikely to get thi s alarm in normal operation. It could be caused by: Something broken inside the pump, like a seized bearing. One fuse blown in the MCC which single phases the motor. 25 Backwash Pump Failure to Run This alarm is activated by the auxiliary contact on the motor starter in the MCC. It indicates the backwash pump has failed to run. This could be caused by: The HOA switch on the MCC is in the Off position. The overload relay tripped in the MCC. A blown fuse on the control transformer in the MCC bucket. A burned out contactor coil in the MCC. A broken wire. A bad output relay on the PLC IFM card. A blown fuse in the IFM card. A bad output in the PLC output module itself. 26 Dynalift SHUTDOWN! Low Permeate Flow This alarm is activated by the flow meter on the backwash skid. It may be caused by: The HOA switch for the permeate pump on the MCC is in the Off position. The permeate pump is in disabled mode. A clogged or defective flow meter. A blown fuse on the control transformer in the MCC bucket. A broken wire. A bad output relay on the PLC IFM card. No analog (4 to 20 ma) speed signal from the PLC. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -92- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com A blown fuse in the IFM card. A bad output in the PLC digital output module or analog output module 27 System feed Pumps Overload This alarm is activated by any of the overloads tripping for the system feed pumps in EQ tank 1 and 2. You will also get a failure to run alarm for the specific pump, so this alarm helps you troubleshoot that problem. This alarm may be caused by: Clogging of the system feed pump. A bearing failure in the pump. 28 System feed Pump Seal Failure This alarm is activated by a sensor inside the system feed pump. It works by sensing the resistance across two probes. Water reaching the probes shorts them out and the sensing relays in the MCC then trigger the alarm. The pump with the failed seal should be disabled and removed from the EQ tank immediately before more serious damage can occur. 29 System feed Pump Failure to Run This alarm is activated by the auxiliary contact on the motor starter in the MCC. It can be caused by: The HOA switch on the MCC is in the Off position. The overload relay tripped in the MCC. A blown fuse on the control transformer in the MCC bucket. A burned out contactor coil in the MCC. A broken wire. A bad output relay on the PLC IFM card. A blown fuse in the IFM card. A bad output in the PLC output module itself. 30 Screen Transfer Pumps Overload This alarm is activated by any of the overloads tripping for the pumps in the screening tank. You will also get a failure to run alarm for the specific pump, so this alarm helps you troubleshoot that problem. This alarm may be caused by: Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -93- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Clogging of the pump. A bearing failure in the pump. A broken wire feeding the pump. Overload relay set too low for motor rating. 31 Screen Transfer Pump Failure to Run This alarm is activated by the auxiliary contact on the motor starter in the MCC. It can be caused by: The HOA switch on the MCC is in the Off position. The overload relay tripped in the MCC. A blown fuse on the control transformer in the MCC bucket. A burned out contactor coil in the MCC. A broken wire. A bad output relay on the PLC IFM card. A blown fuse in the IFM card. A bad output in the PLC output module itself. 32 Dynalift SHUTDOWN! Bioreactor Low Level This alarm is activated by the submersible level transmitter in the Bioreactor A tank. The set point should be set below the lowest system feed pump turn on point. This alarm also puts Dynalift A into Stop mode to prevent losing all the biomass, or concentrating up the MLSS to a level that plugs the membrane. This alarm may be caused by: Pumping off sludge without shutting the A Dynalift down. Failure of one or more of the system feed pumps. Failure of the rotary screen. Failure to restart the rotary screen after servicing. Failure of one or more of the screening pumps. A valve left close in the piping from the screening pumps to the anoxic tank. Failure of the level transmitter in the bioreactor. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -94- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 33 Dynalift High Permeate Flow This alarm is activated by the flow meter on the backwash skid. It is highly unlikely to get this alarm in normal operation. It is provided simply so you can bracket your normal flows with alarm points in the event something unusual were to occur. It can be caused by: Alarm set point too low for normal operational fluctuation. Permeate pump in Hand with flow rate set high. Permeate flow setting set points too high. An unused alarm point in the Dialer Critical indicator pages. 34 Bioreactor A High Air Flow This alarm is activated by the pitot tube differential pressure transmitter located in the galvanized pipe feeding process air to the bioreactor. This alarm could be caused by: Low level in the bioreactor. Broken or missing diffusers in the bioreactor. 35 Dynalift Low Trans-Membrane Pressure This alarm is sensed by the PLC calculating the difference between the membrane feed pressure and the membrane permeate pressure. This pressure difference is what drives the permeate through the membrane. A low TMP alarm can be caused by: Alarm set point too high for low flow TMP conditions. Failure of the Membrane Feed Pressure transmitter. Failure of the Permeate Pressure transmitter. Failure of the Permeate Pump Failure of the Circulation Pump. 36 Bioreactor Low Air Flow This alarm is activated by the pitot tube differential pressure transmitter located in the galvanized pipe feeding process air to the bioreactor. This alarm could be caused by: Closed or poorly adjusted valves in the galvanized piping to the bioreactor. An increase in the level of the bioreactor which raises the pressure needed to push air into the bioreactor. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -95- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Clogged diffusers in the bioreactor. Low air pressure in the process air header Failure of the process air blower. Alarm set point too high for normal flow change due to automatic valve operation. 37 Anoxic Tank High ORP This alarm is activated by the ORP sensor in the side of the Anoxic Tank. This alarm may be caused by: High DO in Bioreactor. Excessive air to the membranes. Lack of carbon to feed bacteria. 38 Bioreactor Low Level This alarm is a warning activated by the submersible level transmitter in the Bioreactor A tank. The set point should be set below the lowest system feed pump turn on point. This alarm may be caused by: Pumping off sludge without shutting the A Dynalift down. Failure of one or more of the system feed pumps. Failure of the rotary screen. Failure to restart the rotary screen after servicing. Failure of one or more of the screening pumps. A valve left close in the piping from the screening pumps to the anoxic tank. Failure of the level transmitter in the bioreactor. 39 Anoxic Tank Low ORP Low DO in Bioreactor. Lack of adequate mixing in Anoxic Tank. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -96- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 40 Bioreactor Low Dissolved Oxygen This alarm is activated by the Dissolved Oxygen (DO) transmitter in the Bioreactor A tank. Under normal operation the DO level wanders up and down between the DO high set point and the DO low set points. This alarm may be caused by: A system disturbance such as starting the system up, or shutting it down for maintenance. Bioreactor air pulse valves in Hand (closed) Pulse valve limits set wrong. Failure of the open pulse valve. Failure of the bioreactor air blower. Out of calibration DO transmitter. The DO transmitter has an electrolyte filler that must be replaced periodically. 41 Bioreactor High pH This alarm is activated by the pH transmitter installed on the side of the bioreactor A near the platform. Under normal operation the pH of the incoming waste water is slightly above 7.0. A caustic injection system has been provided to compensate for possible low pH but is most likely not needed. If the injection system is running then the like causes of this alarm would be: pH set point too high. Caustic pump stroke set too high. Caustic pump PID loop not tuned properly. 42 Dynalift Circulation Pump Low Suction Pressure This alarm is activated by the pressure transmitter in the circulation pump suction header. It can be caused by: Strainer clogged. Strainer valve closed. Set point too high. Bioreactor isolation valve closed Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -97- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 43 Bioreactor High Dissolved Oxygen This alarm is activated by the Dissolved Oxygen (DO) transmitter in the Bioreactor A tank. Under normal operation the DO level wanders up and down between the DO high set point and the DO low set points. This alarm may be caused by: A system disturbance such as starting the system up, or shutting it down for maintenance. Air pulse valves in Off (open). Air pulse valve limits too high or too wide. Out of calibration DO transmitter. The DO transmitter has an electrolyte filler that must be replaced periodically. 44 Dynalift SHUTDOWN! High Feed Pressure This alarm is activated by the pressure transmitter located at the center of the feed header on the membrane rack. In normal operation the pressure here is reduced to a little less than the static head required (about 5.06 psi) to overflow water into the top header, because the air injected at the bottom of the membrane makes the water less dense. This alarm could be caused by: Loss of air flow to the membrane rack. Plugging of the membrane which increases the resistance of water flow through the membranes. Failure of feed pressure transmitter. 45 Dynalift Low Feed Pressure This alarm is activated by the pressure transmitter located at the center of the feed header on the membrane rack. In normal operation the pressure here is reduced to a little less than the static head required (about 5.06 psi) to overflow water into the top header, because the air injected at the bottom of the membrane makes the water less dense. This alarm could be caused by: Clogged suction strainer on circulation pump inlet. Closed Bioreactor Isolation valve. Circulation pump failure, or worn impellor. Feed valve failure. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -98- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Drain valve failure in the open position. Very low level in the Bioreactor. 46 Dynalift High Permeate Pressure This alarm is activated by the pressure transmitter located at the center of the permeate header on the membrane rack. This alarm is likely only during the backwash cycle which occurs frequently. During the backwash cycle the permeate valve on top of the backwash skid closes, the backwash valve opens, and the backwash pump starts, forcing permeate backwards through the membrane. The butterfly valve above the backwash pump is throttled to keep the backwash pressure not more that 14.7 psi to avoid damaging the membrane. This alarm can be caused by: The backwash pump throttling valve is too far open. The membrane is very badly fouled (TMP would be very high) Membrane is badly plugged. 47 Dynalift Low Permeate Pressure This alarm is activated by the pressure transmitter located at the center of the permeate header on the membrane rack. The permeate pump on the backwash skid pulls permeate out of the membrane skid, except during backwash. This alarm could be caused by: Excessive permeate flow rates. Badly fouled membranes. 48 Permeate Pump High Pressure This alarm is activated by the pressure transmitter located in the discharge pipe above the permeate pumps on the backwash skid. The permeate pump pumps permeate into the backwash tank through a diaphragm valve at the top of the backwash skid that provides some back pressure so that the permeate won't just gravity flow through the pump into the backwash tank at a rate greater than desired. This alarm can be caused by: Very high permeate rate. Permeate flow control diaphragm valve closed too far. Permeate pump HOA switch in Hand and speed set high. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -99- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com 49 Permeate Pump Low Pressure This alarm is activated by the pressure transmitter located in the discharge pipe above the permeate pumps on the backwash skid. The permeate pump pumps permeate into the backwash tank through a diaphragm valve at the top of the backwash skid that provides some back pressure so that permeate won't just gravity flow through the pump into the backwash tank at a rate greater than desired. This alarm can be caused by: Very low permeate rate. Permeate flow control diaphragm valve opened too far. Failure of the permeate pump 50 Process Air Bioreactor High Pressure This alarm is activated by the pressure transmitter located on the Bioreactor process air header behind the blowers. This transmitter controls the speed of the blower selected for the bioreactors to maintain a constant pressure. A high pressure alarm could be caused by: The alarm set point is too low. The blower set point has been raised. The PID loop is poorly tuned. Valves closed on the lines going to the bioreactors. Blower HOA switch in hand and speed set too high. Failure of the blower relief valve. 51 Process Air Membrane High Pressure This alarm works the same as Process Air Bioreactor High Pressure above (alarm 114). 52 Process Air Bioreactor Low Pressure This alarm is activated by the pressure transmitter located on the process air header behind the blowers. This transmitter controls the speed of the blower to maintain a constant pressure. A low pressure alarm could be caused by: Blower pressure set point too low. Alarm set point too high. Operations and Maintenance Manual Ultrafilter Wastewater Treatment System -100- DYNATEC SYSTEMS, INC.• 909 Jacksonville Road • Burlington • New Jersey • 0 8016 • (609) 387 -0330 • FAX (609) 387 -2060 www.dynatecsystems.com Failure of blower relief valve. Failure of blower to run. Valves opened to bioreactor and membrane so far that the blower cannot keep up. 53 Process Air Bioreactor Low Pressure This alarm works the same as Process Air Bioreactor Low Pressure above (alarm 119) 54 Effluent Pump Failure to Run This alarm is activated by the run contact on the motor starter in the MCC bucket for this pump. the alarm could be caused by: MCC bucket switch turned off. MCC HOA switch in off position. Over load relay tripped. A failure of the battery charging circuit to recharge the battery. 55 E-STOP Pressed This alarm is activated by pressing the E-stop. It is included merely to log in the alarm history that someone pushed the E-stop. This may help explain an unintended shut down for which no other cause can be found. E n v i r o l i n k THE COTTAGES OF BOONE WWTP AND ENVIROLINK, INC. OPERATION AND MAINTENANCE MANUAL Cottages of Boone Wastewater Treatment Facility Residuals Management Plan This document serves as The Cottages of Boone Wastewater Treatment Facility Residual Management Plan and will remain on site at the wastewater treatment facility for review by The State of North Carolina DEQ personnel. The Cottages of Boone wastewater facility pumps sludge from the activated sludge treatment process to its onsite 36,166-gallon aerobic digestion storage tank for further treatment to meet the 503 Regulations. The treatment process currently sends about 1000 gallons of sludge daily to the digester holding tank and is aerated for proper treatment. The air is periodically turned off and the sludge is allowed to settle, and the supernate is decanted from the tank to allow more room in the digester. This process is continued until the tank reaches the 70% full mark and can no longer be decanted. Once the digester holding tank reaches the 70% full mark, the operator will schedule to have the tank emptied by contracted pump companies. The following companies are approved to haul digested sludge from the Cottages of Boone digester to the City of Boone wastewater treatment facility for final disposal.  A1 Appalachian Pumping - (828) 264-2450 124 Cheyenne Ln Boone, NC 28607  Triple T Pumping - (828) 262-5745 1372 NC-194 Boone, NC 28607 Doby's Septic — (336) 982-3629 712 S. Jefferson Ave West Jefferson, NC 28694 All records of pumping activities including, date, time, gallons removed, location of final disposal, and company performing the hauling activities will be kept on site at the wastewater treatment facility for no less than 5 years. The Cottages of Boone WWTP PROCEDURES FOR CLEANUP AND REPORTING OF SEWAGE SPILLS PURPOSE: To protect the citizens of North Carolina, and the environment by ensuring a timely and thorough response to Sanitary Sewer Overflows (SSOs) and Bypasses from the treatment facility. SCOPE: This procedure applies to The Cottages of Boone employees or contractors that, in the course of their work may deal with SSOs and bypasses. At a minimum, these procedures will be reviewed on an annual basis or whenever revised guidance from state or federal authorities dictate a revision is necessary. REFERENCES: A. 40 Code of Federal Regulations (CFR) Part 122-124. The Clean Water Act, 1969. B. North Carolina General Statute 143.215.1 C. Title 15A, North Carolina Administrative Code, Subchapter 2H .0100-.0200 D. Title 15A, North Carolina Administrative Code, Subchapter 2T Section .0500 E. Title 15A, North Carolina Administrative Code, Subchapter 2B .0506(a) F. NC DEQ Wastewater System Permit # WQ0035784. RESPONSE TIME REQUIREMENTS: Utility Outage or Spill Response Time: Upon notification of a spill or utility outage in the collections system or treatment plant, Envirolink, Inc. shall respond and take action to safeguard life and the property during business hours and non-business hours. NOTIFICATIONS: Per Condition IV.13 of the Permit, any spill that reaches surface waters must be reported by telephone to the Winston-Salem Regional Office at (336) 776-9800 as soon as possible, but in no case more than 24 hours. The following procedures also all for sewage spill of 1,000 gallons or more to surface waters of the State, per N.C.G.S. 143.215.1C. (Note: Conveyances such as drainage ditches and storm sewers are considered waters of the State).  For discharges of 1,000 gallons or more of untreated wastewater to surface waters, issue a press release within 48 hours of first knowledge to the Newspaper.  For discharges of 15,000 gallons or more of untreated wastewater to surface waters, shall publish a public notice captioned "NOTICE OF DISCHARGE OF UNTREATED SEWAGE" within 10 days after NCDEQ has determined the counties that are significantly affected by the discharge and approved the form and content of the notice and the newspapers in which the notice is to be published. See N.C.G.S. 143.215.1C for additional information. REPORTING SSOs: Before any SSO or bypass is reported to the State, the ORC or the Backup ORC must visit and evaluate the spill site within 24 hours. Once the spill site has been evaluated by the ORC or the Backup ORC, the responsible person should discuss the spill, determine estimated volumes and causes before calling the Division within the 24 hour time frame. Containment Upon learning of such an occurrence, the first priority shall be to assess the situation and mobilize resources necessary to remove the blockage or untreated discharge, contain the SSO, and stabilize the overflow condition to the max extreme. Notification should be made to the ORC at this time. As soon as the extent of the SSO or bypass has been determined, a containment berm or a dam should be established at the lower edge of the SSO or bypass, or at an area that meets the needs of containment and clean up operations. The containment dam should be large enough to prevent breaching in dry weather conditions. Force Main or Inaccessible Gravity Sewer Spill In the event a spill occurs at a pump station with no bypass capability or at a force main or gravity sewer where no access to a dump point exists, pump and haul or bypass operations will be considered. Where pump and haul operations are deemed the best solution, sewer will be collected from the closest tanker access point for continuous loading operations while causing minimum environmental damage. Consideration should be made for traffic control, noise, access, etc. 24 hour Pump Service Providers & Repair 1. Godwin Pumps Phone # 919-795-9020 2. Blue Ridge Motor Repair Phone# 828-258-0800 3. Charles R Underwood Phone# 919-775-2463 24 hour Pump and Haul Tanker Services 1. Triple T Phone# 828-262-5745 2. Appalachian Pumping Phone# 828-265-6540 3. Doby's Septic Phone# 336-846-3629 4. Envirolink, Inc. Phone# 252-235-4900 **See attached Pump and Haul Record Form-Complete for each load For Spills involving Asphalt or Concrete 1. Set up containment at or near any threatened storm drainage system; Every attempt should be made to prevent the spill from entering the drainage structures. 2. Spread dry sand or absorbent material to a depth of 1 inch. Let stand for one hour and sweep up. If moisture or grease is still present, repeat. 3. After removing the contaminated material, wash down the area with high water pressure and a mild bleach solution and then pump residue back into the sewer system. 4. If the spill enters a storm drainage structure, a Reportable Spill has occurred and therefore a Spill Report should be filed with NC DEQ and treated as a SSO affecting Waters of the State. Reported volumes would include the initial estimated spill; plus any flush water used; minus the calculated amount removed from storm drain system. SSO or Bypass affecting Waters of the State I. Take conductivity and dissolved oxygen readings of the receiving stream to determine the proper placement of a darn within the intervals on the Conductivity Readings Form. While taking the conductivity readings, be sure to notate them on the Spill & Conductivity Reporting Form. The dam needs to be constructed near a manhole or at a location which is accessible to the jet/vacuum truck. Placement of the dam should be at a point where the lowest conductivity reading is measured. 2. Build the dam using dirt that is capable of handling creek and hydrant flow without breaching during dry weather conditions. Position two pumps at the darn capable of handling creek and hydrant flow with one pump in use and the second as backup. Have a backhoe at the site with additional material at all times so that the earthen dam can be rebuilt if a breach does occur. Pump SSO release from the dam into the manhole. 3. Put up warning tape, "Danger Do Not Enter" from the SSO site to the pump site on both sides of the creek in populated areas. In unpopulated areas restrict access where there is any chance of human contact with the SSO. 4. Flush the stream with de-chlorinated water from a sufficient number of hydrants to remove the waste product from the creek. Continue to pump and flush the stream until the conductivity measurements or readings are equivalent to upstream receiving stream or hydrant water conductivity readings, whichever is higher. Make sure that all readings taken during cleanup are recorded on the Spill & Conductivity Reporting Form and taken within the intervals on the form. 5. If there is rip-rap in the creek, wash down with high water pressure until there is no noticeable waste residue remaining on or within the rip-rap structure. 6. If the creek flows into a body of water used for recreation and/or drinking water supply, notify the affected officials as soon as possible. 7. Continue periodic monitoring of conductivity and Dissolved Oxygen readings. All additional readings should be notated on the Spill and Conductivity Reporting Form. Take an upstream and downstream fecal coliform every 24 hours as needed until the waterway is restored to pre-event condition. SSO not reaching Waters of the State I. In open areas spread powdered lime heavily over the spill site, till into the ground and then repeat the procedure again but not within 24 hours of predicted rain fall event. Seed the disturbed area and place straw over the tilled area. Soil may need to be removed and replaced with clean fill material for a large spill where the ground has become saturated. SSO REPORTING PROCEDURES I. Upon discovery of a possible SSO or bypass, notify the ORC or Back up ORC David Rogers (ORC) Cell# 828-734-1314 Matthew Hukill (Area Manager) Cell# 704-775-6128 Madelyn Mills (Public Notification Coord.) Office# 984-365-9160 2. The individuals listed above will be the Point of Contact between The Cottages of Boone and NC DEQ or the Division of Emergency Management on SSO or bypass matters. These individuals will report overflows from any sewer line or pump station, or the bypass of any wastewater treatment system or any component thereof If Media communications become apparent, the Executive Director will be the POC for all Media questions. 3. Reportable spills must be called into NC DEQ (336-776-9800) within 24 hours of first knowledge of discharge. Document on the Spill Report Form the date, time, incident number and person contacted. 4. During weekends and holidays when DEQ cannot be reached, The Division of Emergency Management will be called at 1-800-858-0368 providing the information requested. Document on the Spill Report Form the date, time, and person contacted. Upon arriving to work after the weekend or a holiday, DEQ should be contacted to receive the incident number for the reported spill. 5. The ORC/Backup ORC should be notified immediately so they have an opportunity to visually see the spill. This will allow the ORC/Backup ORC to provide better estimated volumes. The ORC or the Backup ORC is also required by the Collection System Permit to visit the spill site. 6. The ORC/Backup ORC must fill out the State approved Sanitary Sewer Overflow Form. A legible copy will be faxed within five (5) days to NC-DEQ, Winston Salem Regional office (336-776-9800). If the Director of Operations is unavailable, the ORC will ensure that the necessary paperwork is completed. Records of spills, including those that are not required to be reported will be maintained for at least three (3) years and will be made available to NC-DEQ staff upon request. AVAILABLE MATERIALS FOR SSO Portable Generators Drop Cords Portable Electric Lights Electric Submersible Pumps Gas Mud Pumps Powdered Limestone Fire Hose Sections 6" By-Pass Pump Sewer Jet Vacuum Truck Tractor Backhoe Dump Trucks Flex Suction/Discharge Hose Air Compressor Lime Water Quality Stream Monitoring Devices Dissolved Oxygen/pH/Conductivity Meter SSO TELEPHONE CONTACT NUMBERS NC-DEQ (Winston Salem Regional Office) 336-776-9800 NC Division of Emergency Management 1-800-858-0368 Envirolink, Inc. 252-235-4900 David Rogers (ORC) 828-734-1314 Christy Hodgen, (Manager, Cottages of Boone) 601-900-3599 Madelyn Mills (Public Notification Coordinator) 984-365-9160 Spill and Conductivity Reporting Form Location of Spill: _____________________ Time of Spill: ______________ AM or PM Time of Clearing Spill: ________ AM or PM Date of Spill: Date of Clearing Spill: _______________ Cause of Spill: __________________________________________________________ Did spill reach surface water?: Time ORC was notified: Conductivity/DO Readings Initial DO Initial Conductivity 2nd DO 2nd Conductivity 3rd DO 3rd Conductivity Entry Point Time Recd. 50' Downstream Time Recd. 100' Downstream Time Recd. 150' Downstream Time Recd. 200' Downstream Time Recd. 250' Downstream Time Recd. **Note: 2nd and 3rd readings are to be taken during cleanup. **More readings may be necessary depending upon the size of the spill and the time period in which the stream is being flushed to maintain water quality. Pump and Haul Record Date: Page of Tanker Company Tanker Capacity Drivers Name License Plate# Destination Time Loaded Spill Incident Report Form Facility: _________________________ Incident# ________________ Owner: The Cottages of Boone Region: Winston Salem Regional Office City: _Boone _________________________County: Watuga ________________ Source of SSO __________ Sanitary Sewer _________ Pump Station Specific Location of SSO (example: Lift Station # 1, manhole on Main Street, etc) Incident Start Date: Time: AM or PM Incident End Date: Time: AM or PM Estimated Duration rounded to the nearest hour __________ hour(s) Estimated volume of the SSO ___________ gallons Did SSO reach surface waters? _____ Yes _____ No Volume reaching surface water ______ gallons Surface Water Name Did the SSO result in a fish kill? If so, what is the estimated number of fish killed? Specific Cause of the SSO: Natural Disaster _______ Grease _____________________ Roots __ Inflow & Infiltration ____ Pump Station Equip Failure _____ Power Outage Vandilism Debris in Line _______________ Other Explaination: ________________________________________ Immediate 24-hour verbal notification reported to: (Name) ______________________________________ ____ DEQ ________ Emergency Management Date: Time: AM or PM Safety Standard Operating Procedures For Envirolink, Inc. 1.0 PURPOSE: The purpose of this document is to clearly define objectives and safety standards for Envirolink, Inc. operations personnel and The Cottages of Boone wastewater facility. These objectives and quality standards are established as a framework to effectively carry out Envirolink, Inc.'s safety protocol and safety of the system. SAFETY MEASURES Quality Standards  All signage, gates, and security systems shall be inspected monthly. Deficient signs and/or post shall be identified to the client in writing within 24 hours.  Sign obstructions such as weeds, trees, shrubs, or other debris will be identified to the client within 24 hours.  Any damage or depreciation of signs, gates, and security Safety Equipment  Safety glasses  Safety toe shoes  DOT Class 3 Safety Vest  Hearing Protection  Work Gloves Dos and Don'ts  Never operate equipment on slopes greater than 15'  Never mow on wet grass. Tires may lose traction causing loss of control  Never place hands or feet near rotating parts or under machine  Never wear loose clothing or jewelry  Always wear required PPE  Always maintain unit is a safe operating condition Quality Standards  Supervisors will ensure all personnel are trained in all safety procedures.  Staff will be certified prior to operating any equipment Safety SOP Created By: DLS Version: 01 SOP# Approved By: Date Created: Hazard Identification  Slips, Trips & Falls from debris, wet surfaces uneven terrain ...etc..  Traffic  Sharp waste material such as glass, nails, sticks ...etc.  Seasonal Hazards (Temperature, Ice/Snow, Storms) Safety SOP Created By: DLS Version: 01 SOP# Approved By: Date Created: THE COTTAGES OF BOONE ONSITE WASTEWATER SYSTEM NOTES SITE NOTES: 1. PROJECT ADDRESS: 615 FALLVIEW LANE, BOONE, NC 2860E 2, TOTAL ACREAGE: 50.3MACRES 3. DEED BOOKAND PAGE: 1921, 0464 4, PROJECT PIN NUMBER(S): 2900-22-8691 S. EXISTING TOPO INFOSHOWN WAS PROVIDED BY: BROOKS ENGINEERING ASSOCIATES, PA 6. EXISTING BOUNDARY INFO PROVIDED BY: BROOKS ENGNEERING ASSOCIATES, PA 1. LATITUDE / LONGITUDE: 36.2D5133, 41.103993 GENERAL NOTES: 1. CONTRACTOR SHALL PROTECT ADJACENT PROPERTIES, THE GENERAL PUBLIC AND ALL OF THE OWNER'S FACILITIES AND SHALL BE RESPONSIBLE FOR THE REPAIR OF ALL DAMAGES WHICH OCCUR DURING CONSTRUCTION. 2. LOCATION OF ALL EXISTING UTILITIES, AS SHOWN HEREON, ARE APPROXIMATE ONLY. NO GUARANTEE IS MADE OR TAME 0 BY THE LOCATION REFLECTED IN THE PLANS. IT IS THE CONTRACTOR'S RESPONSIBILITY TO VERIFY THEME, SIZE AND LOCATION OF ALL UTILITIES AND OTHER FEATURES WHICH MAY AFFECT CONSTRUCTION OR THE INTENDED FUNCTION OF THE DESIGN. CONTRACTOR SHALL NOTIFY DESIGNER PRIOR TO CONSTRUCTION IF EXISTING CONDITIONS DIFFER FROM THAT INDICATED IN THE PLANS. 3. NOS TREAM OR WETLAND DISTURBANCE SHALL OCCUR WITHOUT A ARMY CORPS OF ENGINEERS PERMIT. 9. THE ESCAPE OF SEDIMENT FROM THE SITE SHALL BE PREVENTED BY THE INSTALLATION OF EROSION CONTROL MEASURES AND PRACTICES MUOR TO, OR CONCURRENT WITH, LAND DISTURBING ACTIVITIES. 5. ANY EXCESS CUT MATERIAL DEVELOPED IN THE CONSTRUCTION OF THIS SITE SHALL BE DISPOSED OF QI AN APMROPMTELY PERMITTED SPOIL SITE. CONTRACTOR TO PROVIDE PROOF OF PERMITS PRIOR TO CONSTRUMDN. 6, ANY ALTERATION TO THE PUNS MUST BE APPROVED BY THE PROJECT ENGINEER, OR APPROPRIATE AGENCY PRIOR W THE COMMENCEMENT OF WORK. 1, THE CONTRACTOR SHALL OBTAIN, AND PAY FOR, PRIOR TO BEGINNING ANY WORK, ALL PERMITS AND LICENSES NECESSARY TO ACCOMPLISH THE WORK. 8. CONTRACTOR(5) SHALL BE RESPONSIBLE FOR ADEQUATE SUPERVISION TO PREVENT DAMAGE AND MOVEMENT FROM EQUIPMENT WORKING AROUND CONSTRUCTION STAKES, THESE CONSTRUCTION STAKES SHALL REMAIN IN PLACE AND BE PROTECTED UNTIL OWNER APPROVES THEIR REMOVAL. ANY STAKES THAT HAVE BEEN DISPLACED AS A RESULT OF CONSTRUCTION ACTIVITY ARE TO BE REPLACED BY A LICENSED LAND SURVEYOR ENGAGED BY THE CONTRACTOR AT NO COST TO THE OWNER. 9. THE ENGINEER WILL NOT BE CONTINUOUSLY PRESENT IN THE FIELD, IT IS SPECIFICALLY UNDERSTOOD THAT HE DOES NOT UNDERTAKE NOR ASSUME ANY OBLIGATION FOR SUPERVISION OF CONSTRUCTION, SAFETY MEASURES TAKEN DURING THE COURSE OF CONSTRUCTION, RESPONSIBILITY FOR SCHEDULING THE WORK FOR INSURING COMPLETE COMPLIANCE WITH THE CONTRACT DOCUMENTS AND/OR ALL CODE REQUIREMENTS, RULES AND REGULATION OF ANY PUBLIC OR PRIVATE AUTHORITY HAVING JURISDICTION OVER THE WHOLE OR ANY PART OF THE WORK. MAMMON, THE ENGINEER NETTHER UNDERTAKES, ASSUMES, NOR GUARANTEES THE WORK AND/OR PERFORMANCE OF THE CONTRACTOR. INSPECTION SCHEDULE: 1. NO CONSTRUCTION SMALL COMMENCE PRIOR TO A PRECONSDLUCTION MEETING WITH THE OWNER, THE CONTRACTOR, THE ENGINEER, AND A REPRES MTATIVE OF THE APPROVING JURISDICTION. 2. ALL SHOP DRAWINGS SHALL BE SUBMITTED AT OR PRIOR TO THE PREWNSTRUCTION MEETING. 3. ENGINEER TO BE CALLED FOR PERIODIC INSPECTIONS. 4, CALL ENGNEEMNG PRIOR TO COVERING UNDERGROUND STRUCNREE FOR MNAL MSPECRONS, 5, REFER TO MANUFACTURERS SPEOMCATION MANUAL AND STATE AND LOCAL STANDARDS FOR AODITIONAL REQUIREMENTS AND STANDARDS. PROJECT MAP � o e 'H d APARTMENTS WATAUGA COUNTY 3 � ccc �Eff# CONTACTS R i CLIENT: 6 ENVIROLINK, INC. ENGINEER: BROOKS ENGINEERING ASSOCIATES, PA )ONE TO UNVILLEi\ NC 705 PROJECT SITE NC/y NC 321 NTS VICINITY MAP NC 705 \ T O epONf Qo a� SI TE ��' , MR w♦ / ' `e B N.T.S. SURVEYOR: BROOKS ENGINEERING ASSOCIATES, PA NO.: TITLE: WO C EET PROCE955{d1EM4Tl^6 XYDMU CONTACTINFO: DON FELLER OFELLER V E NVIROLIN KINCCOM 4700 HOMEWOOD COURT SUITE 108 RALEIGH, NC 21609 CONTACTINFO: MARK BROOKS, PE MBROONS®BROOKSBA.COM 828-2T14100 15 ARLINGTON STREET ASHEVILLE, NC 2880E IIdu'CS€><f7i 1* PSEXTONGBROOKSEA,CON 82823E-9hJ0 15 ARLINGTON STREET ASHEVILLE, NC 28801 SHEET INDEX NO.: TITLE: IC. -LE .a ^ KEYNOTES: Oco O O ( 1 EQU0.LRARON TANK. 'iO CU U n L /� PROPOSED 4':2':4" PVC SOH. 10 SUPPLY LINE FROM EQUALQARON TANK TO INFLUENT SCREEN. OINFLUENT SCREEN. ® BLOWERS. OSCREENING PUMPSKID. © MAIN POWER SUPPLY PANEL AND BACK UP POWER TRANSFER SWITCH. O(2) ANOXIC REACTOR TANK. O(2) AEROBIC REACTOR TANK. OPOST ANOXIC REACTOR TANK. 10 MEMBRANE ENID ASSEMBLY. SS MEMBRANE CIRCULATION PUMP SKID. 12 CHEMICAL FEED SKID. 13 BACKWASH SKID AND PERMEATE TANK. 14 UV SYSTEM. Q-11-DIMETER. 1 IRRIGATION DOSE FILTRATION AND PUMP SKID, / S IRRIGATION DOSE TANK. / SB 2'x2' FL00R DRAIN (TYP.). / 19 9' PYC DRAIN PIPE FROM FLOOR D-TO SUMP PUMP. ® TANK85UMPPUM1 / Q 2" SCH. 40 PVC FROM GRINDER/SUMP PUMP TO EQUALIZATION TANK. / ®Z 2" PVC DRAIN LINE FROM S-DAY UPSET TANK TO EQUALIZATION TANK, QV PVC OPAIN LINE FROM L.DAY WET WEATHER TANK TO DOSE TANK. ® RAINWRDT" RAIN GOUGE TO INITIATE WET WEATHER STORAGE. / /WASTE WATER TREATMENT BUILMW(BY OTHERS). AL z6 36" STANDARD MANHOLE FOR PIPING ]UNCTION. 1" WATER LINE TO WWTF. QFREEZELESSWATERNYORANT. FAD (BY OTHERS). SWMPSTE0. 0 RETAINING WALL (BY OTHERS). 3S W M STORMWATER DRAIN PIPE, 2 10" ADS STORM INLET 0YP.). 33 YARD INLET CTYP.). 3 18" DRAINAGE HDPE PIPE. pSECURITY FENCING, 36 SLUDGE HOLDING TANK. BACKUP ZO W GENERATOR. PROPOSEDORBINOXMODEL20-3636RATRACTUATEDVALVE. / /') 3g PROPOSED 90% OUTLET PIPE, 2" SCH ED PVC WITH GATE VALVE AT O CONNECTION. PROPOSED 4" DRAIN LINE FROM DRUM SCREEN ROOM L41/ PROPOSED T" LINE FROM 90%OUTLET PERE TO TANK B SUMP PUMP SCALE 1"=10' o• ID• zo' ao "yP N CAR02 9.,-. "•.T,"9gRc.tG,.ec t ((:DD g 1 1 Ml l ' W Q fir W W Oj o _ E / B W \/\ W W C z W !7 z a W U W 51 W W ~ Z Z 0 O goo g g O U ¢ h Lu c7 lu cl W U O Q W W W HE U ~�3 U N T CM ¢ Z Qn` ut°i o EQUALIZATION FORCE MAIN FROM TANK COLLECTION SYSTEM 1= AVG, FLOW = 72.9 GPM PEAK FLOW = 145.8 GPM SCHEMATIC FLOW DIAGRAM NTS 15 GPM (S MIN.) — BACK FLUSH LINE FROM DISC FILTER MBR TURBIDI. IRRIGATION METER DOSE TANK U.V.362 V TURBIDITY > ID MOVw S-DAY UNKPSET ' TA RETURN FLUSHING LINE FROM IRRIGATION OR PUMP TANK 14-DAY WET WEATHER FLOW RATE MANUALLY THROTLED- STORAGE TANK G ib o cT � 3 TO IRRIGATION FIELDS 1.� MAX. DOSE = 118.6 GPM DISC SKID WET WEATHER STORAGE MAX FLUSH = 86,6 GPM WITH PUMPS INITIATED BY HIGH WATER LEVEL IN DOSE TANK DUE TO CYCLE INTERUPTION BY RAIN GAUGE '� IEGEND 1 iN WETWFATMERTANN RETURN ME-11 OE MANWLLY Massa TX0.0TY1lD TDA;2MJMMOWMTE Q OF 93.K fiM WREN COMBINER WDX NBrta OOMEBTIC MFAIENT FI.DA'. O ��*� R vKnMnVwn[ � RMv HYDRAULIC PROFILE I_"" u sl s wwa Q a. .a � Y�«QmM�a M WgaaghR � s HN1 mI. e MAH: fi •,�fYgY8t4`•� E�W�CPp4` 8 NORTH 4� �I,GRDLINA "YJp L-3Y� Project No: 563222 N-4.2 1/Iff Ul6• o +-� m� < s a* I A IF m S ❑ t—I O C ir N o a b i . ,. Z x —"s "•'b' No REMIDNS/SUBMWONS Dote THE COTTAGES OF BOONE-...�fr �kr u.�Op; CAPSTONE COLLEGIATE COMMUNITIES, LLC ■/'�w/'�■K$ ` ` WASTEWATER IRRIGATION SYSTEM ��/�- K '� � � � Eno.NeeNINs Ass ociArss BAM,m„ Ps •z, +j`' 1 s m noomuno rez-n WATAUGA COUNTY ' N NORTH CAROLINA ASM1rnIk, N.C. 18B111 'n,,,,....,,,,.o•°• ; s Www nownumx t R Dr,,icB rue: Planning• Engineering• Surveying---- Facl-82&232-1333 NNLLo5-oUNOT�5EPo0.CON5(WCIION I...... WASTEWATER TREATMENT PLANT DETAILS -Environmental Services• �N.n�,x�.mn, C::tTL SERIES 30 ORBINOX VALVE SOLUTIONS IN MORE THAN 7E COUNTRIES The TL (SER.30) model knife gate is a bi-directional wafer valve designed for media with high consistency. The double seat design assures a non -clogging shut off on either normal or reverse flow. The valve is used in a wide range of demanding applications in industries such as: Pulp & Paper • Power Plants Wastewater Treatment Plants • Etc. Chemical plants Sizes: DN 2"/50mm to DN 40"/1000mm (larger diameters on request) Working pressure: DN 2"/ 50mm to DN 5"/ 125mm 150psi/(10 kg/cm2) DN 6"/150mm to DN 10"/ 250mm 1 15psi/ (8 kg/cm2) DN 12"/300mm to DN 16"/ 400mm 90psi/ (6 kg/cm2) DN 18"/450mm 75psi/ (5 kg/cm2) DN 20"/500mm to DN 24"/ 600mm 60psi/ (4 kg/cm2) DN 28"/700mm to DN 40"/1000mm 30psi/ (2 kg/cm2) Standard flange connection: DIN PN 10 and ANSI B16.5 (class 150) Other flange connections are available on request such as: DIN PN 6 DIN PN 16 DIN PN 25 BS "D" and "E" ANSI 125 Directives: For EU Directives and other Certificates, please see the document: Directives and Certificates Compliance - Knife Gate Valves - Catalogues and Datasheets All valves are tested prior to shirmpina in accordance with the standard developed by the Quality Control Department at ORBINOX. Part: Material: 1- Body GJL250 / GJS400 CF8M 2- Body GJL250 / GJS400 CF8M 3- Gate AISI 304 AISI 316 4-Seat Metal/Metal or EPDM 5- Packing PTFE Im re . Synth. Fibre (ST)+O-ring 6- Gland Follower AlunI 211/50mm to DN 12"/300mm) Ductile Iron (DN 1411/350mm to DN 40"11000mm) CF8M 7- Seat Retainer Ring AISI 304 AISI 316 8- Yoke Carbon Steel - Epoxy Coated 9- Stem Stainless Steel 10- Stem nut Brass 11- Friction washer Brass 12- Handwheel GJS400 (GGG40) 13- Stem Protector Epoxy -coated Carbon Steel 14- Cap Plastic 15- Gasket Aramid fibres 16- Nut Zinc plated Carbon Steel Reserves the right to change specifications without notice ORBINOX CANADA, ORBINOX USA, ORBINOX BRAZIL, ORBINOX CHILE, ORBINOX PERU, ORBINOX SPAIN, ORBINOX UK, ORBINOX FRANCE, ORBINOX GERMANY, ORBINOX INDIA, ORBINOX CHINA, ORBINOX S.E.A. www.orbinox.com OBX 05/21 Rev.13 TL (SER.30)_1 TL SERIES 30 BODY: Wafer style cast two-part bolted body, both internally machined, with reinforcing ribs in larger diameters for extra body strength. The stainless steel version valves include internal high density polyethylene sliders (HMWPE) that ensure smoother gate traveling. Full port design to allow a greater flow capacity and to guarantee a minimal pressure drop. SELFCLEANING GATE: Stainless steel as standard. One piece through -going gate with o-port design. When closing, the gate cuts and moves a disc of material downwards, which is again returned to the flow when opening. Gate is polished on both sides to avoid jamming and to ensure a greater seal between the gate with both packing and seat. The thickness and/or the material of the gate can be changed on request for higher pressure requirement SEAT: (resilient) Unique design that mechanically locks the seal in the interior of the valve body with a stainless steel retainer ring. Standard EPDM also available in different materials such as Viton, PTFE, etc. PACKING: Double stuffing box with several layers of braided fibre plus an EPDM o-ring, with an easy access and adjusting packing gland ensuring a tight seal. Long -life braided packing is available in a wide range of materials. STEM: The standard stainless steel stem offers a long corrosion resistant life. For rising stem handwheel actuators only, a stem protector is provided for additional protection against dust while the valve is in the open position. ACTUATORS: All actuators supplied by ORBINOX are interchangeable, and supplied with a standard mounting kit for installation purposes on site. YOKE or ACTUATOR SUPPORT: Made of EPDXY coated steel (stainless steel available on request). Compact design makes it extremely robust even under the most severe conditions. EPDXY COATING: The epoxy coating on all ORBINOX cast iron and carbon steel valve bodies and components is electrostatically applied making the valves to be corrosion resistant with a high quality finished surface. The ORBINOX standard colour is RAL-5015 blue. GATE SAFETY PROTECTION: ORBINOX automated valves are provided with gate guards in accordance with EU Safety Standards. The design feature prevents any objects from being caught accidentally while the gate is moving. ONLY IN EUROPE Reserves the riqht to chanqe specifications without notice ORBINOX VALVE SOLInION5 IN MARE THAN 70 CQVNTRIES ORBINOX CANADA, ORBINOX USA, ORBINOX BRAZIL, ORBINOX CHILE, ORBINOX PERU, ORBINOX SPAIN, ORBINOX UK, ORBINOX FRANCE, ORBINOX GERMANY, ORBINOX INDIA, ORBINOX CHINA, ORBINOX S.E.A. OBX 05/21 Rev.13 TL (SER.30)_2 www.orbinox.com 1::FTL SERIES 30 Bonnet (Fig.1): Assures tight seal to atmosphere for using with hazardous gas or fluids. Reduces packing maintenance Diamond port: Excellent flow regulation. Flush ports: Allow for cleaning of solids trapped within the body cavities that can obstruct the flow or prevent the valve from closing. Depending on the process, purging can be made with air, steam, liquids, etc. Other materials of construction: Special alloys such as AISI 317 (1.4449), 254SM0 (1.4547), Hastelloys, etc. Fabricated valves: ORBINOX designs, produces and delivers special fabricated valves for special process conditions (big sizes and/or high pressures) Square port (Fig.2): Greater flow capacity for bulk material. Designed for equipment with square flange connections Fig.2 Reserves the riqht to chanqe specifications without notice ORBINOX VALVE sQIWIQN$ IN MARE THAN 70 CQUNTRIE$ Fig.1 Valve components can be protected or coated for a longer life expectancy, depending on the application of the valves and the valve service conditions. At ORBINOX we can offer alternative treatments and coatings for the different valve components to improve their properties against abrasion (Stellite, polyurethane...), against corrosion (Halar, Rilsan, galvanizing...) and against adherence (polishing, PTFE... ). We recommend to contact our technical department ORBINOX CANADA, ORBINOX USA, ORBINOX BRAZIL, ORBINOX CHILE, ORBINOX PERU, ORBINOX SPAIN, ORBINOX UK, ORBINOX FRANCE, ORBINOX GERMANY, ORBINOX INDIA, ORBINOX CHINA, ORBINOX S.E.A. OBX 05/21 Rev.13 TL (SER.30)_3 www.orbinox.com EM TL SERIES 30 MANUAL: Handwheel (rising stem) Handwheel (non -rising stem) Chainwheel Bevel Gear Lever Others (square nut...) All actuators supplied by ORBINOX are interchangeable Used on pneumatic actuated valves SINGLE ACTING (SPRING RETURN) Available from DN 211/50mm to DN 12"/300mm Supply pressure: min. 75 psi/ (5 kg/cm2) max. 150 psi/ (10 kg/cm2) Options: Pneumatic or electric fail open T Pneumatic or electric fail close Other options on request DOUBLE ACTING WITH AIR TANK Available for all valve sizes Supply pressure: min. 50 psi / (3.5 kg/cm2) max. 150 psi / (10 kg/cm2) Options: i Pneumatic or electric fail open Pneumatic or electric fail close Other options on request AUTOMATIC: Electric (rising & non -rising stem) Pneumatic (single & double-acting) Hydraulic Mechanical stops Locking device Manual override Solenoid valves Positioners Limit switches Proximity switches Floor stands Stem extensions Wide range of valve extensions available We recommend consultation with our technical department. ORBINOX VALVE SOLWIQN$ IN MARE THAN 70 CQUNTRIEs OBX 05/21 Reserves the riqht to chanqe specifications without notice Rev.13 ORBINOX CANADA, ORBINOX USA, ORBINOX BRAZIL, ORBINOX CHILE, ORBINOX PERU, ORBINOX SPAIN, ORBINOX UK, ORBINOX FRANCE, ORBINOX GERMANY, ORBINOX INDIA, ORBINOX CHINA, ORBINOX S.E.A. TL (SER, 30)_4 www.orbinox.com C:3 T L SERIES 30 ORBINOX VALVE sQIWIQNs IN MARE THAN 70 CQUNTRIEs SEAT / SEALS PACKING Metal/Metal >482 >250 High temp./Low tightness PTFE impregn. synth. fibre (ST) 482 250 2-13 EPDM (E) 248 120 Acids and non mineral oils Braided PTFE (TH) 500 260 0-14 NBR (N) 248 120 Resistance to petroleum products Graphited (GR) 1112 600 0-14 FKM-FPM (V) 392 200 Chemical service/High temp. Ceramic fibre (FC) 2192 1200 -- VMQ (S) 482 250 Food service/ High temp. PTFE (T) 482 250 Corrosion resistance NOTE: all types include an elastomere O-ring (same material as seal), excluding TH, GR and FC More details and other materials under request B Cast Iron Stainless Steel METAL / METAL Used for applications with high temperature or applications where tight shutoff is not required. k The stainless steel version includes HMW polyethylene seat sliders that ensure a smoother gate Ip traveling 4,6r` Iw I DN 2"/50 - e/150 DN8"/200-24"/600 METAL / METAL, TYPE IIBII Two replaceable reinforced "B" type rings (available in AISI 316, Ni-hard, CA15.... ) protect the seat in abrasive services. HMW polyethylene seat sliders for smoother gate traveling (stainless steel version only) rl DN 2"/50 - ell50 DN 8"/200 - 24"/600 RESILIENT, TYPE "A" The standard resilient seat design consists of an elastomer seal fixed to the valve body with a replaceable stainless steel retainer ring. Temperature limitations according to seat material selected. Verify the above chart or contact our technical department for more information.` F HMW polyethylene seat sliders for smoother gate traveling (stainless steel version only) Wi IT, a T DN2"/50- ell 50 DN 8"/200 - 24"/600 RESILIENT, TYPE "B" 1 Resilient seat design with an elastomer seal fixed to the valve body with two reaplaceable + reinforced seal retainer rings (available in AISI 316, Ni-hard, CA15,...) that protect the seat in V1 abrasive services. Temperature limitations according to seat material selected. Verify the above , [. chart or contact our technical department for more information. HMW polyethylene seat sliders for smoother gate traveling (stainless steel version only) DN 2"/50-6"/150 DN 8"/200-24"/600 DEFLECTION CONE "C" Deflects the media away from any valve internal exposed parts such as gate guides, seats, etc. Different types of material available such as AISI 316, CA15, Ni-Hard, etc. Installed at flow inlet, deflection cones protect the seat. They slightly reduce the inlet bore and the face-to-face dimensions also increase: DN 2"/50mm to DN 10"/250mm X=0.35"/9mm ',I-!.. DN 12"/300mm to DN 24"/600mm X=0.47/12mm OBX 05/21 Reserves the riqht to chanqe specifications without notice Rev.13 ORBINOX CANADA, ORBINOX USA, ORBINOX BRAZIL, ORBINOX CHILE, ORBINOX PERU, ORBINOX SPAIN, ORBINOX UK, ORBINOX FRANCE, ORBINOX GERMANY, ORBINOX INDIA, ORBINOX CHINA, ORBINOX S.E.A. TL (SER, 30)_5 www.orbinox.com CCJITL SERIES 30 Standard manual actuator Consists of: Handwheel: Epoxy coated Cast Iron Floor stand Stem Stem nut Stem protector Available from DN 211/50mm to DN 241I/600mm Options (on request): Locking Device Extensions ORBINOX VALVE $OL1/rION$ IN MARE 1 70 COUNIRIE$ 2"/50 1,57140 5,98/152 4/100 4,33/110 5,07/129 1,85/47 8,86/225 16,88/429 9,13/232 26/12 2,5"/65 1,57140 6,57/167 4/100 4,52/115 5,79/146 1,85/47 8,86/225 17,75/451 10,04/255 30/14 3"/80 1,96/50 7,16/182 4/100 4,88/124 6,37/162 1,85/47 8,86/225 18,74/476 12,20/310 35/16 411/100 1,96/50 7,95/202 4/100 5,52/140 7,36/187 1,85/47 8,86/225 20,35/517 14,44/367 44/20 5"/125 1,96/50 8,50/216 4/100 6/150 8,30/211 1,85/47 8,86/225 23,66/601 17,00/432 64/29 6"/150 2,36/60 9,48/241 4/100 6,89/175 9,33/237 1,85/47 8,86/225 25,67/652 19,56/497 77/35 8"/200 2,36/60 11,57/294 4,80/122 8,07/205 12,16/309 2,64/67 12,20/310 32,36/822 25/635 137/62 10"/250 2,75/70 14,01 /356 4,80/122 9,64/245 14,33/364 2,64/67 12,20/310 40,03/1017 30,59/777 197/89 12"/300 2,75/70 16,14/410 4,80/122 11,02/280 16,30/414 2,64/67 12,20/310 43,38/1102 35,62/905 242/110 14"/350 3,78/96 18,62/473 7,75/197 12/300 19,13/486 2,60/66 16,14/410 50,63/1286 41,22/1047 384/174 16"/400 3,93/100 21,18/538 7,75/197 13,77/350 21,10/536 2,60/66 16,14/410 54,56/1386 46,10/1171 586/266 18"/450 A,17/106 23,15/588 7,91/201 16,53/420 23,15/588 2,60/66 21,65/550 62,32/1583 51,22/1301 718/326 20"/500 4,33/110 25,43/646 7,91/201 17,71/450 25,51/648 2,60/66 21,65/550 65,86/1673 57,52/1461 820/372 24"/600 4,33/110 25,43/754 7,91/201 20,86/530 29,44/748 2,60/66 21,65/550 77,28/1963 67,36/1711 981/445 Reserves the right to change specifications without notice ORBINOX CANADA, ORBINOX USA, ORBINOX BRAZIL, ORBINOX CHILE, ORBINOX PERU, ORBINOX SPAIN, ORBINOX UK, ORBINOX FRANCE, ORBINOX GERMANY, ORBINOX INDIA, ORBINOX CHINA, ORBINOX S.E.A. OBX 05/21 Rev.13 TL (sER.30)_6 www.orbinox.com CM:TL SERIES 30 Recommended for installation where space is limited Consists of: Handwheel DN 21I/50mm - DN 121I/300mm: aluminium DN >141I/350mm: GJS400 (GGG40) Stem Yoke bushing Stem nut fixed to the gate Available from DN 211/50mm to DN 241I/600mm Options (on request): Locking Device Extension Square Nut Drive x kQ C air, ORBINOX VALVE $OL1/rION$ IN MARE 1 70 COUNIRIE$ 2"/50 1,57140 5,98/152 4,92/125 4,33/110 5,66/144 2,48/63 OG 8,86/225 H 12,48/317 9,13/232 2,5"/65 1,57140 6,57/167 4,92/125 4,52/115 6,33/161 2,48/63 8,86/225 13,34/339 10,04/255 3"/80 1,96/50 7,16/182 4,92/125 4,88/124 6,96/177 2,48/63 8,86/225 14,33/364 12,20/310 4"/100 1,96/50 7,95/202 4,92/125 5,52/140 7,95/202 2,48/63 8,86/225 15,94/405 14,44/367 5"/125 1,96/50 8,50/216 4,92/125 6/150 8,89/226 2,48/63 8,86/225 17,28/439 17,00/432 6"/150 2,36/60 9,48/241 4,92/125 6,89/175 9,92/252 2,48/63 8,86/225 19,29/490 19,56/497 8"/200 2,36/60 11,57/294 5,60/142 8,07/205 12,48/317 2,87/73 12,20/310 23,42/595 25/635 10"/250 2,75/70 14,01/356 5,60/142 9,64/245 14,64/372 2,87/73 12,20/310 27,16/690 30,59/777 12"/300 2,75/70 16,141410 5,60/142 11,02/280 16,61/422 2,87/73 12,20/310 30,51/775 35,62/905 14"/350 3,78/96 18,62/473 7,75/197 12/300 20,03/509 3,85/98 16,141410 35,71/907 41,22/1047 16"/400 3,93/100 21,18/538 7,75/197 13,77/350 22,00/559 3,85/98 16,14/410 39,64/1007 46,10/1171 18"/450 A,17/106 23,15/588 7,91/201 16,53/420 24,05/611 3,85/98 21,65/550 44,44/1129 51,22/1301 20"/500 4,33/110 25,43/646 7,91/201 17,711450 26,41/671 3,85/98 21,65/550 47,99/1219 57,52/1461 24"/600 4,33/110 25,43/754 7,91/201 20,86/530 30,35/771 3,85/98 21,65/550 55,07/1399 67,36/1711 Reserves the right to change specifications without notice ORBINOX CANADA, ORBINOX USA, ORBINOX BRAZIL, ORBINOX CHILE, ORBINOX PERU, ORBINOX SPAIN, ORBINOX UK, ORBINOX FRANCE, ORBINOX GERMANY, ORBINOX INDIA, ORBINOX CHINA, ORBINOX S.E.A. OBX 05/21 Rev.13 TL (SER.30)_7 www.orbinox.com CM:TL SERIES 30 Recommended for elevated installations Consists of: Chainwheel: Epoxy coated Cast Iron Stem Stem nut Stem protector Available from DN 211/50mm to DN 241I/600mm Options (on request): Locking Device Extension Non -rising Stem k a C ORBINOX VALVE $OL1/rION$ IN MARE 1 70 COUNIRIE$ 2"/50 1,57140 5,98/152 3,94/100 4,33/110 5,07/129 10,15/258 00 8,86/225 A 16,88/429 9,13/232 2,5"/65 1,57140 6,57/167 3,94/100 4,52/115 5,79/146 11,02/280 8,86/225 17,751451 10,04/255 3"/80 1,96/50 7,16/182 3,94/100 4,88/124 6,37/162 12/305 8,86/225 18,74/476 12,20/310 4"/100 1,96/50 7,95/202 3,94/100 5,52/140 7,36/187 13,66/347 8,86/225 20,39/518 14,44/367 5"/125 1,96/50 8,50/216 3,94/100 6/150 8,30/211 14,96/380 8,86/225 23,66/601 17,00/432 6"/150 2,36/60 9,48/241 3,94/100 6,89/175 9,33/237 16,97/431 8,86/225 25,66/652 19,56/497 8"/200 2,36/60 11,57/294 4,8/122 8,07/205 12,16/309 21,18/538 12/300 32,36/822 25/635 10"/250 2,75/70 14,01 /356 4,8/122 9,64/245 14,33/364 24,92/633 12/300 40,04/1017 30,59/777 12"/300 2,75/70 16,14/410 4,8/122 11,02/280 16,30/414 28,26/718 12/300 43,38/1102 35,62/905 14"/350 3,78/96 18,62/473 7,75/197 12/300 19,13/486 32,20/818 17,87/454 50,59/1285 41,22/1047 16"/400 3,93/100 21,18/538 7,75/197 13,77/350 21,10/536 36,14/918 17,87/454 54,52/1385 46,10/1171 18"/450 4,17/106 23,15/588 7,91/201 16,53/420 23,15/588 40,94/1040 17,87/454 62,09/1577 51,22/1301 20"/500 4,33/110 25,43/646 7,91/201 17,711450 25,51/648 44,48/1130 17,87/454 65,82/1672 57,52/1461 24"/600 4,33/110 25,43/754 7,91/201 20,86/530 29,44/748 51,57/1310 17,87/454 77,24/1962 67,36/1711 OBX 05/21 Reserves the right to change specifications without notice Rev.13 ORBINOX CANADA, ORBINOX USA, ORBINOX BRAZIL, ORBINOX CHILE, ORBINOX PERU, ORBINOX SPAIN, ORBINOX UK, ORBINOX FRANCE, ORBINOX GERMANY, ORBINOX INDIA, ORBINOX CHINA, ORBINOX S.E.A. TL (SER.30)_8 www.orbinox.com CM:TL SERIES 30 Recommended for valves larger than DN 14°/350mm and working pressures greater than 50psi/(3.5 kg/cm2) Consists of: Stem Yoke Bevel Gear Actuator with Handwheel Standard Ratio 4:1) Available from DN 811/200mm to DN 241I/600mm Options (on request): Locking Device Extension Chainwheel Non -rising stem x C ORBINOX VALVE $OL1/rION$ IN MARE 1 70 COUNIRIE$ 8"/200 2,36/60 11,57/294 4,80/122 8,07/205 12,16/309 23,00/584 12/300 39,13/994 7,87/200 25/635 10"/250 2,75/70 14,01/356 4,80/122 9,64/245 14,33/364 26,73/679 12/300 42,87/1089 7,87/200 30,59/777 12"/300 2,75/70 16,14/410 4,80/122 11,02/280 16,30/414 29,29/744 12/300 45,43/1154 7,87/200 35,62/905 14"/350 3,78/96 18,62/473 7,75/197 12/300 19,13/486 32,91/836 18/450 60,47/1536 10,62/270 41,22/1047 16"/400 3,93/100 21,18/538 7,75/197 13,77/350 21,10/536 36,85/936 18/450 64,40/1636 10,62/270 46,10/1171 18"/450 4,17/106 23,15/588 7,91/201 16,53/420 23,15/588 41,65/1058 18/450 69,21/1758 10,62/270 51,22/1301 20"/500 4,33/110 25,43/646 7,91/201 17,71 /450 25,51 /648 45,19/1148 18/450 72,75/1848 10,62/270 57,52/1461 24"/600 4,33/110 25,43/754 7,91/201 20,86/530 29,44/748 52,28/1328 18/450 79,84/2028 10,62/270 67,36/1711 OBX 05/21 Reserves the right to change specifications without notice Rev.13 ORBINOX CANADA, ORBINOX USA, ORBINOX BRAZIL, ORBINOX CHILE, ORBINOX PERU, ORBINOX SPAIN, ORBINOX UK, ORBINOX FRANCE, ORBINOX GERMANY, ORBINOX INDIA, ORBINOX CHINA, ORBINOX S.E.A. TL (SER.30)_9 www.orbinox.com CM:TL SERIES 30 The standard pneumatic actuator (double acting on -off cylinder) consists on: 0 < 12"/ 300mm: Aluminum barrels O > 14"/ 350mm: Composite barrels Aluminum end covers Stainless Steel (AISI 304) piston rod Nitrile coated steel piston Available from DN211/ 50mm to DN 24"/600mm x Supply Pressure: min. 50psi/(3,5 kg/cm2) - max. 150psi/(10 kg/cm2). Actuator designed with 90psi/(6 k9/cm2) air supply For valves installed in a horizontal position, we recommend Utype support plates and/or actuator support Options (on request): Hard anodized barrel and covers Stainless Steel barrel and covers Over / Undersized cylinder Manual override a Fail Safe System c Limit switches Instrumentation (on request): Positioners Solenoid valves Flow regulators Air preparation units G ORBINOX VALVE $OL1/rION$ IN MARE 1 70 COUNWIE$ 2"/50 1,57/40 5,98/152 4/100 4,33/110 9,13/232 5,07/129 7/178 4,53/115 16,41/417 30/14 C4"-2.44"/(100-62) 114"G 2,5"/65 1,57/40 6,57/167 4/100 4,52/115 10,04/255 5,79/146 7,60/193 4,53/115 17,87/454 35/16 C4"-3.03"/(100-77) 114" G 3"/80 1,96/50 7,16/182 4/100 4,88/124 12,20/310 6,37/162 8,31/211 4,53/115 19,56/497 40/18 C4"-3.74/(100-95) 114"G 4"/100 1,96/50 7,95/202 4/100 5,52/140 14,44/367 7,36/187 9,09/231 4,53/115 21,96/558 51/23 C4"-4.52"/(100-115) 114"G 5"/125 1,96/50 8,50/216 4/100 6/150 17,00/432 8,30/211 10,67/271 5,51/140 24,88/632 75/34 CS"-5.52"/(125-143) 4"G 6"/150 2,36/60 9,48/241 4/100 6,89/175 19,56/497 9,33/237 11,65/296 5,51/140 27,87/708 90/41 CS"-6.61"/(125-168) 4" G 8"/200 2,36/60 11,57/294 4,80/122 8,07/205 25/635 12,16/309 14,09/358 6,89/175 34,33/872 160/73 C6.30"-8.66"/(160-220) 1/a' G 10"/250 2,75/70 14,01/356 4,80/122 9,64/245 30,59/777 14,33/364 16,85/428 8,66/220 40,82/1037 231/105 C8"-10.62"/(200-270) 3/8" G 12"/300 2,75/70 16,14/410 4,80/122 11,02/280 35,62/905 16,30/414 18,82/478 8,66/220 46,1All 172 282/128 C8"12.60"/(200-320) 3/8" G 14"/ 350 3,78/96 18,62/473 7,75/197 12/300 41,22/1047 20,08/510 21,61/549 10,90/277 53,50/1359 456/207 C10"-14.76-/(250-375) 3/8" G 16"/ 400 3,93/100 21,18/538 7,751197 13,77/350 46,10/1171 22,05/560 23,58/599 10,90/277 59,40/1509 662/300 C10"-16.73"/(250-425) 3/8" G 18"/ 450 4,17/106 23,15/588 10,63/270 16,53/420 51,22/1301 23,94/608 26,77/680 15,03/382 67,24/1708 833/378 C12"-18.70"/(300-475) 1/2" G 20"/ 500 4,33/110 25,43/646 10,63/270 17,71/450 57,52/1461 26,30/668 28,74/730 15,03/382 72,75/1848 981/445 C12"-20.67"/(300-525) 1/2"G 24"/ 600 4,33/110 25,43/754 10,63/270 20,86/530 67,36/1711 31,33/796 34,64/880 17,48/444 86,85/2206 1365/619 C14"-24.60"/(350-625) 3/4" G Reserves the right to change specifications without notice ORBINOX CANADA, ORBINOX USA, ORBINOX BRAZIL, ORBINOX CHILE, ORBINOX PERU, ORBINOX SPAIN, ORBINOX UK, ORBINOX FRANCE, ORBINOX GERMANY, www. orbinox.com ORBINOX INDIA, ORBINOX CHINA, ORBINOX S.E.A. TL OBX 05/21 Rev. 13 SER. 30)_1 0 C::PrTL SERIES 30 Consists of: Electric motor Rising stem Motor support yoke acc. to ISO 5210/DIN 3338 The standard electric motor is equiped with: Manual emergency operation Limit switches (open/closed) Torque switches Available from DN 211/50mm to DN 24'I/600mm For valves installed in a horizontal position, we recommend U type support plates and/or actuator support Wide range of types and brands available to meet customer's needs Option: Non rising stem ORBINOX VALVE $OL1/rION$ IN MARE 1 70 COUNIRIE$ 2"/50 1,57/40 5,98/152 4/100 4,33/110 5,07/129 14,05/357 6,30/160 20,74/527 9,13/232 10,43/265 9,80/249 2,44/62 9,37/238 0.79 x 0.16/20 x4 7.4/10 2,5"/65 1,57/40 6,571167 4/100 4,52/115 5,79/146 14,92/379 6,30/160 21,61/549 10,04/255 10,43/265 9,80/249 2,44/62 9,37/238 0.79 x 0.16/20 x4 7.4/10 3"/80 1,96/50 7,16/182 4/100 4,88/124 6,37/162 15,90/404 6,30/160 22,59/574 12,20/310 10,43/265 9,80/249 2,44/62 9,37/238 0.79 x 0.16/20 x4 7.4/10 4"/100 1,96/50 7,95/202 4/100 5,52/140 7,36/187 17,51/445 6,30/160 24,21/615 14,44/367 10,43/265 9,80/249 2,44/62 9,37/238 0.79 x 0.16/20 x4 7.4/10 5"/125 1,96/50 8,50/216 4/100 6/150 8,30/211 18,85/479 6,30/160 25,55/649 17,00/432 10,43/265 9,80/249 2,44/62 9,37/238 0.79 x 0.16/20 x4 11.1/15 6"/150 2,36/60 9,48/241 4/100 6,89/175 9,33/237 20,86/530 6,30/160 43,30/1100 19,56/497 10,43/265 9,80/249 2,44/62 9,37/238 0.79 x 0.16/20 x4 18.44/25 8"/200 2,36/60 11,57/294 4,80/122 8,07/205 12,16/309 24,88/632 6,30/160 49,29/1252 25/635 10,43/265 9,80/249 2,44/62 9,37/238 0.98 x 0.2/25x5 25.81/35 10"/250 2,75/70 14,01/356 4,80/122 9,64/245 14,33/364 29,09/739 7,87/200 51,93/1319 30,59/777 11,14/283 10/254 2,55/65 9,76/248 0.98 x 0.2/25 x5 44.25/60 12"/300 2,75/70 16,14/410 4,80/122 11,02/280 16,30/414 32,44/824 7,87/200 55,47/1409 35,62/905 11,14/283 10/254 2,55/65 9,76/248 0.98 x 0.2/25 x5 51.63/70 14"/350 3,78/96 18,62/473 7,75/197 12/300 20,07/510 37,00/940 7,87/200 60,04/1525 41,22/1047 11,14/283 10/254 2,55/65 9,76/248 1.38 x 0.24/35x6 73,75/100 16"/400 3,93/100 21,18/538 7,75/197 13,77/350 22,04/560 42,71/1085 12,40/315 65,74/1670 46,10/1171 15,31/389 13,22/336 3,58/91 11,25/286 1.38 x 0.24/35 x6 103.25/140 18"/450 4,17/106 23,15/588 10,63/270 16,53/420 23,94/608 47,36/1203 12,40/315 70,98/1803 51,22/1301 15,31/389 13,22/336 3,58/91 11,25/286 1.38 x 0.24/35 x6 132.77/180 20"/500 4,33/110 25,43/646 10,63/270 17,711450 26,30/668 50,90/1293 12,40/315 74,52/1893 57,52/1461 15,31/389 13,22/336 3,58/91 11,25/286 1.38 x 0.24/35x6 125.38/170 24"/600 4,33/110 25,43/754 10,63/270 20,86/530 31,33/796 59,25/1505 12,40/315 86,81/2205 67,36/1711 15,31/389 13,22/336 3,58/91 11,25/286 1.38 x 0,24/35x6 162.26/220 OBX 05/21 Reserves the right to change specifications without notice Rev.13 ORBINOX CANADA, ORBINOX USA, ORBINOX BRAZIL, ORBINOX CHILE, ORBINOX PERU, ORBINOX SPAIN, ORBINOX UK, ORBINOX FRANCE, ORBINOX GERMANY, ORBINOX INDIA, ORBINOX CHINA, ORBINOX S.E.A. TL (SER,30)_1 1 www.orbinox.com COFTL SERIES 30 ANSI B16.5, class 150 42" 4 3/n" 5/8" - 11 UNC 7/16" 4 - 0 2 1/2" 51/2" 4 5/8" - 11 UNC 7/16" 4 - 0 3" 6" 4 5/8" - 11 UNC 9/16" 4 - 0 4" 71/2" 8 5/8" - 11 UNC 9/16" 4 - 4 5" 8 1/2" 8 3/4" - 10 UNC 9/16" 4 - 4 6" 91/2" 8 3/4" - 10 UNC 11 /16" 4 - 4 8" 11 3/a" 8 3/4" - 10 UNC 11 /16" 4 - 4 10" 141/4" 12 7/8" - 9 UNC 7/9" 8 4 12" 17" 12 7/8" - 9 UNC 7/9" 8 4 14" 18 3/4" 12 1" - 8 UNC 7/9" 8 4 16" 21 1/4" 16 1" - 8 UNC 1 1 /8" 12 4 18" 22 3/4" 16 1 1 /8" - 7 UNC 7/9" 12 4 20" 25" 20 1 1 /8" - 7 UNC 1 1 /4" 16 4 24" 291/2 " 20 1 1 /4" - 7 UNC 1 " 16 - 4 EN 1092-2 PN 10 50 125 a" M-16 11 4 04 65 145 4 M-16 11 4 - 0 80 160 8 M-16 14 4 4 100 180 8 M-16 14 4 4 125 210 8 M-16 14 4 4 150 240 8 M-20 18 4 4 200 295 8 M-20 18 4 4 250 350 12 M-20 22 8 4 300 400 12 M-20 22 8 4 350 460 16 M-20 28 12 -4 400 515 16 M-24 28 12 -4 450 565 20 M-24 32 16 -4 500 620 20 M-24 32 16 -4 600 725 20 M-27 25 16 -4 Reserves the right to change specifications without notice ON 2"-3" CS ON 1fi"-1 El" T Zd ON 50-65 n o ON 350-400 n o ORBINOX VALVE $OL1/rION$ IN MARE 1HAN 70 COUNWIE$ N C-S" ON 1C"-14" ON 20"-24" 7 BLIND TAPPED HOLES THROUGH HOLES ON SO-90D ono ON 450-600 DIN 550-300 ono ORBINOX CANADA, ORBINOX USA, ORBINOX BRAZIL, ORBINOX CHILE, ORBINOX PERU, ORBINOX SPAIN, ORBINOX UK, ORBINOX FRANCE, ORBINOX GERMANY, ORBINOX INDIA, ORBINOX CHINA, ORBINOX S.E.A. OBX 05/21 Rev.13 TL (SER.30)-12 www.orbinox.com 4d - ;Y .. i _ C" "1 w.c ^ — w.r- " .ti .. Ar r r4 f