HomeMy WebLinkAboutTurbidity Monitoring Report 202408131
Winston, Joey
From:Andy Ferrell <aferrell@danielcommunities.com>
Sent:Tuesday, August 13, 2024 1:24 PM
To:Winston, Joey
Cc:Clement Riddle
Subject:[External] Cashiers Lake Dredge Turbidity Report and Update
Attachments:August 2024_Week 4_Turbidity Monitoring Data.pdf; Page C2-03_ 2026-04-26-NCDEQ
Cashiers Dredge Approved.pdf
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Joey,
Please find attached the Cashiers Lake turbidity data for July 29th – August 4th, 2024.
As you can see, we exceeded the allowable amounts on Tuesday, July 30th but were back within the allowable
amounts by Wednesday, July 31st.
The good news is that the open water dredge was completed the week of July 29th, 2024, and our contractor spent
the week of August 5th, 2024, cleaning up, building the diversion causeway 3, and switching the water flow as
shown on page C2-03 of the approved dredge plans attached.
Please let me know if you have any questions or need any additional information regarding this matter.
Thanks
Andy S. Ferrell
Vice President – Cashiers Lake
Daniel Communities
Cell: 980.721.5177
aferrell@danielcommunities.com
You don't often get email from aferrell@danielcommunities.com. Learn why this is important