HomeMy WebLinkAbout820064_30 day poa_20240805PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES Facility Number: 82-64 County: Sampson Facility Name: McGee Church Rd Honeycutt Farm Certified Operator Name: Timothy Lindsay Operator Number 19087 1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the lowest point on the top of the dam for lagoons without spillways; and from the current liquid level in the lagoon to the bottom of the spillway for lagoons with spillways. Lagoon Name/ID Spillway(Y or N): Level(inches): Lagoon Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5 1 N 18 2. Check all applicable items Liquid level is within the designed structural freeboard elevations of one or more structures. Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are within acceptable ranges. X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A 30 day Plan of Action is attached. Agronomic balance is within acceptable range. Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste to be pumped and hauled is reflected in section III tables. Included within this plan is a list of the proposed sites with related facility numbers, number of acres and receiving crop information. Contact and secure approval from the DWQ prior to transfer of waste to a site not covered in the facility's CAWMP. Operation will be partially or fully depopulated. *Attach a complete schedule with corresponding animal units and dates fro depopulation *if animals are to be moved to another permitted facility, provide facility number, lagoon freeboard levels and herd population for the receiving facility 3. Earliest possible date to begin land application of waste 7/27/2024 I hereby certify that I have reviewed the information listed above and included within the attached Plan of Action, and to the best of my knowledge and ability, the information is accurate and correct. Timothy Lindsay Phone: Facility Owner/Manager (print) Date: Facility Owner/Manager (signature) 919-710-3194 8/5/2024 PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/Identifier (ID): 11 2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard a. current liquid level according to marker 18.0 inches b. designed 25 yr./24 hr. storm & structural freeboard 19.0 inches c. line b - line a (inches in red zone) = 1.0 inches d. top of dike surface area according to design (area at below structural freeboard elevation) 98175 1ft2 e. line c/12 x line d x 7.48 gallons/ft3 61196 gallons 3. Projected volume of waste liquid produced during draw down period f. temporary storage period according to structural design 180 days g. volume of waste produced according to structural design 160883 1ft3 h. current herd # 4880 certified herd # 4880 actual waste produced = current herd # x line g = certified herd # i. volume of wash water according to structural design j. excess rainfall over evaporation according to design k. (lines h + i + j) x 7.48 x 30 days/line f= 4. Total PAN to be land applied during draw down period I. current waste analysis dated 1 7/25/2024 m. ((lines e + k)/1000) x line I = REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) 160883 ft3 0 ft3 59500 Jft3 274744 gallons 1.20 Ibs/1000 gal. 403.1 Ibs. PAN PoA (30 Day) 2/21 /00 II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR./24 HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY 1. Structure ID: 1 line m = 403.1 lb PAN 2. Structure ID: line m = lb PAN 3. Structure ID: line m = lb PAN 4. Structure ID: line m = lb PAN 5. Structure ID: line m = lb PAN 6. Structure ID: line m = lb PAN n.lines 1+2+3+4+5+6= 403.1lbPAN III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD. o. tract # p. field # q. crop r. acres s. remaining IRR 2 PAN balance (lb/acre) t. TOTAL PAN BALANCE FOR FIELD (lbs.) column r x s u. application window' 1621 3A soybeans 6.10 49.00 298.9 Mar -Sep 15 16211 313 soybeans 5.30 42.00 222.6 Mar -Sep 15 1621 3C soybeans 6.10 84.00 512.4 Mar -Sep 15 1621 3D soybeans 5.80 84.00 487.2 Mar -Sep 15 1621 3E soybeans 6.10 92.00 561.2 Mar -Sep 15 1621 3F soybeans 5.80 90.00 522.0 Mar -Sep 15 1621 3G soybeans 3.30 71.00 234.3 Mar -Sep 15 1621 3H soybeans 3.60 77.00 277.2 Mar -Sep 15 3726 2A 5.00 3726 213 5.00 'State current crop ending application date or next crop application beginning date for available receiving crops during 30 day draw down period. v. Total PAN available for all fields (sum of column t) = 3115.8 lb. PAN IV. FACILITY'S PoA OVERALL PAN BALANCE w. Total PAN to be land applied (line n from section II) = 403.1 lb. PAN PoA (30 Day) 2/21 /00 x. Crop's remaining PAN balance (line v from section III) = 3115.8 lb. PAN y. Overall PAN balance (w - x) _ -2713 lb. PAN Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN based on new information. If new fields are to be included as an option for lowering lagoon level, add these fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the receiving facility. Irrigation onto existing spray fields will continue as weather and field conditions permit. PoA (30 Day) 2/21 /00