Mr. John Hennessy
North Carolina Department of Water Resources
Water Quality Permitting Section/NPDES AUG 0 6 Z024
1617 Mail Service Center
Raleigh,NC 27699-1617 NCDEQ/DWRINPDES
Tuesday, July 30,2024
RE: EMC SOC WQ S20-001 August 2024 Quarterly Progress Report
Mr.Hennessy,
Union County Water receieved the fully excuted SOC for the Grassy Branch WRF on June 21,2022.As a
requirement of this SOC the County is to submit quarterly progress reports. This letter is intended to serve
as the quarterly progress report. Below is a summary of items that took place during the May 2024 report
period.
For Collections system permit WQCS00054
• Ongoing inflow and infiltration(I&I)rehabilitation in the Grassy Branch basin.
o All I&I concerns identified in the June 2022 Grassy Branch Collections System
Assessment Report have been addressed.
For NPDES Permit NC0085812
• Submit contract documents for regulatory approval for Grassy Branch WWTP upgrade project.
o Bid opening was held on July 1, 2024. Bid was awarded to Dellinger,Inc.by Union
County Board of County Commissioners July 15,2024.
o Union County submitted all required documentation for NCDEQ-DWI approval of the
bid award on July 18, 2024.
o The formal notice of award will be issued to Dellinger,Inc.upon NCDEQ-DWI approval
of the award.
o The construction Notice to Proceed will be issued by September 30,2024. The
construction contract period is 500 days for final completion.
If you have any further questions please feel free to contact me.
Sincerely,
6.7
Christopher Clark,PE
Water&Wastewater Division Director
CC:Hyong Yi,Public Works Administrator
Josh Brooks,Water&Wastewater Assistant Division Director
John Shutak,Engineering Division Director
Greg Morgan,Utility Field Services Superintendent
Jonathan Jordan,WRF Superintendent