HomeMy WebLinkAboutNC0026441_Quarterly SOC Progress Report (Q2 2024)_20240730 cs>a®w Town of hirer (Ettp Public Works and Utilities EMC SOC WQ S22-033 Quarterly SOC Progress Report 2nd Quarter 2024 Please accept this submittal as a quarterly progress report for the work and activities for the Town of Siler City under the Special Order By Consent. Scheduled Activities paragraph 2(a) Quarterly Reports Quarterly Nutrient Optimization Report and Quarterly SOC Report were submitted on April 30, 2024. Collection System Permit WQCS00056 Permit for Main Interceptor Replacement Project was Submitted on February 28, 2023,Sewer Extension Permit was issued on April 19, 2023. ARPA Sewer Rehabilitation Project Engineering Report was submitted on May 1, 2023,and was approved on April 23, 2024. We are currently awaiting approval of an encroachment agreement from NCDOT. Encroachment Agreement with Norfolk Southern has been approved and executed.Anticipated Construction Completion date is currently November 2025. Main Interceptor Project is included with scope for WWTP expansion and has been delayed based on delays in acquiring funding. Bids were received for this project on April 4, 2024, and Contract was awarded on June 11t", 2024.Anticipated Construction Completion date is currently May 2025. NPDES Permit NC002644.1 IUP Permits were issued to Mountaire Farms, Brookwood Farms, and the Siler City Water Treatment Plant on May 19, 2023. Mountaire Farms requested an adjudicatory hearing for their permit which was held on July 21. Mountaire is currently appealing the results of the hearing. Appeal is scheduled to be heard on June 17, 2024.An Authorization to Construct has been issued to Mountaire Farms for the improvements. Supplemental Aeration Equipment has been installed in the oxidation ditch basins. The installation was complete on May 26, 2023,with initial email notification on May 30 and a formal letter on June 29, 2023, notifying NCDEQ of completion. Sludge equipment was acquired for winter 2023-2024 season by December 1, 2023 6.0 MGD WWTP Expansion funding has been secured with issuance of the Letter of Intent to fund from NCDEQ DWI.The Town received bids on this project on April 25,2024, and Contract was awarded on June 11th, 2024.The date for Final completion of the contract has not been set but it currently anticipated to be Chris McCorquodale Director of Public Utilities cmccorquodale@silercity.org PO Box 769.311 N Second Avenue Phone:919-726-8614•Fax:919-663-3874 Slier City,NC 27344-0769 www.silercity.org To advance a framework for oursuccess through balancedgovernunce,dynandc partnerships,and art engaged commmity. January 2027. Town is working on an interim plan for improvements to maintain compliance with NPDES Permit limits during the construction period. Water Treatment Plant IUP Permit was issued to the Siler City Water Treatment Plant on May 19, 2023. Construction of the WTP Pretreatment Improvements was completed on November 21St, 2023, and confirmation submitted to NCDEQ notifying of the completion. The WTP Solids Handling Improvements plans were submitted on May 17, 2024, to Public Water Supply. The project is indicated as received but no comments have been received to date on the submittal. Once permits can be obtained the Town will proceed with this project as soon as possible. Action Items under Paragraph 4(a) Phase 1 All Action Items associated with Phase 1 have been completed. Phase 2 WWTP project was awarded on June 11, 2024 As noted above, supplemental aeration equipment installation was completed on May 26, 2023. As noted above,the Town is issued updated IUPs on May 19, 2023.Authorization to Construction was issued to Mountaire Farms on March 15, 2024 Phase 3 As noted above, Construction of the WTP Pretreatment Improvements was completed on November 215i, 2023. Additional testing is being conducted on the Actiflo system. The Town and Engineer are continuing working with the Actiflo manufacturer and contractor to get the system fully online. Summary of Expenditures was submitted in February 2024. Phase 4 Sludge equipment was acquired for winter 2023-2024 season by December 1, 2023 As noted above, The WTP Solids Handling Improvements plans were submitted on May 17, 2024,to Public Water Supply. Construction is in progress for the Mountaire Farms Pretreatment improvements. Additional Wastewater Flow Pursuant to Paragraph 4 The Town has not accepted any additional wastewater this quarter. Thank you, Town of S• City Chris McCorquo le �p Chris McCorquodale Director of Public Utilities cmccorquodale@silercity.org PO Box 769.311 N Second Avenue Phone:919-726-8614•Fax:919-663-3874 Siler City,NC 27344-0769 www.silercity.org To ad. ace a fi cnnework for oursurcess thr•:: fb balanced�7over nar. e,dUnamk pen trrershil;. rtrcl on errgaged community.