HomeMy WebLinkAbout20120658 Ver 1_Approval of Restoration Repair Plan_20240730Strickland, Bev
From: Ryan Lavinder <ryan.lavinder@duke.edu>
Sent: Monday, July 29, 2024 9:07 AM
To: Homewood, Sue; Jennifer Burdette; julia.a.tillery@usace.army.mil; Rebecca Stubbs
Cc: James Eason; Nasser Massry
Subject: RE: [External] Duke Unv Campus Dr Stream Restoration (AID SAW-2012-01043/DWR #
20120658)
Follow Up Flag: Follow up
Flag Status: Completed
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Copying Nasser Massry (Duke PM) on this correspondence.
Thanks,
T. Ryan Lavinder, PE
Civil Engineer
Duke Utility & Engineering Services, FMD
Duke University
919-660-9327 office
919-616-6306 cell
From: Homewood, Sue <sue.homewood@deq.nc.gov>
Sent: Monday, July 29, 2024 8:31 AM
To: Jennifer Burdette <burdette@nrconsultnc.com>; julia.a.tillery@usace.army.mil; Rebecca Stubbs
<rstubbs@mcadamsco.com>
Cc: James Eason <eason@mcadamsco.com>; Ryan Lavinder <ryan.lavinder@duke.edu>
Subject: Re: [External] Duke Unv Campus Dr Stream Restoration (AID SAW-2012-01043/DWR #20120658)
All,
The Division has reviewed the proposed repair plan for the Permittee Responsible Mitigation site. The plan
incorporates input provided during a site visit with the agencies and the Division agrees with the proposed plan.
Please confer with the USACE to determine if any authorizations are required to perform the instream work. If the
USACE determines that authorization is required, please contact DWR so that we may ensure that state
documentation matches the USACE documentation.
The work being proposed is to repair unsuccessful portions of the previously authorized permittee responsible
mitigation. As such, the previous monitoring and success criteria shall be followed for the repaired portion of
stream and disturbed buffers upon completion of the work.
1
Thanks,
Sue Homewood (she/her/hers)
401 & Buffer Permitting Branch
Division of Water Resources
sue.homewood@deq.nc.gov please note my new email address
336 813 1863 mobile
919-707-3679 office
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Jennifer Burdette <burdette@nrconsultnc.com>
Sent: Friday, May 24, 2024 11:02 AM
To: julia.a.tillery@usace.army.mil <julia.a.tillery@usace.army.mil>; Homewood, Sue <sue.homewood@deq.nc.gov>
Cc: Rebecca Stubbs <rstubbs@mcadamsco.com>; James Eason <eason@mcadamsco.com>; Ryan Lavinder
(ryan.lavinder@duke.edu) <ryan.lavinder@duke.edu>
Subject: [External] Duke Unv Campus Dr Stream Restoration (AID SAW-2012-01043/DWR #20120658)
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Greetings,
The Campus Drive Stream Restoration is the permittee-responsible mitigation plan required by the IP issued on
March 4, 2013 for the Duke University Water Reclamation Pond. Monitoring for this project was suspended for a
time because of COVID constraints. Due to instability observed by monitoring and a site visit with USACE and DWR
representatives in 2022, the team agreed a repair plan would be needed. McAdams has prepared a Repair Plan for
you to review and approve before proceeding with the necessary repairs.
Please feel free to contact Rebecca Stubbs with McAdams directly if you have any questions about the repair
design. As Julia was not part of the team during the 2022 site visit, I am happy to give Julia a tour to familiarize her
with the project.
72024-05-16 CampusDriveStreamRestoration-RemedialMitPlan.pdf
Thanks,
Jennifer
Jennifer Burdette
Natural Resource Consultants
308 W Millbrook Rd, Ste D #200, Raleigh, NC 27609