SW6240703_Stormwater Report_20240724
STORMWATER CALCULATIONS AND SUPPORTING DATA Magnolia Hill Apartments Carthage, North Carolina SEAL :•• 056498 Prepared by: Engineering Landscape Architecture Planning r 140 Aqua Shed Court Aberdeen, NC 28315 License # P-1095 June, 2024 STORMWATER ANALYSIS NARRATIVE MAGNOLIA HILL APARTMENTS MOORE COUNTY, CARTHAGE Prepared by: n Engineering Landscape Architecture `� Planning r 140 Aqua Shed Court Aberdeen, NC 28315 License # P-1095 June, 2024 Stormwater Analysis Narrative Magnolia Hill Apartments,Carthage NC Stormwater Narrative The proposed project is located 0.12 miles North of the intersection of McCaskill Rd. and NC 22Hwy in Carthage, North Carolina. The site is a 23.57 acre parcel that was previously a natural wooded area with slopes ranging from 2-15%. Southern Pines Apartment Managers, LLC recently purchased the property with the intent of developing 10 new apartment buildings with amenities. The site is located in the Cape Fear River Basin and drains to Little River with stream index number 8-23-(1) and classification WS-III;HQW, thus requiring a State Stormwater Permit. About 17.91 of the 23.57 acres will be disturbed during construction. We're using bioretention ponds to treat the first inch while also sizing them to meet the Town's 10-year pre/post stormwater requirement. Stormwater runoff generated from impervious surfaces and other portions of the site will be directed to catch basins and inlets strategically placed at low points throughout the site. Runoff will then be conveyed to the bioretention ponds via the storm pipe network. The volume of runoff for the first inch was derived using the Simple Method equation for each pond.The volumes were calculated to be 13,149 cubic feet for pond#1 and 15,101 cubic feet for pond #2 (see calculations below). The runoff from the first inch will infiltrate at approximately one inch/hour through the engineered media to the perforated underdrains located 3 feet below the planted surface. From there the treated water will be directed to the outlet structure and discharged through the outlet pipe. Using stage storage calculations, 6-inch orifices have been set on the riser structures just above the treatment volume elevation to allow for increased discharge which satisfies the 10-year pre/post requirement (see the attached stage storage charts). Orifice Calculations Pond #1 orifice is set at 378', pond volume at 378' is 13,410 cubic feet, required treatment volume for pond #1 is 13,149 cubic feet Pond #2 orifice is set at 378', pond volume at 378' is 15,178 cubic feet, required treatment volume for pond #2 is 15,101 cubic feet Page 2 of 3 Stormwater Analysis Narrative Magnolia Hill Apartments,Carthage NC Simple Method Calculations The Below excerpt is from chapter 3 of the NCDENR Stormwater BMP Manual 3.3.1. Simple Method The Simple Method uses a minimal amount of information such as watershed drainage area, impervious area, and design storm depth to estimate the volume of runoff. The Simple Method was developed by measuring the runoff from many watersheds with known impervious areas and curve-fitting a relationship between the percent imperviousness and the fraction of rainfall converted to runoff (the runoff coefficient). This relationship is presented below: RV = 0.05 +0.9 * IA Where: RV = Runoff coefficient [storm runoff (in)/storm rainfall (in)], unitless IA = Impervious fraction [impervious portion of drainage area (ac)/ drainage area (ac)], unitless. Once the runoff coefficient is determined, the volume of runoff that must be controlled is given by the equation below: V = 3630 * RD * Rv * A Where: V = Volume of runoff that must be controlled for the design storm (ft3) RD = Design storm rainfall depth (in) (Typically, 1.0" or 1.5") A = Watershed area (ac) Page 3 of 3 Magnolia Hill Apartments Carthage, North Carolina Bioretention Pond #1 Bioretention Area DATE August,2023 PROJECT NAME PROJECT NO. Magnolia Hill Apartments Spam-23.01 11_0,KE-c LOCATION BY Carthage,North Carolina TDB CHECKED BY Bioretention Pond#1 PAP Basin Design Criteria Impervious Grass Forrest Description Total Area(sf) Area(AC) area 1 CN1 area 2 CN 2 area 3 CN 3 CN Pre Devel. 249,177.64 5.72 - 98 249,178 39.0 - 55 39.0 Post Devel. 249,177.64 5.72 161,476 98 87,701 39.0 - 55 77.2 SCS Runoff(IN)From IN Rain SCS Volume RO(CF) RO VOL(cf)= RO from 1" la (%Imp) Rd Rv S 1 5.7 1 5.7 1 VOL(cf)= 0.000 1 0.050 1,038 0.648 1 0.633 13,149 Runoff to treat from new impervious area=l 13,1491 Impervious Grass Forrest Description Total Area(sf) Area(AC) area 1 C area 2 C area 3 C C Pre Devel. 249,177.64 5.72 - 0.90 249,178 0.20 - 0.20 0.20 Post Devel. 249,177.64 5.72 161,476 0.90 87,701 0.20 - 0.20 0.65 Bioretention Area DATE August,2023 PROJECT NAME PROJECT NO. Magnolia Hill Apartments Spam-23.01 11_0,KE-c LOCATION BY Carthage,North Carolina TDB CHECKED BY Bioretention Pond#1 PAP Hydrograph formulation-Pre-Construction Contour Area Incr.Vol. Accum.Vol. Stage Zest (ft) (sf) (ft^3) (ft^3) (ft) (ft) 4th Order Polynomial 376.00 0 0.00 0 0.00 0.35 Coefficients 376.50 0 0.00 0 0.50 0.35 b 3.545E-01 377.00 9,983 2,495.75 2,496 1.00 0.75 c1 1.668E-04 377.50 10,915 5,224.38 7,720 1.50 1.44 c2 -3.737E-09 378.00 11,846 5,690.13 13,410 2.00 2.05 c3 5.818E-14 378.50 12,649 6,123.75 19,534 2.50 2.57 c4 -3.300E-19 379.00 13,452 6,525.25 26,059 3.00 3.04 379.50 14,380 6,957.89 33,017 3.50 3.49 380.00 15,307 7,421.68 40,439 4.00 3.95 380.50 16,544 7,962.69 48,402 4.50 4.46 381.00 17,780 8,580.93 56,982 5.00 5.01 381.50 19,029 9,202.31 66,185 5.50 5.56 382.00 20,278 9,826.85 76,012 6.00 5.97 382.50 0 5,069.56 0 6.50 0.35 383.00 0 0.00 0 7.00 0.35 383.50 0 0.00 0 7.50 0.35 384.00 0 0.00 0 8.00 0.35 384.50 0 0.00 0 8.50 0.35 385.00 111 0 0.00 0 9.00 0.35 Volume at 378'=13,410 cubic feet Magnolia Hill Apartments Carthage, North Carolina Bioretention Pond #2 Bioretention Area DATE August,2023 PROJECT NAME PROJECT NO. Magnolia Hill Apartments Spam-23.01 11_0,KE-c LOCATION BY Carthage,North Carolina TDB CHECKED BY Bioretention Pond#2 PAP Basin Design Criteria Impervious Grass Forrest Description Total Area(sf) Area(AC) area 1 CN1 area 2 CN 2 area 3 CN 3 CN Pre Devel. 323,546.89 7.43 - 98 323,547 39.0 - 55 39.0 Post Devel. 323,546.89 7.43 183,373 98 140,174 39.0 - 55 72.4 SCS Runoff(IN)From IN Rain SCS Volume RO(CF) RO VOL(cf)= RO from 1" la (%Imp) Rd Rv S 1 5.7 1 5.7 1 VOL(cf)= 0.000 1 0.050 1,348 0.567 1 0.560 15,101 Runoff to treat from new impervious area=l 15,1011 Impervious Grass Forrest Description Total Area(sf) Area(AC) area 1 C area 2 C area 3 C C Pre Devel. 323,546.89 7.43 - 0.90 323,547 0.20 - 0.20 0.20 Post Devel. 323,546.89 7.43 183,373 0.90 140,174 0.20 - 0.20 0.60 Bioretention Area DATE August,2023 PROJECT NAME PROJECT NO. Magnolia Hill Apartments Spam-23.01 11_0,KE-c LOCATION BY Carthage,North Carolina TDB CHECKED BY Bioretention Pond#2 PAP Hydrograph formulation-Pre-Construction Contour Area Incr.Vol. Accum.Vol. Stage Zest (ft) (sf) (ft^3) (ft^3) (ft) (ft) 4th Order Polynomial 376.00 0 0.00 0 0.00 0.36 Coefficients 376.50 0 0.00 0 0.50 0.36 b 3.642E-01 377.00 10,488 2,622.00 2,622 1.00 0.74 c1 1.514E-04 377.50 12,556 5,760.97 8,383 1.50 1.43 c2 -3.318E-09 378.00 14,624 6,794.92 15,178 2.00 2.05 c3 4.766E-14 378.50 15,360 7,495.87 22,674 2.50 2.58 c4 -2.409E-19 379.00 16,096 7,863.83 30,538 3.00 3.04 379.50 16,843 8,234.57 38,772 3.50 3.48 380.00 17,590 8,608.08 47,380 4.00 3.94 380.50 18,349 8,984.75 56,365 4.50 4.46 381.00 19,109 9,364.55 65,730 5.00 5.02 381.50 19,881 9,747.51 75,477 5.50 5.56 382.00 20,653 J 10,133.61 85,611 6.00 5.97 382.50 0 5,163.33 0 6.50 0.36 383.00 0 0.00 0 7.00 0.36 383.50 0 0.00 0 7.50 0.36 384.00 0 0.00 0 8.00 0.36 384.50 0 0.00 0 8.50 0.36 385.00 111 0 0.00 0 9.00 0.36 Volume at 378'=15,178 cubic feet Magnolia Hill Apartments Carthage, North Carolina Drainage Area Map / 1-\\''''/ \\I i4 -\\\ \A\ —\ \ \\\'���` N. \ � \\_/\ / \, _1 /11 I REVISIONS ....n.. • �I \ \ \\��` _� �� DESCRIPTION IDATE BY\ \ \ N. • •. \S . � ; % / Ji ,� \ \ \ / \ � \ //i \ �_ . . . , �� Iyr \ \\\ \ \ \ l \ �) • , . � �.... / 1 1 // � /_ . / 1i / \�I � \ , \ \ \ \ \ \ I \ \ <� \\ j f1 �\ �\\ \ / 1 I ' 1 \ \\ \ \ \ \\ \ \\ \ \ ' . =/ � . • 7� / I/ \ — /// I �in I�l0� �o � 000t� T • iyl/I l \ VA \\\ \ V\\\\V\AAV\ \ / /I 14 �\ \ \\ \ \ \ I r� r � \_ —/ // � Il/ 1 Cm � � � 7jr1�\.� --/ /� 1 v�� a^ oo Z ro\ 'A" \\\\\\\\\ \ \ \ \ \ � /\ , 7/ //� Ol7vCQlO7\ \ I \-.N.-\.\ ' )`' �\\ \ ,\\\ A i��� \ --,-.1.:. � 315 �j/-/j��\ 'O , 1 ' \ \\\V \\\VA � —/,„j% le w ., / i O, J N 4-1 / ...,N._1— l \h� /� /y- \\ \ \\\\ \ --� - ---J� l\ \ / \_ ��j 325/// // I I VI \ \\\\ - — �\ \Z.> =�— /��// 3i%ii/�= 1 CU L. ate, \�\\kI?1j; ��\\\�\�\�\���_--_ �—_ - � __-,/�� cy �/� ^\\ ' \_ a vA \ \ \ —mot1_— - �� i�/ii�tb/z ��\ c \`1'\ I 1 -�� \�� __,-_- _ %%%�'=—i �//�� tip= '1 �\\\�/ii — /%mil /� i36%//�\� �� J `f\II �\ �/'n 1 �.. ' \\\r�r 3-4 — /�, 1 BMP-2 //3 "\\ / \IIII 1 /' \ \� r�L�� 3- 4 !DA: 7.42 ACS. j%i \ 1\\ // 1 �IuII I 44 l l�=\_\�1L��\lJZ 350_�� - 3$0�� \ I� I 1 —` ��= \\ \�\��\\ // i / 3so ro`0°/y���� �—r \ +Y� zl i 1 ....9 —1\ \ NX -4,1-- ------='------ ----- , . , . ____T\,\'\ \ ,) i„i! . ,If-,-•---,---:--±____. '- --,2----_-_-_-_-_-__6 5-,--, _-__-------±-------__------_-_-_,_----------- ; kl ..?. t , 7 ? - ---,‘-,.___,_._ ,N,--_ , 1 111\'\\P /: , , -j; ,:" --__---- --__ \ II\ �I A�1111�IVIIII�1� � % I � Avv�% i/i�. 'y� % , 3��' �, 1 II 1 6 �I ���� BMPliA\..„!„..004N \V� /////-� TM II/ //�--' -37._DA: 2ACS. �� //j/��1 ' 11 ( ems. ���///,oa I 392 — i 1 III 11, I V II II ---- v� //i -.' 1 :',"\138',' �� �" II 11 I II� l\� "' � \\� �/j/777.71 8B ��m 1 1 1 A �.s� \ _— 380\ \\\\_��- // //. 13g '', —390 d1 \� � / / 388 ... -�,..�J I ' z1� 11�1 I j� � - �..',I////JIB,�,) 'j i \0 . _\ _ _u �% 0 Q I / l 1' II\I > �.ni, - -�0116-: T �� _�1 ��3gj i� � O. ` /' _ ` I IJ ce 4 1/ /// hf, 1 i VI / cC� .� �� / rei\' \\ \} LAB M—I k 1 IOa i I I III l' I, E� ,irl /�L ��j ; /� 389 ; \\ �•�I +MI � wa y/' %" �a�i 1111 I�I�� (I I ®"� �i , I 4 /3g6 � iiii % ®I ;--'a _ • "°M'1 I Q fitI �1I 1."I s e" - e a� �� — Z 11 )_ _ eh---0�- ,_ —s j� �9ti WtrI Q / I 11 I��— C�� �� ,���✓ av� ,�► • — / � E 9 / — Imo— I, K 1` I 6 8 a/ .11.4)ti �� \ \ s 1: i‘ ' 141 • _ ov.----k,r \E NI, .-8-8. . Ii. 0 _..\\‘, bis,lc / . '' 'ate/ W� 1 G ` 7 � \' R Y �,d sue" 9� `ter -9. /y�/ J m 1.\,\�` Z `° yq;, B 9P J\ �..,,i'i„°" �r� ° / yr' / I yee3e r 3a. s �j s" i w s / �. / //�� / H o \\\ \ I I \ 1''III+ I . •� sip,,*. i % -�,� 3\° , �'W% c / / / I Q cw \ \\ �\\ III n 8a\ ��` 388 /I ��/� 38B /�388 / ai II '� 0� J 388 /" af• / Q I A a /` c 1 \ J ill I� I ' '/ 4�s°***" 1 .-� �`/ �_, jI / / G U 1 \ \\\ IIII\ \ 9i�9 , \ 3g/ �s� \ I ,ter 1vivo \ F 'S' e \\ 'I� \\'III •I n I �� ^/ � / E \ ) ) II ,y ,,III,' ) I ` ,/ -"" \ Ir, I y o /" / i o . ea ,eo I \ 1 11\\ '' I I -/''� / I I I DATE: March,2023 I I IL\ \\ I >- fly8 9ti //� %// /g ' — / \ GRAPHIC SCALE FULL 512E SHEET 22"x34 (IN FEET) DESIGNED: JDM iA I \ % _ _ DRAWN: JDM vI %� 1! � CHECKED'�.I _ _ _ m //. Magnolia Hill Apartments Carthage, North Carolina Storm Pipe and Culvert Calculations STORM DRAINAGE/HYDRAULIC GRADE LINE DATE DESIGN PHASE ANALYSIS: 10 YEAR Au.ust,2023 PRELIM / / L PROJECT NAME PROJECT NO CONSTR /X/ Magnolia Hill Apartments Spam-23.01 REVISION %/ LOCATION BY RECORD / / Carthage,North Carolina FDW OTHER / // CHECKED BY (SPECIFY) TAC n= 0.013 STORM DRAINAGE SCHEDULE CONTINUED -k 9= 210 h= 21 INLET Tc I Cc INLET INLET Cc INLET TOTAL INLET PIPE TIME RUNOFF FROM TO AREAS AREA AREA Soils Impervious RUNOFF DISCHARGE AREAS TIME TIME OF CONC. INTENSITY COEFF. (INLETS) (SF) (AC) )%) )%) COEFF. (CFS) (AC) (MIN) (MIN) (MIN) (IN/HR) CI-01 FES-02 1 8013.85 0.18 0.45 0.55 0.61 0.90 0.18 5.00 0.00 5.00 8.02 0.61 CI-3 CI-4 3 5467.52 0.13 0.15 0.85 0.84 0.84 0.126 5.00 0.00 5.00 8.02 0.84 CI-4 CI-5 3-4 10127.69 0.23 0.15 0.85 0.84 1.56 0.358 5.00 0.17 5.17 7.96 0.84 CI-5 CI-6 3-5 7325.31 0.17 0.10 0.90 0.88 1.18 0.526 5.00 0.31 5.31 7.92 0.85 CI-6 CI-7 3-6 4895.34 0.11 0.15 0.85 0.84 0.75 0.639 5.00 0.44 5.44 7.88 0.85 CI-7 CI-8 3-7 9799.59 0.22 0.20 0.80 0.80 1.44 0.864 5.00 0.74 5.74 7.80 0.84 CI-8 CI-9 3-8 3577.10 0.08 0.27 0.73 0.75 0.49 0.946 5.00 0.88 5.88 7.76 0.83 CI-9 CI-10 3-9 5353.33 0.12 0.19 0.81 0.81 0.80 1.069 5.00 1.14 6.14 7.68 0.83 CI-10 CI-11F 3-10 34217.39 0.79 0.18 0.82 0.82 5.13 1.854 5.00 1.68 6.68 7.53 0.82 CI-11F CI-11 3-11 118.65 0.00 0.09 0.91 0.88 0.02 1.857 5.00 1.89 6.89 7.47 0.82 CI-11 CI-12 3-11F 17782.46 0.41 0.23 0.77 0.78 2.54 2.265 5.00 2.12 7.12 7.41 0.81 CI-12 CI-13 3-12 8962.04 0.21 0.25 0.75 0.76 1.26 2.471 5.00 2.32 7.32 7.36 0.81 CI-13 FES-14 3-13 4541.03 0.10 0.00 1.00 0.95 0.79 2.575 6.00 2.55 7.55 7.31 0.81 GI-11A GI-11B 11A 5502.95 0.13 0.10 0.90 0.88 0.89 0.126 5.00 0.00 5.00 8.02 0.88 GI-11B GI-11C 11A-11B 22371.71 0.51 0.70 0.30 0.43 1.75 0.640 5.00 0.56 5.56 7.85 0.51 GI-11C CI-11C2 11A-11C 5352.18 0.12 0.50 0.50 0.58 0.57 0.763 5.00 0.83 5.83 7.77 0.52 CI-11C2 CI-11D 11A-11C2 7513.01 0.17 0.15 0.85 0.84 1.16 0.935 5.00 1.11 6.11 7.69 0.58 CI-11D CI-11 11A-11D 1509.72 0.03 0.10 0.90 0.88 0.24 0.970 6.00 1.17 6.17 7.67 0.59 CI-09A CI-09B 09A 23856.77 0.55 0.22 0.78 0.79 3.45 0.548 5.00 0.00 5.00 8.02 0.79 CI-09B CI-09C 09A-09B 4664.81 0.11 0.31 0.69 0.72 0.62 0.655 5.00 0.63 5.63 7.83 0.77 CI-09C CI-09 09A-09C 910.09 0.02 0.00 1.00 0.95 0.16 0.676 5.00 0.85 5.85 7.76 0.78 01-11C1 GI-11C2 11C1 6895.51 0.16 0.15 0.85 0.84 1.06 0.158 5.00 0.00 5.00 8.02 0.84 CI-11E CI-11F 11E 19979.26 0.46 0.27 0.73 0.75 2.75 0.459 5.00 0.00 5.00 8.02 0.75 CI-15 CI-16 15 6649.84 0.15 0.15 0.85 0.84 1.02 0.153 5.00 0.00 5.00 8.02 0.84 CI-16 01-17 15-16 8990.05 0.21 0.20 0.80 0.80 1.32 0.359 5.00 0.07 5.07 7.99 0.82 01-17 CI-18 15-17 6055.99 0.14 0.45 0.55 0.61 0.68 0.498 5.00 0.23 5.23 7.95 0.76 CI-18 CI-19 15-18 8674.23 0.20 0.20 0.80 0.80 1.28 0.697 5.00 0.39 5.39 7.90 0.77 CI-19 CI-20 15-19 14506.51 0.33 0.10 0.90 0.88 2.34 1.030 5.00 0.85 5.85 7.76 0.80 CI-20 CI-21 15-20 8695.43 0.20 0.25 0.75 0.76 1.22 1.230 5.00 1.31 6.31 7.63 0.80 CI-21 CI-22 15-21 8971.56 0.21 0.25 0.75 0.76 1.26 1.436 5.00 1.73 6.73 7.52 0.79 CI-22 CI-23 15-22 7492.04 0.17 0.50 0.50 0.58 0.79 1.608 5.00 2.25 7.25 7.38 0.77 CI-23 SDMH-24B 15-23 7553.20 0.17 0.10 0.90 0.88 1.22 1.781 5.00 2.58 7.58 7.30 0.78 SDMH-24B CI-24 15-24B 1487.19 0.03 0.00 1.00 0.95 0.26 1.815 6.00 2.82 7.82 7.24 0.78 CI-24 SDMH-25 15-24 16609.10 0.38 0.25 0.75 0.76 2.33 2.162 5.00 2.82 7.82 7.24 0.78 SDMH-25 FES-26 15-25 1752.07 0.04 0.00 1.00 0.95 0.31 2.203 5.00 2.91 7.91 7.21 0.78 1 GI-18A CI-18 18A 592.50 0.01 0.00 1.00 0.95 0.10 0.014 5.00 0.00 5.00 8.02 0.95 CI-21A CI-21 21A 9208.20 0.21 0.20 0.80 0.80 1.36 0.211 5.00 0.00 5.00 8.02 0.80 Page 1 of 8 STORM DRAINAGE/HYDRAULIC GRADE LINE DATE DESIGN PHA'DESIGN PHASE ANALYSIS: 10 YEAR Au.ust,2023 0 PRELIM / / LPMPROJECT NAME PROJECT NO 0 CONSTR /X/ Magnolia Hill Apartments Spam-23.01 0 REVISION %/ LOCATION BY 0 RECORD / / Carthage,North Carolina FDW 0 OTHER / // CHECKED BY 0 (SPECIFY) TAC n= 0.013 STORM DRAINAGE SCHEDULE-CONTINUED S. 210 h= 21 Q Q UPSTREAM SIDE- THEO. CAPACITY SEGMENT UPPER UPPER LOWER LOWER RIM FROM TO DISCHARGE STREAM SLOPE SIZE DIA. (FULL) V FULL LENGTH TIME Pipe Rim INV. Pipe Rim INV. ELEV. (CFS) (CFS) (IN) (IN) (CFS) (FPS) (FT) (MIN) (FT) (FT) (FT) (FT) (FT) CI-01 FES-02 0.90 0.0094 7.25 15 6.3 5.1 43 0.14 380.65 379.40 380.25 379.00 382.40 01-3 CI-4 0.84 0.0317 5.62 15 11.5 9.4 95 0.17 386.42 385.17 383.41 382.16 388.17 CI-4 01-5 2.39 0.0050 11.75 15 4.6 3.7 30 0.14 383.31 382.06 383.16 381.91 386.62 CI-5 CI-6 3.54 0.0050 13.62 15 4.6 3.7 66 0.29 383.06 381.81 382.73 381.48 386.14 CI-6 01-7 4.27 0.0050 14.61 15 4.6 3.7 32 0.14 382.63 381.38 382.47 381.22 386.50 _ 01-7 CI-8 5.62 0.0050 16.20 18 7.4 4.2 66 0.26 382.47 380.97 382.14 380.64 386.14 _ CI-8 01-9 6.07 0.0050 16.67 18 _ 7.4 4.2 136 0.54 382.04 380.54 381.36 379.86 387.32 _ 01-9 01-10 10.86 4.09 0.0050 23.38 24 16.0 5.1 65 0.21 381.36 379.36 381.03 379.03 386.27 01-10 CI-11F 15.55 0.0050 23.73 24 16.0 5.1 70 0.23 380.93 378.93 380.59 378.59 385.22 CI-11F CI-11 18.23 2.75 0.0049 26.64 30 28.7 5.8 70 0.20 380.58 378.08 380.24 377.74 385.50 CI-11 CI-12 24.90 4.41 0.0050 30.09 30 29.0 5.9 80 0.23 380.24 377.74 379.84 377.34 385.00 _ CI-12 CI-13 25.96 0.0050 28.75 30 29.0 5.9 137 0.39 379.74 377.24 379.06 376.56 386.37 CI-13 FES-14 26.57 0.0050 29.00 30 29.0 5.9 19 0.05 378.98 376.48 378.89 376.39 384.96 01-11A GI-11B 0.89 0.0061 7.81 15 5.0 4.1 138 0.56 384.60 383.35 383.76 382.51 387.50 01-11B GI-11C 2.58 0.0050 12.10 15 4.6 3.7 61 0.27 381.02 379.77 380.72 379.47 385.50 GI-11C CI-11C2 3.10 0.0045 13.22 15 4.3 3.5 15 0.07 380.62 379.37 380.55 379.30 385.00 CI-1102 CI-11D 4.18 0.0050 14.50 15 4.6 3.7 84 0.38 380.45 379.20 380.03 378.78 385.66 CI-11D CI-11 4.41 0.0050 14.78 15 4.6 3.7 26 0.12 379.93 378.68 379.80 378.55 386.66 CI-09A CI-09B 3.45 0.0050 13.48 15 _ 4.6 3.7 140 0.63 382.86 381.61 382.16 380.91 388.81 _ CI-09B CI-09C 3.97 0.0050 14.21 15 4.6 3.7 49 0.22 382.06 380.81 381.82 380.57 388.32 CI-09C CI-09 4.09 0.0050 14.38 15 4.6 3.7 72 0.32 381.72 380.47 381.36 380.11 387.64 01-1101 GI-11C2 1.06 0.0050 8.67 15 4.6 3.7 58 0.26 383.05 381.80 382.76 381.51 385.95 CI-11E CI-11F 2.75 0.0050 12.39 15 4.6 3.7 74 0.33 380.95 379.70 380.58 379.33 386.66 CI-15 01-16 1.02 0.0050 8.56 15 4.6 3.7 16 0.07 389.63 388.38 389.55 388.30 391.38 CI-16 01-17 2.34 0.0050 11.66 15 4.6 3.7 35 0.16 388.58 387.33 388.40 387.15 391.47 01-17 CI-18 3.00 0.0050 12.81 15 4.6 3.7 104 0.47 387.96 386.71 387.44 386.19 391.00 CI-18 CI-19 4.35 0.10 0.0050 14.84 15 4.6 3.7 102 0.46 387.34 386.09 386.83 385.58 391.45 CI-19 CI-20 6.54 0.0050 17.14 18 7.4 4.2 105 0.42 385.71 384.21 385.19 383.69 390.16 CI-20 CI-21 7.59 0.0050 18.17 24 15.9 5.1 157 0.52 385.19 383.19 384.41 382.41 389.00 _ CI-21 CI-22 10.02 1.36 0.0050 21.10 24 16.0 5.1 102 0.34 384.31 382.31 383.80 381.80 388.22 _ CI-22 CI-23 14.57 3.98 0.0050 25.35 30 29.0 5.9 83 0.23 382.20 379.70 381.78 379.28 387.19 CI-23 SDMH-24B 17.89 2.31 0.0050 26.13 30 29.1 5.9 34 0.09 381.68 379.18 381.51 379.01 386.38 _ SDMH-24B CI-24 18.04 0.0047 25.37 30 28.1 5.7 29 0.09 381.51 379.01 381.37 378.87 386.90 CI-24 SDMH-25 20.24 0.33 0.0050 26.35 30 29.0 5.9 69 0.19 381.27 378.77 380.93 378.43 386.25 SDMH-25 FES-26 20.47 0.0050 26.30 30 29.0 5.9 60 0.17 380.83 378.33 380.53 i 378.03 387.09 01-18A CI-18 0.10 0.0262 2.66 15 10.5 8.5 38 0.07 389.75 388.50 388.76 387.51 391.50 CI-21A CI-21 1.36 0.0050 9.50 15 4.6 3.7 60 0.27 384.37 383.12 384.07 382.82 388.22 Page of STORM DRAINAGE/HYDRAULIC GRADE LINE DATE DESIGN PHASE ANALYSIS: 10 YEAR Au.ust,2023 PRELIM / / L PROJECT NAMECONSTR /X/ Magnolia Hill Apartments Spam-23.01 PROJECTNO REVISION %/ LOCATION NO BY RECORD / / Carthage,North Carolina FDW OTHER / // CHECKED BY (SPECIFY) TAC n= 0.013 HYDRAULIC GRADE LINE CONTINUED -1. 9= 210 BEND LOSS KS h= 21 90 DEG=0.7 45 DEG=0.42 30 DEG=0.28 60 DEG=0.55 15 DEG=0.10 PIPE HYDRAULIC SIDESTREAM HEAD LOSS BEND FRICTION FRICTION FROM TO AREA RADIUS SUMMATION Hf He He Hb Ht LOSS SLOPE VELOCITY (FT) (FT) (CFS) K (FT/FT) (FPS) CI-01 FES-02 1.2272 0.3125 0.00 0.01 0.00 0.00 0.00 0.01 0.00 0.0002 0.73 CI-3 CI-4 1.2272 0.3125 0.00 0.02 0.00 0.00 0.00 0.02 0.00 0.0002 0.68 CI-4 CI-5 1.22 1 0.3125 0.00 0.04 0.01 0.02 0.00 0.08 0.00 0.0014 1.94 CI-5 CI-6 1.2272 0.3125 0.00 0.20 0.03 0.04 0.00 0.27 0.00 0.0030 2.88 CI-6 CI-7 1.2272 0.3125 0.00 0.14 0.05 0.07 0.00 0.25 0.00 0.0043 3.46 CI-7 CI-8 1.7671 0.3750 0.00 0.19 0.04 0.05 0.02 0.30 0.10 0.0028 3.17 C1-8 CI-9 1.7671 0.3750 0.00 0.45 0.05 0.06 0.13 0.69 0.70 0.0033 3.42 CI-9 CI-10 3.1416 0.5000 4.09 0.15 0.05 0.06 0.02 0.28 0.10 0.0023 3.44 CI-10 CI-11F 3.1416 0.5000 4.09 0.33 0.09 0.13 0.00 0.55 0.00 0.0047 4.92 CI-11F CI-11 4.9087 0.6250 6.84 0.14 0.05 0.07 0.02 0.28 0.10 0.0020 3.69 CI-11 CI-12 4.9087 0.6250 11.24 0.29 0.10 0.14 0.22 0.75 0.55 0.0037 5.04 CI-12 CI-13 4.9087 0.6250 11.24 0.54 0.11 0.15 0.04 0.84 0.10 0.0040 5.26 CI-13 FES-14 4.9087 0.6250 11.24 0.08 0.11 0.16 0.25 0.60 0.55 0.0042 5.38 GI-11A GI-11B 1.2272 0.3125 0.00 0.03 0.00 0.00 0.00 0.03 0.00 0.0002 0.72 GI-11B GI-11C 1.2272 0.3125 0.00 0.10 0.02 0.02 0.00 0.14 0.00 0.0016 2.09 GI-11C CI-11C2 1.2272 0.3125 0.00 0.03 0.02 0.03 0.00 0.09 0.00 0.0023 2.52 CI-11C2 CI-11D 1.2272 0.3125 0.00 0.35 0.04 0.06 0.13 0.58 0.70 0.0042 3.40 CI-11D CI-11 1.2272 0.3125 0.00 0.12 0.05 0.07 0.08 0.32 0.42 0.0046 3.58 CI-09A CI-09B 1.2272 0.3125 0.00 0.40 0.03 0.04 0.00 0.47 0.00 0.0028 2.80 CI-09B CI-09C 1.2272 0.3125 0.00 0.18 0.04 0.06 0.11 0.39 0.70 0.0038 3.22 CI-09C CI-09 1.2272 0.3125 0.00 0.29 0.04 0.06 0.12 0.51 0.70 0.0040 3.32 GI-11C1 GI-11C2 1.2272 0.3125 0.00 0.02 0.00 0.00 0.00 0.02 0.00 0.0003 0.86 CI-11E CI-11F 1.2272 0.3125 0.00 0.13 0.02 0.03 0.00 0.18 _' 0.00 0.0018 2.23 CI-15 CI-16 1.2272 0.3125 0.00 0.00 0.00 0.00 0.00 0.01 0.00 0.0003 0.83 CI-16 GI-17 1.2272 0.3125 0.00 0.05 0.01 0.02 0.00 0.08 0.00 0.0013 1.90 GI-17 CI-18 1.2272 0.3125 0.00 0.22 0.02 0.03 0.00 0.28 0.00 0.0022 2.44 CI-18 CI-19 1.2272 0.3125 0.10 0.46 0.05 0.07 0.00 0.58 0.00 0.0045 3.53 CI-19 CI-20 1.7671 0.3750 0.10 0.40 0.05 0.07 0.02 0.55 0.10 0.0039 3.68 CI-20 CI-21 3.1416 0.5000 0.10 0.18 0.02 0.03 0.06 0.29 0.70 0.0011 2.40 CI-21 CI-22 3.1416 0.5000 1.46 0.20 0.04 0.05 0.02 0.31 0.10 0.0019 3.17 CI-22 CI-23 4.9087 0.6250 5.44 0.10 0.03 0.05 0.00 0.19 0.00 0.0013 2.95 CI-23 SDMH-24B 4.9087 0.6250 7.75 0.06 0.05 0.07 0.11 0.30 _ 0.55 0.0019 3.62 SDMH-24B CI-24 4.9087 0.6250 7.75 0.06 0.05 0.07 0.06 0.24 _ 0.28 0.0019 3.65 CI-24 SDMH-25 4.9087 0.6250 8.08 0.17 0.07 0.09 0.11 0.43 0.42 0.0024 4.10 SDMH-25 FES-26 4.9087 0.6250 8.08 0.15 0.07 0.09 0.11 0.42 0.42 0.0025 4.15 GI-18A CI-18 1.2272 0.3125 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0000 0.08 CI-21A CI-21 1.2272 0.3125 0.00 0.03 0.00 0.01 0.00 0.04 0.00 0.0004 1.10 Page of8 STORM DRAINAGE/HYDRAULIC GRADE LINE DATE DESIGN PHASE ANALYSIS: 10 YEAR Au.ust,2023 PRELIM / / p PROJECT NAME PROJECT NO CONSTR /X/ Magnolia Hill Apartments Spam-23.01 REVISION / / LOCATION BY RECORD / / Carthage,North Carolina FDW OTHER / // CHECKED BY (SPECIFY) TAC DESIGN CRITERIA: n= 0.013 HYDRAULIC GRADE LINE-CONTINUED 1.DESIGN FOR THE 10 YR STORM g= 210 2.ASSUME TIME OF CONCENTRATION TO h= 21 AN INDIVIDUAL INLET=5 MIN.(Unless otherwise noted) INLET W.S.ELEV. FREE- 3.INTENSITY=g/(h+T),FOR 10 YR STORM OUTLET OUTLET INLET USE FLOW BOARD (g and h were derived from Raleigh,N.C.Intensity- FROM TO W.S.ELEV CONTOL CONTROL CONDITION RIM COMMENTS Duration-Frequency Charts,REF:NC Erosion and (FT) (FT) (FT) (FT) CONTROL (FT) Sediment Control Planning and Design Manual) CI-01 FES-02 380.00 380.01 380.05 380.05 INLET 2.35 OK INV.EL. 379.00 CI-3 Cl-4 383.28 383.30 385.82 385.82 INLET _ I 2.35 OK CI-4 CI-5 383.20 383.28 382.85 383.28 OUTLET 1 3.34 OK CI-5 CI-6 382.93 383.20 382.79 383.20 OUTLET 1 2.94 OK CI-6 CI-7 382.68 382.93 382.52 382.93 OUTLET 3.57 OK CI-7 CI-8 382.38 382.68 382.16 382.68 OUTLET 3.46 OK CI-8 CI-9 381.70 382.38 381.80 382.38 OUTLET 4.94 OK CI-9 CI-10 381.42 381.70 380.88 381.70 OUTLET 4.57 OK CI-10 CI-11F 380.87 381.42 380.99 381.42 OUTLET 3.80 OK CI-11F CI-11 380.58 380.87 379.92 380.87 OUTLET 4.63 OK CI-11 CI-12 379.84 380.58 380.10 380.58 OUTLET 4.42 OK CI-12 CI-13 378.99 379.84 379.70 379.84 OUTLET 6.53 OK CI-13 FES-14 378.39 378.98 378.99 378.99 INLET 5.97 OK INV.EL. 376.39 GI-11A GI-11B 383.51 383.54 384.00 384.00 INLET 3.50 OK GI-11B GI-11C 381.26 381.40 380.59 381.40 OUTLET 4.10 OK GI-11C CI-11C2 381.17 381.26 380.27 381.26 OUTLET 3.74 OK CI-11C2 CI-11D 380.58 381.17 380.33 381.17 OUTLET 4.49 OK CI-11D CI-11 379.55 379.87 379.86 379.87 OUTLET 6.79 OK WS ELEV CI-11 380.58 CI-09A CI-09B 382.60 383.07 382.58 383.07 OUTLET 5.74 OK CI-09B CI-09C 382.21 382.60 381.89 382.60 OUTLET 5.72 OK CI-09C CI-09 381.70 382.21 381.57 382.21 OUTLET 5.43 OK WS ELEV CI-11 381.70 GI-11C1 GI-11C2 382.51 382.53 382.46 382.53 OUTLET 3.42 OK WS ELEV CI-11C 381.26 CI-11E CI-11F 380.87 381.05 380.54 381.05 OUTLET 5.61 OK WS ELEV CI-11B 380.87 CI-15 CI-16 389.30 389.31 389.04 389.31 OUTLET 2.07 OK CI-16 01-17 388.15 388.23 388.11 388.23 OUTLET 3.24 OK 01-17 CI-18 387.25 387.53 387.59 387.59 INLET 3.41 OK CI-18 CI-19 386.58 387.15 387.25 387.25 INLET 4.20 OK CI-19 CI-20 384.89 385.44 385.55 385.55 INLET 4.61 OK CI-20 CI-21 384.01 384.30 384.44 384.44 INLET 4.56 OK CI-21 CI-22 383.40 383.71 383.75 383.75 INLET 4.47 OK CI-22 CI-23 381.42 381.60 381.33 381.60 OUTLET 5.59 OK CI-23 SDMH-24B 381.12 381.42 381.01 381.42 OUTLET 4.96 OK SDMH-24B CI-24 380.88 381.12 380.84 381.12 OUTLET 5.78 OK CI-24 SDMH-25 380.45 380.88 380.75 380.88 OUTLET 5.37 OK SDMH-25 FES-26 380.03 380.45 380.33 380.45 OUTLET 6.64 OK INV.EL. 378.03 GI-18A CI-18 388.51 388.51 389.13 389.13 INLET 2.37 OK WS ELEV CI-18 387.51 CI-21A CI-21 383.82 383.86 383.80 383.86 OUTLET 4.36 OK WS ELEV CI-21 383.75 Page 4 of 8 STORM DRAINAGE/HYDRAULIC GRADE LINE DATE DESIGN PHASE ANALYSIS: 10 YEAR Au.ust,2023 PRELIM / / L PROJECT NAME PROJECT NO CONSTR /X/ Magnolia Hill Apartments Spam-23.01 REVISION %/ LOCATION BY RECORD / / Carthage,North Carolina FDW OTHER / // CHECKED BY (SPECIFY) TAC n= 0.013 STORM DRAINAGE SCHEDULE CONTINUED -k 9= 210 h= 21 INLET Tc I Cc INLET INLET Cc INLET TOTAL INLET PIPE TIME RUNOFF FROM TO AREAS AREA AREA Soils Impervious RUNOFF DISCHARGE AREAS TIME TIME OF CONC. INTENSITY COEFF. (INLETS) (SF) (AC) (%) (%) COEFF. (CFS) (AC) (MIN) (MIN) (MIN) (IN/HR) DB-22A DB-22B 22A 5738.11 0.13 0.40 0.60 0.65 0.69 0.132 5.00 0.00 5.00 8.02 0.65 DB-22B DB-22C 22A-22B 11615.11 0.27 0.75 0.25 0.39 0.83 0.398 5.00 0.53 5.53 7.86 0.47 DB-22C CI-22D 22A-22C 4883.43 0.11 0.40 0.60 0.65 0.58 0.510 5.00 0.92 5.92 7.74 0.51 CI-22D CI-22 22A-22D 4285.69 0.10 0.15 0.85 0.84 0.66 0.609 5.00 1.30 6.30 7.64 0.57 GI-22E CI-22 22E 18965.16 0.44 0.75 0.25 0.39 1.35 0.435 5.00 0.00 5.00 8.02 0.39 CI-23A CI-23B 23A 9150.26 0.21 0.40 0.60 0.65 1.09 0.210 5.00 0.00 5.00 8.02 0.65 CI-23B CI-23 23A-23B I 8837.23 0.20 0.25 0.75 0.76 1.24 0.413 5.00 0.24 5.24 7.94 0.71 1 CI-24A CI-24 24A 8940.17 0.21 1.00 0.00 0.20 0.33 0.205 5.00 0.00 5.00 8.02 0.20 DB-27 DB-28A 27 3040.48 0.07 0.75 0.25 0.39 0.22 0.070 5.00 0.00 5.00 8.02 0.39 DB-28A DB-28 27-28A 4034.32 0.09 0.50 0.50 0.58 0.43 0.093 5.00 0.52 5.52 7.86 1.02 DB-28 DB-30A 27-28 6864.92 0.16 0.50 0.50 0.58 0.73 0.227 5.00 0.96 5.96 7.73 0.52 DB-30A CI-30 27-29 2782.21 0.06 0.10 0.90 0.88 0.45 0.291 5.00 1.21 6.21 7.66 0.60 CI-30 CI-31 27-30 6885.65 0.16 0.30 0.70 0.73 0.92 0.449 5.00 1.66 6.66 7.54 0.64 CI-31 CI-32 27-31 16304.09 0.37 0.25 0.75 0.76 2.29 0.824 5.00 2.07 7.07 7.43 0.70 CI-32 SDMH-33A 27-32 6134.69 0.14 0.25 0.75 0.76 0.86 0.964 6.00 2.64 7.64 7.28 0.71 SDMH-33A FES-33 27-33A 2356.38 0.14 0.00 1.00 0.95 1.07 0.964 5.00 2.64 7.64 7.28 0.73 GI-32A GI-32B 32A 3540.73 0.08 1.00 0.00 0.20 0.13 0.081 5.00 0.00 5.00 8.02 0.20 GI-32B CI-32 32A-32B 11363.97 0.26 0.75 0.25 0.39 0.81 0.342 5.00 0.43 5.43 7.89 0.34 GI-32B1 GI-32B 32B1 20999.25 0.48 0.75 0.25 0.39 1.50 0.482 5.00 0.00 5.00 8.02 0.39 FES-35 FES-36 35-36 77153.05 1.77 0.75 0.25 0.39 5.50 1.771 5.00 0.00 5.00 8.02 0.39 FES-37 FES-38 37-38 258764.42 5.94 0.75 0.25 0.39 18.45 5.940 5.00 0.00 5.00 8.02 0.39 Page 5 of 8 STORM DRAINAGE/HYDRAULIC GRADE LINE DATE DESIGN PHA:DESIGN PHASE ANALYSIS: 10 YEAR Au.ust,2023 0 PRELIM / / LPMPROJECT NAME PROJECT NO 0 CONSTR /X/ Magnolia Hill Apartments Spam-23.01 0 REVISION %/ LOCATION BY 0 RECORD / / Carthage,North Carolina FDW 0 OTHER / // CHECKED BY 0 (SPECIFY) TAC n= 0.013 STORM DRAINAGE SCHEDULE-CONTINUED S. 210 h= 21 _ Q Q UPSTREAM SIDE- THEO. CAPACITY SEGMENT UPPER UPPER LOWER LOWER RIM FROM TO DISCHARGE STREAM SLOPE SIZE DIA. (FULL) V FULL LENGTH TIME Pipe Rim INV. Pipe Rim INV. ELEV. (CFS) (CFS) (IN) (IN) (CFS) (FPS) (FT) (MIN) (FT) (FT) (FT) (FT) (FT) _ DB-22A DB-22B 0.69 0.0069 6.92 8 _ 1.0 2.9 92 _ 0.53 384.31 383.64 383.67 383.00 387.50 _ DB-22B DB-22C 1.48 0.0050 9.83 12 2.5 3.2 74 0.38 383.07 382.07 382.70 381.70 386.00 _ DB-22C CI-22D 2.03 0.0050 11.05 12 2.5 3.2 18 0.10 382.60 381.60 382.51 381.51 386.50 CI-22D 01-22 2.63 0.0050 12.18 15 4.6 3.7 60 0.27 382.51 381.26 382.21 380.96 387.19 GI-22E 01-22 1.35 0.0155 7.68 15 8.0 6.5 63 0.16 384.50 383.25 383.52 382.27 386.25 CI-23A CI-23B 1.09 0.0050 8.77 15 4.6 3.7 54 0.24 383.06 381.81 382.79 381.54 386.25 CI-23B 01-23 2.31 0.0050 11.63 15 4.5 3.7 61 0.27 382.69 381.44 382.39 381.14 386.47 CI-24A 01-24 0.33 0.0281 4.04 15 10.8 8.8 120 0.23 385.85 384.60 382.48 381.23 388.60 DB-27 DB-28A 0.22 0.0050 4.78 6 0.4 2.0 63 0.52 389.32 388.82 389.00 388.50 393.00 DB-28A DB-28 0.74 0.0050 7.58 8 0.9 2.4 64 0.44 389.00 388.33 388.68 388.01 394.00 _ DB-28 DB-30A 0.91 0.0050 8.18 12 2.5 3.2 48 _ 0.25 387.65 386.65 387.41 386.41 393.00 DB-30A CI-30 1.33 0.0050 9.45 15 4.5 3.7 101 0.46 387.41 386.16 386.91 385.66 391.22 CI-30 01-31 2.17 0.0050 11.34 15 4.6 3.7 90 0.40 386.81 385.56 386.36 385.11 391.26 CI-31 01-32 4.26 0.0050 14.60 15 4.6 3.7 128 0.58 386.26 385.01 385.62 384.37 391.80 CI-32 SDMH-33A 7.38 2.42 0.0360 13.78 15 12.3 10.0 55 0.09 385.52 384.27 383.55 382.30 390.67 SDMH-33A FES-33 7.57 0.0419 13.49 15 13.2 10.8 54 0.08 383.46 382.21 381.19 379.94 391.92 GI-32A GI-32B 0.13 0.0082 _ 3.60 15 5.9 4.8 122 0.43 387.50 386.25 386.49 385.24 389.25 GI-32B 01-32 2.42 1.50 _ 0.0082 _ 12.89 15 5.9 4.8 100 0.35 386.49 385.24 385.67 I 384.42 388.50 I GI-32B1 GI-32B 1.50 0.0075 9.14 15 5.6 4.6 100 0.37 387.00 385.75 386.25 385.00 388.75 FES-35 FES-36 5.50 0.0131 13.41 15 7.4 6.0 100 0.28 387.00 385.75 385.69 384.44 388.75 FES-37 FES-38 18.45 0.0572 16.02 18 25.1 14.2 100 0.12 387.00 385.50 381.29 379.79 388.75 Page 6 of STORM DRAINAGE/HYDRAULIC GRADE LINE DATE DESIGN PHASE ANALYSIS: 10 YEAR Au.ust,2023 PRELIM / / L PROJECT NAMECONSTR /X/ Magnolia Hill Apartments Spam-23.01 PROJECTNO REVISION %/ LOCATION NO BY RECORD / / Carthage,North Carolina FDW OTHER / // CHECKED BY (SPECIFY) TAC n= 0.013 HYDRAULIC GRADE LINE CONTINUED -1. 9= 210 BEND LOSS KS h= 21 90 DEG=0.7 45 DEG=0.42 30 DEG=0.28 60 DEG=0.55 15 DEG=0.10 PIPE HYDRAULIC SIDESTREAM HEAD LOSS BEND FRICTION FRICTION FROM TO AREA RADIUS SUMMATION Hf He He Hb Ht LOSS SLOPE VELOCITY (FT) (FT) (CFS) K (FT/FT) (FPS) 4 DB-22A DB-22B 0.3491 0.1667 0.00 0.30 0.01 0.02 0.00 0.33 0.00 0.0032 1.96 DB-22B DB-22C 0.7854 0.2500 0.00 0.13 0.01 0.02 0.00 0.16 0.00 0.0017 1.88 DB-22C CI-22D 0.7854 0.2500 0.00 0.06 0.03 0.04 0.07 0.19 0.70 0.0032 2.57 CI-22D CI-22 1.2272 0.3125 0.00 0.10 0.02 0.02 0.01 0.15 0.10 0.0016 2.13 GI-22E CI-22 1.2272 0.3125 0.00 0.03 0.00 0.01 0.00 0.04 0.00 0.0004 1.10 CI-23A CI-23B 1.2272 0.3125 0.00 0.02 0.00 0.00 0.00 0.02 0.00 0.0003 0.89 CI-23B CI-23 1.2272 0.3125 0.00 0.08 0.01 0.02 0.04 0.15 0.70 0.0013 1.88 CI-24A CI-24 1.2272 0.3125 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0000 0.27 DB-27 DB-28A 0.1963 0.1250 0.00 0.09 0.00 0.01 0.00 0.11 0.00 0.0015 1.10 DB-28A DB-28 0.3491 0.1667 0.00 0.24 0.02 0.02 0.07 0.35 1.00 0.0038 2.12 DB-28 DB-30A 0.7854 0.2500 0.00 0.03 0.01 0.01 0.01 0.06 0.70 0.0007 1.16 DB-30A CI-30 1.2272 0.3125 0.00 0.04 0.00 0.01 0.01 0.07 0.70 0.0004 1.08 CI-30 CI-31 1.2272 0.3125 0.00 0.10 0.01 0.02 0.00 0.13 _ 0.00 0.0011 1.76 CI-31 CI-32 1.2272 0.3125 0.00 0.56 0.05 0.07 0.10 0.77 0.55 0.0043 3.46 CI-32 SDMH-33A 1.2272 0.3125 2.42 0.71 0.14 0.20 0.23 1.28 0.42 0.0130 5.99 SDMH-33A FES-33 1.2272 0.3125 2.42 0.74 0.15 0.21 0.32 1.42 0.551 0.0137 6.15 GI-32A GI-32B 1.2272 0.3125 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0000 0.11 GI-32B CI-32 1.2272 0.3125 1.50 0.14 0.02 0.02 0.04 0.22 0.70 0.0014 1.97 01-3281 GI-32B 1.2272 0.3125 0.00 0.05 0.01 0.01 0.00 0.07 0.00 0.0005 1.22 FES-35 FES-36 1.2272 0.3125 0.00 0.72 0.08 0.11 0.00 0.91 0.00 0.0072 4.47 FES-37 FES-38 1.7671 0.3750 0.00 3.06 0.42 0.59 0.00 4.07 0.00 0.0307 10.40 Page of STORM DRAINAGE/HYDRAULIC GRADE LINE DATE DESIGN PHASE ANALYSIS: 10 YEAR Au.ust,2023 PRELIM / / p PROJECT NAME PROJECT NO CONSTR /X/ Magnolia Hill Apartments Spam-23.01 REVISION / / LOCATION BY RECORD / / Carthage,North Carolina FDW OTHER / // CHECKED BY (SPECIFY) TAC DESIGN CRITERIA: n= 0.013 HYDRAULIC GRADE LINE-CONTINUED 1.DESIGN FOR THE 10 YR STORM g= 210 2.ASSUME TIME OF CONCENTRATION TO h= 21 AN INDIVIDUAL INLET=5 MIN.(Unless otherwise noted) INLET W.S.ELEV. FREE- 3.INTENSITY=g/(h+T),FOR 10 YR STORM OUTLET OUTLET INLET USE FLOW BOARD (g and h were derived from Raleigh,N.C.Intensity- FROM TO W.S.ELEV CONTOL CONTROL CONDITION RIM COMMENTS Duration-Frequency Charts,REF:NC Erosion and (FT) (FT) (FT) (FT) CONTROL (FT) Sediment Control Planning and Design Manual) DB-22A DB-22B 383.54 383.87 384.14 384.14 INLET 3.36_ OK DB-22B DB-22C 382.50 382.66 382.72 382.72 INLET 3.28 OK DB-22C CI-22D 382.31 382.50 382.39 382.50 OUTLET 4.00 OK CI-22D CI-22 381.96 382.11 382.08 382.11 OUTLET 5.08 OK WS ELEV CI-22 381.60 GI-22E CI-22 383.27 383.31 383.93 383.93 INLET 2.32 OK WS ELEV CI-22 381.60 CI-23A CI-23B 382.54 382.56 382.47 382.56 OUTLET 3.69 OK CI-23B CI-23 382.14 382.29 382.22 382.29 OUTLET 4.18 OK WS ELEV CI-23 381.42 CI-24A CI-24 382.23 382.23 385.23 385.23 INLET 3.37 OK WS ELEV CI-24 380.88 DB-27 DB-28A 388.90 389.01 389.12 389.12 INLET 3.88 OK DB-28A DB-28 388.55 388.90 388.86 388.90 OUTLET 5.10 OK DB-28 DB-30A 387.42 387.48 387.21 387.48 OUTLET 5.52 OK DB-30A CI-30 387.35 387.42 386.83 387.42 OUTLET 3.80 OK CI-30 CI-31 387.22 387.35 386.32 387.35 OUTLET 3.91 OK CI-31 CI-32 386.45 387.22 386.15 387.22 OUTLET 4.58 OK CI-32 SDMH-33A 384.48 385.76 386.45 386.45 INLET 4.22 OK SDMH-33A FES-33 380.94 382.36 384.48 384.48 INLET 7.44 OK INV.EL. 379.94 GI-32A GI-32B 387.44 387.44 386.88 387.44 OUTLET 1.81 OK GI-32B CI-32 387.22 387.44 386.04 387.44 OUTLET 1.06 OK WS ELEV CI-32 387.22 GI-32B1 GI-32B 387.44 387.51 386.44 387.51 OUTLET 1.24 OK WS ELEV CI-32B 387.44 FES-35 FES-36 385.44 386.35 387.24 387.24 INLET 1.51 OK WS ELEV CI-32B 0.00 FES-37 FES-38 380.99 385.06 390.95 390.95 INLET (2.20) OVERFLOW WS ELEV CI-32B 0.00 Page of Magnolia Hill Apartments Carthage, North Carolina Supporting Data Custom Soil Resource Report RI Soil Map (SPAM Soil) K1 N 643300 6434W 643500 643600 6437W 6433800 643900 644000 644100 644200 644300 644400 644500 644600 644700 644800 35°16'12"N 35°16'12"N 8 Little-Rimier 414 8 lig We ,,a.." ;,` ,. MdE 44 Ilk AeD sw.0 AeD, k w �. """ T "r Ud 1 ,. / 'i \ ' • • .' I -1 FaB K yMccas •• ' If it Ct � t '! . B. : / . ... - . / _},— AeD , AeB \ , .. ". 4.2 8 �000J ��ay�otb, a0ot.;h�d '��aOQ° 1 s t, 35°15'38"N a I~ - _....A[ 35°15'38"N 643300 643400 643500 643600 6437W 643800 643900 644000 6441W 6442W 6443W 6444W 6445W 6446W 6447W 644800 3 3 b, 1 Map Scale:1:7,380 if printed on A landscape(11"x 8.5")sheet. v Meters k'' A N 0 100 200 400 600 r: Feet 0 350 700 1400 2100 Map projection:Web Mercator Corner coordinates:WGS84 Edge tics:UTM Zone 17N WGS84 9 Custom Soil Resource Report MAP LEGEND MAP INFORMATION Area of Interest(AOI) 14 Spoil Area The soil surveys that comprise your AOI were mapped at Area of Interest(AOI) 1:24,000. Q Stony Spot Soilsit Very Stony Spot 0 Soil Map Unit Polygons Warning:Soil Map may not be valid at this scale. Wet Spot ,..,. Soil Map Unit Lines Enlargement of maps beyond the scale of mapping can cause p Other misunderstandingof the detail of mapping and accuracyof soil p Soil Map Unit Points pp 9 .• Special Line Features line placement.The maps do not show the small areas of Special Point Features contrasting soils that could have been shown at a more detailed Blowout Water Features scale. Streams and Canals kg Borrow Pit Transportation Please rely on the bar scale on each map sheet for map * clay Spot 1.44 Rails measurements. 0 Closed Depression o,/ Interstate Highways Gravel Pit Source of Map: Natural Resources Conservation Service .r US Routes Web Soil Survey URL: Gravelly Spot Major Roads Coordinate System: Web Mercator(EPSG:3857) ® Landfill Local Roads Maps from the Web Soil Survey are based on the Web Mercator • Lava Flow Background projection,which preserves direction and shape but distorts distance and area.A projection that preserves area,such as the 46 Marsh or swamp Aerial Photography Albers equal-area conic projection,should be used if more It Mine or Quarry accurate calculations of distance or area are required. 4 Miscellaneous Water This product is generated from the USDA-NRCS certified data as O Perennial Water of the version date(s)listed below. v Rock Outcrop Soil Survey Area: Moore County,North Carolina + Saline Spot Survey Area Data: Version 26,Sep 13,2023 Sandy Spot Soil map units are labeled(as space allows)for map scales Severely Eroded Spot 1:50,000 or larger. • Sinkhole Date(s)aerial images were photographed: Apr 23,2022—Apr 31 Slide or Slip 27,2022 oa Sodic Spot The orthophoto or other base map on which the soil lines were compiled and digitized probably differs from the background imagery displayed on these maps.As a result,some minor shifting of map unit boundaries may be evident. 10 Custom Soil Resource Report Map Unit Legend (SPAM Soil) Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI AeB Ailey loamy sand,2 to 8 percent 2.9 1.5% slopes AeD Ailey loamy sand,8 to 15 15.0 7.5% percent slopes CaB Candor sand,0 to 4 percent 37.2 18.6% slopes DoB Dothan loamy sand,2 to 6 18.8 9.4% percent slopes FaB Fuquay loamy sand,0 to 6 9.5 4.7% percent slopes MdE Mayodan fine sandy loam, 15 to 6.3 3.1% 25 percent slopes PkF Pinkston silt loam, 15 to 40 17.4 8.7% percent slopes Ud Udorthents, loamy 24.3 12.2% W Water 4.0 2.0% We Wehadkee loam,0 to 2 percent 64.3 32.2% slopes,frequently flooded Totals for Area of Interest 199.7 100.0% Map Unit Descriptions (SPAM Soil) The map units delineated on the detailed soil maps in a soil survey represent the soils or miscellaneous areas in the survey area. The map unit descriptions, along with the maps, can be used to determine the composition and properties of a unit. A map unit delineation on a soil map represents an area dominated by one or more major kinds of soil or miscellaneous areas. A map unit is identified and named according to the taxonomic classification of the dominant soils. Within a taxonomic class there are precisely defined limits for the properties of the soils. On the landscape, however, the soils are natural phenomena, and they have the characteristic variability of all natural phenomena. Thus, the range of some observed properties may extend beyond the limits defined for a taxonomic class. Areas of soils of a single taxonomic class rarely, if ever, can be mapped without including areas of other taxonomic classes. Consequently, every map unit is made up of the soils or miscellaneous areas for which it is named and some minor components that belong to taxonomic classes other than those of the major soils. Most minor soils have properties similar to those of the dominant soil or soils in the map unit, and thus they do not affect use and management. These are called noncontrasting, or similar, components. They may or may not be mentioned in a particular map unit description. Other minor components, however, have properties and behavioral characteristics divergent enough to affect use or to require different management. These are called contrasting, or dissimilar, components. They 11 Scott Cole,NCLSS 312 Copples Road Ext Asheboro,NC 27205 (336) 460-4554 LKC Engineering,PLLC December 7, 2023 Attn: Mr. Philip Picerno, PE 140 Aqua Shed Court Aberdeen,NC 28315 Re: Seasonal High-Water Table Identification: Magnolia Hill Apartments; McCaskill Rd/NC Hwy 22,Carthage, NC; Moore County,NC parcel 00031348 Soil conditions on the above-referenced property were evaluated within the areas shown on the attached map to determine the depth to the seasonal high-water table. Work was conducted to satisfy the requirements of the North Carolina Department of Environmental Quality Stormwater Design Manual. Samples were collected with a hand auger. SEASONAL HIGH WATER TABLE IDENTIFICATION Seasonal High Water Table depth is determined by field evaluation for soil wetness conditions which are indicated by the presence of redoximorphic(redox)features with a chroma of 2 or less(in Munsell color notation)in mottles or the horizon matrix. Colors of chroma 2 or less due to relic minerals from parent material(underlying rock), anaerobic activity created by placement of fill material, or soil textural class transitions(perched water) are not considered as indicators for seasonal high water. Upon determination of SHWT depth,an additional 6"will be deducted from the observed depth to account for capillary fringe water movement above the SHWT. The SHWT for this project was not observed within 15' of the ground surface at any location. A summary of observations within the proposed Stormwater BMP Devices are shown in the table below. Contour/elevation data obtained from nconemap.gov Test location# Total Depth Profile Summary SHWT Munsell Color elevation) Notation 1 (384') 15' (Elevation 0-4': LS(coarse) Not Observed N/A 4-6': SCL 369') 6-9': Clay 9-15': mixed soil textures 2 (386') 16' (Elevation 0-2.5': SL Not Observed N/A 2.5-6': Saprolite 370 ) 6-10.5': mixed textures (layered;mottled) 10.5-16': LS/SCL (layered;mottled) 3 (381') 15' (Elevation 0-5': LS Not Observed N/A 5-8': SCL(mottled) 366 ) 8-9': SC(cemented) 9-15': mixed textures (layered;mottled) I am pleased to be of service in this matter and can be contacted at your convenience should you have questions concerning information within this report. () L Scott Cole e�, � f�North Carolina Licensed Soil Scientist Uo ° " . cz 01 co \ v. co Mo tCO oMyd OR fA Oo 36 c O d 0 _0 +-' 0 in Z ••.0 co L t' C R ~ VCI • mWI—--V) co O O 111c/ 9 5 * co • ♦Mg co co el; coco 0 OOD O I.. CO t0 N00 00 t ZW .. 17;�N 2 JJ`Z / _ cr\\ N. M 13 IP CJ ����� ;�. d co co M vO co O Fo Ea Z Co M —L L N O. C O.co O) * O a)-a NO O O'00i_ N CO C al co C 03 coC • O1 •t0 co �O~o CO W HN CO T CO M Z MI co • coC:::A O r ■ 133 N t7 0 v. co (NI C •co cc to 1 \YV n • � ` d o PM � 04. on O Zco �, _ d. rt _ , MW CIQ C G.N ..t C b O * O CD•O le• e y� IM S~ 7p CO�A0 9 r ,H(0pcoN a- mWN . .i 41. co 03 co co M V J 0 N —'.."'.'mm.2 39 I I �, ZZ 5N �.-- J el a U�, 314 N 316 382 c c o \ c ._ o c o r 5