Adam Carter <adam@wetlandnc.com> Mon, Jul 22, 2024 at 4:01 PM
To: "Homewood, Sue" <sue.homewood@deq.nc.gov>, "Martin, Matthew K CIV CESAW"
<Matthew.K.Martin@usace.army. mil>
Bcc: Wesley Johnson <wesley@wetlandnc.com>
Hello Sue and Matthew,
Please send a NOV to Mother Nature. To much rain.
Please see attached requested information below.
1. If the USACE requests a response to any comments received as a result of the Public Notice,
please provide the Division with a copy of your response to the USACE. Please see that attached.
2. The application states that the purpose is to construct a driveway, however the project drawings also include impacts to
a wetland from what appears to be a walkway. Please clarify the proposed impacts and update the PCN or drawings
accordingly. The site plan referred to was a draft of the first site plan. Final draft shows the home being moved
away from wetlands in order to avoid the additional wetland impact for the walkway. Only impact being
pursued is the driveway. See final site plan attached.
3. According to the application drawings, impacts are proposed to both streams and wetlands,
however only wetland impacts are depicted on the PCN form. Please clarify the proposed
impacts and update the PCN or drawings accordingly. See attached. Both Stream and wetland are depicted in the site
plan now.
4. As noted by the US Army Corps of Engineers in a letter dated March 22, 2024, it appears that
impacts from the walkway could be avoided with a slight design modification. Please provide
justification of why this impact cannot be avoided.Please see the attached updated site plan which avoids the
wetland impact for sidewalk.
5. Provide a detailed plan and profile drawing of the proposed culvert. See attached.
6. Please note that all work must be done "in the dry". Therefore, dewatering methods will be
necessary to temporarily dewater the stream channel during culvert installation and during
utility line installation. Please provide a construction sequence and dewatering details that
show that dewatering is to be utilized at the site and the sequence of construction events to be
followed to ensure compliance with this condition . In addition, please ensure that the location of the temporary impacts
are shown on the construction drawings and clearly indicated in the
revised impact table. Please see attached culvert profile. This is an intermittent stream with season flow. Wetland
and stream components are very dry with exception of rain events. Planning an install time with no flow or
hydrology should be very easy to do. If needed we will temporarily dike stream for a few hours and pump
stream hydrology around the road construction footprint. Release hydrology back into downstream as very low
energy, so that no erosion or sedimentation transport takes place. All BMPs will be adhered to. Silt fence, celcer
matting, warm weather grass and maintenance regiment after every rain will be performed. We will recess
culvert 20% into stream channel Cap the culvert with clean fill.
Coming in from the western side on the tract HOA owns and will not allow access. Duke power holds easement
and will not let permanent structures in easement such as paved driveway.
Regards,
Adam Carter
Owner
https://mail.google.com/mail/u/l/?ik=06572834cl &view=pt&search=all&permmsgid=msg-a:r15899477137830213&simpl=msg-a: r15899477137830213 1 /2
7/23/24, 10:46 AM Wetland Solutions LLC Mail - Barons Dr addtional requisted information
Wetland Solutions, LLC
P.O. Box 244
Bunnlevel, NC 28323
(910) 890-2779
Adam@WetlandNC.com
www.WetlandNC.com
www linkedin.com/in/adam-carter-wetland
9 attachments
20 Barons Drive DMS Acceptance.pdf
246K
20240403_Itr RFO ACarter AltParNo_00991468_20_Barons_Drive_s_.pdf
362K
2024_02_16_Site Plan (final).pdf
436K
2022_10_15_Site Plan (alt 1).pdf
163K
Barons Drive Fig 2b -Wetlands and Impacts (alt 1).pdf
1379K
Barons Drive Fig 2 -Wetlands and Impacts (final).pdf
1298K
Barons Drive Fig 2c -Wetlands and Impacts (alt 2).pdf
1378K
2024_07_16_Site Plan (alt 2).pdf
863K
Barons Drive —Alternative practicability analysis tables.xlsx
11K
https://mail.google.com/mail/u/l/?ik=06572834cl&view=pt&search=all&permmsgid=msg-a:r15899477137830213&simpl=msg-a:r15899477137830213 2/2