HomeMy WebLinkAboutNCC242071_ESC Approval Submitted_20240710 (lx.taisPWATER RESOURCES
-' <
77,45
cAR
July 9, 2024
Tammala Brooks
Fifth Third Bank
38 Fountain Square Plaza MD 10903K
Cincinnati, OH 45202
Re: Letter of Plan Approval
Project Name: Fifth Third-Apex Sweetwater
Project Location: 112 Moncure Place
Project Number: 002
Submitted By: Infinity Engineering Group, LLC
Date Submitted: 06/14/2024
Disturbed Area: 1.04
The Soil Erosion and Sedimentation Control Plan(S&E) you submitted has been reviewed and
accepted. The Town of Apex (Town)hereby issues this Letter of Plan Approval. The Town's
S&E program is performance oriented, requiring protection of the natural resources and
adjoining properties. If at any time during this project it is determined by Town staff that the
approved S&E Plan is inadequate to meet the Town's S&E ordinance, this office may require
revisions to the S&E Plan and its implementation to ensure compliance with the S&E ordinance
(Section 5154).
In accordance with Section 5-158 of the Town's S&E ordinance, you are hereby notified that this
office has the right to periodically inspect any land-disturbing activities to ensure compliance
with the approved S&E Plan and ordinance. You are to notify this office twentyfour(24)hours
before starting work. You are also required to keep the working drawings on site.
TOWN OF APEX
The Peak of Good Living
PO Box 250 Apex,NC 27502 I (919) 362-8166 I www.apexnc.org
Stormwater runoff generated from sites disturbing one (1) acre or more is permitted pursuant to
the National Pollution Discharge Elimination System (NPDES) administered in North Carolina
by the Division of Energy, Mineral and Land Resources; Stormwater Section. As of April 1,
2019, all new construction activities are required to complete and submit an electronic Notice of
Intent (eNOI) form requesting a Certificate of Coverage (COC)under the NCG010000
Construction General Permit. After the form is reviewed and found to be complete, you will
Letter of Plan Approval
Page 2 of 2
receive a link with payment instructions for the applicable annual permit fee. After the fee
is processed, you will receive the COC via email. As the Financially Responsible Party shown
on the FRO form submitted for this project,you MUST obtain the COC prior to commencement
of any land disturbing activity. The eNOI form and fee details may be accessed
at deq.nc.gov/NCG01. Please direct questions about the eNOI form to the Stormwater Program
staff in the Raleigh central office. If the owner/operator of this project changes in the future, the
new responsible party must obtain a new COC. On or after October 3, 2023, a$120 fee will be
charged annually. This fee is to be sent to the DEMLR Stormwater Central Office staff in
Raleigh.
Complete a Grading Permit Application and receive a Grading Permit from the Building
Inspections & Permitting Department as required by the North Carolina Building Code Appendix
J for Grading. Both the Grading Permit and Certificate of Coverage from NCDEMLR must be
submitted to the Stormwater Field Services Supervisor prior to the commencement of any land
disturbance activity.
The Contractor will be permitted to clear only as necessary to install the required S&E measures.
Once the required S&E measures are installed, contact Environmental Engineering staff to
schedule an on-site inspection. A Certificate of Compliance will be issued after a site inspection
is completed to ensure that the S&E measures are installed per the approved S&E Plan.
The approval of an S&E Plan is conditioned on the applicant's compliance with Federal and
State water quality laws, regulations, and rules. In addition, the Town's NPDES Phase II permit
requires site contractors to control construction site wastes that may cause adverse water quality
impacts. Please have your site contractor review the attached Town Construction Site Waste
Management Plan to become familiar with the requirements. Town staff will inspect your site to
ensure these waste management practices are being implemented. You will need to provide
evidence of compliance if applicable.
I look forward to working with you on this project and if you have any questions,please call
(919) 372-7470.
Regards,
TOWN OF APEX
The Peak of Good Living
PO Box 250 Apex,NC 27502 I (919) 362-8166 I www.apexnc.org
James Misciagno, CES, CPESC
Stormwater Engineering
Enclosures: Town Construction Site Waste Management Plan
Letter of Plan Approval
Page 2 of 2
TOWN OF APEX
The Peak of Good Living
PO Box 250 Apex,NC 27502 I (919) 362-8166 I www.apexnc.org