Loading...
HomeMy WebLinkAbout20061139 Ver 2_401 Application_20071207.' Steve Mitchell Environmental Consulting 1813 Lancaster Drive Gamer, North Carolina 27529 919-550-9055(h) 919-971-6598 (c) srtnitcheil51 ~yahoo.com Lia Myott 1650 Mail Service Center Raleigh, N. C. 27600-1650 Subject: Modification of DWQ EXP# 06-1139v2 The Woods of Blair Hills Dear Ms. Myott: As per our meeting on November 20, 2007, the following is submitted: ~•~ ~~ ~\ ~ ~~ ~F a ~ ~> l ~4T~ h%~U r~~ 1. The application fee of $2,000.00; 2. Five copies of the completed PCN for the modification of the 401; 3. One copy of the completed PCN Addendum; 4. Five copies of the site plan with previously permitted impacts and the proposed (modification) impact. As we discussed this modification is necessary due to the fact that the permitted (exempt) impact for the sewer line stream crossing cannot be accomplished. The permitted crossing was to be accomplished via bore and jack under the stream feature and if attempted could/would result in collapse. The modification if two fold. 1. To excavate the stream crossing and place the eight inch pipe into the trench and fill. This will result in only a temporary impact. If necessary, the stream will be dammed and the flow pumped around. Unfortunately this impact cannot be accomplished in a perpendicular manner as required by the Table of Uses. The exiting and receiving manholes are in place. The elevations and grade in the area of the stream crossing prohibit a crossing between 75 and 105 degrees. The buffer disturbance in this area will be kept to a minimum and will not exceed fifteen (15) feet in width. The trench will be backfilled with the excavated soil material immediately following the placement of the sewer line. - .-~,, .. X 2. To not construct the required preformed scour hole and allow the stormwater r~ to be treated while being conveyed through a centipede vegetated "swale" prior to delivery to an irrigation pond. This feature is man made and is located outside of natural drainage ways not subject to the Neuse Buffer Rules as per NBRRO OS-173. ~f'~''" All impacts other than the two mentioned above have been completed as previously permitted. These proposed impacts cannot be accomplished ~x.p ot~ - ll 3aV~ December 13, 2007 i or reduced in any manner that would better protect water quality or minimize the riparian impact. Best management practices will be utilized during all construction activities to minimize the disturbance, preserve aquatic life and habitat, and protect water quality. If you should have any questions related to the information presented or are in need of additional information please do not hesitate to contact me. My cell number is 919-971-6598 or nights at 550-9055. Sincerely, Steve Mitchell ECI CUS'TO~VI~ I~OI~~:~S, C. A Division of Shield Group, Inc. December 13, 2007 Ormand K. Strickland P.O. Box 898 Lake Glad Rd. Wendell, N. C. 27591-898 RE: Memorandum of Understanding and Agreement Dear Mr. Strickland As discussed, ECI Custom Homes and Development, Inc. would like to obtain a portion of your property for a storm drainage easement. The easement area is clearly shown on the attached easement maps prepared by Thompson Associates. This easement map is dated 12/12/07 and refers to a 20' private drainage easement across the rear of the property with a 10' temporary construction easement along the sides. We have paid for the preparation of the easement maps for clarification at no cost to you. We are prepared to pay you $ 1500 to use this portion of your land for the easement. If this agreement is acceptable to you, please sign below and sign the easement maps. I will return to you a copy of the map once the Town of Wendell has signed-off and recorded it. Sincerely, ~~ Accepted by (Propertyy Owner Jack Lic ter Print name: Ormand K. Strickland Director o elopment Sign name: !9' ~' . Date: l.~ - 1 ~- - Q 7300 Six Forks Road, Raleigh, North Carolina 27615 ~ (919) 250-9256 fax (919) 250-1389 www. ecicustomhomes. com ~.xp o~-1~3~ V2 ar_ ~ ~ ~ 2ooT ~_-~ oEr''R - ~A7ER 1#11ANDS ~ S i (1{Z~~ U~ ~- r Office Use Only: Form Version March OS USACE Action ID No. DWQ No. (If any particular item is not applicable to this project, please enter "Not Applicable" or "N/A".) I. Processing ~r~~n 1. Check all of the approval(s) requested for this project: ^ Section 404 Permit ^ Riparian or Watershed Buffer Rules ^ Section 10 Permit ^ Isolated Wetland Permit from DWQ ^ 401 Water Quality Certification X Express 401 Water Quality Certification 2. Nationwide, Regional or General Permit Number(s) Requested: NW 12 3. If this notification is solely a courtesy copy because written approval for the 401 Certification is not required, check here: ^ 4. If payment into the North Carolina Ecosystem Enhancement Program (NCEEP) is proposed for mitigation of impacts, attach the acceptance letter from NCEEP, complete section VIII, and check here: ^ 5. If your project is located in any of North Carolina's twenty coastal counties (listed on page 4), and the project is within a North Carolina Division of Coastal Management Area of Environmental Concern (see the top of page 2 for further details), check here: ^ II. Applicant Information 1. Owner/Applicant Information Name:ECI Development c/o Mr. Jack Lichner Mailing Address:8317 Six Forks Road, Suite 203 Raleigh, North Carolina 27615 Telephone Number:919-250 9256 Fax Number:919-250-1389 E-mail Address:www.ecicustomhomes.com 2. Agent/Consultant Information (A signed and dated copy of the Agent Authorization letter must be attached if the Agent has signatory authority for the owner/applicant.) Name: Company Affiliation: Mailing Address: Telephone Number:. E-mail Address: Fax Number: Page 1 of 8 III. Project Information Attach a vicinity map cleazly showing the location of the property with respect to local landmarks such as towns, rivers, and roads. Also provide a detailed site plan showing property boundaries and development plans in relation to surrounding properties. Both the vicinity map and site plan must include a scale and north arrow. The specific footprints of all buildings, impervious surfaces, or other facilities must be included. If possible, the maps and plans should include the appropriate USGS Topographic Quad Map and NRCS Soil Survey with the property boundaries outlined. Plan drawings, or other maps may be included at the applicant's discretion, so long as the property is cleazly defined. For administrative and distribution purposes, the USACE requires information to be submitted on sheets no lazger than 11 by 17-inch format; however, DWQ may accept paperwork of any size. DWQ prefers full-size construction drawings rather than a sequential sheet version of the full-size plans. If full-size plans are reduced to a small scale such that the final version is illegible, the applicant will be informed that the project has been placed on hold until decipherable maps aze provided. 1. Name of project: The Woods of Blair Hills 2. T.LP. Project Number or State Project Number (NCDOT Only): 3. Property Identification Number (Tax P1N):1783 44 5069, 1783 54 3219, 1783 54 7392 4. Location County: Wake Nearest Town: Wendell Subdivision name (include phase/lot number):The Woods of Blair Hills Directions to site (include road numbers/names, landmarks, etc.):Located on the east side of Lake Glad Road approximately 1075 feet north of its intersection with Old Nowell Road 5. Site coordinates (For linear projects, such as a road or utility line, attach a sheet that separately lists the coordinates for each crossing of a distinct waterbody.) Decimal Degrees (6 digits minimum): 36 76 57 N 78 37 75 °W 6. Properly size (acres):40.7 acres 7. Name of nearest receiving body of water: UT & Buffalo Creek 27-57-16(3 , C. NSW 8. River Basin: Neuse 03-04-06 (Note -this must be one of North Cazolina's seventeen designated major river basins. The River Basin map is available at http://h2o.enr.state.nc.us/admin/maps/.) 9. Describe the existing conditions on the site and general land use in the vicinity of the project at the time of this application :Infrastructure of development in place, roads, curb& gutter, etc 10. Describe the overall project in detail, including the type of equipment to be used: General earth moving equipment for road and house construction. The general land use in the vicinity of the subdivision is residential. Page 2 of 8 11. Explain the purpose of the proposed work: Di open trench across stream to place 8 inch sewer line. If necessary, block off flow of creek and pump around. Current permitting exisits for road construction (complete). Alter stormwater from approved pre-formed scour hole to centipede sod ditch with dischaz a to irrigation pond. IV. Prior Project History If jurisdictional determinations and/or permits have been requested and/or obtained for this project (including all prior phases of the same subdivision) in the past, please explain. Include the USACE Action ID Number, DWQ Project Number, application date, and date permits and certifications were issued or withdrawn. Provide photocopies of previously issued permits, certifications or other useful information. Describe previously approved wetland, stream and buffer impacts, along with associated mitigation (where applicable). If this is a NCDOT project, list and describe permits issued for prior segments of the same T.I.P. project, along with construction schedules. Project has received DWQ 401 Water Quality Certification DWQ Exp 06-1139) and Authorization Certificate per Neuse Buffer Rules NBRRO OS-173, General Certification WQC #3402, Stormwater Fermit NCGO10000 permit, and Wastewater Collection System Extension Permit (WQ0030834~ V. Future Project Plans Are any future permit requests anticipated for this project? If so, describe the anticipated work, and provide justification for the exclusion of this work from the current application. No further permits aze anticipated. VI. Proposed Impacts to Waters of the United States/Waters of the State It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to wetlands, open water, and stream channels associated with the project. Each impact must be listed separately in the tables below (e.g., culvert installation should be listed separately from riprap dissipater pads). Be sure to indicate if an impact is temporary. All proposed impacts, permanent and temporary, must be listed, and must be labeled and clearly identifiable on an accompanying site plan. All wetlands and waters, and all streams (intermittent and perennial) should be shown on a delineation rnap, whether or not impacts are proposed to these systems. Wetland and stream evaluation and delineation forms should be included as appropriate. Photographs may be included at the applicant's discretion. If this proposed impact is strictly for wetland or stream mitigation, list and describe the impact in Section VIII below. If additional space is needed for listing or description, please attach a separate sheet. 1. Provide a written description of the proposed impacts: Excavation and placement of 8 inch sewer line will temporarily disturb 23.2 linear feet of stream bed. A total of 2,375 square feet (Zone 1 1 415 and Zone 2960) of buffer will be disturbed within the permanent sewer easement. Existing_permitted impacts include two road crossing consisting of 103 feet of perennial stream and 48 feet of intermittent impact. Page 3 of 8 2. Individually list wetland impacts. Types of impacts include, but are not limited to mechanized clearing, grading, fill, excavation, flooding, ditching/drainage, etc. For dams, separately list impacts due to both structure and flooding. Impact COMPLETED. Wetland Impact Type of Wetland Located within Distance to Area of Site Number Type of Impact (e.g., forested, marsh, 100-year Nearest Impact (indicate on map) herbaceous, bog, etc.) Floodplain Stream (acres) es/no) (linear feet) Impact #2 Permanent Road Crossing Headwater wetland No +/- 120. feet 0.03 Total Wetland Impact (acres) 0.03 3. List the total acreage (estimated) of all existing wetlands on the property: 5.26 acres 4. Individually list all intermittent and perennial stream impacts. Be sure to identify temporary impacts. Stream impacts include, but aze not limited to placement of fill or culverts, dam construction, flooding, relocation, stabilization activities (e.g., cement walls, rip-rap, crib walls, gabions, etc.), excavation, ditching/straightening, etc. If stream relocation is proposed, plans and profiles showing the linear footprint for both the original and relocated streams must be included. To calculate acreage, multiply length X width, then divide by 43,560. 1 * is impact requested in modification of 401/404 Permit. Other impacts completed. Stream Impact Perennial or Average Impact Area of Number Stream Name Type of Impact Intermittent? Stream Width Length Impact (indicate on ) Before Im act {lineaz feet) (acres 1 * UT Buffalo Creek Temporary Perennial Impact #1 UT Buffalo Creek Permanent Road Perennial 11'-12' 103' 0.033 Crossing Impact #4 UT Buffalo Creek Permanent Road Itermittent 14' 15' 48 0.019 Crossing Proposed Temporary Stream Crossing Impact (by length and acreage) 15* 0.04 Total Permanent Stream Impact (by length and acreage) 151' 0.052 * Actual linear foot disturbance due to 60° crossing is 17.5 5. Individually list all open water impacts (including lakes, ponds, estuaries, sounds, Atlantic Ocean and any other water of the U.S.). Open water impacts include, but are not limited to fill, excavation, dredging, flooding, drainage, bulkheads, etc. Open Water Impact Name of Waterbody Type of Waterbody Area of Site Number (if applicable) Type of Impact (lake, pond, estuary, sound, bay, Impact (indicate on ma) ocean, etc.) acres NA NA NA NA NA Total Open Water Impact (acres) NA Page 4 of 8 6. List the cumulative impact to all Waters of the U.S. resulting from the project: Permitted Requested Stream Impact (acres): 0.052 0.008 Wetland Impact (acres): 0.03 O en Water Impact (acres): 0 Total Impact to Waters of the U.S. (acres) temporary 0.082 0.04 Total Stream Impact (linear feet): 151 15* * actual linear foot impact due to 60~ crossing is 17.5 7. Isolated Waters Do any isolated waters exist on the property? ^ Yes X No Describe all impacts to isolated waters, and include the type of water (wetland or stream) and the size of the proposed impact (acres or linear feet). Please note that this section only applies to waters that have specifically been determined to be isolated by the USACE. NA 8. Pond Creation If construction of a pond is proposed, associated wetland and stream impacts should be included above in the wetland and stream impact sections. Also, the proposed pond should be described here and illustrated on any maps included with this application. Pond to be created in (check all that apply): ^ uplands ^ stream ^ wetlands Describe the method of construction (e.g., dam/embankment, excavation, installation of draw-down valve or spillway, etc.): NA Proposed use or purpose of pond (e.g., livestock watering, irrigation, aesthetic, trout pond, local stormwater requirement, etc.):NA Current land use in the vicinity of the pond:NA Size of watershed draining to pond:NA Expected pond surface azea:NA VII. Impact Justification (Avoidance and Minimization) Specifically describe measures taken to avoid the proposed impacts. It may be useful to provide information related to site constraints such as topography, building ordinances, accessibility, and financial viability of the project. The applicant may attach drawings of alternative, lower-impact site layouts, and explain why these design options were not feasible. Also discuss how impacts were minimized once the desired site plan was developed. If applicable, discuss construction techniques to be followed during construction to reduce impacts. Wetlands delineated and impacts avoided and minimized. Permitted impacts are completed except sewerline crossing Protect is approved to jack and bore under the stream disturbing a much larder amount of buffer. The substrate below the stream is striated granite and this makes it impossibile to accomplish. Proposal is to dig and open trench and klace the sewer line in. (Three feet deep). VIIL Mitigation DWQ - In accordance with 15A NCAC 2H .0500, mitigation may be required by the NC Division of Water Quality for projects involving greater than or equal to one acre of impacts to Page 5 of 8 freshwater wetlands or greater than or equal to 150 linear feet of total impacts to perennial streams. USACE - In accordance with the Final Notice of Issuance and Modification of Nationwide Permits, published in the Federal Register on January 15, 2002, mitigation will be required when necessary to ensure that adverse effects to the aquatic environment are minimal. Factors including size and type of proposed impact and function and relative value of the impacted aquatic resource will be considered in determining acceptability of appropriate and practicable mitigation as proposed. Examples of mitigation that may be appropriate and practicable include, but are not limited to: reducing the size of the project; establishing and maintaining wetland and/or upland vegetated buffers to protect open waters such as streams; and replacing losses of aquatic resource functions and values by creating, restoring, enhancing, or preserving similar functions and values, preferable in the same watershed. If mitigation is required for this project, a copy of the mitigation plan must be attached in order for U5ACE or DWQ to consider the application complete for processing. Any application lacking a required mitigation plan or NCEEP concurrence shall be placed on hold as incomplete. An applicant may also choose to review the current guidelines for stream restoration in DWQ's Draft Technical Guide for Stream Work in North Carolina, available at http://h2o.enr.state.nc.us/nc~~~etlands/stlmfide.html. 1. Provide a brief description of the proposed mitigation plan. The description should provide as much information as possible, including, but not limited to: site location (attach directions and/or map, if offsite), affected stream and river basin, type and amount (acreage/linear feet) of mitigation proposed (restoration, enhancement, creation, or preservation), a plan view, preservation mechanism (e.g., deed restrictions, conservation easement, etc.), and a description of the current site conditions and proposed method of construction. Please attach a separate sheet if more space is needed. In situations in the past where stream impacts are under 150 feet or temporarypacts to unimportant/intermittent streams have occurred, mitigation is not required by the USACE and cannot be required by NCDWQ, therefore, mitigation has not been proposed. However, should mitigation be required, the applicant shall use the EEP. 2. Mitigation may also be made by payment into the North Carolina Ecosystem Enhancement Program (NCEEP). Please note it is the applicant's responsibility to contact the NCEEP at (919) 715-0476 to determine availability, and written approval from the NCEEP indicating that they are will to accept payment for the mitigation must be attached to this form. For additional information regarding the application process for the NCEEP, check the NCEEP website at http://h?o.enr.state.nc.us/~-rp/index.htm. If use of the NCEEP is proposed, please check the appropriate box on page five and provide the following information: Amount of stream mitigation requested (linear feet): 0 Amount of buffer mitigation requested (square feet): 0 Amount of Riparian wetland mitigation requested (acres): 0 Amount ofNon-riparian wetland mitigation requested (acres): 0 Amount of Coastal wetland mitigation requested (acres): 0 Page 6 of 8 IX. X. Environmental Documentation (required by DWQ) Does the project involve an expenditure of public (federaUstate/local) funds or the use of public (federal/state) land? Yes ^ No X 2. If yes, does the project require preparation of an environmental document pursuant to the requirements of the National or North Carolina Environmental Policy Act (NEPA/SEPA)? Note: If you are not sure whether a NEPA/SEPA document is required, call the SEPA coordinator at (919) 733-5083 to review current thresholds for environmental documentation. Yes ^ No ^ 3. If yes, has the document review been finalized by the State Clearinghouse? If so, please attach a copy of the NEPA or SEPA final approval letter. Yes ^ No ^ Proposed Impacts on Riparian and Watershed Buffers (required by DWQ) It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to required state and local buffers associated with the project. The applicant must also provide justification for these impacts in Section VII above. All proposed impacts must be listed herein, and must be clearly identifiable on the accompanying site plan. All buffers must be shown on a map, whether or not impacts are proposed to the buffers. Correspondence from the DWQ Regional Office may be included as appropriate. Photographs may also be included at the applicant's discretion. Will the project impact protected riparian buffers identified within 15A NCAC 2B .0233 (Meuse), 15A NCAC 2B .0259 (Tar-Pamlico), 15A NCAC 02B .0243 (Catawba) 15A NCAC 2B .0250 (Randleman Rules and Water Supply Buffer Requirements), or other (please identify Meuse Yes X No ^ 2. If "yes", identify the square feet and acreage of impact to each zone of the riparian buffers. If buffer mitigation is required calculate the required amount of mitigation by applying the buffer multipliers. Zone* Impact (s uare feet) Multiplier Required Miti ation 1 1067 3 (2 for Catawba) NA 2 920 1.5 NA Total 1787 NA " Zone 1 extends out 30 feet perpendicular from the top of the near bank of channel; Zone 2 extends an additional 20 feet from the edge of Zone 1. If buffer mitigation is required, please discuss what type of mitigation is proposed (i.e., Donation of Property, Riparian Buffer Restoration /Enhancement, or Payment into the Riparian Buffer Restoration Fund). Please attach all appropriate information as identified within 15A NCAC 2B .0242 or .0244, or .0260. Buffer mitigation is not uro~osed because all impacts are considered "Allowable". Page 7 of 8 Xl<. Stormwater (required by DWQ) Describe impervious acreage (existing and proposed) versus total acreage on the site. Discuss stormwater controls proposed in order to protect surface waters and wetlands downstream from the property. If percent impervious surface exceeds 20°l0, please provide calculations demonstrating total proposed impervious Level. NA Stormwater has been permitted XIL Sewage Disposal (required by DWQ} Clearly detail the ultimate treatment methods and disposition (non-discharge or discharge) of wastewater generated from the proposed project, or available capacity of the subject facility. WWTI' X~II. Violations (required by DWQ) Is this site in violation of DWQ Wetland Rules (15A NCAC 2H .0540} or any Buffer Rules? Yes ^ No X Is this anafter-the-fact permit application? Yes ^ No ^ ~iiV. Cumulative Impacts (required by DWQ} Will this project (based on past and reasonably anticipated future impacts} result in additional development, which could impact nearby downstream water quality? Yes ^ No X If yes, please submit a qualitative or quantitative cumulative impact analysis in accordance with the most recent North Carolina Division of Water Quality policy posted on our website at ~,~~ -iz~~7 ~,4i~-.~ ,~~ ,a~,~ ~E _+~~ ~, t;~,~_~~. If no, please provide a short narrative description: Project is already approved for the construction of 51 residential homes. XV. Wither Circumstances (Optional): It is the applicant's responsibility to submit the application sufficiently in advance of desired construction dates to allow processing time for these permits. However, an applicant may choose to list constraints associated with construction or sequencing that may impose limits on work schedules (e.g., draw-down schedules for lakes, dates associated with Endangered and Threatened Species, accessibility problems, or other issues outside of the applicant's control}. Applicant/Agent's Si re Date t~ I Z'1 ~? (Agent's signature is valid only if an autho ' do etter from the applicant is provided.) Page 8 of 8 TopoZone -USGS Knightdale (NC) Topo Map Page 1 of 1 `~~ r ~ ~ ~1~~01'MB'' " ^ ''~^.~i r~~~cene ~ ^ { 4 ~~ ~ . ~ ~ .. 4 ~ Try ~.r ^ °h. ~~ ^ ~~ ap f $ ~ ~ ~^ ~ .. r ^ - ~ .,,' ~~ ^ ~~~ t . ., r ~ ~. 11 9 .- ~ ~ .s . ^ ^ ^ ^ . ^ !f 1 ~ .r .~ ^ ~~ ~~ ~. ~ ^ ^ f ~ ^ _ -' ^ ^ ~ 4 ~ yl ^ ^ ~. = ~ 4 ,, ~ ~ ` ^ ~a tl .n Ma. ~,Y r ^ ^ x ~ ~. _ W......d` ^ ~ e ~ f ~f I # y' Y'~ 1 ~ ~~~ ~ ~e '* 0 0.1 4.2 0.3 0.4 0.5 km G 0 0.09 0.18 0.27 0.36 0.45 mi UTM 17 737238E 3961283N (NAD83/WGS84) USGS Knlghtdale (NC) Quadrangle i~•q~-;~;.~__;{_+ Projection is UTM Zone 17 NAD83 Datum G-1. ~~5 http://www.topozone.com/print.asp?lat=3 5.767&lon=-78.37575&s=24&size=l&u=4&lay... 11 /19/2007 Addendum to the Pre-Construction Notification and "Buffer Rules" Application Required for Projects Submitted Under the "Express Review Program" North Carolina Division of Water Quality Version 5.0 October 1, 2006 Email Address: 401express~ncmail.net Purpose: To provide a detailed explanation of the information required by the Division of Water Quality in order to expedite the review of applications for 401 General Water Quality Certifications, Isolated Wetland Permits, Stream and Wetland Mitigation Plans and Riparian Buffer Approvals (Please Note: do not leave any questions unanswered or use terms such as "N/A" without an explanation). Fees: 401 Water Quality Certifications Riparian Buffer Authorization: Riparian Buffer Minor Variance: Coastal General "Major Variance" Isolated Wetland Permit: Major (>/= 150' stream or >/= 1 acre wetlands) $2,000.00 Minor (< 150' stream or < 1 acre wetlands) $1,000.00 (exclusively or "in addition" to) $2,000.00 $1,000.00 $1,500.00 General $1,000.00 Please read the entire document before attempting to determine the proper fee. Fees are additive for particular projects. Things to keep in mind when filling out the application: A specific answer must be provided for each question. For instance, if a numerical answer is requested then a numerical answer must be provided along with the supporting information necessary for DWQ staff to verify that the number is accurate. Likewise, if explanations are presented to justify certain responses, the explanations must be completely supported by documentation. DWQ staff cannot assume that unsupported or undocumented information is accurate. "N/A" is not an acceptable answer for any question since the DWQ Staff reviewing the application must have an opportunity to determine whether or not any requested information is pertinent. All forms, guidance, worksheets, applications, etc. used must be the current versions as posted on our web site at http://h2o.enr.state.nc.us/ncwetlands. The Express Review Program website can be found at http://h2o.enr.state.nc.us/ncwetlands/express review.htm. Please note that it will be responsibility of the applicant or the applicant's consultant to verify that the current versions are used. The versions posted on our web site will be considered to be the current versions. You are a very important part of the success of this program, if you have suggestions or clarifications please send your comments to the Wetlands/401 Unit of the DWQ (via email at 401 express~ncmail.net). Filling Out the Pre-Construction Notification Application: The Corps of Engineers (USAGE)/DWQ official, joint Pre-Construction Notification (PCN) Application must be used as a basis for the expedited review process. The completed application should be presented first and the supporting information tabbed and collated in the same order. Using a custom format is not recommended. The open squares (~ are checklist items. The following items correspond to the numbering system on the Pre-Construction Notification Form (PCN): IMPORTANT: USE CHECK BOXES TO TRACK PROJECT /NFORMAT-ON!1 z SECTION I. PROCESSING i~ 1 8 2.The USACE determines which Nationwide, Regional, or General Permit is required. If you have verified with the USACE which permit they intend to use for your project or if yqu already have written approval from the USACE, please indicate by adding "verged" or "verified, attached, respectively, in the blank next to the Permit number requested. Attach the USACE Approval if you have it. ~i 3. It is not anticipated that the expedited process will be requested for this situation. i_' 4. If you propose to impact 150 feet or more of perennial stream or 1 acre or more of wetland and onsite mitigation is not proposed, it is recommended that you either locate an acceptable private bank with available credits (with documentation to show that the bank can and shall provide the credits needed) (~ or obtain approval from the EEP for the entire amount of stream and or wetland as DWQ will make the final determination as to whether or not mitigation applies. A complete Express application is not considered received unless an EEP approval letter is attached if mitigation is requested through EEP. Please note that the USACE may have different mitigation requirements and thresholds. ~~ 5. State whether your project will require a CAMA Minor, Major or General Permit and give the status of the permit. tJ J SECTION II - APPLICATION INFORMATION 1. 15 NCAC 2H .5020 reads as follows: "Who Mus# Sign Applications. The application shall be considered a "valid application" only if the application bears the signature of a responsible officer of the company, municipal official, partner or owner. This signature certifies that the applicant has title to the property, has been authorized by the owner to apply for certification or is a public entity and has the power of eminent domain. Said official in signing the application shall also certify that all information contained therein or in support thereof is true and correct to the best of his/her knowledge." ~-!~ Please indicate how the applicant meets the above definition and provide "supporting documentation. Please provide all of the requested contact information including a fax number and email address. 2. C7 If the a lication is not si ned b the a licant lease attach the a ent authoriz tion PP 9 y PP , P 9 a letter. The applicant must sign the agent authorization letter. The applicant's name and position must also be spelled out as many signatures are difficult to read. 3. C~ Please provide all of the requested contact information including a fax number and email address. SECTION 111-PROJECT INFORMATION The following is the most critical of all the information that you must provide. The quality and detail of the information will often determine the expeditiousness of the review. The following is a checklist of the types of pertinent information required at a minimum: Maps and Plans: The most recent version of the 1:24 000 USGS Topographic Map- Please cleanly delineate the site boundaries, etc. on the map. If the delineation obscures any of the features, it is recommended that a clean copy be provided. Please indicate the quadrangle name. You can go to the USGS web site (http://mac.usgs.gov/mapGstsn to verify the most recent version. ~' r~ The most recent version of the NRCS Soil Survey Map - (required for projects within the Neuse River Basin, Tar-Pamlico River Basin, Randleman Lake Watershed and the Catawba River Basin, also recommended for all projects) -Please cleanly delineate the site boundaries, etc. on the map. If the delineation obscures any of the features, it is recommended that a clean copy be provided. Please indicate the page or map number from which the copy of the map was made. Copies of the current soil survey and/or soil survey map sheets can be obtained from the local NRCS County Office (http://www.nc.nres.usda.gov/). GIS soil layers are not acceptable. ~~ Vicinity map -Please clearly mark the location and approximate boundaries of the property and project on the map. Please indicate north and scale. Please include applicable road names or State Road numbers. The Site Plan -The most critical map to be provided is the site plan. You must provide full 'zed ans. The following is the minimum list of plans that are typically needed. Pre-constructiontPre-existing conditions -This sheet must be scaled and include all jurisdictional and non jurisdictional wetland, stream, water features, State regulated buffers, topographic contours with elevations, approximate extent and nature of forest, field, landscaping, or other cover. Any existing structures and p~ impervious area must be shown. Existing utility lines and easements must be shown. Existing roads, culverts, and other pertinent features must be shown. North an'ow and the scale must be shown. Please note that the impact boundaries on the maps should correspond to the flagged impact boundaries in the field. { Proposed conditions -These sheets must be scaled and show all existing jurisdictional and non-jurisdictional wetland, stream, water features, and State regulated buffers (delineated into Zone 1 and Zone 2) must be underlain on the site plan(s). The plans must show all built-out structures and impervious cover. The plans must include the final grading contours with elevations. The plans must indicate all utilities and easements. It is likely that several versions of the final built- . out site plans will be necessary. Drainage Plans -Final drainage plans must be included. The plans should include the locations and pertinent elevations and sizes of the collection system and drainage ways. Alf inlets and outlets must also be shown with pertinent elevations. Scaled stormwater BMPs must also be indicated as required by DWQ rules and policies. In certain cases, final stormwater management plans must also be provided, but that will be addressed later in this document. Plats -The plans must show the location and layout of all sub-divided parcels with ~ot identifications. Platted parcels must be developable without further impacts to turisdictional and non jurisdictional wetlands, streams. water features. and State / , regulated buffers. f?1 Proposed Impacts -All impacts to jurisdictional and non-jurisdictional wetland, stream, water features, and State regulated buffers must be shown and labeled on the site plans. All excavation, fill, flooding, stabilization, and other impacts that will be conducted in or near jurisdictional and non jurisdictional wetland, stream, water features, and State regulated buffers must be indicated. 4 Wetlan/d Impacts (on the site plan): C~' Precise grading and final elevation contours must be provided. Existing vegetation and any clearing must be specified. All subsurface utility lines must indicate the location of anti-seep collars. Construction detail for anti-seep collars must be provided. ~~~ ~ Roadway or other crossings of riparian wetlands may require ifoodway culverts to maintain existing hydrological conditions. ^ When surtace drainage fea#ures or groundwater recharge areas that feed or would ~ reasonably feed wetlands that are not to be filled are made impervious, it may be necessary to direct some stormwater runoff to those areas in order to maintain hydrology. You must identify these areas and address them. Supporting explanations and discharge information must be provided to show that the wetland would not be eroded or receive too much or too little hydrology. In many cases this could help satisfy part of a stormwater management plan. ~! ~ Flooding ^ (~ Draining Stream/Impacts: r~! Stream impacts must be clearly shown on the plans. The centerline as well as the banks of the stream must be surveyed or located by GPS for the portion of the stream to be impacted. Culvertin~g~ ^ ~u 'The inlet and the outlet of the culvert should be aligned with the stream as much as possible. Inlet and outlet elevations and streambed elevations should be indicated. ^ ,I.f~Any widening of the stream must be shown with elevations. ^ ~(~he extent of and plan details for all dissipation or grade control devices should be shown with pertinent elevations. ^ ,/`~ For shorter culvert sections, such as for road crossings, a longitudinal cross section that shows the stream bed invert at the inlet and outlet, the existing stream bank elevations ,,` ~ the invert of the inlet and outlet of the pipe{s) must be provided. [_7 +" For shorter culvert sections, such as for road crossings, a vertical cross section must be provided that shows the stream cross section at the inlet and outlet overlain with the culvert and fill cross section. ^ ~ or bottomless culverts or other spans, a vertical cross section should be provided that shows the minimum distance from each span to each stream bank, the stream cross section, the height of the span above the stream and tfie minimum distance from the N edge of each footer to each stream bank. ^ „l1~ For bottomless culverts or other spans, a plan view must be provided that shows the a" location of the spans and the stream banks. ^ ~~For longer culverts or culverts that will pass beneath substantial impervious cover, it will be necessary to provide adequate plan detail to show that discharge velocity/energy will be adequately dissipated. ^ Cross section details must be provided showing the provisions for aquatic life passage. ~quatic life passage through culverts is typically achieved by placing the invert of the culvert below the existing bed of the stream per the USACE or North Carolina Wildlife Resource Commission guidelines. Other methods such as baffles may also be used. Please be aware that such placement may require the use of gradeNeiocity control measures up or down stream of culverts on steeper streams to prevent head-cuts or streambed erosion. The culvert placement relative to the streambed can be indicated on the longitudinal profile. Grade and velocity control measures mus# be indicated on the plan view and typical designs should be provided. ^ „~Itiple culverts, wide culverts or sectioned box culverts typically require the use of sills, `~~'' off-setting or other means to match the cross section of the existing stream (in order to maintain stream stability and provide aquatic life passage). A vertical cross section of the culverts should be shown overlain with the up and downstream stream cross section including the stream flood-prone area. ^ ~v impacts associated with dam construction must indicate and enumerate all fill associated with the dam footprint, spillway and any bank stream bank stabilization. The length of m im ounded must also be indicated and enumerated. Stream Relocations: Strea rons must be conducted as specified in General Certification numbers 3402 and 3404 (available on the Wetlands Unit web site). Stream relocation plans must include: ~~IGlorphological measurements (see Appendix B of the Internal Technical Guide for Stream Work in North Carolina available on the Wetlands Unit web site) -not all of the measurements are applicable in every instance. ^ ~ypical stream cross sections - Typically, a riffle cross section and a pool cross section that includes the entire flood prone area. The bankfull and flood prone area elevations should be indicated. Similarly, a riffle cross section of the reference stream(s) should be provided. ^ ~ Plan view -Provide scaled plans that show the location of the proposed (preferably with stationing) and the existing stream. In most instances, the bankfull contours and flood prone area contours, in stream structures, bank revetments/stabilization, channel plugs, ~' planting plan, vegetation conditions, stormwater outlets, grade controls, bridges, culverts, sewer lines, roads, fencing, and easement lines should also be provided. !~, longitudinal Stream Profile - A seated profile that indicates the thalweg, bankfull, and top (~ of bank elevations should be provided for the design and reference streams. In many cases, it will also be necessary to show the existing land elevations for the design stream. ^ 1 t`Planting Plan - A planting and/or vegetation management plan should also be provided ~" that makes use of appropriate native vegetation. The plan should indicate the extent, density, and species of plants to be provided. ^ stream structure, bank revetment/stabilization, and stormwater outlet typicals - 1 Detailed, typical plans should be provided for all in stream structures, bank revetments or stabilization, and stormwater outlets. The typicals should include materials and specifications as well as relative lengths, positions, and angles. ^ ~ Sediment transport analysis - A sediment transport analysis should be provided based on the current, relevant, accepted practices. The sediment transport analysis should be relevant to the streambed load type and should predict bed load transport equilibrium. ~~~ Permanent conservation easement or similar means of protection must also be provided. Other Irk#ormation: ~ f 1. The project should always be referred to by this name in all correspondence as well as the DWQ # once it is provided. f~ This only applies to DOT projects, which are not expected to utilize the Express Review Program. ~, 3. This should be the size of the project as ident~ed by the USACE for 404 Pemyits or by the Division of Water Quality for Buffer Approvals and Isolated Wetland Permits. r 4. Please provide the name (as depicted on the USGS topographic map and DWQ Stream Classification Lists) of the nearest water body(ies) to which your project is a tributary to (e.g. "Neuse River (Falls Lake below normal pool elevation)"). (Do not simple state "stream", "river", "ocean°, "sound" or "lake°.) Please provide the "stream index number" of the named water body or water body section (e.g. "27-(1)n). Also, please provide the full water quality classification (e.g. "WS-IV NSW CA") of the water body. This information can be obtained from the DWQ web site http://h2o. en r.state. nc. uslbims/Reports/reportsWB.html. 5. Please state which river basin and sub-basin that your project is in (e.g. "Neuse River Basin, NEU09'~. This information can be obtained from the DWQ web site / http:l/h2o.enr.state.nc.us/bims/Reports/reportsWB.html. ~! ~ 6. Conditions should also be indicated on the existing site plan where applicable. Photos (including aerial photos) can be helpful in describing the existing conditions. 7. You must provide an attachment that explicitly describes what the proposed project will entail from the planning stage to final construction. ~,, 8. This can be a simple explanation, but it is critically important because the purpose dictates how the no practical alternatives are reviewed. SECTIO~-PRIOR PROJECT HISTORY Please include copies of all 401 Water Quality Certifications, Isolated Wetland Permits, Suffer Approvals, USACE Permits, CAMA Permits for the site as well as a copy of the final approved, site plan. SECTION V -FUTURE PROJECT PLANS C~Y For projects utilizing the express review process, all impacts both present and potential future must be indicated. For instance, the location or configuration of platted lots sometimes suggests that future impacts will be necessary to build, access, or otherwise develop such lots. Failure to account for such potential impacts could delay or disqualify a project from the rapid review process. If you believe that the lot can be developed without impacts, but you anticipate that your assertion may be questioned, it is recommended that you provide a potential building foot print and/or grading plan to show that future impacts could be avoided. SECTION VI -PROPOSED IMPACTS TO WATER OF THE US ~~ 1. It is recommended that the individual impacts be described if there are special things to note about the impacts. Typically the most important thing is to have detailed accurate site plans as described above. Please make sure they are clearly labeled. Cr`Please include all proposed temporary impacts. ~a' Also, a current, signed delineation map from the USACE should be provided (if available) and a map locating the stream origins signed by the appropriate DWQ Staff must be provided if applicable. ^ 2. Each impact to a wetland must be clearly iabeted and identified on the site plan. the C type of impact must be clearly stated. (f the impact is temporary, a specific plan must IJ be described or shown as to how the wetland will be restored. Keep in mind #hat the USACE delineates some features as wetlands that DWQ calls streams. Please list any impacts in this table that DWQ would identify as a stream. If there is any doubt, it is recommended that the impacts be listed as streams. Please follow cun'ent DWQ policy with respect to whether a stream is perennial or not. It is recommended that you assume that a stream is perennial (unless you are positive that it is not) so if mitigation is required then the appropriate amount of mitigation would be anticipated or requested from the EEP or private bank. If the EEP or private bank has pre- approved too short of an amount of stream or if inadequate mitigation is proposed, then that situation wilt result in delays. 3. IYSometimes it is difficult to determine whether a feature is a mod~ed natural channel w~~~or a ditch, especially in the eastern part of the State. Soils, drainage features, 1" topography, macroinvertebrates, and similar factors, all are important for making that determination. ^ 4. '` lather items to address not specifically requested in the application include downstream sediment starvation, thermal pollution, low flow releases from dams, and aquatic life passage. Other important considerations are buffer reestablishment or mitigation around ponds on buffered streams. The site plan should include the precise elevation contour of the normal pool as well as the dam footprint. Mitigation is required for wetland flooding of an acre or greater and for stream fill (if over the 150 foot threshold) under the dam footprint and any outlet stabilization. SECTION VII -AVOIDANCE AND MINIMIZATION Avoidance and minimization are critical aspects of an application pardculariy if you desire the appNcation to tae processed expeditiously. The following is a checklist of avoidance and minimization questions that DWQ Staff often look for in applications. :` ~~ Are there any stream crossings at angles less than 75° or greater than 105°? ^ Are there anw y ~eam crossings that cross two streams above or at the confluence of those ~~s~~treams? Yv tJ ^ V`'~Cre there any stream, wetland, water, and/or buffer impacts other than perpendicular road crossing near the edges of the property? C the stream be relocated as a natural channel design as opposed to culverted or otherwise filled? ^ any single stream crossed more than once? ^ (~iCan property access routes be moved or reduced to avoid stream, wetland, water, and buffer impacts? ^~ ~ Can a building, parking lot, etc. be realigned to avoid impacts? ^ ~ Can the site layout be reconfigured to avoid impacts? f ~an headwalls or steeper side slopes be used to avoid/minimize impacts? ~~ _ Can a retaining wall be used to avoid/minimize impacts? ^ ~ Can cul de sacs be used in place of a crossing? 8 ~ Can lots be reshaped or have shared driveways to avoid impacts? If based solely on the practicable physical possibility, the answer is "yes" to any of the above questions then you must have to provide substantial and convincing justification as to why the impacts are necessary. If the impacts are required by a local govemment or other agency, the claim must be supported with appropriate written documentation from the local govemment or other agency. Most projects typically involve the need to justify avoidance and minimization. If this information is not readily available, then the express review process may not be the appropriate venue to use. Providing alternative plans (such as plans that avoid the impact, minimize the impact and the preferred plan, similar to those used in environmental assessments) and explanations as to why the preferred plan is needed and why the alternative plans won't work are many times helpful in the no practical alternatives review. SECTION VIII -MITIGATION Mitigation for the Express Review Program, final mitigation plans must be presented up front. The final plans (except for plans that propose payment into the Ecosystem Enhancement Program (EEP), Riparian Buffer Restoration Fund, private mitigation banks, or similar banking instruments) must contain detailed plans, specifications, calculations and other supporting data that show that the appropriate mitigation will be achieved at the ratios required. The design plans must be developed to at feast the "90%" level. Monitoring plans must be final and specific. Any means of permanent protection, such as a permanent conservation easement must be provided. If you elect to use the EEP or a private mitigation bank, it is recommended that you request the maximum possible mitigation amount that DWQ may require so that you will not have to get further approval from them on short notice. The EEP and private banks are not park of the expedited review process and cannot be expected to meet any such deadlines. There will be no conditional expedited approvals that require final plans at a later date. It is not recommended that innovative mitigation techniques or greater than 10°~ preservation be requested as part of an expedited process. SECTION IX If your project requires the preparation of an environmental document under NEPA or SEPA and an approval letter has not been issued by the State Clearinghouse, then you cannot apply under the expedited review process. It is your responsibility to find out if such documentation is required. SECTION X There are many aspects of the Buffer Rules that must be addressed in every application, if applicable. The first and most important thing to keep in mind is that allowable activities that require written Approval from DWQ triggers a review of the entire project for compliance wi#h the Buffer Rules. Diffuse Flow ~ Storrnwater Management: The most common issues that arise involve the requirement for diffuse flow of s#ormwater through riparian buffers. Basically one of three things must be indicated in regards to all "nevi' stormwater that is collected and subsequently discharged. First, provisions for diffuse flow through the protected buffer must be made. This usually involves the use of level spreading devices designed to the latest DW4 guidance on level spreader design, which is available on our web site. Please keep in mind that it does not matter how far a discharge point is from a buffer. The stormwater must be flowing in a diffuse manner at whatever point it eventually reaches the buffer. If the stormwater will not be flowing in a diffuse manner through the protected buffer at the point it reaches the buffer, then one of the following options may be allowed: ~~ You may provide a nitrogen removing measure such as a forested filter strip, grassed Swale, stormwater wetland, etc. The measure employed should be 9 designed according to the NC DENR Stormwater Best Management Practices Manual or other DWQ Guidance available at http://h2o.enr.state.nc.us/ncwetlands/regcert.html. After the nitrogen is treated, the `~stormwater can be directly conveyed through the buffer with written DWQ approval. R1'' You may discharge the stormwater to an existing man-made conveyance that `" currently conveys stormwater through the protected buffer (assuming the conveyance was not constructed in violation of the Rules) as long as that conveyance does not need to be altered to convey the flow. Please remember that there are no other choices. The following checklist is intended to help insure that your application will not be deemed incomplete as a result of improper stormwater design. Storrnwater Management (for Buffer Rules compliance only -Also, see Section XI): AA stormwater out-falls must be clearly shown and labeled on the si#e plan for projects in Buffered watersheds. List each out-fall as labeled: G~ Option 1: Level spreading devices designed to the latest DWQ Guidance, and devices that merely control velocity but do not provide diffuse flow such as rip rap dissipators are not proposed. List each of these out-falls as labeled on the site plan and provide a DWQ worksheet available at /http://h2o.enr.s#ate.nc.usficwettands/regcert.html: G~' Option 2: Nitrogen removing measures designed to DWQ Standards are proposed for discharges for which diffuse flow through a protected Buffer cannot be met. List each of these out falls as labeled on the site plan and provide a DWQ worksheet available at http:/lh2o.enr.state.nc.uslncwetlands/regcert.html D ~' option 3: The stormwater wilt be discharged to an existing man-made (not including modified natural channels) conveyance that carries the stormwater through the Buffer. The conveyance was not constructed in violation of the Buffer Rules. Lis# each out-fall as labeled: [~ All stormwater out-fall must meet one of the options above. (Note: if you cannot check this box your application will likely not be accepted into the express review process.) Site Plans: [>~ All applications on properties with DWQ protected buffers must clearly depict the buffers and any impacts to the buffers on the site plans. The impact maps should clearly depict both zones of the protected buffers and the proposed impact areas (provided in square feet). Surfac/e Water 8 Buffer Delineations: G% Any surface waters subject to DWQ protected buffers must be field located and accurately depicted on the site plans and impact maps. The width, dimensions and pattern of the surface water must be delineated. The surface water location must not be taken simply from a USGS map, soil survey or local municipality's map. The buffers must be measured from the surface water as required within the applicable buffer protection rule (e.g., all buffers along streams subject to the Neuse and Tar-Pamlico Buffer Rules must be measured from the "top-o#-bank° of the stream and not the centerline of the stream). Alt streams must be surveyed or located by GPS and shown precisely on the site plans. Impact Table: 10 GY Please provide additional impact tables that Dearly state the area of impact for each corresponding impact site. Variances: ;{~ ~ ^ Projects that require a Major and/or "General° Variance will not be eligible for the use of the Express Review Program (with the exception of the Coastal General "Major Variance. Mitigation: rJ (~ ^ As opposed to applications that are submitted under our regular process, final mitigation plans must be presented up front (see requirements for Section Vlll above). The mitigation plans must comply with the applicable buffer mitigation rule. SECTION XI - STORMWATER Please provide the following information in regards to potential stormwater requirements: ~~ The total acreage of the site. '~~ ~ ~' (acres) The total built-out impervious acreage ®. 5 (acres) ~~~ The total area that wiN be disturbed ~, (acres) ~ ~~ / q ~~ ~/.: ~-~ [~ l,. c~'~ ^ If the total area exceeds 20% imperviousness, the development on the/site is uniform in j ~#'`"T~ density, and you claim that the total impervious area is less than 30°k, you must provide a l~~jUO 2,(~- complete, detailed breakdown of the assumed built-ou# conditions. The breakdown must v be detailed enough to show that all potential impervious areas are accounted for. ^ If there are concentrated areas of development such as multi-family, commercial, cluster, club houses, etc. that exceed 30% imperviousness and the total imperviousness for the site ~ ~ does not exceed 30%, a stormwater management plan will likely be required for those ~1,~,., areas that exceed 30% imperviousness. ~~ ,~ ~ Stormwater management plans must be complete with a final design and an executed ~~' Operation and Maintenance Agreement. There will be no conditional stormwater approvals ~ for the express review process that allow for approval of the final plans at a later date. ~~~ ' Worksheets must be provided that are available at http://h2o. ehnr.state. nc.usJncwetlands/mitresto.html. SECTiO~ -SEWAGE DISPOSAL Response must be clear and detailed. Any disposal method that suggests further impacts may be required other than those shown must be clearly addressed on the site plans. SECTION X111 ^ Answering yes to either of these responses automatically precludes you from the express review process. SECTION XIV -SIGNATURE The name, position and/or title of the applicant must be in type or long hand script here with the signature. It should be the same person as described in Part II. If you have any questions about these requirements, please email the Express Review Program at 401express~ncmail.net and include your question and phone number and the appropriate staff will respond as soon as possible. `o~~F W AT ~9QG ~ r '~'~ ~~~~~ ~ I./~W~•~/~ 0 `~: ~ „~ ,~~• Michael F. Easley, Governor William G. Ross Jr., Secretary North Carolina Department of Ernironment and Natural Resources Alan W. Klimek, P.E. Director Colleen H. Sullins, Deputy Director Division of Water Quality July 1, 2005 Mr. Chris Flowers S&EC 11010 Raven Ridge Road Raleigh, NC 2'1614 NBRRQ OS-173 County: Wake BASIN: Neuse River X Tar-Pamlico (15A NCAC 2B .0233) (15A NCAC 2B .0259) Complaint NOV Buffer Determination X Incident # Appeal Call Project Name: Woods olBlair Rill Property -Wendell Location/Directions: Site is located on the east side of Lake Glad Road (NCSR 2358), .approx. 600 feet north of the intersection of Lake Glad Road and Old Nowell Road in southern Wendell (Wake County). Subject Stream: UT to Buffalo Creek Date of Determfnation: 6lZ~OS Feature Statt Buffer GPS Points (if provided) End Buffer Stream Form Appeal Call Located on Soil Surv Located on USGS Too his A Subject (Not Contested) X X B Subject (Not Contested) X X C Subject Throughout X D Subject at "Start D" Flag X This on~ite determination shall expire, jive (S) years from the date of this letter. Landowners or affected partlcs that dtsp:rte a determheatlon made by the DWQ or Delegated Local Authority that a surface water exists and that U is subject to the bu,,~'er rule may request a determlbtatlon by the Director. A request for a determination by the Director shall be referred to the Director in writueg c% Cyndi Xaroly ,DWQ Wetlands/401 Unit, 2321 Crabtree Blvd, Raleigh, NC 2760 2260. Individuals that dispute a determination by the DWQ or Delegated Local Authority that "exempts" a surface water from the buffer rule may ask for an ad, judicatory hearing. You nwst act within 60 days of the date that you receive this ielter. Applicants are hereby notified that the 60-day statutory appeal time does not start until the affectedpar[y (including downstream and adjacent landowners) is notified of this decision. DWQ recommends that the appUcant conduct this notijlcatton !n order to be certabt that third Raleigh Regional Office 7628 Mail Service Center ?;{:GLi`~:~ phone (919) 571-470Q Customer Service Water Quality Section Raleigh, NC 27699-1628 facsimile (9i9) 571-4718 1-877-823-8748 7/1/2005 Page 2 of 2 party appeals are made hs a timely manner. To ask for a hearing, send a written petition, which conforms to Chapter ISOB of the North Carolbta General Statutes to the t~fice of Administrative Hearings, 6714 Mall Service Center, Raleigh, N.~ 27699-671 This determtnatlon is final and bindbeg unless you ask for a hearing within 60 days. The (owner/future owners) should notes the Division of Water Quality (including any other Local, State, and Federal Agencies) of thb decision concernbtg any future correspondences regarding the subject property (stated above). This project may require a Section 404/401 Permit for the proposed activity. Any inquiries should be directed to the Division of Water Quality (Central O,~Rce) at (919)-7331786, and the US Army Corp of Engtnper,~ (Raleigh Regulatory Field Office) at (919}876-8441. Eric W. Kulz Environmental S ec. III CC: File Copy Central Files DWQ 401/Wetlands Office Teresa D. Piney -Town of Wendell ~_ Raleigh Regional Offlce 1828 Mail Service Center `;i;.lll:i.~ phone (919) 571-4700 Customer Service Water Quality Section Raleigh, NC 27899-1828 facsimile (919) 571-4718 1-877-623-6748 + ~ l r.: r, ~~~ ~. r: ,~ o~ ^ Q LL.\ 1~,f~(~~,p_ ._.,- '1-14 ~ , App ~ .. •q ~ ~, ; ~~) ,4y• ~ ~~ J is 300 - .1 ~ 23 ~`~,, " ~ .• ~, a , . ~ /:i . -rr,t ~. ,~~ s ~ , ~ . .. ~ ,° s ~ ~, :., , ~ . ~ fir""` r, ~ pis ,... ,` ~ ~ ~ ~ _,-; r \ ~ ~ ;~ ~y-Y- 33 ~r, • Lam'" ~~ , `}';~'''. , ~,-,~'--= -_ ~ ;~ . i _- _ ~ .. ~ ~; .r ~~~ N - ~.r~ ~ •~- ea Lc ~~. .~ r `-~ ~„ } .. . . .. ... ._ - ! ~•.,. J _ /:~'{ . Project No. Fi ure 1- USGS Ma 9an.w~ g p Protect Mgr.: The Woods of Bfair Hill sc Thompson & Associates Wake County, NC Scale: 7- ~ 2~000~ 03122/05 Zebulon, Knightdale, Clayton and Flowers Quadrangles y . ~ ~ ~.~,1 = v \.J f ~`:= it .:: !~i' /~,~'/ ~L.. ~ ~ ~...~._<.~ r t ~ Soil & Environmental Consultants, PA 11010 Raven Ridge Rd.• Raleigh, NC 27614 (919) $48900.1919) 846-9467 Web Pape: www.SandEC.can ~ ~ OS ~~ r , ,;-+~f a ti . ~LY.Ll.tY tJ S O~T Ll~ l i~-LC J. - Action FD. ZQQ640822-29Z CauIIty: Wake USGS Quad; l<nit=ittdal$ GEI+IERAL PEF.I~T (REGIONAL AND NA'1'ION~~E} FER~.F~CA'~I~I1~ Property Owner I Authorized Agent: M_ iilrid~e Companies Incorporated Address: 818 S. White Street 'Wake Forest, NC Telephone Na.: 919-556541,$ Size and location of property (water body, road na€ne/number, town, etc.}: The raronerty is located on the east side ssf fake Glad Road, aE3nroximately 1U75 ft nortfr of its intersection with Old Ptowefi Road, Wake County, lYC 3~escriptaan ofprojects area and aet~viiy; 'his termit authorizes the imr3act of #?.{}~ acres of wetland and 151 linear feat of stream, associafed with a suirdivision read. - Applicable Law: ~ Section 444 {Clean Water Acts 33 [TSC 1344} ~ Section l4 {Rivers and Harbors Act, 33 USC 443) Authoriza#ion: Rcgior=al General Pernvt Number: Nationwide Permit Number: 39 Your work is authorized by the above referenced permit provided it is accomplished in strict accordance with the attached conditions and your submitted plans. Any violation of the attached conditions ar deviation from your submitted plans may subject the pennittee to a stop work order, a restoration order and/or appropriate legal action. This verification is valid until the NWP is modified, reissued, or revoked. ~ of the existing NWPs are scheduled to be modified, reissued, or revoked Prior to March l8, 2447. It is incumbent upon you to remain informed of changes to the NWPs. We will issue a public notice when the NWPs are reissued, Furthermore, if you commence or are under contract to commence this activity before the date that the relevant nationwide permit is modified or revoked, you will-have hvelve {12) rrtonths from the date of the modification or :revocation of the NWP to complete the activity under rite present terms and conditions of this nationwide permit. If, prior to the c:.piration date identified below, the nationwide permit authorization is reissued and/or modified, this verification will remain valid until the expiration date identified below, provided it complies with alI new and/or Btodified terms and conditions. The I}istrict $ngineer may, at any times exercise his discretionary authority to modify, susperad, or revoke a case sgecif~c activity`s authorization under any NWP. Activities subject fa Section 444 {as indicated above}.may also require an individual Section 441 Water Quality Certification. You should contact the NC Division of Water Quality {telephone (919) 733-3786}'to determine Section 441 requirements. For activities occurring within the twentp coastal counties subject to regulation under the Coastal Area ltifanagement Act (CAMA}, prior to beginning work you must contact the N.C. Division of GoastaI Management . This Department of the Army verification does not relieve the permittee of the responsibility to obtain any other required Federals State or local approvaLslpermits. If there are arty questions regarding this verification, nay of the conditions of the Permit, ar the Corps of Engineers regulatory Program, Please contact Thomas Brown at (9I9} 876-8441 x22. Corps Regulatory O£frci Bate: September 21, 20x6 Expiration Date of Verification: l+llarch 1 , 21)47 Copy Furnished: -ebt~ie Edwards ~C~ ~ r~ ?Q~0 S&.EC ~101~ Raven Ridge Road sr- Sad & tat ConnAtants PA Raleigh, NC 27014 .Page 1 oft r .~n CX-p Cla " 1 8~`~- Y G. INDEX Of SHEETS fOR THE WDODS Of BU/R HILL STORMWATER AND IMPACT MAPS PREPARED BY THOMPSOAi Et ASSOCNIES, P,A SNEEt` 7 -- L'XfSt;NG CCS~dt?l1tONS St#EE7 2 - S17E" ACAPsP SMEEt 3 ~ 574ttAi4L97ER / £,f`057ON CL3NfRDL Atr?N SMEE7 4 ~- ~TURA~t~A7t"R ~~ EROS~N CDN1ROt PLAN 5NE£7 3 - I~4PAC7 ~1P S~lEE7 b - MNL~f,LTJ ~AfPAC7 AREA k4AP NOTES: ALL APPLJCABLE LOCAL AND STATE PERMITS SHALL BE OBTAINED PRIOR TO THE START OF CONSTRUC110N, \, ACCESS {N07 PART ~ SITEj ~~ 0 VIC1NiTY MAP NO SCALE STORMWATER AND IMPACT MAPS FOR THE WOODS OF BLAIR HILL NORTH CAROLINA DIVISION OF WATER QUAILITY MARI~,S CREEK TOWNSHIP -WAKE COUNTY WENDELL -NORTH CAROLINA ~~~~~~~L~~~: EGI ~4hdES THOMPSON do ASS{1CIATES, PA ~~C~ 153 HOLLY ~'R1NGS ROAD G` `, ~~ HOLLY SPRINGS, NC 27540 4 1 ~ /, FAX {9i )7577D9 PREUNINARY PLANS FAR, lO~j (((,,,,,,,,,///,,, NOT RELEASED fOR CiNiSTRUCTION h'qj ~~,sf FRO ~,~ An 'T7 PRa~ERnES ARE wrtx~u AREAS of n~E roo YERA ~ 500 TEAR goons fEIII ADOn H~LIRO SOUS ARE I.oCATm ALOhG THE HoRTrI<RH AID E4SIERM PAbPERTY LNII£ FEIN YAP 37t83C0602 $ 20/~ x FEIII YIP i 3718300603 F, 20NE .~ . AITE 03/03/}98?. BFE EtfYA 753.00 dC ?3&00 APPEAR ON THE fEIIi PAAlEt. I ~I~MI ~t I ( _ _ ..~ 1 1 :, i ~ i ~~ r~ .tEnb . ~. ,'~. ~ y w~ w // ..~~ :s::=i}'»,,;µ;wµ:::^{ .:_:.:, ~~:~ .....::7 ~~ ~~ ~~~, A1MIL! t A ~~ r _., w~~3';iZC SCALD r `~' _ ;,aD :~x3 * ~ R ' s I , I 1 ~ ; ~~~ r I ~ l____ _ t i ..__~ h t s r " ~.-~ ~ ~ I Er^ "a ! `ta 3 ~ P t^ i i '-~ y_ .._ ~..~..~:.~.,~... ..._.a i i t i _.~.~ ~~ ~ u+c ~ ,,- u+e o~ ,. o c~enc ~,,- ~"~r~ 1uY~~C N w ' .~~ ~ ~ : r: ~• % ~~~ . ,~~~i ~1 i it ~ ~ ~ { ~ ~s jt T 'llli ti i "~ i ! ~t'~~°~ ~i ., „„ ~L3 ~! ,~ p4;{ ?`i~~ R g +43 ~> ~r~~~~ ~ `4 ~ 3. f!3 ~~ ~„,",r r ~~_ r~s ~ ~a Y k. ~ ~ b .,~ viM'~o ~~ ~; l~ ~~g' '+~ i i .. ..gyp, "~ ' ;~ t` " ~ ~ r ~ . ~ •t ~ [< *N ~ '$ ~ ~ ~ ' a ~°~~~~ ,~~ ~ ~~~ ~~~ ~ ~ ~ ~~ ~ ~~~~~~ ~ ~ cam: ~~'•~s~~n~ z ,~~4 R R a~ __~ ~~ :~ ~ ~ s ~. ~ s ~" ~. ~_ F I "~ ~~ ~~ ~~ ~ ~ ~w ~, ~~ ~~~~ ~~~~~` '~<~, yam" ~~~~~ ~~ a 3 3 S i$ z ~ i f f ~_.~. ~,; ?> k~,.? ~ ~'~ e ~ ~'' ~e i i f i i t f 3 ~, : _ : , . ____~ ~ ! '" ~ Est ~,s l ~~~,.-~f t ~ 7 i t 1 ~~~ ~~ ~ ~~ ~ ~ ~ ~ ~ ~ ~~ ~ ~~ ~~ ~~ ~ ~~~~~ M L --- .1 , ,~,,. W~ 'b .-~' ~^1 c7 ~~ ~ ~~~` ~~~ ~~~ n sa ~~* l 4 n ~~ ~~ ~i ii !~ ?i ~~ `t` E~ ~ ~ ~ :~ L: 1p~ k , YiV 4 . . . . . . . . . . . . . . .. .. ... . . . . . e .~yh~'t d~3` ~~ i i J ~_ q b~p~~ ~'h 4t N .fCiQtj uj ~~~~ M ~y ,' ~'I jjiii ~S~is ~x ~5 ~, ~~ ~,~ ~~~~~ ~~ ~ ~,~~~ x ~Q ~~ i '`i' '~ j# } , ~ ~~ ~~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ . ~ ~ ~ ~ Q j ~ Y ~a it q~ 4. ~ ~ ~ Y ~ p. ~ ~ ~ ~ ~~ ~ ~ ~ ~ ~ s ¢~ ~ ~~~ ~ " s~~~s~~~~ ~~~~ s~ ~~~~~~ s~~ ~~~~~~~ ~~~~~ s~~~s~~~ ~s~~ s ~~~~~s~ ~~s ~~~~~~~ ~~~ ~ ~ R ~~47 ~£@~'v ~g E~t ~2A3t f~Y^~~Y ~`d Sd7E 9~~d Ek ~A~~~$``~,f ~V ;2tk~~a f3 di~tl dR2 ~N taB~T~ Z~~i ; Y E ~^yP~~4 $w' g12k4 ; h t yi~~ 2~ ~ ~ ~~~Y~Qq~iK~11g4Y iw ~i i~ l ~r~ % ~3 ~~~~i0 `re~R~ p ~s~~ y ~e g d~~ ~ ~ m rw r t z ~~ a ~r nc4r r~* } ~ if . $ ~$ $ y Q ~ Q ~ & $ ~Q ~ ¢ ~ Q ~ p Y A -K O4Y 5xwrn.49x- "~X J'~ xd S 0.fY~cvi a-~~•~ { x>t^a ~~",>~~y., ~,a g!: ~j ~.:r ~ ~ s, ~ ~ s~s~rsr ~~3~~ ::.~~:~ ~ ....~.. 1 .....~~ ~ :a~e~~~ ~~~3~:~ <fi~~ ,~aas::s ~~ _€ ~9 ~~ 3 j $A Y8~ N G ~ yyA~~. W ~ K ~ ZA A Y L~ ~ Y Y a ~ ~~ ~$~~ a " ~`Y Y es,~ dtb ~~~ ~~ ~~ Y ~x ~~ Y ~ ~ ? ~. ~~,,: ~~ ~, ~~, ~~ ~~ ~~ ~.~ ~Z wa __ i PROPOSED tMPACT AREAS - AdPACf 11 ` L{~ll~t e 1 . ' E ~' 11151 pi ~~~ OFLY~ Cf&,Y ia4,'. .n.» 1 1~ X3 ~ dt+2 zz ass ror~. 9s+~ -- /~~ / •/ P " 1 MIFFCTt, Z1 *~ Xf~E 1.. za ztR~ ~. • ~ % ~ m1~ ~ b ~, . i IMPACTED / AREAS (INCLUDES • c~,L DISSIPATO ~ R) +'ryr ~:' ~ A /~ ti ;~ i ~F" ; i•, • r . •... ~ ,~ ~; ~: ..,, i ~~ Rey p ~.,.•t.~.:'-'~,.:;:; ~ ~ II - -.. I IMPACT ~' JAIPACT A4TP THE WOODS Of BlA1R H1i1S 7V[ s°I4-0~ MNM N0. 1~ID• 7$ lF 48" RCP MATH 24' LdrNi DISSIPATdR. PIPE TO HANIX.E EXISTING FLdW 1HRU DRAW. NO ROADWAY RUNOFF TO ENTER PIPE. ROADWAY RUNOFF TO FLOW TO CI ~ 13 do id THEN TO BMP ,: PROPQ6EO A~ACT AREAS - IMPACT !2 i ~ ~ I ~- I I ~a `. 1.'3 ~~ ~ ~~ :~%~ ,;~ ,;• i ,, '~~ ,1 ~~ ~~ r~ • ~,~ , `~ ~i'~ Z .p ~ '' ~0~ ^' ~ ,.,~ 2~~ IMPACT j2 S ~. ~P' I 74 LF 30" RCP MATH WETLANDS I 15' LdNG DISSIPATdR. PIPE TO HANDLE EXISTING FLOW 1HRU DRAW, Nd ROADWAY RUNOFF Td ENTER PIPE. RdAdWAY RUNOFF Td fldW TO CI ~' 11 @ 12 THEN TO BMP UtPACT AlAP THE WOODS OF BLAiR N1LiS TSSOIWSO~N~ ASSOCIATES. PA ~sacm+aaw i o rr~wa sw r . a ~ saac n" ss .1 ~. ~. ,r c~ ~. aaa mart 9s • ?~ XR 1875 d za at~z - a saa= - !! • a€- ~« rm ~ Pi6 • FE&~'Gpk, Xt " ~~ R, " 2~d£ Z t ~ J~ '• J% ^D! "kMSaT ~ ~ j ~ ~ ~ ~~ ~ ~. ~~ ~ ~ ~ ?'' ,~' .~ ~ ~ REMOVE EX. HEAOWALL`~ f ~ ~~•'•' .;COQ 'ANb EXPEND EX. 38" RCP ~ ~ ~' / q ',32 LF WITH 15' LONG DISSIPATOR ~ 9~ F •' .• ~j, ,~ °~i' f •, ~f 1 CVO 2 _a i / ~'^.. i 15' MADE TEMPORARY IMPACT FOR 8" SANITARY SEWER CROSSING THROUGH EXISTING CREEK. TEMPORARY IMPACT Td 80TH THE EUFFER AND / CHANNEL. OPEN CUt FOR 1 THE} SEMA/R' CROSSING. ~''. ! ~GI•' cCoh.. 6 • ~ ~ ~' ~• ti `. ~: ...-.; , I DPEN :::~::::.. SPACE ~i'., :::: •~~ ; ~ .... ~ ~ .. '~ I i~ ~' ~~ I I ,, ;~ I .; ~_ %~/ i' ~~ ,, ' 1 i // IMPACTED / ~' f r/ ~~~~~~ ~ n R j '~ ER •. ~... OF .~ ~ ~ ` l c~~` '~~.. tUp ~ ~'• 9~cr ~ a rt. "" as. • a u+ ( as,~ , 3 P~ 27 3fli7 x797 ..,` ~PROPER'tY UNE IS CENTERLINE OF ~, ~ . ,~ „ ~,,, EXISTING CREEK ~. t~ > s ~ 21 ~ i, 3& x 2 2 IMPACT AtAP THE WOODS Of BWR HlilS ~ x ~9iR 1h1R-qJ Y s ~pqM iR Y . 1D' !at M1 90 ' ~ ~ r ~• ~• ~p~v~.F- ~~ ~ a ~ ~ , ~; .;~ IMPACTED ARC (~ / }n `~ ~"1 P / IiMPACT ~ ~ S ' ~ U '` ~ R/w ~ \ y ~~ SQ' pUD SR 2358 REPLACE AND EXTEND RAM' EX. 15" RCP 88 LF JAVP~cr AtAF ~ JHE WOOAS OF BU1B HltlS ~ , J w9oiuarnon~'PA Iw" I ildlY s•u-r ~~~ ~ r.,rt sac+tisa ~ 1 c~w~eP jDEYE1.OPER: £~S IIC~tIES 7~1 Slk FOR#S Rs'3RD I RA1EE~ls, NC 2i6T5 i iS19) S69-Ad~S SNFET 6 I r ~. • ~~` ~ ~ ' p>L _