HomeMy WebLinkAbout20061139 Ver 2_401 Application_20071207.'
Steve Mitchell
Environmental Consulting
1813 Lancaster Drive
Gamer, North Carolina
27529
919-550-9055(h)
919-971-6598 (c)
srtnitcheil51 ~yahoo.com
Lia Myott
1650 Mail Service Center
Raleigh, N. C. 27600-1650
Subject: Modification of DWQ EXP# 06-1139v2
The Woods of Blair Hills
Dear Ms. Myott:
As per our meeting on November 20, 2007, the following is submitted:
~•~
~~
~\ ~ ~~
~F a ~ ~>
l
~4T~ h%~U
r~~
1. The application fee of $2,000.00;
2. Five copies of the completed PCN for the modification of the 401;
3. One copy of the completed PCN Addendum;
4. Five copies of the site plan with previously permitted impacts and the proposed
(modification) impact.
As we discussed this modification is necessary due to the fact that the permitted (exempt) impact
for the sewer line stream crossing cannot be accomplished. The permitted crossing was to be
accomplished via bore and jack under the stream feature and if attempted could/would result in
collapse.
The modification if two fold.
1. To excavate the stream crossing and place the eight inch pipe into the trench and fill. This
will result in only a temporary impact. If necessary, the stream will be dammed and the flow
pumped around. Unfortunately this impact cannot be accomplished in a perpendicular
manner as required by the Table of Uses. The exiting and receiving manholes are in place.
The elevations and grade in the area of the stream crossing prohibit a crossing between 75
and 105 degrees. The buffer disturbance in this area will be kept to a minimum
and will not exceed fifteen (15) feet in width. The trench will be backfilled with the
excavated soil material immediately following the placement of the sewer line.
- .-~,, ..
X
2. To not construct the required preformed scour hole and allow the stormwater r~
to be treated while being conveyed through a centipede vegetated "swale" prior
to delivery to an irrigation pond. This feature is man made and is located
outside of natural drainage ways not subject to the Neuse Buffer Rules
as per NBRRO OS-173. ~f'~''"
All impacts other than the two mentioned above have been completed
as previously permitted. These proposed impacts cannot be accomplished
~x.p ot~ - ll 3aV~
December 13, 2007
i
or reduced in any manner that would better protect water quality or minimize the riparian impact.
Best management practices will be utilized during all construction activities to minimize the
disturbance, preserve aquatic life and habitat, and protect water quality.
If you should have any questions related to the information presented or are in need of additional
information please do not hesitate to contact me. My cell number is 919-971-6598 or nights at
550-9055.
Sincerely,
Steve Mitchell
ECI CUS'TO~VI~ I~OI~~:~S, C.
A Division of Shield Group, Inc.
December 13, 2007
Ormand K. Strickland
P.O. Box 898
Lake Glad Rd.
Wendell, N. C. 27591-898
RE: Memorandum of Understanding and Agreement
Dear Mr. Strickland
As discussed, ECI Custom Homes and Development, Inc. would like to obtain a portion
of your property for a storm drainage easement. The easement area is clearly shown on
the attached easement maps prepared by Thompson Associates. This easement map is
dated 12/12/07 and refers to a 20' private drainage easement across the rear of the
property with a 10' temporary construction easement along the sides.
We have paid for the preparation of the easement maps for clarification at no cost to you.
We are prepared to pay you $ 1500 to use this portion of your land for the easement.
If this agreement is acceptable to you, please sign below and sign the easement maps. I
will return to you a copy of the map once the Town of Wendell has signed-off and
recorded it.
Sincerely, ~~ Accepted by (Propertyy Owner
Jack Lic ter Print name: Ormand K. Strickland
Director o elopment Sign name: !9' ~' .
Date: l.~ - 1 ~- - Q
7300 Six Forks Road, Raleigh, North Carolina 27615 ~ (919) 250-9256 fax (919) 250-1389
www. ecicustomhomes. com
~.xp o~-1~3~ V2
ar_ ~ ~ ~ 2ooT ~_-~
oEr''R - ~A7ER
1#11ANDS ~ S i (1{Z~~ U~ ~-
r
Office Use Only: Form Version March OS
USACE Action ID No. DWQ No.
(If any particular item is not applicable to this project, please enter "Not Applicable" or "N/A".)
I. Processing
~r~~n
1. Check all of the approval(s) requested for this project:
^ Section 404 Permit ^ Riparian or Watershed Buffer Rules
^ Section 10 Permit ^ Isolated Wetland Permit from DWQ
^ 401 Water Quality Certification X Express 401 Water Quality Certification
2. Nationwide, Regional or General Permit Number(s) Requested: NW 12
3. If this notification is solely a courtesy copy because written approval for the 401 Certification
is not required, check here: ^
4. If payment into the North Carolina Ecosystem Enhancement Program (NCEEP) is proposed
for mitigation of impacts, attach the acceptance letter from NCEEP, complete section VIII,
and check here: ^
5. If your project is located in any of North Carolina's twenty coastal counties (listed on page
4), and the project is within a North Carolina Division of Coastal Management Area of
Environmental Concern (see the top of page 2 for further details), check here: ^
II. Applicant Information
1. Owner/Applicant Information
Name:ECI Development c/o Mr. Jack Lichner
Mailing Address:8317 Six Forks Road, Suite 203
Raleigh, North Carolina 27615
Telephone Number:919-250 9256 Fax Number:919-250-1389
E-mail Address:www.ecicustomhomes.com
2. Agent/Consultant Information (A signed and dated copy of the Agent Authorization letter
must be attached if the Agent has signatory authority for the owner/applicant.)
Name:
Company Affiliation:
Mailing Address:
Telephone Number:.
E-mail Address:
Fax Number:
Page 1 of 8
III. Project Information
Attach a vicinity map cleazly showing the location of the property with respect to local
landmarks such as towns, rivers, and roads. Also provide a detailed site plan showing property
boundaries and development plans in relation to surrounding properties. Both the vicinity map
and site plan must include a scale and north arrow. The specific footprints of all buildings,
impervious surfaces, or other facilities must be included. If possible, the maps and plans should
include the appropriate USGS Topographic Quad Map and NRCS Soil Survey with the property
boundaries outlined. Plan drawings, or other maps may be included at the applicant's discretion,
so long as the property is cleazly defined. For administrative and distribution purposes, the
USACE requires information to be submitted on sheets no lazger than 11 by 17-inch format;
however, DWQ may accept paperwork of any size. DWQ prefers full-size construction
drawings rather than a sequential sheet version of the full-size plans. If full-size plans are
reduced to a small scale such that the final version is illegible, the applicant will be informed that
the project has been placed on hold until decipherable maps aze provided.
1. Name of project: The Woods of Blair Hills
2. T.LP. Project Number or State Project Number (NCDOT Only):
3. Property Identification Number (Tax P1N):1783 44 5069, 1783 54 3219, 1783 54 7392
4. Location
County: Wake Nearest Town: Wendell
Subdivision name (include phase/lot number):The Woods of Blair Hills
Directions to site (include road numbers/names, landmarks, etc.):Located on the east side of
Lake Glad Road approximately 1075 feet north of its intersection with Old Nowell Road
5. Site coordinates (For linear projects, such as a road or utility line, attach a sheet that
separately lists the coordinates for each crossing of a distinct waterbody.)
Decimal Degrees (6 digits minimum): 36 76 57 N 78 37 75 °W
6. Properly size (acres):40.7 acres
7. Name of nearest receiving body of water: UT & Buffalo Creek 27-57-16(3 , C. NSW
8. River Basin: Neuse 03-04-06
(Note -this must be one of North Cazolina's seventeen designated major river basins. The
River Basin map is available at http://h2o.enr.state.nc.us/admin/maps/.)
9. Describe the existing conditions on the site and general land use in the vicinity of the project
at the time of this application :Infrastructure of development in place, roads, curb& gutter,
etc
10. Describe the overall project in detail, including the type of equipment to be used: General
earth moving equipment for road and house construction. The general land use in the
vicinity of the subdivision is residential.
Page 2 of 8
11. Explain the purpose of the proposed work: Di open trench across stream to place 8 inch
sewer line. If necessary, block off flow of creek and pump around. Current permitting
exisits for road construction (complete). Alter stormwater from approved pre-formed scour
hole to centipede sod ditch with dischaz a to irrigation pond.
IV. Prior Project History
If jurisdictional determinations and/or permits have been requested and/or obtained for this
project (including all prior phases of the same subdivision) in the past, please explain. Include
the USACE Action ID Number, DWQ Project Number, application date, and date permits and
certifications were issued or withdrawn. Provide photocopies of previously issued permits,
certifications or other useful information. Describe previously approved wetland, stream and
buffer impacts, along with associated mitigation (where applicable). If this is a NCDOT project,
list and describe permits issued for prior segments of the same T.I.P. project, along with
construction schedules. Project has received DWQ 401 Water Quality Certification DWQ Exp
06-1139) and Authorization Certificate per Neuse Buffer Rules NBRRO OS-173, General
Certification WQC #3402, Stormwater Fermit NCGO10000 permit, and Wastewater Collection
System Extension Permit (WQ0030834~
V. Future Project Plans
Are any future permit requests anticipated for this project? If so, describe the anticipated work,
and provide justification for the exclusion of this work from the current application. No further
permits aze anticipated.
VI. Proposed Impacts to Waters of the United States/Waters of the State
It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to
wetlands, open water, and stream channels associated with the project. Each impact must be
listed separately in the tables below (e.g., culvert installation should be listed separately from
riprap dissipater pads). Be sure to indicate if an impact is temporary. All proposed impacts,
permanent and temporary, must be listed, and must be labeled and clearly identifiable on an
accompanying site plan. All wetlands and waters, and all streams (intermittent and perennial)
should be shown on a delineation rnap, whether or not impacts are proposed to these systems.
Wetland and stream evaluation and delineation forms should be included as appropriate.
Photographs may be included at the applicant's discretion. If this proposed impact is strictly for
wetland or stream mitigation, list and describe the impact in Section VIII below. If additional
space is needed for listing or description, please attach a separate sheet.
1. Provide a written description of the proposed impacts: Excavation and placement of 8 inch
sewer line will temporarily disturb 23.2 linear feet of stream bed. A total of 2,375 square
feet (Zone 1 1 415 and Zone 2960) of buffer will be disturbed within the permanent sewer
easement. Existing_permitted impacts include two road crossing consisting of 103 feet of
perennial stream and 48 feet of intermittent impact.
Page 3 of 8
2. Individually list wetland impacts. Types of impacts include, but are not limited to
mechanized clearing, grading, fill, excavation, flooding, ditching/drainage, etc. For dams,
separately list impacts due to both structure and flooding. Impact COMPLETED.
Wetland Impact Type of Wetland Located within Distance to Area of
Site Number Type of Impact (e.g., forested, marsh, 100-year Nearest Impact
(indicate on map) herbaceous, bog, etc.) Floodplain Stream (acres)
es/no) (linear feet)
Impact #2 Permanent Road
Crossing Headwater wetland No +/- 120. feet 0.03
Total Wetland Impact (acres) 0.03
3. List the total acreage (estimated) of all existing wetlands on the property: 5.26 acres
4. Individually list all intermittent and perennial stream impacts. Be sure to identify temporary
impacts. Stream impacts include, but aze not limited to placement of fill or culverts, dam
construction, flooding, relocation, stabilization activities (e.g., cement walls, rip-rap, crib
walls, gabions, etc.), excavation, ditching/straightening, etc. If stream relocation is proposed,
plans and profiles showing the linear footprint for both the original and relocated streams
must be included. To calculate acreage, multiply length X width, then divide by 43,560.
1 * is impact requested in modification of 401/404 Permit. Other impacts completed.
Stream Impact
Perennial or Average Impact Area of
Number Stream Name Type of Impact
Intermittent? Stream Width Length Impact
(indicate on ) Before Im act {lineaz feet) (acres
1 * UT Buffalo Creek Temporary Perennial
Impact #1
UT Buffalo Creek Permanent Road
Perennial 11'-12'
103'
0.033
Crossing
Impact #4 UT Buffalo Creek Permanent Road Itermittent 14' 15' 48 0.019
Crossing
Proposed Temporary Stream Crossing Impact (by length and acreage) 15* 0.04
Total Permanent Stream Impact (by length and acreage) 151' 0.052
* Actual linear foot disturbance due to 60° crossing is 17.5
5. Individually list all open water impacts (including lakes, ponds, estuaries, sounds, Atlantic
Ocean and any other water of the U.S.). Open water impacts include, but are not limited to
fill, excavation, dredging, flooding, drainage, bulkheads, etc.
Open Water Impact
Name of Waterbody Type of Waterbody Area of
Site Number (if applicable) Type of Impact (lake, pond, estuary, sound, bay, Impact
(indicate on ma) ocean, etc.) acres
NA NA NA NA NA
Total Open Water Impact (acres) NA
Page 4 of 8
6. List the cumulative impact to all Waters of the U.S. resulting from the project:
Permitted Requested
Stream Impact (acres): 0.052 0.008
Wetland Impact (acres): 0.03
O en Water Impact (acres): 0
Total Impact to Waters of the U.S. (acres) temporary 0.082 0.04
Total Stream Impact (linear feet): 151 15*
* actual linear foot impact due to 60~ crossing is 17.5
7. Isolated Waters
Do any isolated waters exist on the property? ^ Yes X No
Describe all impacts to isolated waters, and include the type of water (wetland or stream) and
the size of the proposed impact (acres or linear feet). Please note that this section only
applies to waters that have specifically been determined to be isolated by the USACE.
NA
8. Pond Creation
If construction of a pond is proposed, associated wetland and stream impacts should be
included above in the wetland and stream impact sections. Also, the proposed pond should
be described here and illustrated on any maps included with this application.
Pond to be created in (check all that apply): ^ uplands ^ stream ^ wetlands
Describe the method of construction (e.g., dam/embankment, excavation, installation of
draw-down valve or spillway, etc.): NA
Proposed use or purpose of pond (e.g., livestock watering, irrigation, aesthetic, trout pond,
local stormwater requirement, etc.):NA
Current land use in the vicinity of the pond:NA
Size of watershed draining to pond:NA Expected pond surface azea:NA
VII. Impact Justification (Avoidance and Minimization)
Specifically describe measures taken to avoid the proposed impacts. It may be useful to provide
information related to site constraints such as topography, building ordinances, accessibility, and
financial viability of the project. The applicant may attach drawings of alternative, lower-impact
site layouts, and explain why these design options were not feasible. Also discuss how impacts
were minimized once the desired site plan was developed. If applicable, discuss construction
techniques to be followed during construction to reduce impacts. Wetlands delineated and
impacts avoided and minimized. Permitted impacts are completed except sewerline crossing
Protect is approved to jack and bore under the stream disturbing a much larder amount of buffer.
The substrate below the stream is striated granite and this makes it impossibile to accomplish.
Proposal is to dig and open trench and klace the sewer line in. (Three feet deep).
VIIL Mitigation
DWQ - In accordance with 15A NCAC 2H .0500, mitigation may be required by the NC
Division of Water Quality for projects involving greater than or equal to one acre of impacts to
Page 5 of 8
freshwater wetlands or greater than or equal to 150 linear feet of total impacts to perennial
streams.
USACE - In accordance with the Final Notice of Issuance and Modification of Nationwide
Permits, published in the Federal Register on January 15, 2002, mitigation will be required when
necessary to ensure that adverse effects to the aquatic environment are minimal. Factors
including size and type of proposed impact and function and relative value of the impacted
aquatic resource will be considered in determining acceptability of appropriate and practicable
mitigation as proposed. Examples of mitigation that may be appropriate and practicable include,
but are not limited to: reducing the size of the project; establishing and maintaining wetland
and/or upland vegetated buffers to protect open waters such as streams; and replacing losses of
aquatic resource functions and values by creating, restoring, enhancing, or preserving similar
functions and values, preferable in the same watershed.
If mitigation is required for this project, a copy of the mitigation plan must be attached in order
for U5ACE or DWQ to consider the application complete for processing. Any application
lacking a required mitigation plan or NCEEP concurrence shall be placed on hold as incomplete.
An applicant may also choose to review the current guidelines for stream restoration in DWQ's
Draft Technical Guide for Stream Work in North Carolina, available at
http://h2o.enr.state.nc.us/nc~~~etlands/stlmfide.html.
1. Provide a brief description of the proposed mitigation plan. The description should provide
as much information as possible, including, but not limited to: site location (attach directions
and/or map, if offsite), affected stream and river basin, type and amount (acreage/linear feet)
of mitigation proposed (restoration, enhancement, creation, or preservation), a plan view,
preservation mechanism (e.g., deed restrictions, conservation easement, etc.), and a
description of the current site conditions and proposed method of construction. Please attach
a separate sheet if more space is needed.
In situations in the past where stream impacts are under 150 feet or temporarypacts to
unimportant/intermittent streams have occurred, mitigation is not required by the USACE
and cannot be required by NCDWQ, therefore, mitigation has not been proposed. However,
should mitigation be required, the applicant shall use the EEP.
2. Mitigation may also be made by payment into the North Carolina Ecosystem Enhancement
Program (NCEEP). Please note it is the applicant's responsibility to contact the NCEEP at
(919) 715-0476 to determine availability, and written approval from the NCEEP indicating
that they are will to accept payment for the mitigation must be attached to this form. For
additional information regarding the application process for the NCEEP, check the NCEEP
website at http://h?o.enr.state.nc.us/~-rp/index.htm. If use of the NCEEP is proposed, please
check the appropriate box on page five and provide the following information:
Amount of stream mitigation requested (linear feet): 0
Amount of buffer mitigation requested (square feet): 0
Amount of Riparian wetland mitigation requested (acres): 0
Amount ofNon-riparian wetland mitigation requested (acres): 0
Amount of Coastal wetland mitigation requested (acres): 0
Page 6 of 8
IX.
X.
Environmental Documentation (required by DWQ)
Does the project involve an expenditure of public (federaUstate/local) funds or the use of
public (federal/state) land? Yes ^ No X
2. If yes, does the project require preparation of an environmental document pursuant to the
requirements of the National or North Carolina Environmental Policy Act (NEPA/SEPA)?
Note: If you are not sure whether a NEPA/SEPA document is required, call the SEPA
coordinator at (919) 733-5083 to review current thresholds for environmental documentation.
Yes ^ No ^
3. If yes, has the document review been finalized by the State Clearinghouse? If so, please
attach a copy of the NEPA or SEPA final approval letter. Yes ^ No ^
Proposed Impacts on Riparian and Watershed Buffers (required by DWQ)
It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to
required state and local buffers associated with the project. The applicant must also provide
justification for these impacts in Section VII above. All proposed impacts must be listed herein,
and must be clearly identifiable on the accompanying site plan. All buffers must be shown on a
map, whether or not impacts are proposed to the buffers. Correspondence from the DWQ
Regional Office may be included as appropriate. Photographs may also be included at the
applicant's discretion.
Will the project impact protected riparian buffers identified within 15A NCAC 2B .0233
(Meuse), 15A NCAC 2B .0259 (Tar-Pamlico), 15A NCAC 02B .0243 (Catawba) 15A NCAC
2B .0250 (Randleman Rules and Water Supply Buffer Requirements), or other (please
identify Meuse Yes X No ^
2. If "yes", identify the square feet and acreage of impact to each zone of the riparian buffers.
If buffer mitigation is required calculate the required amount of mitigation by applying the
buffer multipliers.
Zone* Impact
(s uare feet) Multiplier Required
Miti ation
1 1067 3 (2 for Catawba) NA
2 920 1.5 NA
Total 1787 NA
" Zone 1 extends out 30 feet perpendicular from the top of the near bank of channel; Zone 2 extends an
additional 20 feet from the edge of Zone 1.
If buffer mitigation is required, please discuss what type of mitigation is proposed (i.e.,
Donation of Property, Riparian Buffer Restoration /Enhancement, or Payment into the
Riparian Buffer Restoration Fund). Please attach all appropriate information as identified
within 15A NCAC 2B .0242 or .0244, or .0260. Buffer mitigation is not uro~osed because all
impacts are considered "Allowable".
Page 7 of 8
Xl<. Stormwater (required by DWQ)
Describe impervious acreage (existing and proposed) versus total acreage on the site. Discuss
stormwater controls proposed in order to protect surface waters and wetlands downstream from
the property. If percent impervious surface exceeds 20°l0, please provide calculations
demonstrating total proposed impervious Level. NA Stormwater has been permitted
XIL Sewage Disposal (required by DWQ}
Clearly detail the ultimate treatment methods and disposition (non-discharge or discharge) of
wastewater generated from the proposed project, or available capacity of the subject facility.
WWTI'
X~II. Violations (required by DWQ)
Is this site in violation of DWQ Wetland Rules (15A NCAC 2H .0540} or any Buffer Rules?
Yes ^ No X
Is this anafter-the-fact permit application? Yes ^ No ^
~iiV. Cumulative Impacts (required by DWQ}
Will this project (based on past and reasonably anticipated future impacts} result in additional
development, which could impact nearby downstream water quality? Yes ^ No X
If yes, please submit a qualitative or quantitative cumulative impact analysis in accordance with
the most recent North Carolina Division of Water Quality policy posted on our website at
~,~~ -iz~~7 ~,4i~-.~ ,~~ ,a~,~ ~E _+~~ ~, t;~,~_~~. If no, please provide a short narrative description: Project
is already approved for the construction of 51 residential homes.
XV. Wither Circumstances (Optional):
It is the applicant's responsibility to submit the application sufficiently in advance of desired
construction dates to allow processing time for these permits. However, an applicant may
choose to list constraints associated with construction or sequencing that may impose limits on
work schedules (e.g., draw-down schedules for lakes, dates associated with Endangered and
Threatened Species, accessibility problems, or other issues outside of the applicant's control}.
Applicant/Agent's Si re Date t~ I Z'1 ~?
(Agent's signature is valid only if an autho ' do etter from the applicant is provided.)
Page 8 of 8
TopoZone -USGS Knightdale (NC) Topo Map
Page 1 of 1
`~~
r ~ ~
~1~~01'MB''
" ^
''~^.~i r~~~cene ~
^
{ 4
~~ ~
. ~ ~ ..
4 ~
Try ~.r
^
°h. ~~
^ ~~
ap
f $
~ ~ ~^ ~ ..
r
^ - ~ .,,'
~~
^
~~~ t .
.,
r ~ ~.
11 9
.- ~ ~
.s .
^ ^ ^ ^ .
^
!f
1 ~
.r .~
^
~~
~~ ~. ~ ^
^
f ~
^
_ -' ^ ^ ~ 4
~
yl ^
^
~.
= ~ 4 ,,
~ ~
` ^
~a
tl
.n Ma.
~,Y
r ^ ^ x
~
~.
_
W......d` ^
~ e
~
f
~f I #
y'
Y'~
1 ~
~~~ ~
~e '*
0 0.1 4.2 0.3 0.4 0.5 km G
0 0.09 0.18 0.27 0.36 0.45 mi
UTM 17 737238E 3961283N (NAD83/WGS84)
USGS Knlghtdale (NC) Quadrangle i~•q~-;~;.~__;{_+
Projection is UTM Zone 17 NAD83 Datum G-1. ~~5
http://www.topozone.com/print.asp?lat=3 5.767&lon=-78.37575&s=24&size=l&u=4&lay... 11 /19/2007
Addendum to the Pre-Construction Notification and "Buffer Rules" Application Required for
Projects Submitted Under the
"Express Review Program"
North Carolina Division of Water Quality Version 5.0
October 1, 2006
Email Address: 401express~ncmail.net
Purpose: To provide a detailed explanation of the information required by the Division of Water Quality
in order to expedite the review of applications for 401 General Water Quality Certifications, Isolated
Wetland Permits, Stream and Wetland Mitigation Plans and Riparian Buffer Approvals (Please Note: do
not leave any questions unanswered or use terms such as "N/A" without an explanation).
Fees:
401 Water Quality Certifications
Riparian Buffer Authorization:
Riparian Buffer Minor Variance:
Coastal General "Major Variance"
Isolated Wetland Permit:
Major (>/= 150' stream or >/= 1 acre wetlands) $2,000.00
Minor (< 150' stream or < 1 acre wetlands) $1,000.00
(exclusively or "in addition" to) $2,000.00
$1,000.00
$1,500.00
General $1,000.00
Please read the entire document before attempting to determine the proper fee. Fees are additive for
particular projects.
Things to keep in mind when filling out the application:
A specific answer must be provided for each question. For instance, if a numerical answer is requested
then a numerical answer must be provided along with the supporting information necessary for DWQ staff
to verify that the number is accurate. Likewise, if explanations are presented to justify certain responses,
the explanations must be completely supported by documentation. DWQ staff cannot assume that
unsupported or undocumented information is accurate. "N/A" is not an acceptable answer for any
question since the DWQ Staff reviewing the application must have an opportunity to determine whether or
not any requested information is pertinent.
All forms, guidance, worksheets, applications, etc. used must be the current versions as posted on our
web site at http://h2o.enr.state.nc.us/ncwetlands. The Express Review Program website can be found at
http://h2o.enr.state.nc.us/ncwetlands/express review.htm. Please note that it will be responsibility of the
applicant or the applicant's consultant to verify that the current versions are used. The versions posted
on our web site will be considered to be the current versions.
You are a very important part of the success of this program, if you have suggestions or clarifications
please send your comments to the Wetlands/401 Unit of the DWQ (via email at
401 express~ncmail.net).
Filling Out the Pre-Construction Notification Application:
The Corps of Engineers (USAGE)/DWQ official, joint Pre-Construction Notification (PCN) Application
must be used as a basis for the expedited review process. The completed application should be
presented first and the supporting information tabbed and collated in the same order. Using a custom
format is not recommended. The open squares (~ are checklist items. The following items correspond to
the numbering system on the Pre-Construction Notification Form (PCN):
IMPORTANT: USE CHECK BOXES TO TRACK PROJECT /NFORMAT-ON!1
z
SECTION I. PROCESSING
i~ 1 8 2.The USACE determines which Nationwide, Regional, or General Permit is
required. If you have verified with the USACE which permit they intend to use for
your project or if yqu already have written approval from the USACE, please
indicate by adding "verged" or "verified, attached, respectively, in the blank next
to the Permit number requested.
Attach the USACE Approval if you have it.
~i 3. It is not anticipated that the expedited process will be requested for this situation.
i_' 4. If you propose to impact 150 feet or more of perennial stream or 1 acre or more
of wetland and onsite mitigation is not proposed, it is recommended that you
either locate an acceptable private bank with available credits (with
documentation to show that the bank can and shall provide the credits needed)
(~ or obtain approval from the EEP for the entire amount of stream and or wetland
as DWQ will make the final determination as to whether or not mitigation applies.
A complete Express application is not considered received unless an EEP
approval letter is attached if mitigation is requested through EEP. Please note
that the USACE may have different mitigation requirements and thresholds.
~~ 5. State whether your project will require a CAMA Minor, Major or General Permit
and give the status of the permit. tJ J
SECTION II - APPLICATION INFORMATION
1. 15 NCAC 2H .5020 reads as follows: "Who Mus# Sign Applications. The application
shall be considered a "valid application" only if the application bears the signature of a
responsible officer of the company, municipal official, partner or owner. This signature
certifies that the applicant has title to the property, has been authorized by the owner to
apply for certification or is a public entity and has the power of eminent domain. Said
official in signing the application shall also certify that all information contained therein
or in support thereof is true and correct to the best of his/her knowledge."
~-!~ Please indicate how the applicant meets the above definition and provide
"supporting documentation.
Please provide all of the requested contact information including a fax
number and email address.
2. C7 If the a lication is not si ned b the a licant lease attach the a ent authoriz tion
PP 9 y PP , P 9 a
letter. The applicant must sign the agent authorization letter. The applicant's name
and position must also be spelled out as many signatures are difficult to read.
3. C~ Please provide all of the requested contact information including a fax number and
email address.
SECTION 111-PROJECT INFORMATION
The following is the most critical of all the information that you must provide. The quality and detail of the
information will often determine the expeditiousness of the review. The following is a checklist of the
types of pertinent information required at a minimum:
Maps and Plans:
The most recent version of the 1:24 000 USGS Topographic Map- Please cleanly
delineate the site boundaries, etc. on the map. If the delineation obscures any of the
features, it is recommended that a clean copy be provided. Please indicate the
quadrangle name. You can go to the USGS web site (http://mac.usgs.gov/mapGstsn to
verify the most recent version.
~'
r~ The most recent version of the NRCS Soil Survey Map - (required for projects within
the Neuse River Basin, Tar-Pamlico River Basin, Randleman Lake Watershed and the
Catawba River Basin, also recommended for all projects) -Please cleanly delineate the
site boundaries, etc. on the map. If the delineation obscures any of the features, it is
recommended that a clean copy be provided. Please indicate the page or map number
from which the copy of the map was made. Copies of the current soil survey and/or soil
survey map sheets can be obtained from the local NRCS County Office
(http://www.nc.nres.usda.gov/). GIS soil layers are not acceptable.
~~ Vicinity map -Please clearly mark the location and approximate boundaries of the
property and project on the map. Please indicate north and scale. Please include
applicable road names or State Road numbers.
The Site Plan -The most critical map to be provided is the site plan. You must provide
full 'zed ans. The following is the minimum list of plans that are typically needed.
Pre-constructiontPre-existing conditions -This sheet must be scaled and
include all jurisdictional and non jurisdictional wetland, stream, water features,
State regulated buffers, topographic contours with elevations, approximate extent
and nature of forest, field, landscaping, or other cover. Any existing structures and
p~ impervious area must be shown. Existing utility lines and easements must be
shown. Existing roads, culverts, and other pertinent features must be shown. North
an'ow and the scale must be shown. Please note that the impact boundaries on the
maps should correspond to the flagged impact boundaries in the field.
{ Proposed conditions -These sheets must be scaled and show all existing
jurisdictional and non-jurisdictional wetland, stream, water features, and State
regulated buffers (delineated into Zone 1 and Zone 2) must be underlain on the site
plan(s). The plans must show all built-out structures and impervious cover. The
plans must include the final grading contours with elevations. The plans must
indicate all utilities and easements. It is likely that several versions of the final built-
. out site plans will be necessary.
Drainage Plans -Final drainage plans must be included. The plans should include
the locations and pertinent elevations and sizes of the collection system and
drainage ways. Alf inlets and outlets must also be shown with pertinent elevations.
Scaled stormwater BMPs must also be indicated as required by DWQ rules and
policies. In certain cases, final stormwater management plans must also be
provided, but that will be addressed later in this document.
Plats -The plans must show the location and layout of all sub-divided parcels with
~ot identifications. Platted parcels must be developable without further impacts to
turisdictional and non jurisdictional wetlands, streams. water features. and State
/ , regulated buffers.
f?1 Proposed Impacts -All impacts to jurisdictional and non-jurisdictional wetland,
stream, water features, and State regulated buffers must be shown and labeled on
the site plans. All excavation, fill, flooding, stabilization, and other impacts that will
be conducted in or near jurisdictional and non jurisdictional wetland, stream, water
features, and State regulated buffers must be indicated.
4
Wetlan/d Impacts (on the site plan):
C~' Precise grading and final elevation contours must be provided. Existing vegetation and
any clearing must be specified.
All subsurface utility lines must indicate the location of anti-seep collars. Construction
detail for anti-seep collars must be provided.
~~~ ~ Roadway or other crossings of riparian wetlands may require ifoodway culverts to
maintain existing hydrological conditions.
^ When surtace drainage fea#ures or groundwater recharge areas that feed or would
~ reasonably feed wetlands that are not to be filled are made impervious, it may be
necessary to direct some stormwater runoff to those areas in order to maintain hydrology.
You must identify these areas and address them. Supporting explanations and discharge
information must be provided to show that the wetland would not be eroded or receive
too much or too little hydrology. In many cases this could help satisfy part of a
stormwater management plan.
~! ~ Flooding
^ (~ Draining
Stream/Impacts:
r~! Stream impacts must be clearly shown on the plans. The centerline as well as the banks
of the stream must be surveyed or located by GPS for the portion of the stream to be
impacted.
Culvertin~g~
^ ~u 'The inlet and the outlet of the culvert should be aligned with the stream as much as
possible. Inlet and outlet elevations and streambed elevations should be indicated.
^ ,I.f~Any widening of the stream must be shown with elevations.
^ ~(~he extent of and plan details for all dissipation or grade control devices should be shown
with pertinent elevations.
^ ,/`~ For shorter culvert sections, such as for road crossings, a longitudinal cross section that
shows the stream bed invert at the inlet and outlet, the existing stream bank elevations
,,` ~ the invert of the inlet and outlet of the pipe{s) must be provided.
[_7 +" For shorter culvert sections, such as for road crossings, a vertical cross section must be
provided that shows the stream cross section at the inlet and outlet overlain with the
culvert and fill cross section.
^ ~ or bottomless culverts or other spans, a vertical cross section should be provided that
shows the minimum distance from each span to each stream bank, the stream cross
section, the height of the span above the stream and tfie minimum distance from the
N edge of each footer to each stream bank.
^ „l1~ For bottomless culverts or other spans, a plan view must be provided that shows the
a" location of the spans and the stream banks.
^ ~~For longer culverts or culverts that will pass beneath substantial impervious cover, it will
be necessary to provide adequate plan detail to show that discharge velocity/energy will
be adequately dissipated.
^ Cross section details must be provided showing the provisions for aquatic life passage.
~quatic life passage through culverts is typically achieved by placing the invert of the
culvert below the existing bed of the stream per the USACE or North Carolina Wildlife
Resource Commission guidelines. Other methods such as baffles may also be used.
Please be aware that such placement may require the use of gradeNeiocity control
measures up or down stream of culverts on steeper streams to prevent head-cuts or
streambed erosion. The culvert placement relative to the streambed can be indicated on
the longitudinal profile. Grade and velocity control measures mus# be indicated on the
plan view and typical designs should be provided.
^ „~Itiple culverts, wide culverts or sectioned box culverts typically require the use of sills,
`~~'' off-setting or other means to match the cross section of the existing stream (in order to
maintain stream stability and provide aquatic life passage). A vertical cross section of the
culverts should be shown overlain with the up and downstream stream cross section
including the stream flood-prone area.
^ ~v impacts associated with dam construction must indicate and enumerate all fill associated
with the dam footprint, spillway and any bank stream bank stabilization. The length of
m im ounded must also be indicated and enumerated.
Stream Relocations:
Strea rons must be conducted as specified in General Certification numbers
3402 and 3404 (available on the Wetlands Unit web site). Stream relocation plans must
include:
~~IGlorphological measurements (see Appendix B of the Internal Technical Guide for Stream
Work in North Carolina available on the Wetlands Unit web site) -not all of the
measurements are applicable in every instance.
^ ~ypical stream cross sections - Typically, a riffle cross section and a pool cross section
that includes the entire flood prone area. The bankfull and flood prone area elevations
should be indicated. Similarly, a riffle cross section of the reference stream(s) should be
provided.
^ ~ Plan view -Provide scaled plans that show the location of the proposed (preferably with
stationing) and the existing stream. In most instances, the bankfull contours and flood
prone area contours, in stream structures, bank revetments/stabilization, channel plugs, ~'
planting plan, vegetation conditions, stormwater outlets, grade controls, bridges, culverts,
sewer lines, roads, fencing, and easement lines should also be provided.
!~, longitudinal Stream Profile - A seated profile that indicates the thalweg, bankfull, and top
(~ of bank elevations should be provided for the design and reference streams. In many
cases, it will also be necessary to show the existing land elevations for the design
stream.
^ 1 t`Planting Plan - A planting and/or vegetation management plan should also be provided
~" that makes use of appropriate native vegetation. The plan should indicate the extent,
density, and species of plants to be provided.
^ stream structure, bank revetment/stabilization, and stormwater outlet typicals -
1 Detailed, typical plans should be provided for all in stream structures, bank revetments or
stabilization, and stormwater outlets. The typicals should include materials and
specifications as well as relative lengths, positions, and angles.
^ ~ Sediment transport analysis - A sediment transport analysis should be provided based
on the current, relevant, accepted practices. The sediment transport analysis should be
relevant to the streambed load type and should predict bed load transport equilibrium.
~~~ Permanent conservation easement or similar means of protection must also be provided.
Other Irk#ormation:
~ f 1. The project should always be referred to by this name in all correspondence as well
as the DWQ # once it is provided.
f~ This only applies to DOT projects, which are not expected to utilize the Express
Review Program.
~, 3. This should be the size of the project as ident~ed by the USACE for 404 Pemyits or
by the Division of Water Quality for Buffer Approvals and Isolated Wetland Permits.
r
4. Please provide the name (as depicted on the USGS topographic map and DWQ
Stream Classification Lists) of the nearest water body(ies) to which your project is a
tributary to (e.g. "Neuse River (Falls Lake below normal pool elevation)"). (Do not
simple state "stream", "river", "ocean°, "sound" or "lake°.) Please provide the "stream
index number" of the named water body or water body section (e.g. "27-(1)n). Also,
please provide the full water quality classification (e.g. "WS-IV NSW CA") of the water
body. This information can be obtained from the DWQ web site
http://h2o. en r.state. nc. uslbims/Reports/reportsWB.html.
5. Please state which river basin and sub-basin that your project is in (e.g. "Neuse River
Basin, NEU09'~. This information can be obtained from the DWQ web site
/ http:l/h2o.enr.state.nc.us/bims/Reports/reportsWB.html.
~! ~ 6. Conditions should also be indicated on the existing site plan where applicable.
Photos (including aerial photos) can be helpful in describing the existing conditions.
7. You must provide an attachment that explicitly describes what the proposed project
will entail from the planning stage to final construction.
~,,
8. This can be a simple explanation, but it is critically important because the purpose
dictates how the no practical alternatives are reviewed.
SECTIO~-PRIOR PROJECT HISTORY
Please include copies of all 401 Water Quality Certifications, Isolated Wetland
Permits, Suffer Approvals, USACE Permits, CAMA Permits for the site as well as a
copy of the final approved, site plan.
SECTION V -FUTURE PROJECT PLANS
C~Y For projects utilizing the express review process, all impacts both present and
potential future must be indicated. For instance, the location or configuration of
platted lots sometimes suggests that future impacts will be necessary to build,
access, or otherwise develop such lots. Failure to account for such potential impacts
could delay or disqualify a project from the rapid review process. If you believe that
the lot can be developed without impacts, but you anticipate that your assertion may
be questioned, it is recommended that you provide a potential building foot print
and/or grading plan to show that future impacts could be avoided.
SECTION VI -PROPOSED IMPACTS TO WATER OF THE US
~~ 1. It is recommended that the individual impacts be described if there are special things
to note about the impacts. Typically the most important thing is to have detailed
accurate site plans as described above. Please make sure they are clearly labeled.
Cr`Please include all proposed temporary impacts.
~a' Also, a current, signed delineation map from the USACE should be provided (if
available) and a map locating the stream origins signed by the appropriate DWQ
Staff must be provided if applicable.
^ 2. Each impact to a wetland must be clearly iabeted and identified on the site plan. the
C type of impact must be clearly stated. (f the impact is temporary, a specific plan must
IJ be described or shown as to how the wetland will be restored. Keep in mind #hat the
USACE delineates some features as wetlands that DWQ calls streams. Please list
any impacts in this table that DWQ would identify as a stream. If there is any doubt,
it is recommended that the impacts be listed as streams. Please follow cun'ent DWQ
policy with respect to whether a stream is perennial or not. It is recommended that
you assume that a stream is perennial (unless you are positive that it is not) so if
mitigation is required then the appropriate amount of mitigation would be anticipated
or requested from the EEP or private bank. If the EEP or private bank has pre-
approved too short of an amount of stream or if inadequate mitigation is proposed,
then that situation wilt result in delays.
3. IYSometimes it is difficult to determine whether a feature is a mod~ed natural channel
w~~~or a ditch, especially in the eastern part of the State. Soils, drainage features,
1" topography, macroinvertebrates, and similar factors, all are important for making that
determination.
^ 4. '` lather items to address not specifically requested in the application include
downstream sediment starvation, thermal pollution, low flow releases from dams, and
aquatic life passage. Other important considerations are buffer reestablishment or
mitigation around ponds on buffered streams. The site plan should include the
precise elevation contour of the normal pool as well as the dam footprint. Mitigation
is required for wetland flooding of an acre or greater and for stream fill (if over the
150 foot threshold) under the dam footprint and any outlet stabilization.
SECTION VII -AVOIDANCE AND MINIMIZATION
Avoidance and minimization are critical aspects of an application pardculariy if you desire the appNcation
to tae processed expeditiously. The following is a checklist of avoidance and minimization questions that
DWQ Staff often look for in applications.
:`
~~ Are there any stream crossings at angles less than 75° or greater than 105°?
^ Are there anw y ~eam crossings that cross two streams above or at the confluence of those
~~s~~treams? Yv tJ
^ V`'~Cre there any stream, wetland, water, and/or buffer impacts other than perpendicular road
crossing near the edges of the property?
C the stream be relocated as a natural channel design as opposed to culverted or
otherwise filled?
^ any single stream crossed more than once?
^ (~iCan property access routes be moved or reduced to avoid stream, wetland, water, and
buffer impacts?
^~ ~ Can a building, parking lot, etc. be realigned to avoid impacts?
^ ~ Can the site layout be reconfigured to avoid impacts?
f ~an headwalls or steeper side slopes be used to avoid/minimize impacts?
~~
_ Can a retaining wall be used to avoid/minimize impacts?
^ ~ Can cul de sacs be used in place of a crossing?
8
~ Can lots be reshaped or have shared driveways to avoid impacts?
If based solely on the practicable physical possibility, the answer is "yes" to any of the above questions
then you must have to provide substantial and convincing justification as to why the impacts are
necessary. If the impacts are required by a local govemment or other agency, the claim must be
supported with appropriate written documentation from the local govemment or other agency. Most
projects typically involve the need to justify avoidance and minimization. If this information is not readily
available, then the express review process may not be the appropriate venue to use. Providing
alternative plans (such as plans that avoid the impact, minimize the impact and the preferred plan, similar
to those used in environmental assessments) and explanations as to why the preferred plan is needed
and why the alternative plans won't work are many times helpful in the no practical alternatives review.
SECTION VIII -MITIGATION
Mitigation for the Express Review Program, final mitigation plans must be presented up front. The final
plans (except for plans that propose payment into the Ecosystem Enhancement Program (EEP), Riparian
Buffer Restoration Fund, private mitigation banks, or similar banking instruments) must contain detailed
plans, specifications, calculations and other supporting data that show that the appropriate mitigation will
be achieved at the ratios required. The design plans must be developed to at feast the "90%" level.
Monitoring plans must be final and specific. Any means of permanent protection, such as a permanent
conservation easement must be provided. If you elect to use the EEP or a private mitigation bank, it is
recommended that you request the maximum possible mitigation amount that DWQ may require so that
you will not have to get further approval from them on short notice. The EEP and private banks are not
park of the expedited review process and cannot be expected to meet any such deadlines. There will be
no conditional expedited approvals that require final plans at a later date. It is not recommended that
innovative mitigation techniques or greater than 10°~ preservation be requested as part of an expedited
process.
SECTION IX
If your project requires the preparation of an environmental document under NEPA or SEPA and an
approval letter has not been issued by the State Clearinghouse, then you cannot apply under the
expedited review process. It is your responsibility to find out if such documentation is required.
SECTION X
There are many aspects of the Buffer Rules that must be addressed in every application, if applicable.
The first and most important thing to keep in mind is that allowable activities that require written Approval
from DWQ triggers a review of the entire project for compliance wi#h the Buffer Rules.
Diffuse Flow ~ Storrnwater Management:
The most common issues that arise involve the requirement for diffuse flow of s#ormwater
through riparian buffers. Basically one of three things must be indicated in regards to all
"nevi' stormwater that is collected and subsequently discharged. First, provisions for
diffuse flow through the protected buffer must be made. This usually involves the use of
level spreading devices designed to the latest DW4 guidance on level spreader design,
which is available on our web site. Please keep in mind that it does not matter how far a
discharge point is from a buffer. The stormwater must be flowing in a diffuse manner at
whatever point it eventually reaches the buffer. If the stormwater will not be flowing in a
diffuse manner through the protected buffer at the point it reaches the buffer, then one of
the following options may be allowed:
~~ You may provide a nitrogen removing measure such as a forested filter strip,
grassed Swale, stormwater wetland, etc. The measure employed should be
9
designed according to the NC DENR Stormwater Best Management Practices
Manual or other DWQ Guidance available at
http://h2o.enr.state.nc.us/ncwetlands/regcert.html. After the nitrogen is treated, the
`~stormwater can be directly conveyed through the buffer with written DWQ approval.
R1'' You may discharge the stormwater to an existing man-made conveyance that
`" currently conveys stormwater through the protected buffer (assuming the
conveyance was not constructed in violation of the Rules) as long as that
conveyance does not need to be altered to convey the flow. Please remember that
there are no other choices. The following checklist is intended to help insure that
your application will not be deemed incomplete as a result of improper stormwater
design.
Storrnwater Management (for Buffer Rules compliance only -Also, see Section XI):
AA stormwater out-falls must be clearly shown and labeled on the si#e plan for projects in
Buffered watersheds. List each out-fall as labeled:
G~ Option 1: Level spreading devices designed to the latest DWQ Guidance, and
devices that merely control velocity but do not provide diffuse flow such as rip rap
dissipators are not proposed. List each of these out-falls as labeled on the site
plan and provide a DWQ worksheet available at
/http://h2o.enr.s#ate.nc.usficwettands/regcert.html:
G~' Option 2: Nitrogen removing measures designed to DWQ Standards are
proposed for discharges for which diffuse flow through a protected Buffer cannot be
met. List each of these out falls as labeled on the site plan and provide a DWQ
worksheet available at http:/lh2o.enr.state.nc.uslncwetlands/regcert.html
D ~' option 3: The stormwater wilt be discharged to an existing man-made (not
including modified natural channels) conveyance that carries the stormwater
through the Buffer. The conveyance was not constructed in violation of the Buffer
Rules. Lis# each out-fall as labeled:
[~ All stormwater out-fall must meet one of the options above. (Note: if you cannot check this
box your application will likely not be accepted into the express review process.)
Site Plans:
[>~ All applications on properties with DWQ protected buffers must clearly depict the buffers
and any impacts to the buffers on the site plans. The impact maps should clearly depict
both zones of the protected buffers and the proposed impact areas (provided in square
feet).
Surfac/e Water 8 Buffer Delineations:
G% Any surface waters subject to DWQ protected buffers must be field located and accurately
depicted on the site plans and impact maps. The width, dimensions and pattern of the
surface water must be delineated. The surface water location must not be taken simply
from a USGS map, soil survey or local municipality's map. The buffers must be measured
from the surface water as required within the applicable buffer protection rule (e.g., all
buffers along streams subject to the Neuse and Tar-Pamlico Buffer Rules must be
measured from the "top-o#-bank° of the stream and not the centerline of the stream). Alt
streams must be surveyed or located by GPS and shown precisely on the site plans.
Impact Table:
10
GY Please provide additional impact tables that Dearly state the area of impact for each
corresponding impact site.
Variances:
;{~ ~ ^ Projects that require a Major and/or "General° Variance will not be eligible for the use of the
Express Review Program (with the exception of the Coastal General "Major Variance.
Mitigation:
rJ (~ ^ As opposed to applications that are submitted under our regular process, final mitigation
plans must be presented up front (see requirements for Section Vlll above). The mitigation
plans must comply with the applicable buffer mitigation rule.
SECTION XI - STORMWATER
Please provide the following information in regards to potential stormwater requirements:
~~ The total acreage of the site. '~~ ~ ~' (acres)
The total built-out impervious acreage ®. 5 (acres)
~~~ The total area that wiN be disturbed ~, (acres) ~ ~~ / q ~~ ~/.: ~-~ [~ l,. c~'~
^ If the total area exceeds 20% imperviousness, the development on the/site is uniform in j ~#'`"T~
density, and you claim that the total impervious area is less than 30°k, you must provide a l~~jUO 2,(~-
complete, detailed breakdown of the assumed built-ou# conditions. The breakdown must v
be detailed enough to show that all potential impervious areas are accounted for.
^ If there are concentrated areas of development such as multi-family, commercial, cluster,
club houses, etc. that exceed 30% imperviousness and the total imperviousness for the site
~ ~ does not exceed 30%, a stormwater management plan will likely be required for those
~1,~,., areas that exceed 30% imperviousness.
~~ ,~ ~ Stormwater management plans must be complete with a final design and an executed
~~' Operation and Maintenance Agreement. There will be no conditional stormwater approvals
~ for the express review process that allow for approval of the final plans at a later date.
~~~ ' Worksheets must be provided that are available at
http://h2o. ehnr.state. nc.usJncwetlands/mitresto.html.
SECTiO~ -SEWAGE DISPOSAL
Response must be clear and detailed. Any disposal method that suggests further impacts
may be required other than those shown must be clearly addressed on the site plans.
SECTION X111
^ Answering yes to either of these responses automatically precludes you from the express
review process.
SECTION XIV -SIGNATURE
The name, position and/or title of the applicant must be in type or long hand script here with
the signature. It should be the same person as described in Part II.
If you have any questions about these requirements, please email the Express Review Program at
401express~ncmail.net and include your question and phone number and the appropriate staff will
respond as soon as possible.
`o~~F W AT ~9QG
~ r '~'~ ~~~~~
~ I./~W~•~/~
0 `~: ~ „~
,~~•
Michael F. Easley, Governor
William G. Ross Jr., Secretary
North Carolina Department of Ernironment and Natural Resources
Alan W. Klimek, P.E. Director
Colleen H. Sullins, Deputy Director
Division of Water Quality
July 1, 2005
Mr. Chris Flowers
S&EC
11010 Raven Ridge Road
Raleigh, NC 2'1614
NBRRQ OS-173
County: Wake
BASIN:
Neuse River X Tar-Pamlico
(15A NCAC 2B .0233) (15A NCAC 2B .0259)
Complaint NOV Buffer Determination X
Incident # Appeal Call
Project Name: Woods olBlair Rill Property -Wendell
Location/Directions: Site is located on the east side of Lake Glad Road (NCSR 2358), .approx. 600 feet north of the
intersection of Lake Glad Road and Old Nowell Road in southern Wendell (Wake County).
Subject Stream:
UT to Buffalo Creek
Date of Determfnation: 6lZ~OS
Feature Statt Buffer
GPS Points (if provided) End Buffer Stream
Form Appeal
Call Located
on Soil
Surv Located on
USGS
Too his
A Subject (Not Contested) X X
B Subject (Not Contested) X X
C Subject Throughout X
D Subject at "Start D" Flag X
This on~ite determination shall expire, jive (S) years from the date of this letter. Landowners or affected partlcs
that dtsp:rte a determheatlon made by the DWQ or Delegated Local Authority that a surface water exists and that
U is subject to the bu,,~'er rule may request a determlbtatlon by the Director. A request for a determination by the
Director shall be referred to the Director in writueg c% Cyndi Xaroly ,DWQ Wetlands/401 Unit, 2321 Crabtree
Blvd, Raleigh, NC 2760 2260. Individuals that dispute a determination by the DWQ or Delegated Local
Authority that "exempts" a surface water from the buffer rule may ask for an ad, judicatory hearing. You nwst
act within 60 days of the date that you receive this ielter. Applicants are hereby notified that the 60-day statutory
appeal time does not start until the affectedpar[y (including downstream and adjacent landowners) is notified of
this decision. DWQ recommends that the appUcant conduct this notijlcatton !n order to be certabt that third
Raleigh Regional Office 7628 Mail Service Center ?;{:GLi`~:~ phone (919) 571-470Q Customer Service
Water Quality Section Raleigh, NC 27699-1628 facsimile (9i9) 571-4718 1-877-823-8748
7/1/2005
Page 2 of 2
party appeals are made hs a timely manner. To ask for a hearing, send a written petition, which conforms to
Chapter ISOB of the North Carolbta General Statutes to the t~fice of Administrative Hearings, 6714 Mall
Service Center, Raleigh, N.~ 27699-671 This determtnatlon is final and bindbeg unless you ask for a hearing
within 60 days.
The (owner/future owners) should notes the Division of Water Quality (including any other Local, State, and
Federal Agencies) of thb decision concernbtg any future correspondences regarding the subject property (stated
above). This project may require a Section 404/401 Permit for the proposed activity. Any inquiries should be
directed to the Division of Water Quality (Central O,~Rce) at (919)-7331786, and the US Army Corp of Engtnper,~
(Raleigh Regulatory Field Office) at (919}876-8441.
Eric W. Kulz
Environmental S ec. III
CC: File Copy
Central Files
DWQ 401/Wetlands Office
Teresa D. Piney -Town of Wendell
~_
Raleigh Regional Offlce 1828 Mail Service Center `;i;.lll:i.~ phone (919) 571-4700 Customer Service
Water Quality Section Raleigh, NC 27899-1828 facsimile (919) 571-4718 1-877-623-6748
+ ~ l
r.:
r,
~~~
~.
r: ,~
o~
^ Q LL.\
1~,f~(~~,p_
._.,- '1-14 ~ ,
App ~ .. •q ~
~, ;
~~) ,4y• ~ ~~ J is
300 - .1 ~ 23 ~`~,, " ~
.• ~, a , .
~ /:i
. -rr,t ~.
,~~ s ~ , ~ . .. ~ ,°
s ~ ~, :., , ~ . ~ fir""`
r,
~ pis ,... ,` ~ ~ ~ ~ _,-;
r \ ~ ~
;~ ~y-Y-
33 ~r, • Lam'" ~~ , `}';~'''. , ~,-,~'--= -_ ~ ;~
. i _- _ ~ ..
~ ~; .r ~~~
N - ~.r~ ~ •~- ea Lc ~~.
.~
r `-~
~„
} .. . .
.. ...
._ - !
~•.,. J
_ /:~'{ .
Project No. Fi ure 1- USGS Ma
9an.w~ g p
Protect Mgr.: The Woods of Bfair Hill
sc Thompson & Associates
Wake County, NC
Scale:
7- ~ 2~000~
03122/05 Zebulon, Knightdale, Clayton
and Flowers Quadrangles
y . ~ ~ ~.~,1 = v \.J f ~`:= it .:: !~i' /~,~'/
~L.. ~ ~
~...~._<.~ r
t
~ Soil & Environmental Consultants, PA
11010 Raven Ridge Rd.• Raleigh, NC 27614
(919) $48900.1919) 846-9467
Web Pape: www.SandEC.can
~ ~ OS
~~ r , ,;-+~f a ti
. ~LY.Ll.tY tJ S O~T Ll~ l i~-LC J. -
Action FD. ZQQ640822-29Z CauIIty: Wake USGS Quad; l<nit=ittdal$
GEI+IERAL PEF.I~T (REGIONAL AND NA'1'ION~~E} FER~.F~CA'~I~I1~
Property Owner I Authorized Agent: M_ iilrid~e Companies Incorporated
Address: 818 S. White Street
'Wake Forest, NC
Telephone Na.: 919-556541,$
Size and location of property (water body, road na€ne/number, town, etc.}: The raronerty is located on the east side ssf
fake Glad Road, aE3nroximately 1U75 ft nortfr of its intersection with Old Ptowefi Road, Wake County, lYC
3~escriptaan ofprojects area and aet~viiy; 'his termit authorizes the imr3act of #?.{}~ acres of wetland and 151 linear
feat of stream, associafed with a suirdivision read. -
Applicable Law: ~ Section 444 {Clean Water Acts 33 [TSC 1344}
~ Section l4 {Rivers and Harbors Act, 33 USC 443)
Authoriza#ion: Rcgior=al General Pernvt Number:
Nationwide Permit Number: 39
Your work is authorized by the above referenced permit provided it is accomplished in strict accordance with the attached
conditions and your submitted plans. Any violation of the attached conditions ar deviation from your submitted plans may subject the
pennittee to a stop work order, a restoration order and/or appropriate legal action.
This verification is valid until the NWP is modified, reissued, or revoked. ~ of the existing NWPs are scheduled to be modified,
reissued, or revoked Prior to March l8, 2447. It is incumbent upon you to remain informed of changes to the NWPs. We will issue a
public notice when the NWPs are reissued, Furthermore, if you commence or are under contract to commence this activity before the
date that the relevant nationwide permit is modified or revoked, you will-have hvelve {12) rrtonths from the date of the modification or
:revocation of the NWP to complete the activity under rite present terms and conditions of this nationwide permit. If, prior to the
c:.piration date identified below, the nationwide permit authorization is reissued and/or modified, this verification will remain valid
until the expiration date identified below, provided it complies with alI new and/or Btodified terms and conditions. The I}istrict
$ngineer may, at any times exercise his discretionary authority to modify, susperad, or revoke a case sgecif~c activity`s authorization
under any NWP.
Activities subject fa Section 444 {as indicated above}.may also require an individual Section 441 Water Quality Certification. You
should contact the NC Division of Water Quality {telephone (919) 733-3786}'to determine Section 441 requirements.
For activities occurring within the twentp coastal counties subject to regulation under the Coastal Area ltifanagement Act (CAMA},
prior to beginning work you must contact the N.C. Division of GoastaI Management .
This Department of the Army verification does not relieve the permittee of the responsibility to obtain any other required Federals
State or local approvaLslpermits.
If there are arty questions regarding this verification, nay of the conditions of the Permit, ar the Corps of Engineers regulatory
Program, Please contact Thomas Brown at (9I9} 876-8441 x22.
Corps Regulatory O£frci Bate: September 21, 20x6
Expiration Date of Verification: l+llarch 1 , 21)47
Copy Furnished:
-ebt~ie Edwards ~C~ ~ r~ ?Q~0
S&.EC
~101~ Raven Ridge Road sr- Sad & tat ConnAtants PA
Raleigh, NC 27014
.Page 1 oft
r
.~n
CX-p Cla " 1 8~`~- Y G.
INDEX Of SHEETS fOR
THE WDODS Of BU/R HILL
STORMWATER AND IMPACT MAPS
PREPARED BY THOMPSOAi Et ASSOCNIES, P,A
SNEEt` 7 -- L'XfSt;NG CCS~dt?l1tONS
St#EE7 2 - S17E" ACAPsP
SMEEt 3 ~ 574ttAi4L97ER / £,f`057ON CL3NfRDL Atr?N
SMEE7 4 ~- ~TURA~t~A7t"R ~~ EROS~N CDN1ROt PLAN
5NE£7 3 - I~4PAC7 ~1P
S~lEE7 b - MNL~f,LTJ ~AfPAC7 AREA k4AP
NOTES:
ALL APPLJCABLE LOCAL AND STATE PERMITS SHALL BE
OBTAINED PRIOR TO THE START OF CONSTRUC110N,
\,
ACCESS
{N07 PART
~ SITEj
~~
0
VIC1NiTY MAP
NO SCALE
STORMWATER AND IMPACT MAPS
FOR
THE WOODS OF BLAIR HILL
NORTH CAROLINA
DIVISION OF WATER QUAILITY
MARI~,S CREEK TOWNSHIP -WAKE COUNTY
WENDELL -NORTH CAROLINA
~~~~~~~L~~~:
EGI ~4hdES
THOMPSON do ASS{1CIATES, PA
~~C~
153 HOLLY ~'R1NGS ROAD
G` `, ~~ HOLLY SPRINGS, NC 27540
4 1 ~ /, FAX {9i )7577D9
PREUNINARY PLANS FAR, lO~j (((,,,,,,,,,///,,,
NOT RELEASED fOR CiNiSTRUCTION h'qj
~~,sf FRO
~,~
An
'T7
PRa~ERnES ARE wrtx~u AREAS of n~E roo YERA ~ 500 TEAR goons
fEIII ADOn H~LIRO SOUS ARE I.oCATm ALOhG THE HoRTrI<RH
AID E4SIERM PAbPERTY LNII£ FEIN YAP 37t83C0602 $ 20/~ x
FEIII YIP i 3718300603 F, 20NE .~ . AITE 03/03/}98?.
BFE EtfYA 753.00 dC ?3&00 APPEAR ON THE fEIIi PAAlEt.
I ~I~MI
~t
I
( _ _ ..~
1
1
:,
i ~
i
~~
r~
.tEnb .
~. ,'~.
~ y w~ w
//
..~~
:s::=i}'»,,;µ;wµ:::^{ .:_:.:,
~~:~ .....::7
~~
~~
~~~,
A1MIL! t A
~~ r
_.,
w~~3';iZC SCALD
r
`~' _
;,aD
:~x3 * ~ R
' s
I ,
I 1
~ ; ~~~ r
I ~
l____ _ t
i
..__~ h t
s
r
" ~.-~ ~ ~
I Er^ "a
! `ta 3
~ P t^
i i '-~
y_ .._ ~..~..~:.~.,~... ..._.a
i
i
t
i
_.~.~
~~
~ u+c ~ ,,-
u+e o~ ,.
o c~enc ~,,-
~"~r~ 1uY~~C
N
w
'
.~~ ~
~
:
r:
~•
%
~~~
.
,~~~i
~1 i
it ~ ~
~ {
~ ~s
jt T
'llli
ti
i "~ i
! ~t'~~°~
~i
.,
„„ ~L3 ~!
,~ p4;{
?`i~~
R g +43 ~>
~r~~~~
~ `4 ~
3.
f!3 ~~
~„,",r
r ~~_
r~s ~ ~a Y k.
~ ~ b .,~
viM'~o
~~
~; l~
~~g' '+~ i i ..
..gyp, "~ ' ;~ t` " ~ ~ r ~
. ~ •t ~
[< *N ~ '$
~ ~ ~ '
a ~°~~~~
,~~ ~ ~~~
~~~ ~ ~ ~
~~
~ ~~~~~~ ~
~ cam: ~~'•~s~~n~
z ,~~4
R
R
a~ __~
~~
:~ ~ ~ s
~.
~ s ~" ~.
~_
F
I "~
~~ ~~
~~
~ ~ ~w
~,
~~ ~~~~
~~~~~`
'~<~, yam"
~~~~~ ~~
a 3 3 S i$ z ~ i f f
~_.~.
~,;
?> k~,.?
~ ~'~
e ~ ~''
~e i
i
f
i
i
t
f
3
~, : _ : , .
____~ ~ !
'" ~ Est ~,s
l
~~~,.-~f
t
~ 7
i
t
1
~~~
~~ ~
~~ ~
~ ~
~ ~
~ ~~ ~
~~ ~~
~~ ~ ~~~~~
M
L
--- .1 , ,~,,.
W~
'b .-~'
~^1 c7
~~
~ ~~~`
~~~
~~~
n
sa ~~*
l
4
n
~~ ~~
~i ii
!~
?i ~~
`t`
E~ ~
~ ~ :~
L:
1p~ k ,
YiV
4 . . . . . . . . . . . . . . .. .. ... . . . . . e
.~yh~'t d~3`
~~
i
i
J
~_
q b~p~~
~'h 4t N
.fCiQtj uj
~~~~ M
~y
,'
~'I
jjiii
~S~is
~x
~5
~,
~~
~,~
~~~~~
~~
~ ~,~~~
x
~Q
~~
i
'`i' '~ j#
} ,
~
~~
~~ ~
~
~
~
~
~
~ ~
~ ~
~ ~
. ~
~ ~
~
Q
j
~ Y
~a
it q~
4.
~ ~ ~ Y ~ p.
~ ~ ~ ~ ~~
~ ~ ~
~ ~
s
¢~ ~ ~~~ ~ "
s~~~s~~~~ ~~~~ s~ ~~~~~~ s~~ ~~~~~~~ ~~~~~
s~~~s~~~ ~s~~ s ~~~~~s~ ~~s ~~~~~~~ ~~~ ~ ~ R
~~47 ~£@~'v
~g E~t
~2A3t f~Y^~~Y ~`d
Sd7E 9~~d
Ek ~A~~~$``~,f ~V
;2tk~~a f3 di~tl
dR2 ~N taB~T~
Z~~i
; Y E ~^yP~~4 $w'
g12k4
; h
t yi~~
2~
~
~
~~~Y~Qq~iK~11g4Y iw
~i
i~
l ~r~
%
~3
~~~~i0 `re~R~
p
~s~~ y
~e
g
d~~
~
~
m
rw
r t
z
~~
a ~r nc4r r~* }
~
if
. $
~$
$
y Q
~ Q
~ &
$
~Q
~
¢
~ Q
~ p
Y
A -K O4Y 5xwrn.49x- "~X J'~ xd S 0.fY~cvi a-~~•~ { x>t^a ~~",>~~y., ~,a g!: ~j ~.:r ~ ~ s,
~ ~
s~s~rsr
~~3~~
::.~~:~ ~
....~.. 1
.....~~ ~
:a~e~~~
~~~3~:~
<fi~~
,~aas::s
~~
_€
~9
~~
3 j
$A Y8~ N G ~ yyA~~. W ~ K
~ ZA A Y L~ ~ Y Y
a ~ ~~ ~$~~
a
" ~`Y Y
es,~
dtb
~~~
~~ ~~
Y
~x ~~
Y ~ ~ ?
~.
~~,,:
~~ ~,
~~,
~~
~~
~~
~.~
~Z
wa
__ i
PROPOSED tMPACT AREAS - AdPACf 11 `
L{~ll~t
e
1
. ' E ~'
11151
pi ~~~ OFLY~ Cf&,Y
ia4,'.
.n.»
1 1~ X3 ~ dt+2
zz ass
ror~. 9s+~
--
/~~
/ •/
P " 1 MIFFCTt, Z1 *~ Xf~E 1.. za
ztR~ ~. •
~
%
~ m1~ ~
b
~,
.
i
IMPACTED /
AREAS (INCLUDES • c~,L
DISSIPATO
~ R)
+'ryr ~:'
~
A /~ ti ;~ i
~F" ; i•,
•
r
.
•... ~
,~ ~;
~:
..,, i
~~ Rey p ~.,.•t.~.:'-'~,.:;:; ~ ~
II - -..
I IMPACT ~'
JAIPACT A4TP
THE WOODS Of BlA1R H1i1S
7V[ s°I4-0~
MNM N0.
1~ID•
7$ lF 48" RCP MATH
24' LdrNi DISSIPATdR.
PIPE TO HANIX.E EXISTING
FLdW 1HRU DRAW. NO ROADWAY
RUNOFF TO ENTER PIPE.
ROADWAY RUNOFF TO FLOW TO
CI ~ 13 do id THEN TO BMP
,: PROPQ6EO A~ACT AREAS - IMPACT !2
i ~ ~ I
~- I
I ~a
`. 1.'3
~~ ~ ~~
:~%~
,;~
,;• i ,,
'~~
,1 ~~ ~~
r~ • ~,~ ,
`~
~i'~
Z .p
~ '' ~0~
^' ~ ,.,~ 2~~ IMPACT j2
S ~.
~P' I 74 LF 30" RCP MATH
WETLANDS I 15' LdNG DISSIPATdR.
PIPE TO HANDLE EXISTING
FLOW 1HRU DRAW, Nd ROADWAY
RUNOFF Td ENTER PIPE.
RdAdWAY RUNOFF Td fldW TO
CI ~' 11 @ 12 THEN TO BMP
UtPACT AlAP
THE WOODS OF BLAiR N1LiS
TSSOIWSO~N~ ASSOCIATES. PA ~sacm+aaw
i o
rr~wa
sw r . a ~ saac n" ss .1
~. ~. ,r
c~ ~.
aaa mart 9s
• ?~ XR 1875 d
za at~z - a
saa= - !! •
a€- ~« rm ~
Pi6 • FE&~'Gpk, Xt " ~~ R, " 2~d£ Z t ~ J~ '• J%
^D! "kMSaT ~ ~ j ~
~ ~
~~ ~ ~.
~~ ~ ~
~ ?'' ,~'
.~ ~ ~
REMOVE EX. HEAOWALL`~ f ~ ~~•'•' .;COQ
'ANb EXPEND EX. 38" RCP ~ ~ ~' / q
',32 LF WITH 15' LONG DISSIPATOR ~ 9~ F •' .• ~j, ,~
°~i'
f •,
~f
1 CVO 2
_a i /
~'^.. i
15' MADE TEMPORARY
IMPACT FOR 8" SANITARY
SEWER CROSSING THROUGH
EXISTING CREEK.
TEMPORARY IMPACT Td
80TH THE EUFFER AND
/ CHANNEL. OPEN CUt FOR
1 THE} SEMA/R' CROSSING.
~''. ! ~GI•' cCoh.. 6
• ~
~ ~'
~• ti
`.
~:
...-.; , I
DPEN :::~::::..
SPACE ~i'., :::: •~~ ; ~
.... ~ ~
..
'~ I
i~ ~' ~~ I I
,, ;~ I .;
~_
%~/
i'
~~
,,
' 1
i //
IMPACTED
/ ~'
f r/
~~~~~~ ~
n
R j '~
ER •. ~... OF
.~
~ ~
` l c~~`
'~~.. tUp ~ ~'•
9~cr
~ a
rt.
""
as. •
a u+ ( as,~
,
3 P~ 27 3fli7
x797
..,`
~PROPER'tY UNE IS
CENTERLINE OF
~, ~ . ,~ „ ~,,, EXISTING CREEK
~. t~ > s ~ 21 ~ i, 3& x 2 2
IMPACT AtAP
THE WOODS Of BWR HlilS ~ x
~9iR 1h1R-qJ Y s
~pqM iR Y . 1D' !at M1 90 '
~
~ r ~• ~• ~p~v~.F-
~~
~
a ~ ~ , ~; .;~ IMPACTED
ARC
(~
/ }n `~
~"1
P
/
IiMPACT ~ ~ S
' ~ U
'`
~ R/w
~
\ y
~~
SQ' pUD SR 2358 REPLACE AND EXTEND
RAM' EX. 15" RCP 88 LF
JAVP~cr AtAF ~
JHE WOOAS OF BU1B HltlS ~ , J
w9oiuarnon~'PA Iw" I
ildlY
s•u-r ~~~
~ r.,rt sac+tisa ~ 1
c~w~eP jDEYE1.OPER:
£~S IIC~tIES
7~1 Slk FOR#S Rs'3RD
I RA1EE~ls, NC 2i6T5
i iS19) S69-Ad~S
SNFET 6 I
r ~.
• ~~`
~ ~ '
p>L _