HomeMy WebLinkAbout20240876 Ver 1_Madison 560090 Questionnaire_20240627Questionnaire: BP13.R014 Madison 560090
Existing Structure:
Can the existing bridge deck be removed during the inactive bat season/winter months
(October 16 - March 31)? (If not, please explain) Yes
Trees':
Can the trees in the project footprint be cut during the inactive bat season/winter months
(October 16 — March 31)? (If not, please explain)
*Tree clearing that occurs during the tree -roosting bat active season (April 1 — Oct 15) will require a formal Sec. 7
Consultation (BA). This process takes an additional 9-12 months to acquire a Biological Opinion from the USFWS.
Alternate dates below are provided as possible conservation measures to include in a BA:
-can tree clearing be avoided during the maternity season (May 15 — August 15)?
-can tree clearing be avoided during the pupping season (June 1 —July 31)?
Blasting:
Will blasting be used for this project? Not anticipated
If so, will blasting occur after tree clearing? If so, then yes
Utilities*:
Will any clearing for utilities be necessary? If so, can the trees in the project footprint be cut
during the winter months ( )? (If not, please explain)
*Tree clearing that occurs during the tree -roosting bat active season (April 1 — Oct 15) will require a formal Sec. 7
Consultation (BA). This process takes an additional 9-12 months to acquire a Biological Opinion from the USFWS.
Alternate dates below are provided as possible conservation measures to include in a BA:
-can tree clearing be avoided during the maternity season (May 15 — August 15)?
-can tree clearing be avoided during the pupping season (June 1 —July 31)?
Noise:
What type of noise sources will be used during project construction? (Highlight all that apply)
Pile driver
Scraper
Impact wrench
Guardrail installation/pile driver
Paver
Concrete truck
Rock drill
Jackhammer
Concrete mixer
Pneumatic wrench
Drill rig
Auger drill rig
Vibratory pile driver
Crane
Backhoe
Pneumatic chipper
Pumps, generators,
Ground compactor
Hydromulcher
compressors
Skidder
Slurry machine
Front end loader
Roller
Pneumatic riveter
Gradall
Concrete Vibrator
Circular saw (hand held)
Chain saw
Concrete saw
Road grader
Compressor
Mounted impact hammer hoe -
ram
Lighting:
Will temporary lighting for nighttime construction be necessary during the active bat season
between April 1 and October 15?
Does permanent lighting exist in the project area and if so, will it be removed, or will new
lighting be added as a result of the project? No permanent lighting exists, nor will new lighting
be added.