24 June 2024
Jim Farkus
512 N Salisbury Street, Office 640M
Raleigh, NC 27604
Reference: Rooms to Go Building and Parking Expansion (#SW6131201)
901 Rooms to Go Way
Dunn, NC 28334
Comments Received Date: 05/29/2024 Resubmittal Date: 06/24/2024
The Plan review comments are listed below. Our written responses are in bold font following the
comments.
1. Please clarify what set of rules (either S.L. 2006-246 or the"2017 Rules")you would like the wet
pond designs to reviewed under. If the pond design is not being changed from what was originally
permitted under S.L. 2006-246, with only the drainage area and BUA directed to the SCMs
changing, the SCMs can be reviewed for compliance under S.L. 2006-246, or, as part of the
modification, you can bring the design up to current(2017) rules (NOTE: It appears as though the
project is being brought up to the 2017 rules based on the provided calculations).
Response: We would like the SCM design to be reviewed for compliance under S.L. 2006-246
and have provided the appropriate calculations. Several items listed as comments under the
2017 Rules have been addressed and responded to as we noted they are also applicable to
S.L. 2006-246.
a. If bringing the project up to the current design standards, please correct the following:
i. General:
1. Please ensure that the off-site area for the SCM drainage area is
accounted for at its full build-out potential. The full build-out potential can
be determined by either having the property owners enter a legal
agreement that limits the amount of drainage area and BUA directed from
the off-site area to the SCM or by assuming that the off-site area is 100%
BUA, its full build-out potential.lt is recommended to bypass off-site areas
around the SCM. NOTE: The SCMs are shown to be oversized so this
does not appear to have an impact on the SCM design.
Response: The offsite drainage area was accounted for at 100% BUA.
2. General MDC 4— Please provide calculations showing that the inlets and
outlets for the SCMs will be stable as required per the MDC based on the
revised drainage area compositions.
Response: The inlet and outlet protection will be field verified for
compliance with the previously approved plans. Detail has been
added to the plans to show what was approved.
3. Wet Pond MDC 5b— Please ensure that the bottom of the forebay near the
entrance is deeper than the bottom of the forebay near the exit.
Response: We did find a discrepancy between as-built survey for the
forebay and the construction notes and photos from 2014. Our
documentation indicates that the forebay was constructed to the
adequate depth. We have noted on the plans that the forebay depths
The SITE Group
1111 Oberlin Road 919-835-4787 (o)
Raleigh NC 27605 1/4 919-839-2255 (f)
RTGDE
24 June 2024
should be field verified and repaired to the previously approved
design condition if necessary.
4. Wet Pond MDC 11 — Please provide a planting plan that meets the
requirements of the MDC (The plans indicate that this information is
provided on plansheet SITE 700, however this sheet is not located within
our permit file).
Response: We have included the planting plan from 2014 to show
plantings that were provided and note that the pond plantings have
been professionally maintained and inspected since 2014. The
condition of existing plantings will be included with the next annual
SCM report.
5. "Existing BUA" refers to BUA that existed on-site prior to the rules going
into effect, not necessarily what exists on-site currently. Please revise the
Application Form (Section IV, 10) and Supplement-EZ Form to correctly
account for existing BUA. Please revise as needed.
Response: Noted, the BUA was updated.
6. In order for a project to meet Runoff Treatment, the net increase in BUA
must be captured and treated in one or more primary SCMs. Per the
provided drainage area map, there is 0.53 acres of uncaptured BUA(within
drainage area A3) proposed. Please revise as needed. NOTE: If it is not
practicable to capture and treat the net increase in BUA for this project, the
uncaptured areas can be permitted as a low-density area in accordance
with 15A NCAC 02H .1003(1)(d).
Response: We have revised the plan to indicate that the construction
road to the back of the site is temporary, that gravel should be
removed and revegetated at the end of construction operations. All
BUA will be captured and treated.
ii. Southeast Pond:
1. Wet Pond MDC 7— Per the provided calculations, the drawdown time is
shown as 0.67 days (0.67 days < 2 days).
Response: we have specified modifications to the outlet control
structure to increase the drawdown time as required.
iii. Southwest Pond:
1. Wet Pond MDC 5a—As designed, the forebay is not within 15%-20% of
the main pool volume (Main Pool Volume = 292,708 cf, Forebay Volume =
61,175 cf, 61,175 cf/292,708 cf= 20.9% > 20%).
Response: As noted above, forebay depths will be field verified that
they meet the previously approved design criteria. It has been noted
that any deviation from the original design will be repaired as part of
this project.
2. Wet Pond MDC 7— Per the provided calculations, the drawdown time is
shown as 0.78 days (0.78 days < 2 days). Response: We have specified
modifications to the outlet control structure to increase the
drawdown time as required.
The SITE Group
1111 Oberlin Road 919-835-4787 (o)
Raleigh NC 27605 2/4 919-839-2255 (f)
RTGDE
24 June 2024
3. Please provide the stage-storage table for this SCM. The provided
calculations have two copies of the stage-storage table for the Southeast
Pond and do not include one for this SCM.
Response: Stage storage for both SCMs were included in the manual.
b. If you would like the SCM design to be reviewed for compliance under S.L. 2006-246,
please provide calculations demonstrating that the project will meet those rules.
Response: We would like the SCM design to be reviewed for compliance under S.L.
2006-246 and have provided the appropriate calculations.
2. Please correct the following issues with the Supplement-EZ Form (in addition to any items that
need to be revised per earlier comments):
a. Drainage Areas Page:
i. Please complete the entire site column. The entire site column is an accounting of
the entire project area (similar to how the drainage area columns are an accounting
of the areas draining to the SCMs). NOTE: The entire site column is not
necessarily a sum of the other columns (for example, BUA that is located on-site
but not draining to an SCM would be included in the entire site column but not in
an SCM drainage area column). NOTE: There are generally no off-site
components to the entire site column (since off-site areas are not located within the
project area).
Response: Entire site column has been filled out.
ii. Line 18— Please revise. These values should correspond to those shown in
Section IV, 10 of the Application and should reflect the percent BUA of the area
draining to the SCM.
Response: We have ensured the application and the supplement match.
b. Wet Pond Page:
i. SCM 2, Line 40— Per the calculations, this value is shown as 0.67 days (0.86 days
is shown). Please also see earlier comment with regard to drawdown time.
Response: The appropriate calculations per S.L. 2006-246 have been
provided with this submittal.
3. Please provide a copy of the recorded easements for the stormwater collection and treatment
system. This item is required per permitting condition 1.3. of Permit No. SW6131201.
Response: Easements were not recorded when the ponds were originally built. We are
proposing SCM access and maintenance easements on the revised plans, which will be
recorded upon approval.
4. Please provide a Response to Comments letter indicating, in a point-by-point manner,
how each of the above comments has been addressed. This item is required per 15A
NCAC 02H .1042(3)(b).
Response: A comment response letter has been provided with our submittal.
5. Provide PDFs of all revisions, 2 hardcopies of revised plan sheets, 1 hardcopy of other documents,
and a response to comments letter briefly describing how the comments have been addressed.
a. PDFs must be uploaded using the form at: https://edocs.deq.nc.gov/Forms/SW-
Supplemental-Upload
b. Hard copies must be mailed or delivered to the following address:
The SITE Group
1111 Oberlin Road 919-835-4787 (o)
Raleigh NC 27605 3/4 919-839-2255 (f)
RTGDE
24 June 2024
i. For FedEx/UPS:
Jim Farkas
512 N. Salisbury Street, Office 640M
Raleigh, NC 27604
ii. For USPS:
Jim Farkas
1612 Mail Service
Center
Raleigh, NC 27699-1612
iii. Hand Delivery:
Please reach out to me prior to hand delivering a submission to make sure that I
(or someone else in my group)will be able to receive the submission. Do not
leave the package in the foyer with the security guard.
NOTE: Hard copies should not be sent to a Regional Office. Doing so will delay
the review process and the submission package may be lost while being sent from
the Regional Office to me in the Central Office.
Response: PDFs have been uploaded using the appropriate form and 2 hard
copies are being hand delivered to your group.
Please feel free to call me at(919) 744-9449 or email at bdm@thesitegroup.net if you would like to discuss
any aspect of this project.
Sincerely,
Brandon Moore
The Site Group, PLLC