HomeMy WebLinkAbout820006_30 Day POA_20240520PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
Facility Number:
82-6
Facility Name: Colonel Lamb
County: Sampson
Certified Operator Name: Brandon Norris Operator Number: 1004381
1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the
lowest point on the top of the dam for lagoons without spillways; and from the current liquid level
in the lagoon to the bottom of the spillway for lagoons with spillways.
Lagoon Name/ID
Spillway(Y or N):
Level(inches):
Lagoon Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5
N
19
2. Check all applicable items
Liquid level is within the designed structural freeboard elevations of one or more structures.
Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are
within acceptable ranges.
X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A
30 day Plan of Action is attached. Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste
to be pumped and hauled is reflected in section III tables. Included within this plan is a list
of the proposed sites with related facility numbers, number of acres and receiving crop
information. Contact and secure approval from the DWQ prior to transfer of waste to a site
not covered in the facility's CAWMP.
Operation will be partially or fully depopulated.
*Attach a complete schedule with corresponding animal units and dates fro depopulation
*if animals are to be moved to another permitted facility, provide facility number, lagoon
freeboard levels and herd population for the receiving facility
3. Earliest possible date to begin land application of waste: 5/17/2024
I hereby certify that I have reviewed the information listed above and included within the
attached Plan of Action, and to the best of my knowledge and ability, the information is
accurate and correct.
HD 3 Farms David Mixon Manager Phone
Facility Owner/Manager (print)
Date
Facility Owner/Manager (signature)
910-385-5196
5/15/2024
II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR./24
HR. STORM
STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY
1.
Structure ID: 1
line m =
690.6 lb PAN
2.
Structure ID:
line m =
lb PAN
3.
Structure ID:
line m =
lb PAN
4.
Structure ID:
line m =
lb PAN
5.
Structure ID:
line m =
lb PAN
6.
Structure ID:
line m =
lb PAN
In. lines 1 +2+3+4+5+6=
690.6 lb PAN
III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN
PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD.
o. tract #
p. field #
q. crop
r. acres
s. remaining IRR
2 PAN balance
(lb/acre)
t. TOTAL PAN
BALANCE FOR
FIELD (Ibs.)
^ ~485.3
u. application window'
5
Bermuda
2.86
169.68
Mar -Sep
13
Bermuda
3.18
106.78
339.6
Mar -Sep
'State current crop ending application date or next crop application beginning date for available
receiving crops during 30 day draw down period.
v. Total PAN available for all fields (sum of column t) = 824.8 lb. PAN
IV. FACILITY'S PoA OVERALL PAN BALANCE
w. Total PAN to be land applied (line n from section II) = 690.6 lb. PAN
PoA (30 Day) 2/21 /00
x. Crop's remaining PAN balance (line v from section III) = 824.8 lb. PAN
y. Overall PAN balance (w - x) _ -134 lb. PAN
Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump
and haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new
PAN based on new information. If new fields are to be included as an option for lowering lagoon level, add
these fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be
hauled to another permitted facility, provide information regarding the herd population and lagoon freeboard
levels at the receiving facility.
Irrigation onto existing spray fields occurred as weather and field conditions permited.
PoA (30 Day) 2/21 /00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID): 1
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker 19.0 inches
b. designed 25 yr./24 hr. storm & structural freeboard 19.0 inches
c. line b - line a (inches in red zone) = inches
d. top of dike surface area according to design
(area at below structural freeboard elevation) 1117031 ft2
e. line c/12 x line d x 7.48 gallons/ft3 gallons
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design 180 days
g. volume of waste produced according to structural design 161411 ft3
h. current herd # 4896 certified herd # 4896
actual waste produced = current herd # x line g =
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 1 5/6/2024
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
161411 ft3
01ft3
71328 ft3
290148 gallons
2.38 Ibs/1000 gal.
690.6 Ibs. PAN
PoA (30 Day) 2/21 /00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID):
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker Dinches
b. designed 25 yr./24 hr. storm & structural freeboard Dinches
c. line b - line a (inches in red zone) = inches
d. top of dike surface area according to design
(area at below structural freeboard elevation) Oft2
e. line c/12 x line d x 7.48 gallons/ft3 gallons
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design Odays
g. volume of waste produced according to structural design Oft3
h. current herd # certified herd #0
actual waste produced = current herd # x line g =
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
ft3
�ft3
0 ft3
gallons
Olbs/1000 gal.
0 lbs. PAN
PoA (30 Day) 2/21 /00