HomeMy WebLinkAbout20150994 Ver 1_Emails_20160208Strickland, Bev From: Joey Lawler <JLawler@smeinc.com> Sent: Monday, February 08, 2016 1:31 PM To: Brown, David W SAW Cc: Moore, Andrew W Subject: RE: T-10 Replacement - Sheet Pilings and Temp Bridge at Green River Crossing Attachments: 53020-34-052(IFCO20816).pdf, 20150208 Bi -Weekly Report.pdf David - please see attached the first of the bi-weekly status reports included as a special condition of the permit. The next will be submitted two weeks from today. Also attached is the amended Green River crossing detail drawing for your records. Thanks and please let me know if you need anything else -j Joey Lawler, P.W.S. Project Manager ENGINEERING INTEGRITY S&ME, Inc. 9751 Southern Pine Boulevard Charlotte NC 28273 Map Ph: 704.523.4726 Fax: 704.525.3953 Mobile: 704.604.6474 jlawler@smeinc.com www.smeinc.com S&ME, Inc. moves up twelve spots in 2015 ENR Top 500 to 89. This electronic message is subject to the terms of use set forth at www.smeinc.com/email. If you received this message in error please advise the sender by reply and delete this electronic message and any attachments. Please consider the environment before printing this email. -----Original Message ----- From: Brown, David W SAW[mailto:David.W.Brown@usace.army.mil] Sent: Friday, February 05, 2016 7:09 AM To: Joey Lawler <JLawler@smeinc.com> Cc: Moore, Andrew W <andrew.w.moore@ncdenr.gov> Subject: RE: T-10 Replacement - Sheet Pilings and Temp Bridge at Green River Crossing Joey, This looks good & no additional authorization is needed from the Corps at this crossing. Have a good weekend, David 1 David Brown, PG Regulatory Specialist/Geologist 828-271-7980, ext. 232 david.w.brown@usace.army.mil USACE Wilmington District - Asheville Regulatory Field Office 151 Patton Avenue, Room 208 Asheville, NC 28801-5006 The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we continue to do so, please complete the Customer Satisfaction Survey located at http://corpsmapu.usace.army.mil/cm_apex/f?p=136:4:0 -----Original Message ----- From: Joey Lawler [mailto:JLawler@smeinc.com] Sent: Thursday, February 04, 2016 2:38 PM To: Brown, David W SAW <David.W.Brown@usace.army.mil> Cc: Moore, Andrew W <andrew.w.moore@ncdenr.gov> Subject: [EXTERNAL] RE: T-10 Replacement - Sheet Pilings and Temp Bridge at Green River Crossing David - per our conversation last week - attached is a photo of a similar crossing the contractor did somewhere else. Andrew - I realized that I did not copy you on this last week, so please see below. The contractor is planning on installing some temporary sheet pilings around either side of the live gasline to protect it during the open cut of the Green River. There will be no change what -so -ever in the permitted impact footprint, but since this stuff wasn't depicted on the original plan, so we are having them generate a drawing for your record. Their rough notes are attached for additional reference as well. I'll forward the clean drawing to you as soon as we get it, and please don't hesitate to call me if you have any questions - Joey Lawler, P.W.S. Project Manager ENGINEERING INTEGRITY S&ME, Inc. 9751 Southern Pine Boulevard Charlotte NC 28273 Map <Blockedhttp://maps.google.com/maps?q=9751%2OSouthern%2OPi ne%20BIvd%2CCharlotte%2CNC%2C28273%2CU nite d % 20States> Ph: 704.523.4726 Fax: 704.525.3953 Mobile: 704.604.6474 jlawler@smeinc.com <mailto:y@smeinc.com> Blockedwww.smeinc.com <Blockedhttp://www.smeinc.com/> S&ME, Inc. moves up twelve spots in 2015 ENR Top 500 to 89. This electronic message is subject to the terms of use set forth at Blockedwww.smeinc.com/email <Blockedhttp://www.smeinc.com/emai1> . If you received this message in error please advise the sender by reply and delete this electronic message and any attachments. Please consider the environment before printing this email. From: Joey Lawler Sent: Monday, February 01, 2016 8:44 AM To: 'David.W.Brown@usace.army.miI' <David.W.Brown@usace.army.mil> Cc: crogers@smeinc.com; Tom Perez <TPerez@smeinc.com> Subject: T-10 Replacement - Sheet Pilings and Temp Bridge at Green River Crossing Hey David thanks for speaking with me today. Per our conversation, the contractor had some concern about exposing the existing live line at the Green River crossing, so are taking some additional precautions. This is a sketch that they provided. The sheet pilings will protect the existing pipe, and the bridge will let them string the new pipe and excavate. All will be conducted within the existing permitted footprint - no additional temp workspace is required - no new impacts, just changing the method of installation slightly. I will be able to get you a better drawing for the record in the next few days. Thanks again for your help -j Joey Lawler, P.W.S. Project Manager ENGINEERING INTEGRITY S&ME, Inc. 9751 Southern Pine Boulevard Charlotte NC 28273 Map <Blockedhttp://maps.google.com/maps?q=9751%2OSouthern%2OPi ne%20BIvd%2CCharlotte%2CNC%2C28273%2CU nite d % 20States> Ph: 704.523.4726 Fax: 704.525.3953 Mobile: 704.604.6474 jlawler@smeinc.com <mailto:y@smeinc.com> Blockedwww.smeinc.com <Blockedhttp://www.smeinc.com/> S&ME, Inc. moves up twelve spots in 2015 ENR Top 500 to 89. This electronic message is subject to the terms of use set forth at Blockedwww.smeinc.com/email <Blockedhttp://www.smeinc.com/emai1> . If you received this message in error please advise the sender by reply and delete this electronic message and any attachments. Please consider the environment before printing this email. +�Mhmll •�L A-V February 8, 2016 U.S. Army Corps of Engineers Asheville Regulatory Field Office 151 Patton Avenue, Room 208 Asheville, NC 28801 Attention: Mr. David Brown, P.G. Bi -Weekly — February 6, 2016 Line -Pipeline Replacement Project Polk, Henderson and Buncombe Counties, North Carolina USACE Action ID No. 2015-00457 DWR Project No. 15-0994 Dear Mr. Brown: This letter is in reference to the Line T-01 Pipeline Replacement Project located in Polk, Henderson and Buncombe Counties. In accordance with a special condition of project authorization under Nationwide Permit No. 12, issued by your office on November 19, 2015, this letter represents the first of what will hereafter consist of bi-weekly (once every two weeks) reports summarizing construction progress of the project. The primary construction contractor is Latex Construction Company (Latex). Although mobilization and equipment staging operations commenced around the first week of January, project construction did not officially commence until January 25, 2016. S&ME currently has three Environmental Inspectors assigned to the project. Relevant pre -construction activities (January 11— 24) and a summary of work that has occurred since the official start of construction (January 25- February 6) are listed below: + Project has been broken into three phases for purposes of NPDES reporting: Phase 1 (Stations 0-390) with rain gage at Green River Cove Road; Phase 2 (Stations 390-830) with rain gage at Chestnut Stump Road; Phase 3 (Stations 830-1336) with rain gage at Lewis Road. + S&ME Environmental Inspectors marked streams and wetlands with signage and photographed existing conditions in addition to marking Access Roads with signage and photographing existing conditions. + An environmental orientation and pre -construction meeting were held on January 19, 2015 at PSNC Hendersonville office. Orientation presented by S&ME personnel to Latex personnel (foremen -level and above), S&ME Environmental Inspectors, PSNC personnel, and additional PSNC third -party Inspectors. Mandatory NCDEQ Pre -construction meeting was scheduled for that afternoon at the same location; however, NCDEQ personnel did not attend. Bi -Weekly Status Report: January 11- February 6, 2015 Line T-01 Replacement Project + Latex plans to install some segmentable temporary sheet piling in Green River adjacent to existing pipe to prevent undermining during installation of new pipe. S&ME performed hydraulic study and determined that flow would not be altered substantially if the piling is installed as proposed and the upstream dam releases were ceased during construction. Latex estimates that pipe installation can be accomplished within 3-5 days if this approach is used. PSNC to notify Duke Energy regarding lake release scheduling. + S&ME met with Cathy Ruth (Polk County Planning and Zoning) on January 20, 2016 to view pre - construction conditions at the Green River and Ostin Creek crossings and discuss floodplain encroachment mitigation measures. Clearing — Latex Cleared ROW for Cane Creek HDD (Sta 1169+90 —1218+00) and mobilized to Bright's Creek Golf Course (Sta 388+00). Began clearing ROW at Bright's Creek Golf Course, across the Green River, and towards Silver Creek Road (Sta 388+00 —187+71) installing temporary bridges at streams and timber mats across wetlands. Environmental crew — Installed ECDs for Cane Creek HDD (Sta 1172+00 —1191+00) per plans. Installed ECDs for entry pad at Wetland WC -19 HDD/Clear Creek HDD. Began installing ECDs at Bright's Creek Golf Course towards the Green River (Sta 388+00 — 276+00) per plans. + Grading/ROW — Placed timber mats along ROW for access to Cane Creek HDD (Sta 1169+90 - 1190+00) including entry pad, exit pad, and temporary bridges over Streams SD -35 and SD -36 and Wetlands WD -32 and WD -33. Placed timber mats for entry pad and along ROW for access to Wetland WC -19 HDD (832+50 — 846+29) and Clear Creek HDD (Sta 847+02 — 855+06). Began grading ROW at Bright's Creek Golf Course (Sta 388+00 — 308+00). + Road bore crew mobilized to Clubhouse Lane at Bright's Creek Golf Course on February 6, 2016 and began preparing for road bore under Clubhouse Lane. + Major rain event (4.0" on February 3, 2016); numerous ECDs overwhelmed on Bright's Creek Golf Course, with some sedimentation onto the golf course. Contractor began repairing ECDs and working on removing off-site sedimentation on February 4, 2016, and is currently working on a plan with the golf course operations director to clean up sediment on the driving range. + Daily reports provided by S&ME Environmental Inspectors indicate that construction operations to date have been conducted in accordance with applicable conditions of the aforementioned permits, with no deficiencies identified except as noted in the bullet above. The next bi-weekly report is scheduled for submission on, or about, the week of February 22, 2016. If you have questions or need additional information, please feel free to contact me at 704.523.4726. Sincerely, S&ME, Inc. {r Joey Lawler Project Manager February 8, 2016 Page 2 9 POLK COUNTY, NORTH CAROLINA ATWS / PERMANENT EASEMENT EXISTING PIPELINE T-0018 1 �� I—� F—� �H—� F—� f—H ♦—� SHEET PILE DOWNSTREAM P/L H -BEAM H -BEAM in n SHEET PILE 1 - N IACK SHEET WITH J" CABLE` f0 T MAXIMUbj EPARfION I I I I j I 1122x42'1 I 1 UPSTREAM i ITEMPORARY CO PERMANENT EASEMENT TEMPORARY WORKSPACE ONE UNIT RUNNING �� L WATER LEVEL i y i ) Lo TEMPORARY WORKSPACE — — — _�pQ --- --- / C —FLOW 150' CONSTRUCTION R -O -W. 25' ATWS 75' 50' TEMP /' //BAC UP TURBIDITY CURTAIN i ATWS % 25' X 282' /LIQ PRIMARY TURBIDITY CURTAIN /T PROPOSED 20" — P/L PIPELINE T -001A TER ILEVEL I / ;TION BRIDGE 10' WIDE PERMANENT EASEMENT 1 1 1 1 1 y/ TEMPORARY WORKSPACE ONE UNIT RUNNING WATER LEVEL WA08 / I — / B A —FLOW 990 980 970 960 950 940 930 920 910 900 890 880 870 *I JF]0 SECTION A—A SCALE N.T.S. 50" 25" z 24' TEMPORARY 13• CONSTRUCTION ww w Gia z_ 13 6 24 I TEMPORARY CONSTRUCTION LY m ^ � � Y www z zea °$ w BRIDGE ---- TURBIDITY CURTAINS BRIDGE SHEET PILE SAND)1 .. / N }o o° ANCHOR (TYP.) 1 SAND) fo o ANCHOR (TYP.) SAND ROCK & COBBLE EXISTING i-0018 12 SECTION C—C ROCK & COBBLE EXISTING J 12" SECTION 13-13COBBLE ROCK & EXISTING - 12" CID Li �zw SCALE: N_T_S- SCALE: N 5 04 o D_ U¢ w O Li Li 2 L� 3 OOCD 00 z w 31: " x w 0 OCD O o wU¢ m 990 980 970 960 950 940 930 920 910 900 890 880 870 *I JF]0 SECTION A—A SCALE N.T.S. 245+50 PROJECTION SYSTEM: NAD83 STATE PLANE, NORTH CAROLINA (U.S. SURVEY FEET) R/W INGRESS X=588523.9600' Y=1031736.4737' R/W EGRESS X=588659.9957' Y=1031677.8121' I I I I I I 1 245+00 244+50 244+00 243+50 243+00 242+50 242+00 ISSUED FOR CONSTRUCTION 08—FEB-201 6 3020-31-011 ALJGNMENT SHEET ORAWNING NO. ORANING TIRE REFERENCE DRAWINGS 990 980 970 960 950 940 930 920 910 900 890 880 870 LEGEND - ~- - ww w Gia z_ Y z¢ w [' ^ d'^ P- o P LY m ^ � � Y www z zea °$ cl ---- TURBIDITY CURTAINS SHEET PILE J Ln x 3� 3� I. Lr 3� �J�it a �a zw w uJ) CID Li �zw 04 o D_ U¢ w O Li Li 2 L� 3 OOCD 00 z w 31: " x w 0 OCD O o wU¢ cN 0 U0 0 O LLj LLj w� J Ld Z.. 0 p z 00 wCkf a o w w � w �_ D- m n 00 Lo Lo +*0. + 00 U N + Q ro M p N M N N - M 00 M N N � * N N M -t � c4 N O) C'4'4- to N Lr. N + C r►B r► CXI N NATURAL GRADE WATER ELEV. WITH WATER ELEV. POWER GENERATION 911.178 LOW WATER 90E.653 NATURAL GRADE \\�\ PROPOSE 20"PIPELINE T-0 1A L C P B A 175 FT. CONCRETE COATED PIPE 245+50 PROJECTION SYSTEM: NAD83 STATE PLANE, NORTH CAROLINA (U.S. SURVEY FEET) R/W INGRESS X=588523.9600' Y=1031736.4737' R/W EGRESS X=588659.9957' Y=1031677.8121' I I I I I I 1 245+00 244+50 244+00 243+50 243+00 242+50 242+00 ISSUED FOR CONSTRUCTION 08—FEB-201 6 3020-31-011 ALJGNMENT SHEET ORAWNING NO. ORANING TIRE REFERENCE DRAWINGS 990 980 970 960 950 940 930 920 910 900 890 880 870 MINIMUM MATERIALS 400 FEET -SHEET PILE SPECIFICATION PZC18 BALL & SOCKET, 25" WIDTH X 0.375" WALL THICKNESS IN 25' LENGTHS 250 FEET -H-BEAM FOR TIE -BACK AND WALL STABILIZATION HP14-89 14" FLANGE IN 50' LENGTHS. 600 FEET -TIE-BACK CABLE - 3/<" HIGH STRENGTH WIRE ROPE AND V HIGH STRENGTH COIL CONNECTOR RODS. 25 - MINIMUM NUMBER OF TIE -BACK ANCHORS 12 UPSTREAM AND 13 DOWNSTREAM AT 9 TO 10 FOOT INTERVALS. —FLOW -TEMPORARY CONSTRUCTION BRIDGE --ANCHOR (TYP.) 22" PZC18 BALL&SOCKET, 0.375 WALL THICKNESS 25" SEGMENT -50" UNIT SHEET PILE DETAIL SCALE: N-T.S. .a jC PROPOSED / RIVER i Fi CROSSING > NOTES 1. SHEET PILING TO BE USED BY CONTRACTOR SHALL BE DESIGN BY A QUALIFIED GEOTECHNICAL ENGINEER. 2. SHEET PILING MINIMUM DESIGN SHALL PROVIDE A SAFETY FACTOR OF 1.75. 3. SHEET PILING DESIGN SHALL PROVIDE NECESSARY STABILITY FROM ANY EXPECTED VERTICAL AND HORIZONTAL LOADING TO SUPPORT, EQUIPMENT, SOIL, HYDRAULIC LOADING. 4. SHEET PILE DESIGN SHALL BE DRIVEN TO DEPTHS TO PREVENT HYDRAULIC UNDER MINING AND SHALL HAVE TIE -BACKS APPROPRIATELY DESIGNED TO PREVENT ACTIVE AND PASSIVE WALL ROTATION AFTER MATERIAL IS REMOVED BETWEEN PILE WALLS. 5. ADEQUATE NUMBER OF 14" DEEP WINDOWS SHALL BE PROVIDED TO ACCOMMODATE NOMINAL STREAM FLOW THROUGH THE UPSTREAM AND DOWNSTREAM STRUCTURES WITHOUT UNDUE UPSTREAM HYDRAULIC GAIN. (MINIMUM UPSTREAM WATER HEAD OF 12 INCHES ABOVE MEAN AVERAGE FLOW ELEVATION DOWNSTREAM OF THE STRUCTURES. 6. ALL EQUIPMENT USED WITHIN AND OVER WATER SHALL USE VEGETABLE HYDRAULIC FLUID AND BE EQUIPPED WITH SECONDARY CONTAINMENT FUEL CELLS. 7. CONTRACTOR SHALL PROVIDE ON SITE ALL NECESSARY BOOMS, SORBENTS, BOATS, TO REACT IMMEDIATELY TO MITIGATE ACCIDENTAL RELEASE OF ANY FLUIDS FROM EQUIPMENT. 8. EXCAVATED MATERIAL SHALL NOT BE PLACED WITHIN THE STREAM BUT UPON THE STREAM BANK WITHIN A SEDIMENT CONTAINMENT STRUCTURE AND SUFFICIENT DISTANCE FROM THE WATER TO PREVENT MIGRATING BACK TO THE WATER UNTIL SUCH TIME TO BACKFILL THE CROSSING. 9. EVERYOTHER Z PILE SHEET SHALL BE DRIVEN A MINIMUM OF 6 -INCHES BELOW WATER SURFACE. HP14-89 H -BEAM, FLANGE AND WEB THICKNESS 0.615" SHEET PILE INSTALLATION DETAIL SCALEN T 3 RIVER FLOW RATES NOMINAL FLOW : 42-60 CFS ONE TUXEDO UNITS RUNNING 222-240 CFS TWO TUXEDO UNITS RUNNING 402-420 CFS 2 YEAR 30 MINUTE RAIN FALL EVENT OF 1.2 INCHES, 38,400 ACRE DRAINAGE ADDS 427 CFS 0 25 50 PLAN SC4E' 1•_50' 0 25 50 PROFILE (H) SCHE 1--50' 0 25 50 IE CHmm �7) yy ENGINEER .RA APP�OOED ISSUE RECORD (V) scxE. 1- 14" I H 14" WBA, P, C, FIRM REGISTRATION NUMBER: NC C-2618 PSNC ENERGIG SCANA - T -001A REPLACEMENT GREEN RIVER CROSSING SHEET PILE DETAIL POLK COUNTY NORTH CAROLINA AWN SJS Sc�,E NOTED AFE 0059354 GR WL 02-05-16 DRAWING NO. IKFA SL ;RO„�, DEM 53020-34-052 iPPR�OVED JWL Feb, ­y 08, 2010 — &Ok. LEGEND - ~- - EROSION & SEDIMENTARY CONTROL DEVICE TEMPORARY SPOIL PILE WOOD MATS °$ ENERGY DISSIPATION MATERIAL ---- TURBIDITY CURTAINS SHEET PILE 0 H BEAM TEMPORARY CONSTRUCTION BRIDGE MINIMUM MATERIALS 400 FEET -SHEET PILE SPECIFICATION PZC18 BALL & SOCKET, 25" WIDTH X 0.375" WALL THICKNESS IN 25' LENGTHS 250 FEET -H-BEAM FOR TIE -BACK AND WALL STABILIZATION HP14-89 14" FLANGE IN 50' LENGTHS. 600 FEET -TIE-BACK CABLE - 3/<" HIGH STRENGTH WIRE ROPE AND V HIGH STRENGTH COIL CONNECTOR RODS. 25 - MINIMUM NUMBER OF TIE -BACK ANCHORS 12 UPSTREAM AND 13 DOWNSTREAM AT 9 TO 10 FOOT INTERVALS. —FLOW -TEMPORARY CONSTRUCTION BRIDGE --ANCHOR (TYP.) 22" PZC18 BALL&SOCKET, 0.375 WALL THICKNESS 25" SEGMENT -50" UNIT SHEET PILE DETAIL SCALE: N-T.S. .a jC PROPOSED / RIVER i Fi CROSSING > NOTES 1. SHEET PILING TO BE USED BY CONTRACTOR SHALL BE DESIGN BY A QUALIFIED GEOTECHNICAL ENGINEER. 2. SHEET PILING MINIMUM DESIGN SHALL PROVIDE A SAFETY FACTOR OF 1.75. 3. SHEET PILING DESIGN SHALL PROVIDE NECESSARY STABILITY FROM ANY EXPECTED VERTICAL AND HORIZONTAL LOADING TO SUPPORT, EQUIPMENT, SOIL, HYDRAULIC LOADING. 4. SHEET PILE DESIGN SHALL BE DRIVEN TO DEPTHS TO PREVENT HYDRAULIC UNDER MINING AND SHALL HAVE TIE -BACKS APPROPRIATELY DESIGNED TO PREVENT ACTIVE AND PASSIVE WALL ROTATION AFTER MATERIAL IS REMOVED BETWEEN PILE WALLS. 5. ADEQUATE NUMBER OF 14" DEEP WINDOWS SHALL BE PROVIDED TO ACCOMMODATE NOMINAL STREAM FLOW THROUGH THE UPSTREAM AND DOWNSTREAM STRUCTURES WITHOUT UNDUE UPSTREAM HYDRAULIC GAIN. (MINIMUM UPSTREAM WATER HEAD OF 12 INCHES ABOVE MEAN AVERAGE FLOW ELEVATION DOWNSTREAM OF THE STRUCTURES. 6. ALL EQUIPMENT USED WITHIN AND OVER WATER SHALL USE VEGETABLE HYDRAULIC FLUID AND BE EQUIPPED WITH SECONDARY CONTAINMENT FUEL CELLS. 7. CONTRACTOR SHALL PROVIDE ON SITE ALL NECESSARY BOOMS, SORBENTS, BOATS, TO REACT IMMEDIATELY TO MITIGATE ACCIDENTAL RELEASE OF ANY FLUIDS FROM EQUIPMENT. 8. EXCAVATED MATERIAL SHALL NOT BE PLACED WITHIN THE STREAM BUT UPON THE STREAM BANK WITHIN A SEDIMENT CONTAINMENT STRUCTURE AND SUFFICIENT DISTANCE FROM THE WATER TO PREVENT MIGRATING BACK TO THE WATER UNTIL SUCH TIME TO BACKFILL THE CROSSING. 9. EVERYOTHER Z PILE SHEET SHALL BE DRIVEN A MINIMUM OF 6 -INCHES BELOW WATER SURFACE. HP14-89 H -BEAM, FLANGE AND WEB THICKNESS 0.615" SHEET PILE INSTALLATION DETAIL SCALEN T 3 RIVER FLOW RATES NOMINAL FLOW : 42-60 CFS ONE TUXEDO UNITS RUNNING 222-240 CFS TWO TUXEDO UNITS RUNNING 402-420 CFS 2 YEAR 30 MINUTE RAIN FALL EVENT OF 1.2 INCHES, 38,400 ACRE DRAINAGE ADDS 427 CFS 0 25 50 PLAN SC4E' 1•_50' 0 25 50 PROFILE (H) SCHE 1--50' 0 25 50 IE CHmm �7) yy ENGINEER .RA APP�OOED ISSUE RECORD (V) scxE. 1- 14" I H 14" WBA, P, C, FIRM REGISTRATION NUMBER: NC C-2618 PSNC ENERGIG SCANA - T -001A REPLACEMENT GREEN RIVER CROSSING SHEET PILE DETAIL POLK COUNTY NORTH CAROLINA AWN SJS Sc�,E NOTED AFE 0059354 GR WL 02-05-16 DRAWING NO. IKFA SL ;RO„�, DEM 53020-34-052 iPPR�OVED JWL Feb, ­y 08, 2010 — &Ok.