December 28, 2015
Buncombe County Soil & Water Conservation District
US Army Corps of Engineers
NC Department of Environmental Quality
NC Wildlife Resources Commission
Gary Higgins
Director
RECEIVED
Division of Water Resources
3 s"
JAN - 4 2016
Water Quality Regional Operations
Asheville Re ional Office
I have revised the PCN for the Leicester Youth Center to include and additional 275 feet of stream impact
from grading below the ordinary high water mark. This grading should be minimal, but engineer Jeff
Young feels that it will be necessary to achieve stable side slopes.
Please let me know if you have any questions or comments.
Thank you.
Sin rely,
Gary Hi ins, Dir r
Buncombe SWCD
49 Mount Carmel Road, Suite 101, Asheville NC 28806 buncombecounty.org
p.828.250.4785
C 828.250.6008
C. Proposed Impacts Inventory
pacts Summary
hich sections were completed below for your project (check all that apply):
❑ Pond Construction
La.❑ Wetlands
X Streams —tributaries❑
❑2.Wetland
Buffers
❑ Open Waters
Impacts
on the site, then
complete this
question for each impacted.
area im2e
If there are wetland impacts
proposed
2d.
2e.
2f
2a. 2b.
Wetland impact
2c.
Type of impact
Type of wetland
Forested
Type of jurisdiction
Corps (404,10) or
Area of
impact
number
DWQ (401, other)
(acres)
Permanent (P) or
Tem ora T
Choose one
Yes/No
W1 -
Choose one
Yes/No
W2 _
Choose one
Choose one
W3 _
Choose one
Choose one
Yes/No
W4 _
.Choose one
Choose one
Yes/No
W5 _
Choose one
Choose one
Yes/No
W6 _
Choose one
Choose one
Yes/No
2g. Total Wetland Impacts:
2h. Comments:
3. Stream Impacts
If there are perennial or intermittent stream impacts (including temporary impacts) proposed on the site, then complete this
question for all stream sites impacted. 3e 3f 3g•
3b. 3c. 3d' Impact
3a. a of Average
Stream impact Type of impact Stream name Perennial (PER) jurisdiction stream length
number intermittent (INT) . 1 width (linear
Permanent (P) or (feet) feet)
Temporary (T) Corps 3 20
S1 P Culvert Trib. to Sluder Branch PER
S2 T Excavation Trib. to Sluder Branch
PER Corps 3 275
S3 Choose one
S4 Choose one
S5 Choose one
S6 - Choose one
3h. Total stream and tributary impacts
3i. Comments: along inch
e to
In order to stabilize the stream banks, d with eroding banks in this llarea and bis locateldtlery close to a paved walk ng tra I and street sohsloping e new pback of
the existing pipe. The stream is incise
the stream banks is not feasible. Below this area, the stream banks will be reshaped and sloped back including establishment of vegetation.
Page 4 of 10
PCN Form —Version 1.4 January 2009