NORTH CAROLINA DEPARTMENT OF TRANSPORTATION
FIELD SCOPING MEETING WORKSHEET
TIP No.: N/A
FIELD SCOPING MEETING DATE: May 23, 2024
DIVISION: 11
LOCATION: On-Site
COUNTY: Wilkes
ROUTE (US / NC / SR): SR 2035
PROJECT DESCRIPTION: Replace Bridge #960236 on SR 2035 over branch Elkin River in Wilkes County
FUNCTIONAL CLASSIFICATION: Local
TIER: Sub-Regional Tier
MPO / RPO AREA: Northwest Piedmont RPO
MUNICIPALITY: N/A
ATTENDEES
NAME (PRINT)
PHONE No
E-MAIL
DIVISION CONSTRUCTION ENGINEER
AREA BRIDGE CONSTRUCTION ENGINEER
DIVISION BRIDGE PROGRAM MANAGER
DIVISION UTILITY COORDINATOR
DIVISION ENVIRONMENTAL OFFICER
DIVISION RIGHT OF WAY REPRESENTATIVE
HYDRAULICS REPRESENTATIVE
GEOTECHNICAL REPRESENTATIVE
STRUCTURE DESIGN REPRESENTATIVE
STEWART
STEWART
STEWART
SUNGATE
SUNGATE
VHB
DIVISION (COMPLETED BY DIVISION STAFF AND SENT WITH THE FSM LETTER)
EXISTING FEATURES
FEATURE BRIDGED:
(BRIDGE / CULVERT) LENGTH ’
DECK WIDTH (OUT TO OUT) ’
WATER DEPTH: ’
HEIGHT BED-TO-CROWN: ’
PRIOR SURVEY DATE:
POSTED: SV
TTST:
STRUCTURE TYPE:
SPAN TYPE:
SUFFICIENCY RATING:
POSTED SPEED LIMIT IN PROJECT VICINITY: (MPH / STATUTORY 55MPH)
DETOUR: OFF-SITE
ON-SITE
STAGE CONSTRUCTION
IF DETOUR IS OFF-SITE, PROVIDE DESCRIPTION OF DETOUR ROUTE
APPROXIMATE LENGTH OF DETOUR? (MILES)
IMPROVEMENTS NEEDED TO ROAD ON DETOUR?
IMPROVEMENTS NEEDED TO BRIDGES ON DETOUR?
ARE BRIDGES ON DETOUR CURRENTLY PROGRAMMED ON TIP? COMMENTS:
ARE THERE EMS, SCHOOL , OR BUSINESS ACCESS ISSUES? COMMENTS:
ARE THERE ANY RAILROAD CROSSINGS ON DETOUR? COMMENTS:
SHOULD WORK ZONE PEDESTRIAN ACCESS BE MAINTAINED DURING CONSTRUCTION? REASONS:
IMPACT RATING TO UTILITIES
OVERHEAD UTILITY LINES IN CONFLICT
POWER TRANSMISSION LINES IN CONFLICT
TELEPHONE / CABLE LINES IN CONFLICT
FIBER OPTIC IN CONFLICT
WATER IN CONFLICT
SEWER IN CONFLCIT
NATURAL GAS IN CONFLICT
OTHER IN CONFLICT
BASED ON THE PAST HISTORY NEAR THIS PROJECT SITE, WHAT IS THE ESTIMATED TIME REQUIRED TO COMPLETE UTILITY ADJUSTMENTS MONTHS
IS THERE ANY FUTURE UTILITY CONSTRUCTION ANTICIPATED IN THE PROJECT AREA
IS A FEMA BUY-OUT PROPERTY BEING IMPACTED
HYDRAULICS UNIT (COMPLETED BY HYDRAULICS UNIT STAFF PRIOR TO THE FSM)
WILL THIS PROJECT REQUIRE A FEMA PERMIT?
IS THERE UNUSUAL SCOUR POTENTIAL? IS PROTECTION NEEDED?
ARE BANKS STABLE? IS PROTECTION NEEDED?
DOES STREAM CARRY APPRECIABLE AMOUNT OF LARGE DEBRIS?
WILL THE PLACEMENT OF BENTS IN THE WATER BE ALLOWED COMMENTS
WERE HYDRAULIC ALTERNATIVES BESIDES A BRIDGE CONSIDERED COMMENTS
POSSIBLE SPAN LAYOUT:
GEOTECHNICAL UNIT (COMPLETED BY GEOTECHNICAL UNIT PRIOR TO THE FSM)
EXISTING FOUNDATION REPORTS? IF SO, ATTACH.
KNOWN GEOLOGICAL FEATURES IN AREA WHICH MAY AFFECT DESIGN
ARE PERMITS NEEDED FOR INVESTIGATIVE WORK AT SITE COMMENTS:
ARE THERE ANY HISTORICAL AND / OR VIBRATION SENSITIVE STRUCTURES NEAR BY COMMENTS:
ARE THERE ANY KNOWN LANDFILLS AND / OR GEOENVIRONMENTAL HAZARD SITES AT OR WITHIN CLOSE PROXIMITY TO THE PROJECT SITE COMMENTS:
DEPTH OF WEATHERED ROCK OR ROCK BELOW STREAMBED ( FT. )
ARE ANY IMPACTS ANTCIPATED TO NATURAL SPRINGS OR ARTESIAN WELLS COMMENTS:
POSSIBLE FOUNDATION TYPE: .
PD & EA AND NEU UNIT (COMPLETED BY PDEA STAFF PRIOR TO THE FSM)
TRAFFIC FORECAST (AS PREPARED BY TRANSPORTATION PLANNING BRANCH AND PROVIDED BY PDEA)
Accident History:
-L- BASE YEAR (20 )
ANNUAL AVERAGE DAILY TRAFFIC
% TRUCKS/DUALS
-L- DESIGN YEAR (20 )
ANNUAL AVERAGE DAILY TRAFFIC
% TRUCKS/DUALS
SHOW -Y-LINE TRAFFIC IF APPLICABLE FOR BRIDGES OVER / UNDER.
-Y- BASE YEAR (20 )
ANNUAL AVERAGE DAILY TRAFFIC
% TRUCKS/DUALS
-Y- DESIGN YEAR (20 )
ANNUAL AVERAGE DAILY TRAFFIC
% TRUCKS/DUALS
TRAFFIC SAFETY (AS PREPARED BY THE TRAFFIC SAFETY UNIT AND PROVIDED BY PDEA)
OPERATING SPEED: MPH
CRASH RATE:
WETLANDS AT SITE COMMENTS:
KNOWN ENDANGERED SPECIES POPULATIONS IN AREA COMMENTS:
TROUT OR TVA COUNTY COMMENTS:
CAMA COUNTY PRIMARY NURSERY AREA
MORATORIA IF YES-DURATION
COMMENTS:
IS WATER FEATURE CLASSIFIED AS A WILD AND SCENIC RIVER COMMENTS:
WHAT IS THE WATER QUALITY CLASSIFICATION FOR THIS PROJECT:
WILL A COAST GUARD PERMIT BE REQUIRED COMMENTS:
IS THE PROJECT SITE IN OR NEAR ANY OF THE FOLLOWING:
NATIONAL FOREST
WILDLIFE REFUGE
STATE, COUNTY, OR LOCAL PARK
AIRPORT
A LAKE FOR RECREATION OR POWER GENERATION
WATER SUPPLY RESERVOIR
NUTRIENT SENSITIVE WATERS
PUBLIC USE BOAT RAMP
CEMETARIES
WILL A FEDERAL ENERGY REGULATORY COMMISSION PERMIT BE REQUIRED
IS THE PROJECT AREA KNOWN FOR POTENTIAL INDIAN, COLONIAL, OR OTHER ARCHAEOLOGICAL SITES
KNOWN OR POTENTIAL HISTORIC PROPERTIES IN THE AREA
IS THE BRIDGE STRUCTURE ITSELF, OR ANY PART THEREOF, CONSIDERED HISTORIC
WILL THE PROJECT IMPACT A CHURCH, COMMUNITY CENTER, OR OTHER PUBLIC FACILITY
IS THIS PROJECT ON A STATEWIDE BICYCLE ROUTE OR A LOCAL NON-MARKED BICYCLE ROUTE
ANY CLARIFICATION OR COMMENTS ON ITEMS ABOVE:
ROADWAY DESIGN UNIT (COMPLETED BY ROADWAY DESIGN UNIT PRIOR TO FSM)
ALIGNMENT: EXISTING HORIZONTAL
EXISTING VERTICAL
POSSIBLE DESIGN STANDARDS
POSSIBLE DESIGN SPEED (MPH)
POSSIBLE DESIGN EXCEPTIONS COMMENT
APPROXIMATE PROJECT LENGTH ’
NUMBER AND WIDTH OF LANES
SHOULD THIS PROJECT HAVE CURB AND GUTTER OR SHOULDER APPROACHES COMMENT
TOTAL SHOULDER WIDTH ’
PAVED SHOULDER WIDTH ’
CLEAR ROADWAY ON STRUCTURE
WILL EXISTING DRIVEWAYS, BUSINESS ACCESS, -Y- LINES OR RAMPS NEED TO BE RELOCATED COMMENTS:
IS THERE ADDITIONAL RIGHT OF WAY / PERMANENT EASEMENTS / TEMPORARY EASEMENTS ANTICIPATED FOR CONSTRUCTION COMMENT
ARE ANY RETAINING WALLS ANTICIPATED
IS THERE A POSSIBILITY OF RELOCATEES IF SO, DESCRIBE
ADDITIONAL COMMENTS:
STRUCTURE DESIGN UNIT (COMPLETED BY THE STRUCTURE DESIGN UNIT PRIOR TO THE FSM)
POSSIBLE SUPERSTRUCTURE:
TYPE:
NUMBER OF SPANS
LENGTH OF SPANS
WILL RAILROAD INVOLVEMENT BE REQUIRED
WILL STRUCTURE REQUIRE DESIGN FOR VESSEL IMPACT OR FENDER SYSTEM DESCRIPTION:
ARE ANY RETAINING WALLS ANTICIPATED
CONSTRUCTABILITY AND ACCESS (DISCUSSED AT THE FSM BY DIVISION BRIDGE MANAGER)
METHOD OF ACCESS:
TOP-DOWN
(WORK BRIDGE / CAUSEWAY) PROPOSED LOCATION RELATIVE TO EXISTING STRUCTURE: Work Bridge
PROPOSED LENGTH (FT)
WIDTH (FT)
MATERIAL AND EQUIPMENT ACCESS TO SITE:
TRACTOR-TRAILER ACCESS
BARGE ACCESS
HEAVY EQUIPMENT ACCESS
POSTED ROADS AND POSTED BRIDGES IN VICINITY THAT MAY AFFECT ACCESS
ARE CONSTRUCTION STAGING AREAS AVAILABLE NEAR SITE
ANY ANTICIPATED AREAS OF TEMPORARY SHORING REQUIRED
ADDITIONAL COMMENTS:
ITEMS TO BE DISCUSSED / RESOLVED AT FSM BY ATTENDEES
LIST ALTERNATIVES TO BE STUDIED BY ROADWAY DESIGN:
1)
2)
3)
DESCRIBE ANY DISCUSSION REGARDING HOW THE ALTERNATIVES WERE DECIDED UPON, WHY CERTAIN ALTERANTIVES WERE REJECTED, AND IF AN ALTERNATIVE WAS SELECTED, WHY.
CHECK ONE
TYPE OF ENVIRONMENTAL DOCUMENT (CHECK ONE)
CATEGORICAL EXCLUSION (CE)
MINIMUM CRITERIA DETERMINATION CHECKLIST (MCDC)
THE OPTIMUM LET DATE FOR THIS PROJECT IS:
ADDITIONAL COMMENTS AND/OR UNRESOLVED ISSUES TO BE ADDRESSED: