HomeMy WebLinkAbout20110896 Ver 3_More Info Received_20151215
Strickland, Bev
From:Kim Williams <kwilliams@lmgroup.net>
Sent:Tuesday, December 15, 2015 1:58 PM
To:Policarpo, John N SAW; Coburn, Chad
Cc:Steve Morrison
Subject:RE: SAW-2011-00624 Orton Plantation Holdings LLC - NWP No. 3
Attachments:ER 15-2692.pdf
Hi John
Attached is SHPO’s response regarding the proposed pond outlet at Orton.
Thanks!
Kim
From: Kim Williams
Sent: Friday, December 11, 2015 8:10 AM
To: 'Policarpo, John N SAW' <John.N.Policarpo@usace.army.mil>; 'Coburn, Chad' <chad.coburn@ncdenr.gov>
Cc: Steve Morrison <smorrison@lmgroup.net>
Subject: RE: SAW-2011-00624 Orton Plantation Holdings LLC - NWP No. 3
Hi John
Attached is our response to your comments regarding the NWP application for the Orton Pond Outlet. Let me know if
you have any questions or need additional info.
Chad and John- let me know if you need hard copies of this information and I will mail it to you.
Thanks!
Kim
From: Policarpo, John N SAW \[mailto:John.N.Policarpo@usace.army.mil\]
Sent: Monday, November 30, 2015 11:52 AM
To: Kim Williams <kwilliams@lmgroup.net>; 'Coburn, Chad' <chad.coburn@ncdenr.gov>
Cc: Steve Morrison <smorrison@lmgroup.net>
Subject: RE: SAW-2011-00624 Orton Plantation Holdings LLC - NWP No. 3
Ok Kim, I see what you're talking about. I agree with your assessment, pond on the west side and wetlands to
the east.
In regards to the cubic yards of fill, it is a requirement under the NWP 18 to tell us the volume of fill going into
an area.
Thanks
John
John N Policarpo
US Army Corps of Engineers
1
Wilmington District
910-251-4487
-----Original Message-----
From: Kim Williams \[mailto:kwilliams@lmgroup.net\]
Sent: Monday, November 30, 2015 11:14 AM
To: Policarpo, John N SAW; 'Coburn, Chad'
Cc: Steve Morrison
Subject: \[EXTERNAL\] RE: SAW-2011-00624 Orton Plantation Holdings LLC - NWP No. 3
There is a water control structure on the pond side of the project area, which releases water out of the pipe on
occasion to flood the rice fields located further down gradient. Attached are some pictures of the project area
from June of 2014. During this visit, no water was being released. We don't know how often water is released,
but it is only when the rice fields need additional water. I have also attached the topo, Lidar, and soils map for
the project area. It is not shown as a blue-line on the topo and I don't see a channel feature on the Lidar or soils.
Thanks,
Kim
From: Policarpo, John N SAW \[mailto:John.N.Policarpo@usace.army.mil\]
Sent: Monday, November 30, 2015 10:35 AM
To: Kim Williams <kwilliams@lmgroup.net>; 'Coburn, Chad' <chad.coburn@ncdenr.gov>
Cc: Steve Morrison <smorrison@lmgroup.net>
Subject: RE: SAW-2011-00624 Orton Plantation Holdings LLC - NWP No. 3
Morning Kim,
When I was out there for a site visit, there was a ton of water flowing out of the pipe, so I just assumed it was a
stream channel. Is that typical flow out of that pipe? If not, do you have pictures showing otherwise?
Thanks
John
John N Policarpo
US Army Corps of Engineers
Wilmington District
910-251-4487
-----Original Message-----
2
From: Kim Williams \[mailto:kwilliams@lmgroup.net\]
Sent: Monday, November 30, 2015 8:27 AM
To: Policarpo, John N SAW; 'Coburn, Chad'
Cc: Steve Morrison
Subject: \[EXTERNAL\] RE: SAW-2011-00624 Orton Plantation Holdings LLC - NWP No. 3
Hi John
I hope you had a nice Thanksgiving holiday. I received your comments on Orton and have a couple of questions
for you.
In Comment #1, you request the amount of fill in cubic yards. Would this be just for the Orton Pond side (the
temporary impacts)? LMG considers the other side (with the proposed rip rap) to just be wetlands with no
ordinary high water level.
You mention stream impacts or stream diversion in several of your comments. Do you consider the project area
to be a stream? We considered Orton Pond to be open water and the other side to be wetlands.
Let me know what you think.
Thanks!
Kim
From: Policarpo, John N SAW \[mailto:John.N.Policarpo@usace.army.mil\]
Sent: Friday, November 27, 2015 7:45 AM
To: Kim Williams <kwilliams@lmgroup.net> <mailto:kwilliams@lmgroup.net%3e> ; 'Coburn, Chad'
<chad.coburn@ncdenr.gov> <mailto:chad.coburn@ncdenr.gov%3e>
Subject: SAW-2011-00624 Orton Plantation Holdings LLC - NWP No. 3
Good Morning Kim,
Please find attached a request for additional information for the above referenced project. Please let me know if
you have any questions. The applicants' copy will be directly mailed to him and I'm copying Chad Coburn from
NCDEQ on this email.
Thanks
3
John
John N Policarpo
US Army Corps of Engineers
Wilmington District
910-251-4487
4
North Carolina Department of Natural and Cultural Resources
State Historic Preservation Office
Ramona M. Bartos, Administrator
Governor Pat McCrory
Secretary Susan Kluttz
December 14, 2015
Kim Williams
Land Management Group, Inc.
3805 Wrightsville Avenue, Suite 15
Wilmington, NC 28403
Office of Archives and History
Deputy Secretary Kevin Cherry
kwilliamsglmgroup.net
Re: Orton Pond Outlet Structure Replacement, Off Plantation Road, Belville, Brunswick County,
ER 15-2692
Dear Ms. Williams:
Thank you for your email of November 30, 2015, regarding the above -referenced undertaking. We have
reviewed the materials submitted and offer the following comments.
Infrastructure along Plantation Road needs to be replaced in order to efficiently manage the flow of
irrigation to Orton Plantation's rice fields. Plantation Road is identified as the western boundary in the
nomination for the National Register -listed Orton Plantation (BW0005) and its Boundary Increase
(BW0717). However, as work will predominately occur within a previously maintained DOT right-of-way;
the paved road will be repaired and sloped to its original condition; and disturbed ground will be re -seeded
with a grass mixture to restore it to its pre -work condition, the project will not adversely. a� this historic
property.
The above comments are made pursuant to Section 106 of the National Historic Preservation Act and the
Advisory Council on Historic Preservation's Regulations for Compliance with Section 106 codified at 36
CFR Part 800.
Thank you for your cooperation and consideration. If you have questions concerning the above comment,
contact Renee Gledhill -Earley, environmental review coordinator, at 919-807-6579 or
environmental.review(ancdcr.gov. In all future communication concerning this project, please cite the
above referenced tracking number.
Sincerely,
Ramona M. Bartos
Location: 109 East Jones Street, Raleigh NC 27601 Mailing Address: 4617 Mail Service Center, Raleigh NC 27699-4617 Telephone/Fax: (919) 807-6570/807-6599