HomeMy WebLinkAbout20160035 Ver 1_401 Application_20160116TIMMONS GROUP YOUR VISION ACHIEVED THROUGH OURS. January 4, 2016 Mr. David E. Bailey Ms. Karen Higgins US Army Corps of Engineers NC Dept. of Environment & Natural Resources Raleigh Regulatory Field Office 401 & Buffer Permitting Unit 3331 Heritage Trade Drive, Suite 105 512 N. Salisbury Street Wake Forest, North Carolina 27587 Raleigh, North Carolina 27604 RE: Crosslink Community Church NWP 29 Pre -Construction Notification Application Town of Mebane, Alamance County Dear Mr. Bailey and Ms. Higgins: On behalf of Crosslink Community Church, we are requesting authorization from the USACE to use NWP 29 for 69 linear feet of permanent stream impact and 15 linear feet of temporary stream impact for roadway construction for the proposed community church. We are also requesting a 401 WQC from NCDWR for the above referenced impacts. The site of the proposed Crosslink Community Church is a 16± acre parcel in Alamance County. The project is located on State Road 2126, also known as Old Hillsborough Road (Latitude: 36.055727°N Longitude: -79.28826'W). The project is situated in the Little Haw Creek Watershed, Cape Fear River Basin. McAdams Creek forms the east property border. A small, impounded waterbody lies to the west and connects to McAdams Creek via an intermittent tributary. The Water Quality Classification for McAdams Creek is WS -V; NSW. A request for preliminary Jurisdictional Determination (JD) was submitted to the USACE Raleigh Regulatory Field Office on October 5, 2015 and Mr. David Bailey, USACE, visited the site with Timmons Group staff to confirm the delineation on November 24, 2015. Ms. Sue Homewood, NCDWR, also visited the site on November 24, 2015 to issue a buffer determination. The proposed project impacts consist of 69 linear feet of permanent stream impact and 15 linear feet of temporary stream. The impacts will occur from the installation of a culvert and fill for upgrading a gravel road to a paved road to accommodate congregation traffic. The authorization for buffer impacts were requested though the City of Mebane. There are no proposed wetland impacts. Please refer to attached PCN, supporting materials and plans for details describing the proposed impacts. If you have any questions, please do not hesitate to call me at 919-866-4952 or scott.mitchell(a)timmons.com. Respectfully Submitted, Scott Mitchell NC Environmental Practice Group Leader, PE cc: Sue Homewood, NCDWR RRO, sue. homewood(a)ncdenr.gov Attachments: Pre -Construction Notification (PCN) Agent Authorization USGS Topo Quad Alamance County Soil Survey Impact Map Site Plan N 0 N U Z N 0 a� V) L 0 0 0 L U N C E 0 v 0 M ID ID Ln Ln rn Ln M rn E 0 U 0 C 0 E E o -r Office Use Only: Corps action ID no. DWQ project no. Form Version 1.4 January 2009 Page 1 of 10 PCN Form — Version 1.4 January 2009 Pre -Construction Notification (PCN) Form A. Applicant Information 1. Processing 1 a. Type(s) of approval sought from the Corps: ❑✓ Section 404 Permit ❑ Section 10 Permit 1b. Specify Nationwide Permit (NWP) number: 29 or General Permit (GP) number: 1 c. Has the NWP or GP number been verified by the Corps? ❑ Yes ❑✓ No 1 d. Type(s) of approval sought from the DWQ (check all that apply): ❑✓ 401 Water Quality Certification — Regular ❑ Non -404 Jurisdictional General Permit ❑ 401 Water Quality Certification — Express ❑ Riparian Buffer Authorization 1 e. Is this notification solely for the record because written approval is not required? For the record only for DWQ 401 Certification: ❑ Yes[Z] No For the record only for Corps Permit: ❑ Yes[Z] No 1f. Is payment into a mitigation bank or in -lieu fee program proposed for mitigation of impacts? If so, attach the acceptance letter from mitigation bank or in -lieu fee program. ❑ Yes ❑ No 1 g. Is the project located in any of NC's twenty coastal counties. If yes, answer 1 h below. ❑ Yes[Z] No 1 h. Is the project located within a NC DCM Area of Environmental Concern (AEC)? ❑ Yes✓❑ No 2. Project Information 2a. Name of project: Crosslink Community Church 2b. County: Alamance 2c. Nearest municipality / town: Mebane 2d. Subdivision name: N/A 2e. NCDOT only, T.I.P. or state project no: 3. Owner Information 3a. Name(s) on Recorded Deed: Crosslink Community Church 3b. Deed Book and Page No. Bk 3176 Pg 0554 3c. Responsible Party (for LLC if applicable): Chet Sikes 3d. Street address: 1030 Mebane Oaks Road 3e. City, state, zip: Mebane, NC 27302 3f. Telephone no.: 919-304-0600 3g. Fax no.: 3h. Email address: dreambig@crosslinkcares.org Page 1 of 10 PCN Form — Version 1.4 January 2009 4. Applicant Information (if different from owner) 4a. Applicant is: ❑ Agent ❑ Other, specify: 4b. Name: 4c. Business name (if applicable): 4d. Street address: 4e. City, state, zip: 4f. Telephone no.: 4g. Fax no.: 4h. Email address: 5. Agent/Consultant Information (if applicable) 5a. Name: Scott Mitchell, PE, LSS 5b. Business name (if applicable): Timmons Group, Inc. 5c. Street address: 5410 Trinity Road, Suite 112 5d. City, state, zip: Raleigh, NC 27607 5e. Telephone no.: 919-866-4952 5f. Fax no.: 919-859-5663 5g. Email address: Scott.mitchell@timmons.com Page 2 of 10 B. Project Information and Prior Project History 1. Property Identification 1a. Property identification no. (tax PIN or parcel ID): 9813498204 1 b. Site coordinates (in decimal degrees): Latitude: 35.055727 Longitude: -79.28826 1 c. Property size: 16+/- acres 2. Surface Waters 2a. Name of nearest body of water to proposed project: Little Haw Creek 2b. Water Quality Classification of nearest receiving water: WS -V: NSW 2c. River basin: Cape Fear River Basin 3. Project Description 3a. Describe the existing conditions on the site and the general land use in the vicinity of the project at the time of this application: The land cover is a mix of forest and cultivated fields with an existing gravel road that roughly bisects the property. McAdams Creek flows along the western boundary of the tract and two intermittent tributaries flow east to west into McAdams Creek. One of the tributaries is impounded to form a small pond. There are numerous, small residential subdivisions off of Old Hillsborough Rd in this vicinity as well as a large municipal complex. 3b. List the total estimated acreage of all existing wetlands on the property: 0.009 ac wetland 1.12 ac pond 3c. List the total estimated linear feet of all existing streams (intermittent and perennial) on the property: 2,098 LF 3d. Explain the purpose of the proposed project: The purpose of the project is to build a church for the expanding Crosslink Community Church congregation including utilities infrastructure. 3e. Describe the overall project in detail, including the type of equipment to be used: Equipment typical for road construction, utility installation and grading will be used to construct the proposed project such as track hoes, bulldozers, du 4. Jurisdictional Determinations 4a. Have jurisdictional wetland or stream determinations by the Corps or State been requested or obtained for this property / project (includingall prior phases)in the past? ❑✓ Yes ❑ No ❑ Unknown Comments: Stream Determination 4b. If the Corps made the jurisdictional determination, what type of determination was made? Preliminary ❑ Final 4c. If yes, who delineated the jurisdictional areas? Name (if known): Scott Mitchell, LSS, PE Agency/Consultant Company: Timmons Group Other: David E. Bailey USACE 4d. If yes, list the dates of the Corps jurisdictional determinations or State determinations and attach documentation. Stream/Buffer Determination Letter issued by City of Mebane. Wetlands JD issued by USACE. 5. Project History 5a. Have permits or certifications been requested or obtained for this project (including all prior phases) in the past? ❑Yes ❑✓ No ❑ Unknown 5b. If yes, explain in detail according to "help file" instructions. 6. Future Project Plans 6a. Is this a phased project? ❑ Yes ❑✓ No 6b. If yes, explain. Page 3 of 10 PCN Form — Version 1.4 January 2009 C. Proposed Impacts Inventory 1. Impacts Summary 1 a. Which sections were completed below for your project (check all that apply): ❑ Wetlands ✓❑ Streams —tributaries ❑ Buffers ❑ Open Waters ❑ Pond Construction 2. Wetland Impacts If there are wetland impacts proposed on the site, then complete this question for each wetland area impacted. 2a. Wetland impact number Permanent (P) or Temporary T 2b. Type of impact 2c. Type of wetland 2d. Forested 2e. Type of jurisdiction Corps (404,10) or DWQ (401, other) 2f. Area of impact (acres) W1 Choose one Choose one Yes/No W2 Choose one Choose one Yes/No - W3 Choose one Choose one Yes/No - W4 Choose one Choose one Yes/No - W5 Choose one Choose one Yes/No - W6 Choose one Choose one Yes/No 2g. Total Wetland Impacts: 2h. Comments: No wetland impacts 3. Stream Impacts If there are perennial or intermittent stream impacts (including temporary impacts) proposed on the site, then complete this question for all stream sites impacted. 3a. Stream impact number Permanent (P) or Temporary (T) 3b. Type of impact 3c. Stream name 3d. Perennial (PER) or intermittent (INT)? 3e. Type of jurisdiction 3f. Average stream width (feet) 3g. Impact length (linear feet) S1 P Culvert, fill, riprap outlet pr( UT to McAdams Creek INT Corps 3 69 S2 T Culvert, fill, riprap outlet pr UT to McAdams Creek INT Corps 3 15 S3 Choose one S4 Choose one S5 Choose one S6 Choose one 3h. Total stream and tributary impacts 84 3i. Comments: S1 and S2 are impacts from road construction across the property to the church building and parking lot. Page 4 of 10 PCN Form — Version 1.4 January 2009 4. Open Water Impacts If there are proposed impacts to lakes, ponds, estuaries, tributaries, sounds, the Atlantic Ocean, or any other open water of the U.S. then indivi ually list all open water impacts below. 4a. Open water impact number Permanent (P) or Temporary T 4b. Name of waterbody (if applicable) 4c. Type of impact 4d. Waterbody type 4e. Area of impact (acres) 01 Choose one Choose 02 Choose one Choose 03 Choose one Choose 04 Choose one Choose 4f. Total open water impacts 4g. Comments: 5. Pond or Lake Construction If pond or lake construction proposed, the complete the chart below. 5a. Pond ID number 5b. Proposed use or purpose of pond 5c. Wetland Impacts (acres) 5d. Stream Impacts (feet) 5e. Upland (acres) Flooded Filled Excavated Flooded Filled Excavated P1 Choose one P2 Choose one 5f. Total: 5g. Comments: 5h. Is a dam high hazard permit required? ❑ Yes ❑ No If yes, permit ID no: 5i. Expected pond surface area (acres): 5j. Size of pond watershed (acres): 5k. Method of construction: 6. Buffer Impacts (for DWQ) If project will impact a protected riparian buffer, then complete the chart below. If yes, then individually list all buffer impacts below. If any impacts require miticiation, then vou MUST fill out Section D of this form. 6a. Project is in which protected basin? ❑ Neuse ❑ Tar -Pamlico ❑ Catawba ❑ Randleman ❑✓ Other: Jordan Lake 6b. Buffer Impact number— Permanent (P) or Temporary T 6c. Reason for impact 6d. Stream name 6e. Buffer mitigation required? 6f. Zone 1 impact (square feet) 6g. Zone 2 impact (square feet B1 P No B2 Yes/No B3 Yes/No B4 Yes/No B5 Yes/No B6 Yes/No 6h. Total Buffer Impacts: 6i. Comments: Authorization for Buffer Impacts are being requested through City of Mebane. Page 5 of 10 D. Impact Justification and Mitigation 1. Avoidance and Minimization 1a. Specifically describe measures taken to avoid or minimize the proposed impacts in designing project. Crossing of the stream is proposed at the location of an existing gravel drive crossing in an effort to minimize steam impacts. 1b. Specifically describe measures taken to avoid or minimize the proposed impacts through construction techniques. A pump -around system will be used during a period of low flow to minimize the stream impacts during culvert removal and new culvert installation. 2. Compensatory Mitigation for Impacts to Waters of the U.S. or Waters of the State 2a. Does the project require Compensatory Mitigation for impacts to Waters of the U.S. or Waters of the State? ❑ Yes ❑✓ No 2b. If yes, mitigation is required by (check all that apply): ❑ DWQ ❑ Corps 2c. If yes, which mitigation option will be used for this project? ❑ Mitigation bank El Payment to in -lieu fee program ❑ Permittee Responsible Mitigation 3. Complete if Using a Mitigation Bank 3a. Name of Mitigation Bank: 3b. Credits Purchased (attach receipt and letter) Type: Choose one Type: Choose one Type: Choose one Quantity: Quantity: Quantity: 3c. Comments: 4. Complete if Making a Payment to In -lieu Fee Program 4a. Approval letter from in -lieu fee program is attached. ❑ Yes 4b. Stream mitigation requested: linear feet 4c. If using stream mitigation, stream temperature: Choose one 4d. Buffer mitigation requested (DWQ only): square feet 4e. Riparian wetland mitigation requested: acres 4f. Non -riparian wetland mitigation requested: acres 4g. Coastal (tidal) wetland mitigation requested: acres 4h. Comments: 5. Complete if Using a Permittee Responsible Mitigation Plan 5a. If using a permittee responsible mitigation plan, provide a description of the proposed mitigation plan. Page 6 of 10 PCN Form — Version 1.4 January 2009 6. Buffer Mitigation (State Regulated Riparian Buffer Rules) — required by DWQ 6a. Will the project result in an impact within a protected riparian buffer that requires ❑ Yes ❑✓ No buffer mitigation? 6b. If yes, then identify the square feet of impact to each zone of the riparian buffer that requires mitigation. Calculate the amount of mitigation required. 6c. 6d. 6e. Zone Reason for impact Total impact Multiplier Required mitigation (square feet) (square feet) Zone 1 3 (2 for Catawba) Zone 2 1.5 6f. Total buffer mitigation required: 6g. If buffer mitigation is required, discuss what type of mitigation is proposed (e.g., payment to private mitigation bank, permittee responsible riparian buffer restoration, payment into an approved in -lieu fee fund). 6h. Comments: Page 7 of 10 E. Stormwater Management and Diffuse Flow Plan (required by DWQ) 1. Diffuse Flow Plan 1a. Does the project include or is it adjacent to protected riparian buffers identified ❑✓ Yes ❑ No within one of the NC Riparian Buffer Protection Rules? 1b. If yes, then is a diffuse flow plan included? If no, explain why. ❑✓ Yes ❑ No See attached Diffuse Flow Plan (Sheet No. C2.1) 2. Stormwater Management Plan 2a. What is the overall percent imperviousness of this project? 13 % 2b. Does this project require a Stormwater Management Plan? ❑ Yes ❑✓ No 2c. If this project DOES NOT require a Stormwater Management Plan, explain why: Does not exceed impervious cover threshold. 2d. If this project DOES require a Stormwater Management Plan, then provide a brief, narrative description of the plan: 2e. Who will be responsible for the review of the Stormwater Management Plan? 3. Certified Local Government Stormwater Review 3a. In which localgovernment's jurisdiction is thisproject? ❑ Phase II ❑ NSW 3b. Which of the following locally -implemented stormwater management programs ❑ USMP apply (check all that apply): ❑ Water Supply Watershed ❑ Other: 3c. Has the approved Stormwater Management Plan with proof of approval been El Yes ❑ No attached? 4. DWQ Stormwater Program Review ❑Coastal counties ❑HQW 4a. Which of the following state -implemented stormwater management programs apply ❑ORW (check all that apply): ❑Session Law 2006-246 ❑ Other: 4b. Has the approved Stormwater Management Plan with proof of approval been ❑ Yes ❑ No attached? 5. DWQ 401 Unit Stormwater Review 5a. Does the Stormwater Management Plan meet the appropriate requirements? ❑ Yes ❑ No 5b. Have all of the 401 Unit submittal requirements been met? ❑ Yes ❑ No Page 8 of 10 PCN Form — Version 1.4 January 2009 F. Supplementary Information 1. Environmental Documentation (DWQ Requirement) 1 a. Does the project involve an expenditure of public (federal/state/local) funds or the ❑ Yes[Z] No use of public (federal/state) land? 1 b. If you answered "yes" to the above, does the project require preparation of an environmental document pursuant to the requirements of the National or State ❑ Yes ❑ No (North Carolina) Environmental Policy Act (NEPA/SEPA)? 1 c. If you answered "yes" to the above, has the document review been finalized by the State Clearing House? (If so, attach a copy of the NEPA or SEPA final approval ❑ Yes ❑ No letter.) Comments: 2. Violations (DWQ Requirement) 2a. Is the site in violation of DWQ Wetland Rules (15A NCAC 2H .0500), Isolated Wetland Rules (15A NCAC 2H .1300), DWQ Surface Water or Wetland Standards, ❑Yes ❑✓ No or Riparian Buffer Rules (15A NCAC 2B .0200)? 2b. Is this an after -the -fact permit application? ❑Yes ❑✓ No 2c. If you answered "yes" to one or both of the above questions, provide an explanation of the violation(s): 3. Cumulative Impacts (DWQ Requirement) 3a. Will this project (based on past and reasonably anticipated future impacts) result in El Yes ❑✓ No additional development, which could impact nearby downstream water quality? 3b. If you answered "yes" to the above, submit a qualitative or quantitative cumulative impact analysis in accordance with the most recent DWQ policy. If you answered "no," provide a short narrative description. 4. Sewage Disposal (DWQ Requirement) 4a. Clearly detail the ultimate treatment methods and disposition (non -discharge or discharge) of wastewater generated from the proposed project, or available capacity of the subject facility. Sewage disposal is provided through local sanitary sewer infrastructure. Page 9 of 10 PCN Form — Version 1.4 January 2009 5. Endangered Species and Designated Critical Habitat (Corps Requirement) 5a. Will this project occur in or near an area with federally protected species or ❑ Yes ❑✓ No habitat? 5b. Have you checked with the USFWS concerning Endangered Species Act ❑ Yes ❑✓ No impacts? 5c. If yes, indicate the USFWS Field Office you have contacted.. 5d. What data sources did you use to determine whether your site would impact Endangered Species or Designated Critical Habitat? USFWS database by county www.fws.gov/raleigh/species/cntylist/alamance.htmi 6. Essential Fish Habitat (Corps Requirement) 6a. Will this project occur in or near an area designated as essential fish habitat? ❑ Yes ❑✓ No 6b. What data sources did you use to determine whether your site would impact Essential Fish Habitat? Essential Fish Habitat (EFH) Mapper www.habitat.noaa.gov/protection/efh/ehfmapper 7. Historic or Prehistoric Cultural Resources (Corps Requirement) 7a. Will this project occur in or near an area that the state, federal or tribal governments have designated as having historic or cultural preservation ❑ Yes ❑✓ No status (e.g., National Historic Trust designation or properties significant in North Carolina history and archaeology)? 7b. What data sources did you use to determine whether your site would impact historic or archeological resources? Listed properties on the National Register and NC State Historic Preservation Office Service 8. Flood Zone Designation (Corps Requirement) 8a. Will this project occur in a FEMA-designated 100-year floodplain? ❑ Yes ❑✓ No 8b. If yes, explain how project meets FEMA requirements: 8c. What source(s) did you use to make the floodplain determination? FEMA Map (Special Flood Hazard Area-Floodplain) GIS layer from ConnectGIS (Alamance County GIS) Applicant/Agent's Printed Name Date Applica Agent's Signature (Agent's signature is valid only if an authorization letter from the applicant isprovided.) Page 10 of 10 Strickland, Bev From:Justin Milstein <Justin.Milstein@timmons.com> Sent:Monday, January 11, 2016 3:14 PM To:Higgins, Karen Cc:Montalvo, Sheri A; Strickland, Bev; Scott Mitchell; Adam Aycock Subject:Crosslink Community Church (Alamance County) - PCN Application Attachments:0_Crosslink Community Church Cover Letter.pdf; 1_Crosslink Community Church PCN.pdf; 2_Agent Authorization_Crosslink Community Church.pdf; 3_Crosslink Community Church Soil Survey Maps.pdf; 4_Crosslink Community Church USGS Map.pdf; 6_NCDWR Stream Buffer Letter.pdf; 7_Crosslink Community Church Impact Maps.pdf; 8_Crosslink Community Church Plan Set.pdf Hello Karen, Attached is the PCN application for Crosslink Community Church in Mebane. The hard copies were delivered to your office today. Please let me know if you need any additional information or if you have any questions. Sincerely, Justin Milstein, SSIT Environmental Scientist I Soil Scientist in Training TIMMONS GROUP | www.timmons.com 5410 Trinity Rd, Suite 102 | Raleigh, NC 27607 Office: 919.866.4508 | Fax: 919.859.5663 justin.milstein@timmons.com Your Vision Achieved Through Ours 1 TIMMONS GROUP AGENT AUTHORIZATION and PROPERTY OWNER CERTIFICATION FORM All Blanks to be Filled in by Current Landowner The Department of the Army NCDENR — Division of Water Resources US Army Corps of Engineers 401 & Buffer Permitting Unit Wilmington District 1650 Mail Service Center PO Box 1890 Raleigh, NC 27699-1650 Wilmington, NC 28402-1890 To Whom It May Concern: I, the undersigned, cut -rent property owner designate and authorize representatives of Timmons Group, Inc., to act on my behalf as my agent in the processing of permit applications, to furnish upon request supplemental int rmation in support of applications, etc., from this day forward. This the --day of 20b (numli er) (Month) (Year) I, the undersigned, a duly authorized owner of record of the property/properties identified herein, do authorize representatives of the Wilmington District, U.S. Army Corps of Engineers (Corps) to enter upon the property herein described for the purpose of conducting on-site investigations and issuing a detennination associated with Waters of the U.S. subject to Federal jurisdiction under Section 404 of the Clean Water Act and/or Section 10 of the Rivers and Harbors Act of 1899. This notification supersedes any previous correspondence concerning the agent for this project. Project Name: LlA I< O Location: C) , Property Owner's Name (Pri Property Owner's Signature: Property Owner's Mailing Address: 1030 A.e ;1,.e ba k -s 1?d, 4446 NC- 'Z 7,30z Property Owner's Telephone: -30 fl Fax No, Property Owner's Email Address: CA re 0 N U z ET ru N E 0 U C 0 E E 3 3 s0R�� TIMMONS GROUP YOUR VISION ACHIEVED THROUGH OURS. AGENT AUTHORIZATION and PROPERTY OWNER CERTIFICATION FORM All Blanks to be Filled in bApplicant (When Applicant has property/properties under contract to purchase from duly authorized owner of record) The Department of the Army NCDENR — Division of Water Resources US Army Corps of Engineers 401 & Buffer Permitting Unit Wilmington District 1650 Mail Service Center PO Box 1890 Raleigh, NC 27699-1650 Wilmington, NC 284021890 To Whom It May Concern: I, the applicant, hereby designate and authorize representatives of Timmons Group, Inc., to act on my behalf as my agent in the processing of permit applications, to furnish upon request supplemental information in support of a plications, etc., from this day forward. This the day of Z1, l , 20 — (number) (Month) (Year) I, the undersigned applicant, with written authorization from a duly authorized owner of record of the property/properties identified herein, do authorize representatives of the Wilmington District, U.S. Army Corps of Engineers (Corps) to enter upon the property herein described for the purpose of conducting on- site investigations and issuing a determination associated with Waters of the U.S. subject to Federal jurisdiction under Section 404 of the Clean Water Act and/or Section 10 of the Rivers and. Harbors Act of 1899. This notification supersedes any previous correspondence concerning the agent for this project. Project NameC"!}S Qal(C Co Flyto,c.tL".CI-tuktMLocation: Property Applicant's Name (Print): PgA4T T:a �—.C`C E Property Applicant's Signature: Property Applicant's Mailing Address: 2,-, ff11W20 rtD Ule-qAm, AC 2-7?D Property Applicant's Telephone: T / b 7 -7`7 2-0 Fax No. 'Tt 4 61, 81-6-7 0-7 Property Applicant's Email Address: � /V S C O e LID 1j C' E 0 � CQ M Ln rn Nr E 0 U 0 Z 3 STATE OF NORTH CAROLINA MERANIA DEPARTMENT OF CONSERVATION AND DEVELOPMENT NOR1 7.5 MINUTE Sl RALEIGH, NORTH CAROLINA •.!katr NF' 192X7 um FEET 20' 651 I8r1RLi1y(ili7N NEI c� 17'30" . d 379 q• { I .. 1.'. All n _ t P S I I ael, xw/ cps ; 5 ,3 h y VA } l ' �40 ; °' mr ...{ �.. ' - � N 14+-1 p ��` \ � +� t,! �' i•.�' F , Y' f ff • ll 11\',.".'Leg'} • n'■ _ ��" sem-.; :, .; , - �• • r,. .. �' � tr ' . -.. =•y� • a s as .5 _ • S: r A `I tt� ,��rui I} \ • \l\ - +I 1 �� k ,k - f/�jy{J� � (f S } f •i • 4e �� 4 � ��_i p � ti 1,� ,_„��...�.,<�...G •, .�, z - N t , :1 i �:i3 _ I � - _} r' ..—. _ ,....., ...�I _ . +,`,�: � .. l lww"'r s Water Resources ENVIRONMENTAL QUALITY PAT MCCRORY c;,,, c,,,,,, Se, I "l'11'1' S. JAY ZIMMERMAN D11",!"r January 6, 2016 Timmons Group Mr. Scott Mitchell P5410 Trinity Rd, Suite 112 Raleigh, NC 27607 Subject Property: Crosslink Community Church, 3480 Old Hillsborough Rd, Mebane NC, Alamance County On -Site Determination for Applicability to the Mitigation Rules (15A NCAC 2H .0500) Dear Mr. Mitchell: On November 24, 2015, at your request and in your attendance, Sue Homewood conducted an on-site determination to review features located on the subject project for stream determinations with regards to the above noted state regulations. David Bailey with the US Army Corps of Engineers was also present during the site visit. The Division acknowledges the areas and boundaries identified as jurisdictional wetlands by the USACE. The attached map accurately depicts all stream determinations conducted during the site visit. Please note that at the time of this letter, all intermittent and perennial stream channels and jurisdictional wetlands found on the property are subject to the mitigation rules cited above. These regulations are subject to change in the future. The owner (or future owners) should notify the Division (and other relevant agencies) of this decision in any future correspondences concerning this property. This on-site determination shall expire five (5) years from the date of this letter. 450 W. Hanes Mill Road, Suite 300, Winston-Salem, North Carolina 27105 Phone: 336-776-98001 FAX: 336-776-97971 Customer Service 1-877-623-6748 Internet: www.ncdenr.gov - www.ncwater.org Scott Mitchell January 6, 2016 Landowners or affected parties that dispute a determination made by the Division or Delegated Local Authority that a surface water exists and that it is subject to the buffer rule may request a determination by the Director. A request for a determination by the Director shall be referred to the Director in writing c/o Wetlands and Buffers Permitting and Compliance Unit, 1650 Mail Service Center, Raleigh, NC 27699-1650. Individuals that dispute a determination by the Division or Delegated Local Authority that "exempts" surface water from the buffer rule may ask for an adjudicatory hearing. You must act within 60 days of the date that you receive this letter. Applicants are hereby notified that the 60 -day statutory appeal time does not start until the affected party (including downstream and adjacent landowners) is notified of this decision. The Division recommends that the applicant conduct this notification in order to be certain that third party appeals are made in a timely manner. To ask for a hearing, send a written petition, which conforms to Chapter 150B of the North Carolina General Statutes to the Office of Administrative Hearings, 6714 Mail Service Center, Raleigh, N.C. 27699-6714. This determination is final and binding unless you ask for a hearing within 60 days. This letter only addresses the applicability to the mitigation rules and the buffer rules and does not approve any activity within Waters of the United States or Waters of the State or their associated buffers. If you have any additional questions or require additional information please contact me at 336-776-9693 or sue.homewood@ncdenr.gov. Sincerely, Sue Homewood Winston-Salem Regional Office Enclosures: Timmons Group topo Timmons Group sketch Timmons Group site survey cc: Justin Milstein, Timmons Group (via email) Natalie Landry, Timmons Group (via email) Chet Sikes, Crosslink Community Church (via email) David Bailey, USACE Raleigh Regulatory Field Office (via email) DWR, Winston-Salem Regional Office ),DAdns a1is H -N INV - HD 'dr)H:) A-LINnHHOD >INI-lSSO'dD dnOb) SNOWWI I m gip U IX m ConnectGIS Feature Report Page 1 of 1 c ,�k http:!Ialamancecowity.connectgis.com/DownloadFile.ashx?i= aLs_mapfe429ccaOd68413184dda56c963f43edx.litin&t=print 11/30/2015 MEBANE QUADRANGLE NC 7.5 MINUTE SERIES (TOPOGRAPHIC) 0 STATE OF NORTH CAROLINA DEPARTMENT OF CONSERVATION AND DEVELOPMENT RALEIGH, NORTH CAROLINA y.m m NF 17'30" 'A 20' °51 rQr"'P, 1140 Tcw NE) 653 MESANEI IVOR' 7.5 14INUTE Si --------------- ", f 7J —.. Iortuca fa I mil ✓ 4 �1 - ; — q •WWa7ls1 a h 5 - - Like 1 gyp h r r• J .+ , Y } i' r :d. •4 1"• r .: � ��f{ ,' ? � �'{ w ` i � `� .. awl► - -,h � ,, 'f •, 1 IN ", f 7J —.. Iortuca fa I mil 1 IN d� f \7Z N a 37 s\ o Inv in=582.06' Pump station STREAM BUFFER inv in=572,64--------- (from ssmh A) \\ \ r Bottom=561,72' \\ \. ' Top=583.70' \\\\ Wet well \\ 37 \ �' Hotbox VA ssmh A \\ Rim=583,48' inv out=572.86' inv in=572,96'(plug) Inv out=579,86 o 7 \� HEADWALL STREAM CROSSING CONSTRUCTION SEQUENCE 1. KEEP CLEARING AND EXCAVATION OF THE STREAM BANKS AND BED, AND APPROACH TO A MINIMUM. 2. INSTALL A ROCK DAM UPSTREAM AND DOWNSTREAM. USING CLASS B RIPRAP (D50=13") ON THE FRONT AND #57 STONE ALONG THE BACK TO MAKE THE DAM IMPERMEABLE. 3. HAVE PUMP IN PLACE FOR FLOWING STREAM TO PUMP WATER FROM UPSTREAM DAM PASS THE DOWNSTREAM DAM TO DIVERT FLOW FROM STREAM CROSSING DURING CONSTRUCTION. 4. DURING CONSTRUCTION ON NORMAL FLOW THERE WILL BE SEEPAGE AND A SEDIMENT BAG ON A STONE BED, SHALL BE USED TO PUMP SEEPAGE TO A SEDIMENT BASIN ONLY IF NEEDED DURING CONSTRUCTION. 5. BEGIN CLEARING AND GRUBBING. MAINTAIN PUMP AROUND AS NEEDED. ROUGH GRADE CROSSING. 6. INSTALL FILTER CLOTH AS NECESSARY. 7. INSTALL PIPE CULVERTS AND BACKFILL PROPERLY. 8. INSTALL DISSIPATER PADS AT PIPE OUTLETS. 9. INSTALL PROTECTIVE GROUND COVERS TO PROVIDE PERMANENT EROSION PROTECTION AND IMPROVE VISUAL QUALITY BUT NOT INTERFERE WITH DRIVE LINE OF SIGHT FROM THE ROADWAY. 10. STABILIZE ALL DISTURBED AREAS BEFORE DIVERTING WATER THROUGH STREAM CROSSING. 11. UPON COMPLETION OF CROSSING WITH AREA STABILIZED, THE UPSTREAM AND DOWNSTREAM DAM MAY BE REMOVED. 12. REMOVE PUMP AND SEDIMENT BAG PUMP IF IN USE. 13. ENSURE THAT PERMANENT MEASURED NEEDED TO CONTROL EROSION ARE CONSTRUCTED ACCORDING TO PLAN TO ENSURE ALL EROSION REQUIREMENTS ARE MET. OO °° O 00 O\ ° O O 00°° °o O O k ° k k OUTLET PROTECTION L=16',W=18.' ZONE 2:20' (16'18 AC, E STREAM BUFFER 16.48 ZONE 1 STREAM BUFFER \ ENTERLINE OF McADAMS CR THE PROPERTY /LINE j� ZJ i l5 NCS ZONE 2 20' STREAM BUFFER ZONE 1 ; 30' L4 i STREAM BUFFER / 4s- VERNON S VERN❑N D. CLAPP DB,1529 P,248 PB,22 P,73 PB,61 P.96 PIN:9813494621 LAND USE: SINGLE FAMILY (010) TAX DISTRICT: 45-E ALAMANCE 3 SCALE 1"=40' � o. P �N 0 40' 80' 00Z \ EXISTING CULVERT 30' BUFFFE \ 50' BUFFER EXIST. GRAVEL ROAD A- A - 0 k0 0 0 O .. O- — - — - — - — - — - — - — - — �c7-- Q�- 0 0 n 0 o 0 0 PROPOSED CONDITION SCALE: 1 " =20' PERMANENT ZONE 1 IMPACT: 3,557 SF ZONE 2 IMPACT: 2,175 SF STREAM IMPACT: 69 LF U 0�0 OHO o ACCESS DRIVEWAY TEMPORARY STREAM IMPACT \ CREEK BANK \\ \ EXISTING CULVERT \\ \ TEMPORARY ZONE 1 IMPACT: 1,345 SF ZONE 2 IMPACT: 828 SF STREAM IMPACT: 15 LF 1 \ O 0 V V I N O U O z E o E LU QU � LnN 210 0 LU (D (D N •--� — o Q OU z W O M N O O C11 -z O d N v a CREEK BANK U 3�: LU + X J OW orw -U U) p(7L—r) �z Ln v _ o _ ~ fu H w M � N M � J k.D W EXISTING CONDITION SCALE: 1" =20' EXIST. GRAVEL ROAD E O 0 V V N O U O z E o E LU QU � LnN 210 0 LU (D (D N •--� — o Q OU z W O M N O O C11 -z O d N v a CREEK BANK U EXIST. GRAVEL ROAD E O 0 V V N O U O z E o E LU QU � LnN 210 0 LU (D (D N •--� — o Q OU z W O M N O O C11 -z O d N v a z (n 73 r) O Z U') Mv U 3�: LU + X J OW orw -U U) p(7L—r) �z Ln v _ o _ ~ fu H w M � N M � J k.D W W V) O _ (7 O 0 > W = a U 0 z O (n DATE O9/9/15 } DRAWN BY B. CHAMBERS DESIGNED BY A. CARROLL CHECKED BY A. CARROLL SCALE 1 "=40' �J JOB NO. 36810 SHEET NO. C8.0 3 c PERMANENT ZONE 1 IMPACT: 0 SF ZONE 2 IMPACT: 293 SF TEMPORARY ZONE 1 IMPACT: 0 SF ZONE 2 IMPACT: 7,317 SF STREAM IMPACT: 0 LF m m m m STREAM IMPACT: 0 LF STREAM CROSSING CONSTRUCTION SEQUENCE 1. KEEP CLEARING AND EXCAVATION OF THE STREAM BANKS AND BED, AND APPROACH TO A MINIMUM. 2. INSTALL A ROCK DAM UPSTREAM AND DOWNSTREAM. USING CLASS B RIPRAP (D50=13") ON THE FRONT AND #57 STONE ALONG THE BACK TO MAKE THE DAM IMPERMEABLE. 3. HAVE PUMP IN PLACE FOR FLOWING STREAM TO PUMP WATER FROM UPSTREAM DAM PASS THE DOWNSTREAM DAM TO DIVERT FLOW FROM STREAM CROSSING DURING CONSTRUCTION. 4. DURING CONSTRUCTION ON NORMAL FLOW THERE WILL BE SEEPAGE AND A SEDIMENT BAG ON A STONE BED, SHALL BE USED TO PUMP SEEPAGE TO A SEDIMENT BASIN ONLY IF NEEDED DURING CONSTRUCTION. 5. BEGIN CLEARING AND GRUBBING. MAINTAIN PUMP AROUND AS NEEDED. ROUGH GRADE CROSSING. 6. INSTALL FILTER CLOTH AS NECESSARY. 7. INSTALL PIPE CULVERTS AND BACKFILL PROPERLY. 8. INSTALL DISSIPATER PADS AT PIPE OUTLETS. 9. INSTALL PROTECTIVE GROUND COVERS TO PROVIDE PERMANENT EROSION PROTECTION AND IMPROVE VISUAL QUALITY BUT NOT INTERFERE WITH DRIVE LINE OF SIGHT FROM THE ROADWAY. 10. STABILIZE ALL DISTURBED AREAS BEFORE DIVERTING WATER THROUGH STREAM CROSSING. 11. UPON COMPLETION OF CROSSING WITH AREA STABILIZED, THE UPSTREAM AND DOWNSTREAM DAM MAY BE REMOVED. 12. REMOVE PUMP AND SEDIMENT BAG PUMP IF IN USE. 13. ENSURE THAT PERMANENT MEASURED NEEDED TO CONTROL EROSION ARE CONSTRUCTED ACCORDING TO PLAN TO ENSURE ALL EROSION REQUIREMENTS ARE MET. L- 1001,1 p. 10 TQTq� _ 26,1p �a ------------- F_ ------------ PHASE 2 PARKING �I II II II II PHASE 2 BUILDING II II II II II II II L II II �J L ---- -----------i H❑ELLER INVEST❑RS C❑RP❑RATI❑N DBA72 P,79 PIN;9813588901 74.89 AC, REMAINING (PER DEED) LAND USE: SINGLE FAMILY (010) IISTRICT: 45-E ALAMANCE (16,18 AC, EXCLUDING R/W) 16,42 ACRES —ZONE 2 : 20' STREAM BUFFER ZONE 1 + 30' STREAM BUFFER SCALE 1"=40' 0 40' 80' ZONE 2: PERMANENTIMPACT -- 12- McADAMS CRE L \ EK LARRY G. PARKS AND BILLIE A, PARKS TRUST DB,2733 P,181 TRACT 4 PB,22 P,73 PIN+9813398259 LAND USE: SINGLE FAMILY (010) TAX DISTRICT1 45-E ALAMANCE ZONE 2: PERMANENT IMPACT 4i THOMAS B, & MARY STANCELL DBA29 P,880 LOT 4 PB,59 P,121 PIN19813492013 LAND USE+ VACANT LAND (501) TAX DISTRICT: 45-E ALAMANCE ZONE 2: PERMANENTIMPACT S63'k6'?�, E 1'❑D CORNTR❑L CORNER 4 25'0p' ZONE 2 : 20' STREAM BUFFER ZONE 1 :3 STREAM BUFFER BARRY H, & DIANE T, BURGESS DB,1003 P,185 TRACT 2 PB,22 R73 PIN:9813388737 LAND USE1 SINGLE FAMILY (010) TAX DISTRICT: 45-E ALAMANCE BR❑DIE C, & LYNN H. COVINGT❑` DB,1426 P.364 PIN+9813557432 LAND USE: GENERAL FARM (101) TAX DISTRICT: 45-E ALAMANCE 0 �s HAROLD T, & PATRICIA JONES DB,419 P,344 TRACT 1 PB,22 P,73 PIN19813388570 LAND USE: SINGLE FAMILY (010) TAX DISTRICT: 45-E ALAMANCE E O 0 V V N 0 0 U E w o E Q U N uj �'o� �LLL7N Q 5-3 U N a 0 N N zcros �M � M N W X J0 < waj LL U o (D — z Ln Ln _ o ~ fu N M N M J Lu 0� (A Z 0 I DATE 9/9/15 DRAWN BY B. CHAMBERS DESIGNED BY A. CARROLL CHECKED BY A. CARROLL SCALE 1 "=40' U QC D U a Q a U F --I z Q zJ�- D U ~ a LU O LL OL LL z U m 00 Lu Q Luz F� Jj ( V) (Vr/ V/ 0 0. Io JOB NO. 36810 SHEET NO. C8.1 0 O 0 3 a� 0 Q Q a m 0 ai D Q) 2 0 c m r Q 0 W 0 3 as L 00 0 0 m co �z �0 0� c m 0 � 0 4. 0 =) U C O � 3 Z N 0� � Q x o w Y QY o .3 Q m N x 0 0 O U w 5 �6_ N 0 =0 E -0 =_ U N 0 6ia U O � N .o U 2 �N U� 0 0 @ U Q o U) a) p 0 .a ca r m m` a rn 0 N C 0 a 6 a L_ GROUND STABILIZATION SITE AREA STABILIZATION STABILIZATION DESCRIPTION TIME FRAME TIME EXCEPTIONS • PERIMETER DIKES, BASIN 1 1.24 SWALES, DITCHES, 7 DAYS NONE AND SLOPES 4,748 1,980 • HIGH QUALITY 1.45 1.45 WATER (HQW) 7 DAYS NONE ZONES 2,610 LIMIT OF DISTURBANCE • SLOPES STEEPER IF SLOPES ARE 10' OR LESS IN THAN 3:1 7 DAYS LENGTH AND ARE NOT STEEPER THAN 2:1 14 DAYS ARE ALLOWED • SLOPES 3:1 OR 14 DAYS 7 -DAYS FOR SLOPES GREATER FLATTER REMOVE THAN 50 FEET IN LENGTH • ALL OTHER AREA NONE (EXCEPT FOR PERIMETERS WITH SLOPE 14 DAYS AND HQW ZONES) FLATTER THAN 4:1 1 , - - - - - - - - - - - - \ IN, I PHASE 1 SKIMMER BASIN SUMMARY DIMENSIONS, AREA, & VOLUME OF SKIMMER BASIN ARE AT WEIR ELEVATION * "EXTENSIONS OF TIME MAY BE APPROVED BY THE PERMITTING AUTHORITY BASED ON WEATHER OR OTHER SITE-SPECIFIC CONDITIONS THAT MAKE COMPLIANCE IMPRACTICABLE." (SECTION II. B (2)(b)) / I I / \ \\ \ \ \ \ \ \ \ \ \ \ \ - _ _ _ _ - ' 1p�•�� - - - - - - - - - - - 600 \ / I \ C I EXISTING POND \ \ \ LIMITS OF \ \ \ \\\ DISTURBANCE \ -20NE 1 : 30 -ST REAM BUFFER/ \ -ZONE- 2 20' / l \1 \ t S \ \ \ \ \ s\ - ' / / 595 Z \ � CCESS TO ADJACENT RESIf3fNCE \\ \ \ STREAM BUFFER - MUSTEI\%h�IN OPEN AT ALL TIMES UNTIL RESIDENCE IS VACATED 8" PVC INVERT -590- CD\ ,,J ELS 580.01' _ -� / , // \ \ � _ \ / � � 590 8" PVC INVERT PERMANENT CLEAN -WATER EL: 580.03' 9O % 11 / - - _ - ' / ���I ' \ \ \ 1 t DIVERSION (INST LL EROSION - - - - = 5= _ - / / CONTROL MATTING IMMEDIATELY _ _ v \ \ -- _ \ -------------\T - - - - - -- /i' \ / \ LIMITS OF \ 1 -� / I / _ _ _ - - - - / / \ \ DISTUf26ANCE / I AFTER I NSTALLATIONIJ / / �� \ \ \_ - - _ _ _ _ _ -� _ \ \ \ \ \ 1 `` I -MAINTAIN POSITIVE DRAINAGE i \\ -SILT BASIN - - _ _ _ - - - - - - _ \ \ _ _ _ - _ - 590 _ _ __ _\� _ _ _ _ _ _ _ _ _ 5 \ \ \ \ \ \ \ // / ON CLEAN -WATER DIVERSION 1 _ -- - - - P off\ \ \ TYPE B, - - - - - - - - _ / LIMITS OF - _ - - - - - - - - •rJ - - - _ _ - \ /' ` / \� �� \\ \ \ \ \ \ I ` I I / / r \ / ISTURBANCE - - - - - \ - / / - - - _ - _ \ \ I I -58 - - LIMITS OF \ \ \ INLET `5 _ - - - _ - - - / / , / , ' GJ \ \ i /' / I \ \ \ \ \ DISTURBANCE PROTECTION V E /1 \ I ' I / / \ \ I ry in=582,06' I d\ \ (NP) - - - - - _ - _ - _ \ / 1 •�7f�.17' \ / / \ \ I I / / \ \ \ CHECf� DAM CHECK DAM TEMPORARY - - - - - _ _ _ - / �� ! i \ \ I I I I 1 TMP 1 (TYP) � \\\\\\\ CONSTRUCTION _ 7 TYP p station OORDINATE \18' /RCP INV _ENTRANCE - - - _ _ _ in=572.64' REL CATION OF N \ - _ - - - - - - - EL 579.15' / - OV EXI�ING REMOVE EXISTIN REMI ssrlh A) EXISTING EDESTAL\ 4 - - - - - - - - - --------- /��� \ \ \ \ 1 \ ori=561.72' v 24." B.C� �RAV�L DRIVE \ V v v �`9 ! 1 CHECK DAM W/ OVIDE W=58et .70ell LIMITS OF \ \ \ \ \ 1 - _ - - - - - - - - - J// 4� P INVERT \\ \ \ \ \ \ \ \ \ O \ \ ` , / (TYP). DISTURBANCE SILT FENC8otbo�y � �_ �- - - ' (TYP) 1 \ \ i ��-- --- -------_-- ----- \ \ \ \ \ \ \ \ \ \ \ \\\ \ //` ssmh \� I\STONE -OU-TLET -- STONE \OUTLET Rir=583.4 _TYP) STONE OUTLET (TYP) / _ \ \ \ \ \ \ \ \ \\ \ -- _ � ` / , I -_ -- v out=572, EMO V IS�(TYP) II� STONE OUTLET VMTTS OF \ DIVERSION 572,96'(plug)Inv out=579.861\RCP \ TYP).,- DISTURBANCE ZONE 2 : 20' \ \ / / \ \ \ \ \ \ ` \ \ \ - - - - - - _ _ _ - - / / I \ / / DITCH (TYP) / \ �\ \ I COORDINATE EXISTIITG- \ \\ 1�"-RCP INV STREAM BUFFER - - - - _ WATER METER REMOVAL W/ \ \ \\ \ EL: 579.10' \ \/ \ \ \ \ \ \ \ \ ` - - - _ _ PROVIDER ONCE ADJACENT \ \ ZONE 1 1 30' \ \ \ \ \ \ \ \ _ _ _ _ _ SKIMMER BASIN 1 RESIDENCE IS VACATED - O\ \ \ / \ / _ _ STREAM BUFFER - \ \ \ \ \ \ ` _ - 1 = 1 ` / \ \ / . \ \ \ \\ \ / � \ \ _ \ \� \ \ \ \ ` - PHASE 1 DRAINAGE AREA = 1.24 ac � ' / SILT FENCE STONE OUTLET - _ -585 _ PHASE DISTURBED AREA .10 ac I / SKIMMER BASIN 2 / (TYP) ' (TYP)- _ � � _ _ - _ � ` \ PHASE 1 10 -YR PEAK FLOW = 3.33 cfs i F( / LIMITS OF \ \ \ \lll� \ / / ` ` \ \ \ \ \ \ _ - - _ _ _ - _ - - _ _ _ _ ` ` P ASE 1 DRAINAGE AREA = 1/.45 ac DISTURBANCE _ _ , \\ \ \ \ \ \ _ - _ - - - _ 1 P�ASE 1 DISTURBED AREA = 1.45 ac i \ \ \ _ - - - _ - - - - - - \ \ \ PHASE 1 19 -YR P AK F OW =14.14 / REMOVE EXISTING MAILBOX ONCE ADJACENT r\ \ \\ \ \ - - \ --- 11 / LIMITS OF DISTURBANCE _ LIMITSLOF \ .STC�IE OUTLET \ S8 RESIDENCE IS VACATED \ t S / / DISTI�RBANCt \ \ _ _ _ _ _ _ STXP)- -575 _ HEADWALL �%� \ �� \ ? � \ \ \ \ _ � _� \�/ \ \ _ 80 -ZDNE--2-1 -20= - S WEIR STREAM BUFFER \ \ \ \ - - - -_� 2 S�ZIMMF�R W/\ \ \ - - - - ' - - - - - 1-25" ORIFICE,,,, \ - -___ /� 11 ZTTHE 1 30 \ \ - - - - - / / / / / J, N11 \ \ \ \ \-- /` \ - STREAM BUFFE ♦ \ \ \ \ \ / / / / / / / / --575' ♦♦ \ \\ \` _ / /' / POROUS/' / \ \` \ DIVERSION ' / / / / / / / \ O / / / / -DITCH (TYP) - / / / �� / BAFFLES STONE OUTLET/,POROUS `♦ -\ \ \\ __-___ _- _ ` �'/ /' /' // // (TYP),. (TYP) L BAFFLES/W/ V�,ORIF1jrE­ 5" fSVMMER TYP _ ` /' / / / 1. S (TYP) \ CID -SIFT FENCE- \\(TYP) INVER,S10N %� DITCH (TYPE SICffFENCE / ♦ I/' ` .. \ � (TYP) 2' x 2' ENERGY �� LIMITS OF - _ / / / DEMOLITION NOTES PHASE 1 EROSION CONTROL CONSTRUCTION SEQUENCE �� III / DIssIPATOR�, _ DISTURBANCE - - - _ _ _ _ _-SILZFENCE - _ - / / 5' WEIR \ JJII /// (TYP) _ _ STONE OUTLET \ STONE OUTLET - - - _ _ _ / / (TYP) \ \ \ I DO NOT DISTURB \ � � _ \ � / / 1. REMOVE/ DEMOLISH/ ABANDON AFTER EROSION 1. NOTIFY LOCAL EROSION CONTROL INSPECTOR PRIOR TO ANY LAND DISTURBANCE. LIMITS OF DISTURBANCE = 4.81 ACRES \ // ZONE 1 STREAM �� - - (Typ)- / CONTROL MEASURES ARE IN PLACE AND APPROVAL \ „ BUFFER/�-EEK OF THE CITY INSPECTOR. REFER TO EROSION 2. REMOVE EXISTING 18" DRIVEWAY CULVERT & INSTALL CONSTRUCTION ENTRANCE & CONTROL PLAN. PROPOSED 18" DRIVEWAY CULVERT AS INDICATED ON PLAN. 2. DO NOT INTERRUPT EXISTING UTILITIES SERVING 3. BEGIN INSTALLATION OF SILT FENCE ALONG PERIMETER OF SITE. CLEAR AND GRUB FACILITIES OCCUPIED BY OTHERS AT ANY TIME. ONLY WITHIN SILT FENCE LIMITS. REMOVE STUMPS AS NECESSARY. DISTURB ONLY THE AREAS NECESSARY FOR INSTALLATION DO NOT DISTURB ZONE 1 STREAM BUFFER 3. SAW CUT EXISTING PAVEMENT AT ALL EDGES WHEN ABUTTING NEW PAVEMENT SECTIONS. 4. SUBSURFACE FEATURES ARE SHOWN IN APPROXIMATE LOCATION. 5. VERIFY LOCATIONS AND SIZES OF ALL EXISTING FEATURES PRIOR TO COMMENCEMENT OF CONSTRUCTION. 6. LOCATE EXISTING UTILITIES PRIOR TO CONSTRUCTION AND REPAIR OR REPLACE ANY DAMAGES TO EXISTING UTILITIES RESULTING FROM CONSTRUCTION. 7. REPAIR/REPLACE ANY EXISTING SIDEWALK, CURB AND GUTTER, AND/OR ASPHALT TO REMAIN THAT HAS BEEN DAMAGED BY CONSTRUCTION ACTIVITY. 4. INSTALL TEMPORARY CLEAN -WATER DIVERSION & MAT IMMEDIATELY. 5. CONSTRUCT SKIMMER BASINS AS INDICATED ON PLAN. 6. ONCE THE PERIMETER MEASURES ARE IN PLACE, BEGIN CLEARING AND GRUBBING SITE AND REMOVING EXISTING FEATURES IN ACCORDANCE TO THE DEMOLITION PLAN. 7. PLACE SLOPE MATTING ON ALL SLOPES 3:1 OR GREATER. 8. STABILIZE ALL DISTURBED AREAS WITHIN 14 CALENDAR DAYS OF INACTIVITY. 9. INSPECT AND REPAIR ALL EROSION CONTROL DEVICES ONCE PER WEEK AND AFTER EVERY RAIN EVENT. 10. PROCEED TO PHASE II OF THE EROSION CONTROL SEQUENCE WHEN PHASE I MEASURES HAVE BEEN COMPLETED, INSPECTED, AND APPROVED. DRAIN REA(ACRES) DISTB. AREA(ACRSS) PEAK FL 0W(CFS) BASIN SURFACE AREA(SF) REQUIRED SURFACE AREA(SF) BASIN VOLUME (CF) REQUIRED BASIN VOL LIME (CF) BASIN 1 1.24 1.24 3.33 2,89J 1,082 4,748 1,980 BASIN 2 1.45 1.45 4.14 1,67J 1, 346 2,815 2,610 DIMENSIONS, AREA, & VOLUME OF SKIMMER BASIN ARE AT WEIR ELEVATION * "EXTENSIONS OF TIME MAY BE APPROVED BY THE PERMITTING AUTHORITY BASED ON WEATHER OR OTHER SITE-SPECIFIC CONDITIONS THAT MAKE COMPLIANCE IMPRACTICABLE." (SECTION II. B (2)(b)) / I I / \ \\ \ \ \ \ \ \ \ \ \ \ \ - _ _ _ _ - ' 1p�•�� - - - - - - - - - - - 600 \ / I \ C I EXISTING POND \ \ \ LIMITS OF \ \ \ \\\ DISTURBANCE \ -20NE 1 : 30 -ST REAM BUFFER/ \ -ZONE- 2 20' / l \1 \ t S \ \ \ \ \ s\ - ' / / 595 Z \ � CCESS TO ADJACENT RESIf3fNCE \\ \ \ STREAM BUFFER - MUSTEI\%h�IN OPEN AT ALL TIMES UNTIL RESIDENCE IS VACATED 8" PVC INVERT -590- CD\ ,,J ELS 580.01' _ -� / , // \ \ � _ \ / � � 590 8" PVC INVERT PERMANENT CLEAN -WATER EL: 580.03' 9O % 11 / - - _ - ' / ���I ' \ \ \ 1 t DIVERSION (INST LL EROSION - - - - = 5= _ - / / CONTROL MATTING IMMEDIATELY _ _ v \ \ -- _ \ -------------\T - - - - - -- /i' \ / \ LIMITS OF \ 1 -� / I / _ _ _ - - - - / / \ \ DISTUf26ANCE / I AFTER I NSTALLATIONIJ / / �� \ \ \_ - - _ _ _ _ _ -� _ \ \ \ \ \ 1 `` I -MAINTAIN POSITIVE DRAINAGE i \\ -SILT BASIN - - _ _ _ - - - - - - _ \ \ _ _ _ - _ - 590 _ _ __ _\� _ _ _ _ _ _ _ _ _ 5 \ \ \ \ \ \ \ // / ON CLEAN -WATER DIVERSION 1 _ -- - - - P off\ \ \ TYPE B, - - - - - - - - _ / LIMITS OF - _ - - - - - - - - •rJ - - - _ _ - \ /' ` / \� �� \\ \ \ \ \ \ I ` I I / / r \ / ISTURBANCE - - - - - \ - / / - - - _ - _ \ \ I I -58 - - LIMITS OF \ \ \ INLET `5 _ - - - _ - - - / / , / , ' GJ \ \ i /' / I \ \ \ \ \ DISTURBANCE PROTECTION V E /1 \ I ' I / / \ \ I ry in=582,06' I d\ \ (NP) - - - - - _ - _ - _ \ / 1 •�7f�.17' \ / / \ \ I I / / \ \ \ CHECf� DAM CHECK DAM TEMPORARY - - - - - _ _ _ - / �� ! i \ \ I I I I 1 TMP 1 (TYP) � \\\\\\\ CONSTRUCTION _ 7 TYP p station OORDINATE \18' /RCP INV _ENTRANCE - - - _ _ _ in=572.64' REL CATION OF N \ - _ - - - - - - - EL 579.15' / - OV EXI�ING REMOVE EXISTIN REMI ssrlh A) EXISTING EDESTAL\ 4 - - - - - - - - - --------- /��� \ \ \ \ 1 \ ori=561.72' v 24." B.C� �RAV�L DRIVE \ V v v �`9 ! 1 CHECK DAM W/ OVIDE W=58et .70ell LIMITS OF \ \ \ \ \ 1 - _ - - - - - - - - - J// 4� P INVERT \\ \ \ \ \ \ \ \ \ O \ \ ` , / (TYP). DISTURBANCE SILT FENC8otbo�y � �_ �- - - ' (TYP) 1 \ \ i ��-- --- -------_-- ----- \ \ \ \ \ \ \ \ \ \ \ \\\ \ //` ssmh \� I\STONE -OU-TLET -- STONE \OUTLET Rir=583.4 _TYP) STONE OUTLET (TYP) / _ \ \ \ \ \ \ \ \ \\ \ -- _ � ` / , I -_ -- v out=572, EMO V IS�(TYP) II� STONE OUTLET VMTTS OF \ DIVERSION 572,96'(plug)Inv out=579.861\RCP \ TYP).,- DISTURBANCE ZONE 2 : 20' \ \ / / \ \ \ \ \ \ ` \ \ \ - - - - - - _ _ _ - - / / I \ / / DITCH (TYP) / \ �\ \ I COORDINATE EXISTIITG- \ \\ 1�"-RCP INV STREAM BUFFER - - - - _ WATER METER REMOVAL W/ \ \ \\ \ EL: 579.10' \ \/ \ \ \ \ \ \ \ \ ` - - - _ _ PROVIDER ONCE ADJACENT \ \ ZONE 1 1 30' \ \ \ \ \ \ \ \ _ _ _ _ _ SKIMMER BASIN 1 RESIDENCE IS VACATED - O\ \ \ / \ / _ _ STREAM BUFFER - \ \ \ \ \ \ ` _ - 1 = 1 ` / \ \ / . \ \ \ \\ \ / � \ \ _ \ \� \ \ \ \ ` - PHASE 1 DRAINAGE AREA = 1.24 ac � ' / SILT FENCE STONE OUTLET - _ -585 _ PHASE DISTURBED AREA .10 ac I / SKIMMER BASIN 2 / (TYP) ' (TYP)- _ � � _ _ - _ � ` \ PHASE 1 10 -YR PEAK FLOW = 3.33 cfs i F( / LIMITS OF \ \ \ \lll� \ / / ` ` \ \ \ \ \ \ _ - - _ _ _ - _ - - _ _ _ _ ` ` P ASE 1 DRAINAGE AREA = 1/.45 ac DISTURBANCE _ _ , \\ \ \ \ \ \ _ - _ - - - _ 1 P�ASE 1 DISTURBED AREA = 1.45 ac i \ \ \ _ - - - _ - - - - - - \ \ \ PHASE 1 19 -YR P AK F OW =14.14 / REMOVE EXISTING MAILBOX ONCE ADJACENT r\ \ \\ \ \ - - \ --- 11 / LIMITS OF DISTURBANCE _ LIMITSLOF \ .STC�IE OUTLET \ S8 RESIDENCE IS VACATED \ t S / / DISTI�RBANCt \ \ _ _ _ _ _ _ STXP)- -575 _ HEADWALL �%� \ �� \ ? � \ \ \ \ _ � _� \�/ \ \ _ 80 -ZDNE--2-1 -20= - S WEIR STREAM BUFFER \ \ \ \ - - - -_� 2 S�ZIMMF�R W/\ \ \ - - - - ' - - - - - 1-25" ORIFICE,,,, \ - -___ /� 11 ZTTHE 1 30 \ \ - - - - - / / / / / J, N11 \ \ \ \ \-- /` \ - STREAM BUFFE ♦ \ \ \ \ \ / / / / / / / / --575' ♦♦ \ \\ \` _ / /' / POROUS/' / \ \` \ DIVERSION ' / / / / / / / \ O / / / / -DITCH (TYP) - / / / �� / BAFFLES STONE OUTLET/,POROUS `♦ -\ \ \\ __-___ _- _ ` �'/ /' /' // // (TYP),. (TYP) L BAFFLES/W/ V�,ORIF1jrE­ 5" fSVMMER TYP _ ` /' / / / 1. S (TYP) \ CID -SIFT FENCE- \\(TYP) INVER,S10N %� DITCH (TYPE SICffFENCE / ♦ I/' ` .. \ � (TYP) 2' x 2' ENERGY �� LIMITS OF - _ / / / DEMOLITION NOTES PHASE 1 EROSION CONTROL CONSTRUCTION SEQUENCE �� III / DIssIPATOR�, _ DISTURBANCE - - - _ _ _ _ _-SILZFENCE - _ - / / 5' WEIR \ JJII /// (TYP) _ _ STONE OUTLET \ STONE OUTLET - - - _ _ _ / / (TYP) \ \ \ I DO NOT DISTURB \ � � _ \ � / / 1. REMOVE/ DEMOLISH/ ABANDON AFTER EROSION 1. NOTIFY LOCAL EROSION CONTROL INSPECTOR PRIOR TO ANY LAND DISTURBANCE. LIMITS OF DISTURBANCE = 4.81 ACRES \ // ZONE 1 STREAM �� - - (Typ)- / CONTROL MEASURES ARE IN PLACE AND APPROVAL \ „ BUFFER/�-EEK OF THE CITY INSPECTOR. REFER TO EROSION 2. REMOVE EXISTING 18" DRIVEWAY CULVERT & INSTALL CONSTRUCTION ENTRANCE & CONTROL PLAN. PROPOSED 18" DRIVEWAY CULVERT AS INDICATED ON PLAN. 2. DO NOT INTERRUPT EXISTING UTILITIES SERVING 3. BEGIN INSTALLATION OF SILT FENCE ALONG PERIMETER OF SITE. CLEAR AND GRUB FACILITIES OCCUPIED BY OTHERS AT ANY TIME. ONLY WITHIN SILT FENCE LIMITS. REMOVE STUMPS AS NECESSARY. DISTURB ONLY THE AREAS NECESSARY FOR INSTALLATION DO NOT DISTURB ZONE 1 STREAM BUFFER 3. SAW CUT EXISTING PAVEMENT AT ALL EDGES WHEN ABUTTING NEW PAVEMENT SECTIONS. 4. SUBSURFACE FEATURES ARE SHOWN IN APPROXIMATE LOCATION. 5. VERIFY LOCATIONS AND SIZES OF ALL EXISTING FEATURES PRIOR TO COMMENCEMENT OF CONSTRUCTION. 6. LOCATE EXISTING UTILITIES PRIOR TO CONSTRUCTION AND REPAIR OR REPLACE ANY DAMAGES TO EXISTING UTILITIES RESULTING FROM CONSTRUCTION. 7. REPAIR/REPLACE ANY EXISTING SIDEWALK, CURB AND GUTTER, AND/OR ASPHALT TO REMAIN THAT HAS BEEN DAMAGED BY CONSTRUCTION ACTIVITY. 4. INSTALL TEMPORARY CLEAN -WATER DIVERSION & MAT IMMEDIATELY. 5. CONSTRUCT SKIMMER BASINS AS INDICATED ON PLAN. 6. ONCE THE PERIMETER MEASURES ARE IN PLACE, BEGIN CLEARING AND GRUBBING SITE AND REMOVING EXISTING FEATURES IN ACCORDANCE TO THE DEMOLITION PLAN. 7. PLACE SLOPE MATTING ON ALL SLOPES 3:1 OR GREATER. 8. STABILIZE ALL DISTURBED AREAS WITHIN 14 CALENDAR DAYS OF INACTIVITY. 9. INSPECT AND REPAIR ALL EROSION CONTROL DEVICES ONCE PER WEEK AND AFTER EVERY RAIN EVENT. 10. PROCEED TO PHASE II OF THE EROSION CONTROL SEQUENCE WHEN PHASE I MEASURES HAVE BEEN COMPLETED, INSPECTED, AND APPROVED. SPILL WA Y LENGTH (FT) SKIMMER ORIFICE DIAMETER (IN.) SKIMMER SIZE (IN.) TOP OF BERM ELEV. WEIR ELEV. BOTTOM OF BASIN ELEV. BASIN 1 8 1.25 2 577.00 576.00 574.00 BASIN 2 5 1.00 1.50 573.00 572.00 569.75 DIMENSIONS, AREA, & VOLUME OF SKIMMER BASIN ARE AT WEIR ELEVATION * "EXTENSIONS OF TIME MAY BE APPROVED BY THE PERMITTING AUTHORITY BASED ON WEATHER OR OTHER SITE-SPECIFIC CONDITIONS THAT MAKE COMPLIANCE IMPRACTICABLE." (SECTION II. B (2)(b)) / I I / \ \\ \ \ \ \ \ \ \ \ \ \ \ - _ _ _ _ - ' 1p�•�� - - - - - - - - - - - 600 \ / I \ C I EXISTING POND \ \ \ LIMITS OF \ \ \ \\\ DISTURBANCE \ -20NE 1 : 30 -ST REAM BUFFER/ \ -ZONE- 2 20' / l \1 \ t S \ \ \ \ \ s\ - ' / / 595 Z \ � CCESS TO ADJACENT RESIf3fNCE \\ \ \ STREAM BUFFER - MUSTEI\%h�IN OPEN AT ALL TIMES UNTIL RESIDENCE IS VACATED 8" PVC INVERT -590- CD\ ,,J ELS 580.01' _ -� / , // \ \ � _ \ / � � 590 8" PVC INVERT PERMANENT CLEAN -WATER EL: 580.03' 9O % 11 / - - _ - ' / ���I ' \ \ \ 1 t DIVERSION (INST LL EROSION - - - - = 5= _ - / / CONTROL MATTING IMMEDIATELY _ _ v \ \ -- _ \ -------------\T - - - - - -- /i' \ / \ LIMITS OF \ 1 -� / I / _ _ _ - - - - / / \ \ DISTUf26ANCE / I AFTER I NSTALLATIONIJ / / �� \ \ \_ - - _ _ _ _ _ -� _ \ \ \ \ \ 1 `` I -MAINTAIN POSITIVE DRAINAGE i \\ -SILT BASIN - - _ _ _ - - - - - - _ \ \ _ _ _ - _ - 590 _ _ __ _\� _ _ _ _ _ _ _ _ _ 5 \ \ \ \ \ \ \ // / ON CLEAN -WATER DIVERSION 1 _ -- - - - P off\ \ \ TYPE B, - - - - - - - - _ / LIMITS OF - _ - - - - - - - - •rJ - - - _ _ - \ /' ` / \� �� \\ \ \ \ \ \ I ` I I / / r \ / ISTURBANCE - - - - - \ - / / - - - _ - _ \ \ I I -58 - - LIMITS OF \ \ \ INLET `5 _ - - - _ - - - / / , / , ' GJ \ \ i /' / I \ \ \ \ \ DISTURBANCE PROTECTION V E /1 \ I ' I / / \ \ I ry in=582,06' I d\ \ (NP) - - - - - _ - _ - _ \ / 1 •�7f�.17' \ / / \ \ I I / / \ \ \ CHECf� DAM CHECK DAM TEMPORARY - - - - - _ _ _ - / �� ! i \ \ I I I I 1 TMP 1 (TYP) � \\\\\\\ CONSTRUCTION _ 7 TYP p station OORDINATE \18' /RCP INV _ENTRANCE - - - _ _ _ in=572.64' REL CATION OF N \ - _ - - - - - - - EL 579.15' / - OV EXI�ING REMOVE EXISTIN REMI ssrlh A) EXISTING EDESTAL\ 4 - - - - - - - - - --------- /��� \ \ \ \ 1 \ ori=561.72' v 24." B.C� �RAV�L DRIVE \ V v v �`9 ! 1 CHECK DAM W/ OVIDE W=58et .70ell LIMITS OF \ \ \ \ \ 1 - _ - - - - - - - - - J// 4� P INVERT \\ \ \ \ \ \ \ \ \ O \ \ ` , / (TYP). DISTURBANCE SILT FENC8otbo�y � �_ �- - - ' (TYP) 1 \ \ i ��-- --- -------_-- ----- \ \ \ \ \ \ \ \ \ \ \ \\\ \ //` ssmh \� I\STONE -OU-TLET -- STONE \OUTLET Rir=583.4 _TYP) STONE OUTLET (TYP) / _ \ \ \ \ \ \ \ \ \\ \ -- _ � ` / , I -_ -- v out=572, EMO V IS�(TYP) II� STONE OUTLET VMTTS OF \ DIVERSION 572,96'(plug)Inv out=579.861\RCP \ TYP).,- DISTURBANCE ZONE 2 : 20' \ \ / / \ \ \ \ \ \ ` \ \ \ - - - - - - _ _ _ - - / / I \ / / DITCH (TYP) / \ �\ \ I COORDINATE EXISTIITG- \ \\ 1�"-RCP INV STREAM BUFFER - - - - _ WATER METER REMOVAL W/ \ \ \\ \ EL: 579.10' \ \/ \ \ \ \ \ \ \ \ ` - - - _ _ PROVIDER ONCE ADJACENT \ \ ZONE 1 1 30' \ \ \ \ \ \ \ \ _ _ _ _ _ SKIMMER BASIN 1 RESIDENCE IS VACATED - O\ \ \ / \ / _ _ STREAM BUFFER - \ \ \ \ \ \ ` _ - 1 = 1 ` / \ \ / . \ \ \ \\ \ / � \ \ _ \ \� \ \ \ \ ` - PHASE 1 DRAINAGE AREA = 1.24 ac � ' / SILT FENCE STONE OUTLET - _ -585 _ PHASE DISTURBED AREA .10 ac I / SKIMMER BASIN 2 / (TYP) ' (TYP)- _ � � _ _ - _ � ` \ PHASE 1 10 -YR PEAK FLOW = 3.33 cfs i F( / LIMITS OF \ \ \ \lll� \ / / ` ` \ \ \ \ \ \ _ - - _ _ _ - _ - - _ _ _ _ ` ` P ASE 1 DRAINAGE AREA = 1/.45 ac DISTURBANCE _ _ , \\ \ \ \ \ \ _ - _ - - - _ 1 P�ASE 1 DISTURBED AREA = 1.45 ac i \ \ \ _ - - - _ - - - - - - \ \ \ PHASE 1 19 -YR P AK F OW =14.14 / REMOVE EXISTING MAILBOX ONCE ADJACENT r\ \ \\ \ \ - - \ --- 11 / LIMITS OF DISTURBANCE _ LIMITSLOF \ .STC�IE OUTLET \ S8 RESIDENCE IS VACATED \ t S / / DISTI�RBANCt \ \ _ _ _ _ _ _ STXP)- -575 _ HEADWALL �%� \ �� \ ? � \ \ \ \ _ � _� \�/ \ \ _ 80 -ZDNE--2-1 -20= - S WEIR STREAM BUFFER \ \ \ \ - - - -_� 2 S�ZIMMF�R W/\ \ \ - - - - ' - - - - - 1-25" ORIFICE,,,, \ - -___ /� 11 ZTTHE 1 30 \ \ - - - - - / / / / / J, N11 \ \ \ \ \-- /` \ - STREAM BUFFE ♦ \ \ \ \ \ / / / / / / / / --575' ♦♦ \ \\ \` _ / /' / POROUS/' / \ \` \ DIVERSION ' / / / / / / / \ O / / / / -DITCH (TYP) - / / / �� / BAFFLES STONE OUTLET/,POROUS `♦ -\ \ \\ __-___ _- _ ` �'/ /' /' // // (TYP),. (TYP) L BAFFLES/W/ V�,ORIF1jrE­ 5" fSVMMER TYP _ ` /' / / / 1. S (TYP) \ CID -SIFT FENCE- \\(TYP) INVER,S10N %� DITCH (TYPE SICffFENCE / ♦ I/' ` .. \ � (TYP) 2' x 2' ENERGY �� LIMITS OF - _ / / / DEMOLITION NOTES PHASE 1 EROSION CONTROL CONSTRUCTION SEQUENCE �� III / DIssIPATOR�, _ DISTURBANCE - - - _ _ _ _ _-SILZFENCE - _ - / / 5' WEIR \ JJII /// (TYP) _ _ STONE OUTLET \ STONE OUTLET - - - _ _ _ / / (TYP) \ \ \ I DO NOT DISTURB \ � � _ \ � / / 1. REMOVE/ DEMOLISH/ ABANDON AFTER EROSION 1. NOTIFY LOCAL EROSION CONTROL INSPECTOR PRIOR TO ANY LAND DISTURBANCE. LIMITS OF DISTURBANCE = 4.81 ACRES \ // ZONE 1 STREAM �� - - (Typ)- / CONTROL MEASURES ARE IN PLACE AND APPROVAL \ „ BUFFER/�-EEK OF THE CITY INSPECTOR. REFER TO EROSION 2. REMOVE EXISTING 18" DRIVEWAY CULVERT & INSTALL CONSTRUCTION ENTRANCE & CONTROL PLAN. PROPOSED 18" DRIVEWAY CULVERT AS INDICATED ON PLAN. 2. DO NOT INTERRUPT EXISTING UTILITIES SERVING 3. BEGIN INSTALLATION OF SILT FENCE ALONG PERIMETER OF SITE. CLEAR AND GRUB FACILITIES OCCUPIED BY OTHERS AT ANY TIME. ONLY WITHIN SILT FENCE LIMITS. REMOVE STUMPS AS NECESSARY. DISTURB ONLY THE AREAS NECESSARY FOR INSTALLATION DO NOT DISTURB ZONE 1 STREAM BUFFER 3. SAW CUT EXISTING PAVEMENT AT ALL EDGES WHEN ABUTTING NEW PAVEMENT SECTIONS. 4. SUBSURFACE FEATURES ARE SHOWN IN APPROXIMATE LOCATION. 5. VERIFY LOCATIONS AND SIZES OF ALL EXISTING FEATURES PRIOR TO COMMENCEMENT OF CONSTRUCTION. 6. LOCATE EXISTING UTILITIES PRIOR TO CONSTRUCTION AND REPAIR OR REPLACE ANY DAMAGES TO EXISTING UTILITIES RESULTING FROM CONSTRUCTION. 7. REPAIR/REPLACE ANY EXISTING SIDEWALK, CURB AND GUTTER, AND/OR ASPHALT TO REMAIN THAT HAS BEEN DAMAGED BY CONSTRUCTION ACTIVITY. 4. INSTALL TEMPORARY CLEAN -WATER DIVERSION & MAT IMMEDIATELY. 5. CONSTRUCT SKIMMER BASINS AS INDICATED ON PLAN. 6. ONCE THE PERIMETER MEASURES ARE IN PLACE, BEGIN CLEARING AND GRUBBING SITE AND REMOVING EXISTING FEATURES IN ACCORDANCE TO THE DEMOLITION PLAN. 7. PLACE SLOPE MATTING ON ALL SLOPES 3:1 OR GREATER. 8. STABILIZE ALL DISTURBED AREAS WITHIN 14 CALENDAR DAYS OF INACTIVITY. 9. INSPECT AND REPAIR ALL EROSION CONTROL DEVICES ONCE PER WEEK AND AFTER EVERY RAIN EVENT. 10. PROCEED TO PHASE II OF THE EROSION CONTROL SEQUENCE WHEN PHASE I MEASURES HAVE BEEN COMPLETED, INSPECTED, AND APPROVED. - - - - - - - -ENERGY VSSIPATOR DO NOT DISTURB KIM _ AtJ SCALE 1"=40' NOR 0 40' 80' 1STREAM - ZO BUFFER \ o \\��111111111// �N CAR 0 SEAL = 38573 _ Vis' 1/11111 w 0 \\\ E N C 0 zE Lu w o +, H Lu � � au°' �� � o �.o Luu-(7N-1 ¢<O-oU L.0 O M N o �W-l�z a O (7 m �-' M In ZU) �M -ZU W a X - Q J LL U o O U) Y o N �6 M N M ko J 00 W H vi M O 0 Z) O 2 F- 0 Lu Lu_ m U Q z O M O Z O W W U 00 Lf) Lu Lu LU z z Q Q z m m O w w H LL LL 00 Lcu U U DATE 9/9/15 DRAWN BY B. CHAMBERS DESIGNED BY A. CARROLL CHECKED BY A. CARROLL SCALE 1 "=40' = z U Q T O i U z O U �--I z z zJ0 Q O LU 0 rl z Oww z (n Uwa z 06 � z O V 1 ~ J O O W U 0 JOB NO. 36810 SHEET NO. C2.0 3 ami a m0 Q0� o 2Z Wo � 2 02 T m 5 - 0 ,_ M N d o zN 0 2 a x a� o L = 0 0 Qw 2'§ > E .- Y N m �N ro o N U :F3E ;v N (6 = Y o E o -� �0 U o N N - 5 70 i U) N o U -° o Q� � m �E LEGEND TEMPORARY CONSTRUCTION �o- POROUS BAFFLE ENTRANCE EROSION CONTROL MATTING STONE OUTLET SILT FENCE ® INLET PROTECTION TEMPORARY DIVERSION ® PIPE INLET PROTECTION LIMIT OF DISTURBANCE CHECK DAM SKIMMER BASIN DRAINAGE AREA -E3'r SILT BASIN "TYPE B" REMOVE - - - - - - - -ENERGY VSSIPATOR DO NOT DISTURB KIM _ AtJ SCALE 1"=40' NOR 0 40' 80' 1STREAM - ZO BUFFER \ o \\��111111111// �N CAR 0 SEAL = 38573 _ Vis' 1/11111 w 0 \\\ E N C 0 zE Lu w o +, H Lu � � au°' �� � o �.o Luu-(7N-1 ¢<O-oU L.0 O M N o �W-l�z a O (7 m �-' M In ZU) �M -ZU W a X - Q J LL U o O U) Y o N �6 M N M ko J 00 W H vi M O 0 Z) O 2 F- 0 Lu Lu_ m U Q z O M O Z O W W U 00 Lf) Lu Lu LU z z Q Q z m m O w w H LL LL 00 Lcu U U DATE 9/9/15 DRAWN BY B. CHAMBERS DESIGNED BY A. CARROLL CHECKED BY A. CARROLL SCALE 1 "=40' = z U Q T O i U z O U �--I z z zJ0 Q O LU 0 rl z Oww z (n Uwa z 06 � z O V 1 ~ J O O W U 0 JOB NO. 36810 SHEET NO. C2.0 3 ami a m0 Q0� o 2Z Wo � 2 02 T m 5 - 0 ,_ M N d o zN 0 2 a x a� o L = 0 0 Qw 2'§ > E .- Y N m �N ro o N U :F3E ;v N (6 = Y o E o -� �0 U o N N - 5 70 i U) N o U -° o Q� � m �E IPF - IRON PIPE FOUND IRF - IRON ROD FOUND IPS - IRON PIPE SET PT - CALCULATED POINT CM - CONCRETE MONUMENT FIRE HYDRANT 0 ELECTRIC BOX 0 TELEPHONE PEDESTAL © CABLE TV PEDESTAL POWER POLE < GUY O-* LIGHT POLE I YARD LIGHT LEGEND Q BOLLARD SIGN DEED LINE �D MH DRAINAGE pJ SPRINKLER HEAD - - - - LINE NOT SURVEYED �$ MHSAN/TARY ® SPRINKLER VALVE ------------------------STORM LINE © MH ELECTRIC ® GAS METER - - SAN- - SANITARY LINE OT MH TELEPHONE 4 GAS VALVE X X FENCE MH WATER P OHP OVERHEAD POWER LINE o FLAG POLE G PAINTED GAS LINE ® SPRINKLER BOX GROUND LAMP UGP PAINTED POWER LINE Q ELECTRIC METER STM - - - PAINTED STORM LINE Q❑ CLEAN OUT OW WELL - - UGT- - PAINTED TELEPHONE LINE WATER METER CF MAILBOX gni PAINTED WATERLINE ® WATER VALVE EDGE OF UNDERBRUSH O ROOF DRAIN BRICK CONCRETE ZONE 2 1 20' I I STREAM A STREAM BUFFER (INTERMITTENT) ZONE 1 ; 30' STREAM BUFFER WETLAND A \/ N r J \ p\ \ / / I 1 \\\ \ \ \ \ \ \ \ PQND \A\ 1001.10, / - - 1600' �/ / I I I I \ \ \ \ \ \ \ \ \ \ \ \ \ rpTAL, 4 . � _ _ - - - - - - - - - - \ \ \ \ \ \ \ \ \ \ - _ _ 1p26,10 ��`6�� - HOELLER INVESTORS CORPORATION DB,472 P.79 I _ _ PIN:9813588901 74.89 AC, REMAINING I to (PER DEED) 0% I I I I \ \ \ \ \ ` LAND USE: SINGLE FAMILY (010) I I I I \�.fl� \ \ \ \ \ \ \ \ \ \ \ apo \ / 600 / ' _ _ TAX DISTRICT: 45-E ALAMANCE I I \\ \ \ / / / - - / / I I I I I 563°676.10' E _ PROD / EXISTING POND CONTRO \\ 1 I I I I \ \ \ \ �� - - ' f/ _ - _ _ _ _ - - - - / - _ / , , j 595 I II I I I I I I CORNE� BRODIE C. PIN:981355743OVINGTON DB .1426 P,364 \ \ \ \\ \� 595® t / / I I I \ \ \ \ \ \ \ \ I I I _ - ' - / ' ' / \ \ \ ' _ / / / / / / I I • I �5100j \ \ \ \ LAND USE, GENERAL FARM (101) TAX DISTRICT: 45-E ALAMANCE go ZONE 11 30' \ \ \\ \ \ \ \\ - _ - - "STREAM BUFFER, 159 STREAM BUFFER \\ ✓ s 1 / 1 \ / h / / In l ) - STREAM D •590 _ \ / 1S\ P T r� EL: 580.01' _ _ , ? / / / \ \_ J \ \ / / I I / \ / / /l / / / /1 1 I I I/ I / / I I (INTERMITTENT) _ ice' / \ _ / \ y \ / / if EL 580,03' _ =� ' �/ / - _ _ _ _ / ' ` J� \ \ \ _ / I 1 1 / I _-_5 TRE�4M BUFFER/ \06 585 / - _-g0 _`%/ I \ \ /I( I____ Inv In=58I } \ _ - - - - - - -585 - - / '- f / 576.17, ' - - ST EA BUFFER Pump station \ -' %J \ \ \ - \ / inv in=572,64, / \\ N \ \ 18' RCP INV - _ _ - - - EL: 579,15', CfrorossMhA) j \\\ � \ \ �-------- ------- Bottom561,72' \\ \ \ _ _ / _ s if \ \ _ _�80- - �_------- 4' P INV RT Top=583.70' \\ \ \ \ \ / ' Wet well \ _ _ - Hotbox- \ \ _ - - \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ - - - - , h�0 / I 1 I �h qk�mh✓ \\\ \\ /-- \ \ \ \ \ \ \ �� \ \ \ -/ RiM=583,45'-__ �/ \ Inv out=572,86' \ S. _ _ - / - - \ \ \ d) \ \ \ \ \ \ \ - 59 / / / I j / / / , ;565` Inv Ii 0 Inv out=579.8 \ \� \ ONE 2 : 20' / \\ STR M B' \ \ T. STREAM BUFFER \ \ \ C16, 8 ACS EXCLUDING R/W3 8' RCP INV / \v / (INTE MITTEN I) \ \ \ \ \ \ 16 4� AC!?EC _ \ / ' / / I I \ \ / / / / / / ' / , / / / / / / / / / T \ \ \ \\ \ EL, 579.10' \ \ \ \ \ \ / / / / / , / / ONE 1 30' �\ ` \ \ \ \ \ \ \ - - - - - - - - _ _ - / _ \ \ / \ / / / / / / _ \� STREAM BUFFER _ \ \ \ \ \ \ \ ` - - _ \ - _ _ ' / / / / / - - - / 585 ` - _ / 1 / / / / / / / / / / / � = 6� " NTERLINE OF McADAMS CREEK -LS -THE PROPERTY HAROLD T. & PATRICIA JONES HEADWALL _.,IIA SCALE 1"=50' NOR 0 50' 100' L_ -575" 1 \1 \\\sem\ \\ \\ \\ 73 \ \ _ - \ - \ _ / / / / / / / / / I DB,419 P,344 580 - \ \ _ _ - _ SBS\ \ - - - - - - - - - - - ' / / / / / / / / / , ' / II TRACT 1 --- --- \ \ �\ \ / / / / / / SII I8570 PB,22 P,73 _580 LAND USE, SINGLE 8FA FAMILY (010) TAX DISTRICT: 45-E ALAMANCE STREAM BUFF \ \ \ \ _ _ \ \ \ _ -575- 1',,-'--- _ - _ VERNON D. (LAPP // _ _ _ _ _ _ l.�1�, 10 Ir / BARRY H. & DIANE T. BURGESS D 22 P248 PB. 29 , 7'- II DB,1003 P,185 PB.61 P,96 -\\ / / / 1 j% �- ~ �\ -- _--- -------- - - - �/ /� / , / �� / II l TRACT 2 PIN:9813494621PB.22 P,73 c /7 `� - - _ _ _ _ _ _ - - _ / / / PIN:98 3388737 LAND USES SINGLE FAMILY (010) \ \\�\ / �// I I •� // - \ - - - - _ - - - - _ _5j5\ - - _ / / TAX DISTRICT: 45-E ALAMANCE \ �� - \ , 111I /// \ \\\ - - _ _ _ / / ' / / / o+ LAND USE: SINGLE FAMILY (010) \ / / / / -i / TAX DISTRICT 45-E ALAMANCEIr \ pill -- - - -- -`- 14- _ 18 LARRY G, PARKS AND BILLIE A. PARKS TRUST \ THOMAS B. & MARY STANCELL \ DB,2733 P,181 DB.429 P.880 TRACT 4 LOT 4 \ PB.59 P,121 PB.22 P.73 PIN19813492013 PIN19813398259 LAND USE: VACANT LAND (501) LAND USE SINGLE FAMILY (010) TAX DISTRICT: 45-E ALAMANCE TAX DISTRICT: 45-E ALAMANCE ai E N O 0 U E = o E H 0 L au°' �LO o ii Luu-(7N-I Q O -o U w O M N O �W-��z a O (7 m M Z to - Z V) M u W a X - J LL U o O U) = Y o ~ i N M J 00 W H w a D DATE MAulm DRAWN BY B. CHAMBERS DESIGNED BY A. CARROLL CHECKED BY A. CARROLL SCALE 1 "=50' U D U z0W U V) zLu O W z ~ UmV) W z rJ V / V / ,0 0. U 30B NO. 36810 SHEET NO. C1.0 6 c U N O L m N O Q 7 Q a c m `o ro N a� a 0 co s N O co co CL O m 0 c � a �O O O ro U) z O 22 O c � o 0 c m � N d o D c z N O � a g x H o w� O C 0 Q� 2'§ ac Y � N X 0 0 0 O U w � N m c 0 (" U � O 0 E U N -0� m :2.O 4 U N � N ,o O U L c: M� N O U 0_ o o-0 U� _E LINE TABLE LINE LENGTH BEARING L1 22.04 S43°34'54'W L2 166.25 N39'36'37'E L3 80.15 N39°29'44'E L4 84.92 N33°16'24'E L5 46.14 N56°21'37'E L6 81.08 N45°46'05'E L7 105.28 N48'38'20'E L8 56.03 N41°06'49'W L9 54.67 N34'15'06'E L10 63.20 N62.28'22'E L11 89.71 N40°18'50'E L12 45.82 N16'37'25'E L13 127.51 N44°06'48'E L14 29.09 N08'39'45'E L15 64.16 N05'25'03'W L16 29.70 N37°11'56'E L17 28.74 S84°43'15'E L18 51,38 N22°37'19'E L19 122.42 N52°12'16'W L20 51.58 N14°50'19'E L21 27.00 N00'51'41'W L22 63.67 N56°24'01'W L23 69.41 N05°23'04'E L24 71.90 N16°59'49'E HEADWALL _.,IIA SCALE 1"=50' NOR 0 50' 100' L_ -575" 1 \1 \\\sem\ \\ \\ \\ 73 \ \ _ - \ - \ _ / / / / / / / / / I DB,419 P,344 580 - \ \ _ _ - _ SBS\ \ - - - - - - - - - - - ' / / / / / / / / / , ' / II TRACT 1 --- --- \ \ �\ \ / / / / / / SII I8570 PB,22 P,73 _580 LAND USE, SINGLE 8FA FAMILY (010) TAX DISTRICT: 45-E ALAMANCE STREAM BUFF \ \ \ \ _ _ \ \ \ _ -575- 1',,-'--- _ - _ VERNON D. (LAPP // _ _ _ _ _ _ l.�1�, 10 Ir / BARRY H. & DIANE T. BURGESS D 22 P248 PB. 29 , 7'- II DB,1003 P,185 PB.61 P,96 -\\ / / / 1 j% �- ~ �\ -- _--- -------- - - - �/ /� / , / �� / II l TRACT 2 PIN:9813494621PB.22 P,73 c /7 `� - - _ _ _ _ _ _ - - _ / / / PIN:98 3388737 LAND USES SINGLE FAMILY (010) \ \\�\ / �// I I •� // - \ - - - - _ - - - - _ _5j5\ - - _ / / TAX DISTRICT: 45-E ALAMANCE \ �� - \ , 111I /// \ \\\ - - _ _ _ / / ' / / / o+ LAND USE: SINGLE FAMILY (010) \ / / / / -i / TAX DISTRICT 45-E ALAMANCEIr \ pill -- - - -- -`- 14- _ 18 LARRY G, PARKS AND BILLIE A. PARKS TRUST \ THOMAS B. & MARY STANCELL \ DB,2733 P,181 DB.429 P.880 TRACT 4 LOT 4 \ PB.59 P,121 PB.22 P.73 PIN19813492013 PIN19813398259 LAND USE: VACANT LAND (501) LAND USE SINGLE FAMILY (010) TAX DISTRICT: 45-E ALAMANCE TAX DISTRICT: 45-E ALAMANCE ai E N O 0 U E = o E H 0 L au°' �LO o ii Luu-(7N-I Q O -o U w O M N O �W-��z a O (7 m M Z to - Z V) M u W a X - J LL U o O U) = Y o ~ i N M J 00 W H w a D DATE MAulm DRAWN BY B. CHAMBERS DESIGNED BY A. CARROLL CHECKED BY A. CARROLL SCALE 1 "=50' U D U z0W U V) zLu O W z ~ UmV) W z rJ V / V / ,0 0. U 30B NO. 36810 SHEET NO. C1.0 6 c U N O L m N O Q 7 Q a c m `o ro N a� a 0 co s N O co co CL O m 0 c � a �O O O ro U) z O 22 O c � o 0 c m � N d o D c z N O � a g x H o w� O C 0 Q� 2'§ ac Y � N X 0 0 0 O U w � N m c 0 (" U � O 0 E U N -0� m :2.O 4 U N � N ,o O U L c: M� N O U 0_ o o-0 U� _E L_ GROUND STABILIZATION SITE AREA STABILIZATION STABILIZATION DESCRIPTION TIME FRAME TIME EXCEPTIONS • PERIMETER DIKES, BASIN 1 2.87 SWALES, DITCHES, 7 DAYS NONE AND SLOPES 4,748 4,644 • HIGH QUALITY 0.27 0.27 WATER (HQW) 7 DAYS NONE ZONES 486 �ci�z • SLOPES STEEPER IF SLOPES ARE 10' OR LESS IN THAN 3:1 7 DAYS LENGTH AND ARE NOT STEEPER z LU � U1 THAN 2:1 14 DAYS ARE ALLOWED • SLOPES 3:1 OR 14 DAYS 7 -DAYS FOR SLOPES GREATER FLATTER w THAN 50 FEET IN LENGTH • ALL OTHER AREA N NONE (EXCEPT FOR PERIMETERS WITH SLOPE 14 DAYS AND HQW ZONES) FLATTER THAN 4:1 (w `' ' Lr) l PHASE 1 SKIMMER BASIN SUMMARY \\��111111111/// �N CAR 0 SEAL = 38573 f = 2r4 \, \ \ \ 11 \ \\ \\\ \\ \ \ IN, \ \ \ \ \ I DRAIN REA(ACRES) DISTB. AREA(ACRSS) PEAK FL 0W(CFS) BASIN SURFACE AREA(SF) REQUIRED SURFACE AREA(SF) BASIN VOLUME (CF) REQUIRED BASIN VOL LIME (CF) BASIN 1 2.87 2.58 7.70 2,89J 2,503 4,748 4,644 BASIN 2 0.27 0.27 0.77 1,67J 250 2,815 486 \\��111111111/// �N CAR 0 SEAL = 38573 f = 2r4 \, \ \ \ 11 \ \\ \\\ \\ \ \ IN, \ \ \ \ \ I y1AiI�P�\\,, rn E CD 0 I I \ \ \ \ \ \ \ \ \ I l / I I I \ \\ \\ \\� \ \ \ \ \ \ \ \ \ \ \ \ - - - - - _ _ _ _ _ DIMENSIONS, AREA, & VOLUME OF SKIMMER BASIN ARE AT WEIR ELEVATION r'\„ * "EXTENSIONS OF TIME MAY BE APPROVED BY THE PERMITTING AUTHORITY / I / \\ \\ \ \ \ \ \ \ \ \ \ _ / ' w o E BASED ON WEATHER OR OTHER SITE-SPECIFIC CONDITIONS THAT MAKE / 3�/? / ! / \ \ \ \ \ \ \ \ \ _ _ _ _ Nbg„g _ r = o COMPLIANCE IMPRACTICABLE." (SECTION II. B (2)(b)) / \ \ \ \ \ \ \ \ \ \ - _ - - 100 ~ � � Nb O /---------- 0Ma) Ln LU LU NbS,.8 -__J �0 `°z 0 LULU \ \ \ \ \\ \ \ \ 1 _ - - O � a � � 600 - ` / i �S'„8 _ - 1 � W � X J (n W W `n �,- Q���Z O QQ ca co z LU LU CD \ / - _ I I I EXISTING POND \ 1 I I I \ Z\\ I/ ' / i /0�5� I M LU I I \ rj re) LU 00 \ _ ' \ I / 0 \ \\ LIMITS OF , I 1 1 \ \ \\ DISTURBANCE �ZONE 1 1 30' I I \ \ \ - r \ / \ - /LU In In -STREAM BUFFER /I I \ \ \ \ \ ` \ \ 59 / / \ \ \ / w Ln 00 �/ 2 Q \\ \ \\ TYP CHECK D�\w _ - - STREAM BUFFER/ ' / / \ I % \ \ \ - - - - - - - - - / / 5 �, ` / ' / / \ \ / / O \ \ \\ (TYP)/� \ \\-------' i'\j' - �'' `� / // // / �1) \ - - _ �/// / // / DATE EROSION CONTR-b� - - - - - - \ \ \ _ / ' - - / % 1\ 8" PVC INVERT - � � \ \ \ \ , - - ' / \�/ ' ♦ �' \\ l ! / / /1 � \ \ / / / / / / / M 9/9/15 \ \ \-MATTf1S111�1-SWALE p \ EL1 580,01' _ / �i \ \ 1 y I l 1 ` / O \ \ _ \ ,J - - / \ :590 �_ ; \ I 59 / , >- \ \ y \ \ CENTERLINE \ I �`\ 8" PVC INVERT \\ - '�� / ' \ Z / I \ \ / I PERMANENT CLEAN -WATER / / / ELI 580.03' \\ - _�_ �_ _ �' - / // / _ _ \ �_�- ! / \ \ ` I I DIVERSION (INSTALL EROSION \ \ \ \ _ _ - - _ \\ _ CONTROL MATTING IMMEDIATELY / EROSION CO1tlTf20L MATTING I \ \ \ \ / - -_ - - _ - - :59 - ; ' / �� • EROSION CONTROL / _ - _ --- _ \� - _ _ _ - - _ _ - - - - _ - - _ - �/ \ \ / I I AFTER INSTALLATION) IN SWALE CENTERLINE \ _ _ _ - - - - - I _ _ - Z LVERT IWLET -_ �_ - _ - - -_ - _ _ - //'\I `' MATTING IN SWALE \ / PROTECTIOhI = - \ _ _ - - - - - - - - - / i ' \P \ \ \ \ \ \ CENTERLINE INLET ` // I I / EW3c ROL \ \ \ CHECK Dpm ti -590 -- __\-__ -- - �_- - �% \ PROTECTION - - _ - - - - - - _ - - _ _ _ MA TIItiG IN SWALE \ \ LIMITS OF \ \ I I TYP • INLET - _ _ _ - - - _ _TEMPORARY \ - _ - - - _ _ - - _ - \ TERCINE \ '\ DISTURBAN E \ (TYP) I I f = sIL�BxzSWm = _ _ COOTRUCTTOIV ' LIMITS OF - _ 1 - - �� I \ -ENTRANCE - / DIST-U�RBANCE / - - - - - _ - - _ _ - _ - LB1aSiN - / I \ \ ' ` I LIMITS OF • \ \ \ \ (TYP) 5 \ - - - - - - _ _ _ - / / / - _ PE �' ^ \ / / / 1 / _ -58 - DISTURBANCE CULVERT 1917ET - \ / / / I - - ' / - \ -PROTECTION - _ - - _ 585S<9 INLET PROTECTION - ry in=582,06' 1 d _ B \I \ - - - - - - - - - $ - - NbS..8 - Nt/S.. N�/ ..8- S NbS..8 NV S IM (TYP() CHECK DAM 1� • CHECK • P station \�\ �j \ - NQS„8 _ _ - - - - - - , 8� \ \ \ \ M I I I I \ `�' \ cs S8� _ (TYP) / SBE gyp) in=572.64' _ _ - - - _ _ - - - L ssmr) A,) , \\SILT BASIN Nom\ yg„8 - - - - 8 5a - - _ - - - - - - 0� -�8S \ \ \ \\ (TYP) I \ 86' 6a \ - � 8 6 \ 9 \ \ 5 � 6 \ M,.Z M.,Z M„Z M..Z >' M„Z • ori=561.72' N _ - - / _ _ \ \ \ / M..8 M..8/ �18 M.,8 p=583.70' "TYPE B" - „Z M..Z A Z\ AA M Z M„Z M„Z M., I = • Wet well LIMITS OF \\ zi \ \� - - - M.. \ \ \-�M,.8 M.8 DISTURBANCE - 58 _ \ \ \ \ _ / 1 ' e • Hco otbo \ �\ SILT FENCE STONE OUTLET \ \ \ � ` - � _ _ ssroh STONE OUTLET \ 1 ' (TYP)_ TYP STONE OUTLET \ \ (TYP) \ \ \ SIL \ \ SKIMMER BASIN 1� _ Rim=583.4 \ \ 1 / 0 - - - - - - _ _ ( ) (TYP) - - \ \ \ \ \ \ \ \ 584 - - - _ - u PHASE 2 DRAINAGE AREA = 2.87 alc / - !-v out=572, \ \ I t1NffTS OF \ / \ \ \ \ \ \ \ 59 0� I 572,96'Cplu9) DISTURBANCE - ' \ \ \ \ \ \ \ / \ / \� \ \ \ / Q _ \ \ PHASE 2 DISTURBED AREA = 2.58 c DIVERSION Inv out 579.86 \ \ \ \ ZONE 2 1 20' \ \ / \ \ \ \ \ \ \ - - - - - - - _ - / PHASE 2 10 -YR PEAK FLOW = 7.70 fs-DITCH (TYP) STONE OUTLET STREAM BUFFER \ \ \ / \ \ \ \ \ \ \ \ \ 83 \ / / \ \ / TYP \ --- SILT FENCE \�\ate \ \\ ( ) �\ \ \\ \ \ \ \ \\ \ \ \` -- - --- _-�--- / �O (TYP) \\ // V _ ZONE 1 30' V v v v v v A / STREAM BUFFER Sy ENCE _ 585 - - _ (TYP) - LIMITS OF \ \ \ \ \ \ \ / / / \ / _ _ - \ \ \ \ \ - I - - - _ _ FFE I I fLO TS OF \ \ \ \ \ \ 582 � m ' ' 587/.00 / I I / / � / DISTURBANCE \ \\\ ,\ \ \ \l I\\ / / \ \ \ \ / ' \ \ \ \ \ \ \ \ \ _ - - - - _ _ _ _ _ r / / STON� QUTCET 81- E/ moi' DISTURBANCE ep LIMITSLOF UI \ ---5'5' WEIF3 STL�RBANC -575' e e / w HEADWALL 5 / \ - Z❑PdE-2-I( - 8 PHOT 10LV \ \� / \ ' `�\ / E O, 10 TR L fSROT ON ' - _ _ STREAM BUFFER EYP) \ \ _ MATT! ON SLOP / (TYP) E-ATER TIJAN 3:1 4 \ \ \ ^ \ \ \ \ \ \ \ \ - _ _ _ _ - __ !IIII 1 Q\ /� STREAM BUFFE ` \ \ \ \ \ _INLET -575- - \ \ - P OT CT 10 STONE OUTLET - - STONE OUTLET P OUS \ ♦ \ \ \ Q / / / , (TYP) / (TYP) L BAFFLES \ \ _� (TYPr -Q-`��_"% -���� ZT-FENCE _ \ -----•--_-__/ �- \ _ ! 2" SKIMMER W/ ITS Q - DJVER� / DISTURB DITCH TYP SICffFENCE /' -� ♦ U 1.25" ORIFICE _ _ 57 - _ _ (� PHASE 2 EROSION CONTROL CONSTRUCTION SEQUENCE \ �z$ _- '�,' IIII i 2'x 2' ENERGY EROSION CONTROL _ _ - \ \ 5\ _ _ - / , (TYP,) li `�`� / - -MATTING ON SLOPES - - - - - _ _ - _ / / 5' WEIR DISSIPATOR \�`-SWLZFENCE � // \ zF-THAN 3:1 - (TYP) SKIMMER B � / 1. MAINTAIN ALL EXISTING EROSION CONTROL FEATURES PREVIOUSLY CONSTRUCTED AND \ ��I /-- U - - - _ -STONE OUTLET \ \ \ 1 DO NOT DISTURB \ ��\ STONE OUTLET - _ _ _ - PHASE 2 DRAW AG AREA= 0.27 66--j ASSOCIATED WITH PHASE 1 EROSION CONTROL. / _ _ -(TYP)_ _ _ _C - -- - (TYP) \ / ZONE 1 STREAM \ - zJ D PHASE 1 DISTURBED AREA = 0.27 ac 11 BUFFER PHAS 1 = 0.77 cfs 10 -YR PEAK FLOW 2. REMOVE EXISTING 24 RCP CULVERT AND REPLACE WITH 36 RCP AS INDICATED ON PLANS N (SEE DETAIL SHEET C5.2 FOR STREAM CROSSING CONSTRUCTION SEQUENCE IF FLOWING) Q6` 3. BEGIN GRADING OPERATIONS AND INSTALL STORM DRAINAGE SYSTEM FROM OUTLET POINT (LOW END) AND WORK UPSTREAM. PIPE INLET PROTECTION SHALL BE UTILIZED AT THE END OF EACH WORK DAY TO ASSURE PIPE NETWORK IS NOT INUNDATED WITH SEDIMENT. MASS GRADE SITE ALONG WITH STORM DRAINAGE PIPE INSTALLATION TO ASSURE NO GRADES CAUSE OFFSITE SEDIMENTATION. INSTALL ADDITIONAL EROSION CONTROL MEASURES AS NECESSARY. 4. INSTALL REMAINING UNDERGROUND UTILITIES. SCALE 1"=40' 5. GRADE SITE TO SUBGRADE AND BEGIN BUILDING FOUNDATION CONSTRUCTION. NOR 6. INSTALL CURB & GUTTER, GRAVEL BASE, AND BASE ASPHALT. 0 40' 80' 7. WHEN ALL CONTRIBUTING AREAS ARE COMPLETELY STABILIZED, CONTACT EROSION CONTROL INSPECTOR FOR PERMISSION TO REMOVE SKIMMER BASINS. 8. ONCE SKIMMER BASINS ARE REMOVED, REDRESS & STABILIZE FILL SLOPES ABOVE BASINS & INSTALL LEVEL SPREADER. LIMITS OF DISTURBANCE - 4.81 ACRES 9. ONCE ALL AREAS ARE COMPLETELY STABILIZED, CONTACT EROSION CONTROL INSPECTOR FOR FINAL INSPECTION. AFTER APPROVAL, REMOVE ALL REMAINING EROSION CONTROL DEVICES - �� \ - - - - - - - - �� - �\ � \ � �'� 2'x 2' ENERGY DISSIPATOR DO NOT DISTURB \ \ ZONE 1 STREAM BUFFER DRAWN BY B. CHAMBERS DESIGNED BY A. CARROLL CHECKED BY A. CARROLL SCALE 1 "=40' = SPILL WA Y LENGTH (FT) SKIMMER ORIFICE DIAMETER (IN.) SKIMMER SIZE (IN.) TOP OF BERM ELEV. WEIR ELEV. BOTTOM OF BASIN ELEV. BASIN 1 8 1.25 2 577.00 576.00 574.00 BASIN 2 5 1.00 1.50 573.00 572.00 569.75 y1AiI�P�\\,, rn E CD 0 I I \ \ \ \ \ \ \ \ \ I l / I I I \ \\ \\ \\� \ \ \ \ \ \ \ \ \ \ \ \ - - - - - _ _ _ _ _ DIMENSIONS, AREA, & VOLUME OF SKIMMER BASIN ARE AT WEIR ELEVATION r'\„ * "EXTENSIONS OF TIME MAY BE APPROVED BY THE PERMITTING AUTHORITY / I / \\ \\ \ \ \ \ \ \ \ \ \ _ / ' w o E BASED ON WEATHER OR OTHER SITE-SPECIFIC CONDITIONS THAT MAKE / 3�/? / ! / \ \ \ \ \ \ \ \ \ _ _ _ _ Nbg„g _ r = o COMPLIANCE IMPRACTICABLE." (SECTION II. B (2)(b)) / \ \ \ \ \ \ \ \ \ \ - _ - - 100 ~ � � Nb O /---------- 0Ma) Ln LU LU NbS,.8 -__J �0 `°z 0 LULU \ \ \ \ \\ \ \ \ 1 _ - - O � a � � 600 - ` / i �S'„8 _ - 1 � W � X J (n W W `n �,- Q���Z O QQ ca co z LU LU CD \ / - _ I I I EXISTING POND \ 1 I I I \ Z\\ I/ ' / i /0�5� I M LU I I \ rj re) LU 00 \ _ ' \ I / 0 \ \\ LIMITS OF , I 1 1 \ \ \\ DISTURBANCE �ZONE 1 1 30' I I \ \ \ - r \ / \ - /LU In In -STREAM BUFFER /I I \ \ \ \ \ ` \ \ 59 / / \ \ \ / w Ln 00 �/ 2 Q \\ \ \\ TYP CHECK D�\w _ - - STREAM BUFFER/ ' / / \ I % \ \ \ - - - - - - - - - / / 5 �, ` / ' / / \ \ / / O \ \ \\ (TYP)/� \ \\-------' i'\j' - �'' `� / // // / �1) \ - - _ �/// / // / DATE EROSION CONTR-b� - - - - - - \ \ \ _ / ' - - / % 1\ 8" PVC INVERT - � � \ \ \ \ , - - ' / \�/ ' ♦ �' \\ l ! / / /1 � \ \ / / / / / / / M 9/9/15 \ \ \-MATTf1S111�1-SWALE p \ EL1 580,01' _ / �i \ \ 1 y I l 1 ` / O \ \ _ \ ,J - - / \ :590 �_ ; \ I 59 / , >- \ \ y \ \ CENTERLINE \ I �`\ 8" PVC INVERT \\ - '�� / ' \ Z / I \ \ / I PERMANENT CLEAN -WATER / / / ELI 580.03' \\ - _�_ �_ _ �' - / // / _ _ \ �_�- ! / \ \ ` I I DIVERSION (INSTALL EROSION \ \ \ \ _ _ - - _ \\ _ CONTROL MATTING IMMEDIATELY / EROSION CO1tlTf20L MATTING I \ \ \ \ / - -_ - - _ - - :59 - ; ' / �� • EROSION CONTROL / _ - _ --- _ \� - _ _ _ - - _ _ - - - - _ - - _ - �/ \ \ / I I AFTER INSTALLATION) IN SWALE CENTERLINE \ _ _ _ - - - - - I _ _ - Z LVERT IWLET -_ �_ - _ - - -_ - _ _ - //'\I `' MATTING IN SWALE \ / PROTECTIOhI = - \ _ _ - - - - - - - - - / i ' \P \ \ \ \ \ \ CENTERLINE INLET ` // I I / EW3c ROL \ \ \ CHECK Dpm ti -590 -- __\-__ -- - �_- - �% \ PROTECTION - - _ - - - - - - _ - - _ _ _ MA TIItiG IN SWALE \ \ LIMITS OF \ \ I I TYP • INLET - _ _ _ - - - _ _TEMPORARY \ - _ - - - _ _ - - _ - \ TERCINE \ '\ DISTURBAN E \ (TYP) I I f = sIL�BxzSWm = _ _ COOTRUCTTOIV ' LIMITS OF - _ 1 - - �� I \ -ENTRANCE - / DIST-U�RBANCE / - - - - - _ - - _ _ - _ - LB1aSiN - / I \ \ ' ` I LIMITS OF • \ \ \ \ (TYP) 5 \ - - - - - - _ _ _ - / / / - _ PE �' ^ \ / / / 1 / _ -58 - DISTURBANCE CULVERT 1917ET - \ / / / I - - ' / - \ -PROTECTION - _ - - _ 585S<9 INLET PROTECTION - ry in=582,06' 1 d _ B \I \ - - - - - - - - - $ - - NbS..8 - Nt/S.. N�/ ..8- S NbS..8 NV S IM (TYP() CHECK DAM 1� • CHECK • P station \�\ �j \ - NQS„8 _ _ - - - - - - , 8� \ \ \ \ M I I I I \ `�' \ cs S8� _ (TYP) / SBE gyp) in=572.64' _ _ - - - _ _ - - - L ssmr) A,) , \\SILT BASIN Nom\ yg„8 - - - - 8 5a - - _ - - - - - - 0� -�8S \ \ \ \\ (TYP) I \ 86' 6a \ - � 8 6 \ 9 \ \ 5 � 6 \ M,.Z M.,Z M„Z M..Z >' M„Z • ori=561.72' N _ - - / _ _ \ \ \ / M..8 M..8/ �18 M.,8 p=583.70' "TYPE B" - „Z M..Z A Z\ AA M Z M„Z M„Z M., I = • Wet well LIMITS OF \\ zi \ \� - - - M.. \ \ \-�M,.8 M.8 DISTURBANCE - 58 _ \ \ \ \ _ / 1 ' e • Hco otbo \ �\ SILT FENCE STONE OUTLET \ \ \ � ` - � _ _ ssroh STONE OUTLET \ 1 ' (TYP)_ TYP STONE OUTLET \ \ (TYP) \ \ \ SIL \ \ SKIMMER BASIN 1� _ Rim=583.4 \ \ 1 / 0 - - - - - - _ _ ( ) (TYP) - - \ \ \ \ \ \ \ \ 584 - - - _ - u PHASE 2 DRAINAGE AREA = 2.87 alc / - !-v out=572, \ \ I t1NffTS OF \ / \ \ \ \ \ \ \ 59 0� I 572,96'Cplu9) DISTURBANCE - ' \ \ \ \ \ \ \ / \ / \� \ \ \ / Q _ \ \ PHASE 2 DISTURBED AREA = 2.58 c DIVERSION Inv out 579.86 \ \ \ \ ZONE 2 1 20' \ \ / \ \ \ \ \ \ \ - - - - - - - _ - / PHASE 2 10 -YR PEAK FLOW = 7.70 fs-DITCH (TYP) STONE OUTLET STREAM BUFFER \ \ \ / \ \ \ \ \ \ \ \ \ 83 \ / / \ \ / TYP \ --- SILT FENCE \�\ate \ \\ ( ) �\ \ \\ \ \ \ \ \\ \ \ \` -- - --- _-�--- / �O (TYP) \\ // V _ ZONE 1 30' V v v v v v A / STREAM BUFFER Sy ENCE _ 585 - - _ (TYP) - LIMITS OF \ \ \ \ \ \ \ / / / \ / _ _ - \ \ \ \ \ - I - - - _ _ FFE I I fLO TS OF \ \ \ \ \ \ 582 � m ' ' 587/.00 / I I / / � / DISTURBANCE \ \\\ ,\ \ \ \l I\\ / / \ \ \ \ / ' \ \ \ \ \ \ \ \ \ _ - - - - _ _ _ _ _ r / / STON� QUTCET 81- E/ moi' DISTURBANCE ep LIMITSLOF UI \ ---5'5' WEIF3 STL�RBANC -575' e e / w HEADWALL 5 / \ - Z❑PdE-2-I( - 8 PHOT 10LV \ \� / \ ' `�\ / E O, 10 TR L fSROT ON ' - _ _ STREAM BUFFER EYP) \ \ _ MATT! ON SLOP / (TYP) E-ATER TIJAN 3:1 4 \ \ \ ^ \ \ \ \ \ \ \ \ - _ _ _ _ - __ !IIII 1 Q\ /� STREAM BUFFE ` \ \ \ \ \ _INLET -575- - \ \ - P OT CT 10 STONE OUTLET - - STONE OUTLET P OUS \ ♦ \ \ \ Q / / / , (TYP) / (TYP) L BAFFLES \ \ _� (TYPr -Q-`��_"% -���� ZT-FENCE _ \ -----•--_-__/ �- \ _ ! 2" SKIMMER W/ ITS Q - DJVER� / DISTURB DITCH TYP SICffFENCE /' -� ♦ U 1.25" ORIFICE _ _ 57 - _ _ (� PHASE 2 EROSION CONTROL CONSTRUCTION SEQUENCE \ �z$ _- '�,' IIII i 2'x 2' ENERGY EROSION CONTROL _ _ - \ \ 5\ _ _ - / , (TYP,) li `�`� / - -MATTING ON SLOPES - - - - - _ _ - _ / / 5' WEIR DISSIPATOR \�`-SWLZFENCE � // \ zF-THAN 3:1 - (TYP) SKIMMER B � / 1. MAINTAIN ALL EXISTING EROSION CONTROL FEATURES PREVIOUSLY CONSTRUCTED AND \ ��I /-- U - - - _ -STONE OUTLET \ \ \ 1 DO NOT DISTURB \ ��\ STONE OUTLET - _ _ _ - PHASE 2 DRAW AG AREA= 0.27 66--j ASSOCIATED WITH PHASE 1 EROSION CONTROL. / _ _ -(TYP)_ _ _ _C - -- - (TYP) \ / ZONE 1 STREAM \ - zJ D PHASE 1 DISTURBED AREA = 0.27 ac 11 BUFFER PHAS 1 = 0.77 cfs 10 -YR PEAK FLOW 2. REMOVE EXISTING 24 RCP CULVERT AND REPLACE WITH 36 RCP AS INDICATED ON PLANS N (SEE DETAIL SHEET C5.2 FOR STREAM CROSSING CONSTRUCTION SEQUENCE IF FLOWING) Q6` 3. BEGIN GRADING OPERATIONS AND INSTALL STORM DRAINAGE SYSTEM FROM OUTLET POINT (LOW END) AND WORK UPSTREAM. PIPE INLET PROTECTION SHALL BE UTILIZED AT THE END OF EACH WORK DAY TO ASSURE PIPE NETWORK IS NOT INUNDATED WITH SEDIMENT. MASS GRADE SITE ALONG WITH STORM DRAINAGE PIPE INSTALLATION TO ASSURE NO GRADES CAUSE OFFSITE SEDIMENTATION. INSTALL ADDITIONAL EROSION CONTROL MEASURES AS NECESSARY. 4. INSTALL REMAINING UNDERGROUND UTILITIES. SCALE 1"=40' 5. GRADE SITE TO SUBGRADE AND BEGIN BUILDING FOUNDATION CONSTRUCTION. NOR 6. INSTALL CURB & GUTTER, GRAVEL BASE, AND BASE ASPHALT. 0 40' 80' 7. WHEN ALL CONTRIBUTING AREAS ARE COMPLETELY STABILIZED, CONTACT EROSION CONTROL INSPECTOR FOR PERMISSION TO REMOVE SKIMMER BASINS. 8. ONCE SKIMMER BASINS ARE REMOVED, REDRESS & STABILIZE FILL SLOPES ABOVE BASINS & INSTALL LEVEL SPREADER. LIMITS OF DISTURBANCE - 4.81 ACRES 9. ONCE ALL AREAS ARE COMPLETELY STABILIZED, CONTACT EROSION CONTROL INSPECTOR FOR FINAL INSPECTION. AFTER APPROVAL, REMOVE ALL REMAINING EROSION CONTROL DEVICES - �� \ - - - - - - - - �� - �\ � \ � �'� 2'x 2' ENERGY DISSIPATOR DO NOT DISTURB \ \ ZONE 1 STREAM BUFFER DRAWN BY B. CHAMBERS DESIGNED BY A. CARROLL CHECKED BY A. CARROLL SCALE 1 "=40' = z J U J O I --I z z~� Jz oO <U �ci�z � o O 0 z LU � U1 Uma z Q LU � w N z (w `' ' Lr) l V / O 0. U JOB NO. 36810 SHEET NO. C2.1 3 ami a- mO -0O� U) wo �2 02 C T� E� - 0 C m MN 0- O ZN O aNi 2 a 75; x o Y m 0 o_ w 2'§ N Y 7 N 0x C ro 0 O U :F3E llN (6 0 0 (/1 U C `oa� E U O O -0 �0 U O C N O N- O U � CNE In O O U ;n a E L f6 m Q LO 0 00 Ln 0 N 0 M �O 0 0 a L_ NOTE: PROVIDE ADEQUATE EROSION CONTROL MEASURES (SILT FENCE, INLET PROTECTION, ETC.) TO ENSURE NO SEDIMENT ENTERS STORM DRAINAGE SYSTEM OR LEAVES SITE. LEGEND - - - - - - - - - - - \ \ \ \ \ x EC 845.00 PROPOSED EDGE OF CONCRETE GRADE / NOTE: ALL DISTURBED AREAS ARE TO BE SEEDED x EP 845.00 PROPOSED EDGE OF PAVEMENT GRADE \ \ \ \ \ ! I I I \ \ \ \ \ UNLESS OTHERWISE NOTED. x TC 845.00 C _ \ \\\\\\ \\ \\\ \ \\\\ \ \ \ PROPOSED TOP OF CURB GRADE xTW845.00 PROPOSED TOP OF WALL GRADE IN, \\ \ \ \\ \ \ � �\ Opp \ \ \ \ _ xBW845.00 PROPOSED BOTTOM OF WALL GRADE --845-- EXISTING GRADE -845- PROPOSED GRADE cP - - _- I / \\\ \ \\ \ \ \ \ \ \ \ \ \ P� 10�po' i 1600" /' / / / � / I NVS„8 / LO 671 - - - - - - -S, j\\ I i CDi I EXISTING POND \\ \ I I I \ \ z _ - , _ - ' �/ 00 F - -- - - - - -- / \/ O co 'STRE0NE BUFFER / I I I I \ \ \ - - \S;- - - _ - / / / / STREAM BUFFER ' \ I J J,- \ \ \ \ - - - - l / / / \ -5 - - \ \ ' ' / / / \ 8" PVC INVERT \ \ \ \ \ 90 - _ \ 0 1 \ ELI 580,01' _ �/ / / \ \ :590 ,r \ \ ! / \ - _ _ 590 8" PVC INVERT _ 'i��' / /i' \ z / l \ \ l - - - _ _ _ _ _ - _ \ ` 1 90\ ELI 580,03' 1\\ _ _ _ '-_ - / / _\ o9T < \ \ o \ . - -_-- - _ -_- - _ -590 _ - --_eU L�Rot�- - _ \ --_--_- -_---- _ - _ ��- _ - \ \ \ l� _ _ _\ _ _- _ _- _- _ - - , / \ r�5�� \ \ \ L_\ \ \ \ I I 586.40 TC TC \ \ \ \ ! _ 587.14 586.73,- - 86.73/ y \ \ \ 6 1 S8 - - - - - \ v / / - - - _-_- �- _ NC60T STD 838.80 \ / / 1� \ I \ 59 I / - - 1- PERMANENT CLEAN \ \ \ \ \ \ 5 - - - - - - - _ - _ - - ; / / / / cj� CONCR E ENDWA / / _ J I -= _ WATER DIVERSION _INV: 577. b� - \ 59 - - - /- - - -58 / _ 58 _ I TC Inv in=582,06' I \ d \ \ - - - - - - - SG 59 - \ - \ - - 1 TCI / 586.19 \I \ d'�, ES - - - S - NVS ,8. _ N dS„ Nb ..8 S Nt/S, 8 Nd S [586. 83 5871.14 \\\ \ \ 11 - - - - N s� y _ - - _ \ �u' v _ - \ \ \ \ 1 I \ TC TC TC '-5191' 8 TC 7 586 TC 2 _ _ _ - - - - ' \ T I 49 585.07 4 93 `r 6 586.28 TC TC 86 \ \ \ \ 58 586.57 a, 86.89 586.96 / /SG \\ 2 1 \ Nd s .2a yro sss s2/ _ - - - 685-�5a _ _ _ _ - _ - - -Rid 0 0 42' RCP S - 8 \ \ \ \ 58 $6 M„Z - I TC M„Z M„Z �. \\ \ _ ssa.�2 1.001.-5 !/ - 8 \ \ Q 5 M„8 M„ / il9 TC TC . . \\ S _ - �N„Z M..Z „Z\ M \ M Z M,.Z M„Z M„ TC 58 .64• 585 52 \\ 3 �3 as - ssaS \ M..8 \ M,.8 M..8 584.59 584.36 / • • 586.8 7 TC 8 _ \ O SG / S 6, gTGA TC 586.98 586.98 �- - - 586.00 \ _ sas.�o 2 - 8 e - - 42,, FES ! \ \ \ \ \ \ \ \ \ \ \ \ 5a� TC 584 28 - - - 586.4$1 5 - - - - - - - - - - - - - - - - - - - - - - - - - -INV: 576.40 \ \ \ \ \ \ \ ` \ \ 8 \ 584.06 1 SG / 586 48 SG 586.10 � 86.8/ 58.88 S I �SG IS SGJ g S \ / 586.98 586.98 S 5§.632 OUTLET PROTECTIOf� \ \ CA \ 586.87 h \ 1 �3 � � �' \ \ L=16',W=18�', \ \ \ \ \\ \\ � � � , � _, _ - � / 5 6.98586.87 � - - - - _ \ \ J / 586.98' - \\ \\ I 1 ---- _ \ _ \ \ 584 `r 58 T - \ D50 -' .5', d = 1. 3' 1 6.87 I 585.6 Inv out=579,86 \ \ \ \ \ \ \ B ZONE 2 1 2' \ \ / / / ' \ \ \ \ \ \ \ \ \ \ \ \ \ \ _ - - - _ ` _ $ 58a78 SG STREAM BUFFER \ \ ` / \' \ \ \ \ \ \ \ \ 83 \ - - - - - - - - _ _ \ 586.98 ZONE 1 1 30' \ _ STREAM BUFFER _ - \ \ \\ \ \ \ \ \ \ \ \ - - - - - - - - - - - - - _ - I \ \ l l / TC \ \ \ OUTLET PROTE , - _ _ _ _ �\ \ \ \ - ) 584.61- \ \ \ \ L=9',W-10 / \ \ \ \ \ \ \ \ - _ _ _ - _ c,, / / to _ _--___,- \ \ \ \ \ \ \ �-- 82 - - - I- w FFE587.00 / ! / /� \ \ \\\\ \ \ \ \ . \ \ S S D50 = Q.& d = 0.68' \ \ \ \ \ \ \ \ _ 1 - - - _ - ' _ _ - _ \ - 586 98 SG / / _ ---- S 58698 .9 I 6. 7 586 8 58 98 8 _ , ,S. \ `� 586.98 SG _ S) C- \ \ \ \ \ \ \ - - - - ' - _ _ - ' ' _ - _ \ `1 _ dr, - - _ - SG / 585.9 \' 586.98 G �� - - \ \ \ 8 - - _ \ 586.37 f8j 85.87 X85.90 / i \ / \ \ \ \ _ _ 58� - - ' ` ' \ \ \ ES _ _ _ 5892 / -5%5 � \ \\ \\ \ ---_- _ ----- \ _ � � \ \ _ 5.87 ee e ••/ HEADWALL \''r \\ \ \ \\ \ �\ - �__ _ _ - \ \ S T / T /584.1C \ \ \ \ \ \ \ \ - -ZONE-2-1 rj \ 85. 5 6.3 T 5 5. \ Jr \ _ - \ TC \ \ \ TC L L L / 5 5.7 ' / / / J \\ IN, -STREAM BUFFER _ \ -� \ _ C 82\ \ 585.32. T _ - - - - S \1 \ \\ \ O \ \ \ \ m 11 1 \ \ Z73RlE 1 30' - - - - 0 \ 585.21 TC '585.49 585.49 \ \ 8 585.66 _ _ / STREAM BUFFE \ \ \ \ A - _ 58 584.19' -575 _ --_ 2 / , T tc 0 , \\ \�\ \ \ \ \ \ y \ \ \ �� \ \\\ \ \ - \ 100 LEVEL SPREADER \ - 583. - 8g - - 85.6 5.5.2 / (SEF DETAIL SHEET C5.V) 11; 35 �� _ -___ - ____ - -' / o/ STORM PIPE TABLE PIPE # DIA FROM - TO UPSTREAM DOWNSTREAMINVERT INVERT SLOPE LENGTH DESCRIPTION 2 24" 1 - 3 579.45 578.29 0.50% 232.90 LF 24 inch RCP 4 24" 3 - 5 578.19 577.47 0.50% 144.29 LF 24 inch RCP 6 30" 5 - FES1 576.97 576.77 1.00% 20.25 LF 30 inch RCP 8 24" 7 - 5 581.74 577.47 1.84% 232.38 LF 24 inch RCP 10 24" 9 - 5 579.23 577.47 0.96% 184.00 LF 24 inch RCP STORM STRUCTURE TABLE STRUCTURE # TOP STRUCTURE HEIGHT DESCRIPTION 1 583.20 3.75' NCDOT 840.02 Catch Basin w/ NCDOT 840.03 Frame, Grate, & Hood 3 583.85 5.66' NCDOT 840.02 Catch Basin w/ NCDOT 840.03 Frame, Grate, & Hood 5 582.20 5.23' NCDOT 840.02 Catch Basin w/ NCDOT 840.03 Frame, Grate, & Hood 7 585.49 3.75' NCDOT 840.02 Catch Basin w/ NCDOT 840.03 Frame, Grate, & Hood 9 582.98 3.75' NCDOT 840.14 Drop Inlet w/ NCDOT 840.16 Grate FES1 579.56 ???' 30" Flared End Section STORM STRUCTURE TABLE STRUCTURE # TOP STRUCTURE HEIGHT DESCRIPTION 12 582.50 3.00' NCDOT 840.14 Drop Inlet w/ NCDOT 840.16 Grate FES2 581.94 ???' 15" Flared End Section FES2A 582.21 ???' 18" Flared End Section FES3 578.21 ???' 18" Flared End Section STORM PIPE TABLE PIPE # DIA FROM -TO UPSTREAM DOWNSTREAMINVERT INVERT SLOPE LENGTH DESCRIPTION 11 15" FES2 - 12 580.50 579.75 2.35% 31.92 LF 15 inch RCP 11A 18" FES2A - 12 580.50 579.60 7.50% 12.00 LF 18 inch RCP 13 18" 12 - FES3 579.50 576.50 3.26% 92.00 LF 18 inch RCP 42 in Culvert 42" - 577.00 576.40 1.00% 60.00 LF 42 inch RCP - -_ - _ \\_ _ __ _ ✓ �''� �= 20 �\ // \ NZ \ \ -,A,A SCALE 1 "=40' \ 0 40' 80' ai E N � 0 U E W o +, aULn a �� � M a) LO LU � (7 N •--I ¢<O-oU W 0' N O C11- W.-I�Z a O a) m M In Z 0 - ZU LU Q J W U o O U)21 = Y o ~ i N �o M N M LU 00 W H vi crfM O Z) O F- 0 W W_ 2 U Q z O M O z z z O W W U 00 Lf) LU LLJ Lu z z Q Q m m z W W O g g LL W 00 W U U Ln Ln W .-I I I 0 rj O O DATE 9/9/15 DRAWN BY B. CHAMBERS DESIGNED BY A. CARROLL CHECKED BY A. CARROLL SCALE 1 "=40' U i U I --I z z z~a J O J U a 2 �z O H Z Q 0 Ld U m °C LU (D z W V / O 0. 30B NO. 36810 SHEET NO. C4.0 -0 a- 0 O O °Z N 0 � 2 02 c T� E� ,_ O N d o ZN O aNi 2 a 75; x o Y CD 0 o_ w o .3 0 > E .- Y N M 7 N X !_ N O O U 2 eN (6 = N o E U O O U O N O M ._ O U -0 2 N O � O Q� U� _E ALAMANCE COUNTY, NORTH CARGL#NA (Shwa -f 16) z'r r v � r 'S�" '� � i• IA ,�- �, 'r. Td4R � gym`? +Ga �;, i' _ '-k'''•-' r *s ^s . r.,.. r..,:.. -: ,+R �,, t .�� ,... ,_ � ...�' r -��{' .r:, ,,. , f', •x' �#�!' !: �, ,mow' i7 c' ` i�f'" ''•fit '?� � ,t � F F. -: �,,i » ._..s""' � ,: � k ��� °? - Fp. Naf�, � , '`�aH2 �` tet'„ a• � yarn °�•'' ^�, ,� �+� ,,>�' �''a ;' 4t y . . j i q, �x ho '',. $i i,.. ,; •.! w•�' '. � ''L..,,: ..+y+'t.1 •.:. .r =ry,+�r .. ' : ., ` / '� A k - ,.- S I'A _ - Y `'I '�%;`14':. �,s .•:.� n� v 1 t , `sxr II SfF f4 r 4 Ni k - v IN Y rY r ,-. �, Ka.,^ ,.,_ � �, x - �' ,,�•`f it fi;. ,:•.e - � +� `,g� 4t �y il; i r -fir %,., ., i., a' �• � � � �:r a '6 lQl V •i�RfTJ'. -, • r"f'. k Y: .:ba ,'�. ,.: �. ,• .b , .'. . gyp ,.-. •: -:::' "� �' � 1 .. ...r - �-- . - `. •...,• r. >: � -'- s - � c •, p•. s y .t .. `tom s a., -..J- _ r x ", � -';�< `».rw' ... � S � � +gym,, �, �. _y,.,� f '-e:.: +' �.,:', r :� :�a `i•° -^r .. - r JJ, m r V } � r '.t^�`�,:� i*.c,'' a`a$�,''+.�': r r', #t!#i 't':a. -r^.;' ��' �iat7> :rr61 �. •$ �� 3 'x } � :.; 4x •- �� :'4 :444- '.:',. .. .. ,. .:, :.. {,� •*- 1� 4�. j ALA "tank , � ::N � ter. .�f ,..x • �bC.T3 ��'3- y' 'Y 'r� . vy t i v- r i +•Sf' �' x ,�*. . {t'B1 "�4i v ., d' S� �f a N � � . � �.... m - , xO i, „�''.. ", ik' < y,-; ♦ «- :,. ,- a.. `fir ,,_ t�ldB ,. x ;. _. ,, .d� p: tt u y +� P• T 73 < + - ' .. '.. �r .r .p, S �*.. ,�. .,�( -..�.. F , •, �+� .. r{' r. ate' ,,� ,,,C' •f, y ' Y. .. .. �`.: ' � •-.� �''y. ��4 '+ ^r'.� S', •` fir a J , r. F- y r 9 ��q : , ,i 4 r ig Fr. V , , • r, _• �a r. - �� fr�''' :�' i . �" r• �fl iii I, xs,. � ''t`, `,,� . . i J- � "Y ."' -: ✓i� -^ cam' 4 '�� W rIv a n J t113, �L ! �"{�}+ #� .+f1Vi 9 4 k �^ � .�+-- A ,.✓4 ..� r I: 9p '-,Y �� f 'tlt _ 6 � . t _ � r � '!� a• y .� Y.�` .v^�'''"�'+ t� J§ J _.'`Y�'+.R s.. � ., . � � �, A ,. �.. . rr.. r - ':p b J� rw J�< r},. � • + '�,l 5 d R;. f �'tel- � 5 ..f :r. .e 5"i ri96 i» Y 1j'dR'- 'dUP` ✓/ fat i t .�. !+ ,f,r s " i • r �. r . v �, bt , r � • ,r _ ,iu"rai•' -f. ., IIIY"""�,,, Illi+.. i:{, ,.. =i r .�,•,�. +.M N. :.fir''„ a �F 5€DID 'R3: