HomeMy WebLinkAbout20220293 Ver 2_Compliance Action Plan_BrittandHalesROY COOPER
Governor
ELIZABETH S. BISER
Secretary
RICHAM E. ROGERS, JR.
Director
\f Qunri Na j
NORTH CAROLINA
Environmental Quality
DATE: April 22, 2024
TO:
FROM:
THROUGH:
Michael Beinenson
Eco Terra, LLC
Katie Merritt
Nutrient Offset & Buffer Banking Coordinator
Stephanie Goss
Supervisor — 401 & Buffer Permitting Branch
SUBJECT: Compliance Action Plan Agreement between DWR and Eco Terra, LLC to address
non-compliance with the Joshua Creek Mitigation Banking Instrument and corresponding Bank
Parcel Development Package and the Britt & Hales Mitigation Banking Instrument and
corresponding Bank Parcel Development Package
COMPLIANCE ACTION PLAN FOR ECO TERRA, LLC
In 2023, Eco Terra, LLC (Eco Terra) submitted two draft Mitigation Banking Instruments (MBI) for
two proposed bank parcels known as the Britt & Hales Mitigation Bank Parcel (Britt & Hales) and
the Joshua Creek Mitigation Bank Parcel (Joshua Creek), identifying as the "Bank Sponsor" to the
Division of Water Resources (DWR) for their review and approval. Additionally, the DWR received
two separate draft Bank Parcel Development Packages (Plans) for Britt & Hales and Joshua Creek
from Eco Terra.
Prior to receiving approvals for the two MBI documents and the two Plans, the DWR discovered that
Eco Terra had implemented all mitigation activities on the two bank parcels, which included planting
trees, installing easement boundaries, performing culvert maintenance, installing monitoring plots
and applying seeding. All activities were described in detail within the draft Plans, which had yet to
be approved in writing by the DWR but had been placed on Public Notice and made available for
public commenting. The public notice, which was agreed to by Eco Terra in the two draft MBI
documents, had not concluded at the time Eco Terra had performed these activities.
On May 4, 2023, Katie Merritt with the DWR, notified Eco Terra via email, of non-compliance.
This non-compliance was primarily associated with planting and constructing two nutrient offset and
buffer mitigation projects specifically to generate nutrient offset credits and/or riparian buffer credits,
without first having approvals of a Mitigation Banking Instrument (per 15A NCAC 02B .0703 and
North Carolina Department of Environmental Quality! Division of Water Resources
4NORT�HCv 512 North Salisbury Street 1 1611 Mail Service Center I Raleigh, North Carolina 27699-1611
NoarrionaouNa a 919.707.9000
Department ofEnvlronmantal Ouali�
Compliance Action Plan
Eco Terra, LLC
April 22, 2024
15A NCAC 02B .0295) or approved Plan. Copies of that correspondence for both projects are
attached as Exhibit A.
DWR staff has developed this Compliance Action Plan to provide a course of action for Eco Terra to
resolve the non-compliance noted in the correspondence dated May 4, 2023. The CAP is provided
in two parts, Part 1 and Part II, as described below and is to begin on the date signed by the last party
on page 3.
Part I: Site Inspection Plan - Adjusted timelines for inspecting future bank site projects submitted
to DWR by Eco Terra for purposes of generating nutrient offset and buffer mitigation credits. The
Site Inspection Plan will expire within one (1) calendar year of the last parry's signature.
Justification: Item A of Section V of the Joshua Creek MBI and Britt and Hales MBI reads as
follows, "The Bank Parcel Development Package submitted under this Instrument shall be submitted
to DWR for review and must be approved by DWR prior to any construction on the Bank Parcel".
Item C of Section V reads, `Any restoration activities or proposed construction within streams,
riparian buffers and other riparian areas on the Bank Parcel to produce Riparian Buffer Credit
and/or Nutrient Offset Credit must be approved by DWR in writing prior to implementation.
A. Extend timeframes for Site Viability Requests by 2-3 months. Completed in 2023
a. DWR staff postponed site visits for five (5) pre -scheduled site viability request
evaluations by 2-3 months in the Summer of 2023. Thus, delaying Eco Terra
from receiving a Site Viability Letter for potential banks by at least 5-8 months
from receipt of request.
B. Require two separate, self -evaluating site inspections for proposed bank sites prior to
issuing approvals.
a. Within 5 calendar days from when DWR posts a Final Draft Plan on public notice
for public commenting, Eco Terra is to submit sufficient, time -stamped photos
documenting current land -use conditions within the riparian areas adjacent to all
water conveyance features proposed in the Plan. Photos must be labeled, include
the timestamp and a description of where the photo was taken. A supporting
map/figure that shows where the Photo Point was taken must also be included.
Photos must adequately represent the width of the riparian areas being proposed
in the Final Draft Plan (0-200' where applicable).
b. Prior to issuing a Plan Approval letter, which usually occurs within 7 business
days after the public comment period has ended, Eco Terra will be required to
submit more timestamped photos at the same locations as where the photos were
taken for "Item a" above and submitted in the same format. Photos should be
documenting the existing land -use conditions and easily compared to the photos
that were taken for Item a. If DWR can confirm that no site work, planting, or
other activities related to site preparation and riparian restoration have begun,
DWR will issue a Plan Approval letter.
C. The public commenting period for Final Draft Plans and Mitigation Banking Instruments
is 15 calendar days for providers. However, Eco Terra will be held to an extended public
comment period of 20 calendar days.
Page 2 of 6
Compliance Action Plan
Eco Terra, LLC
April 22, 2024
Part II: Modified Credit Release Schedule - Table 3.0 within the Britt & Hales MBI and the
Joshua Creek MBI will be modified from what was originally agreed upon between DWR and Eco
Terra
Justification: Item A of Section VIII of the Joshua Creek MBI and Britt and Hales MBI reads as
follows, `DWR may modem Credit Release Schedules based on the information submitted or the order
in which required information is received. DWR will notes the Sponsor of any modification to the
credit release schedule ".
A. Extend the 9 required Tasks to 10 required Tasks.
a. No credits are released for the approval of a Year 1 Monitoring Report
b. The sites will be monitored for 6 years instead of 5, depending on compliance
status.
B. The percentage of credits being released are adjusted based on the following new credit
release schedule:
Page 3 of 6
Compliance Action Plan
Eco Terra, LLC
April 22, 2024
Modified Table 3.0 Credit Release Schedule for the Britt & Hales Mitigation Banking Instrument & the Joshua Creek Mitigation
Banking Instrument with Eco Terra, LLC
Credit Release Schedule for Riparian Buffer and Nutrient Offset Credits for Britt & Hales Bank Parcel & Joshua Creek Bank Parcel
% Credit
Available
DWR Comments & Justification for
Task
Project Milestone
for Sale
changes to credit release
Instrument and BPDP Approved by DWR, Conservation Easement
1
Recorded*, and Financial Assurance Posted
20
Task 2 & Task 3, which are both
All mitigation activities, including Riparian Earthwork, Planting and Installation
affiliated with planting the site
of Monitoring Devices Completed, Easement Boundaries adequately marked,
according to the approved BPDP &
and all applicable permits obtained. A site visit by DWR is required for this
MBI that were placed on public notice,
2
task.
10
are proposed at Half the credits from
what is typically released for these two
Monitoring Financial Assurance Posted and Approval of As -Built
tasks.
3
Report
5
Monitoring for credit release delayed by
Monitoring Report #1: Approved by the DWR** & financial assurance
1 year to allow DWR to oversee Eco
renewed; a site visit by DWR has been conducted
Terra's compliance status with other
Fall 2023
projects (resulting in 1 trial year)
4
0
Rewarding w/ 5% more than the
average 10% to encourage Eco Terra to
Monitoring Report #2: Approved by the DWR** & financial assurance renewed
make good faith effort on CAP through
5
Fall 2024
15
first monitoring report submittal
Rewarding w/ 10% more than the
average 10% to encourage Eco Terra to
Monitoring Report #3: Approved by the DWR** & financial assurance renewed
make good faith effort on CAP through
6
Fall 2025
20
first monitoring report submittal
Item B (1) of Section X in this Instrument has been completed and
F
7
approved by DWR
5
No remaining credits will be released until Task 7 has been satisfied, assigning the conversation easement to an approved land trust or
long-term steward
Normal release is 10% for credit
Monitoring Report #4: Approved by the DWR** & financial assurance renewed
releases not affiliated with a CAP.
Fall 2026
EcoTerra will receive the average
8
10
release for monitoring report approval
Monitoring Report #5: Approved by the DWR** & financial assurance renewed
Adding an option for early closeout to
Fall 2027- DWR may consider an early closeout for Task 10 at Task 9 if all
be assessed by DWR if earned and if
following conditions are met: consistent successful vegetation conditions site
site meets expectations.
wide (vigor, height, density, diversity), no history of unresolved easement
encroachments, no substantial stem mortality or substantial supplemental
planting needed during years 1-5, Sponsor is not affiliated with a compliance
action plan by DWR for other bank sites (excluding Britt & Hales and Joshua
Creek) and Sponsor has managed and maintained the easement boundary and
vegetation in a responsible manner according to the expectations in the
approved BPDP during years 0-5. A site visit by DWR is required to be
9
performed for a 15% release
5 or 15
Monitoring Report #6: Approved by the DWR** and final site visit by DWR
10
has been performed. No Task 10 if DWR issued 15% for Task 9
10 or -0-
Total
100%
*For specification, please see Section V in this Instrument
**DWR Approval provided upon a determination that the site is meeting performance standards contained within the approved BPDP
Note: This credit release schedule is defined as Part II of the Compliance Action Plan (CAP)
Page 4 of 6
Compliance Action Plan
Eco Terra, LLC
April 22, 2024
ECO TERRA, LLC
(Print)
(Signature)
Title:
Date:
NORTH CAROLINA DEPARTMENT OF ENVIRONMENTAL QUALITY - DIVISION OF WATER
RESOURCES
Stephanie Goss
By: (Print)
(Signature)
Title: 401 & Buffer Permitting Branch Supervisor
Date: 4/23/24
Page 5 of 6
Compliance Action Plan
Eco Terra, LLC
April 22, 2024
EXHIBIT A - DWR CORRESPONDENCE
Page 6 of 6
From: Merritt, Katie
Sent: Thursday, May 4, 2023 3:43 PM
To: michael@ecoterra.com
Cc: Jordan Burbage <jordan@ecoterra.com>; Hartshorn, Blake <blake.hartshorn@ncdenr.gov>;
Goss, Stephanie <stephanie.goss@ncdenr.gov>; Norton Webster <norton@ecoterra.com>
Subject: Notification of Non -Compliance - Britt & Hales MBI/BPDP
Good Afternoon Michael,
DWR received the attached documentation from McAdams notifying DWR that the Britt & Hales site
was fully planted and ready for DWR to assess site conditions for the Task 2 milestone according to
the MBI. According to the attached notification letter, Eco Terra planted this site March 30, 2023 &
April 1, 2023. The Bank Parcel Development Package (BPDP) was approved on April 21, 2023 and
the Mitigation Banking Instrument (MBI) was signed by Eco Terra on March 31, 2023 and DWR on
April 21, 2023.
Eco Terra did not have an approved Banking Instrument (required under 15A NCAC 02B .0295 and
15A NCAC 02B .0703), nor did they have an approved BPDP for the site (required under 15A NCAC
02B .0295 and 15A NCAC 02B .0703) prior to conducting activities for buffer mitigation and nutrient
offset credits. Both rules referenced above clearly state that an approved plan by DWR is required
prior to conducting activities for buffer mitigation or nutrient offset credits. Secondly, Eco Terra
submitted an MBI and BPDP to DWR that contained inaccurate and falsified information.
Eco Terra is in non-compliance with 15A NCAC 02B .0295
Eco Terra is in non-compliance with 15A NCAC 02B .0703
Eco Terra is in non-compliance with the Approved Britt & Hales BPDP - submitted to DWR by Eco
Terra on March 29, 2023, public noticed on March 31 and approved by DWR on April 21
Eco Tera is in non-compliance with the Approved Britt & Hales MBI — submitted to DWR by Eco Terra
on March 31, 2023, public noticed on March 31 and approved on April 21.
At this time, DWR will not be able to proceed with the issuance of credit releases for the proposed
buffer mitigation credits and proposed nutrient offset credits until these matters have been
discussed. DWR will discuss the non-compliance issues with Eco Terra and DWR management in the
near future prior to determining further actions needed.
Thank you for your attention to this matter,
Katie
Katie Merritt
Nutrient Offset & Buffer Banking Coordinator
401 & Buffer Permitting Unit
North Carolina Department of Environmental Quality
Office: 919-707-3637
Work Cell: 919-500-0683
Website: https://deq.nc.gov/about/divisions/water-resources/water-quality_permitting/401-buffer-
permitting-branch
512 N. Salisbury Street, Raleigh, NC 27620
1617 Mail Service Center, Raleigh, NC 27699-1617
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Merritt, Katie
Sent: Thursday, May 4, 2023 3:42 PM
To: michael@ecoterra.com
Cc: Jordan Burbage <jordan@ecoterra.com>; Hartshorn, Blake <blake.hartshorn@ncdenr.gov>;
Goss, Stephanie <stephanie.goss@ncdenr.gov>; Norton Webster <norton@ecoterra.com>
Subject: Notification of Non -Compliance - Joshua Creek MBI/BPDP
Good Afternoon Jordan,
DWR received the attached documentation from McAdams notifying DWR that the Joshua Creek site
was fully planted and ready for DWR to assess site conditions for the Task 2 milestone according to
the MBI. According to the attached notification letter, Eco Terra planted this site March 27, 2023 &
March 28, 2023. The Bank Parcel Development Package (BPDP) was approved on April 21, 2023 and
the Mitigation Banking Instrument (MBI) was signed by Eco Terra on March 31, 2023 and DWR on
April 21, 2023.
Eco Terra did not have an approved Banking Instrument (required under 15A NCAC 02B .0295 and
15A NCAC 02B .0703), nor did they have an approved BPDP for the site (required under 15A NCAC
02B .0295 and 15A NCAC 02B .0703) prior to conducting activities for buffer mitigation and nutrient
offset credits. Both rules referenced above clearly state that an approved plan by DWR is required
prior to conducting activities for buffer mitigation or nutrient offset credits. Secondly, Eco Terra
submitted an MBI and BPDP to DWR that contained inaccurate and falsified information.
Eco Terra is in non-compliance with 15A NCAC 02B .0295
Eco Terra is in non-compliance with 15A NCAC 02B .0703
Eco Terra is in non-compliance with the Approved Joshua Creek BPDP - submitted to DWR by Eco
Terra on March 30, 2023, public noticed on March 31 and approved by DWR on April 21
Eco Tera is in non-compliance with the Approved Joshua Creek MBI — submitted to DWR by Eco
Terra on March 31, 2023, public noticed on March 31 and approved on April 21.
At this time, DWR will not be able to proceed with the issuance of credit releases for the proposed
buffer mitigation credits and proposed nutrient offset credits until these matters have been
discussed. DWR will discuss the non-compliance issues with Eco Terra and DWR management in the
near future prior to determining further actions needed.
Thank you for your attention to this matter,
Katie
Katie Merritt
Nutrient Offset & Buffer Banking Coordinator
401 & Buffer Permitting Unit
North Carolina Department of Environmental Quality
Office: 919-707-3637
Work Cell: 919-500-0683
Website: https://deq.nc.gov/about/divisions/water-resources/water-quality_permitting/401-buffer-
permitting-branch
512 N. Salisbury Street, Raleigh, NC 27620
1617 Mail Service Center, Raleigh, NC 27699-1617
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.