HomeMy WebLinkAbout_External_ RE_ SAW-2024-00365 Clarke Creek Greenway Phase A_ Request for Additional InformationCarpenter, Kristi
From: Fox, Doug <Doug.Fox@kimley-horn.com>
Sent: Tuesday, April 9, 2024 6:35 PM
To: Lipsky, Amber L CIV USARMY CESAW (USA); Plummer, Mary B
Cc: Kiker, Taylor; Tinklenberg, Chris
Subject: [External] RE: SAW-2024-00365 Clarke Creek Greenway Phase A: Request for
Additional Information
Attachments: 01_Clarke Creek -Response to USACE Comments.pdf
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
Good afternoon Amber and Mary,
Attached is our response to your request for additional information. Unfortunately, the supporting documents are too
large to be included in this email. Could you please provide a DOD Safe Link that we can upload them to? Additionally, if
any further questions arise from our responses, we are happy to set up a call to discuss them or provide additional
documentation. Thank you for your patience!
Best,
Doug Fox
Kimley-Horn 1 580 Kingsley Park Dr. Suite 125, Fort Mill, SC, 29715
Direct: 1 (803)-881-3371 1 Mobile: (828) 448-5656
Celebrating 17 years as one of FORTUNE's 100 Best Companies to Work For
The electronic files ("Files") furnished by Kim ley -Horn to the intended receiver ofthe Files ("Receiving Party") are provided only for the convenience of Receiving
Party and only for its sole use. Receiving Party agrees that it shall be bound by and subject to the terms of this notice.
For any signed and sealed plans or final deliverables, if there are discrepancies between the Files and the hardcopy of the Files prepared by Kim ley -Horn, the
hardcopy shall govern. Only printed copies of such documents conveyed by Kimley-Horn may be relied upon.
Any use of these electronic Files will beat the Receiving Party's sole risk. Receiving Party accepts the Files on an "as is" basis with all faults.
From: Lipsky, Amber L CIV USARMY CESAW (USA) <Amber.L.Lipsky@usace.army.miI>
Sent: Monday, April 8, 2024 7:13 AM
To: Kiker, Taylor <Taylor.Kiker@kimley-horn.com>; Plummer, Mary B <mary.plummer@deq.nc.gov>
Cc: Fox, Doug <Doug.Fox@kimley-horn.com>; Tinklenberg, Chris <Chris.Tinklenberg@kimley-horn.com>
Subject: RE: SAW-2024-00365 Clarke Creek Greenway Phase A: Request for Additional Information
Taylor,
I am okay with that.
Hope you had a nice weekend,
Amber
From: Kiker, Taylor <Taylor.Kiker@kimley-horn.com>
Sent: Friday, April 5, 2024 3:33 PM
To: Lipsky, Amber L CIV USARMY CESAW (USA)<Amber.L.Lipsky@usace.army.mil>; Plummer, Mary B
<mary.plummer@deg.nc.gov>
Cc: Fox, Doug <Doug.Fox@kimley-horn.com>; Tinklenberg, Chris <Chris.Tinklenberg@kimley-horn.com>
Subject: [Non-DoD Source] RE: SAW-2024-00365 Clarke Creek Greenway Phase A: Request for Additional Information
Amber and Mary,
We have responded to 95% of your comments. We are finalizing a couple of comments with our engineers, however,
some have been away due to spring break. May we have an extension until Tuesday, April 91h? We would greatly
appreciate it.
Let us know, thank you!
Taylor (she/her/hers)
Taylor Kiker, PWS
Kimley-Horn 1200 South Tryon Street, Suite 200, Charlotte, NC 28202
Direct: 980 296 0810 1 Mobile: 704 562 9381
From: Lipsky, Amber L CIV USARMY CESAW (USA) <Amber.L.Lipsky@usace.army.mil>
Sent: Thursday, March 7, 2024 3:19 PM
To: Kiker, Taylor <Taylor.Kiker@kimley-horn.com>
Cc: Fox, Doug <Doug.Fox@kimley-horn.com>
Subject: RE: SAW-2024-00365 Clarke Creek Greenway Phase A: Request for Additional Information
Some people who received this message don't often get email from amber.l.lipsky@usace.army.mil. Learn why this is important
Good afternoon,
I have completed my review of the above referenced application and have the following questions/comments. Please
provide one consolidated response. If you have any questions, let me know.
General:
1. Could you please provide the T&E report that was sent to USFWS?
2. The Corps believes this project is more appropriate to verify under NWP 42.
a. Can you confirm discharges at this location will comply with part "C. Regional Conditions Applicable to
NWP 42" (i.e. will not result in above -grade fills that will result in an increased water surface elevation)?
If they do, a "no -rise" certification from FEMA should not be necessary.
3. Please provide revised impact sheets where the area of grading/fill within wetlands is visually depicted on the
plan sheet and profile. Using colors can be helpful for this. There's a lot of linework making it difficult to see
impacts clearly.
4. Per the notation on the Wetland Data Sheets, please include a site map showing the sampling point locations.
Please also include the location of the enclosed photos on the map. We're starting to request that a figure like
this be included in all JD requests.
Regarding impacts proposed under NWP 14:
5. On some sheets, a Temporary Construction Easement (TCE) is within a wetland. Are temporary impacts
anticipated in these area?
6. Can you confirm the boardwalks will be elevated at least 3 feet to allow for high flow events?
7. Can you elaborate on the purpose and need for wetland fill/grading for Wetland Impacts 1, 3 and 4? Why can
boardwalks not be used, or the limits of disturbance be shifted slightly, to avoid impacts to these areas?
a. For example, Wetland Impact 3 shows impacts due to grading. Why does the fill line 'jut out' in these
areas causing the impacts? Could you provide an additional plan view sheet showing the grading details
with the existing wetland/grades and subsequent grading areas clearly depicted?
8. Regarding Wetland Impacts 5 and 6- Mechanized clearing, including the stumping of trees to facilitate the noted
topsoil removal, is considered a permanent conversion impact.
i. Why is the clearing area so extensive for Wetland Impact 5?
ii. Please note since this would be considered a permanent impact, you would exceed the
mitigation threshold for this project and the Corps will require evidence of mitigation credit
availability for this project. Conversion impacts can be mitigated for at a 1:1 ratio.
9. Do the swale bridge details outlined on Sheet C-7.0 correspond to the bridges shown on sheet C-4.10 and C-
4.15? If so, the concrete footers and associated temporary shoring need to be accounted for in the wetland
impacts. Otherwise, please provide bridge details for the bridges with footers in wetlands.
Regarding impacts proposed under NWP 13:
10. Are proposed impacts within a riffle/pool complex?
11. Is the proposed discharge greater than an average of one cubic yard per running foot below the OHWM?
a. To process this under the NWP 42, please provide the acreage of impacts below the OHWM due to
these activities.
12. On Sheet C-4.10, does the 58 LF of bank stabilization refer to both sides of the bank? The arrow on the plan view
only points to one side, but stream grading is called out on both sides of the profile view. Should the profile view
call out on the right be for wetland grading? The riprap fill is also not depicted, only grading. Could you provide
a profile view that includes where the rip rap is being placed and indicates the wetland fill/grading impacts as
well?
Thank you,
Amber
From: Fox, Doug <Doug.Fox@kimley-horn.com>
Sent: Wednesday, March 6, 2024 12:19 PM
To: Lipsky, Amber L CIV USARMY CESAW (USA) <Amber.L.Lipsky@usace.army.mil>
Cc: Kiker, Taylor <Taylor.Kiker@kimley-horn.com>
Subject: [Non-DoD Source] RE: SAW-2024-00365 Clarke Creek Greenway Phase A: Request for Additional Information
Hey Amber,
This shapefile shouldn't have any fill within the project boundary. Let me know if you need anything else!
Best,
Doug Fox
Kimley-Horn 1 580 Kingsley Park Dr. Suite 125, Fort Mill, SC, 29715
Direct: 1 (803)-881-3371 1 Mobile: (828) 448-5656
Celebrating 16 years as one of FORTUNE's 100 Best Companies to Work For
The electronic files ("Files") furnished by Kim ley -Horn to the intended receiver ofthe Files ("Receiving Party") are provided only for the convenience of Receiving
Party and only for its sole use. Receiving Party agrees that it shall be bound by and subject to the terms of this notice.
For any signed and sealed plans or final deliverables, if there are discrepancies between the Files and the hardcopy of the Files prepared by Kim ley -Horn, the
hardcopy shall govern. Only printed copies of such documents conveyed by Kimley-Horn may be relied upon.
Any use of these electronic Files will beat the Receiving Party's sole risk. Receiving Party accepts the Files on an "as is" basis with all faults.
From: Lipsky, Amber L CIV USARMY CESAW (USA) <Amber.L.Lipsky@usace.army.mil>
Sent: Wednesday, March 6, 2024 11:46 AM
To: Fox, Doug <Doug.Fox@kimley-horn.com>
Cc: Kiker, Taylor <Taylor.Kiker@kimley-horn.com>
Subject: RE: SAW-2024-00365 Clarke Creek Greenway Phase A: Request for Additional Information
Hi Doug,
Is it possible to give me a file that doesn't have the "fill"? Pic below for reference
AC 4
f
t �►'
J
. - k4
i 74%
Thanks!
From: Fox, Doug <Doug.Fox@kimley-horn.com>
Sent: Wednesday, March 6, 2024 11:39 AM
To: Lipsky, Amber L CIV USARMY CESAW (USA) <Amber.L.Lipsky@usace.army.mil>
Cc: Kiker, Taylor <Taylor.Kiker@kimley-horn.com>
Subject: [Non-DoD Source] RE: SAW-2024-00365 Clarke Creek Greenway Phase A: Request for Additional Information
Good morning Amber,
4
Attached is a zipped shapefile of the project area. Please let us know if you need anything else!
Best,
Doug Fox
Kimley-Horn 1 580 Kingsley Park Dr. Suite 125, Fort Mill, SC, 29715
Direct: 1 (803)-881-3371 1 Mobile: (828) 448-5656
Celebrating 16 years as one of FORTUNE's 100 Best Companies to Work For
The electronic files ("Files") furnished by Kim ley -Horn to the intended receiver ofthe Files ("Receiving Party") are provided only for the convenience of Receiving
Party and only for its sole use. Receiving Party agrees that it shall be bound by and subject to the terms of this notice.
For any signed and sealed plans or final deliverables, if there are discrepancies between the Files and the hardcopy of the Files prepared by Kim ley -Horn, the
hardcopy shall govern. Only printed copies of such documents conveyed by Kimley-Horn may be relied upon.
Any use of these electronic Files will beat the Receiving Party's sole risk. Receiving Party accepts the Files on an "as is" basis with all faults.
From: Lipsky, Amber L CIV USARMY CESAW (USA) <Amber.L.Lipsky@usace.army.mil>
Sent: Wednesday, March 6, 2024 11:01 AM
To: Kiker, Taylor <Taylor.Kiker@kimley-horn.com>
Subject: SAW-2024-00365 Clarke Creek Greenway Phase A: Request for Additional Information
Good morning Taylor,
Could you please provide a shapefile of the project area? Since this is a long, linear project having one will help
streamline my review.
Thanks,
Amber Lipsky (she/her)
Regulatory Specialist, Charlotte Regulatory Field Office
U.S. Army Corps of Engineers, Wilmington District
8430 University Executive Park Drive, Suite 615
Charlotte, NC 28262
Email: Amber.L.Lipsky@usace.army.mil
Office: (704)510-1441
Mobile: (704)962-6947