Town of Black Mountain
Pre -Construction Meeting Minutes
April 10, 2024, 1:00 PM — 2:30 PM
MEETING MINUTES
• Attendees list attached.
• Introductions, representation and responsibilities
o Define Representation
■ Contractor to direct the public to Angela Reece.
• Decorum of construction site
o Illegal for firearms, alcohol, or illegal drugs
• Schedule and Progress Meetings
o Notice to Proceed: May 13, 2024
o All grading and stabilization shall be completed within 60 calendar days by July 12,
2024
o Planting shall be completed by Dec 31, 2024. Substantial completion will not be
granted until all plantings have been installed
o Construction Signs will be provided by the Town.
o Working Hours (park is open sunrise to sunset)
o Contractor to provide and maintain a detailed schedule.
■ Contractor expects the grading/stabilization to take 5 weeks.
o There will be bi-weekly progress meetings. The first meeting is anticipated to be
scheduled for the week of May 27, 2024.
o Weather delays, rain gage, and daily logs
■ Contractor to log rain impact days and provide with pay applications
■ Contractor to maintain all required NPDES inspections and forms
■ Contract days will be changed (if needed) at end of contract through one
change order
• Special Requirements
o Contractor is responsible for all damages on the property.
o Contractor to maintain record drawings, documenting any changes in work.
o Working in the wet is limited to the 1-40 ROW only.
■ NCDOT requested to be notified prior to the work taking place so that they
can have a representative onsite during the work.
These comments were prepared by Kimley-Horn and Associates with the intent to capture the main body of discussion with supporting facts and results from
the subject meeting. Should your recollection of the events and discussion of this meeting differ, please forward your revisions and/or additions to Jason Diaz
[Jason.Diaz@Kimley-Horn.com] so that he may amend and/or modify this summary to be more accurate.
Veterans Park Stream Repair Project
Town of Black Mountain
Pre -Construction Meeting Minutes
April 10, 2024, 1:00 PM — 2:30 PM
o Wood structures shall be installed within 72 hours of being cut. Dead or brittle
wood will not be accepted.
o Stockpile topsoil and spread 1.5" over zones A and B.
o Montreat College — Contractor to coordinate with Tommy Hendrix prior to using the
construction entrance and if there are excess spoils.
o Hellbender — relocate if encountered.
■ WRC staff showed the contractor the desired relocation area upstream of 1-
40. WRC staff mentioned that they do not need to perform a pre -
construction survey.
o Protect exiting greenway and include personnel to supervise the crossing.
o The Town will coordinate gates/locks prior to mobilization.
o Contractor to be mindful of clearing trees with potential bat habitat and will
coordinate with the appropriate agencies if potential habitat is noted.
o WRC requested that the temporary stream crossing be located just upstream of the
existing riffle to avoid disturbance to the existing rock in the channel.
o Contractor to install safety fence along the restored stream bank in Site 1 after work
is completed. The fence will remain in place until after the planting is completed.
• Change Condition (change orders)
o Must be in writing
o Contingency will only be used for approved change orders
• Progress Payments
o Contractor to submit Application for Payment
■ Include MBE and sales tax data
o Consultant will review within 7 days
■ Due to the project schedule it is anticipated that there will be one
application for payment at the end of the grading.
These comments were prepared by Kimley-Horn and Associates with the intent to capture the main body of discussion with supporting facts and results from
the subject meeting. Should your recollection of the events and discussion of this meeting differ, please forward your revisions and/or additions to Jason Diaz
[Jason.Diaz@Kimley-Horn.com] so that he may amend and/or modify this summary to be more accurate.
Veterans Park Stream Repair Project
Town of Black Mountain
Pre -Construction Meeting -April 10, 2024 @ 1:00 - 2:30 pm
Attendees List
NAME
COMPANY
PHONE
EMAIL
Andrew Moore
DWR
828-296-4684
Andrew.Moore@deg.nc.gov
Matthew Azurite
RES
502-229-4123
mazurite@res.us
Angela Reece
Town of Black Mountain
8238-419-9315
Angela.Reece@tobm.org
Andrea Leslie
NC WRC
828-400-4223
Andrea.Leslie@ncwildlife.org
Anne Phillip
Town of Black Mountain
828-419-9374
Anne. Phillip@tobm.org
Mitchell Anderson
USACE
Mitchell.L.Anderson@usace.army.mil
Jacob Evans
NCDOT Division of Highways
828-250-3207
iwevans4@ncdot.gov
Jason Claudio -Diaz
Kimley-Horn and Associates, Inc.
704-954-7464
Jason.Diaz@kimley-horn.com