HomeMy WebLinkAbout20240175 Ver 1_Add Info Recvd_20240312Homer, Seren M From: David Brown <david@jenningsenv.com> Sent: Tuesday, March 12, 2024 5:27 PM To: Fuemmeler, Amanda J CIV USARMY CESAW (USA) Cc: Homer, Seren M; Zan Price Subject: [External] Re: Mouth of Hardin Creek Restoration Queston/Comment Attachments: Revised Sheet 2.3 and 2.4 Mouth of Hardin Creek Permit Drawing Revised March 12..pdf CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message button located on your Outlook menu bar on the Home tab. Amanda, Sorry for the delay in responding to your comment. Attached are revised plan sheets 2.3 & 2.4 which show the stormwater outfalls you noted. On the revised sheets these outfalls flow into a floodplain depression & are no longer a ditched feature. This is similar to what we constructed on Holly Branch at the Mayland Community College site. This revision does not change proposed impacts to streams & wetlands. Let me know if you have questions or additional comments. Thanks, David David Brown, PG Sr. Geologist, Environmental Services Leader I Jennings Environmental, PLLC 828384 1890 david@jenningsenv.com iAsheville, NC 'enningseny.com 0 im This information is confidential and is intended solely for use by the recipient and others authorized to receive it. Any disclosure, copying, distribution or taking action in relation to this information is strictly prohibited and may be unlawful. From: Fuemmeler, Amanda J CIV USARMY CESAW (USA) <Ama nda.Jones@usace. army. mit> Date: Friday, March 1, 2024 at 2:25 PM To: David Brown <david@jenningsenv.com> Subject: Mouth of Hardin Creek Restoration Queston/Comment Mr. Brown, Hope all is well. Just looking through the PCN and noticed the plan sheet with the stormwater outfalls (attached). Any way to incorporate having the wetlands/flood plain out there be able to treat/dissipate this versus what is being proposed as a ditch draining directly to the creek. I'm assuming the current conditions is just that so seems like a good opportunity to correct this if possible. Thanks for the consideration! Amanda Jones Project Manager US Army Corps of Engineers Asheville Regulatory Field Office 828-271-7980 ext. 4225 b W co cn Of r z 0 Of r co WIN— 0 A. r, .�Ev. IRW IN\ 7,T ARMOR STORMWATER Uji now e- R Me yft- - �y Mr CONVEYANCE WITH ? to 9M TYP. FLOODPLAIN —: Z7—'Z: " NCDOT CLASS 1 RIPRAP DEPRESSION A !�'Aft 4 ft;� �� \ , —_ -­ ;a W-"- TO, At 0�' 7V =7 -�BB ; i so Ono 0 0 gicHUR-M-ft 0:111111 assum owns - some ON .800 "I monsoon EMMONS ,mono SEEM.. PEI% Samoa as loommomon osmosis M 0 oplaw MIN -ib - LES! :m .�1.0000 100 5*gtommmmmmoffim on museum: a so ME asom SEE no, OEM son On 01 hii mono sm--Eg.m.:. :11:1�;" 10111 osommosonsbl:: Boom MOONS IN s s ........ IS IS 11 0_1 I I is is is in in 1 WIN so a 1100:1:0slimn millogim gis main 0::Inllnll Imemommummom ... Wiliam so molown -6000- :Mason 1­6600 M,,Immsmnmmmmsanm Wiiiialb Soo SEE -------- Not" I A BE :4 is 6+00 3100 4— 3095 3090 3085 KIT-Iff 6+'00 cy) Lq IN cl? cy) cy') (Z) CN M (_0 LU _j 0- LU co CD 0-) CO CD N co co Uj _j a_ Uj 1.19% 00 0.00% 7 00 8+00 9+00 1 +00 1 +100 12 00 I I I 1 11 3100 CN 00 M I- It 1­ 00 00 00 c� U? 7 rl-� IN co IN co T_ I- co T_ M CD LO CD o) 6 00 cl� C6 c? r--: C? r_� (6 M M M M 00 00 00 00 r'_ 00 r_ 00 M 00 00 C) C) C) c) C) CO C) r-_ C) U-) C) C) M C) C) 00 C) M CO U-) co C:) CO Itt co 00 CO n M 0) M + co + CO + co + CO + + r__ > + oo + 00 + 00 + 0') + M C) CD Uj W Uj W Uj W Uj W a_ W a_ W a_ W a_ W a_ W a_ W a_ W a_ LU 0- LU 0- LU 0- LU -2-36 �r, 0 PR.BANKFULL �50 % 0.00 I 0�0 0.00% � �16 -1.995, Z 0 EX. STORMWATER OUTFALL (TYP.) EX. GRO UND PR. THALWEG 0.00 I I I Nt I I I cr) Cy) C) 00 00 00 Lr) Cy) L0 L0 M c\1 a) 00 IN 0� 00 Nt (7) m 00 0? 1- 00 LO r- cq (D 1­ (.0 Lr) C) 00 00 00 00 00 00 00 00 00 00 (0 CD 0c) CD C) I,- C) C) C) (Z) C) C) CO C) P­ CD CD + CO cy) CO LO co + CO C) CO -It co + cy) 0c) cy) cy) co + CO + (D + r'- + 00 + 00 .. 00 > :�; + 00 :�; + cy) .. Cy) > bi i Uj 0- LU _j Uj a_ C) L-U, Uj LU _j Uj a_ LU 6 _j Uj 0- Uj _j Uj bi _j Uj a_ Uj _j LU a_ Uj _j LU bi _j LU 7+00 8+00 9+00 -1.99 0.00% RY : -1 % L.-52 03 No.o"'O%��"'o -0-86% 3095 3090 KIT-W KIT -ore. c\1 LO co T_ LO 00 It oo 00 r'_ c\1 rl- 0') LO IN 0') LO CD 0? 00 Lo . 't CO CO 0� ­t 1,- 00 00 r'_ CID r'_ CID r1_ 00 (0 CO 0-) CID C) C) + C) 0-) C) It C) + C) 00 C) a) CO + co CD CO + CO + co co + CO + 0) C) > > Uj Uj Uj Uj Uj LU LU _j _j _j _j _j _j _j a_ Uj a_ Uj Uj a_ Uj a_ Uj Uj a_ Uj 10+100 11+100 12+100 NU I Lzb: 2 CL N 0 < 1. CONTRACTOR TO IDENTIFY AND PROTECT EX. UTILITIES. z -777-12. f> < ct cn 0� 0 DISTURBANCE OF WETLANDS, z TREES, AND/OR WOODY VEGETATION ED 0 Z 0 Uj SHALL BE KEPT TO MINIMUM EXTENT >_ co �z 0 PRACTICAL TO COMPLETE WORK. W 0 co LU Z 0 co RESTORE ACCESS PATHS AND z co STORAGE AREA(S) TO ORIGINAL CONDITION UPON COMPLETION OF c' W > 0 THE PROJECT OR UPON SUCH TIME AS DIRECTED BY THE PROJECT OWNER AND ENGINEER. ON —SITE ROCK MATERIAL MAY BE REUSED FOR STRUCTURES, AT THE DIRECTION OF THE ENGINEER. CONSTRUCTED RIFFLE CAN BE REPLACED WITH WOODY RIFFLE OR ENHANCED HABITAT RIFFLE, AT THE APPROVAL OF THE ENGINEER. TOE WOOD TO EXTEND 10'INTO DOWNSTREAM RIFFLE BANK. TOE WOOD CAN BE REPLACED WITH ROCK TOE, AT THE APPROVAL OF THE ENGINEER. 7. FLOODPLAIN DEPRESSIONS TO NOT EXCEED 18" BELOW BANKFULL ELEVATION. LOCATION SUBJECT TO CHANGE AT THE DIRECTION OF THE ENGINEER. SHEET INDEX < C) C) z + Z Z -:] CN D L D 0 9r— 0 c) 0 z 0 < C) (D C:) 0 (D 3: z c) + F­­ C/) D < F­­ 0� — �: Qc) Lu 0 < < cf) < Z U) Z LL, z �e LU 0 W 0� LLJ z 0 LU 0� C) LU 0 LLJ 0 z 13� 00 a_ LL 0 C) LL 0 00 I— 0� Z z < z 0 n 7 SAMUEL ASHE DRIVE ASHEVILLE, NC 28805 DATE: 3/12/2024 SCALE (34"X22"): ill = 30' SCALE (1 7"X1 1 "): ill = 60' 0 30 60 SCALE IN FEET PR HARDIN CREEK - SCALE: HOR 1" = 30'; VERT 1" = 3' SHEET NUMBER NOT TO SCALE 2.3 A 7 1> 4, N, -n -S > Q i f r f J, Z' V_ TYP. FLOODPLAIN 4� 4__ I 'I Aw DEPRESSION D(i '_X % Nor 10 VX\ oe N"OV111 '"N SAN SAN lo x i N V, C, SAN SAN 7SA: lip ["%a M Now 4 SAN SAN F\NA\( k, 0 % N ------- J P, C/) /'y' '00""�� \ I I 'x :ol\ F py 'T A FPT A1 v TIE OUT TO SOUTH PT\\ -1 -' '- 11� uy FORK NEW RIVER 0- ro ­7 cy) C14 20 C14 01 GRADE BANKS 4:1 't Jjj C14 CD DOWNSTREAM OF N C4 SEWER CROSSING Y 3\ —.v\ o' I 4/'o TYP. ROCK TOE =3 FP_ MIX OF NCDOT CLASS 1 '70 ------ 1­1 �rp* :PT y ui & CLASS B ROCK TO 0 1101 FWAY ------------- FWAY - BE PACKED AROUND _j Ir \N, A( PIERS IN CHANNEL 411*�\ N TYP. CONSTRUCTED RIFFLE C) s I uj 00 two is m TYP. LOG J-HOOK VANE BOULDER J-HOOK. CHANNEL PR BRIDGE CROSSING. logo imp I f \' � I BED ON RIGHT SIDE TO BE w w mot' cn I SEE SHEET 2.5 _14\ I. I I > TYP. TOE WOOD 0.5'HIGHER THAN LEFT. w Mg ON -16— — -n v to 0') b w co C/) 0� r z r co X_ 121100 13+100 14+100 15+�00 6+100 17+100 co 't 00 9 CIO 't o? 11 CD q Lo co co 11 m G� m Iq 3095 O� co, G� Lo' Lo co co r*-: C_� cq C) CD m 00 m C) "t 00 "t C) (D co co C) CD CO CN C) co co rl_ CD 00 CD co 00 m 0 00 co '�t C) co 00 m CD C) 00 c\1 C) + co + co + co + co + co + co + co + co + co + co CN M co Lo Lo co co I­ LU _j Lu _j LU _j Lu _j uj _j ui _j LU _j ui _j Lu _j ui _j a_ ui a_ ui a_ ui a_ w a_ ui 0- ui a_ Lu a_ Lu a_ ui 0- ui c'? c� co 00 CD 00 + CD co 3090 > ui U) Lu -0-86% —7- 3085 — -.05% PR.BANKFULL Q�o -2.00% 0.00% (b. 0\0 -2.130 Yo 143 �o 1% col�j 3080 0. 00% -2-29% EX. TRAIL CULVERT 131% TO BE REMOVED I PR. THALWEG TYP. LOG J-HOOK VANE 1 1 3075 -- I I EX. GROUND 12+00 CD 00 C) _j a_ ui 7 0 3095 r 3090 SANITARY SEWER LINE SUSPENDED OVER CHANNEL � 3085 3080 3075 Lo co It CN rl- 1­ 00 m rl- co 't N N Lo co r-- r-� N 00 N (D (o o? m cli c� C's cy� c� 06 m co r. 6 CD 00 7 m 00 00 00 r-- co 00 co 00 00 00 4 00 co 00 CD 00 CD 00 co 00 C) r'- 00 co rl- N r'- 00 r'- (D r- CD r- CD r- co CD + CD "T CD co CD + CD N CD r__ CD + CD CD a) 0 + CD -'t CD M CD + CD N CD + m co + co + m M + M + co Lo Co + M + m M + M + M r'_ M + M N 'r__ :�; co co IV- Lo V_ Lo IV- co V_ co '- — > > I- > LU Lu Lu uj Lu uj uj ui ui LU ui ui uj 0 uj uj _j _j _j _j _j _j _j _j IL: _j _j _j _j _j — _j _j 0- Lu Lu 0- Lu 0- Lu Lu 0- Lu 0- Lu Lu a_ Lu 0- Lu Lu a_ Lu a- Lu 2 Lu a- Lu 13+00 14+00 15+00 16+00 17+00 18+00 NOTES: m N < 1. CONTRACTOR TO IDENTIFY AND PROTECT EX. UTILITIES. z 2. 3. f> < ct cn 0� 0 DISTURBANCE OF WETLANDS, z TREES, AND/OR WOODY VEGETATION ED 0 Z 0 ui SHALL BE KEPT TO MINIMUM EXTENT �z 0 PRACTICAL TO COMPLETE WORK. W 0 co Lu Z 0 co RESTORE ACCESS PATHS AND Q) z co STORAGE AREA(S) TO ORIGINAL CONDITION UPON COMPLETION OF c' w > 0 THE PROJECT OR UPON SUCH TIME > w AS DIRECTED BY THE PROJECT OWNER AND ENGINEER. 4. ON -SITE ROCK MATERIAL MAY BE 00 REUSED FOR STRUCTURES, AT THE >_ 1­­_ < z m + DIRECTION OF THE ENGINEER. z z _j r*-_ Ir- o D u o 0 z 5. CONSTRUCTED RIFFLE CAN BE FZ < 1­0 CD REPLACED WITH WOODY RIFFLE OR 0� 0 (D m z C) + ENHANCED HABITAT RIFFLE, AT THE co < APPROVAL OF THE ENGINEER. w Ill- < 0 < < F--- c/) �: co Z 0 6. TOE WOOD TO EXTEND 10'INTO LIJ uj ui Z y uj C) DOWNSTREAM RIFFLE BANK. TOE 0� UJ 0 yj 0� O� WOOD CAN BE REPLACED WITH 0 z ui 0� 0 co ui a_ 0 o u_ ROCK TOE, AT THE APPROVAL OF — 0 u- 0 z I_ 0 THE ENGINEER. < Z Z Z �: < 7. FLOODPLAIN DEPRESSIONS TO NOT 0 EXCEED 18" BELOW BANKFULL ELEVATION. LOCATION SUBJECT TO CHANGE AT THE DIRECTION OF THE ENGINEER. SHEET INDEX 7 SAMUEL ASHE DRIVE ASHEVILLE, NC 28805 DATE: 3/12/2024 SCALE (34"X22"): ill = 30' SCALE (1 7"X1 1 "): ill = 60' 0 30 60 SCALE IN FEET PR HARDIN CREEK - SCALE: HOR 1 " = 30'; VERT 1 " = 3' NOT TO SCALE SHEET NUMBER 2.4