Loading...
HomeMy WebLinkAbout20240269 Ver 1_USACE Provisional Verification_20240403Baker, Caroline D From: Martin, Matthew K CIV (USA) < Matthew.K.Martin@usace.army.mil > Sent: Wednesday, April 3, 2024 3:55 PM To: rrojas@drbgroup.com Cc: dshirley@sandec.com; Thomas, Zachary T Subject: [External] Provisional Verification: SAW-2022-01734 (Weldon Subdivision/ Knightdale, Wake County) CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message button located on your Outlook menu bar on the Home tab. Dear Ric Rojas, This correspondence is in response to a Pre -Construction Notification (PCN) received on February 13, 2024 and considered complete on March 22, 2024. In submitting the PCN, you requested verification that the proposed project is authorized by a Department of the Army (DA) Nationwide Permit (NWP). The work affecting waters of the United States is part of an overall project known as the Weldon Subdivision. The activities in waters of the United States include the permanent discharge of fill material into 0.044 acre of wetland waters, the permanent discharge of fill material into 170 linear feet of stream waters (0.019 ac) considered a loss and permanent discharge of fill material into 91 linear feet (0.009 ac) of stream waters no considered a loss. Additionally, the project involves the temporary discharge of fill material into 74 linear feet (0.012 ac) of stream waters. The project is located 0.10 mile directly northwest of the intersection of Lucus Road and Horton Road in Knightdale Wake County, North Carolina. The project is at Wake County Parcel number 1755757607. This letter is a provisional notification that your proposed project has been reviewed under NWP 29 and 18. In accordance with 40 CFR Part 121 (401 Rule), the Corps cannot take final action on the NWP verification request until the procedures outlined in the 401 Rule for an individual Water Quality Certificate (WQC) have been completed. Specifically, a Department of the Army (DA) permit or verification cannot be issued until a Section 401 WQC has been either issued, waived, or denied, and the neighboring jurisdiction review process described in 40 CFR 121 has been successfully completed. Conditions of the Individual Section 401 WQC will generally become conditions of any final NWP verification letter. Should state action on the required WQC approve a project different from that shown on the current application, a modification to the PCN will be required. You should notify our office of any such changes as substantial changes may require further evaluation. As stated above, this is a provisional notification. This letter does NOT provide Department of the Army (DA) authorization. You are cautioned that commencement of the proposed activity(ies) requested prior to receiving a written DA authorization would constitute a violation of Federal law and subject you to further enforcement action. Receipt of a certification from the state (e.g., NC Division of Water Resources and/or NC Division of Marine Fisheries) does not preclude the requirement for obtaining DA authorization (e.g., an NWP verification letter) prior to commencing the work. In all future correspondence, please refer to file number SAW-2022-01734. This correspondence has also been copied to State and/or Federal agencies for their information. If you have any questions, please contact Matthew K. Martin at (984) 800-3741, or by email at matthew.k.martin@usace.army.mil. Sincerely, Matthew K. Martin, PWS Regulatory Specialist U.S. Army Corps of Engineers CE-SAW-RG-R 3331 Heritage Trade Drive, Suite 105 Wake Forest, NC 27587 Mobile: (984) 800-3741 Email: matthew.k.martin@usace.army.mil We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey can be accessed by copying and pasting the following link into your web browser: https://re_ u�y.ops.usace.army.mil/customer-service-surveyl. Thank you for taking the time to visit this site and complete the survey.